ID Task Task Name Duration Start Finish Predecessors

04 Jun '17 30 Jul '17 24 Sep '17


Mode W S T M F
1 PROPOSED CONDITIONAL 217 days Mon 04-09-17 Tue 03-07-18
ASSESSMENT AND STRUCTURAL
SURVEY FOR EXISTING WEST
WHARVES, KEMAMAN SUPPLY BASE,
TERENGGANU.
2 Start 0 days Mon 04-09-17 Mon 04-09-17 04-09
3 Prelim 37 days Mon 04-09-17 Tue 24-10-17
4 Prelim Item 30 days Mon 04-09-17 Fri 13-10-17 2
5 Survey Works 30 days Wed 13-09-17 Tue 24-10-17 4SS+7 days
6 Structural Repair to Damaged Pile 210 days Wed 13-09-17 Tue 03-07-18
7 Mob & Demob 7 days Wed 13-09-17 Thu 21-09-17 4SS+7 days
8 hacking Works 55 days Fri 22-09-17 Thu 07-12-17 7
9 New Piling Works 120 days Tue 03-10-17 Mon 19-03-18 8SS+7 days
10 Construction New Slab and Pile 120 days Thu 12-10-17 Wed 28-03-18 9SS+7 days
Caps
11 Make good existing pile 120 days Fri 08-12-17 Thu 24-05-18 8
12 Installation of new fender 28 days Fri 25-05-18 Tue 03-07-18 11
13 Structural Repair to Wharf 69 days Thu 29-03-18 Tue 03-07-18
14 Repair of cracklines 60 days Thu 29-03-18 Wed 20-06-18 10
15 Repair of concrete spalling 60 days Mon 02-04-18 Fri 22-06-18 14SS+2 days
16 End 0 days Tue 03-07-18 Tue 03-07-18 4,5,10,11,12,15,9

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: Kemaman Wharves Work Milestone Inactive Milestone Start-only


Date: Sat 22-07-17 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 1
24 Sep '17 19 Nov '17 14 Jan '18 11 Mar '18 06 May '18 01 Jul '18
F T S W S T M F T S W S T M

-09

03-07

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: Kemaman Wharves Work Milestone Inactive Milestone Start-only


Date: Sat 22-07-17 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 2