07/26/2017

18:05:25

DISEO MALLA DE PERFORACION EXP

DATOS

Altura de Banco = 32.50 Pies = 9.91 m


Densidad del Material = 3.75 Ton / m3
Factor de Potencia = 0.40 Lib / Ton = 0.18 kg / Ton
Diametro Taladro = 2.50 Pulg = 0.06 m
Densidad de Anfo = 0.80 gr / cm3

CALCULO

BURDEN = B
SUB DRILLING = 0.3 B
ESPACIAMIENTO = 1.25 B

VOLUMEN = H x B x E

= 9.906 m x Bm x 1.25 Bm

= 12.3825 B2 m3

TONELAJE = Volumen x P.E.Material

= 12.3825 B2 m3 x 3.75 Ton


m3
= 46.43 B2 Ton

LIBRAS DE ANFO ( Lib / Ton ) = Factor Potencia x Tonelaje

= 0.4 lib x 46.43 B2 Ton


ton

= 18.57 B2 lib

VOL. ANFO EN 1 mt DE TALADRO = Pi x r2 x h

0 Taladro 3.1416 x 0.001 m2 x 1 m

1m = 0.0032 m3

CAP. DE ANFO EN 1 m TALADRO = Volumen anfo en 1 m x densidad anfo

= 0.0032 m3 x 0.8 gr x 1E+06 cm3 x 1 lib


1 m cm3 1 m3 454 gr

= 2533.5433
453.592

= 5.59 lib / m

ALTURA DE CARGA DE ANFO = Consumo de Anfo / Capacidad de Taladro

= 18.57 B2 lib / 5.59 lib


m
= 3.3253 B2 m

ALTURA DE COLLAR = Altura de Banco + Sub Drilling - Altura de Carga

Ecuacion 1

+ 9.906 m + 0.3 B - 3.3253 B2

Ecuacion 2
0.7 B
-( 9.906 + 0.7 B - 3.33 B2 )

(a) (b) (c)


+ 3.3253 B2 + 0.7 B - 9.906 = 0

0.3 B Donde

X= - b +/- b2 + 4ac
2a

- 0.7 +/- 132.25


6.651
B= 1.62 m

REEMPLAZANDO SE TIENE:
Burden = B = 1.62 m
Espaciamiento = 1.25 B = 2.03 m
Volumen ( Rotura x Taladro ) = 12.38 B2 = 32.65 m3
Tonelaje = 46.43 B2 = 122.45 Ton/Tal
Libras de anfo = 18.57 B2 = 48.98 lib anfo/Talad HSQ

Altura de carga = 3.33 B2 = 8.77 m Pag 1


07/26/2017
18:05:25

COSTO DE PERFORACION EXP01

DATOS

Costo Broca + Accesorios = 215.22 US$ / Und Broca Botones RIM 12 4" =
Broca Rimadora 12 5" =
Costo equipo Perforacion = 12.50 US$ / Hr Broca Botones R32 51mm =
Broca Cruz R32 51mm =
Tiempo de Perforac. ( Rend. Broca ) = 80.00 Hr Broca Retractil R32 2-1/2" =
Adaptador Piloto T38 x 12 =
Rendimiento Broca = 762.00 m / broca Barra Extension SP R32 x 5 =
Barra SP T38 x 4' =
Ton / Taladro = 122.45 Ton / Taladro Shank 1238 T38 x 575 mm =
Shank AdapL400 R32x380 m =
Altura de banco = 9.91 m
Alquiler Jumbo =
Horas Prog. Perforacion =
Costo Jumbo =

Rendimiento Broca 51mm =


Shank R32 =
Barra R32 5' =
Adaptador =
Rimadora =

Costo Broca =
Shank R32 =
Barra =
Adaptador =
Rimadora =
CALCULO Total =

COSTO PERFORACION ( US$ / m ) = Costo Broca + Costo Equipo Perforac. x


Rendimiento Broca

= 215.22 US$ + 12.50 US$ x


Broca Hr
762.00 m
Broca

= 1,215.22
762.00

= 1.59 US$ / m

COSTO PERFORACION ( US$ / Ton ) = Costo Perforacion ( US$/m)


