Sei sulla pagina 1di 54

TDD Product

Support Dept.

LTE TDD ZXSDR BS8900A


Outdoor Cabinet Quick
Installation Guide (B900)
LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

LEGAL INFORMATION

By accepting this certain document of ZTE CORPORATION you agree to the following terms. If you do
not agree to the following terms, please notice that you are not allowed to use this document.

Copyright 2015 ZTE CORPORATION. Any rights not expressly granted herein are reserved. This
document contains proprietary information of ZTE CORPORATION. Any reproduction, transfer,
distribution, use or disclosure of this document or any portion of this document, in any form by any
means, without the prior written consent of ZTE CORPORATION is prohibited.

is registered trademarks of ZTE CORPORATION. ZTE's company name, logo and product names
referenced herein are either trademarks or registered trademarks of ZTE CORPORATION. Other
product and company names mentioned herein may be trademarks or trade names of their respective
owners. Without the prior written consent of ZTE CORPORATION or the third party owner thereof,
anyone's access to this document should not be construed as granting, by implication, estopped or
otherwise, any license or right to use any marks appearing in the document.

The design of this product complies with requirements of environmental protection and personal
security. This product shall be stored, used or discarded in accordance with product manual, relevant
contract or laws and regulations in relevant country (countries).

This document is provided ''as is'' and ''as available''. Information contained in this document is
subject to continuous update without further notice due to improvement and update of ZTE
CORPORATION's products and technologies.

ZTE CORPORATION

Address: NO. 55
Hi-tech Road South
Shenzhen
P.R.China
518057
Website: http://support.zte.com.cn

Email: 800@zte.com.cn

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. I


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

Revision History

Document Serial
Product Version Reason for Revision
Version Number
V3 R1.0 This is the initial release.
Adding instructions for GPS
antenna on the cabinet top
V3 R1.1
cover; adding instructions and
diagrams of DCPD7A.
Adding instructions for second
disconnection of DCPD7A;
V3 R1.2
adding instructions for one more
DCPD7A.
1. Changing the data of the
cabinet base diagram of Chapter
4.3;
2.Adding instructions for
DCPD6A of Chapter 1.1;
3.Changing the system diagram
of Diagram 5-1 and Diagram 5-2;
4.Adding Diagram 5-3 and
V3 R1.3 Diagram 5-4 for B900 with
DCPD6and B900 with DCPD7A;
5.Changing instructions for Table
7-2 of Power Cable for the Fan of
PC8910A Cabinet;
6. Changing instructions of one
end of Power Cable for the Fan
of PC8910A Cabinet in Chapter
7.2.2.

Author
Document
Date Prepared by Reviewed by Approved by
Version
2015-1-26 R1.0 Liu Zhe
2015-3-26 R1.1 Liu Zhe
2015-5-26 R1.2 Liu Zhe
2015-9-18 R1.3 Liu Zhe

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. II


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

Applicable to: Constructors at the BS side

Proposal: Before reading this document, you had better have the following knowledge and skills:
SEQ Knowledge and skills Reference material
Knowledge of ZXSDR B8200 system ZXSDR B8200 TL200(V2.00)TD-LTE
1 features, technical specifications, and Baseband Resource Unit Hardware
operation and maintenance. Description
Knowledge of ZXDU58 B900 system
ZXDU58 B900 (V4.5R99M01) DC Power
2 features, technical specifications, and
System Product Description
operation and maintenance.
3
4
5

Follow-up document: After reading this document, you may need the following information:
SEQ Reference material Information
ZXSDR BS8900A L200 (V2.00) Outdoor LTE Detailed description of the maintenance of
1
Macro eNodeB Maintenance Guide BS8900A

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. III
LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

About This Document

Summary
Chapter Description
1 Overview This chapter introduces the purpose of this document and
provides information such as the production configuration,
installation workflow and scenario.
2 Installation Workflow This chapter describes in details the cabinet installation
workflow.
3 Installation Preparation This chapter describes the installation precautions.
4 Installing the BS8900A Cabinet This chapter describes how to safely install the BS8900A
cabinet in details.
5 Cables Installation Preparation This chapter describes in details the install the cable
installation preparation.
6 Connecting Cables Outside the This chapter describes how to safely install the cables outside
BS8900A Cabinet the BS8900A cabinet in details.
7 Connecting Cables Inside the This chapter describes how to safely install the cables inside
BS8900A Cabinet the BS8010A cabinet in details.
8 Installation Check This chapter briefs the dos and don'ts during the installation
check.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. IV


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

TABLE OF CONTENTS
1 Overview ......................................................................................................... 1
1.1 Product Configuration ....................................................................................... 1
1.2 Installation Scenario ......................................................................................... 2

