WORK METHOD
STATEMENT
1 EXECUTIVE SUMMARY
2 PROJECT EXECUTION
2.1 Scope of Work
2.2 Project Management
2.2.1 Planning /Pre-execution of Construction
2.3 Engineering
2.4 Procurement, Fabrication & Factory Acceptance Test
2.5 General Execution
2.5.1 Construction Organisation
2.6 Construction/Installation
2.6.1 Installation Sequence /Planning & schedule
2.6.2 Civil/Mech Works
2.6.3 Electrical Works
2.7 Project commissioning
2.8 Training
2.9 Development of Local content
2.10 Documentation
2.11 Reporting
2.12 HSE Programme
2.11.1HSE
2.11.2HSE-MS
2.13 Risk Assesment/Management
2.14 Change Management
2.15 Cost Control
2.16 Project Control
2.17 Progress Measurement
2.18 Recovery Plan
2.19 Interface Management
2.19.1 Interface between LADOX and Shell
2.19.2 Interface between LADOX Base Office, Fabrication and
Construction sites
2.19.3 Interface between LADOX and Other Stakeholders
(Subcontractors, vendors, Government Agency and community)
TECHNICAL BID FOR ELECTRICAL FACILITIES UPGRADE EAST NG0101526
LADOX will work closely with SPDC in the Project planning, executive
monitoring team and operation team throughout the active phase of the
project enumerated above.
The SPDC host community would also be carried board on all the execution
phases. The essence of this interfacing relationship is to allow for smooth and
timely and safe delivering of the project since the execution would likely be
within SPDC operation areas.
All relevant standard electrical operation guide lines and SPDC DEPS would be
adhered as to guarantee a seamless Tie- in of the new project to SPDC
electrical power ring System
The Project Management Team will cover all aspect of Project organisation,
Planning, administration, supervision of subcontractors, finance and general
coordination of the entire Project. This activity spans through the entire
Project period of One year for a typical substation as described in the Project
Schedule in AppendixA9
TECHNICAL BID FOR ELECTRICAL FACILITIES UPGRADE EAST NG0101526
The Project management team (PMT) will be based in the main office at 2 Old
Aba road or branch office at 52 Effurum road Warri and will be interfacing with
the site activities at the Shell site Office.
2.3 ENGINEERING
For Most OEM equipment, Factory acceptance test will be done between
LADOX, the manufacturers and SPDC witnessing the tests. SPDC agree on
time will give final approval on this activity
LADOX has also identified vendors (Agency) and other Nigerian Manufacturer for these
services as listed below
Description of Company
S/N Company Name Scope Type Address
Jib Engineering Procurement of ABB Ordinance Junction,
1
Ltd Equipment/Products Nigerian T/Amadi Junc, Ph
Procurement of ABB 8 Elelenwo Street,
2 Unistockist
Equipment/Products Nigerian GRA Phase 2, PH
KablelMetal Nig Cable 3 Portharcourt Road,
7
Ltd Manufacturers Nigerian Aba
Procurement of LV 29 Obafemi awolowo
8 Teco Nig Ltd
switchboard Nigerian way, Ikeja Lagos
Cable
10 NigerChin Nig ltd
Manufacturers Nigerian 30 Aba Road, Ph
Logistics,
Emmanique Procurement of
13
Services Ltd Equipment/material Communit 2a Old aba Road
s y Portharcourt
Procurement of
Celetrans Nigeria
14 Equipment/material 302 Aba Road
Ltd
s Nigerian Portharcourt
MATERIALS MANAGEMENT/LOGISTICS
LADOX is to provide logistics for transportation of all Materials relevant to the
Project to site. Only pre-mobbed equipment would be used in all our
operations. Whenever necessary, SPDC would be required to provide cranes,
and operator to load out permanent materials in SPDC site/locations.
LADOX would however manage, supervise and direct the handling of items to
be loaded out.
TECHNICAL BID FOR ELECTRICAL FACILITIES UPGRADE EAST NG0101526
2.5 GENERAL EXECUTION
CONSTRUCTION ORGANIZATION
SPDC would be managed by our Project Manager who is also our site
report on the site progress to LADOX and client. LADOX would only mobilized
quality device.
TECHNICAL BID FOR ELECTRICAL FACILITIES UPGRADE EAST NG0101526
CONSTRUCTION SITE ORGANIZATION CHART
MANAGING DIRECTOR
?
SECRETARY / DOC.
CONTROLLER.
?
TECHNICAL SUPPORT.
