C) At present, 2 Nos. FF positioners are not in C) New FF positioners are being procured Instrumentation 05-01-2017 Shutdown
place. and would be commissioned after Required
completion of Action A and B above.
2. On-line flue gas oxygen Oxygen analyser is working. Local display FF cable and linking device to be laid and Instrumentation 20-12-2016
analyser (FGA-19-001) is to be available. Display in HMI not available. configured respectively. Device to be
made operational and its downloaded in Rockwell System and HMI
display is to be provided in the display to be provided.
control panel in order to
maintain proper air/ gas ratio.
3. There are six zones in the As given in Sl.No. 1. As given in Sl.No. 1. As given in Sl.No. As given in As given
furnace. Each zone contains 1. Sl.No. 1. in Sl.No.
one control valve for air and 1.
one control valve for gas.
Hence there are total twelve
control valves. These control
valves are to be rectified for
complete operation. The
valves should be operated
from HMI and in auto mode.
4. Online CV readings are to be a) CV analyser M/S Ametek is not yet a) Project Division to arrange Project 30-12-2016
displayed in the HMI to commissioned.HMI Display not commissioning of the analyser.
facilitate for maintaining available in WRM control room. b) Connection to be given from GMS
WRM Furnace Action Plan
proper air/ gas ratio. b) One CV analyser has been installed to WRM & BM RHF. instrumentation 10-01-2017
at gas mixing station.
6. All the flow transmitters and All the flow transmitters and other
other instruments need to be instruments are calibrated on regular basis.
calibrated on regular basis.