NARRATVE REPORT

[REPORT SUBTITLE]
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

TABLE OF CONTENTS
I. TITLE PAGE
II. TABLE OF CONTENTS
III. DEDICATION
IV. ACKNOWLEDGEMENT
V. INTRODUCTION
VI. COMPANY PROFILE
PULSAR CONSTRUCTION HISTORY
PULSAR VISION AND MISSION
PULSAR ORAGANIZATION CHART
VII. NARRATIVE REPORT
DAILY ACCOMPLISHMENT REPORT
NARRATIVE REPORT ON WEEKLY
ACTIVITIES
LEARNINGS
VIII. APPENDICES
EVALUATION SHEET
CERTIFICATE OF On-the-Job-Training
DAILY TIME RECORD
LETTERS, WAIVER AND MEMORANDUM
OF AGREEMENT

PAGE 1
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DEDICATION

I dedicate my narrative report to my family, my ever-supporting parents,

thank you for your financiaI support, trust, love and care for me.

Also dedicate this to our respective adviser Engr. Stiler and to Engr. John

Michael B. Casibang (Chairmain of Civil Engineering). Ive learned a lot from

you on how to perform the standard ways, how to be a responsible OJT student

trainee, and for the assurance of the document needed for the OJT.

To Pulsar Construction, all supervising and staff. To my co trainees and above

all to almighty God, thank you for the guidance, strength, power of mind,

protection, and skills and for giving me a healthy life.

PAGE 2
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

ACKNOWLEDGEMENT
I want to give an overwhelming thanks and acknowledgement to all people who helped
me in accomplishing my On-the Job Training and with all gratefulness.

To the Lord Almighty for the wealth and vitality and for enlightens me to pursue my
study.

PAGE 3
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

INTRODUCTION

On the job Training are part of a college curriculum that aims to train and orient students

about the work and their future career. OJT is very important not only to teach students

their chosen career but to show students the reality about working.

As one of the 4th year students that have undertaken the course in Civil Engineering.it

was a very special opportunity for me to put my academic training experience into a

real world application. The course has provided me the venue to further enhance and

broaden my knowledge and competency as a civil engineering student and for future

career objectives after graduation. As a student trainee, I have been able to take

advantage of the tools and skills I have been equipped by my intensive academic

formation in the university, to be competent enough in pursuing different

opportunities available in the outside world.

PAGE 4
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY ACCOMPLISHMENT REPORT

DAY 1:

Date: June 19, 2017

Time in: 7:00 am

Time out: 5:00pm

PROJECT TITLE: Road Widening

LOCATION: Larion, Tuguegarao City

SUPERVISOR: Engr. Myrda Matalang

ACTIVITIES:

Orientation

Base Preparation

Measuring of Retaining Wall

Description of Activities:

This is the first day of our On-The-Job Training (OJT). Before we assigned to our
designated sites, Engr. Uno (Head bababa) oriented us about the company rules and
regulations. Even the Dos and Donts are discussed to. He also introduced us to our supervisor
Engr. Myrda Matalang. My group was assigned at Larion Widening. After the introduction, to
start with our work, Engr. Myrda oriented us about the project. She tasked us to measure the
height and length of the finish retaining. After the She discussed about the design of the
retaining wall. In the afternoon we observed road base preparation at Larion near four diamond
resort. Our first day was very good start and we was motivated.

Lesson learn:

We learned how to design a retaining wall


PAGE 5
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY ACCOMPLISHMENT REPORT

DAY 2:

Date: June 20, 2017

Time in: 7:00 am

Time out: 5:00pm

PROJECT TITLE: Road Widening

LOCATION: Larion, Tuguegarao City

SUPERVISOR: Engr. Myrda Matalang

ACTIVITIES:

Compaction

FDT (Field Density Test)

Concrete Pouring

Description of Activities:

DPWH engineers arrived at the site for inspection. Before concrete pouring, we
conducted Field Density Test (FDT). FDT to determine the moisture content of the soil before
pouring. As we perform FDT one DPWH engineer discussed us about FDT, and its important,
He also lectured us about the different equipment and tools used in road constructions.
Concrete pouring started at 10:00 AM. Engr. Myrda assigned us to get some concrete sample,
Samples were placed in a beam mold. The beam mold is used to prepare concrete specimen for
flexural testing of concrete. Available in a 20 in. length with a cross-section of 6x6 inches. We
also helped in spraying curing compound. We also help Engr. Mydra to measure the finished
widening and record the length and station for their accomplishment report.

