Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
ABSTRACT
Unlike in other areas, construction performance and learning factor analysis in LNG
tank construction have been limited, compared to their important roles in LNG facilities.
The LNG tank construction cost is the largest single cost in a receiving terminal. The
specific construction cost of LNG storage tanks have decreased with an increase in
storage capacity. However, quantitatively utilizing the past experiences in cost estimation
and profitability analysis was a long term unsettled task in LNG projects.
Learning curve resources were accumulated by Kogas and KBR from three different
types of storage tanks: membrane type aboveground tanks, 9% Nickel full containment
storage tanks, and membrane type in-ground tanks (total 28 tanks, each type built at the
same site). Case based construction analysis was performed in view of tank type,
construction method, construction duration, accumulated experience, storage capacity,
and other parameters that affect construction performance. This paper presents the effects
of the Learning Curve Management (LCM) on construction performance and cost
reduction based on past experiences. A re-learning factor is incorporated in the learning
function and the ultimate level of performance has been implanted in the new model of
the learning curve. This paper demonstrates that the LCM, derived from the case based
construction analysis, provides a reasonable basis of cost analysis, cost estimation, and
profitability studies, all of which are related to the evaluation of future costs and
confidence level in an analysis.
RESUME
Contrairement dautres secteurs, lexcution de performance et lanalyse dtude
factorielle dans la construction de rservoirs de GNL ont t inactivement limits
jusquici, compar leurs rles importants dans les facilits de GNL. Le cot de
construction de rservoirs de GNL est le cot singulier le plus important dans un terminal
mthanier. Le cot spcifique de construction de rservoirs de stockage de GNL a
diminu avec laugmentation des capacits de stockage. Cependant, utiliser
PO-08.1
SESSIONS CONTENTS
Poster PO-08
INTRODUCTION
The construction of an LNG storage tank requires the longest construction period in
LNG plants. Its cost is also the largest single cost in LNG terminal construction.
Technical innovations and cost reductions in LNG facilities, such as in LNG storage
tanks, have strengthened LNG relative to other energy sources. Ever since the worlds
first LNG storage facility was built at Arzew, Algeria, in 1962, over 275 units of LNG
storage tanks, of which capacity range is from 30,000 m3 to 200,000 m3, have been built
and operated thus far.
Over the last three decades there have been no articles or papers focused on LNG tank
construction performance analysis. Most companies do not measure learning curve
performance in construction activities. In order to investigate the effect of past experience
on construction performance (cost and construction period) with the same type of the
LNG storage tanks, learning curve theory is introduced for a logical evaluation of
construction performance. Construction histories of three different types of LNG storage
tanks (totaling 28 tanks) were selected and analyzed by Kogas and KBR in view of cost
(escalated as of the end of 2001) and time (construction duration excluding foundation).
Korea Gas Corporation (Kogas) constructed three (3) above-ground membrane tanks
at Pyeong-Taek terminal in 1986 and added one more membrane tank in 1987. Kogas
performed an expansion project which added six (6) more storage tanks at the same site.
All of them are above-ground membrane tank and their capacities are 100,000 m3. Ten
(10) units of pre-stressed concrete (PC) 9% Nickel full containment (FC) type tanks have
been constructed over a time interval at the Incheon terminal. The terminal has also
constructed eight (8) units of membrane type underground storage tanks of which
capacity ranges from 140,000 to 200,000 m3. These three types of storage tanks are the
most widely used storage tanks in LNG terminals as well as in LNG plants.
The objectives of this study are to develop the construction analysis process and to
investigate the effects of learning based on the construction performance from the past
experience. The investigation results were used to develop a new learning curve model
PO-08.2
SESSIONS CONTENTS
Poster PO-08
which allows estimating construction cost and duration, and for profitability analysis with
a high confidence level.
n
y = C1 exp + C 3 (1)
2
C
where,
y : construction period for n unit of tank constructed
n : number of tanks constructed
C1 : constant reflecting storage volume and type
C2 : constant reflecting the construction performance
C3 : constant reflecting the ideal minimum construction period for the type of tank
50
48
Construction Period, [mon]
46
44
40
C3
38
36
1 3 5 7 9 11
PO-08.3
SESSIONS CONTENTS
Poster PO-08
The learning-curve function is a relationship of variables C1, C2, and C3. C1 implies a
readiness, ability to be prepared, and a difficulty in the area or in technology. C2 relates to
how fast the organization is learning. C3 is the level of performance for any company or
contractor. This level reflects the companys technical and operational capacity and
management policies as it pertains to storage tank construction.
