screen.
Answer: B
Answer: B
A. Physiological satisfaction
B. Attainment of survival
C. Esteem
D. Self-actualization
Answer: D
Hint: Read Maslow's theory on hierarchy of needs. Self-
actualization is on top of the pyramid.
A. Project engineer
B. Project manager
C. Quality manager
D. Team member
Answer: B
Hint: PMBOK 5 Page 16, Sec 1.7 Role of the Project Manager
A. control tool.
B. scheduling method.
C. planning tool.
D. rule of thumb.
Answer: D
Hint: PMBOK 5 Page 204, Sec 7.2.2 Estimate Costs: Tools &
Techniques
A. 350
B. -75
C. 400
D. -50
Answer : D
Hint: CV = EV - AC
7 A project manager has just been assigned to a new project and
has been given the preliminary project scope statement and the
project charter. The first thing the project manager must do is:
Answer: B
8 You are taking over a project during the planning process group
and discover that six individuals have signed the project charter.
Which of the following should most concern you?
Answer: D
A. Planning
B. Executing
C. Monitoring and controlling
D. Closing
Answer: D
Answer: B
Answer: A
Answer: C
Hint: PMBOK 5 Page 66 Sec 4.1 Develop Project Charter; Page 16,
Sec 1.7 Role of the Project Manager
Answer : C
Answer : C
A. Functional
B. Matrix
C. Expediter
D. Coordinator
Answer: A
A. Temporary
B. Definite beginning and end
C. Interrelated activities
D. Repeats itself every month
Answer : D
Answer : C
Answer: D
A. Invitation to bid.
B. Request for information.
C. Request for proposal.
D. Request for bid.
Answer: C
Answer: A
Hint: Option A is most lucrative incentive while option C also offers
incentives. Read about Type of Vendor Contracts such as Cost Plus
Incentive Fee (CPIF)
A. mitigation.
B. transfer.
C. acceptance.
D. avoidance.
Answer B
Hint: PMBOK 5 Page 344 Sec 11.5.2.1 Strategies for Negative Risks
Answer: D
Answer : D
Hint: CPFF is the best contract type from buyer perspective as the
seller is aware that cost overruns may have to be borne by him.
Answer: D
A. Initiating
B. Before the project management process
C. Planning
D. Executing
Answer : C
A. Forcing
B. Smoothing
C. Compromise
D. Problem solving
Answer : D
A. Scope planning.
B. Decomposition.
C. Scope base lining.
D. Bill of Materials (BOM).
Answer : B
A. Company processes
B. The company culture
C. Historical WBSs
D. Project scope statement
Answer : D
A. Identify Risks
B. Perform Quantitative Risk Analysis
C. Plan Risk Responses
D. Control Risks
Answer : D
A. Team member.
B. Customer.
C. Stakeholder.
D. Supporter.
Answer : C
32 Quality is:
Answer : C
Answer : A
35 During the full life cycle of the project, a plot of the project.s
expected expenditures will usually follow a characteristic ..S..
shape. This indicates that:
Answer :D
A. project archives.
B. a project charter.
C. a project management plan.
D. a risk analysis plan.
Answer : A
Answer : B
A. Problem solving
B. Forcing
C. Withdrawal
D. Compromising
Answer : C
Answer : B
A. Major project.
B. Project office.
C. Program.
D. Group of projects.
Answer : C
Answer : A
A. Simulation
B. Risk mitigation
C. Overall risk ranking for the project
D. Involving of other stakeholders
Answer : D
A. Project planning
B. Project closing
C. Project executing
D. Project initiating
Answer : D
A. Activity.
B. Task.
C. Work package.
D. Cost account.
Answer : C
A. Rework
B. Quality training
C. Scrap
D. Warranty costs
Answer : B
Hint: PMBOK 5, Page 235
48 What type of contract do you not want to use if you do not have
enough labor to audit invoices?
Answer : A
Answer : C
Answer : B
A. Expert Judgment
B. Rolling wave
C. Strategic
D. Operational
Answer:B
Hint:In Rolling wave, high level plan is made and detailed plans are
made for activities just a little before they have to be executed.
