ID Task Task Name Duration Start Finish Predecessors

Mode 16 Jul '17 23 Jul '17 30 Jul '17 06 Aug '17 13 Aug '17 20 Aug '17 27 Aug '17 03 Sep '17 10 Sep '17 17 Sep '17 24 Sep '17 01 Oct '17 08 Oct '17 15 Oct '17 22 Oct '17 29 Oct '17 05 Nov '17 12 Nov '17 19 Nov '17 26 Nov '17
1 DATA CENTER PROJECT 129 days 18/07/17 23/11/17
2 PHASE INITIAL 21 days 18/07/17 07/08/17
3 Kick of Meeting 1 day 18/07/17 18/07/17
4 Site Survey & Data Gathering 2 days 19/07/17 20/07/17 3
5 Gambar Kerja 18 days 21/07/17 07/08/17
6 Initial Drawing 6 days 21/07/17 26/07/17
7 General Layout Ruang 1 day 21/07/17 21/07/17 4
8 Schematic Layout FSS 1 day 21/07/17 21/07/17 4
9 Design Sign-Off / Approval Design 2 days 25/07/17 26/07/17 7;8
10 Detailed Drawing 12 days 27/07/17 07/08/17
11 Gambar Detail Sipil 4 days 27/07/17 30/07/17 9
12 Gambar Detail Security System 4 days 27/07/17 30/07/17 9
13 Schedule Implementasi Detail 4 days 31/07/17 03/08/17 11;12
14 Sign-off / Approval 3 days 05/08/17 07/08/17 13
15 PHASE IMPLEMENTASI 125 days 19/07/17 20/11/17
16 Persiapan 10 days 25/07/17 03/08/17
17 Kick of Implementasi 2 days 27/07/17 28/07/17 6
18 Procurement proses 10 days 25/07/17 03/08/17 4
19 Equipment Delivery 35 days 19/07/17 22/08/17 3
20 Fire Suppression System 26 days 28/07/17 22/08/17
21 Novec Main Equipment 20 days 03/08/17 22/08/17 18SS+3 days
22 MH Clean Agent Equipment 20 days 28/07/17 16/08/17 18SS+3 days
23 Piping & Support Material 10 days 30/07/17 08/08/17 18SS+3 days
24 Partisi Ruang 29 days 19/07/17 16/08/17
25 Partisi Gypsum 10 days 30/07/17 08/08/17 18SS+3 days
26 Partisi Caging 20 days 28/07/17 16/08/17 18SS+3 days
27 Partisi Kaca 16 days 19/07/17 03/08/17
28 Support Material 5 days 04/08/17 08/08/17 18SS+3 days
29 Security System 25 days 29/07/17 22/08/17
30 CCTV 25 days 29/07/17 22/08/17 18SS+3 days
31 Access Door 20 days 03/08/17 22/08/17 18SS+3 days
32 Support Material 10 days 30/07/17 08/08/17 18SS+3 days
33 INSTALASI 51 days 04/08/17 23/09/17
34 Perapihan Ruang 6 days 04/08/17 09/08/17 18
35 Civil work 45 days 09/08/17 22/09/17 17
36 Gypsum Partition 45 days 09/08/17 22/09/17 14;25
37 Caging Partition 10 days 20/08/17 29/08/17 26;36SS+5 days
38 Glass Partition 30 days 19/08/17 17/09/17 27;36SS+10 days
39 Fire Suppression System 25 days 09/08/17 02/09/17
40 Main Equipment 2nd floor 10 days 23/08/17 01/09/17 21;36SS+10 days
41 Main Equipment B2 floor 5 days 17/08/17 21/08/17 22
42 Piping Instalation 2nd floor 25 days 09/08/17 02/09/17 23;36SS
43 Piping Instalation B2 floor 10 days 15/08/17 24/08/17 23;36SS
44 Security System 32 days 23/08/17 23/09/17
45 CCTV 30 days 23/08/17 21/09/17 30;35SF-3 days
46 Access Door 7 days 25/08/17 31/08/17 31;35SF-3 days
47 Test Security System 2 days 22/09/17 23/09/17 45;46
48 Testing dan Commissioning 8 days 13/11/17 20/11/17
49 Integrasi Test FSS & Security dengan perangkat8lainnya
days 13/11/17 20/11/17 33FS+3 days
50 PROJECT HAND-OVER 3 days 21/11/17 23/11/17
51 Training 2 days 22/11/17 23/11/17 49
52 BAST 2 days 21/11/17 22/11/17 49
53 DATA CENTER PROJECT 129 days 18/07/17 23/11/17
54 PHASE INITIAL 21 days 18/07/17 07/08/17
55 Kick of Meeting 1 day 18/07/17 18/07/17
56 Site Survey & Data Gathering 2 days 19/07/17 20/07/17 55
57 Gambar Kerja 18 days 21/07/17 07/08/17
58 Initial Drawing 6 days 21/07/17 26/07/17
59 General Layout Ruang 1 day 21/07/17 21/07/17 56
60 Schematic Layout FSS 1 day 21/07/17 21/07/17 56
61 Design Sign-Off / Approval Design 2 days 25/07/17 26/07/17 59;60
62 Detailed Drawing 12 days 27/07/17 07/08/17
63 Gambar Detail Sipil 4 days 27/07/17 30/07/17 61
64 Gambar Detail Security System 4 days 27/07/17 30/07/17 61
65 Schedule Implementasi Detail 4 days 31/07/17 03/08/17 63;64
66 Sign-off / Approval 3 days 05/08/17 07/08/17 65
67 PHASE IMPLEMENTASI 125 days 19/07/17 20/11/17
68 Persiapan 10 days 25/07/17 03/08/17
69 Kick of Implementasi 2 days 27/07/17 28/07/17 58

