BILL OF MATERIALS AND COST ESTIMATES

ITEM WORK DESCRIPTION QUANTITY UNIT UNIT COST AMOUNT

I. EXCAVATION
Earthwork 24 cu.m. 200.00 PHP 4,800.00
Earth fill 16 cu.m. 100.00 1,600.00
Gravel Fill (Mixed) 12 cu.m. 200.00 2,400.00
Sand Fill 8 cu.m. 250.00 2,000.00
PHP 10,800.00
II. CONCRETE AND MASONRY
Cement 500 bags 240.00 PHP 120,000.00
Gravel 22 cu.m. 300.00 6,600.00
Fine Sand (S-1) 54 cu.m. 250.00 13,500.00
5" Concrete Hollow Block 1800 pcs. 9.00 16,200.00
4" Concrete Hollow Block 1500 pcs. 8.00 12,000.00
PHP 168,300.00
III. REINFORCING STEEL BARS
16mm x 6m RSB 140 pcs. 310.00 PHP 43,400.00
12mm x 6m RSB 90 pcs. 175.00 15,750.00
10mm x 6m RSB 400 pcs. 125.00 50,000.00
#16 G.I Tie Wire 2 rolls 1650.00 3,300.00
PHP 112,450.00
IV. FORMWORKS SCAFFOLDINGS
2" x 3" x 12' (900 Bd. Ft.) 150 pcs. 40.00 PHP 36,000.00
2" x 2" x 12' (400 Bd. Ft.) 150 pcs. 40.00 16,000.00
x 4' x 8' Ordinary Plywood 30 pcs. 380.00 11,400.00
4" - 3" - 2" - 1" Assorted C.W. Nail 20 kls. 60.00 1,800.00
PHP 65,200.00
V. STEEL TRUSSES
3/16 x 2" x 6m Angle Bar 34 pcs. 470.00 PHP 15,980.00
3/16" x 1 " x 6m Angle Bar 16 pcs. 365.00 5,840.00
2" x 3" x 6m Cee Purlins 46 pcs. 340.00 15,640.00
3/16" x 1 " x 6m Flat Bar 16 pcs. 260.00 4,160.00
Welding Rod 10 kls. 70.00 700.00
Blind Rivets 1 box 500.00 500.00
1" x 2" x 10' Fascia Board 14 pcs. 650.00 9,100.00
PHP 51,920.00
VI. ROOFING
Roof Panels and Bending
Accessories (Lumpsum) 92000.00 PHP 92,000.00
BILL OF MATERIALS AND COST ESTIMATES

VII. STEEL WINDOWS


Steel Casement 15.88 sq.m. 3000.00 PHP 47,640.00

VIII. CEILING JOIST AND BOARDS


2 x 2 x 12' (480 Bd. Ft.) 120 pcs. 40.00 PHP 57,600.00
' x 4' x 8' Marine Plywood 28 pcs. 400.00 11,200.00
' x 4' x 8' Hardiflex 16 pcs. 400.00 6,400.00
3" - 2" - 1" Assorted C.W. Nail 10 kls. 60.00 600.00
Wooden Preservatives 2 gals. 600.00 1,200.00
PHP 77,000.00
IX. CABINETRY
Dresser, Kit Nook and Cabinet 24 pcs. 1150.00 PHP 27,600.00
" x 4' x 8' Plyboard 40 pairs 60.00 2,400.00
Concealed Hinges 2 gals. 400.00 800.00
Stikwel 20 pcs. 280.00 5,600.00
Comice Design (1 x 3" x 10') 4 kls. 80.00 320.00
2" - 1 1/2" Finishing Nail PHP 36,720.00

X. DOOR JAMB AND DOOR PANEL


1.00 x 2.10m 1 set 8000.00 PHP 8,000.00
0.80m x 2.10m 4 sets 6000.00 24,000.00
0.60m x 2.10m 2 sets 3500.00 7,000.00
PHP 39,000.00
XI. TILES
Floor Tiles (.60m x .60m) 270 pcs. 190.00 PHP 51,300.00
Wall Tiles (.30m x .60m) 122 pcs. 112.00 13,664.00
Kitchen Counter (Granite) 3 pcs. 1500.00 4,500.00
Tile Groute 4 kls. 75.00 300.00
PHP 69,764.00
XII. PLUMBING MATERIALS
Sanitary Fixtures and
Cold Water Line (Lumpsum) PHP 18,000.00

XIII. ELECTRICAL MATERIALS


Lumpsum PHP 65,000.00

XIV. PAINTING MATERIALS


Lumpsum PHP 50,000.00
BILL OF MATERIALS AND COST ESTIMATES

XV. FINISHING FIXTURES


Lumpsum PHP 40,000.00

XVI. MISCELLANEOUS PHP 15,000.00