Sei sulla pagina 1di 22

Design, Construction,

Commission, and
Qualification of Critical
Utility Systems
Part I: Overview
B Y D AV I D W. V I N C E N T A N D H E R B E RT M AT H E S O N


INTRODUCTION
ties, this article will only cover general procedures used to
Overview of Critical Utility Systems bring these systems to a validated state and, once they are
The use of critical utility systems in the pharmaceutical validated, to establish a routine environmental program. The
industry is very important to final product quality. That is Routine Environmental Monitoring (REM) program is de-
why the design, construction, commissioning, qualification, signed to ensure that the validation lifecycle is maintained
and routine monitoring of these systems is important in en- for these systems. The REM program also ensures that the
ssuring that the end product will maintain a reproducible systems are capable of maintaining the same quality output
quality. Critical utility systems can be considered the back- throughout the life of the system.
bone of any production facility and should be the first sys- This article will not describe the detailed procedures
tems to be validated. Without properly functioning utilities, needed to validate these systems. It is impractical to discuss
the quality of any product will be open to question. all the existing methods and procedures used to validate
Critical utilities found in pharmaceutical, medical device, utility systems within the scope of this article. However, this
and biotechnology production facilities usually support var- article will discuss an approach to integrate the commis-
ious equipment and processes. These utilities must meet both sioning and qualification phases of the project in order to
quantitative and qualitative specifications in order to be con- streamline the qualification phase while verifying that the
sidered satisfactory. The actual criteria may vary from one critical utilities meet their pre-determined design features.
utility system to another and may even be influenced by the The critical utilities that will be addressed in the article
particular equipment being supported. The design, construc- are as follows:
tion, commissioning, qualification, and monitoring of each 1. Water systems
utility will vary depending on the system. Therefore, it is im- 2. Clean steam system
portant to follow a logical, comprehensive scheme when at- 3. Heating Ventilation and Air Conditioning (HVAC)
tempting to validate or monitor these systems. systems
This article will discuss the various phases of design, 4. Process gases
construction, commissioning, qualification, and the routine This article is the first of three-parts. Part I is an
monitoring of various critical utility systems. While it takes overview of critical utility systems and the planning needed
a great deal of time and effort to qualify most critical utili- before specific utilities may be addressed.

236 Journal of Validation Technology


David W. Vincent and Herbert Matheson

User Requirement Specifications to ensure and record that system design meets user require-
ments.
The development of User Requirement Specifications One of the first steps that should be considered is defin-
(URS) is one of the most critical elements in the compliance ing which areas are to be qualified and what their intended
documentation process. A successful project is dependent uses will be. A facility room classification or design speci-
on clear definition, communication, the understanding of fication should be based on the product being manufactured
project scope and objectives, as well as other stakeholder and the processes being used. It is important that the Archi-
requirements as defined by them and the end user. At the tecture and Engineering (A/E) team who are creating the
outset of the project, after the front end conceptual study has design and layout are aware of those areas.
been completed, the user must specify the requirements for
individual aspects of the utility systems in terms of function, The reasons for this are as follows:1
throughput, operation, and applicable regulatory require- To define exactly those areas for which qualifica-
ments to the engineering service provider. This enables the tion data must be developed.
development and assessment of specific engineering op- To prevent any misunderstanding, either by the
tions. These requirements are normally formalized in a de- owner or the Food and Drug Administration
tailed URS document. (FDA), as to what areas will be subject to qualifi-
The URS describes critical installation and operating pa- cation. During a pre-construction review of the
rameters. It includes performance standards that are re- drawings with the FDA, the list of areas that were
quired for the intended use of the equipment and provides specified should be discussed. Then, if there are
the basis for the qualification and maintenance of equip- any differences of opinion between the owner and
ment. The URS should be prepared by the equipment owner the FDA, they can be resolved before construction
in collaboration with representatives from departments that starts. It should also be added that drawings are re-
will participate in qualifying and maintaining the equip- quired of the entire facility noting production fea-
ment, and from departments that will be affected by the op- tures and functions. If the A/E firm knows ahead of
eration of that equipment. time that as-built drawings are required, the field
people who are responsible for monitoring the con-
Design Specifications and the struction activities will make the changes to the
Design Review Phase drawings as the actual changes are being made in
the field. This is the way to be assured that as-built
Design specifications for each system are established drawings will truly be as builts, instead of I
based on engineering and manufacturing provisions, as well think-builts.
as input from various organizations and departments. Design
specifications are the foundation for the development of the Good Manufacturing Practices (GMPs) call for the fol-
qualification document acceptance criteria. It is necessary to lowing pertaining to layouts:
track compliance with specifications throughout the valida- Smooth flow of personnel and product
tion project. In the end, validation activities will demonstrate Adequate space to perform each operation
that the design intent has been achieved through the proper Spatial separation, where appropriate, to prevent
tracking and control of design specifications. product mix-ups, component mix-ups, etc.
A formal design review process at the beginning of the Adequate lighting
project will decrease the number of deviations associated Environmental controls
with improper control of design specifications during the
execution of Installation and Operational Qualification The design and construction of any facility requires a
(I/OQ) protocols. A design review process compares the de- team effort. The Design Qualification (DQ) phase of the
sign of equipment and systems with the applicable user and project requires the assistance of various departments and
process requirements as defined in the current URS, pro- professionals such as Quality Control (QC) and Quality As-
cessing requirements, product specifications, license com- surance (QA), Regulatory Affairs (RA), Facilities/Engineer-
mitments, manufacturing records, and applicable Standard ing, Validation, Manufacturing, as well as the general con-
Operating Procedures (SOP). The design review is intended tractor and sub-contractors.

M a y 2 0 0 5 Vo l u m e 11 , N u m b e r 3 237
David W. Vincent and Herbert Matheson

