I) Status
II) Critical Areas & Action (Identifying the Responsibility and Time Frame)#
6#1500 MIJ Qty 4 nos ordered Delivery completed. 4 nos dispatched already.
- + 1 Proto type testing completed as per QAP 3.8 and reports already submitted to LNT Mr. Pradnyesh
Fairtech/LNT showed their unhappiness on the progress and once again put more pressure on Goodrich to
follow the delivery schedule as required by LNT ie. At the earliest and Goodrich confirmed that they will deliver
balance MIJs before 24-1-15.
Page 1 of 2
III) Support from L&T Management, PMC, OWNER
Page 2 of 2