CIMARRON ENG LTD
PROJECT MANAGER
AEG SYSTEMS LTD
OGBONNAYA MARTINS
AREVA T&D LTD
EATON HOLEC
COMMISSIONING
ENGRS
ENGINEERING /
LOCAL CONTENT HSE & COMMUNITY
MANAGER AFFAIRS MANAGER
ISAGUA JOHN AKANI SAMPSON
SUPERVISORS QA/QC
SUB
OBINNA O (ELECT) ENGINEERS
CONTRACTORS
DOZIE L (MECH) TBA
TECHNICIANS
ELECTRICIANS (10)
MECHANICS/FITTERS & LABOURS
DRIVERS (10)
TECHNICAL BID FOR ELECTRICAL FACILITIES UPGRADE EAST NG0101526
FUNCTION OF KEYS OFFICER
PROJECT MANAGER
Our project manager will manage the execution of the contract in a safe
obligations.
The Project Manager has overall management authority for all operations on
site, and is also responsible for ensuring that all project activities are
completed in accordance with Project requirements, in this plan. In the
absence of the Manager, the Engineering Manager will assume his
responsibilities. His functions include:
HSE/COMMUNITY MANAGER
He Is responsible for the safety of all personnel at the work site. He is also
Manages HSE issues at site in accordance with the procedures set forth
in the HSE policy/plan,
Ensure all HSE risks are reduced to as low as practicable.
Also liaise with Clients liaison officer to deal with community issues
He is the custodian of LADOXHSE site documentations.
He ensures site HEMP management and also development our site HSE
Statistics & reports to our client representative.
He administers the site safety activities with the site HSE Officer.
TECHNICAL BID FOR ELECTRICAL FACILITIES UPGRADE EAST NG0101526
PROCUREMENT/LOGISTICS MANAGER;
Oversees the procurement of local and foreign equipment and materials
The transportation of equipment, personnel and materials to work site
QA/QC MANAGER/COORDINATOR
LADOXHSE Officer/ First Aider Functions directly with the HSE manage
Manages HSE issues at site in accordance with the procedures set forth
in the HSE policy/plan,
Ensure all HSE risks are reduced to as low as practicable.
Also liaise with Clients liaison officer to deal with community issues
Administration of first aid treatment on site.
Custodian of the site first aid box & drug administration note book.
He attains to any of the safety audit relevant to drug & administration
Issues form for staff to visit retainership clinic
Design of site specific earthing systems based on known local soil resistivity
or the results of a Survey.
Standby Generators
Static (complete with disconnect assemblies for tanker loading/off
loading)
LV and HV supply systems
TECHNICAL BID FOR ELECTRICAL FACILITIES UPGRADE EAST NG0101526
Technical Earthing for equipment sensitive to fault currents
Transformers
Feeder Pillars
Telecommunications Systems
Wind Farms
Deep drilled boreholes, (for poor soil resistivity or limited available
space ), up to 100m deep and back-filled with conductive slurry or
conductive cement.
AND SWITCHBOARDS
Design approvals
Study of underground for re-routed survey
Processing of PTW excavation/ isolation and other necessary permit and
documentations.
Under ground network re-routing
Sitting out for generator house construction
Excavation of soil surface
Concrete blinding works
Iron /wood works
Survey of floor area of leveling
To make sure that the entire installation is in conformance and in
accordance with the design intent of the project for the Electrical and Low
Voltage System in addition to the specification and as per approved shop
drawings and comply with local and International Standards.
Ensures that clearance in front of switchgear is adequate as indicated in
AFC drawing.
Terminate PVC, SWA PVC cables inside enclosure by securing cables to
switchboards, AMF/ACO panels with gland bracket; and enclosure with
glanding plates
2.8 TRAINING
After project commissioning COBIEX/SPDC contract holder would agree on a
local venue, time and training scope which is to be provided by LADOX/
Equipment manufacturer vendor
Basically the essence of the training is to ascertain that the key operational
principal of the sub-station is understood by the SPDC operation/
maintenance team.
Training scope is to also include power system trouble shouting, ACB
protection settings and interpretation of system fault signal from the
manufacturer interface module.
On completion of training, LADOX would present certificate of participation to
the trained staff.
2.10 DOCUMENTATION
LADOX document numbering/index would be used to track document via a
muster document registration which LADOX would also issue to SPDC.
To track the status of document submission and reviews, a revision
designation will be given to all documents as follows:
o Alphabets for revisions indicate that the document need to be approved
o Numeric for revisions indicates that the documents have been approved,
but SPDC /LADOX has requested for a change.