Ton x 1 Taladro
Taladro Altura Banco + SubDrilling
07/26/2017
18:05:26

1.59 US$
= m
122.45 Ton x 1 Taladro
Taladro 9.91 m
= 1.59
12.36

= 0.13 US$ / Ton


07/26/2017
18:05:26

315.00 US$
564.00 US$
74.04 US$
28.77 US$
141.50 US$
149.00 US$
138.00 US$
240.00 US$
275.00 US$
102.60 US$

9,000 US$/mes
24 Hrs/Dia
12.5 US$ / Hr

pp mp
2,500 762
2,825 861
3,542 1,080
7,910 2,411
7,910 2,411

74.04 US$
65.52 US$
52.26 US$
23.40 US$
US$
215.22 US$

Tiempo Perf.

80.00 Hr
07/26/2017
18:05:26

HSQ

Pag 2
07/26/2017
18:05:26

COSTO DE VOLADURA EXP01

DATOS

COSTO PRECIOS
Anfo = 0.21 US$ / Lib Examon 0.47 US$/Kg
Emulsion Semexa 65% 1-1/2" x 12" 0.59 US$/Cart
Dinamita = 0.13 US$ / Cartucho Dinamita semexa 65% 7/8" x 7" 0.13 US$/Cart
Cordon detonante 3P 0.12 US$/m
Retardos Fanel = 1.03 US$ / Unidad Carmex 7 0.45 US$/Pza
Fanel blanco 4 mts 1.04 US$/Pza
Cordon Detonante = 0.12 US$ / Pie Fanel rojo 4 mts 1.04 US$/Pza
Fanel standar rojo 8 m 1.50 US$/Pza
Camion Anfocar = 0.00 US$ / Hr Fanel standar rojo 15 m 2.20 US$/Pza
Fulminante # 8 0.08 US$/Pza
Chispeo = 0.08 US$ / Pie Guia de Seguridad 0.08 US$/m
Mecha rapida Ignic 0.26 US$/m
Mano de Obra = 2.00 US$ / Hr

Tonelaje = 122.45 Ton / Taladro

Pentacord Empleado en 1 Taladro [(H+E+0.3 B+B)+5%(H+E+0.3B+B)] = 14.24 m


= 46.71 pies

Tiempo Empleado en el Carguio de 1 Taladro Anfocar = 0.14 Hr

Mecha Seguridad Empleado en el Chispeo de 1 Taladro = 14.00 Pies

N De Hombres Empleado en el Carguio de 1 Taladro = 3.00 Hombres


Tiempo Empleado en el Carguio de 1 Taladro = 0.14 Hr/Tal

CALCULO
PU CONSUMO TOTAL

Anfo 0.21 US$ * 48.98 lib anfo = 10.29 US$ / Taladro


lib Taladro

Dinamita 0.13 US$ * 1.5 Cart. = 0.20 US$ / Taladro


Cart Taladro

Retardos 1.03 US$ * 1 Und = 1.03 US$ / Taladro


Und Taladro

Pentacord 0.12 US$ * 46.71 pies = 5.61 US$ / Taladro


pie

Camion 0.00 US$ * 0.14 Hr = 0.00 US$ / Taladro


Hr Taladro

Chispeo 0.08 US$ * 14 Pie = 1.12 US$ / Taladro


Pie

Mano de Obra 2.00 US$ * 0.4 Hr = 0.84 US$ / Taladro


Hr Taladro

TOTAL 19.09 US$ / Taladro

COSTO DE VOLADURA ( US$ / Ton ) = Costo de Voladura por Taladro


Ton / taladro

19.09US$
= Taladro
122.45 Ton
Taladro
GAYALA

= 0.156 US$/Ton Pag 3


07/26/2017
18:05:26

REQUERIMIENTO DE PERFORADORA EXP01

DATOS

Produccion mina = 1,451.67 TPD PRODUCCION


TPM = 43,550
Altura de Banco = 9.91 m Dias Operac = 30
TPD = 1,452
Longitud de Taladro = 9.91 m

Ton / Taladro = 122.45 Ton/taladro

Rendimiento Broca = 762.00 m/Broca

Tiempo Perforacion = 80.00 Hr

Horas Programadas = 530.00 Hr

Horas Trabajadas = 250.00 Hr

Eficiencia Perforadora = 0.47 %

CALCULO

N PERFORADORA = Produccion ( TPD )


