Sei sulla pagina 1di 12

IPA, 2012 - 35th Annual Convention Proceedings, 2011

IPA11-E-071

PROCEEDINGS, INDONESIAN PETROLEUM ASSOCIATION


Thirty-Fifth Annual Convention & Exhibition, May 2011

DRILLING OPTIMIZATION USING MECHANICAL EARTH MODEL IN AN OVER-


PRESSURED FIELD IN EAST JAVA, INDONESIA: A CASE STUDY

M. Khawadja Kamaluddin*
Andi M. Adiwiarta*
Somesh Bahuguna**
Cicik Sukma Setya Wahyu**

ABSTRACT upcoming drilling activities in the field by


improving borehole stability,defining the pore
The Lengowangi field, located onshore East Java, pressure profile and by establishing the safe and
Indonesia was discovered in 2006. The main stable mud weight windows.
challenges in this area have been the over-pressured
Lower Ngrayong and Tuban formations. The first INTRODUCTION
well, L-1, was successfully drilled in 2006 and
currently produces up to 10 MMCFD. The second JOB Pertamina Petrochina East Java planned to
well, L-2, was drilled up-dip in 2008, but could not drill well L-3 in the Lengowangi field, located
reach the target because of well control issues onshore East Java. Figure 1 shows 2D and 3D views
related to high pore pressure. Well was TDd about of the offset wells and planned wells. L-3 was to be
2800 ft MD shorter than planned depth. drilled 10 m West of offset L-2, which is located
near the crest of the anticline. L-1 is located down-
The third well, L-3, was drilled as twin well near L- dip at the flank of Sekarkorong anticline, about 1.8
2. To optimize drilling the L-3 well, a detail km Northeast of well L-2. In order to optimize the
geomechanical evaluation study was conducted. drilling program, we conducted a recent drilling
The study utilized the drilling and log data gathered experience review and used all relevant logs,
in L-1 and L-2 and aimed to establish the cause of drilling and other data to understand the drilling
overpressure and define the pore pressure profile of problems in the offset wells.
the field. The study concluded that significant
overpressure exists in Lengowangi field. As overpressure is the main cause of wellbore
Subsequently, a Mechanical Earth Model was instability in the offset wells and the main source of
constructed for L-3 and safe and stable mud weight uncertainty in the planned well L-3, a Mechanical
windows were established. Earth Model (MEM) was constructed and a
wellbore stability analysis conducted in order to
L-3 was spud in early 2010 with study recommend the safe and stable mud weights for
recommendations taken into account for well drilling the proposed wellsafely and efficiently. In
designing and drilling. Postdrill analysis of L-3 November 2009, Schlumberger finalized a predrill
showed that pore pressure matched with the upper geomechanical study for well L-3.
limit of the predrill estimate. The highest pore
pressure estimated was 17.1 lbm/gal near the well The study was conducted in stages, with addition of
bottom. For drilling further, mud weight could not qualified and relevant data as and when available. A
be increased to recommended value of 17.4 lbm/gal representative predrill MEM for well L-3 was
due to drilling restrictions. constructed using data acquired in the two offset
Hence, some flows and connection gas were wells, L-1 and L-2. An MEM is a depth based
observed due to low overbalance. Drilling was representation of the rock elastic properties, rock
considered a success as well TDd close to plan strength, three principal geo-stresses and the pore
with improved borehole stability as compared to L- pressure of the subsurface referenced to the
1 and L-2. Mechanical Earth Model constructed for stratigraphic column. The input data includes sonic
Lengowangi field can now be used for optimizing log and other open hole logs e.g. density, porosity,
gamma ray, geological and petrophysical
* JOB Pertamina Petrochina East Java interpretations and drilling reports.
** Schlumberger
Well L-3 was drilled and completed in March 2010. Youngs Modulus, Poissons Ratio, Unconfined
Postdrill analysis of well L-3 was conducted and Compressive Strength (UCS) and geo-stress profile.
data acquired was used to update the wellbore Dipole shear sonic tool provides the required
stability evaluation analysis. compressional and shear slownesses.