System Level Impact Assessment


A simplified approach can be summarized as follows:
Determine facility design task force (QA, QC, En- System impact assessments are performed to differenti-
gineering, Manufacturing, Validation, etc.) ate those systems that have a direct impact on product qual-
Determine process environment requirements ity from those having indirect or no impact on product qual-
Determine operation requirements, including per- ity. The system impact assessments are preliminary until the
sonnel flow and material and waste flows completion of subsequent component impact assessments
Quantify production, process, and equipment space for each of the systems. The results of the component im-
requirements pact assessments could change the results of the system im-
Develop conceptual layout pact assessments, which is why the initial system impact as-
Approve final facility layout sessment should be considered preliminary.
Develop detail system engineering The advantage of performing system impact assess-
Prepare designs and specifications ments is that only direct impact systems require qualifica-
Obtain acceptance of the design review team tion. Indirect impact and no impact systems are subject to
Prepare bidding documents less stringent test and inspection procedures based on busi-
Determine bidding and acceptance process ness risk and typical Good Engineering Practices (GEPs). A
Determine construction start date number of utility systems that were commonly qualified in
the past, such as plant steam, chill water, industrial cold
It is important to remember that the products and manu- water, and heating hot water, are typically no longer quali-
facturing processes usually determine the design and layout fied based on the results of system impact assessments.
of the facility. It is also important to arrange a pre-construc-
tion meeting with the FDA. This meeting can decrease the The following summarizes the system impact assess-
effort expended in justifying the design after the fact. By de- ment process:
veloping a formalized and well-documented design review Identification of the system and system number:
process, the critical component, design specification, and pa- This information is typically obtained from the
rameters can be referenced in the validation protocols, project Process and Instrumentation Diagrams
thereby decreasing and streamlining the amount of informa- (P&IDs). Complete the system description with a
tion that requires verification in the qualification protocols. general narrative of the system and its major com-
ponents, design, operation, functional capabilities,
Impact Assessments and critical functions.
System Boundary Definition: Identifying the
Impact assessments are a formal process used to identify boundaries and scope of the system is typically
systems and the components of those systems that have a di- done using the system P&IDs as well as other
rect impact on product quality. Direct impact systems are drawings and specifications, as appropriate. The
expected to have an impact on the product quality, whereas easiest and clearest way to accomplish this is to
an indirect impact system is not expected to have an im- mark the system P&IDs to identify the system
pact on the product quality. Both systems require commis- boundaries and all components of the system in-
sioning; however, the direct impact system will be subject to cluded within those bounds. Specify system
qualification practices to meet the additional regulatory re- boundaries by inserting a horizontal or vertical line
quirements of the FDA and other regulatory authorities. The at the boundary. These lines should be placed to
impact assessment process decreases the scope of IQ/OQ clearly identify whether or not the adjacent compo-
protocols by allowing the validation activities to focus on nent is part of the system.
those systems and components that have been identified as
having a direct impact on product quality, rather than all sys-
tems and components within those processes.
Impact assessments should be performed on two levels:
the system level and the component level.

238 Journal of Validation Technology


David W. Vincent and Herbert Matheson

Figure 1
______________________________________________________________________________
Impact Assessment Questions

Challenge Yes No

1. Does the system have direct contact with the product (e.g. air quality) or
direct contact with a product contact surface [e.g.: Clean in Place (CIP)
solution]?
2. Does the system provide an excipient, or produce an ingredient or solvent
[e.g.: Water For Injection (WFI)]?
3. Is the system used in cleaning, sanitizing, or sterilizing (e.g.: clean steam)?
4. Does the system preserve product status (e.g.: nitrogen purge for oxygen
sensitive products)?
5. Does the system produce data that is used to accept or reject product (e.g.:
electronic batch record system, critical process parameter chart recorder, or
release laboratory instrument)?
6. Is the system a process control system (e.g., PLC, DCS) or does it contain a
process control system that may affect the product quality and there is no
system for independent verification of control system performance in place?
7. Is the system expected to not have a direct impact on product quality, but
supports a direct impact system?

To help in establishing a system boundary, utilize the System Classification


following general guidelines (there may be exceptions to
these guidelines): The system is classified as direct impact, indirect im-
pact, or no impact as follows:
If the component number of a valve, etc., is la- If the response to any of challenges one through six
beled as part of the main system being assessed, in Figure 1 is Yes, then the system shall be clas-
then it generally will be part of that system. sified as a direct impact system.
The control system I/O for a given system will If the response to challenges one through six is
become part of that system. No, but the response to challenge seven is Yes,
Disposable, flexible piping connectors, portable the system shall be classified as an indirect im-
tanks, etc., should not be highlighted as part of pact system.
the system and should be noted either on the If the response to challenges one through seven is
drawing or in the comments section of the form No, the system shall be classified as a no im-
so it is clear that not highlighting them was in- pact system.
tentional. Based on the above criteria, the hypothetical nitrogen
system would be classified as direct impact because it has
System Impact Assessment: Once the system has direct product contact. Document the reasons for this clas-
been identified and the system boundaries defined, sification with a brief explanation to ensure the understand-
the impact of the system may be determined. The ing of future reviewers and approvers.
impact of the system is determined by answering a
series of seven questions about the system. In Figure
1, the Impact Assessment Questions show how the
assessment could be completed for the example of a
hypothetical nitrogen gas system.

M a y 2 0 0 5 Vo l u m e 11 , N u m b e r 3 239
David W. Vincent and Herbert Matheson

Component Criticality Assessments System Classification


After system impact assessments have been completed, A positive answer to any questions in Figure 2
component criticality assessments are performed to identify identifies the component as a critical component
those components within a system that have direct, indirect that should be verified during IQ and OQ testing.
or no impact on product quality. The results of the compo- When answers to all the questions in Figure 2 are
nent criticality assessments have a direct bearing on the val- in the negative, the component is thereby identified
idation of the system, in that IQ and OQ testing of the sys- as a non-critical component of the system that does
tem can be focused on those components identified as hav- not require verification during IQ and OQ testing.
ing a direct impact on product quality.
Volume 5, Commissioning and Qualification, of the Component Approval
International Society for Pharmaceutical Engineering
(ISPE) Pharmaceutical Engineering Guides for New and The construction contractors translate the project speci-
Renovated Facilities recommends that components within fications and design documents created by the A/E team
direct impact, indirect impact, and in some cases, no impact into a completed facility. The project specifications created
systems, should be assessed for criticality. This is suggested by the A/E team are typically detailed and often specify a
to ensure that systems previously judged to have indirect or component to a specific manufacturer and model, allowing
no impact in the early, high level assessment, have not sub- the use of an approved equal. The construction contrac-
sequently acquired a critical function as the detailed design tors are required to submit to the A/E team technical data on
has progressed to conclusion. the components that they intend to use during the construc-
The component criticality assessment process requires tion of the facility so that the A/E team can approve the pro-
the detailed review of the system P&IDs and system instru- posed components.
ment lists. Like the system impact assessment, the compo- Due to a number of legitimate reasons, including cost
nent criticality assessment is performed by answering a se- and availability, the components that contractors submit for
ries of questions about each of the system components. The use often do not match all the detailed specifications created
questions proposed by the ISPE Commissioning and Qual- by the A/E team. The A/E team reviews the technical data
ification Guideline are as follows below in Figure 2. provided by the contractor to determine whether the pro-
posed components are acceptable for use. Oftentimes, the

Figure 2
______________________________________________________________________________
Component Criticality Assessment Questions

Challenge Yes No

1. Is the component used to demonstrate compliance with the registered


process?
2. Does the normal operation or control of the component have a direct effect
on product quality?
3. Will the failure or alarm of the component have a direct effect on product
quality or efficacy?
4. Is information from this component recorded as part of the batch record, lot
release data, or other GMP-related documentation?
5. Does the component have direct contact with the product or product compo-
nents?
6. Are the component controls critical process elements that may affect product
quality without independent verification of the control system performance?
7. Is the component used to create or preserve a critical status of a system?