Ton x Long Tal. x Rend.Broca x
Taladro Tiempo Perf

1,451.67 Ton
= dia
122.45 Ton x 1 Tal x 762.00 m x
Tal 9.91 m 80.00 Hr

= 1,451.67
1,332.93

= 1.09

= 1.1 Perforadoras

METROS PERFORADO (m/dia) = Produccion ( TPD )


Ton / Taladro

1,451.67 Ton
= Dia
122.45 Ton x 1 Tal
07/26/2017
18:05:26

Tal 9.91 m

= 1,451.67
12.36

= 117.4 m / dia

= 385.3 pies / dia


07/26/2017
18:05:26

43,550 Ton
30 Dias
1,452 Ton / Dia

Produccion ( TPD )
1 dia x Efic.Perf

24 Hr x 0.47
1 dia
07/26/2017
18:05:26

GAYALA

Pag 4
07/26/2017
18:05:26

CARGUIO EXP01

DATOS

Produccion Mineral = 1,451.67 TPD


Ratio D / M = 0.00 TPD
Produccion Desmonte = 0.00 TPD
Mineral + Desmonte = 1,451.67 TPD
Capacidad de Cuchara = 3.00 Yds3 / pase
Factor de Cuchara = 75.00 %
Densidad rota material = 2.70 Ton / m3
Tiempo De 1 Pase = 120.00 Seg / pase
Disponibilidad Mecanica = 80.00 %
Disponibilidad Operativa = 85.00 %
N de Horas por Guardia = 10.00 Hr / guardia
N Guardia por Dia = 2.00 guardias / dia
Costo por Hr del Equipo = 60.00 US$ / Hr

CALCULOS

TONELADA POR PASE ( SCOOP ) = Yds3 / Pase x Densid. rota x Factor Cuchara

= 3.00 Yds3 x 2.70 Ton x 0.765 m3 x 0.75


pase m3 1 yd3

= 4.65
1.00

= 4.65 Ton /pase

N DE PASES POR HORA = 1 Hr / Tiempo de 1 pase

60 min
= Hr
120.00 seg x 1 min
pase 60 seg

= 30 Pase / Hr

PRODUCCION ( Ton / Hr ) = Ton / Pase x Pases / Hr x Disponib.Mecanica x Disponib.Operativa

= 4.65 Ton x 30 Pase x 0.8 x 0.85


Pase Hr

= 94.81 Ton / Hr

PRODUCCION ( Ton / Dia ) = Produccion ( Ton / Hr ) x ( Hr / Guardia ) x ( N guardia / dia )

= 94.81 Ton x 10.00 Hr x 2.00 grd


Hr grd dia

= 1,896.13 Ton / dia

REQUERIMIENTO DE SCOOP = ( Material Ton / dia ) / ( Produccion Ton / dia )

= 1,451.67 Ton / dia


1,896.13 Ton / dia

= 0.8 Scoop

COSTO DE CARGUIO ( US$ / Ton ) = ( Costo por Hr del Equipo ) / ( Produccion Ton / Hr )

60.00 US$
= Hr
94.81 Ton
Hr
GAYALA
= 0.63 US$/Ton Pag 5
07/26/2017
18:05:26

LIMPIEZA EXP01

DATOS

Produccion Mineral = 1,451.67 TPD


Produccion Desmonte = 0.00 TPD
Mineral + Desmonte = 1,451.67 TPD
Capacidad de Cuchara = 5.00 Yds3 / pase
Factor de Cuchara = 75.00 %
Densidad rota material = 2.70 Ton / m3
Tiempo De 1 Pase (viaje) = 480.00 Seg / pase
Disponibilidad Mecanica = 80.00 %
Disponibilidad Operativa = 80.00 %
N de Horas por Guardia = 10.00 Hr / guardia
N Guardia por Dia = 2.00 guardias / dia
Costo por Hr del Equipo = 60.00 US$ / Hr

CALCULOS

TONELADA POR PASE ( SCOOP ) = Yds3 / Pase x Densid. rota x Factor Cuchara

= 5.00 Yds3 x 2.70 Ton x 0.765 m3 x 0.75


pase m3 1 yd3

= 7.75
1.00

= 7.75 Ton /pase

N DE PASES POR HORA = 1 Hr / Tiempo de 1 pase

60 min
= Hr
480.00 seg x 1 min
pase 60 seg

= 7.5 Pase / Hr

PRODUCCION ( Ton / Hr ) = Ton / Pase x Pases / Hr x Disponib.Mecanica x Disponib.Operativa

