WI/OPR - E021
METHOD OF STATEMENT FOR CABLE Rev 0
SYSTEM WORKS
Date -
CONTENTS :
1. SCOPE
1.1. General Rules and Information
1.2. Work Coverage
1.3. Override
1.4. Recognition
2. MATERIALS
2.1. Resources and Specifications
2.2. Procurement, Handling and Storage
2.3. Check and Inspection
7. DRAWING
8. FORMS
8.1 Inspection Control Sheet FM/OPR E014
8.2 Material Delivery Receiving Inspection Report FM/OPR E026
8.3 Request for Inspection FM/OPR E027
Page 2 of 12
WI/OPR - E021
METHOD OF STATEMENT FOR CABLE Rev 0
SYSTEM WORKS
Date -
Project
Industrial Plant (Mining, Oil & Gas, etc) Building : (Low Rise/High Rise)
Project Category
Power Plant Other :
Location
Owner
Designer/Engineer
Contractor
Sub-Contractor
Number of Storey
Building Height
Page 3 of 12
WI/OPR - E021
METHOD OF STATEMENT FOR CABLE Rev 0
SYSTEM WORKS
Date -
1. SCOPE
1.3. Override
For any instance that there are some changes of works occur that are not mentioned in
this Method of Statement shall be properly discussed immediately and the outcome of
discussion shall be absolutely followed and the agreed procedures may override.
1.4. Recognition
To avoid any inherent mistakes during execution of this particular work, the contents of
this Method of Statements shall be thoroughly verified. A copy shall be distributed and
recognized by all concerns prior to the commencement of works.
2. MATERIALS
Table 1
Submittal Approval
Item Description
Reference Date
Page 4 of 12
WI/OPR - E021
METHOD OF STATEMENT FOR CABLE Rev 0
SYSTEM WORKS
Date -
Table 2
Page 5 of 12
WI/OPR - E021
METHOD OF STATEMENT FOR CABLE Rev 0
SYSTEM WORKS
Date -
Preparation :
Material Approval SM / PM/ENG SM : Site Manager
Shop Drawing PM : Project Manager
Method Statement ENG : Engineer
No Customer
2. Approved ?
Yes
3. Material ;
Vendor Selection Purchasing
Procurement
4. Material On site
Inspection material
Warehouse control /Stock S M / Staff SM : Site Manager
Card
5. Installation Staff
7. Repair
Not Good
* 6. * Item 6 Inspection :
Inspection ?
Internal Inspection by PT.
Good Kinden Indonesia
External Inspection by
Owner / Main Con
If found deviation, should
8. Completion
repaired by Project Team
Photograph for Report
At Inspection event
Page 6 of 12
WI/OPR - E021
METHOD OF STATEMENT FOR CABLE Rev 0
SYSTEM WORKS
Date -
Page 7 of 12
WI/OPR - E021
METHOD OF STATEMENT FOR CABLE Rev 0
SYSTEM WORKS
Date -
4.3. References
4.3.1 Maximum number of conductor in metric sizes conduit (CMWD 05 04/26)
4.3.2 Crimping of wires (CMWD E 1202)
4.3.3 Insulation process (CMWD E 1203)
4.3.4 Connection of wires to devices and fixtures (CMWD E 1206/1209)
4.4.1 For installation method of wires in a conduit the following steps shall be
observed:
A. Verify and study carefully the circuit homeruns and panel designation prior to
pulling of wires in the conduits.
B. Double check for locknut and bushing if properly installed for E pipes and end bell
for high impact conduit.
C. Insert guide wires and pulling string inside the conduit.
Page 8 of 12
WI/OPR - E021
METHOD OF STATEMENT FOR CABLE Rev 0
SYSTEM WORKS
Date -
D. Tie tightly one end of sets of wires to the pulling string and make sure it will not
detached while inside the conduit then wrap with electrical tape around the joint.
E. Check the distance of pull box to pull box, if the distance is long and passing
through maximum offsets, it is advisable to use pulling compound to protect wire
insulation from damage.
F. After pulling the wires, cut with the desired length. Take note before cutting of wires
in the panel: see to it that the length of has enough allowance for wire loop.
4.4.2 For loop check and Circuit tracing of wires the following should be observe:
A. Check again the circuit homeruns and panel board designation, but by this time,
tester instrument is needed for actual identification.
B. Using handheld UHF/VHF radio communication is important, first identify the circuit
number of wire inside the panel board then locate the other end outside, as soon
as already located try to couple then check for the continuity and repeat the
procedures until ensure that the circuits are correct.
Page 9 of 12
WI/OPR - E021
METHOD OF STATEMENT FOR CABLE Rev 0
SYSTEM WORKS
Date -
Nature of
item Hazards Effects Countermeasures
Works
Personnel
used hand gloves
cut and hand injury and
1 Wire stripping and extra care for
injury lost of
cutting is advised
time
Personnel
Hand allergy to injury and
2 Wire pulling Wear hand gloves
cables and dust lost of
time
Personnel
injury and
3 Scaffoldings Fall from heights Wear safety belts
lost of
time
hand
4 Crimping Finger pinch work cautiously
injury
Page 10 of 12
WI/OPR - E021
METHOD OF STATEMENT FOR CABLE Rev 0
SYSTEM WORKS
Date -
7. DRAWING
Page 11 of 12
WI/OPR - E021
METHOD OF STATEMENT FOR CABLE Rev 0
SYSTEM WORKS
Date -
8. FORMS
8.1. Inspection Control Sheet FM/OPR E014
8.2. Material Delivery Receiving Inspection Report FM/OPR E026
8.3. Request for Inspection FM/OPR E027
Page 12 of 12