The geomechanical study involved the following In wells L-1 and L-2, gamma ray, resistivity,
phases: density and neutron logs were available over most
of the interval. Noticeably, compressional slowness
Predrill data collection and review: Integrate data was absent over some sections in the offset
and analyze the existing relevant logs, drilling wells and shear slowness log was not available in
and other data from the offset wells, L-1 and L- the wells. This is because the sonic data was
2. acquired using Bore Hole Compensated sonic tool
Construction of predrill MEM: Determine stress (BHC) which, in general, gives poor acoustic data
magnitudes, stress orientations, pore pressures in bad boreholes and slow formations. In addition, it
and formation mechanical properties. cannot provide shear slowness measurement in slow
Calibration of the predrill MEM: Calibrate and formations. Hence, the shear slowness log was
refine the MEM, using calipers and drilling synthetically modelled using a lithology model
events to constrain and reduce the uncertainties derived from the formation evaluation package.
associated with limitations and availability of Basic petrophysical analysis produced volumetric
the existing data. lithology, porosity and fluid volumes. These
Wellbore stability analysis: Compute safe and volumes became part of the input data for
stable mud weight ranges to drill well L-3 that geomechanical modeling.
will minimize or avoid incidents, for example,
lost circulation, tight hole and wellbore Drilling events related to geomechanics were
collapse. extracted from drilling reports. This information
Postdrill data collection and review: Integrate helped in identifying and characterizing the drilling
and analyze the existing relevant logs, drilling problems experienced in the field. These drilling
and other data from well L-3. problems were then cross-referenced to the
Construction of postdrill MEM: Determine geomechanical study to highlight areas of concern,
stress magnitudes, stress orientation, pore to support and confirm findings and hypotheses
pressure profile and formation mechanical based on the geomechanical analysis, and to help
properties. understand root causes of observed instability or
drilling problems. The main events that occurred in
Calibration of the postdrill MEM: Calibrate and
offset wells, L-1 and L-2, were trip gas, kick/ pit
refine the MEM, using calipers and drilling
gain/ flows, gumbo and tight hole. This indicates
events to constrain and reduce the uncertainties
presence of overpressure and insufficient
associated with limitations and availability of
overbalance.
the existing data.
Predrill Mechanical Earth Model Construction
METHOD
The basic approach to geomechanical analysis is to
Predrill Data Collection and Review use the available data for interpretation of rock
strength, stress and pressure. The key is to ensure an
A very significant part of most geomechanics internally consistent approach, and the integration
projects consists of data gathering. Building a MEM and interpretation of all data. By examining the
involves integrating data from many different available data and understanding the key issues
sources in order to accurately describe the previously encountered in drilling, testing or
formations in terms of geomechanical attributes. production, we can focus efforts on specific issues
Key input data to a MEM includes compressional that will have the greatest impact on exploration and
and shear sonic slowness, bulk density, gamma ray, field development.
resistivity, hole caliper, petrophysical values
porosity and clay volume, drilling reports and other In analyzing geomechanics for a field, there are a
relevant data. Bulk density, compressional and series of steps that must be followed in order to
shear slownesses are essential log data for the fully grasp the quality of data and determine the
construction of a MEM. These logs are needed to amount of uncertainty in the conclusions that are
generate key rock mechanical parameters such as drawn from the data. Skipping or ignoring the
importance of any one of these steps can lead to and gas flows in well L-1 were corrected for
inconsistencies or poor assumptions in the results. buoyancy effect to estimate the upper limit of pore
Development of a MEM (Plumb et al., 2000) is pressure over the sands (prognosis) in well L-3.
essential in making the best use of field Table 1 shows the buoyancy computation which
geomechanics information. acted as upper limit of pore pressure estimate in the
up-dip L-3. Therefore, the change in pressure in the
Rock elastic properties represent the deformation continuous sand body will follow the gas gradient
behaviour of the rock. The stress-strain behaviour of (assumed to be 0.15 g/cc). Up-dip, this will yield
rock is dependent upon the type of rock. For higher pressure in the reservoirs compared to the
isotropic elastic materials, the stress-strain bounding shales. Buoyancy inclusion affects not
behaviour can be described by two parameters, only pore pressure in the particular sand, but also
typically Youngs modulus and Poissons ratio. the fracture gradient, stress magnitudes and
Rock elastic properties are basic inputs to the wellbore stability analysis. Figure 2 shows the pore
computation of rock strength and in-situ stresses. pressure estimate for planned well, L-3.
The static properties can be determined from the
stress-strain curves of laboratory compressive tests. Minimum horizontal stress direction was acquired
Dynamic elastic properties can be calculated if by analyzing breakouts in the resistivity image of a
compressional slowness and shear slowness are nearby well and was found to be about N 125o E.
available. Since compressional slowness data was Stress magnitudes cannot be measured directly but
absent over some sections in the offset wells and can be modeled or inferred from other