One common way of assessing tank construction performance is the specific LNG
tank construction cost, defined as a cost for unit storage volume ($/m3). However,
performance should also relate to the rate of learning (C2), the improvement of tank
construction in a series (C1), and the capability to maintain an achieved performance level
(C3). The capability of a company to construct LNG tanks directly relates to the
management of these variables, C1, C2, and C3. These specifically involve the successful
learning through experience, labor skills available, regional experience, employee
training, keeping well-trained employees, understanding policies and procedures by the
company, and the availability of tools and information accessible to the company.
Greater learning leads to better possibilities of long-lasting improvement [1]. The
higher the level of response accuracy to the construction results, the better the chances of
increasing construction performance and capacity. Construction personnel experience is
critical to both the reduction of inefficient work and to the improvement of construction
capabilities. Construction experience is a composite of local type experience - tanks
constructed with the same type design. It also requires general training for each
construction process. Likewise, a captain needs skills and training in order to navigate an
LNG carrier.
Overall construction performance has been greatly influenced by a companys
construction capacity and tank construction personnel. The less the organizational
construction capacity, the more the organization is at the mercy of the available tank
construction personnels experience in interpreting the specific work procedure and
organizing the low-level workforce. That is why a company that depends solely on its
construction personnel for performance becomes unproductive when personnel leave the
organization [2].
PO-08.4
SESSIONS CONTENTS
Poster PO-08
study have well-established plans that help minimize the number of constraints, the
effects of expansion on construction capabilities are considered insignificant.
The following tables summarize the learning curve resources used in the construction
analysis process and in the LCM. The construction duration excludes the period for site
improvement and piling because the required period varies from location to location,
even within the same site. Table 1 shows the construction history of the membrane type
above-ground tank. All of these tanks have a capacity of 100,000 m3 and were
constructed by the same contractor. A long time interval (about 6 years) exists between
the first tanks (# 4) in operation and the first expansion tank (# 5) in operation.
Table 2 presents the history of the PC 9% Nickel FC type aboveground tanks. All of
these tanks at the Incheon terminal have the same as 100,000 m3 and were consecutively
constructed by one contractor.
The construction history of membrane type inground tanks are shown in Table 3. The
first four of each type of tank (#1 - 2, #3 - 4) have been constructed by two different
companies (A, B). The remaining two tanks have just been completed and two are still
under construction by a different contractor (C).
PO-08.5
SESSIONS CONTENTS
Poster PO-08
n
y = 10.19 exp + 30.9 (2)
7.34
The required period of the first tank construction was about 38 months. Site
improvements and piling are excluded in this period in order to accurately evaluate the
accurate effects of LCM on construction performance. The duration for the foundation
(including piling) varies depending on the source rock distribution, even with tanks (same
design and capacity) constructed at the same site. The required period for the 2nd and 3rd
were almost the same because the tanks were constructed simultaneously.
PO-08.6
SESSIONS CONTENTS
Poster PO-08
However, the construction of LNG tank #5 began 6 years later after the construction
of tank #4. The LC shows the re-learning effect. The requirement of re-learning can be
depicted through the company that lost experienced personnel, causing low learning
levels within the company. The re-learning process rapidly recovers the companys
construction capabilities. The normal expected construction period would be 31 months.
However, the re-learning adds 6.0 more months to the schedule. If the company
effectively maintains its construction capabilities, it could decrease the re-learning period.
After re-learning the construction process, construction performance dramatically
improves. The re-learning effect (C2) is almost twice as faster than in the case where the
company lacked previous experience.
A tank was constructed almost every year throughout the expansion stage. Therefore,
a deduction can be made which suggests that the trained engineers and skilled technicians
were well maintained throughout the remainder of the expansion stage. The limit on the
construction period (C3) with the above-ground membrane storage tanks (100,000 m3)
under the given conditions is about 31 months. These conditions involve a companys
construction performance capacity, its learning capabilities, its construction
characteristics of the given tank type, and its general construction conditions at the site.
40
Re-learned C1
Construction Period , [months]
38
C2
36
Re-learned C2
C1
34
32
C3
30
28
1 2 3 4 5 6 7 8 9 10
The company involved in 9% Nickel FC tank has previous experience, which enables
it to build a similar type of cryogenic tank for ethylene. The LC also shows the smooth
learning effect based on past experiences (Fig. 3). The LC can be expressed as follows:
n
y = 5.43 exp + 31.6 (3)
4.55
The learning rate is lower than that of the membrane tank. Several reasons for this are
explained as follows: the storage tanks are constructed within a relatively short period of
PO-08.7
SESSIONS CONTENTS
Poster PO-08
time, the company did not have enough time to accumulate the learning effect on the
construction performance, and a limitation existed on the available skilled employees and
well trained engineers to build the tanks within the short time period. A significant
increase in construction performance appeared in tank #4. The large block prefabrication
method was applied to the roof structure [6].
