SSR 2009

NORMS OF OUTPUT SSR-2009

S/No Item of works Output

A Labour norms
a) FORMATION
1 Carriage of constructional materials (Manually) : 4.56 cum per labour per day

2 Jungle clearance such as clearance of shrubs : 23 sqm per labour per day
brushwoods, under growth and small trees not
exceeding 30 cms in girth measured at one mtr above
ground level including grubbing up roots in areas
having annual rainfall upto 200 cms

3 - Do - in areas having rainfall more than 200 cms : 12 sqm per labour per day

4 Cutting down trees exceeding 30 cms and not : 1.0 labour, sawyer each per
exceeding 75 cms measured at 1.0 mtr above ground tree per day
level, grubbing up roots, filling up holes/hollows,
rammed properly and leveled incl lopping branches,
trimming, stacking the useful materials and removal of
rubbish upto a distance of 20 mtr
5 - Do - each additional 25 cm girth exceeding 75 cms : 1/7 sawyer and 15/14 labour per
tree per day
6 Rough excavation in soil/soil mixed with small : 2.27 cum per labour per day
boulders, getting out incl disposing all excavated
materials lead upto 3 m and upto 1.5 m depth
7 Rough excavation in soft rock which can be : 1.06 cum per labour per day
quarried/split with crowbars and disposing all
excavated materials lead upto 3 m and upto 1.5 m
depth
8 Rough excavation in hard rock by drilling with : 1.87 cum per labour per day
compressor, blasting and getting out including stacking
of serviceable materials and disposal of unserviceable
materials lead upto 3 m and upto 1.5 m depth
9 Earth work in excavation in soil/soil mixed with : 2.00 cum per labour per day
boulders including dressing up road formation,
cambering and getting out incl disposing all excavated
materials lead upto 3 m and 1.5 m depth
10 Excavation in soft rock which can be quarried /split : 1.0 cum per labour per day
with crowbars or wedges dressing up road formation
including cambering and getting out incl disposing all
excavated materials lead upto 3 m and 1.5 m depth
11 Excavation in hard rock by drilling with compressor, : 1.5 cum per labour per day
blasting including dressing up road formation,
cambering, providing cross slop and by filling up
hollows with stone metal where required and getting
out including stacking of serviceable materials and
disposing all excavated materials lead upto 3 m and
1.5 m depth
12 Earth work in embankment including raising or : 3.72 cum per labour per day
lowering spreading in layers not exceeding 30 cm incl
watering, rolling and finishing to required shape and
level not exceeding 1.5 mtr high above the base in
ordinary soil.

1-7
SSR 2009

S/No Item of works Output

13 Turfing of slopes of embankments including : 37.00 sqm per labour per day
preparation of ground, sieving, spreading manure/
planting grass roots/seeding to obtain even surface
and initial watering by spray
14 Temporary culverts composing of bally support : 3 carp with 6 labour per nos of
and decking with ballies including dismantling culvert
the same and clearing the site, upto 2 mtr span

15 Erection and launching/delaunching of temporary : 7 labour per MT


bailey bridge

b) MATERIAL
1 Collection of rubble stone 15 x 20 cms average : 1.75 cum per labour per day
section suitable for walling/aprons bunds, road side
edging etc, including breaking to size and stacking at
loading point
2 Collection of stone boulders/quarried stone the : 2.24 cum per labour per day
smaller dimension shall be equal to 15 cms to 22.5
cms and no stone shall be more than 25 cms, the
longer dimension, stacking at loading point
3 Collection of bond/through stone 20 x 25 cm average : 0.92 cum per labour per day
section including breaking to size and stacking at
loading point
4 Collection of shingle : 1.13 cum per labour per day
5 Collection of sand from river bed including screening : 0.57 cum per labour per day
etc. with an average lead of 100 mtrs and 25 mtrs lift
including stacking
6 Breaking stone to stone metal standard size 63 mm : 0.42 cum per labour per day
for WBM or hard core including stacking.

