DATOS DEL ANALISIS PLUVIOMETRICO

CUADRO 01:

CUADRO 02: VALORES DE Imax. ANUAL (mm/24h) - CLASIFICADO EN ORDEN DECRECIENTE

N DE ORDEN Precipitacin Imax Frecuencia f=


( Imax - X )2
(m) mm./24h. m/(n+1)
1 92 0.03125 852.45
2 91.2 0.06250 806.38
3 86 0.09375 538.09
4 80.1 0.12500 299.18
5 79.6 0.15625 282.13
6 77.8 0.18750 224.90
7 76.1 0.21875 176.80
8 74 0.25000 125.37
9 72.1 0.28125 86.43
10 70.2 0.31250 54.71
11 69 0.34375 38.40
12 67.2 0.37500 19.33
13 65.1 0.40625 5.28
14 65 0.43750 4.83
15 63 0.46875 0.04
16 62 0.50000 0.65
17 60.1 0.53125 7.31
18 59 0.56250 14.46
19 57 0.59375 33.68
20 55 0.62500 60.89
21 53.9 0.65625 79.27
22 53 0.68750 96.10
23 51 0.71875 139.32
24 49.2 0.75000 185.05
25 49 0.78125 190.53
26 47.7 0.81250 228.11
27 47 0.84375 249.74
28 45.6 0.87500 295.95
29 45 0.90625 316.95
30 44 0.93750 353.56
31 40 0.96875 519.99
1946.9 6285.88

1).- Clculo de la media arimetica:


X = 1946.9 62.803
31
2).- Clculo de la de la Desviacion Estandar:

SY =
(y i - y) 2
= 14.48
n -1
3).- Distribucion de Valores Extremos para Maximas Anuales:
Sy Tm
y = y- y n + ln . ln
Gn Tm - 1
Donde:
y = Precipitacion mxima anual en 24 horas.
Sy = Desviacin Estndar de los valores de precipitacin mxima en 24 horas (Registrados por ao)
Yn = Media (Gumbel I ), en funcin del N de aos de registro (dato de tabla)
Gn = Desviacion Estandar (Gumbel I ), en funcin del N de aos de registro (dato de tabla)
Tm = Tiempo de retorno de un mximo anual esperado
Como N de aos de registro es igual a : 31 entonces:
Yn = 0.5321
Gn = 1.1159

Luego remplazando valores para un TEMPO DE RETORNO de: 16 aos


Sy Tm
y = y- y n + ln . ln
Gn Tm - 1
y= 91.45 mm

CUADRO 03: DISTRIBUCIN PORCENTUAL DE LA Imax PARA 6, 12 Y 24 HORAS

Precipitacin
Duracin en horas % Precipitacin
(mm)
6 75 68.59
12 80 73.16
24 100 91.45

CUADRO 04: DISTRIBUCIN PORCENTUAL DE LA Imax PARA 1, 2, 3, 4, 5 y 6 HORAS

Precipitacin
Duracion en horas % Precipitacin
(mm)
6 100 68.59
5 92 63.10
4 84 57.61
3 75 51.44
2 64 43.90
1 49 33.61

Entonces el I max de diseo es: I max.diseo = 369.15 mm / h

Con este valor se procedera a determinar el Q de diseo, utilizando el Metodo RACIONAL en cada tramo , con la
formula:

Q = Cm*I*A/3600
CALCULO DE LOS CAUDALES TOTALES QUE LLEGAN A LAS CUNETAS

CUNETA N 01: (Jr. Mariscal Cseres, Mz - A)


Lado Izquierdo

* Clculo de rea techada:

Mz - 01
2
Az-01 = 392.84 392.84 m

* Clculo de rea de via:

Cr - 01
2
Ac-01 = 413.19 413.19 m

CALCULO DEL CAUDAL Q = Cm*I*A/3600

Tipo de Area Cm Consideracion Imax (mm/h) Area (m2) Q=Cm*I*A/3600 (lts/seg)


Area Techada : 0.85 Tejados Impermeables 369.15 392.84 34.24
Area de Via : 0.80 Pavimento de Asfalto 369.15 413.19 33.90
Qtotal = 68.14

Lado posterior

* Clculo de rea techada:

Mz - 01
2
Az-01 = 2913.80 2913.80 m

* Clculo de rea de via:

Cr - 01
2
Ac-01 = 775.31 775.31 m

CALCULO DEL CAUDAL Q = Cm*I*A/3600

Tipo de Area Cm Consideracion Imax (mm/h) Area (m2) Q=Cm*I*A/3600 (lts/seg)


Area Techada : 0.85 Tejados Impermeables 369.15 2913.80 253.97
Area de Via : 0.80 Pavimento de Asfalto 369.15 775.31 63.60
Qtotal = 317.57

Lado derecho

* Clculo de rea techada:

Mz - 01
2
Az-01 = 87.24 87.24 m

* Clculo de rea de via:

Cr - 01
2
Ac-01 = 606.18 606.18 m

CALCULO DEL CAUDAL Q = Cm*I*A/3600

Tipo de Area Cm Consideracion Imax (mm/h) Area (m2) Q=Cm*I*A/3600 (lts/seg)


Area Techada : 0.85 Tejados Impermeables 369.15 87.24 7.60
Area de Via : 0.80 Pavimento de Asfalto 369.15 606.18 49.73
Qtotal = 57.33
Corte Tipico de una Seccin Transversal
(bosquejo, detalle final en el plano)

Eje de Via
vereda municipal

vereda privada
cuneta

DISEO HIDRAULICO DE LA CUNETA N 01:

Lado derecho

Clculo de la seccin de la cuneta (Mtodo Manning) :


Luego con el lado de mayor caudal y asiendo uso de la formula de MANNING, disearemos una seccin a Mxima

Datos Generales :

Q= 0.0573 m3/seg
n= 0.017 (Para canales revestidos con concreto)
S= 3.30% Para efectos de calculo S ( Pendiente del cunetas), consideraremos valores extraidos
perfil longitudinal
Z= 0

Diseo a M.E. H :

y Q * n * 1.49 b
= 8 / 3 1/ 2 = 2 * Tang b y 1
; = 90 = 2 = = 0.5
b b S 0
y
y b 2

De la tabla N 01 (Anexos) se obtiene :


y/b Z = 0 Q * n * 1.49 0.295
=
0.50 0.295 b8 / 3 S 1/ 2

Remplazando valores Generales:

Q * n * 1.49
3/8

b = = 0.258 m b= 0.258 m
1/ 2
0.295 * S

Valor constructuvo = 0.30

Remplazando el valor de "b" en (**) :

y = 0.50 x 0.30 = 0.15 m

Calculos de los elementos de seccin :


f=0.05m
*) .- Borde Libre : f = 0.33 x Y = 0.33 x 0.15 H = 0.20 m
_ f= 0.05 m Y= 0.15m
*) .- Altura : H =Y + f = 0.15+0.05
_ H= 0.20 m
*) .- Base : b
_ b= 0.30 m b = 0.30 m
*) .- Perimetro Mojado : Pm =2Y + b = 2*0.15+0.30
_ Pm = 0.600 m
*) .- Area Hidraulica : A = b x Y =0.30*0.15
2
_ A = 0.045 m
*) .- Radio Hidraulico : R = A/Pm =0.045/0.60
_ R = 0.075 m
Verificacin por manning del caudal :

AR 2 / 3 S 1 / 2 ^(2/3)
Q= Q = 0.045*0.075 0.033^1/2
n 0.017
Q = 0.086 m3/seg

Q = 0.086 m3/seg > Qdiseo = 0.057 m3/seg OK

*).- Verificacin por velocidad :

V= Q
A
V= 0.086
0.045 = 1.90 m /seg

V= 1.90 m /seg > 0.80 m/sg (Vmin por sedimentacion) OK

Lado Posterior

Clculo de la seccin de la cuneta (Mtodo Manning) :


Luego con el lado de mayor caudal y asiendo uso de la formula de MANNING, disearemos una seccin a Mxima

Datos Generales :

Q= 0.3176 m3/seg
n= 0.017 (Para canales revestidos con concreto)
S= 2.10% Para efectos de calculo S ( Pendiente del cunetas), consideraremos valores extraidos
perfil longitudinal
Z= 0

Diseo a M.E. H :

y Q * n * 1.49 b
= = 2 * Tang ; b y 1
b b8 / 3 S 1/ 2 y = 900 = 2 = = 0.5
y b 2

De la tabla N 01 (Anexos) se obtiene :

y/b Z = 0 Q * n * 1.49 0.295


=
0.50 0.295 b8 / 3 S 1/ 2

Remplazando valores Generales:

Q * n * 1.49
3/8

b = = 0.535 m b= 0.535 m
1/ 2
0.295 * S

Valor constructuvo = 0.55

Remplazando el valor de "b" en (**) :

y = 0.50 x 0.55 = 0.275 m


Calculos de los elementos de seccin :
f=0.125 m
*) .- Borde Libre : f = 0.33 x Y = 0.33 x 0.275 H = 0.40 m
_ f= 0.09 m Y= 0.275m
*) .- Altura : H =Y + f = 0.275+0.09
H= 0.37 m
H= 0.40 b = 0.55 m
*) .- Base : b
_ b= 0.55 m
*) .- Perimetro Mojado : Pm =2Y + b = 2*0.275+0.55
_ Pm = 1.100 m
*) .- Area Hidraulica : A = b x Y =0.55*0.275
2
_ A = 0.151 m
*) .- Radio Hidraulico : R = A/Pm =0.151/1.10
_ R = 0.138 m

Verificacin por manning del caudal :

AR 2 / 3 S 1 / 2 ^(2/3)
Q= Q = 0.151*0.138 0.02.1^1/2
n 0.017
Q = 0.343 m3/seg

Q = 0.343 m3/seg > Qdiseo = 0.318 m3/seg OK

*).- Verificacin por velocidad :

V= Q
A
V= 0.343
0.151 = 2.27 m /seg

V= 2.27 m /seg > 0.80 m/sg (Vmin por sedimentacion) OK

Lado Izquierdo

Clculo de la seccin de la cuneta (Mtodo Manning) :


Luego con el lado de mayor caudal y asiendo uso de la formula de MANNING, disearemos una seccin a Mxima

Datos Generales :

Q= 0.3857 m3/seg
n= 0.017 (Para canales revestidos con concreto)
S= 2.70% Para efectos de calculo S ( Pendiente del cunetas), consideraremos valores extraidos
perfil longitudinal
Z= 0

Diseo a M.E. H :

y Q * n * 1.49 b
= = 2 * Tang ; b y 1
b b8 / 3 S 1/ 2 y = 900 = 2 = = 0.5
y b 2

De la tabla N 01 (Anexos) se obtiene :

y/b Z = 0 Q * n * 1.49 0.295


=
0.50 0.295 b8 / 3 S 1/ 2

Remplazando valores Generales:

Q * n * 1.49
3/8

b = = 0.548 m b= 0.548 m
1/ 2
0.295 * S

Valor constructuvo = 0.55

Remplazando el valor de "b" en (**) :

y = 0.50x 0.55 = 0.275 m

Calculos de los elementos de seccin : f=0.125 m


*) .- Borde Libre : f = 0.33 x Y = 0.33 x 0.275 H = 0.40 m
_ f= 0.09 m Y= 0.275m
*) .- Altura : H =Y + f = 0.15+0.05
H= 0.37 m
H= 0.40 m
*) .- Base : b b = 0.55 m
_ b= 0.55 m
*) .- Perimetro Mojado : Pm =2Y + b = 2*0.275+0.55
_ Pm = 1.100 m
*) .- Area Hidraulica : A = b x Y =0.55*0.275
2
_ A = 0.151 m
*) .- Radio Hidraulico : R = A/Pm =0.151/1.10
_ R = 0.138 m

Verificacin por manning del caudal :

^(2/3)
AR 2 / 3 S 1 / 2 Q = 0.151*0.138 0.027^1/2
Q=
n 0.017
3
Q = 0.389 m /seg

Q = 0.389 m3/seg > Qdiseo = 0.386 m3/seg OK

*).- Verificacin por velocidad :

V= Q
A
V= 0.389
0.151 = 2.57 m /seg

V= 2.57 m /seg > 0.80 m/sg (Vmin por sedimentacion) OK

CUNETA N 02: (Jr. Mariscal Cseres, Mz - B)

Lado Izquierdo
* Clculo de rea techada:

Mz - 01
2
Az-01 = 392.84 392.84 m

* Clculo de rea de via:

Cr - 01
2
Ac-01 = 413.19 413.19 m

CALCULO DEL CAUDAL Q = Cm*I*A/3600

Tipo de Area Cm Consideracion Imax (mm/h) Area (m2) Q=Cm*I*A/3600 (lts/seg)