(2) What is the term used for the area that entails processes and
activities that define, combine, unify and coordinate the processes
and project activities carried out within the various Project
Management Process Groups?
Answer: A
A. Unification
B. Consolidation
C. Communication
D. Review
Answer: D
Answer:C
Answer:A
Answer: A
Answer: B
Answer: B
Answer: D
A. Tasks.
B. Milestones
C. Deliverables
D. Life cycles
Answer: C
Answer: C
Hint: Direct and Manage Project Work, Page 79, PMBOK 5
Answer: A
Answer: C
Answer: D
A. Cost Management
B. Time Management
C. Performance of Corporate Social Responsibility
D. Scope Management
Answer: C
Answer: D
Answer: B
Answer: A
Answer: B
A. Agreements
B. Approved Change Requests
C. Validated Changes
D. Accepted Deliverables
A. Project manager
B. Functional managers
C. The customer
D. Both a and b
Answer:D
A. Functional manager
B. Project manager
C. Director of project management
D. Customer
Answer: B
A. Conceptual
B. Planning
C. Implementation
D. Design
Answer: B
Answer:D
Answer:A
(6) Which of the following is NOT one of the primary needs for
good project scheduling?
Answer: D
(7) The inputs used in the Define Activities process includes all but
A. Scope baseline
B. EEF
C. OPA
D. Milestone list
Answer: D
Answer: C
Answer: A
A. Analogous Estimating
B. Group Decision-Making Techniques
C. Reserve Analysis
D. Leads and Lags
Answer: D
a. Define Activities
b. Develop Schedule
d. Sequence Activities
g. Control Schedule
Answer: B
A. WBS
B. Activity Resource requirements
C. Resource breakdown Structure
D. None of the above
Answer: C
A. Schedule Compression
B. Schedule Model
C. Schedule Data
D. None of the above
Answer: B
Answer: A
A. Activity List
B. Schedule Management Plan
C. Activity List
D. Project Schedule Network Diagram
Answer: B
(16) The following inputs are used in both Sequence Activities and
Estimate Activity Resources process, excluding
Answer: C
A. Decomposition
B. Rolling Wave Planning
C. Alternative Analysis
D. Reserve Analysis
Answer: B
A. Sequence Activities
B. Define Activities
C. Develop Schedule
D. Estimate Activity Durations
Answer: A
A. Finish-to-start
B. Start-to-finish
C. Predecessor-Follower
D. Only A and B
E. A, B, and C
Answer: D
A. Alternative Analysis
B. Bottom-up Estimating
C. Parametric Estimating
D. Three-point estimating
Answer: B
A. Preliminary
B. Definitive
C. Order of magnitude
D. Conceptual
Answer:B
Answer: A
Answer: B
Hint: Work package is the lowest unit of work to estimate cost and
duration.
A. CV = EV - PV
B. CV = EV - AC
C. CV = EV / AC
D. A and c
Answer:B
Answer:B
Answer: C
Answer: D
A. -$150
B. $150
C. -$50
D. $50
Answer: A
Hint: CV=EV-AC
(9) One of the types of cost estimation is Rough Order of
Magnitude. This estimate:
Answer: D
A. Planned Value
B. Aggregated Planned Value
C. Budget at Completion
D. Estimate at Completion
Answer: C
Answer: A
A. Control Costs
B. Estimate Costs
C. Plan Cost Management
D. Determine Budget
Answer: C
A. Determine Budget
B. Control Costs
C. Estimate Costs
D. Plan Cost Management
Answer: B
a. Determine Budget
c. Estimate Costs
d. Control Costs
Answer: C
A. Estimate Costs
B. Determine Budget
C. Both A & B
D. None of the above
Answer: A
(16) Which one of the following is not an input used in the process
of Estimate Costs?
