Step Action
1. Create a new Item Item-001 using the item master application
Go To > Inventory > Item Master
Item = Item-001
Description Item 001 for Hard and Soft Reservation Scenario
Maximo Asset Management v7.5 Whats New workshop Exercise 006
Unit Cost = 5
Default Bin = B-1
Current Balance = 5
5. Click OK and Save the record
Maximo Asset Management v7.5 Whats New workshop Exercise 006
6. Now, open the work order application and create a new workorder
to perform this scenario
Storeroom = Central
Reservation Type = Soft
Quantity = 8
Maximo Asset Management v7.5 Whats New workshop Exercise 006
13. Click on Preview, you would observe that this reorder process
did not consider the shortage of 3 quantities.
14. Click Cancel and return back to the work order
Maximo Asset Management v7.5 Whats New workshop Exercise 006
15. Un-approve [Waiting for Approval] the work order and change the
reservation type as Hard in place of Soft for the same quantity =
8
20. Now to perform the next scenario Set the lead time = 5 before
returning from Inventory application to Workorder application.
26. You would see that system did not consider this shortage of ITEM
in to reorder consideration. Do you know why???/
27. Cancel it and go back to work order
Maximo Asset Management v7.5 Whats New workshop Exercise 006
28. Change status back to Waiting for approval and change the
Required Date = just 2 days from todays.
{In previous step, you had set up the date as of after a week}
Keep the reservation type same as Automatic
29. Navigate to Inventory application and run the Reorder
Preview
You would observe that system is now considering the quantity in
short into reorder consideration. Do you know why?