Lesson learned:

The process of road widening


How to performed Field Density Test
How to performed and get concrete sample

PAGE 6
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY ACCOMPLISHMENT REPORT

DAY 3:

Date: June 21, 2017

Time in: 7:00 am

Time out: 5:00pm

PROJECT TITLE: Road Widening

LOCATION: Larion, Tuguegarao City

SUPERVISOR: Engr. Myrda Matalang

ACTIVITIES:

Continuation of Concrete Pouring

FDT

Booming

Spraying Curing Compound

Description of Activities:

We continued concrete pouring located at larion near camella tuguegarao. We measure


the spacing of tie bars and dowels. As the process of road widening we conducted first FDT but
we only get one sample. Then during the concrete pouring we get concrete samples. We also
helped in spraying cuing compound.

Lesson learned:

The process of road widening


How to performed Field Density Test
How to performed and get concrete sample

PAGE 7
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY ACCOMPLISHMENT REPORT

DAY 4:

Date: June 22, 2017

Time in: 7:00 am

Time out: 5:00pm

PROJECT TITLE: Road Widening

LOCATION: Larion, Tuguegarao City

SUPERVISOR: Engr. Myrda Matalang

ACTIVITIES:

Continuation of Concrete Pouring

FDT

Booming

Spraying Curing Compound

Description of Activities:

Lesson learned:

The process of road widening


How to performed Field Density Test
How to performed and get concrete sample

PAGE 8
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY ACCOMPLISHMENT REPORT

DAY 5:

Date: June 23, 2017

Time in: 7:00 am

Time out: 5:00pm

PROJECT TITLE: Road Widening

LOCATION: Larion, Tuguegarao City

SUPERVISOR: Engr. Myrda Matalang

ACTIVITIES:

Continuation of Concrete Pouring

FDT

Booming

Spraying Curing Compound

Description of Activities:

Lesson learned:

The process of road widening


How to performed Field Density Test
How to performed and get concrete sample

DAILY ACCOMPLISHMENT REPORT

PAGE 9
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAY 6:

Date: June 24, 2017

Time in: 7:00 am

Time out: 5:00pm

PROJECT TITLE: Road Widening

LOCATION: Larion, Tuguegarao City

SUPERVISOR: Engr. Myrda Matalang

ACTIVITIES:

Continuation of Concrete Pouring

FDT

Booming

Spraying Curing Compound

Description of Activities:

Lesson learned:

The process of road widening


How to performed Field Density Test
How to performed and get concrete sample

PAGE 10
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY WORK ACTIVITIES

WEEK 1

DAY DATE DAILY ACTIVITIES NO OF WORKING


HOURS
MONDAY JUNE 19,2017 Road Base preparation (Compaction) 9

TUESDAY JUNE 20,2017

WEDNESDAY JUNE 21,2017

THURSDAY JUNE 22,2017

FRIDAY JUNE 23,2017

SATURDAY JUNE 24,20177 Road Base preparation and


installation of forms

Week 1

The Pulsar Construction assigned our group in Camasi, Penablanca which the
project is road widening. Engr. Myrda and Engr. Rose Ann are the project supervisors,
they orient us with the project which there are different sections; the bridge in Camasi,
the road widening in Caggay and in Larion. Our group was assigned in Caggay for the
whole week. The activities in our first day is the preparation for road widening. We
observed how they prepare for the road. and We measure the depth or the road which is
0.4 meters. The road consist of 0.3 m concrete and 0.1 m item 201( ). There are some
problems in the project which is an existing road and drainage. But the slightly serious
problem is the water line system beneath the road. More than 8 water pipes has been
damaged when they are excavating, 1 main line was damaged and in this situation Engr.
Rose Ann give us some tips on how to manage this problems.

