Sei sulla pagina 1di 4

ASSOCIATION

INTERNATIONALE DES TRAVAUX


EN SOUTERRAIN ITA
AITES
INTERNATIONAL
TUNNELLING
ASSOCIATION
Towards an In Consultative Status, Category II with the
improved use United Nations Economic and Social Council
of underground http://www.ita-aites.org
Space

Topic
IMMERSED AND FLOATING TUNNELS
Title
New Tyne Crossing, Newcastle, joint venture of bored and immersed tunnel completes the link
Author
J.C.W.M. de Wit, T.J. Fay
Originally published
in "(Re)Claiming the Underground Space",
Vol. 1, pp. 283 - 285, Year 2003.
by A.A. Balkema, Lisse ,The Netherlands, www.balkema.nl and www.szp.swets.nl
Working Group: -
Open Session, Seminar, Workshop: "Immersed Tunnels", Amsterdam, 2003
Others: Meetings

Abstract: This paper outlines the topics of the New Tyne Crossing, Newcastle UK. The existing 2 lane bored tunnel in
the motorway A 19 will be joined by a new 2 lanes immersed tunnel to complete the link.
Rsum: -
Remarks: -

Secretariat : ITA-AITES c/o EPFL - Bt. GC CH-1015 Lausanne - Switzerland


Fax : +41 21 693 41 53 - Tel. : +41 21 693 23 10 - e-mail : secretariat@ita-aites.org - www.ita-aites.org
09042-45.qxd 2/17/03 5:57 PM Page 283

(Re)Claiming the Underground Space, Saveur (ed.)


2003 Swets & Zeitlinger, Lisse, ISBN 90 5809 542 8

New Tyne Crossing, Newcastle, joint venture of bored and


immersed tunnel completes the link

J.C.W.M. de Wit
Royal Haskoning Rotterdam

T.J. Fay
Posford Haskoning Newcastle

ABSTRACT: This paper outlines the topics of the New Tyne Crossing, Newcastle UK. The existing 2 lane
bored tunnel in the motorway A19 will be joined by a new 2 lane immersed tunnel to complete the link.

1 INTRODUCTION the tunnel was constructed comprises well faulted coal


measures which vary substantially along the align-
For many years serious congestion has occurred at ment from alluvial soft clay to boulder clay inter-
peak times on the A19 trunk road at its crossing under spersed with water bearing beds of silt, sand and
the river Tyne east of Newcastle. The Bottleneck gravel, shale, sandstone and coal seams. Mainly
occurs in the 2 lane bi-directional Tyne Tunnel which because of the variations and the fissures that occur in
was constructed in the sixties and designed to carry the coal measures the construction of the existing tun-
24,000 vehicles per day; it now carries 35,000 vehi- nel was very complicated with a lot of set backs and
cles per day. Upgrading of the existing crossing is incidents and an average production rate of approx.
essential to reduce congestion (incl. air and noise pol- 7 m/week.
lution), improve safety and travel times and will help
to attract investment along the A19 corridor and
improve access of the people of South Tyneside 4 REFERENCE DESIGN
(which has one of the highest unemployment rates in
the UK) to job opportunities in North Tyneside. In the reference design the existing tunnel will carry
the northbound traffic (2 lanes), whereas the new tun-
nel carries the southbound traffic (2 lanes). The align-
2 FEASIBILITY STUDIES ment of the new tunnel is mainly determined by the
water depth required depth in the navigation channel
A feasibility study was carried out to select the most in the River Tyne and the crossing points over the
suitable option for the New Tyne Crossing. Several existing tunnel in the northern bank. This resulted in
bridge and tunnel options were considered. On the a 6% downward gradient on the north side of the river
basis of environmental impact and navigational require- and a 5% upward gradient on the south side. The hor-
ments on the river a tunnel option was considered to izontal alignment is presented in Figure 1.
be most appropriate. On the basis of whole life costing The new crossing, comprising a 2 lane traffic tube
and construction risk there appeared to be a benefit in and a 1.5 m wide escape/service tube, consists of:
an immersed tunnel as opposed to a bored tunnel. 380 m long immersed part at the river Tyne;
cut and cover south of approx. 800 m;
cut and cover north of approx. 320 m.
3 EXISTING TUNNEL
An immersed tunnel is constructed by dredging a
The existing Tyne Tunnel is 10.2 m diameter bored tun- trench in the river bed and then floating pre assem-
nel; it was excavated using hand boring tools and con- bled tunnel elements into place before back filling
structed of cast iron segments, each bolted together them and covering them with protective rock. The
and the joint sealed with lead. The subsoil in which immersed part of the New Tyne tunnel consists of

283
09042-45.qxd 03/Mar/03 10:48 AM Page 284

Figure 1. Plan view of Tyne tunnel.