240 Journal of Validation Technology


David W. Vincent and Herbert Matheson

A/E team determines that a component is acceptable even Attach supporting vendor technical literature to the
though it does not exactly match all of the project specifica- submittal review form.
tions; they indicate approval with a stamp on the submittal. Appropriate representatives of the building owner
should check the submittal review package. These
In the real world, gaps in the submittal process are com- representatives typically should include the system
mon, such as in the following situations: owner along with Facilities, Engineering, and Qual-
Contractors often submit generic product data ity Assurance personnel. The acceptability of a com-
sheets that do not adequately specify the compo- ponent is determined based on its intended use and
nent that will be installed. In example, a generic its compliance with project specifications. The dis-
valve data sheet may identify the options available position of a component is identified typically as
for materials and finishes, but may not identify ACCEPTED, ACCEPTED WITH COMMENTS, or
which of these options the contractor will select. REJECTED. The reviewers then approve the form.
The submittal process is often slow and may not be
completed for all components before the compo- This process ensures that there is an approved submittal
nents are installed in the facility. package for each of the critical components identified dur-
Submittals are often stamped as approved by the ing the component criticality review.
A/E but not by a designated representative of the
client for whom the facility is being constructed. Note: The IQ protocols can be simplified, be-
cause the IQ need only verify that the in-
Submittal Review stalled critical components match the ap-
proved submittals by manufacturer and
A review and approval of the submittals by the building model numbers. This is allowed because the
owner is a useful process to resolve these discrepancies and critical attributes of the components have al-
to improve the efficiency of the IQ process. A submittal re- ready been approved through the submittal
view should be completed for each of the critical compo- review process.
nents identified by the component criticality assessment.
The submittal review process proceeds as follows: Systematic Risk Assessment for System
Identify the critical component by description and Qualifications
tag number as appropriate.
Identify the system that contains the component. The Risk Assessment section discusses the potential im-
Identify the specification number that applies to the pact on current Good Manufacturing Practice (cGMP) op-
critical component. erations associated with the use of the equipment, and the
Identify the submittal number that applies to the steps that will be taken to reduce those risks. Identify con-
critical component. ditions that could lead to failure of the equipment and the ef-
In a Specified Attribute column, list the critical fects of failure on cGMP operations. Evaluate the degree of
attributes of the component as indicated in the ap- risk to product quality, company operations, and the safety
plicable specification, such as manufacturer, model of personnel and equipment.
number, materials of construction, capacity, etc. During the risk assessment, it is important to perform an
In an Actual Attribute column, enter the existent impact assessment on the system. An impact assessment is
component information for each of the critical at- the process by which the effects of the system - and the crit-
tributes as determined by the component vendor. ical components within those systems - on product quality
are evaluated. System risk assessment is measured in a min-
Note: It is especially important to identify imum of three categories: direct product impact, indirect
where the component varies from the speci- product impact, and no direct product impact. By perform-
fied attribute in order for reviewers to make ing design impact assessments, companies can reduce the
an informed decision as to the acceptability scope of the systems and the components subject to qualifi-
of the component. cation, and allow appropriate focus to be placed on the com-
ponents that may present a potential risk to the product.

M a y 2 0 0 5 Vo l u m e 11 , N u m b e r 3 241
David W. Vincent and Herbert Matheson

Risk Assessment Example

The elements in Figures 3 and 4 indicate one example of how applying risk assessment to a validatable
system can be beneficial in developing a scientific rationale and justification for the selection of the differ-
ent types of qualification needed to support a system.

Figure 3
______________________________________________________________________________
Impact Analysis

Summarize risks and associated controls in an impact and complexity analysis. Rate the impact of the
equipment on product quality, safety, and purity, and on the safety of personnel and equipment. Evaluate
the systems in place to control those risks.

A. Quality Impact Score


No impact: Equipment will not be directly or indirectly associated with cGMP activity. 0
Minimal impact: Equipment indirectly affects cGMP processes or procedures. (Non-direct
1
product impact)
Potential Impact: Equipment performs or directly supports a cGMP process or procedure; 2
failure could potentially affect product quality. Equipment failure could negatively impact
operational efficiency or costs. (Indirect product impact)
Direct Impact: Equipment is an essential component of a cGMP process or procedure, or 3
is in direct contact with the drug substance or product. Equipment failure could result in
loss of product; safety hazard; damage to materials, equipment, or facility; or negative in-
spection findings. (Direct product impact)
B. Quality Risk Management Score
No risk control necessary. 0
Failure of the equipment would be detected immediately and be corrected before affecting
a cGMP process or procedure. 1
Failure could not go undetected. Systems and procedures are in place to detect negative
2
impact on product quality safety or purity before significant loss of productivity.
Failure could potentially go undetected and cause failure of other processes or procedures. 3

242 Journal of Validation Technology


David W. Vincent and Herbert Matheson

Figure 4
______________________________________________________________________________
Complexity Analysis

Describe the technological risks and controls associated with the equipment. The complexity analysis
evaluates the risk of failure due to technical sophistication of the equipment, and the relative difficulty of
maintaining the equipment in a state of control.

C. Technology Risk Score


Very simple system; minimal chance of failure. 0
Commonly understood technology, rugged equipment; low probability of failure. 1
Somewhat complex equipment, generally reliable technology, components, and controls. 2
Highly complex or sensitive equipment, sophisticated technology, unique components,
3
or processes.
D. Technology Risk Management Score
Control and repair possible without impacting cGMP activities. 0
Equipment requires that minimal training, simple maintenance procedures; backup, repair, 1
or like-for-like replacement is readily available.
Requires trained operators and maintenance technicians. Backup systems, repair, 2
maintenance, and replacement are readily available.
Operators and maintenance technicians must be highly trained. Maintenance, repair, or 3
replacement requires specialized or time-consuming effort; backup systems, repair,
maintenance, or replacement are not readily available.

Risk Score

The calculation used to evaluate the overall risk (as seen in Figure 4) of the equipment combines the individ-
ual impact and complexity scores in the following formula:

(A + B) x (C + D)

Where: A = Quality Impact


B = Quality Risk Management
C = Technology Risk
D = Technology Risk Management

M a y 2 0 0 5 Vo l u m e 11 , N u m b e r 3 243
David W. Vincent and Herbert Matheson

Validation Requirements

Identify the qualification requirement for the equipment based on the impact and complexity analysis as
shown in Figure 5. For smaller, less complex system qualification, protocols can be combined into I/OQ or
IQ/OQ and Procedure Qualification (PQ) protocols. Any additional information to support and justify the valida-
tion requirements should be included.