Our second day was tiring yet exciting. Engr. Rose Ann and Engr. Myrda let our
group observed the pouring concrete in the road widening of Larion.

PAGE 11
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY ACCOMPLISHMENT REPORT

DAY 1:

Date: June 26, 2017

Time in: 7:00 am

Time out: 5:00pm

PROJECT TITLE: Ballroom/Hotel

SUPERVISOR: Engr. John Jarvis Guzman

LOCATION: Pulsar Hotel, Caggay, Tuguegarao City

ACTIVITIES:

Orientation

Removing concrete sample

Site inspection

Description of Activities:

My group were assigned at Pulsar Hotel, Caggay, Tuguegarao City for six days. The
project is construction of ballroom and Hotel owned by Jojo Lasam Lara. Engr. John Jarvis
Guzman is our supervisor this week. He oriented us about the project and showed the
architectural and structural plan of the project. Before we went to the site for visitation, he
assigned us to removed the concrete sample from the cylindrical mold. Then we submerged the
sample into the water for curing.

In the afternoon Engr. Jarvis accompanied us to the site for site inspection. We asked question
about what observed at the site, we learned a lot that day.

Lesson Learned:

PAGE 12
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY ACCOMPLISHMENT REPORT

DAY 2:

Date: June 27, 2017

Time in: 7:00 am

Time out: 5:00pm

PROJECT TITLE: Ballroom/Hotel

SUPERVISOR: Engr. John Jarvis Guzman

LOCATION: Pulsar Hotel, Caggay, Tuguegarao City

ACTIVITIES:

Installation of tire wire

Mearusing slab

Estimation of concrete

Description of Activities:

Engr. Jarvis assigned us to compute the volume of concrete to the un fineshed slap at
ballroom mezanime. We do it in actual measurement, after we measured slab we estimated
how many cubic meter to be pour at that area. We noticed that some of the reinforcement were
not tie, so we helped the workers. And in the afternoon we joined their meeting.

Lesson Learned:

PAGE 13
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY ACCOMPLISHMENT REPORT

DAY 3:

Date: June 28, 2017

Time in: 7:00 am

Time out: 5:00pm

PROJECT TITLE: Ballroom/Hotel

SUPERVISOR: Engr. John Jarvis Guzman

LOCATION: Pulsar Hotel, Caggay, Tuguegarao City

ACTIVITIES:

Estimation

Description of Activities:

Engr. Jessi Mercader assigned us to compute the number of stirrup at hotel level 6.
Engr. Jarvis

PAGE 14
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY WORK ACTIVITIES

WEEK 2

DAY DATE DAILY ACTIVITIES NO OF WORKING


HOURS
MONDAY JUNE 26,2017 Road Base preparation (Compaction) 9

TUESDAY JUNE 27,2017

WEDNESDAY JUNE 28,2017

THURSDAY JUNE 29,2017

FRIDAY JUNE 30,2017

SATURDAY JULY 01,20177 Road Base preparation and


installation of forms

PAGE 15
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY ACCOMPLISHMENT REPORT

DAY 13

DATE: JULY 03, 2017

TIME IN: 7:00 AM

TIME OUT: 7:00 PM

SUPERVISOR: Engr. John Jarvis Guzman

LOCATION: Pulsar Hotel, Caggay, Tuguegarao City

ACTIVITIES:

Orientation

DESCRIPTION OF ACTIVITIES

PAGE 16
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY ACCOMPLISHMENT REPORT

DAY 14

DATE: JULY 04, 2017

TIME IN: 7:00 AM

TIME OUT: 5:00 PM

SUPERVISOR: Engr. John Jarvis Guzman

LOCATION: Pulsar Hotel, Caggay, Tuguegarao City

ACTIVITIES:

Orientation

DESCRIPTION OF ACTIVITIES

PAGE 17
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY ACCOMPLISHMENT REPORT

DAY 15

DATE: JULY 05, 2017

TIME IN: 7:00 AM

TIME OUT: 5:00 PM

SUPERVISOR: Engr. John Jarvis Guzman

LOCATION: Pulsar Hotel, Caggay, Tuguegarao City

ACTIVITIES:

Orientation

DESCRIPTION OF ACTIVITIES

PAGE 18
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY ACCOMPLISHMENT REPORT

DAY 16

DATE: JULY 06, 2017

TIME IN: 7:00 AM

TIME OUT: 5:00 PM

SUPERVISOR: Engr. John Jarvis Guzman

LOCATION: Pulsar Hotel, Caggay, Tuguegarao City

ACTIVITIES:

Orientation

DESCRIPTION OF ACTIVITIES

PAGE 19
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY ACCOMPLISHMENT REPORT

DAY 17

DATE: JULY 07, 2017

TIME IN: 7:00 AM

TIME OUT: 5:00 PM

SUPERVISOR: Engr. John Jarvis Guzman

LOCATION: Pulsar Hotel, Caggay, Tuguegarao City

ACTIVITIES:

Orientation

DESCRIPTION OF ACTIVITIES

PAGE 20
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY ACCOMPLISHMENT REPORT

DAY 18

DATE: JULY 08, 2017

TIME IN: 7:00 AM

TIME OUT: 5:00 PM

SUPERVISOR: Engr. John Jarvis Guzman

LOCATION: Pulsar Hotel, Caggay, Tuguegarao City

ACTIVITIES:

Orientation

DESCRIPTION OF ACTIVITIES

PAGE 21
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY WORK ACTIVITIES

WEEK 3

DAY DATE DAILY ACTIVITIES NO OF WORKING


HOURS
MONDAY JULY 03,2017 9

TUESDAY JULY 04,2017

WEDNESDAY JULY 05,2017

THURSDAY JULY 06,2017

FRIDAY JULY 07,2017

SATURDAY JULY 08,20177

PAGE 22
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY ACCOMPLISHMENT REPORT

DAY 19

DATE: JULY 10, 2017

TIME IN: 7:00 AM

TIME OUT: 5:00 PM

SUPERVISOR: Engr. Marlon

Engr. Ed Visaya

LOCATION: Namabbalan Sur, Tuguegarao City

ACTIVITIES:

Orientation

DESCRIPTION OF ACTIVITIES

PAGE 23
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY ACCOMPLISHMENT REPORT

DAY 20

DATE: JULY 11, 2017

TIME IN: 7:00 AM

TIME OUT: 5:00 PM

SUPERVISOR: Engr. Marlon

Engr. Ed Visaya

LOCATION: Namabbalan Sur, Tuguegarao City

ACTIVITIES:

Orientation

DESCRIPTION OF ACTIVITIES

PAGE 24
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY ACCOMPLISHMENT REPORT

DAY 21

DATE: JULY 12, 2017

TIME IN: 7:00 AM

TIME OUT: 5:00 PM

SUPERVISOR: Engr. Marlon

Engr. Ed Visaya

LOCATION: Namabbalan Sur, Tuguegarao City

ACTIVITIES:

Orientation

DESCRIPTION OF ACTIVITIES

PAGE 25
Republic of the Philippines
Cagayan State University
CARIG CAMPUS
COLLEGE of ENGINEERING CIVIL ENGINEERING DEPARTMENT

DAILY WORK ACTIVITIES

WEEK 4

DAY DATE DAILY ACTIVITIES NO OF WORKING


HOURS
MONDAY JULY 10,2017 Road Base preparation (Compaction) 9

TUESDAY JULY 11,2017

WEDNESDAY JULY 12,2017

THURSDAY JULY 13,2017

FRIDAY JULY 14,2017

SATURDAY JULY 15,20177 Road Base preparation and installation of


forms

PAGE 26