shear slowness log was not available, synthetic measurements or indications (e.g. deformation,
compressional and shear slowness logs were strain, pressure, failure etc.). Determining the
derived in order to get the complete data set. In this Minimum horizontal stress (h) is relatively
pre-drill study, rock elastic and strength properties straightforward if h is also the minimum principal
were constructed in offset well L-1 and was then stress, which was the case here. The horizontal
propagated to plan well L-3 along the correlation stress magnitudes were modeled using computed
markers. rock elastic properties generated earlier during the
MEM construction. A Poro-elastic Horizontal Strain
Wireline density logs were integrated with respect Model was used to compute the horizontal stresses.
to depth to compute the vertical or overburden This model required values of horizontal tectonic
stress in planned well, L-3. To estimate the density deformation (x and y) as input. Tectonic
over intervals of bad or missing data, for example, deformation cannot be measured directly but useful
above the top of logged interval, an exponential calibration data was available in the form of Leak-
curve that best fit the available log data was Off tests in several wells to provide estimates of the
extrapolated to ground surface. minimum principal stress at discrete depths. We
analyzed drilling events and borehole breakout and
Pore pressure can be measured directly in used our observations to iteratively update the
permeable zones. Pore pressure measurement from MEM. The anisotropy between the maximum and
Drillstem Test (DST) conducted at one depth minimum horizontal stress for planned well was
interval was available in well L-1. A continuous log small. Based on the modeling it was estimated that
estimate of Pore pressure was made using Eatons the stress regime corresponds to thrust (H > h >
method and it was calibrated using the DST data v).
and with pore pressure events reported during the
drilling of the well. The pore pressure in well L-2 Using the propagated MEM as described in the
could not be estimated by using logs because of previous section, wellbore stability analysis was
poor log quality. In this well, the mud weight was conducted for the well L-3. Figure 3 shows the mud
regularly increased to control high gas readings. weight stability plot for well L-3. Based on the mud
Hence, mud weight has been taken as an upper limit weight window generated for L-3,
of pore pressure estimate in well L-2. Since planned recommendations were made for upper and lower
well is up-dip of the offset wells, buoyancy limit of drilling mud weights. Since, there was a
correction has been applied to pore pressure possibility of high pore pressure in sand zones due
estimate. It was reasonably assumed, based on to buoyancy effect (red diamonds), upper bound
seismic profiles, that the planned well would be mud weight (red curve) were recommended in order
drilled through the same hydraulically continuous to avoid kicks. The synthetic image associated with
gas bearing sands as were the L-1 and L-2. Pore predicted wellbore failure for the given
pressure estimates based on connection gas, kicks, recommended mud weight range is plotted in Track
8. Some breakouts (borehole enlargements) were The pore pressure estimation in well L-3 was
observed over the depth of 620 ft 1400 ft MD, calculated using Eatons Method based on sonic log
mainly in the shale interval. These were expected to and was calibrated with pore pressure related
be minor and could be managed by good borehole events, for example, flows, connection gas etc.
cleaning practices. Based on real-time experiences Figure 5 shows pore pressure analysis for well L-3.
while drilling L-2, the mud weights were to be Pore pressure increased with depth across Ngrayong
adjusted within the recommended range. shale formation and reached its highest value of
17.1 lbm/gal in Tuban formation near the well TD.
Execution Since drill mud weight used was very close to pore
pressure and less than the recommended value,
Well L-3 was spud in January 2010. The main some flows and connection gas events were
drilling problem encountered in this well was the observed. Annular pressure was not recorded
over pressure in shale formation as predicted by the downhole, so a conservation estimate of Equivalent
predrill modelling. Over pressure events such as Circulating Density (ECD) is made by adding 3% to
kick, gain, connection gas and trip gas were the drill mud weight. Some partial and dynamic
observed mainly in the Lower Ngrayong and Tuban losses probably occurred due to high ECD which
formation. Mud weight was gradually increased was close to mud-loss gradient. As a comparison,
from 16 to 17.1 lbm/gal over this section but still predrill pore pressure and recommended mud
had to be kept lower than recommended value of weight are also plotted. Postdrill pore pressure
17.4 lbm/gal near the section. For drilling further, estimate shows a good match with predrill pore
mud weight could not be increased to recommended pressure upper limit estimate.
value due to drilling restrictions.
Figure 6 shows postdrill wellbore stability analysis
Postdrill Data Collection and Review for well L-3. The safe mud weight window
between the pore pressure gradient and the
Compressional and shear slowness was logged minimum horizontal stress gradient is less than 1
using Dipole Shear Sonic Imager*** (DSI) over the lbm/gal over the Tuban section. Mud weight used
7-in and 5-in cased hole. Noticeably, density was and the estimated ECD was also plotted. The well
logged only over 7-in cased hole which had an was drilled and completed close to plan TD with
interval of only 317 ft. Hence, data correction and much improved borehole stability compared to L-1
editing was required to obtain a complete data set and L-2.
for updating the MEM.

