NRS 040-5:2007
Edition 1
HIGH-VOLTAGE OPERATING
REGULATIONS
N R S
This specification is issued by
the Standardization Section, Eskom,
on behalf of the
User Group given in the foreword.
Table of changes
Change No. Date Text affected
COPYRIGHT RESERVED
Foreword
This part of NRS 040 was prepared on behalf of the Electricity Suppliers Liaison Committee (ESLC)
and approved by it for use by supply authorities and other users.
This part of NRS 040 was prepared by a working group which, at the time of publication, comprised
the following members:
A reference is made in the NOTE to clause 1 to "legislation". In South Africa this means the
Occupational Health and Safety Act (OHS Act), 1993 (Act No. 85 of 1993) (as amended from time
to time) and the Regulations promulgated in terms of the Act.
NRS 040 consists of the following parts, under the general title High-voltage operating regulations:
Part 1: Definitions.
Part 2: Voltage colour coding for diagrammatic displays in control rooms Colour coding for wall-
mounted operating diagrams and electronic displays relating to the generation, transmission and
distribution of electricity.
Part 3: Model regulations Recommended model regulations relating to power systems for
operating, access control and supervision of systems that exceed 1 000 V, for the transmission and
distribution of electricity.
Part 4: Recommended model for the training, competency assessment and authorization of the
electricity supply industry for network operations.
Part 5: Standard procedure and terminology for the issuing of operating instructions.
3
NRS 040-5:2007
Introduction
This part of NRS 040 has been prepared to establish and promote uniform requirements for the
issuing of operating instructions for application in the South African Electricity Distribution Industry.
The ESLC expresses the wish that all supply authorities will adopt the text of this part of NRS 040 in
so far as their particular conditions will permit. Any differences between the requirements of this
part of NRS 040 and the purchaser's requirements should, as far as possible, be clearly indicated
and, where appropriate, be submitted for consideration in future revisions of this part of NRS 040.
Keywords
earthing, network management centres, operating instructions.
4
1 NRS 040-5:2007
Contents
Page
1 Scope .......................................................................................................................................... 3
4 Requirements .............................................................................................................................. 4
1 Scope
This part of NRS 040 defines a procedure and terminology for control and field staff interaction
when operating medium-voltage and high-voltage apparatus.
NOTE This part of NRS 040 is an extension of legislation. Read this part of NRS 040 in conjunction with
legislation (see foreword).
2 Normative references
The following document contains provisions which, through reference in this text, constitutes
provisions of this part of NRS 040. All documents are subject to revision and, since any reference to
a document is deemed to be a reference to the latest edition of that document, parties to
agreements based on this specification are encouraged to take steps to ensure the use of the most
recent edition of the document listed below. Information on currently valid national and international
standards can be obtained from Standards South Africa.
NRS 040-3, High-voltage operating regulations Part 3: Model regulations Recommended model
regulations relating to power systems for operating, access control and supervision of systems that
exceed 1 000 V, for the transmission and distribution of electricity.
bus coupler
apparatus used for connecting two sets of busbar
controller
employee or official on duty at a control centre, who is responsible for the general operation of the
power system or of a section thereof
NRS 040-5:2007 4
security linking
contingency configuration of the network where isolation for maintenance could compromise
network stability (i.e. redundancy or firm supply requirements)
voltage regulator
device used for automatic voltage control at a pre-set voltage
3.2 Abbreviations
AVR: automatic voltage regulator
HMI: human machine interface
HV: high voltage
IPS: interconnected power system
MV: medium voltage
PTO: permission to operate
PTS: permission to sectionalize
VT: voltage transformer
4 Requirements
4.1 Operating process
The following block diagram depicts the process and communication between control and field staff
as discussed in this part of NRS 040.
Personal Site and plant Scope of work System integrity check and
introduction identification verification contingency planning
Approval for
PTO/PTS or
e-operating
Handover of
Commencement of Report completed apparatus
actual operating operating
4.2.1 At every occasion that contact is established between a control officer and an authorized
person in the field, the control officer and the authorized person will introduce one to the other by
stating their full names.
