LOAD UPGRADING IN ANOTHER AREA OF HIGH QUALITY FARM

1. STEEL POLE 25 (CLASS 9) ------------------------- 12 PCS @ 9800 ------------- 117,600.00


2. SECONDARY RACK (3 SPOOLS) ------------------ 26 PCS @ 250 ------------------ 6,500.00
3. SPOOL INSULATOR --------------------------------- 78 PCS @ 35 ------------------- 2,730.00
4. POLY ACSR # 2/0 ------------------------------------ 2110 MTS @ 56 --------------118,160.00
5. 3 PHASE TRANSFORMER 220/440V
50 KVA --------------------------------------------------------------------------- 35,000.00
30 KVA --------------------------------------------------------------------------- 21,000.00
6. CB 200AT 3P 220V ----------------------------------------------------------------------- 10,000.00
7. CB 100AT 3P 440V ------------------------------------------------------------------------- 5,000.00
8. CLAMP LOOP DEAD END 2/0 --------------------- 12 PCS @ 250 ------------------- 3,000.00
9. THHN COPPER WIRE #2/0 ------------------------- 15 MTS @ 380 ------------------ 5,700.00
10. THHN COPPER WIRE # 2 --------------------------- 15 MTS @ 190 ------------------ 2,850.00
11. PLASTIC TAPE ----------------------------------------- 12 PCS @ 30 ----------------------- 360.00
12. RUBBER TAPE ------------------------------------------- 6 PCS @ 105 --------------------- 630.00
13. MISCELLANEOUS --------------------------------------- 1 LOT @ 2000 -----------------2,000.00

NOTE:
Delivery of purchased materials (by owner).
MATERIAL COST ------------------- PHP 330,530.00
LABOR COST ------------------------------- 82,132.00
PROFIT -------------------------------------- 16,426.00
PHP 429,088.00

(FOUR HUNDRED TWENTY NINE THOUSAND EIGHTY EIGHT PESOS ONLY)

SCOPE OF WORK
1. EXCAVATION / ERECTION / STRINGING OF 3 CONDUCTORS AS SHOWN IN DRAWING.
2. INSTALLATION OF 2 DRY- TYPE TRANSFORMER, 1 50 KVA , 1 30 KVA AND SUPPLY.
3. ENERGIZATION AND TESTING.
4. TRANSFORMER HOUSE (BY OTHERS)

PREPARED / SUBMITTED BY:

ENGR. MER O. CAISIP