= 7.75 Ton x 7.5 Pase x 0.8 x 0.8


Pase Hr

= 37.18 Ton / Hr

PRODUCCION ( Ton / Dia ) = Produccion ( Ton / Hr ) x ( Hr / Guardia ) x ( N guardia / dia )

= 37.18 Ton x 10.00 Hr x 2.00 grd


Hr grd dia

= 743.58 Ton / dia

REQUERIMIENTO DE SCOOPS = ( Material Ton / dia ) / ( Produccion Ton / dia )

= 1,451.67 Ton / dia


743.58 Ton / dia

= 1.95 Scoop

COSTO DE LIMPIEZA ( US$ / Ton ) = ( Costo por Hr del Equipo ) / ( Produccion Ton / Hr )

60.00 US$
= Hr
37.18 Ton
Hr
GAYALA
= 1.61 US$/Ton Pag 6
07/26/2017
18:05:26

TRANSPORTE EXP01

DATOS

Capacidad de camion = 30.00 Ton


Eficiencia de llenado = 95.00 %
Tiempo de Acarreo = 10.00 min
Tiempo de Retorno = 8.00 min
Tiempo de Giro y Descarga = 2.00 min
Tiempo para Cargarse = 2.00 min
Ciclo de Camion = 22.00 min
Disponibilidad Operativa Camion = 85.00 %
Disponibilidad Mecanica Camion = 80.00 %
Requerimiento de Scoop = 0.77 Scoop
Costo Hr de Camion = 60.00 US$ / Hr
Costo Mantenimiento Camion = 0.00 US$ / Hr
Tiempo Carguio Camion ( Tolva ) = 5.00 Minutos

CALCULOS

CICLO TOTAL DE UN CAMION = Tiempo de Carguio Camion + Ciclo Camion

= 5.00 min + 22.00 min

= 27.00 min

N DE VIAJES POR Hr CAMION = 1 Hr / Ciclo Total camion

60 min
= Hr
27.00 min
viaje

= 2.22 Viaje / Hr

PRODUCCION DE 1 CAMION = N de Viajes x Cap.Camion x Efic.Camion x Disp.Ope x Disp. Mec.

= 2.22 viaje x 30 Ton x 0.95 x 0.85 x 0.8


Hr viaje

= 43.1 Ton / Hr

N CAMIONES POR TOLVA = Ciclo total de Camion / Tiempo Carguio Camion

= 27.00 min
5.00 min

= 5.4 Camiones

FLOTA DE CAMIONES = N de camiones por Pala x N Palas + 20 % Stand By de # Camiones

= 5.4 Camio x 0.77 palas + 0.2 x 4.134 Camiones


pala

= 5.0 Camiones

= 4 Camiones en Operacion
1 Camiones en Stand By

PRODUCCION DE FLOTA DE CAMIONES = N de Camiones x Porduccion Camion por Hr

= 4 camio x 43.1 Ton


Hr

= 178.05 Ton / Hr

COSTO DE TRANSPORTE ( US$ / Ton ) = N de Camiones x Costo Hr camion + Costo Mant. N Camiones Sd-by
Produccion Camion Ton/ Hr

4 Cami x 60 US$ + 1 x 0 US$


= Hr Hr
178 Ton
Hr
GAYALA
= 1.39 US$ / Ton Pag 7
07/26/2017
18:05:26

RELLENO CEMENTADO EXP01

DATOS

Produccion Mineral = 1,451.67 TPD


Produccion Relleno = 392.34 m3
Capacidad de Cuchara = 3.00 Yds3 / pase
Factor de Cuchara = 75.00 %
Densidad rota material Relleno = 2.00 Ton / m3
Tiempo De 1 Pase ( viaje ) = 480.00 Seg / pase
Disponibilidad Mecanica = 80.00 %
Disponibilidad Operativa = 80.00 %
N de Horas por Guardia = 10.00 Hr / guardia
N Guardia por Dia = 2.00 guardias / dia
Costo por Hr del Equipo = 60.00 US$ / Hr
Densidad de Mineral = 3.70 Ton / m3

