Sei sulla pagina 1di 3

COMMISIONING OF EQUIPMENT

Completion Commisioning
Description Panel Remarks by Quest-Air
Target DateTarget Date Work by/care of Target Date Work/By
ELEVATOR
PE - 1 PELEV3 ## April 15, 2017 May 23, 2017
PE - 2 PELEV3 ## April 1, 2017 May 9, 2017
SE - 1 PELEV4 ## April 3, 2017 KPECI May 11, 2017 SCHINDLER
SE - 2 PELEV4 ## April 3, 2017 May 11, 2017
SE - 3 PELEV3 ## March 23, 2017 April 30, 2017

ESCALATOR
ESC outdoor PPGA, PP2G, PP3A, PP3B ## April 7, 2017 May 4, 2017
ESC atrium 1 PPGF, PP2F, PP3F ## April 8, 2017 KPECI May 5, 2017
SCHINDLER
ESC atrium 3 PP2B,PP3G ## April 12, 2017 May 9, 2017
ESC atrium 4 PP2f ## April 15, 2017 May 12, 2017

AIR CONDITIONING
COOLING TOWER MCC ## April 19, 2017 KPECI April 29, 2017 QAT Accomplishment:
Equipment installed, Loadside with terminal lugs
terminated to motors
Issues and concern:
No termination of lineside @ MCC of CT

CHILLER MCC ## April 19, 2017 KPECI May 9, 2017 QAT Accomplishment:
Installed equipment, complete piping and
ready for chemical flushing and treatment
Issues and concern:
Load side wiring incomplete wire set;
Line side termination to MCC not yet installed
AHU PPGC, GD, GF ## April 19, 2017 KPECI May 9, 2017 QAT Accomplishment:
Installed equipment, complete piping and
ready for chemical flushing and treatment
PP2A, PP2B, PP2E ## April 19, 2017 KPECI May 9, 2017 QAT up to the motors
PP3A, PP3B, PPAHU ## April 19, 2017 KPECI May 9, 2017 QAT Issues and concern:
Line side conduit and termination
BALANCING ALL AC PANEL May 23, 2017 QAT Upon energization of panels and equipment

CISTERN Accomplishment:
Transfer Pump PPUMP A, PPUMP B ## April 7, 2017 KPECI April 28, 2017 QAT Installed; Waiting for Energization of Panel/T&C of

Issues and concern:


Tanks Accomplishment:
Filled w/ Water (Domestic Mall tanks, Fire water tanks)
Issues and concern:

GRAY WATER TANK Accomplishment:


Transfer Pump QAT Installed; Waiting for Energization of Panel/T&C of

Issues and concern:


Tanks Accomplishment:

Issues and concern:


PUMPS AT BASEMENT
Sump Pit Pump 1 PPBF ## April 15, 2017 KPECI 4/29/17 QAT Installed eqpt and Panel ; Waiting for Energization of Panel/ECB
Sump Pit Pump 2 PPBE ## April 14, 2017 KPECI 4/28/17 QAT Installed eqpt and Panel ; Waiting for Energization of Panel/ECB
Sump Pit Pump 3 PPBD ## April 13, 2017 KPECI 4/27/17 QAT Installed eqpt and Panel ; Waiting for Energization of Panel/ECB
Sump Pit Pump CISTERN PPUMP ## April 12, 2017 KPECI 4/26/17 QAT Installed 1-unit;
Sump Pit Pump GWT PPBD ## April 11, 2017 KPECI 4/25/17 QAT Installed eqpt and Panel ; Waiting for Energization of Panel/ECB
ESCALATOR PIT PUMP 1 PPBA ## April 10, 2017 KPECI 4/24/17 QAT Installed eqpt and Panel ; Waiting for Energization of Panel/ECB
ESCALATOR PIT PUMP 2 PPBG ## April 19, 2017 KPECI 5/3/17 QAT Installed eqpt and Panel ; Waiting for Energization of Panel/ECB
ELEVATOR PIT PUMP 1 PPBC ## April 19, 2017 KPECI 5/3/17 QAT Installed eqpt and Panel ; Waiting for Energization of Panel/ECB
ELEVATOR PIT PUMP 2 LPGG ## April 19, 2017 KPECI 5/3/17 QAT Installed eqpt and Panel ; Waiting for Energization of Panel/ECB
ELEVATOR PIT PUMP 3 PPBB ## April 19, 2017 KPECI 5/3/17 QAT Installed eqpt and Panel ; Waiting for Energization of Panel/ECB