7 Breaking stone to stone metal standard size 45 mm : 0.364 cum per labour per day
for PCC including stacking.

8 Breaking stone to stone chips standard size 22.4 mm : 0.196 cum per labour per day
for PCC including stacking.
9 Breaking of Jhama/overburnt bricks to : 0.82 cum per labour per day
metal/coarse aggregate and stacking along
roadside.
10 Dressing stone 15 x 20 cms average section by : 0.26 cum per mason per day
hammer for face work in coursed rubble stone
masonry or otherwise including stacking

c) PERMANENT
1 Excavation in trenches not exceeding 1.2 m width and : 1.78 cum per labour per day
1.5 m depth in soil/soil mixed with boulders dressing
bottom and sides, getting out incl disposing all
excavated materials lead upto 3 m
2 - Do - soft rock : 0.83 cum per labour per day

3 - Do - hard rock (by blasting) : 1.40 cum per labour per day

4 Add for extra lead for 3 m and part thereof on item on : 5.66 cum per labour per day
srl No. 11, 12 and 13 above
5 Hard core comprising of broken road metal size 50 : 1.50 cum per labour per day
mm graded downward spread in layers not exceeding
15 cm including watering, ramming and finishing to
required level and gradient.
6 Dewatering below water table zone in area having : 1.09 labour per cum per day
rain fall upto 200 cm

S/No Item of works Output

2-7
SSR 2009

7 Dewatering below water table zone in area having : 1.308 labour per cum per day
rain fall above 200 cm

8 Laying cement concrete 1:3:6 or 1:4:8 or 1:5:10 (1 : 20 cum per 25 labs and 0.05
cement, 3 sand and 6 coarse aggregate /1 cement mason per day
4 sand and 8 coarse aggregate/1 cement 5 sand
and 10 coarse aggregate) mixed in concrete mixer
(one bag cement capacity) excluding centering
and shuttering in foundation of walls etc.

9 Reinforced/plain cement concrete 1:2:4 (1 : 7 cum per 25 labs and 0.2857


cement 2 sand and 4 coarse aggregate) in slabs, mason per day
mixed in concrete mixer (one bag cement
capacity) excluding centering and shuttering
10 RCC M-20, RCC M-25, RCC M-30 & M-35 excluding : 7 cum per 25 labs and 0.1429
centering and shuttering mason per day

11 Centering and shuttering including strutting and : 5.3 sqm per carpenter with 1.1
propping labour per day

12 Cutting, bending, placing and binding reinforcement : 91 kg per B/smith with 1 labour
of MS round bars upto 12 mm dia per day

13 -Do- beyond 12 mm dia : 137 kg per B/smith with 1 labour


per day
14 Pre cast slab RCC 1:2:4 : 7 cum per 25 labs and 2
mason, 1.0549 B/Smith &
2.3679 Carp per day
15 Masonry work in concrete hollow block : 3.144 labour per cum with
0.2584 B/smith & 0.5922 mason

16 Finishing surface of concrete road pavement by : 100 sqm per labour per day
belting
17 Finishing surface of concrete road pavement by : 50 sqm per labour per day
brooming
18 Brick walling in cement mortar : 1.25 cum per mason with 1.80
labour per day
19 Walling of rubble stone, laid dry well bonded face : 0.92 cum per mason with 1.8
with selected bond stone evenly spaced @ 2 Nos labour per day
per Sqm of wall face
20 Sausage walling (Rubble masonry) : 1.0 cum per 1.09 mason
+ 2.09 labour and 0.13 B/smith
per day

21 Dry walling in Geo-Synthetic netting : 0.92 cum per mason with 2


labour per day
22 Slope reinforcement with Geo-synthetic netting : 2.00 labour with 0.50 mason per
10 sqm per day
23 Random or polygonal rubble walling brought to : 0.92 cum per mason with 2
course at 45 to 60 cm in cement mortar labour per day

24 Filling of stone/selected materials in proper manner : 1.89 cum per labour per day
behind the retaining/breast wall
25 Stone pitching with required thickness : 4.25 cum per mason with 3
labour per day

S/No Item of works Output

3-7
SSR 2009

26 Sausage walling (Dry boulder filling) : 2.07 labour with


0.09 mason + 0.09 B/smith per
cum per day

27 1.2 cm plaster in CM 1:6 (1 cement: 6 sand) : 10.52 sqm per mason with
labour per day

28 2.5 cm plaster in CM 1:6 (1 cement: 6 sand) : 6.6 sqm per mason with 2/3
labour per day
29 Flush or rule pointing on stone works with cement : 11.52 sqm per mason with
mortar 1:3 (1 cement: 3 sand) labour per day
30 White washing : 0.20 labour per 10 sqm per day