4.2.2 If called for by either party, the identification will be confirmed with additional information like
unique or identification numbers.
a) the location of the plant will include the name of the line, feeder or substation as it appears on
the equipments nameplate and operating diagram nametag. The line name may be
abbreviated; and
b) the equipment to be operated will be identified by the standard symbol on the operating
diagram and the equipment nameplate on the structure.
The authorized person will refer to the controller as control while the controller will address the
authorized person by his first name and surname (for example Koos Snyman).
Controller:
<First name and surname of authorized person>, at <name of substation>, <nominal voltage,
name of the panel >: open (or close) <name of the apparatus>, followed by all consecutive
instructions, as necessary.
NRS 040-5:2007 6
Controller
<First name and surname of authorized person>, at <name of substation>, <nominal voltage,
name of the panel>: I shall <open/close> <name of the apparatus>, followed by all consecutive
instructions.
After all isolation and earthing have been completed, the controller shall hand over the apparatus to
the authorized person. Handover is an instruction and the operation shall be written out in full by the
authorized person on an operating instruction form together with the time of handing over (handing
back).
4.11.2 Controller
<First name and surname of authorized person>, at <name of substation>, <nominal voltage,
name of the apparatus> has been opened, isolated and earthed at all points of supply. You may
commence with the specified work. On completion, remove all tools, equipment and workers and
report back to me.
<First name and surname of authorized person>, at <name of substation>, <nominal voltage and
name of the apparatus> has been opened, isolated and earthed at all points of supply. I may
commence with the specified work. On completion remove all tools, equipment and workers and
report back to you.
7 NRS 040-5:2007
4.12 Handing over and handing back of power lines or sections of power
lines
After all isolation and earthing have been completed, the controller shall hand over the apparatus to
the authorized person. Handover is an instruction and shall be written out in full by the authorized
person on an operating instruction form together with the time of hand over (hand back).
4.12.2 Controller
<First name and surname of authorized person>, at <nominal voltage of and name of line>, from
<abbreviated pole number> to <abbreviated pole number> the line has been opened and isolated
from all points of supply, with a control earth at the point of isolation. You may test and apply
working earths, commence with the specified work. On completion, remove all tools and equipment,
workers and working earths from the line and hand back the line to me.
<First name and surname of authorized person>, at <nominal voltage of and name of line>, from
<abbreviated pole number> to <abbreviated pole number> the line has been opened and isolated
from all points of supply, with a control earth at the point of isolation. I may test and apply working
earths, commence with the specified work. On completion, I shall remove all tools and equipment,
workers and working earths from the line and hand back the line to you.
4.16.1 When an outage is requested by field staff, the scope of work, operating sequence and
number of earths required shall be discussed in detail before any instructions are issued. This is
necessary to eliminate any misunderstanding or confusion.
a) switching;
b) linking;
d) earthing.
4.17.2 Where technology allows, control and equipment are not installed in separate rooms,
switching shall be performed in the following order:
a) supervisory facility;
Auto-reclose schemes differ from one protection scheme to the next. The breakers auto-reclose
function shall be made inoperable as given in the site-specific procedure.
Supervisory schemes differ from substation to substation and each substation requires different
treatment. At some stations the supervisory shall be switched OFF before any operating is
performed, whilst at others it shall be switched OFF depending on whether operating has been
completed or whether operating is conducted remotely, manually or HMI.
4.19.1 Where VT selection on busbars are not automated, the VT selection shall be performed
manually when a busbar is taken out of service.
4.19.2 The racking in and out of truck type voltage transformers shall only be carried out under
dead conditions. The particular requirements shall be stated in the local operating procedure.
4.22.1 When taking a transformer out of service and when returning it to service, the authorized
person shall ensure that the substation auxiliaries and AVR controls are correctly selected as given
in the site-specific procedure.
4.22.2 In the case of voltage regulators, the authorized person shall ensure that the tap changer
is in the neutral or mid tap position and manual position before bypassing.
4.23.1 Taking a line breaker out of service for maintenance purposes (alive back)
4.23.1.1 The procedure in 4.23.1.2 to 4.23.1.8 shall be followed when a line breaker is taken out of
service for maintenance purposes.