Figure 5
______________________________________________________________________________
Qualification and Validation Justification

Risk Score Qualification Requirements Validation Maintenance Requirements

Document installation Documentation maintained by


0 and commissioning users or Facilities Department.
Installation, commissioning,
1 to 3 IQ maintenance, and change control
documentation maintained by
QA.
Operate, maintain, and calibrate
according to written SOPs.
Document preventive and
4 to 6 IQ/OQ corrective maintenance and
calibration according to SOPs.
Apply change control procedures
according to SOPs and change
control programs.
Perform operation, maintenance,
calibration, and performance
verification tasks according to
7 IQ/OQ/PQ written procedures.
Document preventive and
corrective maintenance and
calibration according to SOPs.
Apply change control procedures
according to SOPs and change
control programs.

244 Journal of Validation Technology


David W. Vincent and Herbert Matheson

Construction Qualification (CQ) Activities


The SOPs necessary to support these requirements must
The construction of a pharmaceutical manufacturing fa- be reviewed and approved by the appropriate contractor and
cility requires strict adherence to the requirements outlined the QA Department owner. The following is a partial list of
in the Code of Federal Regulations (CFR), title 21, section typical SOPs necessary to support the integration of con-
211.42 of the cGMPs2 for processing human drugs and struction activities into the qualification process:
newly proposed regulatory requirements. A great deal of Contractor training
emphasis is placed on design compliance with cGMP re- Good Documentation Practices
quirements, but the effects of construction issues on cGMP Equipment and component receipt verification
compliance are profound and must be understood by own- Red line drawing control
ers, facility operators, and contractors. Air duct cleaning and inspection
Integration of construction and qualification activities is Air duct leakage testing
critical to a successful validation project. Document pro- HEPA filter installation
curement and the verification and documentation of con- HEPA filter leak testing
struction activities are critical to supporting Installation Boroscope inspection procedures
Qualification (IQ). Slope verification procedures
The proper integration of qualification and construction, Weld inspection procedures
commissioning, and startup activities will: Weld log procedure
Accelerate the start-up effort. Welder qualification procedures
Produce superior documentation. Piping system walk down procedures
Reduce time to completion of subsequent IQ Hydrostatic pressure testing
and OQ activities. Pneumatic pressure testing
Ensure that product is produced in a GMP- Cleaning and passivation
compliant facility. Clean build protocol

Critical Systems Coordinator and Team Members


The following are common critical systems that should Depending upon the project size, a CQ coordinator and
be inspected during the CQ phase: CQ team with engineering and construction background,
Cleanroom HVAC should be assigned to monitor and document the construc-
Purified Water (WP) system tion activities necessary to support the qualification process.
Water For Injection (WFI) system A CQ coordinator is most successful in the role when he or
Computerized systems she reports directly to the client or is a representative of the
Product contact compressed gases client. This direct reporting relationship will eliminate the
Clean-in-Place (CIP) systems conflict of interest that would derive from the coordinator
Product Piping systems being part of the construction company.
Architectural finishes
The Construction Qualification Team is tasked to per-
Documentation form the following duties:
In order to utilize tests and inspections performed during Work closely with the general contractor and me-
the construction phase of the project, it is necessary that the chanical contractors, to procure, verify, and organ-
tests be performed and documented in compliance with ize documentation for the Turn Over Packages
cGMP requirements, including: (TOPs) for direct and indirect impact systems as
The tests and inspections must be performed per part of Good Engineering Practices:
written and approved procedures.
The personnel performing and documenting the Project specifications
tests and inspections have been trained in the test Vendor or manufacturer submittals
procedures, and that training has been documented. Manufacturer mechanical specifications
The test results have been documented using Good Purchase orders
Documentation Practices (GDP). Vendor test reports

M a y 2 0 0 5 Vo l u m e 11 , N u m b e r 3 245
David W. Vincent and Herbert Matheson

Material certifications Audit the construction site for cleanliness and com-
Calibration data pliance with specified construction sequences, prac-
State and local code compliance tices, and craftsmanship standards. Enter observa-
ASME, ANSI, and other certifications tions into a Construction Site Audit Log.
Pipe specifications Document and report any problems that may affect
Cleaning and passivation reports the construction schedule or have a negative impact
Stainless steel weld documentation on the qualification phase of the project.
Instrumentation specifications
Drawings Specific Documentation Packages Format
Material and finish verification
MSDS Items listed in the previous sections are included in the
Any other useful documentation CQ packages according to the following guidelines:

Monitor the construction schedule as it relates to CQ Summary Sheet


validation activities to ensure that the required tests The CQ Summary Sheet, placed before the CQ
and inspections are documented. packages defined here, will briefly describe CQ
Verify during component receipt inspection that the findings. Specific items for discussion should in-
actual components delivered to the jobsite match clude identification of construction and installation
the components approved for use during the sub- contractor(s), start and completion dates, historical
mittal review process. This requirement applies to overview of CQ effort, and a description of CQ
the components identified as being critical during documentation. Both the CQ coordinator and proj-
the component criticality assessments. ect manager, serving as approval for the entire CQ
Witness tests and inspections performed during the package, will approve the CQ Summary Sheet.
construction process necessary to support the qual-
ification of the critical utility systems. The tests and CQ Section Index
inspections should be witnessed to assure that the The CQ Section Index shall list all major CQ sec-
procedures are performed according to specifica- tions.
tions and should be fully documented.

Figure 6
______________________________________________________________________________
Tests Required for Two Common Critical Utility Systems

System Test or Inspection


HVAC Critical component receipt inspection
Air duct cleaning and inspection
Air duct leakage testing
HEPA filter installation
HEPA filter leak testing
Drawing verification
WFI Critical component receipt inspection
Weld documentation and inspection
Hydrostatic pressure testing
Slope verification procedures
Drawing verification
Cleaning and passivation