31 Painting (2 coats) : 20 sqm per painter with one


labour per day
32 False ceiling with ply wood 4 mm thick : 18.9043 labour with 1.8519
carpenter per 10 sqm per day
SURFACING
1 Moorum spreading : 4.07 labour per 10 sqm per day

2 Granular Sub Base 10 cm thick with sand, : 0.243 labour per 10 sqm per
moorum & Gravel day
3 Granular Sub Base 15 cm thick with sand, : 0.277 labour per 10 sqm per
moorum & Gravel day
4 Granular Sub Base 10/15 cm thick with brick : 10.50 sqm per labour per day
aggregate
5 Granular Sub Base 10 cm thick with stone : 10.50 sqm per labour per day
aggregate
6 Granular Sub Base 15 cm thick with stone aggregate : 9.00 sqm per labour per day

7 Shingling 50 mm thick : 0.186 labour per 10 sqm per day

8 Shingling 75 mm thick : 0.213 labour per 10 sqm per day

9 Shingling 100 mm thick : 0.246 labour per 10 sqm per


day
10 Shingling 150 mm thick : 0.279 labour per 10 sqm per
day
11 Lime soil stabilisation : 1.42 labour per 10 sqm

12 Sand blanketing 25/100 mm thick : 0.15 labour per 10 sqm

13 Scarifying existing BT surface : 1.3165 labour per 10 sqm

14 Water Bound Macadam 10 cm consolidated : 10.3 sqm per labour per day
thickness incl all work as specified
15 - Do - 7.5 cm thick : 15.4 sqm per labour per day

16 Wet Mix Macadam 75 mm thick : 46.5 sqm per labour per day

17 Wet Mix Macadam 100 mm thick : 35.0 sqm per labour per day

18 Preparing WBM surface laying 2.5 cm premix carpet : 7 sqm per labour per day
with stone chippings applying sand seal coat and
rolling

19 -Do- 2 cm premix carpet : 7.7 sqm per labour per day

20 Liquid seal coat : 15 sqm per labour per day

S/No Item of works Output

4-7
SSR 2009

21 Preparing WBM surface and laying precoated : 6.7 sqm per labour per day
bituminous mixture of 2 parts broken stone
metal and 1 part sand including consolidation
complete as in premix dense carpet 4 cm
consolidated thickness
22 -Do- 5 cm (2) : 5.34 sqm per labour per day

23 Surface dressing (Two coat) with bitumen 80/100 : 10 sqm per labour per day

24 Surface dressing (Two coat) with CBE : 0.5089 sqm per labour per day

25 Surface dressing renewal coat : 0.456 lab per 10 sqm

26 Premixed sand seal coat consisting of 6.8 Kg bitumen : 0.01 labour per 10 sqm per day
and 0.06 cum of sand per 10 sqm of road
27 2 cm thick premix carpet with liquid seal coat using : 1.01 labour per 10 sqm
cationic bitumen emulsion
28 2 cm thick premix carpet with premixed seal coat, : 1.01 labour per 10 sqm per day
using cationic bitumen emulsion

29 Built up spray grouting 75 mm thick : 1.63 labour per 10 sqm per day

30 Mix seal surfacing type A : 1.0848 labour per 10 sqm per


day
31 Mix seal surfacing type B : 1.0428 labour per 10 sqm per
day
32 Laying 5 cm (laid thickness) shingle or other : 53.76 sqm per labour per day
similar approved material spread and
leveled to gradient
33 Laying 7.5 cm (laid thickness) shingle or other : 46.95 sqm per labour per day
similar approved material spread and
leveled to gradient
34 Laying 10 cm (laid thickness) shingle or other : 40.65 sqm per labour per day
similar approved material spread and
leveled to gradient
35 Laying 15 cm (laid thickness) shingle or other : 35.84 sqm per labour per day
similar approved material spread and
leveled to gradient
36 Lime stabilisation : 1.42 labour per 10 sqm per day

37 For reduction in labour for black topping over an : 0.373 labour per 10 sqm per day
already existing black topped surface
38 Bituminous macadam 7.5 cm thick : 3.50 labour per 10 sqm per day