4.23.1.8 Safety test: the following shall be done during a safety test:
4.23.2.1 The procedure in 4.23.2.2 to 4.23.2.11 shall be followed when a line breaker is returned to
service after maintenance.
4.23.2.3 Remove earths at the busbar and line sides of the breaker (specify voltage), and specify
the number of earths.
4.23.2.11 Verify with control centre that all alarms are clear.
4.23.3 Taking a line and breaker out of service for maintenance (dead back)
4.23.3.1 The procedure in 4.23.3.2 to 4.23.3.17 shall be followed when a line and breaker are
taken out of service for maintenance.
NOTE Operating instructions are issued in separate steps because two or more authorized persons are
involved. Control centres will co-ordinate operating in conjunction with each other.
4.23.3.2 Verify with control centre that all alarms are clear.
4.23.3.5 Open breaker (specify voltage). (Supervisory shall be switched on for remote switching.)
NOTE The busbar isolator can be left in the closed position if work is to be done on the line only. Earthing is
then necessary only for the line.
4.23.3.9 Control centres to confirm the status of plant with one another.
4.23.3.12 Earth busbar side of breaker if the busbar isolator is open (specify voltage).
4.23.3.13 Earth line side of breaker if the busbar isolator is open (specify voltage).
4.23.3.16 Control centres to hand over the line with one another as given in NRS 040-3.
4.23.3.17 Control centres to hand over the line to various authorized persons to apply and remove
working earth as given in NRS 040-3.
4.23.4 Returning a line and breaker to service after maintenance (dead back)
4.23.4.1 The procedure in 4.23.4.2 to 4.23.4.14 shall be followed when a line and breaker are
returned to service after maintenance.
4.23.4.3 Control centres to hand back to each other and co-ordinate removal of earths.
4.23.4.5 Control centres to confirm removal of earths from one another and agree on linking.
4.23.4.9 Control centres confirm status and agree on closing and switching of auto-reclose and
supervisory.
4.23.4.14 Verify with control centre that all alarms are clear.
4.23.5 Taking an interconnected power system (IPS) line out of service for
maintenance
4.23.5.1 Outage is sanctioned by National Control and operating instructions will be issued in
separate steps as indicated in 4.23.5.2 to 4.23.5.8. This normally involves two control centres who
will issue the isolation and earthing instructions in conjunction with each other.
4.23.5.2 Authorized persons to contact relevant control centres to commence with the requested
outage.
4.23.5.3 Control centres to contact National Control and individually request permission to take line
out. National Control assesses the situation, checks voltage and loading, and switches out the line
at both ends (if required) through supervisory and applies a tag to the breakers. National Control
hands out the line to each control centre to issue the necessary operating instructions and, on
completion, hand back to National Control.
4.23.5.4 Control centres contact each other and co-ordinate the switching OFF of the supervisory
and auto-reclose and proceed with the isolation of line and busbar isolators. Control centres issue
instructions to individual authorized persons.
4.23.5.5 Control centres notify each other that isolations are complete and co-ordinate application
of earths.
NRS 040-5:2007 12
4.23.5.8 Each control centre can now hand out the line or panel to the various authorized persons.
4.24.1 The procedure in 4.24.2 to 4.24.10 shall be followed when an IPS line is returned to service
after maintenance.
4.24.3 Control centres to hand line back to each other and co-ordinate removal of earths.
4.24.4 Control centres issue instructions to remove earths and return them to the authorized
person.
4.24.5 Control centres contact National Control individually to hand back the line, clear of all
earths.
4.24.6 National Control will sanction busbar selection and switch ON supervisory to control
centres.
4.24.7 Control centre issues instructions to close busbar and line isolators and switching ON of
supervisory to authorized persons. Receive confirmation that linking has been completed as
instructed.
4.24.9 National Control closes breakers at both ends through the network supervisory system and
requests auto-reclose to be switched ON.
NOTE Authorized person shall remain on site to verify all remote switching.
4.25.1 The procedure in 4.25.2 to 4.25.11 shall be followed when a transformer panel is taken out
of service for maintenance. If the HV busbar links are connected to an IPS busbar, sanction from
National Control shall be obtained before the transformer panel can be isolated.