246 Journal of Validation Technology


David W. Vincent and Herbert Matheson

Project Specifications Figure 7


_____________________________________
Project specifications are provided by the archi- Table of Contents Example for a Typical CQ
tect(s) of the project and serve as guidelines for con- Package
struction. Only those project specification sections
applicable to the CQ system should be included.
Section 1 - General
Purchase Orders 1. DESIGN SPECIFICATIONS
All available purchase orders for equipment and 2. PURCHASE ORDERS
materials within the system will be included. Each
individual purchase order will be included in a sep- Section 2 - Equipment
arate subsection. Dollar amounts may be removed. 3. EQUIPMENT DATA SHEETS
4. EQUIPMENT CHECKLIST
Purchase Specification 5. SPARE PARTS LIST
The Purchase Specifications section will immedi- 6. VENDOR TEST REPORTS
ately follow "Purchase Orders." Purchase specifica- 7. VENDOR CERTIFICATION
tions should include documentation provided from ASME
the vendors, contractors, and manufacturers. ANSI
MATERIAL CERTIFICATIONS
Purchase specifications should serve as succeeding 8. OPERATION AND MAINTENANCE
documentation for the Installation Qualification (IQ) MANUALS
protocol of the CQ system. In addition, those areas 9. DRAWINGS
of the purchase specification giving direct evidence
to IQ requirements should be highlighted, using a Section 3 - Piping and Duct
single color. 10. SPECIFICATION LIST/INDEX
11. MATERIAL CERTIFICATIONS
Test Reports 12. WELD DOCUMENT
The Test Reports section will immediately follow WELDER QUALIFICATIONS
Purchase Specifications. Test reports include docu- WELD LOG
ments such as pressure test reports, factory test re- WELD INSPECTIONS
ports, and certifications. Test reports included in CQ WELD AUDIT
packages should depict the static attributes of the 13. HYDROSTATIC TEST REPORTS
system, not operational testing. Wherever practical, 14. CLEANING REPORTS
the CQ coordinator or validation team member 15. PASSIVATION REPORTS
should witness tests. 16. LINE SLOPE VERIFICATION
17. VALVE LABEL VERIFICATION
Drawings 18. LINE LABEL VERFICATION
The Drawings section will be the final section of the 19. TAG INSPECTION
CQ package. Drawings will be classified as either 20. LINE SUPPORT
reference or as built. Reference drawings should be
reviewed and signed by at least one person, while Section 4 - Drawings
as-built drawings should be reviewed and signed 21. PIPING AND INSTRUMENTATION
(and red lined, if necessary) by at least one person. DIAGRAMS
(It is desirable to have two reviewers for as-built 22. ISOMETRIC
drawings.) 23. RED-LINED DRAWINGS

Additional Sections
Any additional sections will be included in the CQ
between the Test Reports and the Drawings sections.

M a y 2 0 0 5 Vo l u m e 11 , N u m b e r 3 247
David W. Vincent and Herbert Matheson

Review Note: There is no clear demarcation between


Once each document is received and verified, it the construction qualification and commis-
should be stamped "CONSTRUCTION QUALIFI- sioning phases of the project. CQ and com-
CATION Reviewed by" the CQ coordinator with missioning activities will often take place
signature and date. concurrently. As in the CQ phase, tests and
inspections performed during the commis-
CQ Section Index sioning phase of the project must be per-
The CQ Section Index listing all major CQ sections formed and documented in compliance with
should be included immediately following the CQ written and approved SOPs.
Summary Sheet.
Aspects of Commissioning
Commissioning and Startup
Commissioning activities should encompass all aspects
The ISPE Baseline Guide, Volume 5, defines commis- of the completion phase of any facility built. Some of the
sioning as: key aspects include:

"A well planned, documented, and managed Organizing and planning


engineering approach to the start-up and Factory testing
turnover of facilities, systems, and equipment Static testing (pre-commissioning)
to the end-user that results in a safe and Operator training
functional environment that meets estab- Walk down and tagging
lished design requirements and stakeholder Startup reports
expectations." Full functional testing
Turnover and punch lists
The commissioning phase of the project, which typi- As-built documentation
cally occurs after mechanical completion of the system and System and equipment manuals
prior to turnover of the system to the owner, is another op- Spare parts management
portunity to integrate qualification activities into the facility IQ documentation (as applicable)
construction, commissioning, and start-up process. While OQ documentation (as applicable)
the qualification activities during the construction phase of
the project primarily support IQ, qualification activities dur- Commissioning Team
ing the commissioning and start-up phase will primarily
support Operational Qualification (OQ). Every project team needs a leader who is empowered by
Pharmaceutical manufacturing facilities, laboratories, the company to manage the project from start to finish, from
and even office buildings demand a complete program of inception to completion. "Completion" should be defined as
start-up, functional challenge, training, documentation, and a time when the appropriate signatures on all punch lists,
turnover. It is incumbent upon the individuals responsible commissioning documents, as-built drawings, validation
for design and construction to finish the job by handing over protocols, and SOPs are attained. The project leader or proj-
a completely operable and documented facility so that vali- ect manager should not leave the project until the "ink is dry"
dation activities can follow with minimal problems. Too on each of those documents. Organizing and planning for
often, an owner's project manager will move on to his or her commissioning are the keys to a successful project. Each of
next big project before the whole job is finished, leaving the project members should report to one individual, who
maintenance technicians, facility operators, and validation can ensure that all project objectives (cost, quality, schedule,
personnel with the tasks of: struggling to locate as-built safety, etc.) are continuously considered in decision making.
documents, making equipment work, calling vendors for Commissioning suffers when the project team does not
training, working off the punch list, and attempting to en- plan or organize itself early enough. The commissioning
force warranties. manager must be selected early and should report to the proj-
ect manager. By early selection, the commissioning manager

248 Journal of Validation Technology


David W. Vincent and Herbert Matheson

and team can plan for completion when project engineers Pre-Delivery Activities
and construction staff are actively involved in the daily rig-
ors of construction. Selection of the commissioning manager Provide detail and instructions for each pre-delivery ac-
is extremely important; the individual must have operations tivity.
experience as well as good planning and interpersonal skills.
The commissioning manager must then select an appropriate Examples of pre-delivery activities include:
complement of field technicians, calibration and metrology Control of specifications
staff, document specialists, and technical writers. Some of Review of vendor submittals
these individuals may be sometimes "loaned" by mainte- Vendor audits
nance and operation groups and then returned to those Third party inspections of off-site fabrication
groups after project completion. In fact, the loaning of team Module and equipment vendor quality control and
members is often the best solution because it enables start- inspections
up knowledge to transfer from project team to operations. Factory Acceptance Testing (FAT)
Factory inspection plan
Commission Plan
Equipment and Material Receipt Control
The commission plan is, properly, one of the most im-
portant criteria documents that will be used on the project. Describe the procedures, documentation, and methods of
The commissioning plan should indicate the various com- control to be utilized for equipment and material receipt.
mission activities for both GMP and non-GMP systems. The system should include the following:
The plan should identify the overall commissioning strategy Approving and rejecting components and equip-
for the project and complement the Validation Master Plan ment
(VMP) to identify the integration of commissioning and Defining storage locations and conditions for criti-
validation activities. It also should define the roles and re- cal components (direct contact copper tubing verses
sponsibilities of each functional department and their ven- non-critical copper) to minimize mix-up
dors as they relate to the commissioning and integration of Separation of non-GMP materials from GMP mate-
the qualification activates. rials