2.11 REPORTING
LADOX Int. would provide all necessary project reporting to SPDC to enable
SPDC track progress of project work /task as laid out in the project schedule .
TECHNICAL BID FOR ELECTRICAL FACILITIES UPGRADE EAST NG0101526
DAILY JOB REPORTING (DJR)
This document would provide the primary report medium during project
execution, as if provide the details record of exert and work performers on
site.
The LADOX/SPDC report would approve this document prior to issue
MINUTES OF MEETINGS
Minutes of all meetings held by SPDC and LADOX/ or primary sub-contractor
or other agencies would be generated by LADOX and signed by leaders of
participating team. The reviews of such minutes and finals review issued for
signature with 5 days.
MONTHLY REPORT
LADOX would make available to SPDC her monthly report and would indicate
the work progress through the month, and also planned activities for the next
month.
AUDIT REPORT
All site audits by LADOX/SPDC would be documented held of site for the
successful close out items identified. The report will include intended closed
out date and the actual close out will be tracked.
LADOX our staff have undergone various HSE training with the following
organizations.
Nigeria institution of safety proposal
Nigeria red cross society
PTI
TECHNICAL BID FOR ELECTRICAL FACILITIES UPGRADE EAST NG0101526
Activities will be timely planned, risk level assessed and control measures put
in place as to a level that is as low as reasonably practicable
LADOX would only commerce jobs that are viewed safe otherwise it would not
be done.
LADOX work force (sub-contractors inclusive) has HSE responsibilities as part
of their tasks and targets. They are also their brothers keepers by watching
out for each other and achieve ongoing coaching.
2.12.3 LADOXHSE MS
LADOX HSE MS is targeted at achieve goals Zero in all their task execution.
This is achieved via a smart
HSE leadership and commitment as all LADOX policy must be sign by the
Managing director.
Strategic policy objective that are in conformity with SPDC
TECHNICAL BID FOR ELECTRICAL FACILITIES UPGRADE EAST NG0101526
Organization responsibilities and resources are documented and known
by all staff
Used of trained HSE /first Aiders and Pre-mobbed equipment on site.
Approved/signature job hazard analysis is readily attached to valid permit
and always available on site
Host community complaint register being on site
Daily tools box briefly is done on site and documented
Monthly HSE /safety meeting is done at the project site and
documentation
Retainership clinic is known to all work force
Warning signs available and adequate on site
Unsafe Act(UA)/Unsafe Condition(UC)/Near Miss (NM) register available
on the substation site
Adequate PPEs for different task execution on site
Waste being generated are segregated and waste consignment not is
used
SHOC card for different chemical usages on site.
All joiners to be planned by our Journey manager
Access control to LADOXIntl. site to be adequate and managed vie
Visitors note book
Visitors briefing
Cordoning of work site
Golden rules and also aligned to the 12 life safety rules now bring impended.
SECURITY
The site security plan would also be developed with the following objectives;
TECHNICAL BID FOR ELECTRICAL FACILITIES UPGRADE EAST NG0101526
Emphasizing community relation CLO to manage expectations with the host
ENVIROMENT
LADOX and its /sub-contractors in the project team will comply with all
The project team has established the following objectives to achieve goal
and subcontractors.
The interface between SPDC and LADOX spans across the entire Project. From
Engineering, Procurement, Construction, Installation, Commissioning and
Close out. For the successful execution of this project the interface
relationship with our client for this project would have to be properly defined
and documented
Responsibilities of COBIEX
Responsibilities of CLIENT
- LADOX shall mange all Interfaces between the Base office, fabrication site
- There will be clear responsibilities spelt out on what activities each area will
coordinate
progress
The interface between LADOX and these other Stakeholders above, also
spans spans across the entire Project, From Engineering, Procurement,
Construction, Installation, and Commissioning.
The interface relationship with other stakeholders for this project would be
defined, documented and properly managed
PROJECT SCHEDULE;
PROCUREMENT: The procurement activity for this project is planned such that
all the long lead orders will be placed and arrive within (5-7) months, which
include LV/HV equipments, transformers and HV EXLPE cables (If required).
Order for LV cables will be placed via Local Cable Manufacturers.
The allocated period will include Approvals, Manufacturing, Shipment and
Clearing of Equipments, as well as the Factory Acceptance Test which will be
witnessed by Client.
TRAINING; any required training will be conducted within two weeks after
commissioning of the Project
S-CURVE: The S curve only shows the planned schedule for this Project. No
variance is captured at this stage because we do not know the required Client
target Schedule for the project