MG ING LUIS DIAZ H.

CIP# 36994
TELF.2249785-999004184

ANALISIS DEL ADELANTO DE MATERIALES N 01 SOLICITADO POR EL CONTRATISTA

Obra : AMC - N -2008- " CASCO ESTRUCTURAL DE OFICINAS ADMINISTRATIVAS"

Contratista: TTP CONTRATISTAS GENERALES


Supervisor: MG ING LUIS DIAZ H. FR= 0.97005

1) CHEQUEO POR PORCENTAJE MAXIMO DEL 40.00% Supervision


ITEM DESCRIPCION MONTO S/.
1.00 CONCRETO ARMADO 29,914.46
2.00 MUROS 5,117.52

COSTO DIRECTO S/. 35,031.98


GASTOS GENERALES S/. 5,254.80
UTILIDAD S/. 3,503.20
SUB TOTAL S/. 43,789.98
FACTOR DE RELACIN
SALDO BRUTO POR VALORIZAR (Afectado por Factor de Relacin) - SIN IGV 43,789.98
% ADELANTO MAXIMO PERMISIBLE>>>>>>> 40.00% 16,991.39
ADELANTO MATERIALES SOLICITADO >>>> 40.00%

Nota: El Monto solicitado, ES EL PORCENTAJE MAXIMO de 40% (O.K)


EL MONTO SOLICITADO, ES MENOR IGUAL CALCULADO POR LO TANTO ES OK.

2) CHEQUEO POR FORMULA POLINOMICA: Monto mximo = Coef.Inc. x.Porc. Incid. x Fr x Saldo Bruto por Valorizar x Ima/Imo =CIX%XSbxFrxFr x(Ima/Imr)
Indice Descripcin Coefic. Porcentaje Saldo Bruto por Indices Unificados Contratista Supervisin
Unificado Incidencia Incidencia Valorizar x F.R. Imo ( DICIEMBRE) Ima.(MAYO) Solicitado Monto Maximo
21 CEMENTO PORLAND T-1 0.133 72.93% 423.83 423.83 4120.2794458865 S/. 3,338.42
5 PIEDRA CHANCADA 0.133 17.29% 605.43 612.25 987.8256710488 S/. 800.38
17 LADRILLO ARCILLA 0.109 11.93% 835.92 854.73 564.8068954154 S/. 457.63
4 ARENA GRUESA 0.109 88.07% 42,478.47 579.85 607.18 4269.9727932722 S/. 3,459.71
43 MADERA NACIONAL PARA ENCOFRADO 0.103 89.32% 619.66 612.73 3864.2964689664 S/. 3,131.01
3 ACERO CORRUGADO 0.170 100.00% 501.62 497.61 7163.6109918129 S/. 5,804.25

MONTOS TOTALES (SIN IGV) S/. 20,970.79 S/. 16,991.39


MONTOS TOTALES (Afectado por Factor de Relacin) - SIN IGV 16,991.39
MONTO DEL ADELANTO MAXIMO PERMISIBLE>>>>>>> S/. 0.00

Nota:

CONCLUSIONES Y RECOMENDACIONES:

Se RECOMIENDA aprobar la Suma de:


Monto Directo
Impuesto General a la Ventas (IGV)
Monto Total Aprobado >>>>>>>>>
Porcentaje Aprobado >>>>>>>>>>>>
MG ING LUIS DIAZ H.
CIP# 36994
TELF.2249785-999004184

16038 TAMBIEN PUEDE SER OK


DATOS :
PB = 43,789.98
Fpb= DICIEMBRE
Fr= 0.97005
Po= 42,478.47 42,478.47

UBICACIN : TACNA

AVANCE PROGRAMADO ACUMULADO (APA)


MES JULIO AGOSTO SETIEMBRE
VP 12,000.00 13,000.00 18,789.98
VA 12,000.00 25,000.00 43,789.98

EL CONTRATISTA SOLICITA EL ADELANTO DE MATERIALES : 2 DE JULIO


LA ENTIDAD LO CANCELA EL 8 DE JULIO
DIC MAYO JUNI

PRESENTA VALORIZACION 30 DE JULIO , SIENDO EL K DE JUNIO

HASTA 1 DE JULIO TENGO LOS INDICES DE MAYO


JULIO
1

17 SALE K DE JULIO

30

KJUNIO