The following items describe the key elements of suc- Construction Quality Assurance Activities
cessful commissioning plan:
A description of the equipment and systems to be com- It is critical to define the role and responsibility of the
missioned including their means of automation quality unit during the commissioning phase. While it is
A description of the methods and tools to be used in clearly understood that commissioning is usually an engi-
commissioning execution neering function, sometimes it is not clear what the Quality
A detailed description of the commissioning strategy in- Unit role is during the commissioning phase of the project.
cluding integration of commissioning and validation ac- During the engineering phase of the project, QA may audit
tivities the approved equipment and utility system vendors to ver-
Overall sequence of commissioning activities ify that they have the necessary quality systems in place to
A detailed description of project deliverables including ensure the quality of their product or service. Part of the in-
identification of the parties responsible for providing the tegration concept also involves auditing design and con-
deliverables struction activities for compliance with cGMPs, verifying
Roles and responsibilities of personnel involved in the documentation, and keeping a close eye on the installation
commissioning effort throughout construction and com- progress throughout the projects construction phase.
missioning The Quality Unit must be aware that GMP requires qual-
The commissioning plan should include a strategy for ification activities. Whether some of the qualification is per-
integrating the qualification phase into the commissioning formed during the commission phase or not, the regulations
activities. require these activities be reviewed and signed-off by the
Quality Unit. Therefore, if any aspects of the qualification

M a y 2 0 0 5 Vo l u m e 11 , N u m b e r 3 249
David W. Vincent and Herbert Matheson

activities are being captured during the commissioning Startup and Formal Commissioning
phase, the Quality Unit must at least agree and sign-off on
the commissioning plan or strategy. (Because some qualifi- This section of the commission plan should de-
cation activities are integrated into the commissioning phase scribe, in detail, the components of startup and
does not mean that they are no longer GMP activities.) commissioning execution.
Components may include:
Describe the roles and responsibilities for all proj- Special pre-startup checks
ect quality control and quality assurance activities. Notification to stake holders that startup activi-
Define the scope of the quality control program, ties will commence that may affect certain
authorized documentation, and responsibilities for process equipment or systems, i.e.: backup gen-
the implementation and maintenance of the pro- erator, etc.
gram. Startup procedures
Detail the requirements for in-process inspections Setting to work and initial shakedown
and the methods to be used to document the in- Software structural testing
spections. Inspections
Describe the requirements for the creation, mainte- Functional testing
nance, and verification of red-line, as-built drawings Cycle development
Specify the requirements, methods, and procedures Special testing
to be utilized for foreign material exclusion for di-
rect impact components and materials. Commissioning Documentation and Turnover Pack-
ages
Commissioning Execution
This section of the commission plan should de-
Pre-Commissioning scribe, in detail, the commissioning documents and
requirements for turnover packages.
A pre-commissioning phase includes the comple-
tion of tasks necessary to verify that the system is Components may include:
mechanically complete and ready for the initiation Commissioning Documentation that specifies the
of subsequent commissioning activities. requirements for commissioning including: re-
quired documentation, references, documenta-
These activities include: tion practices, and final reports.
Mechanical completion
Safety reviews Turnover Packages, which provide an outline of
Code inspections the procedures and requirements for the assem-
Site Acceptance Testing bly and turnover of system manuals and other
Tagging and labeling verification turnover packages.
Valve or damper lineups
Installation of temporary strainers and filters Commissioning Completion and Turnover to Owner
Walk down of the system
This section of the commission plan should de-
scribe, in detail, the commissioning completion
and turnover to owner. Project closeout procedures,
deliverables, and responsibilities must be clearly
defined well before construction commences. The
method of project turnover, whether phased or in
single project completion turnover package, should
be clearly defined in this section.

250 Journal of Validation Technology


David W. Vincent and Herbert Matheson

Components of turnover strategy may include: Start-up date


Deliverables including final release of liens, cer- Applicable system number (cross reference)
tificate of occupancy, final as-built drawings and
specifications, turnover packages, finalized Instrument List
punch list, etc. Instrument tag number
Project supplied training Instrument name
Spare parts Critical or non-critical?
Owner acceptance of operational responsibilities P&ID reference
Vendor name
Commissioning Documentation List Manufacturer submittal received (date and time)
Local or panel mounted
Commissioning starts with the preparation of many lists,
which ultimately form the foundation for planning and doc- The Role of Qualification Phase
ument management. An orderly set of equipment lists, in- in Commissioning
strument lists, vendor lists, etc., will allow the commission-
ing manager to organize his thoughts and begin paying at- Qualification is a process that focuses on systems affect-
tention to details early. ing product quality - those defined as direct impact systems
The key to preparing the needed lists is an exhaustive during the system impact assessment process. However, this
review of all systems in the facility and selecting the right represents only a fraction of what must be done to properly
number of turnover packages. This is best accomplished by commission and document an entire facility. The qualifica-
reviewing Process Flow Diagrams (PFDs) or P&IDs, key tion phase, therefore, must be considered a part of the com-
documents for any manufacturing facility. These diagrams missioning umbrella. IQ and OQ activities should be
are best used to distinguish the boundaries of each system. planned to take advantage of key commissioning activities,
The turnover packages will become a central theme for which take place in parallel.
commissioning and will be described later in more detail. As the schedule indicates, commissioning and qualifica-
The various lists may well be the most tedious and time- tion should start together and should be executed together.
consuming part of the commissioning manager's job. Validation documents should be considered supplemental
and complimentary to commissioning documents, and du-
A few of the key lists and the related data are recom- plication should be avoided. This approach, if adopted, will
mended below: yield the earliest possible project delivery. Figure 8 is a typ-
Drawings and Specifications List ical validation flow chart.
Drawing or revision number(s)
Drawing title Use of an Integrated and Streamlined Validation Ap-
Drawing status proach
Drawing developed by . . . One cost effective method for managing the validation
Final walk down completed on . . . project is the using of an integrated and streamlined ap-
Applicable system number (cross reference) proach to optimize commissioning and validation activities
on a project.
Equipment List Using an integrated approach, project success would in-
Equipment tag number clude the following benefits:
(should match maintenance system tag) Reduced project schedules and better overall
Equipment name schedule management
Critical or non-critical? Reduced start-up time needed in the field
P&ID reference Reduced project costs
Vendor name Fewer defects or deviations during the qualification
Installation date phase
Vendor submittal received (date and time) Reduced internal resource needs at the end of the
SOP required? (yes or no) project

M a y 2 0 0 5 Vo l u m e 11 , N u m b e r 3 251
David W. Vincent and Herbert Matheson

