Contracts,

Change Order Administration


and Claims Management

Dieter J. Preiser, PMP


PreiserConsulting
dieter@preiserconsulting.com
What is a Contract?
 A contract is a mutual business agreement recognized by
law under which one party undertakes to do work (or
provide a service) for a second party for a “consideration”.
 A contract is an agreement between two parties, one called
the contracting party or owner and the other the contracted
party or the contractor to perform a previously determined
scope of work for a previously determined amount of
money.

8/3/2010 2
Why do we need written
contracts?
 Basic lack of trust
 Clearly establishes the risks and obligations of each party
 Provides means by which performance can be assessed and
measured
 Provides means by which breaches can be identified
 Provides means by which default can be established
 Establishes the owner’s means of control
 Establishes the contractor’s scope of work

8/3/2010 3
What does a written contract do
for us?
 A written contract provides the document
by which risks, obligations, and
relationships of both parties are clearly
established, thus ensuring the performance
of these elements in a disciplined manner.

8/3/2010 4
Goals of Contract Management
and Administration
 The effective management and
administration of contracts results in
reducing risks, maximizing cost savings,
minimizing claims, and improving
economic return.

8/3/2010 5
How do contracts minimize
risks?
 A contract provides the means to manage and allocate
risks. You want to “share” the risks appropriately through
your contractual relationship.
 Your contracting strategy needs to be built around the
relationship between the terms and conditions, and the
accompanying risks and cost impacts.
 The type of contract and the specific language used should
flow from these relationships.
 Failure to manage risks in this manner can result in cost
overruns, loss of market, or loss of quality.

8/3/2010 6
Risk Areas
 Cost - possibility of overruns and other
financial losses
 Time - delays in schedule and resultant loss
of market
 Quality - loss of desired quality of
engineering and construction

8/3/2010 7
Contracting Strategy
 Priority of project management goals
– Cost, schedule, quantity
 Status of project definition
 Schedule and cost constraints
– Facility startup date and availability of capital
 State of the economy
– Market urgency for product
– Number of competitive bidders
– Workload of competitive bidders
– Vendor backlogs
8/3/2010 8
Types of Contracts
 Lump-sum fixed price
 Unit price
 Fixed price with escalation (price adjustment)
 Guaranteed maximum price (target price)
 Cost plus incentive fee (time/cost goals)
 Cost plus fixed fee
 Cost plus percentage of cost

8/3/2010 9
Elements of Cost
 Labor Costs
 Material Costs
 Equipment Costs
 Overhead Costs - Direct and Indirect
 Profit

8/3/2010 10
Analysis of Cost
DIRECT COST INDIRECT COST

Items of Work OVERHEAD COSTS Profit Margin

At the Job Operating


Costs which Difference
are incurred Costs which Costs which between all
for specific cannot be cannot be costs and
items of work allocated to allocated to all income
specific items specific jobs

The Work The Site The Firm The Motive

COST FEE

TOTAL CONTRACT SUM


8/3/2010 11
Fixed Price vs. Cost Reimbursable
Definitions
Fixed Price Cost Reimbursable
Agreement to perform the Agreement to perform
scope of work at a set work on a reimbursable
price regardless of basis.
Contractor’s actual cost.

8/3/2010 12
Fixed Price vs. Cost Reimbursable
Basic Conditions
Fixed Price Cost Reimbursable
Fair and reasonable price can be Scope & cost of work not defined
established using a detailed sufficiently to allow fixed price
scope of work, complete design quotes.
and specifications and known Qualified contractors unwilling to
environmental and business accept financial risk of fixed price.
conditions. Owner wishes to exert more control,
Adequate professional develop design as project
inspection & supervision progresses, or achieve technology
provided by other parties. transfer from contractors.
Risk: Contractor assumes Owner is required to be more
maximum amount of risk, and sophisticated in contractor selection
has incentive to perform and oversight.
economically. Risk: Owner accepts most risk
8/3/2010 13
Fixed Price vs. Cost Reimbursable
Advantages
Fixed Price Cost Reimbursable
Less risk on the Owner, at least Construction can be phased.
on the surface. Changes can be accommodated
Substantial amount of case law more easily.
and administrative protocol. Reduces adversarial
Overall cost known before relations:Contractor & Owner
project begins. are partners.
Minimal Owner involvement Reduced Contractor
Owner realizes price contingency included in price.
competition.
Contractor has incentive to
finish early.

8/3/2010 14
Fixed Price vs. Cost Reimbursable
Disadvantages
Fixed Price Cost Reimbursable
Adversarial relations Generally, the construction
Contractor may bear risk for costs are higher.
conditions beyond his control Increased Owner involvement.
Changes more likely to end in Final cost not known until
dispute. project is finished.
Contractor has no direct More detailed negotiations and
financial motivation to provide contractor selection process.
superior quality or service. More cumbersome
Extra time required to complete administrative and
the plans and specs. bookkeeping requirements.