39 Bituminous macadam 5 cm thick : 2.9 labour per 10 sqm per day

40 Asphaltic concrete : 1.23 labour per 10 sqm per day

41 Add to or deduct from any item of bituminous work for : 0.014 labour per 10 sqm per day
variation in the quantity of paving bitumen per
Kg
42 Add to or deduct from any item of bituminous work for : 0.01 labour per 10 sqm per day
variation in the quantity of chippings per 0.01
cum size of chipping 12.5 mm graded
downwards
43 25 mm thick Semi Dense Bituminous concrete : 1.7688 labour per 10 sqm per
day per day
44 Forming 12 mm thick expansion joints filled with : 0.22 labour per 10 m per day
preformed filler and top 30 mm premixed and
sealed with sealing compound 100 mm depth

45 -Do- 150 mm depth : 0.22 labour per 10 m per day

46 -Do- 200 mm depth : 0.31 labour per 10 m per day

47 -Do- 250 mm depth : 0.31 labour per 10 m per day

5-7
SSR 2009

S/No Item of works Output

48 Forming 20 mm thick expansion joints filled with : 0.25 labour per 10 m per day
preformed filler and top 30 mm premixed and
sealed with sealing compound 100 mm depth
49 -Do- 150 mm depth : 0.25 labour per 10 m per day

50 -Do- 200 mm depth : 0.34 labour per 10 m per day

51 -Do- 250 mm depth : 0.34 labour per 10 m per day

52 Add to items of expansion joints, if provided with 20 : 0.252 labour per No. with
mm dia mild steel dowel one metre long with 0.189 B/smith per day
ferrules, faced at 400 mm centers including
boring form work and preformed filler for
dowel
53 Forming contracting (Dummy) joint 60 mm deep x 10 : 0.25 labour per 10 m per day
mm wide filled with sealing compound
54 Forming construction joint 30 mm x 10 mm wide filled : 0.15 labour per 10 m per day
with sealing component
55 Add to or deduct from the item of contraction joint for : 0.02 labour per 10 m per day
every 5 mm depth of joint
56 CSB 75/100 mm thick : 15.40 sqm per labour per day

57 Mastic Asphalt 25 mm thick 10.00 labour per 35 sqm per


day
58 Tack coat on prepared bituminous/granular : 1750 Sqm per labour per day
surface
59 Fixing road delineator : 30 Nos per labour per day

60 Erecting/fixing of W beam crash barrier : 4.50 mtr per labour per day

61 Fixing roads cat eyes : 50 Nos per labour per day

B Plant/Equipment
1 Rough excavation in mixed soil (soil mixed with : 43.28 cum per Doze-II per hour.
boulders) and getting out

2 Rough excavation in soft rock, which can be quarried : 28.32 cum per Doze-II per hour.
or split with dozer blade and getting out
3 Rough excavation in hard rock by blasting and : 28.32 cum per Doze-II per hour.
getting out
4 Rough excavation in mixed soil (soil mixed with : 60 cum per hydraulic excavator
boulders) and getting out per hour.
5 Rough excavation in soft rock with 250/260 cfm : 240 cum per Compr per day
compressor with 2 jack hammers
6 Rough excavation in hard rock with 250/260 cfm : 120 cum per compr per day
compressor with 2 jack hammers
7 Dismantling of structures with 250/260 cfm : 9 cum per compr per day
compressor with 2 jack hammers
8 Earthwork in embankment by filling with earth : 500 cum per RR per day
free from roots etc. spreading in layers
9 Earthwork in embankment by filling with earth : 100 cum per motor grader per
free from roots etc. spreading in layers hour
10 Loading materials or similar items : 30 cum per hour per JCB

11 Crushing stone metal size 50 mm graded down to : 11.43 cum per hour per 20 TPH
12.50 mm out of selected stone crusher

6-7
SSR 2009

S/No Item of works Output

12 Crushing stone chips of size 20 mm nominal size : 11.03 cum per hour per 20 TPH
graded downwards out of selected stone crusher
13 Crushing stone chippings of size 6 mm nominal : 10.67 cum per hour per 20 TPH
size graded downwards out of selected crusher
stone
14 Dewatering below water table zone in area having : 1.09 water pump per cum
rain fall upto 200 cm
15 Dewatering below water table zone in area having : 1.308 water pump per cum
rain fall above 200 cm
16 Mixing mortar for concrete (1:5:10, 1:4:8 & 1:3:6) : 20 cum per mixer day

