GENERAL CONSTRUCTION CONCERNS
13.4.1 Mobilization and site establishment
Mobilization for Bidder personnel will commence 2 months after the notice to
proceed. The first mobilization will manage and coordinate the initial
construction works, such as accommodation preparation, temporary site
offices, and other temporary facilities to meet the project milestones.
Bidder will utilize its owned fabrication shop space available near the site
location. As this area is much more developed Bidder will use this as Bidder
accommodation. By doing so, Bidder will not spend too much time to do the
preparation works and can speed up the start of construction for the actual
project.
Apart from the tangible work described above, the non-tangible works are
equally important to make the project a success. In addition to the above
tasks, the first mobilization of personnel will be responsible for building up
local community relationship with local community leaders, and preparing
plan for hiring of workers from the surrounding areas. These non-tangible
activities are very important to ensure a smooth project, and are often
overlooked by even the most experienced contractor.
13.4.2 Health, Safety and Environment Protection plans
As Bidder standard practice, Bidder will issue a specific HSE Plan for this
project. HSE Plan will have the following table of content:
Once the HSE Plan is issued and approved, the HSE implementation shall be
observed to be in line with this plan.
Upon materials being received at the job site, the quantity received will be
tracked as per the bill of material quantity. Any shortage or excess material
against bill of material and purchase order quantity will be constantly
monitored.
Material Storage
All materials will be stored and protected in warehouse and storage yard.
Each material checklist will designate the storage class as stipulated in the
procedure that will be developed during execution stage.
Carbon Steel, Low Alloy and Alloy material will be stored at different place or
tray where they will be divided and set in warehouse in order to prevent
material contamination and easy identification of material issue for fabrication
and installation.
Material storage area will be divided based on type of material for pipe, valves
and fittings, other big material, etc and material classification.
Traceability
Equipment Preservation
Eliminate re-work
QA/QC manager will monitor all quality matters in this project from
preparation of project QC plan, QC procedures, ITP and application of
QC plan during engineering phase, fabrication, construction and
installation.
For the local transport and logistic, Bidder will use its own transportation
barges or regular group of freight forwarders which have been used in Bidder
previous projects. In particular, these barges will be ideal transport vehicles
during mobilization and demobilization. By having its own transportation
barges, Bidder will have the following advantages:
- Project material will not be transported with other materials. This is
common practice for transporting using conventional shipment
- Bidder will have overall control on the schedule of shipment
For overseas transport and logistic, Bidder intends to use freight forwarder
agency which is based in Singapore. The chosen freight forwarder shall be
experienced in handling the formalities for importation into Indonesia using
the Master list facilities. This Singapore based forwarder will be required to be
in association with a local custom clearance agency in Jambi for ensuring
smooth custom clearance process. The local agency shall not only have good
relation with the government officials, but also it shall have its own
transportation vehicles (not hired/rented).
6. Hiab Crane 1 1
7. Medium Truck 2
8. Light Vehicle 4
9. Generator set 4