8/3/2010 15
Fixed Price vs. Cost Reimbursable
Applicability
Fixed Price Cost Reimbursable
Routine projects. High-risk industrial or
Conditions with an manufacturing projects
abundance of qualified (petrochemical, power,
contractors. offshore).
Public works projects. Situation where qualified
contractors are scarce.
R&D projects (aerospace,
military).

8/3/2010 16
Types of Contracts
Min

Min
Lump Sum
Lump Sum + Variation

Bill of Quantities
Owner's Flexibility
Owner’s Control

Schedule of Rates

Cost + Fixed Fee


Cost + % Fee
Max
Max

Client‘s Risk
Min Max
Contractor's Incentive to Perform
Max Min
Firm Client’s Project Definition Changeable
Project Schedule Duration vs.
Type of Contract
5
Engineering
Contract Type

Required
4 to Start
Construction
Construction
3
Start of
Project
Construction
2 Completion

1
Project Duration

1. Cost Reimbursable w / %Fee


2. Cost Reimbursable w / Fixed Fee
3. Cost Reimbursable w / Incentive
4. Guaranteed Maximum Price
5. Lump-Sum Fixed Price
8/3/2010 18
Phased Construction
Traditional Construction Method

Design Bid/Award Construction Phase


(Single Construction Contract)

Phased Construction Method


Design
Foundations

Mechanical

Landscape
Electrical
Structures
Sitework

Construction Phase
(Multiple Construction Contracts)
8/3/2010 19
Precontracting Activities
Score
Establish Prepare Contractors Pre-Quals Bid Slate
Plan of Pre-Qual Develop and Prepare Management
Action Documents Response Bid Slate Approval

Prepare Release
Management Management Pre-Qual
Submittal Review

Prepare Review Revise Prepare Release


Contract Contract Contract Job Ex Bid
Draft Draft Draft Meeting Package

Job Ex
Meeting

8/3/2010 20
Pre-Contracting Activities
Receive Contract
Bids Award
Contractor Tech Price Prepare
Prepares Bid Bid Management Management Prepare Contractor Owner
Bid Review Review Recommendation Review Contract Signs Signs

Prepare
Company Functional
Estimate Review

8/3/2010 21
Pre-Qualification Process
 Financial Strength and Credit Rating
 Previous Experience on Similar Projects
 Organization
 Loss Prevention Program
 QA/QC Program
 Equipment Availability
 Availability of Key Personnel
 Current and Future Workload
8/3/2010 22
Components of Contract Package
 Invitation for the Bid
 Instructions to Bidders
 Bid Form
 Contract Form
 Schedule of Plant
 General Conditions or Provisions
 Special Conditions, Supplementary
Conditions or Special Provisions
8/3/2010 23
Components of Contract Package
 Performance Schedule
 Price Schedules
 Scope of Work
 Specifications
– Performance Specification
– Proprietary Specification
 Design Drawings

8/3/2010 24
Contract Bonds
 Bid Bond (5% to 10% of contract price)
 Performance Bond (50% of contract price)
 Payment Bond
 Maintenance Bond

8/3/2010 25
Insurance
 Public Liability Insurance
– Provides coverage against bodily injury and property
damage to third parties as the result of construction
activities.
 Builder’s Risk Insurance
– Protects against loss/damage of structures and
equipment
 Comprehensive Automobile Liability
Insurance
 Special Policies
8/3/2010 26
CHANGE ORDER
ADMINISTRATION
Change Order Administration
 An organized effort to eliminate
unnecessary cost and time impact as a result
of processing project work outside the
scope of the contract.

A Change is not a Claim.

8/3/2010 28
Contract Change Clause
 Fixed price contract require a change
clause.
 Establishes the owner’s right to make
changes and provides a mechanism for their
administration and resolution.

8/3/2010 29
Types of Changes
 Formal
– Via contract change clause
 Constructive
– Action of owner that has the effect of directing
a change, although not initially documented as
such.
 Cardinal
– Change totally out of scope of original contract.
– Should re-negotiate entire contract.
8/3/2010 30
Change Orders
 Virtually all project have change orders.
 Need to recognize their implications.
 Set up an effective management system to
handle them.
 Minimize cost/time impact and prevent
costly legal action.
 Modification of the contract.

8/3/2010 31
Sources of Change Orders
 Unanticipated site conditions
 Owner requested design modifications,
additions or deletions
 Clarification of contract documents

8/3/2010 32
Disagreements
 Change or design development
 Scope of the change
 Material cost
 Equipment rental rates
 Acceptable profit
 Overhead cost
 Consequential effects of the change

8/3/2010 33
Change Orders
 Prior approval
– Adverse effect on construction
 Unilateral change order
– Urgent situations or conditions
 After the fact

8/3/2010 34
Change Order Process

Change Order Bid C.O.