2 Installation Workflow ...................................................................................... 4

3 Installation Precautions ................................................................................. 5

4 Cabinet Installation......................................................................................... 7
4.1 The BC8910A Cabinet Top Cover Installation................................................... 7
4.2 The GPS Antenna Installation on the Cabinet Top (optional) ............................ 8
4.3 The PC8910A Cabinet Base Installation ........................................................... 9
4.4 The BC8910A Cabinet and the PC8910A Cabinet Stack ................................ 11
4.5 Batteries Installation ....................................................................................... 12
4.6 BS8900A Installation Diagram ........................................................................ 13

5 Cable Connection Preparation..................................................................... 15


5.1 Disassembling Preparation ............................................................................. 15
5.1.1 Disassembling Cable Hole of The Base .......................................................... 15
5.1.2 Disassembling Waterproofing Plug of The BC8910A Cabinet ......................... 16
5.1.3 Disassembling Cable Hole Cover on Top of The PC8910A ............................ 16
5.1.4 Disassembling Cable Guiding Rails on Two Sides of The PC8910A Cabinet . 18
5.2 Connecting the Cable Through the Waterproofing Module.............................. 18
5.3 Cable Connection Diagram ............................................................................. 19

6 Connecting Cables outside the Cabinet ..................................................... 23


6.1 Cabling Combination for Left-Sided Waterproofing Module of the BC8910A
Cabinet .......................................................................................................... 23
6.1.1 Connecting the Grounding Cable of the Cabinet ............................................. 24
6.1.2 Connecting the AC Input Power Cable............................................................ 24
6.1.3 Connecting the GPS Feeder ........................................................................... 26
6.2 Cabling Combination for Right-Sided Waterproofing Module of the BC8910A
Cabinet .......................................................................................................... 27
6.2.1 Connecting the RRU Power Cable .................................................................. 28
6.2.2 Connecting the Optical Cable ......................................................................... 29

7 Connecting Cables inside the Cabinet ........................................................ 30


7.1 Cabling Combination for Left-Sided Cylinder-shaped Cabling Through of the
PC8910A Cabinet .......................................................................................... 32
7.1.1 Connecting Power Cables for Batteries .......................................................... 32
7.1.2 Connecting the Heat Detecting Cable for the Battery ...................................... 34
7.2 Cabling Combination for Right-Sided Cylinder-shaped Cabling Through of the
PC8910A Cabinet .......................................................................................... 35
7.2.1 Connecting the Water Sensing Expansion Cable ............................................ 35
7.2.2 Connecting the Access Control Cable of PC8910A Cabinet ........................... 36

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. V


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

7.2.3 Connecting the Power Cable for the Fan of PC8910A Cabinet ....................... 37
7.2.4 Connecting the Heater Power Cable of PC8910A Cabinet (optional) .............. 37

8 Post-Installation Check ................................................................................ 38


8.1 Cabinet Installation Check .............................................................................. 38
8.2 Cable Installation Check ................................................................................. 39
8.3 Other Checks.................................................................................................. 39

FIGURES

Figure 1-1 DCPD6 Diagram ................................................................................................. 1


Figure 1-2 DCPD7A Diagram ............................................................................................... 1
Figure 1-3 Stacked Installation Scenario (Front View) .......................................................... 2
Figure 1-4 Stacked Installation Scenario (Top View) ............................................................ 2
Figure 1-5 Side by Side Installation Scenario (Front View) ................................................... 3
Figure 1-6 Side by Side Installation Scenario (Top View) ..................................................... 3
Figure 2-1 BS8910A Installation Workflow ........................................................................... 4
Figure 4-1 BS8900A Installation Diagram (DCPD6) ........................................................... 13
Figure 4-2 BS8900A Installation Diagram (DCPD7A) ......................................................... 14
Figure 5-1 BBU Cable Connection Diagram (DCPD6) ........................................................ 19
Figure 5-2 BBU Cable Connection Diagram (DCPD7A) ..................................................... 20
Figure 5-3 B900 Wiring Diagram with DCPD6 and DCPD6A .............................................. 21
Figure 5-4 B900 Wiring Diagram with DCPD7A ................................................................. 21
Figure 5-5 Monitoring Cable Connection Diagram .............................................................. 22
Figure 5-6 SA Board Cable Diagram .................................................................................. 22
Figure 5-7 SA Board Cable Connection Diagram ............................................................... 23
Figure 7-1 Cabling Combination for Waterproofing Module of the PC8910A Cabinet ......... 30

TABLES

Table 1-1 Description of Product Configuration .................................................................... 1


Table 1-2 Instructions of DCPD6, DCPD6A and DCPD7A ................................................... 1
Table 3-1 Description of Installation Tools .............................................................................. 5
Table 6-1 Cabling Combination for Left-Sided Waterproofing Module of the BC8910A
Cabinet ................................................................................................................................. 23

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. VI


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

Table 6-2 Color Indication for Single-phrase AC ................................................................ 26


Table 6-3 Cabling Combination for Right-Sided Waterproofing Module of the BC8910A
Cabinet ................................................................................................................................. 27
Table 7-1 Cabling Combination for Left-Sided Cylinder-shaped Cabling Through of the
PC8910A Cabinet ................................................................................................................. 32
Table 7-2 Cabling Combination for Right-Sided Cylinder-shaped Cabling Through of the
PC8910A Cabinet ................................................................................................................. 35

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. VII
LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

1 Overview
This document describes how to install the BS8900A cabinet based on the following
production configuration and installation scenario.