A. Scope Baseline
B. Human Resource Management plan
C. Cost Management Plan
D. Project Funding Requirements
Answer: D
A. Cost Aggregation
B. Cost of Quality
C. Expert Judgement
D. Historical Relationships
Answer: B
Answer: B
A. Cost Forecasts
B. Change Requests
C. Activity Cost Estimates
D. Work Performance Information
Answer: C
(20) The tools and techniques used in Control costs includes all
but
Answer:C
Answer: A
Answer: A
Hint: PMBOK 5, Page 231 Sec 8.1 Plan Quality Management
A. Audit
B. Peer Review
C. Process Analysis
D. Walkthrough
Answer:C
Answer:E
(6) The term for the process and activities of the performing
organization that determine quality policies, objectives and
responsibilities so that the project will satisfy the needs for which it
was undertaken is :
Answer: C
A. quality
B. product design
C. pricing
D. a and b
Answer: D
Answer: B
Answer: A
Answer: A
(11) The common tools and techniques used in both Plan Quality
Management and Control Quality is:
A. Cost-Benefit Analysis
B. Benchmarking
C. Seven Basic Quality Tools
D. Inspection
Answer: C
Answer: D
(14) All of the following are the outputs of the Control Quality
Process excluding:
A. Change Requests
B. Quality Metrics
C. Quality Control Measurements
D. Work Performance Information
Answer: B
(15) Which of the following are used to identify the vital few
sources that are responsible for causing most of a problem's
effects?
A. Pareto Diagrams
B. Check sheets
C. Scatter Diagrams
D. Control Charts
Answer: A
A. Scatter Diagrams
B. Histograms
C. Cause-and-effect diagrams
D. Pareto Diagrams
Answer: A
A. Statistical Sampling
B. Design of Experiments (DOE)
C. Benchmarking
D. Cost-Benefit Analysis
Answer: B
A. Brainstorming
B. Nominal Group Technique
C. Force-Field Analysis
D. Quality Management and Control Tools
Answer: B
A. Quality Checklists
B. Process Improvement Plan
C. Quality Management Plan
D. Quality Metrics
Answer: D
(20) The name for the tool used in Perform Quality Assurance to
represent decomposition hierarchies such as the WBS (work
breakdown structure), RBS (risk breakdown structure), and OBS
(organizational breakdown structure) is:
A. Tree Diagrams
B. Process decision program charts (PDPC)
C. Affinity Diagrams
D. Matrix Diagrams
Answer:E
Hint: PMBOK 5, Page 264 Sec 9.1.3 Plan Human Resource Management: Outputs
(2) Expert power is the power that comes from the amount of knowledge a person
has obtained in a specific area. This type of power is:
Answer: D
Hint: PMBOK 5, Page 16, Sec 1.7 Role of the Project Manager
(3) To successfully motivate a team in today's high tech - high demand environment,
which motivational theories should the PM use to maintain a happy, productive
team?
Answer: D
(4) To successfully manage a project, the project manager must play both a manager
and leadership role. In a manager's role, the project manager will do all but which of
the following:
Answer:B
A. Referent power
B. Formal authority
C. Informal power structure
D. Broad span of control
Answer:A
Hint: Referent power is based on the authority extended by a more powerful person.
A project manager can exercise the power given by project sponsor to take decisions
in the project interest.
(6) Which form of power is the LEAST effective from the project manager's
viewpoint in terms of influencing functional managers?
A. Formal power
B. Expert power
C. Penalty power
D. Referent power
Answer: C
Hint: Penalty is the least effective forms of influencing and should not be used at all,
if possible.
(7) The Project manager should be able to fulfill the role of:
A. an integrator
B. a functional manager
C. a line manager
D. a sponsor
Answer: A
Hint: A project manager is responsible for collective project success. Refer PMBOK
5, Page 16, Sec 1.7 Role of the Project Manager
A. Work their way up from assistants in the project office to full-fledged project
managers, supplementing that experience with formal education.
B. Comes right from Harvard's MBA program into managing very large projects.
C. Are the technical experts.
D. Have considerable experience as a functional manager before moving into the
project management arena.
Answer: A
(9) Which of the following is an important action that must be taken by top
management when implementing project management in an organization?