CALCULOS

TONELADA POR PASE ( SCOOP ) = Yds3 / Pase x Densid. rota x Factor Cuchara

= 3.00 Yds3 x 2.00 Ton x 0.765 m3 x 0.75


pase m3 1 yd3

= 3.44
1.00

= 3.44 Ton /pase

N DE PASES POR HORA = 1 Hr / Tiempo de 1 pase

60 min
= Hr
480.00 seg x 1 min
pase 60 seg

= 7.5 Pase / Hr

PRODUCCION ( Ton / Hr ) = Ton / Pase x Pases / Hr x Disponib.Mecanica x Disponib.Operativa

= 3.44 Ton x 7.5 Pase x 0.8 x 0.8


Pase Hr

= 16.52 Ton / Hr

PRODUCCION ( Ton / Dia ) = Produccion ( Ton / Hr ) x ( Hr / Guardia ) x ( N guardia / dia )

= 16.52 Ton x 10.00 Hr x 2.00 grd


Hr grd dia

= 330.48 Ton / dia

REQUERIMIENTO DE SCOOP = ( Material Ton / dia ) / ( Produccion Ton / dia )

= 392.34 Ton / dia


330.48 Ton / dia

= 1.2 Scoop

COSTO DE TRANSPORTE ( US$ / Ton ) = ( Costo por Hr del Equipo ) / ( Produccion Ton / Hr )

60.00 US$
= Hr
16.52 Ton
Hr

= 3.63 US$/Ton

COSTO MATERIAL RELLENO ( US$/Ton ) = Costo de preparacion relleno / densidad de mineral

Costo Preparacion Agregados Zarandeados = 2.50 US$ / m3


Costo Preparacion Planta de Concreto = 1.47 US$ / m3
Costo Transporte Relleno a Chupa = 2.60 US$ / m3
Costo Consumo Cemento (3.5% = 90 kg/m3) = 10.80 US$ / m3
Total = 17.37 US$ / m3

= 4.69 US$/Ton

COSTO TOTAL RELLENO 3.5% ( US$ / Ton ) = 8.33 US$/Ton

COSTO MATERIAL RELLENO ( US$/Ton ) = Costo de preparacion relleno / densidad de mineral

Costo Preparacion Agregados Zarandeados = 2.50 US$ / m3


Costo Preparacion Planta de Concreto = 1.47 US$ / m3
Costo Transporte Relleno a Chupa = 2.60 US$ / m3
Costo Consumo Cemento (3% = 78 kg/m3) = 9.60 US$ / m3
Total = 16.17 US$ / m3

= 4.37 US$/Ton

COSTO TOTAL RELLENO 3.0% ( US$ / Ton ) = 8.00 US$/Ton

HSQ

Pag 8
07/26/2017
18:05:26

RELLENO DETRITICO EXP01

DATOS

Produccion Mineral = 1,451.67 TPD


Produccion Relleno = 414.76 m3
Capacidad de Cuchara = 3.00 Yds3 / pase
Factor de Cuchara = 75.00 %
Densidad rota material Relleno = 3.00 Ton / m3
Tiempo De 1 Pase ( viaje ) = 480.00 Seg / pase
Disponibilidad Mecanica = 83.00 %
Disponibilidad Operativa = 85.00 %
N de Horas por Guardia = 10.00 Hr / guardia
N Guardia por Dia = 2.00 guardias / dia
Costo por Hr del Equipo = 60.00 US$ / Hr
Densidad de Mineral = 3.50 Ton / m3

CALCULOS

TONELADA POR PASE ( SCOOP ) = Yds3 / Pase x Densid. rota x Factor Cuchara

= 3.00 Yds3 x 3.00 Ton x 0.765 m3 x 0.75


pase m3 1 yd3

= 5.16
1.00

= 5.16 Ton /pase

N DE PASES POR HORA = 1 Hr / Tiempo de 1 pase

60 min
= Hr
480.00 seg x 1 min
pase 60 seg

= 7.5 Pase / Hr

PRODUCCION ( Ton / Hr ) = Ton / Pase x Pases / Hr x Disponib.Mecanica x Disponib.Operativa