Note: As the product configuration, installation scenario and the delivery


materials are different amongst fields. The document describes only based on the
product below. Any question about the installation specifications, please contact TDD
Product Team for support.

1.1 Product Configuration

Table 1-1 Description of Product Configuration


Outdoor Power Power
Item Battery Main Equipment
Cabinet Supply
BC8910A 12V 150AH
(for equipment) ZXDU58 valve-regulated TD-LTE ZXSDR
Type
PC8910A B900 lead-acid enclosed BBU
(for battery) battery

Table 1-2 Instructions of DCPD6, DCPD6A and DCPD7A


Specification Outdoor Lightning
Item Wiring Instructions
Instructions Protection
DCPD7A is composed of six
breakers of first disconnection (100A
RC, 620A, indicated by 5~10)
and four breakers of second First Disconnection
disconnection (50A RC, Supporting;
Default Delivery
DCPD7A 220A+210A, indicated by 1~4). It Second
Specification
is suggested that you may select port Disconnection Not
1 and port 2 to power BUU, select Supporting.
port 3 and port 4 to power the
transmission equipment, and select
port 5~ port 10 to power RRU.
DCPD6 is composed of nine 20A
breakers, is considered to connect
Matching with DCPD6A
DCPD6 the first disconnection devices Supporting
for six RRUs or above.
outside the cabinet, such as RRU, as
default.
9 10A
DCPD6A
Matching with DCPD6 for BBU Not Supporting
six RRUs or above. DCPD6A is composed of nine 10A
breakers, is considered to connect

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 1


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

the second disconnection devices


inside the cabinet, such as BBU, as
default.

Figure 1-1 DCPD6 Diagram

Figure 1-2 DCPD7A Diagram

If DCPD6A is needed to match with DCPD7A, it is suggested that the second disconnection terminals of 20A of
DCPD7A indicated as 1 or 2 above, connecting DCPD6A

1.2 Installation Scenario


The BC8910A cabinet and the PC8910A cabinet can be either stacked or installed side
by side. The document take the stacked cabinets as an example to describe the
installation specifications of the equipment modules and cables within the cabinets.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 2


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

Figure 1-3 Stacked Installation Scenario (Front View)

Note:

The height of the concrete base at the bottom of the cabinet must be greater than
200 mm.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 3


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

Figure 1-4 Stacked Installation Scenario (Top View)

Note:

For stacke installation scenarion, the size of the concrete base at the bottom of the
cabinet must be no less than 1600 mm1500 mm..

Figure 1-5 Side by Side Installation Scenario (Front View)

Note:

For side by side installation scenario, the distance between the two BS8910A
cabinets should be more than 100mm and be less than 500mm.

100mmL500mm.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 4


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

Figure 1-6 Side by Side Installation Scenario (Top View)

Note:

For side by side installation scenarion, the size of the concrete base at the bottom of
the cabinet must be no less than 2200 mm1500 mm.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 5


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

2 Installation Workflow
Figure 2-1 BS8910A Installation Workflow

Start

Cabinet
Installation

External Cables
Installation

Internal Cables
Installation

Inspection

Power On &
Power Off

End

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 6


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

3 Installation Precautions
Task Purpose

This document is designed to provide installation specifications for the outsourcing team
before commissioning.

Task Staff
Installation Supervisor
Outsourcing Employee

Prerequisites
The installation site meets the engineering design requirements
The installation site meets the first environment acceptance requirements
Goods Unpacking Inspection and Distribution on site is finished.

Tools

Table 3-1 Description of Installation Tools


Name Illustration Function

Electric drill To install the base

Nail hammer To install the base

Vacuum cleaner To install the base

To install the top cover and


M12 hexagon spanner to connect the cabinet to
the base

Pliers
To create cable connectors

Crimpers To create cable connectors

Diagonal cutting pliers To route cables

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 7


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

To create and to waterproof


Paper cutter
cable connectors

Philips screwdriver To install power cables

Spanner To install GPS feeders

Workflow

1. Cabinet installation (including cabinet base installation, cabinet top installation, and
BC8910A cabinet and PC8910A cabinet stack);

2. External cables installation (including grounding cable, AC power cable, GPS feeder,
RRU power cable, optical cable, ETH cable, monitoring cable and so on );

3. Internal cables installation (including battery power cable, battery heat detecting
cable, water monitoring extension cable, access control cable, fan power cable,
heater power cable and so on);

4. Inspection (including cabinet inspection, cable inspection and so on);

5. Power on & power off .

Instructions

1. Read ZXSDR B8200 TL200 TD-LTE Baseband Unit User Manual and

ZXDU58 B900 DC Power System User Manual before the installation so as to learn the
system structure.