17 Mixing mortar for concrete (1:2:4,1:1.5:3) : 7 cum per mixer day

18 Consolidation of sub-grade in SMB with 8 to 10 : 1850 sqm per roller per day
ton road roller
19 Consolidation of Granular Sub Base 15 cm with 8 to : 190 sqm per roller per day
10 ton road roller
20 Consolidation of Granular Sub Base 10 cm with 8 to : 250 sqm per roller per day
10 ton road roller
21 Consolidation of shingle with 50 mm 8 to 10 ton road : 476 sqm per roller per day
roller
22 Consolidation of shingle with 75 mm 8 to 10 385 sqm per roller per day
ton road roller
23 Consolidation of shingle with 100 mm 8 to 10 ton : 385 sqm per roller per day
road roller
24 Consolidation of shingle with 150 mm 8 to 10 ton 385 sqm per roller per day
road roller
25 Consolidation of water bound macadam surface : 248 sqm per roller per day
10 cm thick with 8 to 10 ton road roller
26 Consolidation of water bound macadam surface : 372 sqm per roller per day
7.5 cm thick with 8 to 10 ton road roller
27 Mixing aggregates with wet mix plant 60 TPH : 13.07 cum per hour

28 Mixing aggregates with hot mix plant 20/30 TPH : 8.89 cum per hour

29 Consolidation of Wet Mix Macadam 75 mm thick with : 315 sqm per roller per day
8 to 10 ton road roller
30 Consolidation of Wet Mix Macadam 100 mm thick : 248 sqm per roller per day
with 8 to 10 ton road roller
31 - Do - 2 coats surface dressing : 560 sqm per roller per day

32 Consolidation of 2.5 cm thick premix carpet : 560 sqm per roller per day
including sand seal coat with 8 to 10 ton
road roller
33 -Do- 2 cm thick : 560 sqm per roller per day
34 Heating bitumen with tar boiler 2000 Ltrs : 1900 Kg of bitumen per day
35 Consolidation of bituminous mixture 2 part of broken : 372 sqm per roller per day
stone metal and one part of sand 4 cm thick
with 8 to 10 ton road roller
36 Consolidation of 20 cm thick moorum spreading : 250 sqm per roller per day
to 15 cm (consolidated) with road roller
8/10 ton
37 Consolidation on soil stabilisation (with lime) 15 cm : 909 sqm per roller per day
thick (consolidated) with RR 8/10 ton
38 Consolidation of sand blanketing 25/100 mm thick : 2000 sqm per roller per day
with Road Roller 8/10 ton

7-7
SSR 2009

S/No Item of works Output

39 Consolidation of built up spray grouting 7.5 cm thick : 248 sqm per roller per day
with Road Roller 8/10 ton
40 Consolidation of bituminous macadam 7.5 cm/5 cm : 372 sqm per roller per day
thick with Road Roller 8/10 ton
41 Consolidation of Asphaltic concrete 4 cm thick with : 372 sqm per roller per day
Road Roller 8/10 ton
42 Consolidation of surface dressing renewal coat with : 560 sqm per roller per day
Road Roller 8/10 ton
43 Consolidation of 2 cm thick premix carpet with liquid : 560 sqm per roller per day
seal coat with Road Roller 8/10 ton
44 Consolidation of premixed sand seal coat with RR : 1850 sqm per roller per day
8/10
45 Consolidation of mix seal surfacing type A/ type B : 762 sqm per roller per day
with RR 8/10
46 Consolidation of 25 mm thick semi dense bituminous : 595 sqm per roller per day
concrete with RR 8/10
47 Carrying capacity of tipper (4.5 cum) for stone chips : 7 Trips per veh per day
and sand upto 5 Km initial lead (3.75 cum per
trip)
48 Carrying capacity of tipper (4.5 cum) for : 8 Trips per veh per day
boulders/stone/ballast upto 5 Km initial lead
(3.75 cum per trip)
49 Carrying capacity of tipper (4.5 cum) for stores : 4 Trips per veh per day
upto 5 Km initial lead (5 MT per trip)
50 Carrying capacity of tipper (12 cum) for stone : 8 Trips per veh per day
chips and metal upto 5 Km initial lead (9.6
cum per trip)
C Manpower alongwith Veh/Eqpt/Plant