Figure 8
______________________________________________________________________________
Typical Validation Flowcart

Engineering Validation

Front End Concept Study

Validation Master Plan (VMP)


Engineering Specifications/User
Requirement Specification (URS)
GMP Audit, Design Qualification
Generate
(DQ) and Impact Assessment
and Address
Functional and Detail Design
Snag List

Factory Acceptance Test (FAT)


Tender

Generate Pre-delivery Inspection (PDI)


Procedure and Construct and Address
Snag List
Protocol Development
Install

Commission Formal Installation Qualification (IQ)/


Generate Operational Qualification (OQ)
and Address
Snag List
Formal Project Turnover Formal Equipment Performance
Generate Qualification (EPQ)
and Address
Snag List
Release and Use
Decommissioning

Periodic Review, Change Control


and Revalidation

252 Journal of Validation Technology


David W. Vincent and Herbert Matheson

Adherence to compliance requirements pletion of the facility, thus tying IQ/OQ closely to the con-
Overall project quality improvement struction contractors scope of work that includes commis-
sioning. To avoid the effort and inconvenience of discover-
During streamlining, the commissioning and validation ing and rectifying basic problems, it is recommended that
activities should adhere to the following basic principles: all systems go through an informal shakedown phase before
Start the project by evaluating the impact of a system IQ/OQ commences. This will help ensure a smooth transi-
on product quality tion between IQ and OQ, and will minimize the number of
Focus resources on the qualification of systems with deviations that may occur during the IQ and OQ phases.
"direct impact" on product quality according to Scheduling of PQ is particularly critical because PQ
GMP testing is often the most time consuming part of the qualifi-
Focus on critical components that will have a direct cation. Scheduling should take into account any prerequi-
impact on the project quality sites that should be achieved prior to PQ execution (such as
Establish system boundaries in the early phase of the commissioning of all support systems, availability of SOPs,
project system interdependencies). The PQ protocol often receives
Evaluate system design from both a quality perspec- the greatest amount of scrutiny from the approval team.
tive and a risk-based approach Again, it is important that IQs and OQs are completed and
Provide contractors, vendors, and engineers with the that there are no major deviations that may have negative
project validation requirements up-front to enable impact on the PQ phase.
them to plan installations to meet these requirements
Design and commission those systems that have no Integrate Commissioning with Validation Activities
"direct impact" on product quality according to GEP There are considerable advantages of time, cost, and
Enhance the commissioning, qualification, and vali- quality in integrating the many functions carried out by
dation documentation generation, review, and ap- skilled resources, such as engineering, contractor, and vali-
proval processes dation teams. The responsibility for timely and appropriate
Integrate the commissioning and qualification activ- execution should be a combination of both the validation and
ities to avoid duplication of work engineering teams, this will reduce the time spent on vali-
Conduct training of employees, contractors, con- dating the facility and scaling up to production. The use of a
sultants, and other personnel early in the project competent, expert, multi-disciplinary team will ensure that
lifecycle best practice is deployed and that duplication of activities is
avoided.
Strategies Integrating activities such as Design Qualification, Con-
struction Qualification, Factory Acceptance Testing, Site Ac-
The following section includes some detailed strategies ceptance Testing and commissioning into qualification and
that could be followed to reduce project resource require- validation activities can control validation costs and mini-
ments and improve the efficiencies of the commissioning mize project delays. Instruments, components, and equip-
and validation programs. ment can be verified at the vendor site during the FAT and
CQ phases of the project. This reduces delays caused by
Integrate Validation Schedules into the Overall Project identifying potential problems before equipment is delivered
Schedule to the job site. If these items are not altered or dismantled in
The project manager, with support of team members, any way for transport, these checks, if properly documented,
should ensure the development of a commissioning and val- could be used in support of SAT or qualification activities.
idation plan as an integral part of the project plan and sched- For OQ, the duration of the testing can be shortened by
ule. Integrating validation into the overall project schedule identifying the critical operational criteria that require test-
can save both time and money. Integrated schedules should ing prior to the facility, utility, or equipment being used in
be developed with input from the construction and valida- production and planning the schedule accordingly. This
tion project teams and be maintained and updated at regular can be performed by determining which functional con-
intervals. trols are critical and non critical in the early stages of the
IQ/OQ may be conducted as part of the physical com- DQ phase of the project. Testing the non-critical functions

M a y 2 0 0 5 Vo l u m e 11 , N u m b e r 3 253
David W. Vincent and Herbert Matheson

during the FAT or SAT will reduce the amount of testing direct impact systems are appropriately planned,
required during OQ phase. created, organized, and authorized so that they may
If FAT is executed for equipment, i.e., alarms and inter- become an integral part of the qualification support
locks testing, some or all of these tests can be performed at documentation.
the vendor site, or these tests can be performed as part of Combining engineering and validation information
commissioning, and can be used in support of the OQ. Per- to minimize duplication.
formance testing carried out as part of commissioning can
contribute to PQ when performed consistently with qualifi- Once qualification protocols are written, they should be
cation practices. Thus, if the integrated approach is used and approved, and this may be a time consuming process. Sev-
proper inspections, field verification, documentation, and eral ways to streamline this process include:
certain required field execution work is accomplished by the Minimizing the number of approvals required by
construction vendors and contractors, then the qualification developing approval matrixes.
scope can be reduced to that of review, verification, cross Clarifying the review process with all parties early
linkage to FAT and SAT documents, monitoring, and com- in the project.
piling. The integration of commissioning and qualification Instituting a formalized protocol tracking process.
merges activities, minimizes resource requirements, and Minimizing the number of review cycles allowed
streamlines the validation effort by reducing the number of by the team.
protocols and reports. Implementing a simple review and approval proce-
Approaches to streamline the amount of paperwork re- dure with time limit for the review cycle.
quired to give sufficient documented evidence of validation Instituting protocol review meetings for all parties
may include: involved.
Using standardized protocol and report templates Ensuring the protocol review and approval process
wherever possible, so that reviewers become accus- is included in the overall project schedule.
tomed to protocol formats and contents.
Using procedures and forms that can minimize re- Define which activities the vendors are responsible for
dundancy normally found in qualification proto- executing when utilizing an integrated approach to com-
cols. missioning and validation activities. Figure 9 is an example
Structuring executed protocols as reports to obviate of the integration of commissioning, qualification testing,
the need for writing a separate report. and verification activities related to WFI skid and distribu-
Combining IQ and OQ documents (to I/OQ) will tion system (See Figure 9):
result in fewer documents to develop, track, review,
and approve. However, the IQ section must be Note: Vendors performs 100% loop check
completed before OQ commences. during commissioning phase. Validation
Including only critical tests in the protocol, and not engineer performs 10% during Qualifica-
repeating non-critical ones already conducted in tion Phase. If failure is detected during
FAT or SAT phases, simply verifying that these test the 10% verification, then 100% inspec-
have been performed in the qualification protocols. tion is performed by validation engineer
Understanding upfront the critical and test items to or validation engineer witnesses 100%
be included in the qualification can reduce both performed by vendor.
cost and unnecessary deviations.
Establishing realistic protocol acceptance criteria
based upon the process demands for reproducibil-
ity and product quality.
Recording deviations in the qualification protocol
attachments and then having them immediately re-
viewed and approved by the Quality Unit rather
then waiting until the entire protocol is executed.
Ensuring that commissioning documentation for