2. Remove watches, hand chains, rings or other conductive objects before the
operation. Wear special gloves for protection.

3. Apply only the tools described in this document.

4. Pay attention to the safety tags or warnings attached to the equipment. Do not cover
the tags and warnings or even remove them off the equipment under any conditions.

5. Never install the equipment in a place where there is a risk of liquid or objects falling
inside the equipment as short circuit may occur and damage the equipment!

6. Do not stack heavy objects on top of the cabinet so as prevent damage to the
equipment!

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 8


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

7. While drilling, operators should take measures to prevent dust from entering
people's respiratory tracks or eyes.

8. Wear safety helmets on site as objects falling from heights might cause severe
physical injuries or even deaths. It is forbidden to stand right under the heavy
objects!

9. The electrical devices should be installed or reconstructed by experienced


electricians as any faults in electrical installation may cause fires, electric shock, or
explosions.

10. People working at heights should be qualified with related certificates. They should
conform to the local laws, regulations, and instruction guides.

11. Never work at heights (e.g. on the tower) in severe weather (e.g. in rains or fogs).

12. When working at or around the transmit antenna, ensure that the antenna is in a
disconnected state or its power is reduced to a safety level.

13. When installing batteries, pay attention that:

(1) The batteries should be of the same type. Old and new batteries must not be
used together;

(2) The battery packs must not be short-circuited in any way during the operation;

(3) Before the cables are connected to the battery, power off the battery to prevent
any possible physical injuries.

14. Insulated tools should be used for electrical connection. Connection terminals and
exposed parts should be fully insulated.

(1) The cross-sectional area of cables should match the load;

(2) When the colors of the power cables indicated in this document differ from
those in the local area, adopt the cables of different colors in that local area.
Remember to use the black heat shrinkable sleeve or insulation tapes for a
black power cable so as to prevent any confusion.

15. When operating with the optical cables, ensure that:

(1) The temperature is above -20 ;

Protective measures are taken for your eyes so as to prevent them from direct sight of the
optical ports.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 9


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

4 Cabinet Installation

4.1 The BC8910A Cabinet Top Cover Installation


1. Place the top cover on top of the BC8910A cabinet.

2. Fix the top cover using the hexagon spanner and four M12 inner hexagon bolts with
steel washers.

4.2 The GPS Antenna Installation on the Cabinet Top


(optional)
The GPS antenna can be installed on anyone of the four corners of the cabinet top.

1. Remove the four M12 inner hexagon bolts on the cabinet top, align the eyebolt with
the installation holes of the GPS installation accessories and the cabinet top, and
screw the eyebolts to fasten the GPS installation accessories on the cabinet top.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 10


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

2. Use the fixture clamping the GPS antenna.

Note: For better procedure, the GPS feeder should be connected to the GPS
antenna and be sealed with waterproof tapes before the GPS antenna is clamped with
the fixture.

3. Fasten the fixture on the GPS installation accessories with two bolts.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 11


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

4.3 The PC8910A Cabinet Base Installation


1. Place the base at the place according to the design, and then determine the four
drilling holes for the four expansion bolts;

531mm
80mm
413mm

2. Use a 12 bit to drill four holes, each of which is 16 mm in diameter and 80 mm in


depth. Use the vacuum cleaner to clear the dust;

3. Put the M12 bolt into the expansion tube, and then place the flat washer, spring
washer, and nut onto the bolt in order. Use the nail hammer to set the bolt into the
hole, and then tighten the nut clockwise. Leave a clearance of 30 mm between the
tightened nut and the ground, and then remove the nut, spring washer, and flat
washer off the bolt.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 12


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

4. Put the insulating spacer onto the bolt, and then place the base into the bolt.
Place the insulating flange, flat washer, and spring washer onto the bolt in order,
and then tighten the nut. Finally, use a multimeter to test whether the base is
insulated from the ground.

5. Fix the front cabinet door using the cabinet door support. Disassemble the
baseboard of the PC8910A cabinet to expose the four bolt holes.

6. Use four M12 inner hexagon bolts with rubber washers and the matched spanner to
fasten the PC8910A cabinet to the base.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 13


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

7. Assemble the baseboard of the PC8910A cabinet in the end.

4.4 The BC8910A Cabinet and the PC8910A Cabinet


Stack
1. Remove two rectangular cabling trough covers and two round cable hole covers at the
top of the PC8910A cabinet.

(1) Use the Philips screwdriver to remove one screw of the rectangular cover plate,
and then you can remove the cover plate.

(2) Use the Philips screwdriver to remove four screws on the round cable hole cover
plates inside the PC8910A cabinet, and then you can remove the cover plate.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 14


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

2. Stack the BC8910A cabinet onto the PC8910A cabinet, and then align the BC8910A
cabinet with the PC8910A cabinet.

Use the delivered inner hexagon spanner and four M12 bolts with rubber spacers to fix
the BC8910A cabinet and the PC8910A cabinet through the quadrangular bolt holes at
the bottom of the BC8910A cabinet.

