Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
together. Before closing the joints, the flanges must be parallel to each other, with all
bolts inserted in the bolt holes. After the fittings have thus been aligned and well
supported, the joint shall be bolted up to a uniform tightness using torque wrenches to
achieve the required compression force on the gasket. Diagonally opposing bolts shall
be tightened sequentially.
If and where full face gaskets are used, the jointing material shall be flush with, or
protrude beyond, the outer circumference of the flange (this in not applicable to raised
face flanges). On completion of the joint, the flanges and bolts shall be protected as
described in Clause PSL 3.9.3.8.
PSL 5.2.3 Welding (Steel Pipelines DN 600 or Greater)
Delete the title and replace with Welding (Steel Pipelines).
st
Delete the 1 sentence and replace with:
Field welding of steel pipelines shall be carried out in accordance with the relevant
requirements of the latest version of API 1104. The Contractor, prior to
commencement of welding, shall produce a qualified welding procedure in
accordance with the latest version of API 1104, for the intended sizes, processes,
positions and consumables to be used on this project.
Welding shall be carried out by welders who are competent in terms of the procedure
approval test given in API 1104. Prior to commencement of welding, the current
qualification of each welder must be produced in accordance with the welding
procedure. Should constant repairs be required on welds carried out by one particular
welder, the Engineer may request that the welder be re-tested or removed from the
project.
Add to the Sub-clause:
Examination of Welds
The Contractor shall include in his prices for the manufacture of pipes, bends, fittings
and specials for the cost of carrying out, under the supervision of the inspector
appointed by the Employer, examination of shop welds on the following basis:
(a) Manufacture of Pipes (Not applicable to pipes supplied by the Employer)
i) FIVE percent random radiographic examination of all welds deposited by an
approved automatic process.
ii) TEN percent random radiographic examination of all welds deposited
manually or semi-automatically, and repairs to welds done by an automatic process
(should repairs exceed 25% of the tests the percentage of examination shall be
increased to 20%).
(b) Field Welds
Radiographic testing will be performed on butt welds and dye penetrant testing on
fillet welds. Welds will be tested and adjudicated in accordance with API 1104
and will be tested with the following frequencies:
The first 10 welds executed by each Welder will be tested. Thereafter, if no
discontinuities are discovered, 10% of his/her further welds, chosen at random by the
Engineer, will be tested. If during the 10% testing, discontinuities are discovered both
welds immediately adjacent to the defective weld will be tested. If these joints are
found acceptable testing will remain at 10%. If, however, defective welds continue to
be evident, testing will be increased to 100%. Only once the welding has returned to
an acceptable standard and at the discretion of the Engineer, will the percentage be
reduced again.