The frequent events that occurred in this well are CONCLUSIONS


flow, gain, trip gas, connection gas and kick, which
all reflect the presence of overpressure and Predrill and postdrill MEMs and wellbore stability
insufficient drill mud weight. Based on the Drilling models for well L-3 were generated and validated,
chronology summary (figure 4), overpressure events which include stress magnitudes and orientations,
(kick, connection gas and flow) were observed pore pressure and formation elastic and strength
mainly in the 7-in section. Dynamic and partial properties. The predrill study indicated a narrow
losses occurred primarily in the 5-in section, mud weight window based on assumption that
probably due to presence of carbonate streaks or targets were being drilled at an up-dip location
natural open fractures. Lost Circulation Mud (LCM) compared to offset well. The model gave drillers
was pumped to manage losses. enough inputs to optimize the casing depths and the
mud weights within reasonable uncertainty. While
Postdrill Mechanical Earth Model Construction drilling the well, the recommended mud weight was
used as a guide. Planned TD could not be reached
The postdrill Mechanical Earth Model was due to drilling restrictions as mud weight could not
constructed in order to update the predrill model. be increased up to recommended value. However,
The newly estimated elastic and rock strength the well could be drilled deeper than the offset well
properties differed from predrill estimate within the and penetrated its reservoir targets.
uncertainty range. For example, Poissons ratio was
about 0.05 higher than predrill estimate on average. The postdrill update of the MEM for well L-3
This is because predrill estimates were derived shows that over pressure related events like kicks,
using synthetic shear slowness from well L-1. flows occurred because drill mud weight was close
*** Schlumberger tool to the formation pressure. The mud weight could
not be increased because the safe drilling mud Eaton B., 1975, The Equation for Geopressure
weight window is less than 1 lbm/gal. Partial and Prediction from Well Logs, SPE 5544.
dynamic losses probably occurred while drilling
over carbonate streaks or over pre-existing fractures Fjaer E., Holt R. M., Horsrud P., Raaen A. M., and
which opened when the ECD came close or Risnes R., 1992, Petroleum Related Rock
exceeded the minimum horizontal stress gradient. Mechanics Developments in Petroleum Science, 33.

ACKNOWLEDGEMENT
Plumb R. A., 1994, Influence of Composition and
We would like to thank JOB Pertamina Petrochina Texture on the Failure Properties of Clastic Rocks,
East Java and Schlumberger for allowing us to SPE/ISRM 28022.
publish this work.

REFERENCES Plumb R. A., Edwards S., Pidcock G., and Lee, D.,
2000, The Mechanical Earth Model Concept and its
Bratton T., Bornemann T., Li Q., Plumb R., Rasmus Application to High-Risk Well Construction
J., and Krabbe H., 1999, Logging Interpretations: Projects, SPE 59128.
Proceedings of 40th SPWLA Symposium.
Chardac O., Murray D., Carnegie A., and Marsden TerraTek Inc., 1998, The Difference Between Static
J. R., A Proposed Data Acquisition Program for and Dynamic Mechanical Properties, TerraTek
Successful Geomechanics Projects, SPE 93182. Standard Publications.

TABLE 1

THE BUOYANCY POINTS WHICH ACT AS UPPER LIMIT OF PORE PRESSURE ESTIMATE
IN WELL L-3

Pressure gradient Pressure gradient
Type L-1 (ft TVD) L-3 (ft TVD)
(lbm/gal) (lbm/gal)
Connection Gas xx61 11.2 xx98 14.07
xx30 13.2 xx57 16.62
Kick xx28 13.6 xx53 16.64
xx98 14.1 xx23 16.92
xx13 12.81 xx40 16.14
Well Flow
xx65 13.07 xx90 16.27

L3 L2
L1

L1

L2 L3

Figure 1 - 2D and 3D view of the offset wells and planned well.