Note:

1. If there is a heater in the BC8910A cabinet, before assembling the four M12 bolts to
stack the BC8910A cabinet up the PC8910A cabinet, disassemble the screws of the
heater and pulled out the heater. Meanwhile, the power cable of the heater should
not be disassembled.

2. before assembling the four M12 bolts to stack the BC8910A cabinet up the
PC8910A cabinet, disassemble the two dummy panels.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 15


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

4.5 Batteries Installation


Insert the batteries one by one into the battery compartment inside the PC8910A cabinet
according to the "Battery Clearance Requirements".

When only four batteries are installed, place them at the bottom of the compartment.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 16


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

4.6 BS8900A Installation Diagram

Figure 4-1 BS8900A Installation Diagram (DCPD6)

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 17


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

Figure 4-2 BS8900A Installation Diagram (DCPD7A)

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 18


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

5 Cable Connection Preparation

5.1 Disassembling Preparation

5.1.1 Disassembling Cable Hole of The Base

1. Use the double offset ring spanner at the bottom of the base to loosen the screw of
the screen at the side of the base where the cable hole is located.

2. Push open the screen.

3. Loosen the six screws of the front screen in the base and then remove the screen.

Note: The dust screen and the baffle should be installed after all of the installation
and connection: Put the dust screen in the trough in the front of the base; and then
fasten the baffle of the base with six screws.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 19


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

5.1.2 Disassembling Waterproofing Plug of The BC8910A Cabinet

Remove the rubber waterproofing plug.

5.1.3 Disassembling Cable Hole Cover on Top of The PC8910A

1. Use the Philips screwdriver to remove the four screws off the rectangular cable hole
cover plate inside the BC8910A cabinet, and then you can remove the cover plate.

2. Insert the cylinder-shaped cabling through into the position where the cover plate is
removed within the PC8910A cabinet, and insert the cylinder-shaped rubber
waterproofing plug into the cabling through.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 20


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

Note:

Pay attention that the cylinder-shaped cabling assembly and the rubber waterproofing plug
are fixed inside the PC8910A cabinet, bundled with the white cable ties with shipment.

5.1.4 Disassembling Cable Guiding Rails on Two Sides of The PC8910A


Cabinet

Remove the rectangular cable guiding rails on the left and right sides of the PC8910A
cabinet.

5.2 Connecting the Cable Through the


Waterproofing Module
1. Estimate the cable lengths required after the cables are led into the cabinet through
the cable holes in the waterproofing module, and leave an extra clearance of 20 cm.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 21


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

2. Select the proper cable holes (as described in sections 6.1 and 6.2) according to the
cable diameters. Then, insert the cables into the rubber waterproofing plugs..

3. Bind the cables along the cable through inside the cabinet, and adjust the cable
length inside the cabinet.

4. Insert the rubber waterproofing plugs into the original cable holes.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 22


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

5.3 Cable Connection Diagram

Figure 5-1 BBU Cable Connection Diagram (DCPD6)

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 23


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

Figure 5-2 BBU Cable Connection Diagram (DCPD7A)

Figure 5-3 B900 Wiring Diagram with DCPD6 and DCPD6A

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 24


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

Figure 5-4 B900 Wiring Diagram with DCPD7A

Figure 5-5 Monitoring Cable Connection Diagram

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 25


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

Note:

Cable have already been connected at factory, and cable has to be assembled
at site. Water sensing extension cable is needed when cabinets are stacked.

Figure 5-6 SA Board Cable Diagram

Figure 5-7 SA Board Cable Connection Diagram

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 26


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

6 Connecting Cables outside the Cabinet

6.1 Cabling Combination for Left-Sided


Waterproofing Module of the BC8910A Cabinet

Table 6-1 Cabling Combination for Left-Sided Waterproofing Module of the BC8910A
Cabinet
Connecting Point Connecting Connecting
Identificati Diamet Quantit inside BC8910A Point inside Point outside
Cables
on er y Cabinet PC8910A Cabinet
Cabinet
BC8910A cabinet PC8910A Outdoor
Grounding grounding busbar cabinet grounding
V 17mm 2
Cable grounding busbar
point
AC Power B900 AC Input AC Power
W 19mm 1 /
Cable
N-type connector for / GPS Antenna
J 9.5mm GPS feeder 1 the GPS surge
protector

6.1.1 Connecting the Grounding Cable of the Cabinet

1. Determine the proper length of the grounding cable according to the distance
between the grounding point of the PC8910A cabinet and the grounding busbar of
the BC8910A cabinet;

2. Connect on end of the grounding cable to the general grounding busbar of the
BC8910A cabinet, and lead the cable through the cylinder-shaped cabling through
on the right of the PC8910A cabinet. Connect the other end of the cable to the
grounding point of the PC8910A cabinet and fix it;

3. Lead another grounding cable through the left-sided waterproofing module on


bottom of the BC8910A cabinet, connecting one end of the cable to the general

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 27


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

grounding busbar of the BC8910A cabinet and the other end to the adjacent outdoor
copper grounding busbar.

