When the wind blows

27 February 2012

In March, ESTA will bring together a group of crane and specialised transport
industry experts in the field of wind turbine erection and transport to discuss
safety. Kevin Walsh looks at the some of the issues to be covered in just one
day.

In March, ESTA will bring together a group of crane and specialized transport
industry experts in the field of wind turbine erection and transport to discuss the
safety problems that have dogged the industry of late.
While crane-related accidents do occur from time to time, and always too often
as many will attest, the number of accidents that have happened involving
sizable and well-engineered cranes during the installation of wind turbines has
caused some alarm.
Cranes overturning or experiencing a boom collapse due to a failure of one
crane type would arguably be less of a cause for industry-wide concern, as the
problem may be localised to an individual design concept, but this summit
along with warnings from both the FEM and ESTA will indicate this is far
from being the case. This is everyones problem, and everyone will have to pitch
in to solve it.
Warnings highlighting the importance of crucial data during wind turbine lifting
operations were issued in a joint statement released by the FEM and ESTA
back in April 2010. The statement focused on two pieces of information, the Cw
factor used to determine the wind drag on a static rotor blade during lifting, and
the sail area, the maximum surface area exposed to the wind during lifting.
While these values have been provided in the load charts of crane manuals for
over 40 years, these were assumed values based on typical loads being lifted
which didnt take into account the nature of turbine rotor designi.e to
maximise the effect of wind on the load.
The charts have always stipulated that for any loads which did not adhere to the
principles behind the assumed valuesfor example, that for every tonne of
weight the sail area was roughly 1m2if the crane operator obtained the
correct Cw factor and sail area for the load they could recalculate for
themselves what the correct crane working limits would be for a particular lift,
taking into account wind speeds.
Unfortunately, due to a general lack of awareness surrounding the difference in
these values during wind turbine erection, along with Cw factors not fit for
purpose initially being provided by the turbine manufacturers, a number of
accidents have followed.
In April 2010 ESTAs general secretary, Sren Jansen, explained the reason for
the incorrect Cw factors provided by manufacturers, saying, What prompted
this safety alert was the realisation that the Cw factor on rotor blades and the
complete rotor was indeed a lot higher than anyone expected. No wind turbine
manufacturer actually had the correct figure because their interest is not as
much in the Cw factor of the rotor blade itself, its more in the rotating rotor.
That is what their concern is, that it has as little [wind] resistance as possible,
and that was really what contributed to why they didnt know it.
But despite turbine manufacturers now being aware of this problem and starting
to provide better information, crane operators on site still need to be educated
regarding its proper use, says Liebherrs general manager of its design
department, Hans- Dieter Willim.
For forty years now we have assumed that the area of the wind on a typical
load is 1m2 per tonne of load, and weve also assumed, as we cant know the
shape of every load being lifted, that the drag factor is 1.2. Now we know in
most cases for wind turbines the drag factor is 1.6, so a lot more than in our
assumptions, and [using the standard chart values] we assumed that a 20t rotor
has a sail area of 20m2, when in reality it has more than 180 or 200m2.

1 of 5 25/12/2016 02:17 PM
When the wind blows - Cranes Today http://www.cranestodaymagazine.com/features/when-the-wind-blows-/