1 Dozer D-50 (Size-II) : 3 labour per day


2 Compressor 250/260 cfm with two jack hammer : 3 labour per day
3 Road Roller 8/10 ton : 1 labour per day
4 Hot Mix Plant 20/30 TPH : 17 labour per day
5 Wet Mix Plant 60 TPH : 14 labour per day
6 Sensor Paver : 6 labour per day
7 Pay loader/ Wheel Dozer/JCB : 4 labour per day
8 Motor grader 100 cum per hour : 2 labour per day
9 Stone Crusher 20 TPH : 10 labour per day
10 Load Carrier/Tipper : 7 labour per day
11 Water Truck 9 KL capacity : 1 labour per day
12 Concrete mixer : 25 labour per day
13 Crane 10 Ton : 10 labour per day
14 Bitumen pressure distributor : 2 labour per day
D MATERIALS AND STORE NORMS

Surfacing Works
1 GSB 10 cm thick with sand,morrum & gravel : S/Metal 0.72 cum
S/Chips 0.56 Cum
Sand 0.32 cum
Per 10 sqm
2 GSB 15 cm thick with sand,morrum & gravel : Gravel 1.08 cum
Sand 0.72 cum
per 10 sqm
3 GSB 10 cm thick with brick aggregate : Brick Agg- 1.52 cum per 10
sqm
4 GSB 15 cm thick with brick aggregate : Brick Agg- 2.28 cum per 10
sqm

8-7
SSR 2009

S/No Item of works Quantity

5 GSB 10 cm thick with stone aggregate : S/Metal 0.56 cum


S/chips 0.72 cum
Sand 0.32 cum
Per 10 sqm
6 GSB 15 cm thick with stone aggregate : S/Metal 0.84 cum
S/chips 1.08 cum
Sand 0.48 cum
Per 10 sqm
7 Shingling 50 mm : Shingle 0.675 cum per 10
sqm
8 Shingling 75 mm : Shingle 1.0125 cum per 10
sqm
9 Shingling 100 mm : Shingle 1.20 cum per 10 sqm

10 Shingling 150 mm : Shingle 1.80 cum per 10 sqm

11 Sand blanketing 25 mm : Sand 0.3125 cum per 10 sqm

12 Sand blanketing 100 mm : Sand 1.25 cum per 10 sqm

13 WBM 7.5 cm thick S/metal 0.99 cum


S/chips - 0.135 cum
Sand 0.075 cum
per 10 sqm
14. WBM 10 cm thick : S/metal 1.32 cum
S/chips - 0.285 cum
Sand 0.10 cum
per 10 sqm
15. Wet Mix Macadam 75 mm thick Sand/dust 0.3616 cum
S/metal 0.3616 cum
S/chips 0.4821 cum
Per 10 sqm
16. Wet Mix Macadam 100 mm thick Sand/dust 0.4821 cum
S/metal 0.4821 cum
S/chips 0.6429 cum
Per 10 sqm
17. Premix carpeting with sand seal coat 2 cm thick : Stone chips -0.274 cum,
over WBM surface Sand 0.06 cum and
Bitumen 21.75 Kg
Firewood 45.13 Kg
Per 10 sqm
18. Premix carpeting with sand seal coat 2.5 cm thick : Stone chips - 0.343 cum,
over WBM surface Sand 0.06 cum,
Bitumen 25.48 Kg
Firewood 53.69 Kg
Per 10 sqm
19 2 cm thick BT with sand seal coat on existing BT : Stone chips - 0.274 cum
surface Sand 0.06 cum
Bitumen 21.75 Kg
Firewood 45.13 Kg
Per 10 sqm
20 Premix carpeting 4 cm thick over WBM surface : S/chips 0.40 cum,
Sand 0.20 cum
Bitumen-33.50 Kg
Firewood 75.50 Kg
Per 10 sqm
21 Premix carpeting 5 cm thick over WBM surface : S/chips 0.50 cum,
Sand 0.25 cum
Bitumen-41.90 Kg
Firewood 94.40 Kg
Per 10 sqm
S/No Item of works Quantity

