ABSTRACT:
The converter transformer which is related to the safe operation of the entire power grid project
running efficiently is the key equipment HVDC transmission project, and it is the core equipment in the
AC-DC transmission system. The partial discharge test of the converter transformer should be carried
out before a major transition in order to prevent and detect the insulation inside. Based on the 800kV
converter transformer valve side entrance capacitance derived to calculate partial discharge
compensation reactance, and use of existing equipment for the test conducted one hour long induced
voltage test, obtain and analyze test data to explain the use of the parallel resonance principle
advantages of partial discharge test.
KEY WORD: Partial Discharge, Parallel resonant, Entrance capacitance, Reactance compensation,
Frequency Power
1.Introduction
Since the first HVDC transmission project which in Sweden Gothic put into operation in the world in
1954,the HVDC transmission technology has already obtained the development at all speed. HVDC
has been widely used all over the world as an important supplement of HVAC transmission technology.
It has many own advantages, such as long distance transmission, low cost, and so on. Though the
HVDC transmission technology is started lately in China, it is developing very quickly and it has
reached the leading level of the world[1]. The 800 kV UHVDC transmission project of Xiangjiaba -
Shanghai which is the independent research and development, design and construction by China in
2009 is the most advanced technological DC transmission project in the word. Its successful operation
marked that China has solved this universal problem in the field of UHVDC and UHVAC[1-2].
As the main equipment in the converter station, the converter transformers operation is of the
most important to the reliability of DC transmission. Before the hand-over test of transformers partial
discharge (PD) test must be carried out according to the requirements of The Precautionary Test For
the Electric Equipments. The PD test of the converter transformer is very important, because inside of
the converter transformer will be under AC and DC voltage. Generator cant meet the requirements of
the PD test, because of the converter transformer with large capacity. But frequency-converting power
and the parallel resonant are without the restriction. The advantages of the parallel resonant system are
small capacity power, low distortion, strong over loading resistance, high reliability, small size, and so
on. So this method is now paid more attention to in the field of high voltage test.
2.The principle of parallel resonant
The parallel resonant called current resonance also, see Fig.1.In the circuit, it is composed of
resistance and inductance, which is paralleled with capacitance. For capacitance, the circuit is the
resistance circuit when the phase of voltage and current at the same phase, and the branch current is
greater than the loop current. So the voltage of the capacitance will be very high.
I1cos1
I1
R I
U I1 I2
I2
L
I1sin1-I2
I1sin1
I1
U
U .....................................1
Z1 R 2
X
2
L
XL .................................................2
1 arctan
R
We can get current I2 in the same way.
U U
I2 j CU .....................................3
Z2 XC
The current I can be got in the loop circuit form (1) and (3).
I 1 sin 1 I 2 ......................................5
arctan
I 1 cos 1
From the formulas (4), we know that if I1sin1=I2,=0.We can get from (1),(2),(3).
1 R2 ..................................................6
2
LC L
1
0 LC ............................................7
1
f0
2 LC
T1 T2 H V FP T3 Sam ple
9H
L
9H
B D
A
E
U1
U2 U2
1.1Um/ 1.1Um/
<1/3U 2
1/3U 2 3 3
U1 U 2 U U
U U2 U A ( 1 2 )U A ( pu 1 pu 2 )U A pU A
If 1 UA UA UA
U 'U 2 ' U ' U ' ,
U 1 'U 2 ' 1 U A ( 1 2 )U A ( pu 1 ' pu 2 ' )U A p ' U A
UA UA UA
p '2 * UA 2 C .............................(10)
3h 3 h2 h 0
0 0
( p p' )2
( p p ' ) p ' p ' 2 ) * UA 2 C
3
( p p' )2
pp ' * UA 2 C
3
Reference
[1]Liu Zhenya. Ultra-high voltage[M].Beijing. China Economic Press. 2005.
[2] Liu Zhenya.The power and energy in China. Beijing.China Power Press. 2012.
[3]Hu Qifan.Test technology of transformer. Beijing.China Power Press. 2014.
[4]Wang Guanzheng. The test of transformer.Beijing.China Machine Press.2009
[5]IEC 60076-3:2000 Power transformers-Part 3:Insulation levels,dielectric test and extrnal clearances
in air.
[6]Yin Baoxun. Capacitance calculation of the transformer in the excited state[J].Transformer.
2013,07:11-15.
[7]Yang Zaibao. The Research and application of Parallel resonance In the Partial Discharge test of the
800kV converter transformer [D].Shandong University,2014.