XXX
Overburden
Pressure

XXX

Upper estimate
Pore Pressure
XXX

XXX

Lower estimate Pore


Pressure
XXX

Pore Pressure
Buoyancy
XXX

XXX

Figure 2 - Pore pressure estimate in planned well L-3. The red diamonds define the gas buoyancy points at
well L-3 after applying gas buoyancy effect for key events in well L-1 (see Table 1). Green pore
pressure gradient curve defines the upper estimate pore pressure in well L-3.
L-2 Csg.
XXX

L-2
LOT

XXX

XXX

XXX Upper Limit MW


Lower Limit MW

XXX

PP Buoyancy
XXX

XXX

XXX

Figure 3 - Wellbore stability analysis in planned well L-3. Track 1 through 4 show formation name,
measured depth, litho-column and vertical depth. Track 5 shows computed stresses, pore
pressure and minimum horizontal stress direction. Track 6 shows computed rock strength (UCS
magenta curve, friction angle dark green curve, tensile strength blue curve), Poissons ratio
(light green curve). Track 7 shows mud weight window including following shaded areas: kick
(brown), shear failure or breakout (red), losses (blue) and breakdown (black). Recommended
lower bound mud weight is shown in light green curve, while recommended upper bound mud
weight is shown in red curve. Buoyancy points shown as red diamonds. LOT from well L-2
(magenta diamond) is also plotted. Track 8 shows synthetic failure image.
L3
DrillingChronology
Time(Date)
1/12/10 1/17/10
XXX 1/22/10 1/27/10
XXX 2/1/10 2/6/10
XXX 2/11/10 2/16/10
XXX 2/21/10 2/26/10
XXX 3/3/10 3/8/10
XXX
0
XXX UpperNgrayong 18
30" FIT@XXXft Depth(ft)
20" EMW13.12ppg Kick
17
XXX
500 PartialLoss
TightHole
16
XXX
1000 13.375" ConnectionGas
Kick@XXXftduring
Seriesof Flow
LOT@XXXft circulation 15
TripGas Flowduring
EMW18.09ppg TightHole@1780ft DynamicLoss
XXX
1500 pumpoutofhole
Gumbo 14 Slougingcutting
9.625" LOT@XXXft
@XXXft
Casing
MD(ft)

LOT@XXXft EMW21.63ppg
2000
XXX 13
EMW20.295ppg Gumbo
7"
Gain
12
2500
XXX Overpullduring Lower Overpull
reamandwash Ngrayong
FIT
down 11
XXX
3000 LOT
Tuban 10 TripGas

XXX MW
3500 SeriesofPartialLosses
5" 9
duringdrillinginto
formation
XXX
4000 8

Figure 4 - Drilling chronology for well L-3


400 us/ft 40

XXX 13 ppg 18

DTCO

Overburden
XXX

Drill MW

Recommended
MW

XXX
Post-drill PP

Pre-drill PP
Lower Limit

Pre-drill PP
XXX Upper Limit

Figure 5 - L-3 pore pressure estimation. Tracks 1 through 5 show formation name, TVD and casing points,
lithology and MD respectively. Track 6 shows compressional slowness (blue curve). The
postdrill pore pressure profile is shown in Track 7 as blue curve and it is calibrated with
connection gas (black diamond) and flow (green diamond) recorded in daily drilling report.
Predrill pore pressure lower limit (pink curve) and upper limit (dashed blue curve) are also
plotted as comparison. Yellow circle indicated some events during circulation.
XXX

NO DATA AVAILABLE

Estimated ECD

XXX

Drill MW Connection
Gas

Flow

XXX

Partial and
dynamic
losses

Figure 6 - Postdrill wellbore stability analysis for well L-3. Track 1through 4 show formation name,
measured depth and casing points, litho-column and vertical depth. Track 5 shows overburden
pressure (red curve), minimum (light green curve) and maximum (dark blue curve) horizontal
stress, pore pressure (light blue curve), and LOT (brown diamond). Track 6 shows computed
rock strength (UCS magenta curve, friction angle dark green curve, tensile strength blue
curve), Poissons ratio (dashed green curve). Track 7 shows mud weight window including
following shaded areas: kick (brown), shear failure or breakout (red), losses (blue) and
breakdown (black). Drill mud weight is shown in light green curve, while estimated ECD is
shown in dark green curve. Some unexpected breakdown (black shaded) were observed due to
spiky data. Track 8 shows synthetic failure image. Track 9 and 10 show drilling events recorded
by DDR.

Potrebbero piacerti anche