Note: As to the specific cabling hole on the waterproofing module, please


refer to fig 6-1 Cabling Combination for Waterproofing Module within PC8910A
Cabinet.

Remove the rust from the surface of the copper grounding busbar before connection.
Apply antirust paint around the grounding bolt on the busbar and attach a label onto
the ground cable.

6.1.2 Connecting the AC Input Power Cable

Note:

Do not reverse the live wires and neutral wires.

Make sure that the AC input power is cut off during the operation to connect the AC input
cables.

1. Disassemble the screws on the cover of ZXDU58 B900 and remove the cover;

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 28


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

1. Grounding bolt 2. Connection Terminals 3. Power Distribution Unit

4. Signal Interfaces 5. ZXD030 S480 Rectifiers 6. CSU

2. Determine the appropriate length of the power cable, make connecting ends of the
cable with special crimping plier and insert the connector into the connecting holes.

1 Strip the insulation sheath of the power cable, insure the length of the wire
core exposed is left 0.5~1mm after the tubular terminal is plugged.

0.5~1mm

2 Use the special crimping plier for compression as below.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 29


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

3 Press the locking button with a slotted screwdriver, insert the tubular terminal
into the appropriate connector. Pay attention that the tubular terminal can not
be pulled out easily.

Note:

For single-phrase AC, connect the cable ends to B900 indicated by AC Input L and N;

connect the PE end of the AC power cable to the grounding busbar within the
BC8910A cabinet.

Table 6-2 Color Indication for Single-phrase AC


Indicatio One Terminal The Other
PIN Color
n Terminal
1 L Red B900 AC Input AC Power
2 N Blue
3 PE Yellow&Green Grounding busbar

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 30


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

within the cabinet

6.1.3 Connecting the GPS Feeder

1. Lead one end of the GPS feeder into the cabinet from its left-sided cable hole, and
join the cable to the N-type connector for the GPS surge protector fastened on the
left side of the cabinet. Then, tighten the joint clockwise using a spanner whose
torque ranges from 1.7 Nm to 2.0 Nm.

2. Connect the other end of the GPS feeder to the outdoor GPS antenna port and then
perform waterproofing and sealing for it.

Note: The GPS feeder should be connected to the GPS antenna before the GPS
antenna is installed.

Knowledge:

The GPS jumper should be connected to the REF port on the CC board.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 31


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

Note:

The cable holes without cable in the waterproofing module should be sealed with the
waterproofing rubber!

6.2 Cabling Combination for Right-Sided


Waterproofing Module of the BC8910A Cabinet

Table 6-3 Cabling Combination for Right-Sided Waterproofing Module of the BC8910A
Cabinet
Connecting Point Connecting
Identificati Diamet Quanti
Cables inside BC8910A Point outside
on er ty
Cabinet Cabinet
RRU Power DCPD6/DCPD7A RRU
V 17mm 3
Cable
Optical cable/ BBU RRU/Transmiss
D 7mm 1
ETH cable ion

6.2.1 Connecting the RRU Power Cable

1. Determine the appropriate length of the power cable, make connecting ends of the
cable with special crimping plier and insert the connector into the connecting holes.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 32


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

1 Strip the insulation sheath of the power cable, insure the length of the wire
core exposed is left 0.5~1mm after the tubular terminal is plugged.

0.5~1mm

2 Use the special crimping plier for compression as below.

3 Press the locking button with a slotted screwdriver, insert the tubular terminal
into the appropriate connector. Pay attention that the tubular terminal can not
be pulled out easily.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 33


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

When the wire is assembled, press the locking button with a slotted
screwdriver and pull out the wire.
1

2. Connect the other end of the power cable to RRU side.

6.2.2 Connecting the Optical Cable

6.2.2.1 Connecting to the Microwave Equipment

Note: Connect the ends of the ETH cable to ETH01 on CC board! If the
optical fiber is used, please refer to 4.3.2.2 for the fiber operation specifications.

6.2.2.2 Connecting to RRU

1. On the BBU side, remove the white dust cap off the end of the optical cable.

Ensure that the blue lever on the BBU optical module face in a same direction with
the blue clip of the optical cable connector.

Press the blue lock tab and then align the optical cable connector with the port on
the optical module on the BBU before you insert the lock tab into the optical module. If
you want to unplug the optical cable connector, also press the blue lock tab and use care
to pull the connector out.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 34


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

2. Attach labels to the tail of the optical fibers so as to identify different sectors.

The bending radius of the optical cable should be 20 times the length of its diameter.
In most cases, greater than 40 mm is recommended.

At the BBU side, the optical fibers inside the cabinet should be protected using coil
tubes.

Note:

Connect the ends of the optical fibers of sectors 1, 2 and 3 to TX0 RX0, TX1 RX1, and
TX2 RX2 ports on the BPL board in the BBU. Connect the other ends of the optical fibers
to the OPT1 ports of the corresponding RRU.