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Pembangunan Fisik Pusat Data
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Slack
Baru.
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1
ID Task Task Name Duration Start Finish Predecessors
Mode 16 Jul '17 23 Jul '17 30 Jul '17 06 Aug '17 13 Aug '17 20 Aug '17 27 Aug '17 03 Sep '17 10 Sep '17 17 Sep '17 24 Sep '17 01 Oct '17 08 Oct '17 15 Oct '17 22 Oct '17 29 Oct '17 05 Nov '17 12 Nov '17 19 Nov '17 26 Nov '17
70 Procurement proses 10 days 25/07/17 03/08/17 56
71 Equipment Delivery 35 days 19/07/17 22/08/17 55
72 Fire Suppression System 26 days 28/07/17 22/08/17
73 Novec Main Equipment 20 days 03/08/17 22/08/17 70SS+3 days
74 MH Clean Agent Equipment 20 days 28/07/17 16/08/17 70SS+3 days
75 Piping & Support Material 10 days 30/07/17 08/08/17 70SS+3 days
76 Partisi Ruang 29 days 19/07/17 16/08/17
77 Partisi Gypsum 10 days 30/07/17 08/08/17 70SS+3 days
78 Partisi Caging 20 days 28/07/17 16/08/17 70SS+3 days
79 Partisi Kaca 16 days 19/07/17 03/08/17
80 Support Material 5 days 04/08/17 08/08/17 70SS+3 days
81 Security System 25 days 29/07/17 22/08/17
82 CCTV 25 days 29/07/17 22/08/17 70SS+3 days
83 Access Door 20 days 03/08/17 22/08/17 70SS+3 days
84 Support Material 10 days 30/07/17 08/08/17 70SS+3 days
85 INSTALASI 51 days 04/08/17 23/09/17
86 Perapihan Ruang 6 days 04/08/17 09/08/17 70
87 Civil work 45 days 09/08/17 22/09/17 69
88 Gypsum Partition 45 days 09/08/17 22/09/17 66;77
89 Caging Partition 10 days 20/08/17 29/08/17 78;88SS+5 days
90 Glass Partition 30 days 19/08/17 17/09/17 79;88SS+10 days
91 Fire Suppression System 25 days 09/08/17 02/09/17
92 Main Equipment 2nd floor 10 days 23/08/17 01/09/17 73;88SS+10 days
93 Main Equipment B2 floor 5 days 17/08/17 21/08/17 74
94 Piping Instalation 2nd floor 25 days 09/08/17 02/09/17 75;88SS
95 Piping Instalation B2 floor 10 days 15/08/17 24/08/17 75;88SS
96 Security System 32 days 23/08/17 23/09/17
97 CCTV 30 days 23/08/17 21/09/17 82;87SF-3 days
98 Access Door 7 days 25/08/17 31/08/17 83;87SF-3 days
99 Test Security System 2 days 22/09/17 23/09/17 97;98
100 Testing dan Commissioning 8 days 13/11/17 20/11/17
101 Integrasi Test FSS & Security dengan perangkat8lainnya
days 13/11/17 20/11/17 85FS+3 days
102 PROJECT HAND-OVER 3 days 21/11/17 23/11/17
103 Training 2 days 22/11/17 23/11/17 101
104 BAST 2 days 21/11/17 22/11/17 101

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Pembangunan Fisik Pusat Data
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Slack
Baru.
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 2