Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Topic
IMMERSED AND FLOATING TUNNELS
Title
New Tyne Crossing, Newcastle, joint venture of bored and immersed tunnel completes the link
Author
J.C.W.M. de Wit, T.J. Fay
Originally published
in "(Re)Claiming the Underground Space",
Vol. 1, pp. 283 - 285, Year 2003.
by A.A. Balkema, Lisse ,The Netherlands, www.balkema.nl and www.szp.swets.nl
Working Group: -
Open Session, Seminar, Workshop: "Immersed Tunnels", Amsterdam, 2003
Others: Meetings
Abstract: This paper outlines the topics of the New Tyne Crossing, Newcastle UK. The existing 2 lane bored tunnel in
the motorway A 19 will be joined by a new 2 lanes immersed tunnel to complete the link.
Rsum: -
Remarks: -
J.C.W.M. de Wit
Royal Haskoning Rotterdam
T.J. Fay
Posford Haskoning Newcastle
ABSTRACT: This paper outlines the topics of the New Tyne Crossing, Newcastle UK. The existing 2 lane
bored tunnel in the motorway A19 will be joined by a new 2 lane immersed tunnel to complete the link.
283
09042-45.qxd 03/Mar/03 10:48 AM Page 284
1.4 1.4
-19.000m OD
-21.0m OD
1025
7750
OD level
OD level +0.410m OD
3000 250
-2.800m OD
-4.4m OD
Grout prop Gravel layer
12000 -7.3m OD
four 95 m long elements (b h 14 8.75 m), each The approaches are to be constructed using cut and
consisting of units of 19 m. It is envisaged that the cover techniques involving deep braced excavations
elements will be constructed in two shifts in a tempo- with diaphragm walls, removal of soil to a temporary
rary construction dock in Howdon Basin on the north storage, construction of the concrete structure in the
side of the river and situated within the alignment of building pit, back filling using the excavated material
the new tunnel. It will be necessary to dredge a berthing and reinstatement of the surface. Excavations of over
pocket for the temporary storage of the 1st shift ele- 25 m in depth and partly within bed rock have to be
ments whilst the 2nd shift elements are constructed. performed to allow for construction of the permanent
This is to allow all four elements to be immersed con- concrete body (Figure 3, left). The new tunnel is
secutively after dredging of the immersion trench. required to cross the existing tunnel in two locations on
The temporary berthing pocket is located at the edge the north side of the river. During construction of the
of the navigation channel so as not to interfere with new tunnel the existing tunnel will continue to be used.
shipping movements and to avoid destabilising river For reasons of protecting the existing tunnel it is desir-
edge structures. able to maximise the vertical separation between the
284
09042-45.qxd 03/Mar/03 10:48 AM Page 285
two tunnels at the crossing points. This is the main Issues like traffic and construction noise, air quality,
reason why a 6% gradient is adopted at the northern landscape and visual impact, land and river ecology,
approach of the new tunnel. Still the works required water quality and protection of adjacent structures
to construct the new tunnel must be carried out in (e.g. existing bored tunnel and nearby housing) were
such a way that the risk of disturbing loading condi- careful investigated.
tions is minimised. Therefore special techniques and
construction phasing is applied. Both the diaphragm
walls and the building pit base are supported by the 6 FINANCIAL
same grout body of approx. 3 m in depth. After a
minor excavation the roof is constructed and back Tyne & Wear Passenger Transport Authority has com-
filled again, followed by excavation and construction missioned a consortium of advisors to look in detail at
of the concrete structure underneath the tunnel roof. the issues surrounding the construction of a New
During construction the existing tunnel will be care- Tyne Crossing and to develop a reference design. The
fully monitored (Figure 3, right). crossing will be designed by a consortium of private
sector companies following a tendering process. The
concessionaire will be the consortium which success-
fully tenders to design, build, finance and operate the
5 ENVIRONMENTAL new crossing. The concessionaire will take responsi-
bility for the operation for a period of up to 30 years.
Since the tunnel will be situated in an urban sur- Traffic studies and financial analyses (incl. capital
rounding special attention is paid to the environmen- and operating costs) were carried out to determine the
tal impact of construction and operation of the tunnel. concession period and annual toll revenues.
285