The cable holes without cable in the waterproofing module should be sealed with the
waterproofing rubber!

7 Connecting Cables inside the Cabinet


Note: There may be changes amongst remarks of every batch of the equipment and
take the remarks on equipment as standard.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 35


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

Figure 7-1 Cabling Combination for Waterproofing Module of the PC8910A Cabinet

Note: Cable hole 1-12 for scenario stack and cable hole 13-20 for scenario
side by side.

1.Water Sensing Cable 2.PE Cable for PC8910A Cabinet

3. Access Control Cable 4.Power Cable for Fan

5. Power Cable for Heating Sheet 6.Spared

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 36


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

7. Power Cable for Battery 8.Heat Detecting Cable for Battery

9. Heat Detecting Cable for Battery 10. Power Cable for Battery

11. Power Cable for Battery 12. Power Cable for Battery

13. Power Cable for Fan 14. Access Control Cable

15. Heat Detecting Expansion Cable for Battery/Heat Detecting Cable for Battery

16. Heat Detecting Expansion Cable for Battery/Heat Detecting Cable for Battery

17.Power Cable for Heating Sheet 18. Power Cable for Battery

19. Power Cable for Battery 20. PE Cable for PC8910A Cabinet

7.1 Cabling Combination for Left-Sided


Cylinder-shaped Cabling Through of the
PC8910A Cabinet

Table 7-1 Cabling Combination for Left-Sided Cylinder-shaped Cabling Through of the
PC8910A Cabinet
Connecting Point Connecting Point
Quantit
No. Cables inside BC8910A inside PC8910A
y
Cabinet Cabinet
Battery Power B900 BATT Input Battery Switch of
1 4
Cable PC8910A Cabinet
Battery Heat B900 FAN/BATT Battery within
2 1
Detecting Cable PC8910A Cabinet

7.1.1 Connecting Power Cables for Batteries

1. To remove the cover plate over the battery switch, use a screwdriver to remove two
screws for fixing the plate cover on top of the PC8910A cabinet.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 37


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

2. Lead the black cable and the red cable through the left-sided cylinder-shaped cable
hole.

(1) As shown in the figure below, connect the A1 end of the black cable to the BATT
input (-48 V) terminal on the left side of the B900 power supply in the BC8910A
cabinet; connect the A2 end to the battery switch terminal on top of the PC8910A
cabinet BAT-.

(2) As shown in figure below, connect the B1 end of the red cable to the "+"3
terminal on the left side of the B900 power supply in the BC8910A cabinet;
connect the B2 end to the battery switch terminal BAT+ on top of the PC8910A
cabinet.

3. Lead one end of another black cable to the black cable terminal (low potential), that
is, C1 or E1 as indicated in the figure below; lead one end of another red cable to
the red cable terminal (high potential), that is, D1 or F1 as also indicated in the figure
below.

Note: In step 3, the ends of the black and red cables at the switch side were
already connected to the battery switch before delivery.

Warning:If only batch batteries (four pieces) are required, the left cable terminals
(e.g. C1 and D1) need to be wrapped with insulation tape.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 38


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

4. Connect the cell terminals in series using metal clips.

5. Install the cover with the two screws when the battery cables are installed.

7.1.2 Connecting the Heat Detecting Cable for the Battery

1. Connect one end of the heat detecting cable to the socket printed with FAN/BATT on
the B900 power supply within the BC8910A.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 39


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

2. Attach the heat detector (after the label is ripped off the detector) to the side of the
battery at the center. The connection of the heat detecting cable for the battery is
finished.

Note:

The cable holes without cable in the waterproofing module should be sealed with the
waterproofing rubber!

7.2 Cabling Combination for Right-Sided


Cylinder-shaped Cabling Through of the
PC8910A Cabinet

Table 7-2 Cabling Combination for Right-Sided Cylinder-shaped Cabling Through of the
PC8910A Cabinet
Connecting Point Connecting Point
Quantit
No. Cables inside BC8910A inside PC8910A
y
Cabinet Cabinet
Water Sensing BFAN5 Water Sensor Socket
1 1
Extension Cable WATER/HUMIDITY within PC8910A

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 40


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

installed at factory Cabinet


Access Control BFAN5 TEC/DOOR Access Control Cable
2 Cable of PC8910A 1 installed at factory Terminal within
Cabinet PC8910A Cabinet
The second
disconnection of
Power Cable for DCPD7A, one of the Fan Power Cable
3 the Fan of 1 Loads indicated by Terminal within
PC8910A Cabinet 1-4; PC8910A Cabinet
One of the Loads of
DCPD6A.
Heater Power B900 AC Output
Switch within PC8910A
4 Cable of PC8910A 1
Cabinet
Cabinet (optional)

7.2.1 Connecting the Water Sensing Expansion Cable


1. Disconnect the cable (bundled at the side of the BC8910A) labeled with WATER from
the water detector.

2. Join the water sensing extension cable (delivered part) to the water sensing cable
labeled with WATER and the detector.