With these wind charts we say you have to reduce the [safe working] wind
speed in such a way that you get the same wind forces on the load as we have
in our load assumptions, thats the point. To reduce the wind speed, there are
two charts in the operator manual, or you can give a formula with a square root.
Now if customers would go to the operators manual and go in the charts which
have been in there for 40 years, they would know they have to reduce the safe
working wind speed.
But when I go over the square root with a crane driver or lift planner, they
cannot do the calculation with the charts. Also when they go into the diagrams,
for the average crane operator its very difficult to read out the allowable wind
speed for this wind area. So what many crane drivers do is think that because
they dont have the maximum load on the crane there is a lot left for higher wind
speeds. That is their impression but this is completely wrong.
A turbulent business
By the very nature of the industry, crane operators erecting turbines will always
be working in areas where wind speeds are higher than normal, and lifting to
heights where wind speeds are more keenly felt by each load.
As the number of wind farms across the world grows, more rapidly each year,
prime locations with the highest wind yields become sparser. However, the
higher the rotor blades are above ground level the greater the yield, so we can
only expect to see future wind turbine designs including hub heights well in
excess of 100m.
Willim explains: In the past we had 80m towers, and there you dont have the
highest wind speeds. The towers are being manufactured taller because for
every 1m of additional tower height you get about 1% more power output.
So 10m extra height brings you 10% more output for the same machine, but
also you have 10% more wind on the crane boom during erection, therefore the
danger will also increase in the future. If you see the sizes of cranes we are
selling now we are coming to heights we have never thought about.
These higher wind speeds at greater heights also mean that the direction of the
wind takes on greater importance, as it can not only make the accuracy of such
calculations even more critical, but also harder to perform.
Crane booms designed in accordance with EN13000 or the ASME B30.5
standard are constructed with the assumption that the side loading from any
load lifted by the crane will not exceed around 2% of its weight, so when the
wind blows from either side of a crane the resultant additional moment of the
load and wind loading on the crane boom can be quite significant. To further
complicate the situation, Willim says that most load moment indicators, while
perfectly capable of registering the wind loading on a crane boom when it
comes from in front of or behind a crane, will more often than not fail to register
a side wind.
Another relevant point that I will cover in my presentation is the rated capacity
limiter, says Willim. It reacts, I would say, when the wind is coming from the
back of the crane, then it shows you more load. When the wind is coming from
the front it shows you less load, but when the wind is coming from the side it
shows you nothing. No increase, no decrease.
But when the wind comes from the side, the side loading is very critical
because then the whole boom bends, and the more side bending of your boom
system, the more your load goes out and gives additional moment. Two percent
is very little when you compare this to the wind forces that are applied to these
big rotors.
Some tower heights are as high as 150m now, and this means we are getting
into areas where the wind is blowing all day long. We will have higher wind
speeds when lifting rotors in the future, and as boom systems get longer and
longer just to lift to these high hub heights the danger will increase.
Further contributing to the dangers of side loading, the increased turbine
installation heights also reduces the effectiveness of the taglines often used to
help secure the rotor/hub assemblys position as it is being lifted. A more
vertical angle between the rotor hub assembly and the ground-level securing
points for the taglines means they provide less resistance to wind side loading.
With wind turbine rotors often lifted in their sailing position, an orientation

2 of 5 25/12/2016 02:17 PM
When the wind blows - Cranes Today http://www.cranestodaymagazine.com/features/when-the-wind-blows-/

chosen to minimise wind forces on the rotor that could make the blades rotate
during lifting, this simultaneously maximises the surface area on another plane
of the rotor/hub assembly.
All of these factors combined can provide such a large load moment, with
longer boom system lengths acting as a lever arm, that the outrigger ground
bearing pressure underneath the crane is dramatically affected, producing more
side load in the process that can eventually lead to overturning.
Failing to prepare
A number of different factors can come into play on any wind turbine erection
job, and the differences in conditions between the erection of one turbine on
site and another just 100m away can vary wildly.
With the one factor least controllable by lift planners being the wind, even when
a weather station is near enough to the job site to provide accurate data on the
overall weather conditions during a project, sudden unexpected gusts can still
cause delays, with worse consequences still if these changes occur midway
through a lift.

This means that in addition to calculating the maximum wind speed at which it
is safe to lift, the crane operator needs to calculate the wind speed at the boom
tip at the time of the lift, to check its variance from the information provided by
the weather station, as well as the three-second gust value.
However, a large part of the ESTA Expert Summit in March will focus on factors
more easily controllable by the lifting firms, such as preparation of the site and
on-site logistics.
Among the topics will be consideration of the way civil works are undertaken to
ensure access to the sitewhich is often across agricultural landis level, to
support the partially assembled cranes moved around site and other transport
onto site. Even a small inclination of the road above 2 can significantly
contribute to a crane or transport trailers risk of overturning.
Trailer manufacturer Nooteboom is aware of a number of difficulties in this field
that it believes can be avoided simply through better communication between
stakeholders, as director Han Rekers explains.
Rekers says that on occasion he has witnessed the transport of components for
some of the larger turbines on trailers that were not designed for that purpose,
and as a result require a number of safety risks to be taken during transport.
He attributes this to a dearth in numbers of trailers designed by manufacturers
to cope with such enormous components, which in turn speaks to a lack of
communication between the industry and the wind turbine manufacturers.
Turbine blades are getting longer and longer, and in the beginning no-one
wanted to have a discussion about it, they all said were just going to wait and
well see what happens, says Rekers.
In the end there are just a few trailers on the market at this moment to do this
kind of transport. The Vestas V112s for instance, but also the 3.XM from
Repower and the E101 from Enercom, suddenly theyre all on the market, but
there isnt enough capacity to move all these long blades.
So what is happening at the moment is that people are changing their existing
equipment, with tools and some beams and some counterweights, all kinds of
stuff, just to be able to do the transport. But it is not secure, it is unsafe, it is not
what [the trailer] was meant for one and a half years ago when it was
developed.
Rekers says the hesitance from trailer manufacturers that led to the low
numbers of suitable transport options being available was caused by
uncertainty as to which way wind turbines were developing.
He comments that the rumour mill, some years ago, had industry workers split
between whether to expect longer blades being produced by turbine
manufacturers or blades that would be manufactured in two pieces which could
later be assembled at the site.
Rekers explains: That was something that was said two or three years ago, but
the blades are not splitting, they are still long. REpowers is 61.5m, and they are
even starting with 73m, and then when you ask them are you going to split the

