CHINA CEC ENGINEERING CORPORATION AND LN FANGDA CHEMICAL PLANNING AND DESIGN CO LTD JV

DCEP 60,000 TPA Integrated PVC Resin Manufacturing Plant in Mekelle, Ethiopia


WEEKLY REPORT(2017.03.23--2017.03.29)

No. Issues

2017.03.23-2017.03.29
What we have done in this week
A

Work plan to finish this week Work finished this week Instruction

323-3296328(45
Weather of this week: Sunny from March 23th to March 29thMarch 28th heavy rain4:00-5:00 pm

Actual compared with schedule


(36)
1 Plant area constructionthe construction work of march in general schedule: the construction work was organised according to the
foundation drawing of accrommodation area and foundation drawing of raw salt storage area confirmed on 6th March and the general drawing
of interal road

1.1 Excavation of ditch against flood out of north fence Finish.
shall be finished.


1.2 Excavation of road around the fence shall be Finish
finished.


1.3 Preparation work before backfill of road around the Finish
fence shall be finished.
800m. CEC-FDG JV has asked SUR to satrt the
1.4 Excavation of other road in plant shall be executed Not satrted excavation work of internal road, however,
and 800m shall be finished. the work were not excuted.

1.5 Construction of accommodation area shall be Have started;
executed.
CEC-FDG JV has asked SUR to satrt the

excavation work of salt storage and
1.6 Excavation of foundation in the salt storage and Not satrted
conveying section , however, the work were
conveying section shall be started.
not excuted.
1
2
Construct of the campsite I area.

100%
Finish 100% of the excavation work and concrete
2.1 Finished
cushion work for the trench around basketball and
dormitory

35%
2.2 Finished
Finish 35% of all sewer and water supply pipe work.

75%
2.3 Finished
Finish 75% of roofing system of Canteen.
35%
2.4 Finish 35% of installation work for precast coping Finished
for the fence.
300mm150mm75%. Because the elevation of SUR's road is
2.5 Finish 75% Road 300mm fill and surveying work and 35% was finished difference from the desinging elevation of
150mm aggregate spreading. the cross point of composite road.
100%
The EGA material for the ridge has not been
2.6 Finish 100% of Guard house roof system were 90% was finished
delivered to the site.
finished.
50%
2.7 Finished
Finish 50% of marsonary stone for north gate.

75%
2.8 Finish 75% of HCB work for the well in Dormitory Finished
area.

Clean
2.9 Finished
up the material of prefabrication house.


Extra work finished this week

1
Plant area construction

CBR
1.1
CBR test of in situ material and elevation checking of road after excavation have been executed with the owner.
90.
1.2
Backfill of the fence foundation around the west gate and foundation masonary work of the fence at south side of gate have been finished.

2000m.
1.3
2000m coping work of plant fence has been finished in total.

1
2
Construction of the campsite I area.

50% 100% of
2.1
marsonary stone for north gate were finished.

60%
2.2
60% of the plastering work for the internal of Canteen were finished.

100%75%
2.3
100% of first layer plaster work and 75% of second layer plaster work for the guard room were installed.

25% 25% of
2.4
HCB work for the masonary trench aoround basketball were finished.


Quality

1
Quality under control

SURCEC-FDG JVSUR
1.1 The thickness of coping of south plant fence were not constructed according to the drawings, CEE-FDG JV has put forward the rectify
requirements aiming to this quality problem and SUR has promised to rectify and reform according to the requirements.


HSE

1
HSE under control

CEC-FDG JVSUR
1.1 Certain excavation of foundation in plant site have been finished,CEC-FDG JV required SUR to set the safety precautions around the
foundation and warning the personel in site pay attention to falling.

2017.03.30~2017.04.05
B
What we are going to do next week
Plant area construction the construction work of march in general schedule: the construction work was organised according to
the foundation drawing of accrommodation area and foundation drawing of raw salt storage area confirmed on 6th March and the general
1
drawing of interal road


1.1
Backfill and compaction of north road around the fence shall be finished.


1.2
The first layer backfill and compaction of east road around the fence shall be finished .

800m.
1.3
Excavation of other road in plant shall be executed and 800m shall be finished.

.
1.4
Excavation of the fence in accommodation area shall be finished.

.
1.5
Backfill of the fence in accommodation area shall be finished.

.
1.6
Masonry work of the fence in accommodation area shall be started.

23
1.7
Excavation work of the 2nd and 3rd residence buildings are palned to satrt .


1.8
Excavation of foundation in the salt storage and conveying section shall be started.


1.9
Construction preparation work of office building area shall be started.

1
2
Construction of the campsite I area.

100%
2.1
100% of HCB work for the masonary trench aoround basketball were finished.

65%
2.2
Finish 65% of all sewer and water supply pipe work .

100%
2.3
Finish 100% of roofing system of Canteen.

55%
2.4
Finish 55% of installation work for precast coping for the fence.
100%
2.5
Finish 100% of Guard house roof system were finished.

.
2.6
Construction work of ground and installition of window and door in guard room shall be finished.


2.7
Concrete pouring of cushion for ground in canteen shall be finished.

100%
2.8
Finish 100% of HCB work for the well in Dormitory area.

100%
2.9
60% of the plastering work for the internal of Canteen were finished.

5%
3
Finish 5% of prefabrication house installation work.

2017.04.06~2017.04.12
C
Key points for the third week


1
Plant area construction plan.


1.1
The inside fence road excavation work.


1.2
The inside fence road backfill work.


1.3
Accomodation area foundation excavation work.

Salt
1.4
storage foundation excavation work.

1
2
Construction of Campsite I area

4-1
2.1
The decoration work in Canteen.

6M
2.2
Construction of the 6 meters road.

Electrical and
2.3
plumbing work for the temperary composite.

34
2.4
Construction of the 3 meters wide road and 4 meters wide road.

D
Problems and suggestions


E
Photos

P2:excavation of fence foundation in accomodation area


P1:Ditch aginst flood

P3:Canteen roof system P4: sewer pipe work and well work