Area Techada : 0.85 Tejados Impermeables 0.00 392.84 0.00
Area de Via : 0.80 Pavimento de Asfalto 0.00 413.19 0.00
Qtotal = 0.00
Lado posterior

* Clculo de rea techada:

Mz - 01
2
Az-01 = 2913.80 2913.80 m

* Clculo de rea de via:

Cr - 01
2
Ac-01 = 775.31 775.31 m

CALCULO DEL CAUDAL Q = Cm*I*A/3600

Tipo de Area Cm Consideracion Imax (mm/h) Area (m2) Q=Cm*I*A/3600 (lts/seg)


Area Techada : 0.85 Tejados Impermeables 0.00 2913.80 0.00
Area de Via : 0.80 Pavimento de Asfalto 0.00 775.31 0.00
Qtotal = 0.00

Lado derecho

* Clculo de rea techada:

Mz - 01
2
Az-01 = 87.24 87.24 m

* Clculo de rea de via:

Cr - 01
2
Ac-01 = 606.18 606.18 m

CALCULO DEL CAUDAL Q = Cm*I*A/3600

Tipo de Area Cm Consideracion Imax (mm/h) Area (m2) Q=Cm*I*A/3600 (lts/seg)


Area Techada : 0.85 Tejados Impermeables 0.00 87.24 0.00
Area de Via : 0.80 Pavimento de Asfalto 0.00 606.18 0.00
Qtotal = 0.00

Corte Tipico de una Seccin Transversal


(bosquejo, detalle final en el plano)

vereda municipal Eje de Via

vereda privada cuneta

DISEO HIDRAULICO DE LA CUNETA N 01:

Lado derecho

Clculo de la seccin de la cuneta (Mtodo Manning) :


Luego con el lado de mayor caudal y asiendo uso de la formula de MANNING, disearemos una seccin a Mxima

Datos Generales :

Q= 0.0000 m3/seg
n= 0.017 (Para canales revestidos con concreto)
S= 3.30% Para efectos de calculo S ( Pendiente del cunetas), consideraremos valores extraidos
perfil longitudinal
Z= 0

Diseo a M.E. H :

y Q * n * 1.49 b
= = 2 * Tang ; b y 1
b b8 / 3 S 1/ 2 y = 900 = 2 = = 0.5
y b 2

Calculamos los Demas Valores Geometricos:

H= ###### m = 1.1 cm.

T= ##### m = 2.2 cm.

B= ##### m = 3.2 cm

De la tabla N 01 (Anexos) se obtiene :

y/b Z = 0 Q * n * 1.49 0.295


=
0.50 0.295 b8 / 3 S 1/ 2

Remplazando valores Generales:

Q * n * 1.49
3/8

b = = 0.000 m b= 0.000 m
1/ 2
0.295 * S

Valor constructuvo = 0.30

Remplazando el valor de "b" en (**) :

y = x
0.50 0.30 = 0.15 m

Calculos de los elementos de seccin :


f=0.05m
*) .- Borde Libre : f = 0.33 x Y = 0.33 x 0.15 H = 0.20 m
_ f= 0.05 m Y= 0.15m
*) .- Altura : H =Y + f = 0.15+0.05
_ H= 0.20 m
*) .- Base : b
_ b= 0.30 m b = 0.30 m
*) .- Perimetro Mojado : Pm =2Y + b = 2*0.15+0.30
_ Pm = 0.600 m
*) .- Area Hidraulica : A = b x Y =0.30*0.15
2
_ A = 0.045 m
*) .- Radio Hidraulico : R = A/Pm =0.045/0.60
_ R = 0.075 m

Verificacin por manning del caudal :


^(2/3)
AR 2 / 3 S 1 / 2 Q = 0.045*0.075 0.033^1/2
Q=
n 0.017
Q = 0.086 m3/seg

Q = 0.086 m3/seg > Qdiseo = 0.000 m3/seg OK

*).- Verificacin por velocidad :

V= Q
A
V= 0.086
0.045 = 1.90 m /seg
=
V= 1.90 m /seg > 0.80 m/sg (Vmin por sedimentacion) OK

Lado Posterior

Clculo de la seccin de la cuneta (Mtodo Manning) :


Luego con el lado de mayor caudal y asiendo uso de la formula de MANNING, disearemos una seccin a Mxima

Datos Generales :

