Completion Commisioning
Description Panel Remarks by Quest-Air
Target DateTarget Date Work by/care of Target Date Work/By
ELEVATOR
PE - 1 PELEV3 ## April 15, 2017 May 23, 2017
PE - 2 PELEV3 ## April 1, 2017 May 9, 2017
SE - 1 PELEV4 ## April 3, 2017 KPECI May 11, 2017 SCHINDLER
SE - 2 PELEV4 ## April 3, 2017 May 11, 2017
SE - 3 PELEV3 ## March 23, 2017 April 30, 2017
ESCALATOR
ESC outdoor PPGA, PP2G, PP3A, PP3B ## April 7, 2017 May 4, 2017
ESC atrium 1 PPGF, PP2F, PP3F ## April 8, 2017 KPECI May 5, 2017
SCHINDLER
ESC atrium 3 PP2B,PP3G ## April 12, 2017 May 9, 2017
ESC atrium 4 PP2f ## April 15, 2017 May 12, 2017
AIR CONDITIONING
COOLING TOWER MCC ## April 19, 2017 KPECI April 29, 2017 QAT Accomplishment:
Equipment installed, Loadside with terminal lugs
terminated to motors
Issues and concern:
No termination of lineside @ MCC of CT
CHILLER MCC ## April 19, 2017 KPECI May 9, 2017 QAT Accomplishment:
Installed equipment, complete piping and
ready for chemical flushing and treatment
Issues and concern:
Load side wiring incomplete wire set;
Line side termination to MCC not yet installed
AHU PPGC, GD, GF ## April 19, 2017 KPECI May 9, 2017 QAT Accomplishment:
Installed equipment, complete piping and
ready for chemical flushing and treatment
PP2A, PP2B, PP2E ## April 19, 2017 KPECI May 9, 2017 QAT up to the motors
PP3A, PP3B, PPAHU ## April 19, 2017 KPECI May 9, 2017 QAT Issues and concern:
Line side conduit and termination
BALANCING ALL AC PANEL May 23, 2017 QAT Upon energization of panels and equipment
CISTERN Accomplishment:
Transfer Pump PPUMP A, PPUMP B ## April 7, 2017 KPECI April 28, 2017 QAT Installed; Waiting for Energization of Panel/T&C of