Page 1 of 13
WI/OPR - E019
METHOD OF STATEMENT FOR MAIN Rev 0
FEEDER SYSTEM WORKS
Date -
CONTENTS :
1. SCOPE
1.1. General Rules and Information
1.2. Work Coverage
1.3. Override
1.4. Recognition
2. MATERIALS
2.1. Resources and Specifications
2.2. Procurement, Handling and Storage
2.3. Check and Inspection
7. DRAWING
8. FORMS
8.1 Inspection Control Sheet FM/OPR E0
8.2 Material Delivery Receiving Inspection Report FM/OPR E026
8.3 Request for Inspection FM/OPR E027
Page 2 of 13
WI/OPR - E019
METHOD OF STATEMENT FOR MAIN Rev 0
FEEDER SYSTEM WORKS
Date -
Project
Industrial Plant (Mining, Oil & Gas, etc) Building : (Low Rise/High Rise)
Project Category
Power Plant Others :
Location
Owner
Designer/Engineer
Contractor
Sub-Contractor
Number of Storey
Building Height
Page 3 of 13
WI/OPR - E019
METHOD OF STATEMENT FOR MAIN Rev 0
FEEDER SYSTEM WORKS
Date -
1. SCOPE
1.3. Override
For any instance that there are some changes of works occur that are not mentioned in this
Method of Statement shall be properly discussed immediately and the outcome of
discussion shall be absolutely followed and agreed procedures may override.
1.4. Recognition
To avoid any inherent mistakes during execution of this particular work, the contents of this
Method of Statements shall be thoroughly verified. A copy shall be distributed and
recognized by all concerns prior to the commencement of works.
2. MATERIALS
Table 1
Submittal Approval
Item Description
Reference Date
Page 4 of 13
WI/OPR - E019
METHOD OF STATEMENT FOR MAIN Rev 0
FEEDER SYSTEM WORKS
Date -
Table 2
Page 5 of 13
WI/OPR - E019
METHOD OF STATEMENT FOR MAIN Rev 0
FEEDER SYSTEM WORKS
Date -
Preparation :
Material Approval SM / PM/ENG SM : Site Manager
Shop Drawing PM : Project Manager
Method Statement ENG : Engineer
No Customer
2. Approved ?
Yes
3. Material ;
Vendor Selection Purchasing
Procurement
4. Material On site
Inspection material
Warehouse control /Stock S M / Staff SM : Site Manager
Card
5. Installation Staff
7. Repair
Not Good
* 6. * Item 6 Inspection :
Inspection ?
Internal Inspection by PT.
Good Kinden Indonesia
External Inspection by
Owner / Main Con
If found deviation, should
8. Completion
repaired by Project Team
Photograph for Report
At Inspection event
Page 6 of 13
WI/OPR - E019
METHOD OF STATEMENT FOR MAIN Rev 0
FEEDER SYSTEM WORKS
Date -
Page 7 of 13
WI/OPR - E019
METHOD OF STATEMENT FOR MAIN Rev 0
FEEDER SYSTEM WORKS
Date -
4.4.1 For installation method of cables in a conduit the following steps shall be
observed:
A. Verify and study carefully the route area and panel designation prior to pulling of
cables in the conduits.
B. Double check for locknut and bushing if properly installed for GIC pipes and end
bell for high impact conduit.
C. Insert guide wires and pulling string inside the conduit.
D. Tie tightly one end of sets of wires to the pulling string and make sure it will not
detached while inside the conduit then wrap with electrical tape around the joint.
Page 8 of 13
WI/OPR - E019
METHOD OF STATEMENT FOR MAIN Rev 0
FEEDER SYSTEM WORKS
Date -
E. Check the distance of pull box to pull box (30m or less), if the distance is long and
passing through maximum offsets, it is advisable to use pulling compound to
protect wire insulation from damage.
F. After pulling the cables, cut with the desired length. Take note before cutting of
cables in the panel: see to it that the length of cable has enough allowance for
looping and termination.
4.4.2 For installation method of cables in a cable rack the following steps shall be
observed:
A. Install order of cables from longest to shortest route.
B. Install order of cables from thickest to thinnest sizes.
C. Install cable tag as close as possible to the panel. ( or coordinate with person in
charge for the location of cable tag )
D. Install the cable straight as far as possible avoiding the cables from meandering or
intersecting.
E. Bind and support the cables with binding bonds at intervals of 2 meters or less for
vertical part and 2-6 meters for horizontal part.
F. Ensure the cables are not very close to information/communication/control cables
to avoid interference and keep a maximum distance of 150mm or more, if
impossible separator. (100mm high shall be insert)
4.4.3 For installation method of cables in a cable pit the following steps shall be
observed:
A. Ensure that the pit is thoroughly clean and sufficiently dried-up.
B. If a low voltage cable and high voltage cable are installed in the same pit, a metallic
separator shall be provided and must be properly grounded.
C. Proper looping shall be considered inside the pit especially for sinkable soil.
4.4.5 For loop check and Circuit tracing of cables the following should be observe:
A. Check again the tag name and panel board designation, but by this time, tester
instrument is needed for actual identification.
Page 9 of 13
WI/OPR - E019
METHOD OF STATEMENT FOR MAIN Rev 0
FEEDER SYSTEM WORKS
Date -
Personnel
used hand gloves
cut and hand injury and
1 Cable stripping and extra care for
injury lost of
cutting is advised
time
Personnel
Cable laying / Hand allergy to injury and
2 Wear hand gloves
pulling cables and dust lost of
time
Personnel
injury and
3 Scaffoldings Fall from heights Wear safety belts
lost of
time
hand
4 Crimping Finger pinch work cautiously
injury
Page 10 of 13
WI/OPR - E019
METHOD OF STATEMENT FOR MAIN Rev 0
FEEDER SYSTEM WORKS
Date -
Page 11 of 13
WI/OPR - E019
METHOD OF STATEMENT FOR MAIN Rev 0
FEEDER SYSTEM WORKS
Date -
7. DRAWING
Page 12 of 13
WI/OPR - E019
METHOD OF STATEMENT FOR MAIN Rev 0
FEEDER SYSTEM WORKS
Date -
8. FORMS
8.1. Inspection Control Sheet FM/OPR E0
8.2. Material Delivery Receiving Inspection Report FM/OPR E026
8.3. Request for Inspection FM/OPR E027
Page 13 of 13