Answer: D
Hint: It is important for project success that all stakeholders agree on the importance
of project management concepts and theories.
(10) The project manager has the most authority in the __________________ type of
organization.
A. Project expediter
B. Matrix
C. Projectized organization
D. Functional
Answer: C
(11) The process that organize, manage, and lead the project team for the completion
of a project is called
A. 1-2-3-4
B. 3-2-1-4
C. 2-1-3-4
D. 1-3-2-4
Answer:D
(13) Which of the following techniques is not used in the process of Plan Human
Resource Management?
A. Networking
B. Pre-assignment
C. Organizational theory
D. Meetings
Answer:B
(14) The various inputs used while executing the process of Develop Project Team
includes all but
Answer:C
(15) The process of Manage project team uses which of the following inputs in its
execution?
A. Issue Log
B. Resource Calendars
C. Activity Resource Requirements
D. Human Resource Management Plan
Answer:A
Answer:C
(17) The information used for the development of the human resource management
plan includes all except
Answer:D
(18) The concept that provides information regarding the way in which people,
teams, and organizational units behave is known as
A. Networking
B. Organizational Theory
C. Expert Judgment
D. None of the above
Answer:B
(19) The phase of team building where the team begins to address the project work,
technical decisions, and the project management approach is known as
A. Performing
B. Storming
C. Forming
D. Norming
Answer:B
(20) The Conflict Management approach that is used for emphasizing upon the areas
of agreement rather than areas of differences conceding one's position to the needs of
others to maintain harmony and relationships is called
A. Collaborate/Problem Solve
B. Compromise/Reconcile
C. Smooth/ Accommodate
D. Withdraw/Avoid
Answer:C
Answer:D
A. Written documents
B. Oral communication
C. Tactile contact
D. Informal contact
Answer: A
A. Progress report
B. Project directive
C. Project manager
D. Customer
Answer: C
Hint: Project manager is responsible for executing and facilitating
all the project-related communication.
Answer:C
Answer:E
Answer: D
Hint: Telepathy is not an advisable method of transmitting
information in Project Management
Answer: D
A. Communicator
B. Message
C. Medium
D. Recipient
Answer: C
A. Conflict is bad
B. Conflict is caused by trouble makers
C. Conflict should be avoided
D. Conflict is often beneficial
Answer: D
A. 10-20%
B. 50-70%
C. 75-90%
D. 21-45%
Answer: C
(11) What is the term used for processes that are required to
ensure timely and appropriate planning, collection, creation,
distribution, storage, retrieval, management , control monitoring,
and the ultimate disposition of project information?
Answer: A
Answer: B
Hint: PMBOK 5, Page 287, Section 10.1
Answer: D
Answer: D
A. Change Requests
B. Work Performance Information
C. Project Communications
D. OPA Updates
Answer: C
Answer: A
A. Project Environment
B. Skills of the project team
C. Sensitivity and confidentiality of the information
D. Ease of use
Answer: B
(18) The type of Communication Methods tool that uses very large
volume of information ,or for very large audience, and requires the
recipients to access the communication content at their own
discretion is called
A. Interactive Communication
B. Pull Communication
C. Push Communication
D. None of the above
Answer: B
A. Manage Communications
B. Plan Communications Management
C. Control Communications
D. Both A & C
Answer: A
A. Performance Reporting
B. Information Management System
C. Expert Judgment
D. None of the above
Answer: A
Answer:A
A. Scope Baseline
B. Risk Register
C. Quality Management Plan
D. Risk Management Plan
Answer: C
A. indefinite, probabilities
B. uncertain, objectives
C. sure, goals
D. definite, uncertainties
Answer: B
(4) When is the risk and uncertainty in a project's life cycle at the
highest?
A. start
B. design
C. closing
D. implementation
Answer:A
(5) A new project that was initiated, involved new technology and
had never been done before. What type of contract would the
owner want to issue to reduce or eliminate as much risk as
possible?
A. fixed price
B. Cost plus fix fee
C. Cost plus incentive fee
D. Time and Material
Answer:A
Hint: A fixed bid project has lesser risk for the firm that gives high-
risk work on contract
(6) The process of Control Risks does not have one of the following
as an output. Which one is it?