Identification C.O. Closing Award
Design
C.O. Cost/Schedule Bid Bid
Request Analysis Period Analysis

Prepare
Bid Package

8/3/2010 35
Cost of Changes
Engineering Construction

Time

8/3/2010 36
CLAIMS MANAGEMENT
Typical Claims Against Owner
 Poor project planning
 Scope changes
 Constructive change orders
 Errors and omissions
 Contract accelerations and stoppages
 Site access or availability
 Other construction interference and delays
 Strikes and acts of God
 Low bidders
8/3/2010 38
Typical Claims Against
Contractor
 Late completion - liquidated damages
 Out of specification materials
 Defective work
 Property damage

8/3/2010 39
Delays
 Excusable Delay
– Beyond control of owner or contractor
 Inexcusable Delay
– Beyond the control of the contractor
– Owner caused changes to work
– Differing site conditions
– Suspension or termination of work by owner
 Concurrent Delay
– Two or more delays in same time frame

8/3/2010 40
Claims Analysis
 Brief of the case
 Owner’s position
 Contractor’s position
 Analysis and evaluation
 Recommendations

8/3/2010 41
Claim Prevention Suggestions
 Carefully analyze and consider exactly what you
are building and precisely how it will be built so
the contractor does not have to assume or guess
about any aspect of the job.
 Complete the project design before the contract is
bid, and if some parts of the project cannot be
completely designed at bid stage, clearly identify
them and its possible impact.

8/3/2010 42
Claim Prevention Suggestions
 Conduct a thorough review of the design prior to
the bid stage to identify and correct any design
errors or inadequacies.
 Give bidders sufficient time to carry out a
complete review of the bid package and an
investigation of the construction site.
 Allow enough construction time, remember in this
context, time is not money. Do not assume that
bidders will simply increase their bids to cover a
short schedule.
8/3/2010 43
Claim Prevention Suggestions
 Identify with enough anticipation what type of
contract will best suite the project.
 Think about every sentence included in the
contract, why it is there and whether it is
necessary.
 Clearly identify in the contract every operation
that the contractor must accomplish to complete
the job.

8/3/2010 44
Claim Prevention Suggestions
 Draft for clarity, not confusion. Use standard list
of definitions, and always use the same defined
word consistently.
 Consider material arrival schedules as part of the
contract. Identify long-lead items and possible
vendors in the bid package. Avoid sole-source
procurement unless absolutely necessary.
 Clearly identify who will be responsible for
material delays.

8/3/2010 45
Claim Prevention Suggestions
 Analyze all potential bidders before preparing a
bid slate. Examine contractors’ prior contracting
experience, claims history, management
capabilities and financial ability.
 Carefully analyze contractors’ technical proposal
paying particular attention to the proposed method
of construction and the planned number of man-
hours claimed necessary to execute the job.

8/3/2010 46
Claim Prevention Suggestions
 Seriously question the contractors’ excessively
low bid.
 If you are forced to accept a low-ball contractor,
anticipate a claim and work on it from the
beginning.
 Be reasonable when analyzing the contractors’
complaints about changes and omissions.
Negotiate settlement as soon as possible and keep
in mind that the older the issue, the more difficult
it will be to settle.
8/3/2010 47
Claim Prevention Suggestions
 Appreciate the contractors’ right to perform the
contract in any fashion he deems appropriate, as
long as the methods and results conform to
contractually specified standards.
 Keep in min that the owner has the obligation to
provide: a suitable construction site, accurate plans
and specifications, well-defined scope of work,
and inspection without interference.

8/3/2010 48
Claim Prevention Suggestions
 Understand how many factors can affect a contract
and delay and disrupt the work. Cooperate to
establish an atmosphere of understanding and
mutual respect.
 Keep strict control of: progress reports, daily
meetings, schedule revisions, cost estimates,
change orders and their justifications,
correspondence.
 Develop a solid document control plan.

8/3/2010 49
Contract Disputes Resolution
Continuum
Review Contract
Identify Disputes Documents for
Policies and Risk Assessment Resolution Completeness Budget and
PM Selection Procedures and Allocation in Contract and Accuracy Contract

Phase I - Program/Project Planning (NO COST RESOLUTION RISK)


A Problem and Change Change Order Denial of
Budget and Pre-construction Request for Order Estimate and Change Order Entitlement
Contract Meeting Information Request Negotiation Settlement Issued and Cost

Phase II - Contract Administration (LOW COST RESOLUTION RISK)

8/3/2010 50
Contract Disputes Resolution
Continuum
Selection of
Denial of Negotiations Contracting Outside
Entitlement Rapid Response Disputes Involving the Officer’s Intervention
and Cost Team Review Board Party Principals Decision Options

Phase III - Contract Identified Resolution (MEDIUM COST RESOLUTION RISK)

Selection of
Outside
Intervention Construction Rent-a- Selection of
Options Master Mediation Mini-Trial Judge/Jury Venue Options

Phase IV - Outside Intervention (HIGH COST RESOLUTION RISK)

8/3/2010 51
Contract Disputes
Resolution Continuum

Selection of Settlement Non-Binding Binding


Venue Options Hearings Arbitration Arbitration Litigation

Phase V - Arbitration and/or Litigation (MAXIMUM COST RESOLUTION RISK)

8/3/2010 52