Q= 0.0000 m3/seg
n= 0.017 (Para canales revestidos con concreto)
S= 2.10% Para efectos de calculo S ( Pendiente del cunetas), consideraremos valores extraidos
perfil longitudinal
Z= 0

Diseo a M.E. H :

y Q * n * 1.49 b
= = 2 * Tang ; b y 1
b b8 / 3 S 1/ 2 y = 900 = 2 = = 0.5
y b 2

De la tabla N 01 (Anexos) se obtiene :

y/b Z = 0 Q * n * 1.49 0.295


=
0.50 0.295 b8 / 3 S 1/ 2

Remplazando valores Generales:

Q * n * 1.49
3/8

b = = 0.000 m b= 0.000 m
1/ 2
0.295 * S

Valor constructuvo = 0.55

Remplazando el valor de "b" en (**) :

y = 0.50 x 0.55 = 0.275 m

Calculos de los elementos de seccin :


f=0.125 m
*) .- Borde Libre : f = 0.33 x Y = 0.33 x 0.275 H = 0.40 m
_ f= 0.09 m Y= 0.275m
*) .- Altura : H =Y + f = 0.275+0.09
H= 0.37 m
H= 0.40 b = 0.55 m
*) .- Base : b
_ b= 0.55 m
*) .- Perimetro Mojado : Pm =2Y + b = 2*0.275+0.55
_ Pm = 1.100 m
*) .- Area Hidraulica : A = b x Y =0.55*0.275
2
_ A = 0.151 m
*) .- Radio Hidraulico : R = A/Pm =0.151/1.10
_ R = 0.138 m

Verificacin por manning del caudal :


^(2/3)
AR 2 / 3 S 1 / 2 Q = 0.151*0.138 0.02.1^1/2
Q=
n 0.017
3
Q = 0.343 m /seg

Q = 0.343 m3/seg > Qdiseo = 0.000 m3/seg OK

*).- Verificacin por velocidad :

V= Q
A
V= 0.343
0.151 = 2.27 m /seg

V= 2.27 m /seg > 0.80 m/sg (Vmin por sedimentacion) OK


Lado Izquierdo

Clculo de la seccin de la cuneta (Mtodo Manning) :


Luego con el lado de mayor caudal y asiendo uso de la formula de MANNING, disearemos una seccin a Mxima

Datos Generales :

Q= 0.0000 m3/seg
n= 0.017 (Para canales revestidos con concreto)
S= 2.70% Para efectos de calculo S ( Pendiente del cunetas), consideraremos valores extraidos
perfil longitudinal
Z= 0

Diseo a M.E. H :

y Q * n * 1.49 b
= = 2 * Tang ; b y 1
b b8 / 3 S 1/ 2 y = 900 = 2 = = 0.5
y b 2

De la tabla N 01 (Anexos) se obtiene :

y/b Z = 0 Q * n * 1.49 0.295


=
0.50 0.295 b8 / 3 S 1/ 2

Remplazando valores Generales:

Q * n * 1.49
3/8

b = = 0.000 m b= 0.000 m
1/ 2
0.295 * S

Valor constructuvo = 0.55

Remplazando el valor de "b" en (**) :

y = 0.50x 0.55 = 0.275 m

Calculos de los elementos de seccin : f=0.125 m


*) .- Borde Libre : f = 0.33 x Y = 0.33 x 0.275 H = 0.40 m
_ f= 0.09 m Y= 0.275m
*) .- Altura : H =Y + f = 0.15+0.05
H= 0.37 m
H= 0.40 m
*) .- Base : b b = 0.55 m
_ b= 0.55 m
*) .- Perimetro Mojado : Pm =2Y + b = 2*0.275+0.55
_ Pm = 1.100 m
*) .- Area Hidraulica : A = b x Y =0.55*0.275
2
_ A = 0.151 m
*) .- Radio Hidraulico : R = A/Pm =0.151/1.10
_ R = 0.138 m

Verificacin por manning del caudal :


^(2/3)
AR 2 / 3 S 1 / 2 Q = 0.151*0.138 0.027^1/2
Q=
n 0.017
3
Q = 0.389 m /seg

Q = 0.389 m3/seg > Qdiseo = 0.000 m3/seg OK

*).- Verificacin por velocidad :

V= Q
A
V= 0.389
0.151 = 2.57 m /seg

V= 2.57 m /seg > 0.80 m/sg (Vmin por sedimentacion) OK