SITE TEST REPORT Date :

Contractors name: Advance Customer:


Energy Company (AECC) NG-SA
Contract No. :
Name of substation: 115/13.8KV Khafji Substation - 5 31131152/00
Page 1 of 2
AUXILIARY RELAY DC OPRD.AUX. RELAY (ELECTR. RESET)
Make: Equip. No.: Dwg. Ref.: Record No.:

1. GENERAL DATA AND INFORMATION:

Panel No. Designation


Make ABB Type RXMD1
Serial No. Aux. Voltage 125V DC
Model No. 1MRK 001 602-AP No. of Contacts 4C/O

2. MECHANICAL CHECKS AND VISUAL INSPECTION: (Ref: 4.1 of TCS-P-105-R1)

ITEM DESCRIPTION REMARKS


1 Inspect for any physical damage or defects.
2 Verify connections as per approved drawings.
3 Check tightness of all connections.
4 Check that serial no. of relay matching with serial no. of case.
Check condition of any connectors, contacts alignment and travel. (if
5
applicable)
6 Check armature gap. (if applicable)
7 Check Reset mechanism.

3. ELECTRICAL TEST: (Ref: 4.2 of TCS-P-105-R1)

ITEM DESCRIPTION REMARKS


1 Check the continuity of the contacts.
2 All output contacts resistance measured.(0.2 Max).
3 Check Flag Operation (if applicable).
4 Check Reset Operation.
5 Check operate and Reset Coil resistance.
6 Check the cut off facility.
Voltage operated relays to have a pickup voltage less than 80% of the rated
7 substation voltage to allow for proper operation of the relay even during
substation DC under-voltage condition.

3.1 Relay burden test:

COIL Voltage (V) Current (mA) Burden (VA )

Operate

Reset

TEST DATE:TEST EQUIPMENT CALIB.DATE & DETAIL

TESTING ENGINEER CSD- Engineer

Signature: ________________ Signature: ________________


Name : ________________ Name : ________________
SITE TEST REPORT Date :
Contractors name: Advance Customer:
Energy Company (AECC) NG-SA
Contract No. :
Name of substation: 115/13.8KV Khafji Substation - 5 31131152/00
Page 2 of 2
AUXILIARY RELAY DC OPRD.AUX. RELAY (ELECTR. RESET)
Make: Equip. No.: Dwg. Ref.: Record No.:

3.2 OPERATING TIME TEST:

Relay
COIL Expected operating Time (ms ) Actual Operating Time (ms)
Terminals
Operate

Reset

Limit: Make contact 4.0ms (According to relay catalogue page NO. 03)
Break contact 4.0ms
Bounce time (make contact) 4.0ms

4. TEST EQUIPMENT USED:

ITEM Test Equipment Serial Number Calibration date Calibration due date
1

TEST DATE:TEST EQUIPMENT CALIB.DATE & DETAIL

TESTING ENGINEER CSD- Engineer

Signature: ________________ Signature: ________________


Name : ________________ Name : ________________