= 5.16 Ton x 7.5 Pase x 0.83 x 0.85


Pase Hr

= 27.32 Ton / Hr

PRODUCCION ( Ton / Dia ) = Produccion ( Ton / Hr ) x ( Hr / Guardia ) x ( N guardia / dia )

= 27.32 Ton x 10.00 Hr x 2.00 grd


Hr grd dia

= 546.45 Ton / dia

REQUERIMIENTO DE SCOOP = ( Material Ton / dia ) / ( Produccion Ton / dia )

= 414.76 Ton / dia


546.45 Ton / dia

= 0.8 Scoop

COSTO DE TRANSPORTE ( US$ / Ton ) = ( Costo por Hr del Equipo ) / ( Produccion Ton / Hr )

60.00 US$
= Hr
27.32 Ton
Hr

= 2.20 US$/Ton

COSTO MATERIAL RELLENO ( US$/Ton ) = Costo de preparacion relleno / densidad de mineral

Costo Preparacion Agregados Zarandeados = US$ / m3


Costo Transporte de Desmonte = 1.75 US$ / m3
Total = 1.75 US$ / m3

= 0.50 US$/Ton

GAYALA
COSTO TOTAL RELLENO ( US$ / Ton ) = 2.70 US$/Ton Pag 9
07/26/2017
18:05:26

PRODUCCION Y COSTOS EXP01

MALLA DE PERFORACION

Burden = 1.62 m

Espaciamiento = 2.03 m

Volumen ( Rotura x Taladro ) = 32.65 m3

Tonelaje = 122.45 Ton/Tal

Libras de anfo = 48.98 lib anfo/Talad


Altura de carga = 8.77 m

PERFORACION

COSTO PERFORACION ( US$ / m ) = 1.59 US$ / m

COSTO PERFORACION ( US$ / Ton ) = 0.13 US$ / Ton

N PERFORADORA = 1.09 Perforadoras

METROS PERFORADO (m/dia) = 117.44 m / dia

VOLADURA

COSTO DE VOLADURA ( US$ / Ton ) = 0.16 US$/Ton

LIMPIEZA

REQUERIMIENTO DE SCOOPS = 1.95 Scoop

COSTO DE LIMPIEZA ( US$ / Ton ) = 1.61 US$/Ton

CARGUIO

REQUERIMIENTO DE SCOOP = 0.77 Scoop

COSTO DE CARGUIO ( US$ / Ton ) = 0.63 US$/Ton

TRANSPORTE

FLOTA DE CAMIONES = 4.13 Camiones en Operacion

PRODUCCION DE FLOTA DE CAMIONES = 178.05 Ton / Hr

COSTO DE TRANSPORTE ( US$ / Ton ) = 1.39 US$ / Ton

RELLENO CEMENTADO

COSTO DE TRANSPORTE ( US$ / Ton ) = 3.63 US$/Ton

COSTO MATERIAL RELLENO ( US$/Ton ) = 4.69 US$/Ton

COSTO TOTAL RELLENO 3.5% ( US$ / Ton ) = 8.33 US$/Ton Minado Hz

COSTO TOTAL RELLENO 3.0% ( US$ / Ton ) = 8.00 US$/Ton Minado Vt

RELLENO DETRITICO

COSTO DE TRANSPORTE ( US$ / Ton ) = US$/Ton

COSTO MATERIAL RELLENO ( US$/Ton ) = US$/Ton

COSTO TOTAL RELLENO ( US$ / Ton ) = US$/Ton

COSTO MINADO PROYECTADO ( US$ / Ton ) 11.82 US$ / Ton

COSTO MINADO ( US$ / Ton ) = 12.25 US$ / Ton

GAYALA
Pag 10
REQUERIMIENTO EQUIPOS EXP01 PRODUCCION

N PERFORADORA = 1.09 Perforadoras

REQUERIMIENTO DE SCOOPS LIMPIEZA = 1.95 Scoop

REQUERIMIENTO DE SCOOPS CARGUIO = 0.77 Scoop

REQUERIMIENTO DE SCOOP RELLENO = 1.19 Scoop

TOTAL SCOOPS = 3.91 Scoop

FLOTA DE CAMIONES TRANSPORTE = 4.13 Camiones en Operacion

REQUERIMIENTO VENTILADORES =

REQUERIMIENTO DE BOMBAS =