BILL OF QUANTITY

(i) Site Clearance


ITEM DESCRIPTION QUANTITY UNIT AMOUNT
NO. (RM)
1 Clear the site including grubbing the
trees, shrubs and demolish any - - 1039.50
existing structure and cart away and
dump to the specified location.

(ii) Foundation
(Pile cap, stump)

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)
1 Excavation work:

Excavation of depth 60 / 4.7m


4.7m
1.7m
2253.18 m3 37177.47

2 Formwork:

Rough surface of footings 60/ 4 / 4.5m


0.85m
918 m2 46450.80

Rough surface of stump 60 / 4 / 0.4m


1.5m
144 m2 7286.40

3 Reinforcement:

Pad footing:
T20 60 /2 / 10
2.2m
2.47kg/m
6520.8 kg 24192.17

Stump:
T16 60/6/1.67m
1.58kg/m
949.9 kg 3419.64

R6 60 / 6
1.2m
0.22kg/m
95 kg 352.45

4 Concrete work:

Mass concrete for footings 60 / 4.5m


(Grade 25) 4.5m
0.85m
1032.75 m3 227277.29

Mass concrete for stump 60 / 0.4m


(Grade 25) 0.4m
1.5m
14.4 m3 3169.01
Total cost: 349325.23

(iii) Column :

Ground floor column:

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

Formwork:

1 Rough surface of column 60 / 4 / 0.28m


2.6m
174.72 m2 8840.83

2 Reinforcement:

T16 40/8/1.6m
1.58kg/m
809 kg 2912.40

T20 20/4/1.6m
2.47kg/m
316.2 kg 1173.10

R6 60/6/0.6m
0.22kg/m
47.52 kg 176.30

3 Concrete work:
Mass concrete of column 60 / 3.79
227.4 m3 50043.92

Total cost: 63146.55

1st floor column:

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

Formwork:

1 Rough surface of column 249.88 m2 12643.93

2 Reinforcement:

T16 60/10/2.57m
1.58kg/m
2436.36 kg 8770.90

R6 60/8/0.5m
0.22kg/m
52.8 kg 195.90

3 Concrete work:

Mass concrete for column 60 / 3.79


227.4 m3 50043.92

Total cost: 71654.65

2nd floor column:

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

Formwork:

1 Rough surface of column 249.88 m2 12643.93


2 Reinforcement:

T16 60/2/2.57m
1.58kg/m
487.27 kg 1754.17

R6 60/8/2.5m
0.22kg/m
264 kg 979.44

3 Concrete work:

Mass concrete for column 60 / 3.79


227.4 m3 50043.92

Total cost: 65421.46

3rd floor column:

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

Formwork:

1 Rough surface of column 249.88 m2 12643.93

2 Reinforcement:

T16 60/12/2.2m
1.58kg/m
2502.72 kg 9009.79

R6 60/2/2.7m
0.22kg/m
71.28 kg 264.45

3 Concrete work:

Mass concrete for column 60 / 3.79


227.4 m3 50043.92

Total cost: 71962.09


4th floor column:

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

Formwork:

1 Rough surface of column 249.88 m2 12643.93

2 Reinforcement:

T16 60/8/2.57m
1.58kg/m
2047.68 kg 7371.65

R6 60/8/0.5m
0.22kg/m
52.8 kg 195.89

3 Concrete work:

Mass concrete for column 60 / 3.79


227.4 m3 50043.92

Total cost: 70255.39


(iv) Beam

Ground beam:

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

Formwork:

1 Rough surface of beam 353.2 m2 17871.92

Reinforcement:

2 T12 1419.45 5110.02


kg
T16 317.85 1144.26
R6 432.24 1603.61

Concrete work:

3 Lean concrete 0.132 29.05


m3
Mass concrete 15.595 3431.99

Total cost: 29190.85

1st floor beam:

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

Formwork:
1
Rough surface of beam 355.894 m2 18008.24

Reinforcement:
T12 343.48 1236.53
2 T16 680.98 kg 2451.53
T20 722.57 2680.73
R6 315.1 1169.02

Concrete work:

3 Mass concrete of beam 19.893 4377.85


m3

Total cost: 29923.90


2nd floor beam:

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

Formwork:

1 Rough surface of beam 326.7 m2 16531.02

Reinforcement:

2 T12 236.45 851.22


kg
T16 1317.26 4742.14
R6 123.45 458.00

Concrete work:

3 Mass concrete 15.595 3431.99


m3
Total cost: 26014.37

3rd floor beam:

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

Formwork:

1 Rough surface of beam 337.19 m2 17061.81

Reinforcement:

2 T12 213.57 768.85


kg
T16 1213.26 4367.74
R6 130.98 485.94

Concrete work:

3 Mass concrete 13.21 2907.12


m3
Total cost: 25591.46
4th floor beam:

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

Formwork:

1 Rough surface of beam 319.21 m2 16152.03

Reinforcement:

2 T16 1563.79 5629.64


kg
R6 141.36 524.45

Concrete work:

3 Mass concrete 14.21 3127.19


m3
Total cost: 25433.31

Roof beam:

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

Formwork:

1 Rough surface of roof beam 311.71 m2 15772.53

Reinforcement:

2 T12 345.13 1242.47


T16 236.7 852.12
kg
T20 214.13 794.42
R6 312.65 1159.93

Concrete work:

3 Mass concrete of roof beam 25.76 m3 5669.00

Total cost: 25495.47


(v) SLAB

Ground slab:

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

Formwork:

1 Formwork of ground slab 436.49 m2 51649.86

Reinforcement:

2 BRC A8 T 8 13395.96 kg 170396.61

Concrete work:

3 Mass concrete for slab 87.30 19212.11


m3
Total cost: 241257.97

1st floor slab:

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

Formwork:

1 Formwork of ground slab 484.32 m2 57309.60

Reinforcement:

2 BRC A8 T 8 13654.32 kg 173682.95

Concrete work:

3 Mass concrete for slab 93.30 20532.53


m3
Total cost: 251525.08
2nd floor slab:

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

Formwork:

1 Formwork of ground slab 476.18 m2 56346.38

Reinforcement:

2 BRC A8 T 8 14184.25 kg 180423.66

Concrete work:

3 Mass concrete for slab 91.76 20193.62


m3
Total cost: 256963.66

3rd floor slab:

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

Formwork:

1 Formwork of ground slab 426.18 m2 50429.88

Reinforcement:

2 BRC A8 T 8 13454.14 kg 171136.66

Concrete work:

3 Mass concrete for slab 83.21 18312.02


m3

Total cost: 239878.56


4th floor slab:

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

Formwork:

1 Formwork of ground slab 436.72 m2 51677.08

Reinforcement:

2 BRC A8 T 8 13178.65 kg 167632.43

Concrete work:

3 Mass concrete for slab 89.23 19636.85


m3

Total cost: 238946.36

Roof floor slab:

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

Formwork:

1 Formwork of ground slab 432.18 m2 51139.86

Reinforcement:

2 BRC A8 T 8 12908.43 kg 164195.23

Concrete work:

3 Mass concrete for slab 86.13 18954.63


m3

Total cost: 234289.72


(vi) Brickwall

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

1. Ground floor brickwall 1422.14 m2 54467.96

2. 1st floor brickwall 1456.268 m2 55775.06

3. 2nd floor brickwall 1543.23 m2 59105.71

4. 3rd floor brickwall 1498.36 m2 57387.19

5. 4th floor brickwall 1473.28 m2 56426.62

Total cost: 283162.54

(vii) Staircase

ITEM DESCRIPTION QUANTITY UNIT AMOUNT


NO. (RM)

1 Formwork:

Formwork of staircase 134.53 m2 1145.58

2 Reinforcement:

Y12, 12.8m 76.12 27.19


T12, 59.02m 152.46 kg 130.63
R6, 12.4m 32.755 6.80

3 Concrete work:

Mass concrete for staircase 67.13 m3 2230.86


(viii) Others

No. DESCRIPTION QUANTITY UNIT AMOUNT(RM)


1. Windows and door 158 - 312470

2. Finishes
-wall finishes(plastering & painting) 5894.64 m2 104335.13
-floor finishes(cement rendering) 2538.75 m2 128460.75
-ceiling(gypsum plaster board 382.73 m2 6774.32
-

Summary of Bills of Quantities

DESCRIPTION AMOUNT(RM)
1. Site Clearing 1,039.50
2. Foundation 349,325.23
3. Column 342,170.14
4. Beam 161,649.36
5. Slab 1,462,861.35
6. Brickwall 283162.54
7. Staircase 116,228.81
8. Others 239,570.20

Subtotal 1 2,956,007.13

9. Building services(5%) 147,800.36


10. External works(3%) 88,680.21

Subtotal 2 3,192,487.70

11. Preliminaries(3%) 95,774.63

TOTAL 3,288,262.33
Price Index

NO item unit Rate


(RM)

1 Site clearing m2 2.40

2 excavation m3 16.50

3
Concrete :
(Foundation, walls , beams and columns)
Grade 25 m3 220.07

4
Reinforcement :
6 mm dia. Mild steel bar (R6) 3.71
20 mm dia. high tensile bar (T20) 3.71
16 mm dia. high tensile bar (T16) kg 3.60
12 mm dia. high tensile bar (T12) 3.60
10 mm dia. high tensile bar (T10) 3.71
BRC A8 T8 m2 12.72

5 Sawn Formwork as specified :


To sides of foundation and ground beam 50.60
To sides wall, column, staircase and beam m2 50.60
To soffit of suspended floor slab, roof slab 118.33

6 Brickwall m2 38.30
7 12mm thk plasterboard in ceiling m2 49.00

8 Windows and door - 215.00

9 Finishes
-wall finishes(plastering & painting) m2 17.70
-floor finishes(cement rendering) m2 10.60
-ceiling(gypsum plaster board m2 17.70