254 Journal of Validation Technology


David W. Vincent and Herbert Matheson

Figure 9
______________________________________________________________________________
Commissioning and Qualification Integration Approach

Tests and Verification Commissioning Phase Qualification Phase


Activities CQ FAT SAT IQ OQ PQ
Functional Design, Verification,
and Design Specifications
Facility As-built and Piping and
Instrumentation Drawings
Electrical drawings
Critical Component Verification
Materials of Construction
Welding Documentation
Alarm and Interlock Test
Control System Component

Verification
Hydrostatics Testing
Material Incoming Receipt
Cleaning and Passivation
Steam in Place Startup
Surface Finish Documentation

Report
Vent Filter Integrity
Spare Part Inventory
Operation Control Function

Non-Critical
Operation Control Function
Critical
Software Installation Verification
Operation and Maintenance
Procedures Verification
Pump and Motor Checkouts (Ro-
tation, Lube, Alignment, Belt, etc.)
Control System Function
*Loop Check Verification
Compliance (ASME Certifications)
Control System Security Access
and Password Protection
Sequence of Operations
Radio Frequency Interference Test
Voltage test
Shut Down and Startup
sequence
Data Trending Ability
Operation Parameter Control
Baseline Performance
CQ = Construction Qualification DQ = Design Qualification FAT = Factory Acceptance Testing
IQ = Installation Qualification OQ = Operational Qualification PQ = Performance Qualification
SAT = Site Acceptance Testing

M a y 2 0 0 5 Vo l u m e 11 , N u m b e r 3 255
David W. Vincent and Herbert Matheson

This is the first part of a three-part article. Parts II and III


Article Acronym Listing
will be published in the Journal of Validation Technology in
the August and November 2005 issues, respectively. A/E Architecture and Engineering
ANSI American National Standards Institute
About the Author ASME American Society of Mechanical
Engineers
David W. Vincent has over 25 years experience in the CFR Code of Federal Regulations
Biopharmaceutical industry with 19 years dedicated cGMP Current Good Manufacturing Practice
to the fields of validation and engineering. He has a CIP Clean in Place
BS degree in Microbiology and Mechanical Engineer- CQ Construction Qualification
ing Technology; Mr. Vincent has consulted for many
DCS
companies both nationally and internationally. He has
DQ Design Qualification
presented many training seminars and has written
FAT Factory Acceptance Test
numerous articles and technical guides regarding val-
idation topics. Mr. Vincent teaches "Validation Pro- FDA Food and Drug Administration
gram for the Pharmaceutical, Biotechnology, and GDP Good Documentation Practice
Medical Device Industries" at San Diego State Uni- GEP Good Engineering Practice
versity (SDSU) for their Regulatory Affairs Master De- GMP Good Manufacturing Practice
gree program. HEPA High Efficiency Particulate Air
HVAC Heating, Ventilation,
Currently, Dave is the Chief Executive Office (CEO) and Air Conditioning
for Validation Technologies Incorporated (VTI), a I/O Input/Output
worldwide validation and technical services company. IQ Installation Qualification
VTI is also a certified commissioning company that ISPE International Society for
offers commissioning and startup functions for the Pharmaceutical Engineering
healthcare industry. Dave can be reached by phone MSDS Material Safety Data Sheet
at 800-930-9222, by fax at 858-638-5532, or by e- OQ Operational Qualification
mail at david@validation.org. (Web Site is located at P&ID Process and Instrumentation Diagram
www.validation.org) PFD Process Flow Diagram
PLC
PQ Performance Qualification
The following references are those applicable to Part I. PW Purified Water
The full list of references used in the three-part article QA Quality Assurance
will appear with Part III in the November 2005, Journal QC Quality Control
of Validation Technology. RA Regulatory Affairs
REM Routine Environmental Monitoring
References SAT Site Acceptance Testing
SOP Standard Operating Procedure
1. Center for Drugs and Biologics, Center for Devices and TOP Turn Over Package
Radiographic Health, "Guidelines on General Principles URS User Requirement Specification
of Process Validation," FDA Rockville, Maryland, 1987. VMP Validation Master Plan
2. "cGMP Compliance in Architecture and Construction of
WFI Water For Injection
Biopharmaceutical Manufacturing Facilities" BioPharm,
Prepared January-February, 1993.
Biologics Evaluation and Research, Office of Regula-
3. "Code of Federal Regulations Section 21 Parts 200 to
tory Affairs, "Guidelines on Sterile Drug Products Pro-
299 and Parts 600 to 799," Food and Drugs Adminis-
duced by Aseptic Processing," FDA Rockville, Mary-
tration (FDA).
land, June 1987.
4. "Guidelines for Bulk Drug Manufacturers," Food and
6. Center for Drug Evaluation and Research, Center for
Drugs Administration (FDA).
Biologics Evaluation and Research, Office of Regula-
5. Center for Drug Evaluation and Research, Center for
tory Affairs, "Guidelines on Sterile Drug Products Pro-

256 Journal of Validation Technology


David W. Vincent and Herbert Matheson

duced by Aseptic Processing," FDA Rockville, Mary-


land, June 1987.
7. PDA Environmental Task Force, "Fundamentals of a Mi-
crobiological Environmental Monitoring Program," Vol.
44, Supplement 1990.
8. "Microbiological Control and Validation," The Institute
for Applied Pharmaceutical Sciences, March 7-9, 1994.
9. Powell-Evans, K., "Streamlining Validation; Value
Added Qualifications." Institute of Validation Technol-
ogy. December 2000. Newsletter.
10. Graham C. Wrigley, Pfizer Global Manufacturing, and
Jan L. du Preez, Ph.D., "Research Institute for Indus-
trial Pharmacy Facility Validation: A Case Study for In-
tegrating and Streamlining the Validation Approach to
Reduce Project Resources," Volume 8, Number 2, Feb-
ruary 2002.

M a y 2 0 0 5 Vo l u m e 11 , N u m b e r 3 257

Potrebbero piacerti anche