9-7
SSR 2009

22. Liquid seal coat : S/chippings 0.09 cum


Bitumen 9.80 Kg
Firewood 16.10 Kg
Per 10 sqm
23 Surface dressing renewal coat (two coat) : S/chips 0.25 cum
Bitumen 32.00 Kg
Firewood 49.50 Kg
Per 10 sqm
24. Built up spray grouting 7.5 cm thick : S/metal - 1.13 cum,
Bitumen 30 Kg
Firewood 30.00 Kg
Per 10 sqm
25 Bituminous Macadam 7.5 cm thick : S/chips 0.9022 cum,
Sand 0.1592 cum
Bitumen 54.3293 Kg
LDO 14.553 Ltrs
Per 10 sqm
26. Bituminous Macadam 5 cm thick : S/chips 0.6014 cum,
Sand 0.1061 cum
Bitumen 36.2195 Kg
LDO 9.702 Ltrs
Per 10 sqm
27 Dense Bituminous Macadam 7.5 cm thick : S/chips 0.405 cum,
Sand 0.33 cum
S/dust 0.015 cum
Bitumen 73.5769 Kg
LDO 14.553 Ltrs
Per 10 sqm
28 Dense Bituminous Macadam 5 cm thick : S/chips 0.27 cum,
Sand 0.1061 cum
S/dust 0.01 cum
Bitumen 49.0513 Kg
LDO 9.702 Ltrs
Per 10 sqm
29. Asphaltic concrete 4 cm thick : S/chips 0.3215 cum
Sand 0.2514 cum
Cement 18.0524 kg
Bitumen 47.1204 kg
LDO 7.7616 Ltrs
Per 10 sqm
30. Asphaltic concrete 2.5 cm thick : S/chips 0.201 cum
Sand 0.1571 cum
Cement 11.2827 kg
Bitumen 29.4503 kg
LDO 4.9588 Ltrs
Per 10 sqm
31 Semi-dense bituminous concrete 2.5 cm thick : Sand 0.1469 cum
S/chips 0.213 cum
S/Dust 0.0074 cum
Bitumen 25.9615 kg
LDO 4.851 Ltr
Per 10 sqm
32 Semi-dense bituminous concrete 4 cm thick : Sand 0.2351 cum
S/chips 0.3409 cum
S/Dust 0.0118 cum
Bitumen 41.5385 kg
LDO 7.7616 Ltr
Per 10 sqm
33 Mastic Asphalt 25 mm thick : Bitumen 57.2857 Kg
S/chippings 0.1114 cum
S/chips 0.1629 cum
Lime 102.8571 Kg
Per 10 sqm
S/No Item of works Quantity

10 - 7
SSR 2009

34 Tack coat : Bitumen emulsion 2.50 Kg


Per 10 sqm

35 Premix carpet with liquid seal coat 2.5 cm thick : S/chips - 0.3425 cum,
Sand 0.09 cum
Bitumen 28.05 kg
Firewood 58.325 Kg
Per 10 sqm
36 Premix carpet with liquid seal coat 2 cm thick : S/chips - 0.274 cum,
Sand 0.09 cum
Bitumen 24.72 kg
Firewood 50.20 Kg
Per 10 sqm
37 Premix sand seal coat : Sand 0.060 cum
Bitumen 6.80 Kg
Firewood 11.00 Kg
Per 10 sqm
38 2 cm thick premix with liquid seal coat using CBE : S/chips 0.27 cum
S/chippings 0.09 cum
CBE 31.30 Kg
Per 10 sqm
39 2 cm thick premix with sand seal coat using CBE : S/chips 0.27 cum
Sand 0.06 cum
CBE 28.30 Kg
Per 10 sqm
40 Two coat surface dressing with CBE : S/chips 0.20 cum
CBE 20.00 Kg
Per 10 sqm

41. Prime coat : CBE 7.50 Kg


Per 10 sqm

42. CSB 7.5 cm thick : S/metal 0.328 cum


S/chips 0.3147 cum
Sand 0.3473 cum
Per 10 sqm
43. CSB 10 cm thick : S/metal 0.4374 cum
S/chips 0.4196 cum
Sand 0.463 cum
Per 10 sqm
44 Mix seal surfacing Type A : Sand 0.060 cum
S/chips 0.21 cum
Bitumen 22.00 kg
Firewood 40.90 Kg
Per 10 sqm
45 Mix seal surfacing Type B : Sand 0.060 cum
S/chips 0.21 cum
Bitumen 19.00 kg
Firewood 37.90 Kg
Per 10 sqm
PERMANENT WORKS

46 Excavation in hard Rock : Explosive 0.35 kg per cum of


Hard Rock
47 Excavation in soft Rock : Explosive 0.175 kg per cum of
soft Rock
48 Hard core : S/metal 1.05 cum per cum