A. Work Performance Information
B. Change Requests
C. OPA updates
D. Risk Register
Answer: D
Answer: B
Answer: C
(9) The total amount of risk that is calculated for a project is found
by
A. Multiplying the sum of each the risk times the amount at stake
B. Calculating the cumulative sum of the probability for each risk and
multiplying this value times the consequence of occurrence of the risk
events
C. Cannot be calculated since all risks are not known
D. The amount of project reserves available
Answer: B
A. Share
B. Accept
C. Enhance
D. Exploit
Answer: C
3. Identify Risks
6. Control Risks
A. A.1-2-3-4-5-6
B. B.1-3-2-4-5-6
C. C.1-3-4-2-5-6
D. D.3-1-2-4-5-6
Answer:B
Answer:B
A. Risk Threshold
B. Risk Appetite
C. Risk Tolerance
D. None of the above
Answer:A
(14)
Which of the following tools and techniques is not used in the process of
Identify Risks
A. SWOT Analysis
B. Diagramming Techniques
C. Checklist Analysis
D. Risk Categorization
Answer:D
Answer:B
A. Meetings
B. Expert Judgment
C. Analytical Techniques
D. Both B& C
Answer:C
A. Methodology
B. Roles and Responsibilities
C. Budgeting
D. Tracking
Answer:D
Answer:B
(19)
The technique used under the Quantitative Risk Analysis that translates the
specified detailed uncertainties of the project into their potential impact on
project activities is called
Answer:B
A. Mitigate
B. Transfer
C. Accept
D. Avoid
A. funding management
B. managing relationships and interfaces
C. performance control
D. all of the above
Answer: D
A. express
B. implied
C. negotiated
D. A and B
E. A, B, and C
Answer: D
Answer:B
A. acquisition process
B. contract administration
C. ecological environment
D. offer, acceptance, and consideration
E. a and b
Answer: E
A. Make-or-buy analysis
B. Market Research
C. Bidder Conferences
D. Expert Judgment
Answer: C
Answer: E
Hint: Read about types of contracts under Sec 12.1.1.9, Page 362
PMBOK 5
A. True
B. False
C. Not sure
D. Incomplete Information
Answer: A
Answer: B
Answer: A
2. Control Procurements
3. Conduct Procurements
4. Close Procurements
A. A. 1-2-3-4
B. B. 1-3-2-4
C. C. 1-4-3-2
D. D. 3-1-2-4
Answer: B
A. Seller Proposals
B. Procurement statement of work
C. Source Selection Criteria
D. Agreements
Answer: D
Hint: Agreements are the output on conduct procurements process
Answer: A
Answer: A
Answer: C
Answer: B
Answer: A
A. Market Research
B. Make-or-buy Analysis
C. Expert Judgment
D. None of the above
Answer: B
Answer:B
A. Manage Communications
B. Plan Stakeholder Management
C. Manage Stakeholder Engagement
D. Control Stakeholder Engagement
Answer: C
Hint: Manage Stakeholder Engagement, Page 391, PMBOK 5
A. Stakeholder register
B. Procurement documents
C. Project management plan
D. all of the above
E. A and C
Answer: B
Answer:A
A. Supplier
B. Customer
C. PMO
D. Competitor
Answer:D
A. Managerial grid
B. Johari window
C. Performance grid
D. Salience model
Answer: D
Answer: C
A. Leading
B. Supportive
C. Active
D. Neutral
Answer: A
Answer: D
Hint: The matrix helps map the difference between Desired and
Actual engagement level.