3 of 5 25/12/2016 02:17 PM
When the wind blows - Cranes Today http://www.cranestodaymagazine.com/features/when-the-wind-blows-/

blades? they say no, that is not possible.


If we would have invested enormous engineering and innovation capacity to
develop a 65m trailer to do it and then they said dont worry we will split the
blades in two parts that would be a big problem.
The squeezed middle men
Although a fledgling sector compared to the established power generation
industries around coal, gas and nuclear power, a booming industry has sprung
up rapidly around the market for providing energy from wind.
As an ever increasing number of countries looks to reduce their domestic
reliance on CO2 producing power networks, crane and special transport
equipment manufacturers develop new products in anticipation of a wealth of
wind farms springing up across the globe.
According to the World Wind Energy Association the pace of this growth is
quickening, with 15% more wind turbine installations globally in the first half of
2011 than the previous half year, up from 16,000MW to 18,405MW.
As a result competition is becoming increasingly fierce. Manufacturers in
countries such as China and Vietnam, the former already a dominant force in
the wind energy market, are allegedly using unfair government subsidies to
flood the world market with cheaper turbine components and consequently
devaluing it.
While the US Department of Commerces International Trade Administration
launched an investigation into these purportedly illegal subsidies in January,
many already competing in the industry are worried that the gradually declining
price of wind turbines could further squeeze profits, which more worryingly
could encourage corner cutting during installations to reduce costs.
During his time as director of Danish crane rental company BMS, Jansen says
that he came to understand how some of the pressures on tough wind turbine
erection jobs could help compromise safety when undertaken by smaller firms.
Some smaller companies who hire out big cranes needed for the erection of
some of the bigger turbines are increasingly coming under pressure from the
turbine manufacturers, price pressure, says Jansen. They dont have any
negotiation power when they dispatch to a multinational turbine manufacturer or
whoever.
Jansen believes that some smaller firms are forced to walk a dangerous
tightrope between conducting lifts safely while keeping to a tight schedule on
site.
At a lift that I did at my former job as president of BMS Denmark, we often saw
that if a crane rental company starts asking too many safety-related questions
on a job site they are often, unfortunately, considered difficult to work with.
We had a rule, that still applies, if the crane operator doesnt feel okay about
doing this job, then he doesnt do it. But the penalties for delays when installing
a wind turbine are very big, and for a small company it can kill you. So often
they are scared, they dont dare to stop because they know that the penalties
that can be given afterwards can be very big.
Also they dont want to ask questions because then they are considered
difficult to work with by the site manager, and then they wont be asked for the
next job. I know about companies that have been asked to leave a job site
because they were difficult.
Many believe that there should be greater importance given to the role of the
crane operator on such jobs, so that they not only have received specific
training in wind turbine lifting operations, but also so that their word on whether
a lift is safe to perform is final, regardless of the cost implications of deviations
from the schedule.
The whole supply chain needs to deal with the issues causing this pricing
pressure and stakeholders must collaborate to ensure the familiar battle
between market forces and operational safety does not tip too far in either
direction.
In the end, the use of bigger cranes can solve many of the safety problems
currently inherent in wind turbine transport and erection. Now the industry will

4 of 5 25/12/2016 02:17 PM
When the wind blows - Cranes Today http://www.cranestodaymagazine.com/features/when-the-wind-blows-/

be hoping that at the ESTA summit everyone will recognise there is no room for
shortcuts, and play a part in developing a solution.

A Manitowoc Model
16000 at work in India
with wind attachment
and boom raising
system

Terex's wind kit for CC


6800 crawlers

Liebherr's new parallel


boom system promises
to increase capacities
signicantly on crawlers,
helping them work on
big wind energy jobs,
including installations
and dockside
component moves