38
Construction Period, [months]
36
C2
C1
34
C3
32
30
28
1 2 3 4 5 6 7 8 9 10
Figure 4 illustrates the LCM for in-ground membrane tanks. The storage capacities of
the first two tanks constructed by a company (A) are 140,000 m3. Tanks #3 and #4 were
constructed by a company (B). The storage capacities of tanks #3 8 are 200,000 m3.
Tanks #5 and #6 were constructed by a company (C). The rest of the tanks (#7 8) are
also under construction by company (C). Figure 4 highlights an interesting detail in the
LCM for the different capacity tanks and for the different contractors. The construction
experience can be transferred indirectly to the company who constructed the same types
of tanks later on. The latter company has a steeper LC in construction performance. The
specific construction performance, which is defined as the construction monthly period
divided by LNG storage volume (1000 m3), of companies A and B result in values of
0.343 and 0.275 for 140,000 m3 and 200,000 m3, respectively. The reduced specific
performance can be interpreted to indicate that as the LCM for the large tank increases, a
reduction in the construction costs follows. The ultimate values of C3 in each storage
capacity are projected at 42 and 51 months for 140,000 m3 and 200,000 m3, respectively.
C3 values highly depend on the depth of the slurry walls.
PO-08.8
SESSIONS CONTENTS
Poster PO-08
59
200, 000 Kl
constructed by
Construction Period, [months]
55
a company C
51
Capacity
Factor
47 200, 000 Kl
constructed by
a company B
43
140, 000 Kl
39 constructed by
a company A
35
1 2 3 4 5 6 7 8 9
Cumulative Tank Construction Units
Fig. 4 LCM for In-ground Membrane Tank
PO-08.9
SESSIONS CONTENTS
Poster PO-08
n
(TIC ) f = C P exp + Cm (4)
Cv
where,
(TIC)f : future installed cost
n : number of tanks in the field
Cp : constant reflecting storage volume
Cv : constant reflecting construction performance
Cm : constant reflecting the ideal minimum cost for an area
120
115
Specific Tank Construction Cost, [%]
110
105
100
95
90
85
80
1 2 3 4 5 6 7 8 9 10 11
PO-08.10
SESSIONS CONTENTS
Poster PO-08
were prefabricated in a nearby workshop and then moved to a temporary shop where the
roof insulation was installed. The completed large blocks were transported to the
construction site [6]. The new construction method demonstrably shortened the field
construction period. A new welding jig had also developed and applied on the inner shell
welding job based on the site welding experience. The new welding jig reduced the repair
job, resulting in an increase in welding constructability. However, the shortened roof
fabrication period is not directly affected by the shortening of the whole tank construction
because it is mainly performed inside the tank during the PC wall erection. The harder
work that has a lower LC effect is side-wall work.
1000
Working Period for Each Activity, [days]
Others
800
Cool-
down
600 Insulation
Inner-
shell
400
Roof fab
200 Sidewall
0
1 2 3 4 5 6 7 8 9 10
CONCLUSIONS
1. The developed LC model for LNG tank construction well represents the
improvements of construction performance based on past construction experience,
and improves estimations of future costs for three types of LNG tanks.
2. LCM can be a useful tool for project developers to estimate future tank costs, and
for contractors to confidently predict the profitability of the companies
construction activities.
3. The construction analysis strengthens the level of learning based on past
experiences, resulting in an increase in construction performance and capability.
4. In order to minimize the re-learning factor (forget effect), a company needs to
organize the developed construction processes, manage learning resources, hold
experienced employees, and pay careful attention to the indirect activity of macro
LCM.
PO-08.11
SESSIONS CONTENTS
Poster PO-08
ACKNOWLEDGEMENT
The authors wish to thank Korea Gas Corporation (KOGAS) for their permission to
reference their construction and operation data of LNG terminals. Special thanks are
extended particularly to J.S. Jung at Kogas Maintenance and Engineering Co. and S. B.
Hong at Daewoo Engineering & Construction Co. for their kind assistance and useful
discussion.
REFERENCES CITED
1. Hosin, Y.A.: Learning Curve for Interrupted Production, Proc., 1989 Int. Industrial
Engineering Conference, Institute of Industrial Engineers, June 23, 1989.
2. Millheim, K., Maidla, E., and Kravis, S.: An Example of the Drilling Analysis
Process for Extended Reach Wells, SPE Paper 49111, the Annual Technical
Conference and Exhibition, New Orleans, USA, 27-30 September 1998.
3. Construction Report of Pyeongtaek Expansion Project, Korea Gas Corporation, 1988.
4. Construction Report of Incheon Terminal, Korea Gas Corporation, 2000.
5. Construction Report of LNG Storage Tanks #11 14, Korea Gas Corporation, 2002.
6. Kwon, Y.J.: Commissioning of Korea Gass New Receiving Terminal at Incheon,
Proc., LNG 12, Perth, West Australia, May 4- 7 1998.
PO-08.12
SESSIONS CONTENTS