Answer: A
Answer: D
Answer: C
A. Delphi Technique
B. Management Skills
C. Interpersonal Skills
D. Communication Methods
Answer: A
Answer: C
A. Internal/External
B. Aware/Unaware
C. Optimistic/Pessimistic
D. Supportive/Resistant
Answer: C
Answer: C
Answer: B
Answer: D
Answer: B
1 Which of the following is an advantage of centralized contracting?
Answer: B
Answer: B
A. Physiological satisfaction
B. Attainment of survival
C. Esteem
D. Self-actualization
Answer: D
Answer: B
Hint: PMBOK 5 Page 16, Sec 1.7 Role of the Project Manager
A. control tool.
B. scheduling method.
C. planning tool.
D. rule of thumb.
Answer: D
Hint: PMBOK 5 Page 204, Sec 7.2.2 Estimate Costs: Tools &
Techniques
A. 350
B. -75
C. 400
D. -50
Answer : D
Hint: CV = EV - AC
Answer: B
8 You are taking over a project during the planning process group
and discover that six individuals have signed the project charter.
Which of the following should most concern you?
Answer: D
A. Planning
B. Executing
C. Monitoring and controlling
D. Closing
Answer: D
10 The WBS and WBS dictionary are completed. The project team
has begun working on identifying risks. The sponsor contacts the
project manager, requesting that the responsibility assignment
matrix be issued. The project has a budget of U.S. $loo,ooo and is
taking place in three countries using 14 human resources. There is
little risk expected for the project and the project manager has
managed many projects similar to this one. What is the next thing
to do?
Answer: B
Answer: A
Answer: C
Hint: PMBOK 5 Page 66 Sec 4.1 Develop Project Charter; Page 16,
Sec 1.7 Role of the Project Manager
Answer : C
Answer : C
Answer: A
A. Temporary
B. Definite beginning and end
C. Interrelated activities
D. Repeats itself every month
Answer : D
Answer : C
Answer: D
A. Invitation to bid.
B. Request for information.
C. Request for proposal.
D. Request for bid.
Answer: C
Answer: A
A. mitigation.
B. transfer.
C. acceptance.
D. avoidance.
Answer B
Hint: PMBOK 5 Page 344 Sec 11.5.2.1 Strategies for Negative Risks
Answer: D
Answer: B
Answer : D
Hint: CPFF is the best contract type from buyer perspective as the
seller is aware that cost overruns may have to be borne by him.
Answer: D
A. Initiating
B. Before the project management process
C. Planning
D. Executing
Answer : C
Hint: PMBOK 5 Page 61 Table 3-1 Project Management Process
Group and Knowledge Area Mapping
A. Forcing
B. Smoothing
C. Compromise
D. Problem solving
Answer : D
A. Scope planning.
B. Decomposition.
C. Scope base lining.
D. Bill of Materials (BOM).
Answer : B
A. Company processes
B. The company culture
C. Historical WBSs
D. Project scope statement
Answer : D
Hint: PMBOK 5, Page(s) 61, 106. Scope statement is output of
Define Scope process under Planning.
A. Identify Risks
B. Perform Quantitative Risk Analysis
C. Plan Risk Responses
D. Control Risks
Answer : D
A. Team member.
B. Customer.
C. Stakeholder.
D. Supporter.
Answer : C
32 Quality is:
Answer : C
Hint: PMBOK 5, Page 556, Definition of Quality
Answer : C
Answer : A
35 During the full life cycle of the project, a plot of the project.s
expected expenditures will usually follow a characteristic ..S..
shape. This indicates that:
A. project archives.
B. a project charter.
C. a project management plan.
D. a risk analysis plan.
Answer : A
Answer : B
Answer : A
A. Problem solving
B. Forcing
C. Withdrawal
D. Compromising
Answer : C
Answer : B
A. Major project.
B. Project office.
C. Program.
D. Group of projects.
Answer : C
Answer : A
A. Simulation
B. Risk mitigation
C. Overall risk ranking for the project
D. Involving of other stakeholders
Answer : D
Answer : C
Hint: PMBOK 5, Page 138, Sec 5.6.1.1 - Configuration
management plan
A. Project planning
B. Project closing
C. Project executing
D. Project initiating
Answer : D
A. Activity.
B. Task.
C. Work package.
D. Cost account.
Answer : C
A. Rework
B. Quality training
C. Scrap
D. Warranty costs
Answer : B
Answer : A
Answer : C