3. Tighten the water detector clockwise in the PC8910A cabinet, as shown in the figure
below.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 41


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

7.2.2 Connecting the Access Control Cable of PC8910A Cabinet

1. Lead the access control cable (bundled at the side of the BC8910A cabinet) into the
PC8910A cabinet.

Note: One end of the access control cable has been connected to port printed
with TEC/DOOR on FCE of the BC8910A at factory.

2. Connect the access control cable to the cable terminal of the PC8910A cabinet so as
to finish the connection of the access control cable.

Note: One end of the access control cable is composed of two sub-cables. One
of the two sub-cables on the left is the dry contact cable as indicated below, and the
other on the right as indicated below is the cable terminal of connecting the access
control cable.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 42


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

7.2.3 Connecting the Power Cable for the Fan of PC8910A Cabinet

1. Lead the power cable for the fan of PC8910A cabinet, bundled at the side of the
BC8910A cabinet, through the right-sided cylinder-shaped cabling through into the
PC8910A cabinet.

2. Connect the other end of the fan power cable to the cable terminal of the PC8910A
cabinet. The connection of the power cable for the fan is finished.

7.2.4 Connecting the Heater Power Cable of PC8910A Cabinet (optional)

1. Connect on end of the power cable for the heater to port indicated by L and N on
the left of B900 power within the BC8910A cabinet, live wire to L and null wire to N,
shown as the figure below.

2. Connect the other ends of the fan power cable to the heater socket within the
PC8910A cabinet. The connection of the power cable for the heater is finished.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 43


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

Note: As to the specific cabling hole on the waterproofing module, please refer
to fig 6-1 Cabling Combination for Waterproofing Module within PC8910A Cabinet.

Tip: Assemble the screen with the six screws of the front screen in the base
when all cables both outside and inside the cabinet are installed. And do not forget to
close the screen at the side of the base!

The bending radius of the cables in the base should be no less than 20 times of the
cable diameter!

Note:

The cable holes without cable in the waterproofing module should be sealed with the
waterproofing rubber!

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 44


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

8 Post-Installation Check

8.1 Cabinet Installation Check


Item Description Result
Check whether the fixing screws of the cabinet (baseband
cabinet and other auxiliary cabinet) are tightened.
Check whether the horizontality and verticality of the cabinet
satisfy the design requirement.
Check whether the distance between cabinets and the
maintenance space of the cabinet satisfy the design
Cabinet requirement.
Installation
Check whether the cabinet (baseband cabinet, PC cabinet,
and other auxiliary cabinet) is stable.
Check whether the top cover of the cabinet is fastened tightly.
In overlapped cabinet installation, check whether the gaps
between two cabinets and the gap of fixing screws are filled
by adhesive.
Insulating
condition Use a multi-meter to check whether it is insulated between the
between cabinet (baseband cabinet, PC cabinet, and other auxiliary
cabinet and cabinet) and ground.
ground

8.2 Cable Installation Check


Item Description Result
Check whether the cable is laid smoothly and whether the
distance between two bundling points satisfies the design
requirement.
In AC power supply mode, check whether the outdoor AC cable
and the power supply terminal of baseband cabinet are
Power connected correctly, and check whether the screws are
cable and fastened tightly.
grounding Check whether the blue cable of power distribution unit is
cable connected tightly with -48 V DC terminal and whether the red
layout cable is connected tightly with the GND terminal of power
distribution unit.
Check whether the power cable is tightly bundled on the cable
trough of the cabinet.
Check whether the protective is connected tightly with the
grounding busbar.
Battery Check whether the cable layout satisfies the design
installation requirement.
and cable Check whether the red power cable is connected tightly with the
layout of positive pole of the battery and whether the blue power cable is

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 45


LTE TDD ZXSDR BS8900A Outdoor Cabinet Quick Installation Guide (B900)

PC cabinet connected tightly with the negative pole of the battery.


Check whether the monitoring cable adheres to the battery
surface and whether the other end of the cable is connected
tightly with the interface of the power module.
If the heating board is available, check whether it is installed
properly.
Check whether the SA cable is connected tightly with the SA
SA cable interface of eBBU.
installation Check whether the grounding cable of SA cable is connected
tightly with the grounding terminal of eBBU.
Check whether the optical fiber layout satisfies the design
Optical requirement.
fiber Between eBBU and RRU, check whether one end of the fiber is
layout connected properly with eBBU and whether the other end of the
fiber is connected properly with RRU.

8.3 Other Checks


Item Description Result
Antistatic Check whether the antistatic wrist strap is installed in the hole at
wrist strap the right side of the cabinet.

Label Check whether the labels are filled correctly and pasted properly.

Cable inlet Check whether each cable inlet is tightly sealed.

ZTE Confidential Proprietary 2015 ZTE CORPORATION. All rights reserved. 46