MHWS = +2.4m OD = 5.0m CD


0.0m OD = +2.6m CD
MLWS = -1.9m OD = +0.7m CD

-7.8m OD existing river


-9.8m OD = -7.2m CD backfill level

1.4 1.4 rock armour protection 1.0m thick

1.4 1.4
-19.000m OD
-21.0m OD

assumed bed rock level

profile of dredged -28.6m OD


immersion trench

Figure 2. Immersed tunnel and existing bored tunnel.

800 13400 800 800 13400 800


+8.2m OD +10.5m OD +9.6m OD
Diaphragm wall 0.8m +7.0m OD Diaphragm wall 0.8m
Diaphragm wall

1025
7750
OD level
OD level +0.410m OD
3000 250

-2.800m OD

-4.4m OD
Grout prop Gravel layer
12000 -7.3m OD

-16.0m OD EXISTING TUNNEL -15.2M OD -12.4m OD

Figure 3. Cross section approach and cross over.

four 95 m long elements (b h 14 8.75 m), each The approaches are to be constructed using cut and
consisting of units of 19 m. It is envisaged that the cover techniques involving deep braced excavations
elements will be constructed in two shifts in a tempo- with diaphragm walls, removal of soil to a temporary
rary construction dock in Howdon Basin on the north storage, construction of the concrete structure in the
side of the river and situated within the alignment of building pit, back filling using the excavated material
the new tunnel. It will be necessary to dredge a berthing and reinstatement of the surface. Excavations of over
pocket for the temporary storage of the 1st shift ele- 25 m in depth and partly within bed rock have to be
ments whilst the 2nd shift elements are constructed. performed to allow for construction of the permanent
This is to allow all four elements to be immersed con- concrete body (Figure 3, left). The new tunnel is
secutively after dredging of the immersion trench. required to cross the existing tunnel in two locations on
The temporary berthing pocket is located at the edge the north side of the river. During construction of the
of the navigation channel so as not to interfere with new tunnel the existing tunnel will continue to be used.
shipping movements and to avoid destabilising river For reasons of protecting the existing tunnel it is desir-
edge structures. able to maximise the vertical separation between the

284
09042-45.qxd 03/Mar/03 10:48 AM Page 285

two tunnels at the crossing points. This is the main Issues like traffic and construction noise, air quality,
reason why a 6% gradient is adopted at the northern landscape and visual impact, land and river ecology,
approach of the new tunnel. Still the works required water quality and protection of adjacent structures
to construct the new tunnel must be carried out in (e.g. existing bored tunnel and nearby housing) were
such a way that the risk of disturbing loading condi- careful investigated.
tions is minimised. Therefore special techniques and
construction phasing is applied. Both the diaphragm
walls and the building pit base are supported by the 6 FINANCIAL
same grout body of approx. 3 m in depth. After a
minor excavation the roof is constructed and back Tyne & Wear Passenger Transport Authority has com-
filled again, followed by excavation and construction missioned a consortium of advisors to look in detail at
of the concrete structure underneath the tunnel roof. the issues surrounding the construction of a New
During construction the existing tunnel will be care- Tyne Crossing and to develop a reference design. The
fully monitored (Figure 3, right). crossing will be designed by a consortium of private
sector companies following a tendering process. The
concessionaire will be the consortium which success-
fully tenders to design, build, finance and operate the
5 ENVIRONMENTAL new crossing. The concessionaire will take responsi-
bility for the operation for a period of up to 30 years.
Since the tunnel will be situated in an urban sur- Traffic studies and financial analyses (incl. capital
rounding special attention is paid to the environmen- and operating costs) were carried out to determine the
tal impact of construction and operation of the tunnel. concession period and annual toll revenues.

285

Potrebbero piacerti anche