4.25.11 Open tertiary or auxiliary transformer isolator (where applicable) (specify voltage).
4.26.1 In the case of work on transformers and breakers, and on the busbar side of the primary
and secondary breakers, the primary, secondary and tertiary windings of the transformer shall be
as specified in NRS 040-3 (specify voltages).
4.26.2 In the case of work on transformers only, earth the primary, secondary and tertiary sides of
the transformer (specify voltages).
4.26.3 In the case of work on a breaker only, earth the busbar and transformer sides of the
breaker (specify voltage).
4.26.5 Fully isolate the panel and earth only the apparatus to be worked on. The handout shall be
for that apparatus only.
4.27.1 The procedure in 4.27.2 to 4.27.13 shall be followed when a transformer panel is returned
to service after maintenance.
4.27.2 The authorized person hands back the panel to the control centre office clear of workmen
and equipment and fit for service.
4.27.3 If the primary busbar links are connected to an IPS busbar, sanction shall be obtained from
National Control before the IPS line can be linked up.
4.27.6 Close tertiary or auxiliary transformer isolator (where applicable) (specify voltage).
4.29 Taking a bus coupler breaker or bus section breaker out of service
NOTE Some stations have automatic overcurrent and earth-fault protection schemes.
4.29.1 When changing over busbars from one to the other, start from one end of the busbar,
proceed down the busbar closing all necessary isolators and thereafter proceed up the parallel
busbar opening all necessary isolators.
4.29.2 When changing over busbars without a bus coupler, the dead busbar shall be proved
healthy by means of a line or transformer breaker where possible.
4.29.3 The method of closing and opening each panel in turn is only used in special
circumstances where the possibility of paralleling two zones through isolators exists. This method
shall not be used where a bus coupler is not available.
4.29.4 On the bus coupler breaker, make sure that it is off overcurrent and earth-fault protection
(where applicable). Then follow the steps in (a) to (h):
a) link over all the relevant panels from one busbar to the other;
b) apply on earth busbar 2 on the bus coupler side of the breaker; and
c) apply earth on the bus section breaker, earth both sides of the bus section breaker.
4.30 Returning a bus coupler breaker or bus section breaker back to service
NOTE Some stations have automatic overcurrent and earth-fault protection schemes.
4.30.1 The procedure in 4.30.2 to 4.30.5 shall be followed when returning a bus coupler breaker or
bus section breaker back to service.
h) switch ON supervisory.
b) close relevant busbar isolators of the bus section breaker (specify voltage);
4.30.6.2 With the bus coupler or the bus section breaker closed and with overcurrent and earth-
fault protection switched off, complete steps 4.30.6.3 to 4.30.6.9.
4.30.6.3 Link over the required panels to clear the busbar or section.
4.30.6.4 Check that bus coupler or bus section breaker carry no load.
4.30.6.8 Apply earths on the busbar or section of busbar according to NRS 040-3.
Owing to different technologies and busbar configurations, all operating on unique plant shall be in
accordance with local operating procedure.
17 NRS 040-5:2007
4.31.1 After the apparatus has been earthed in accordance with NRS 040-3, it shall be handed
over to the authorized person. The authorized person shall be responsible for safety testing and for
the application and removal of working earths when and where necessary on lines only.
The authorized person shall write out the hand over or hand back on an operating instruction form
together with the time handed over and time handed back on completion of work. All normal open
points that are excluded should, where applicable, be recorded as part of the hand over.
4.31.2 After a line has been opened, isolated and earthed in accordance with NRS 040-3 between
two control centres, an intercontrol hand over shall take place. In other words the control centres
shall hand over the line to each other for safety purposes irrespective of whether the control centre
has work to be done. This is also applicable when working with customers that have recognized
control centres.
4.32.1 The intercontrol hand over shall be recorded in both network management centres'
operating logs.
4.32.2 The operating diagrams shall be dressed with the appropriate hand-over labels (i.e. inter-
control or the authorized persons name).
4.32.3 The symbols used for dressing the operating diagram shall depend on local requirements.
When lines have been handed out between control centres (i.e. intercontrol hand over) the lines
shall only be handed back when they are ready to be made live and not when work has been
completed, i.e. all authorized persons have to hand back first.