S/No Item of works Quantity

11 - 7
SSR 2009

49 PCC 1:5:10 : S/metal 0.98 cum


Sand 0.49 cum
Cement 126 kg
Per cum
50 PCC 1:4:8 : S/metal 0.97 cum
Sand 0.48 cum
Cement 165 kg
Per cum
51 PCC 1:3:6 : S/metal 0.92 cum
Sand 0.46 cum
Cement 220 kg
Per cum
52 PCC 1:2:4 : S/chips 0.90 cum
Sand 0.45 cum
Cement 275.33 kg
Per cum
53 RCC 1:2:4 : S/chips 0.90 cum,
Sand 0.45 cum and
Cement 275.33 kg
Per cum
54 RCC M-20 : S/chips 0.90 cum
Sand 0.45 cum
Cement 347.33 kg
Per cum
55 RCC M-25 : S/chips 0.90 cum
Sand 0.45 cum
Cement 403.33 kg
Per cum
56 RCC M 30 : S/chips 0.90cum
Sand 0.45 cum
Cement 406.67 kg
Per cum
57 RCC M 35 : S/chips 0.90cum
Sand 0.45 cum
Cement 422.00 kg
Per cum
58 RCC M 40 : S/chips 0.90cum
Sand 0.45 cum
Cement 435.00 kg
Per cum
59 Masonry work in Concrete Hollow block : S/chips 0.534 cum
Sand 0.4678 cum
Cement 170.37 kg
Per cum
60 Brick masonry in cm 1:6 : Sand 0.202 cum
Bricks 500 Nos
Cement 47.00 Kg
Per cum
61 Brick masonry in cm 1:4 : Sand 0.20 cum
Bricks 500 Nos
Cement 71.00 Kg
Per cum
62 Brick masonry in cm 1:3 : Sand 0.175 cum
Bricks 500 Nos
Cement 85.00 Kg
Per cum
63 RRM dry : Rubble stone 1.10 cum per
cum

64 Sausage walling (masonry) : Rubble stone 1.22 cum


GI wire 11.80 Kg
Per cum
S/No Item of works Quantity

12 - 7
SSR 2009

65 Sausage walling (boulder filling) : Stone boulder 1.22 cum


GI wire 9.23 Kg
Per cum
66 Dry walling with Geo-synthetic netting : Rubble stone 1.22 cum
Geo-synthetic net 11.80 sqm
Per cum
67 Rubble walling in cement mortar 1:6 : Rubble stone 1.10 cum
Sand 0.31 cum
Cement 73.5 kg
Per cum
68 Rubble walling in cement mortar 1:4 : Rubble stone 1.10 cum
Sand 0.32 cum
Cement 112 kg
Per cum
69 Rubble walling in cement mortar 1:3 : Rubble stone 1.10 cum
Sand 0.32 cum
Cement 144 kg
Per cum
70 Lined drain : Rubble stone 0.3625 cum
Per mtr
71 Flush pointing on Stone work with CM 1:3 : Sand 0.08 cum
Cement 36.50 kg
Per 10 sqm
72 1.2 cm thick plaster 1:6 : Sand 0.227 cum
Cement 55.00 Kg
Per 10 sqm
73 2.5 cm thick plaster 1:6 : Sand 0.36 cum
Cement 88.00 Kg
Per 10 sqm
74 Providing steel centering and shuttering including : Timber 0.04 cum per 10 sqm
preparing and removing the same
(considering use of 10 times)
75 False ceiling with ply wood 4 mm thick : Ply wood 4 mm - 10.0309 sqm
Timber - 0.0818 cum
per 10 sqm
76 Filling of stone : Stone boulder - 1.10 cum
per cum of back fill qty
77 Stone pitching : Rubble stone 1.25 cum per
cum
78 White washing : Lime - 2.40 kg per 10 sqm

79 Painting :
Paint - 5.00 Ltrs per 10 sqm for
two coats
80 Road marking with thermoplastic paint 25 mm : Paint 25.00 Kg
Glass beads 2.50 Kg
LPG gas 4.44 Kg
Per 10 sqm
Not The highlighted norms are updated as per MoSRT&H Standard Data Book
e for Rate Analysis. All norms are suggestive only and actual quantity will
be worked out based on Job mix formula/design mix.

13 - 7