2016 ACPA

Discussion Topics
T-13

www.concrete-pipe.org
2

Topics

Nonredundant Load Modifier for


Earth Loads
Live Load Applications
Shear on Boxes
Precast Concrete Pipe

www.concrete-pipe.org
3

Consistency?
12 inch RCP (D-Loads)

Standard Depth (ft)

1 2 3 10 15 20 25

AASHTO 1150 650 475 750 1100 1425 1750


Standard Spec

AASHTO LRFD 1700 1050 800 900 1250 1600 1975


(2010)

AASHTO LRFD 1492 1322 880 788 1164 1547 1929


(2016)

www.concrete-pipe.org
Non Redundancy Factor
5

12.5.4 Load Modifiers and Load


Factors
For strength limit states, buried
structures shall be considered
nonredundant under earth fill and
redundant under live load and
dynamic load allowance loads.
Commentary?

www.concrete-pipe.org
Review of Live Load
Application, and
Proposal for an Up-to-
Date Method
7

What has AASHTO Done for You


Lately?

12 inch RCP D-Loads


AASHTO Fill Height (ft)
Standard 1 2 3 4 5 6 7 8
STD 1150 650 475 475 500 525 575 650
LRFD 2010 1700 1050 800 725 700 700 750 800
LRFD 2016 1492 1322 880 727 694 705 741 788

Note: This excludes the use of 4.6.2.10.3


8

24 inch RCP D-Loads


AASHTO Fill Height (ft)
Standard 1 2 3 4 5 6 7 8
STD 950 575 450 450 475 525 575 650
LRFD 2010 1050 875 725 650 650 675 725 775
LRFD 2016 1202 1203 818 690 665 680 717 764

36 inch RCP D-Loads


AASHTO Fill Height (ft)
Standard 1 2 3 4 5 6 7 8
STD 775 525 425 450 475 525 600 650
LRFD 2010 850 700 675 650 650 675 725 775
LRFD 2016 1244 1137 789 687 665 687 728 775

Note: This excludes the use of 4.6.2.10.3


9

48 inch RCP D-Loads


AASHTO Fill Height (ft)
Standard 1 2 3 4 5 6 7 8
STD 625 500 425 450 475 550 600 650
LRFD 2010 825 650 625 650 650 700 750 800
LRFD 2016 966 935 732 663 655 684 726 774

Note: This excludes the use of 4.6.2.10.3


10

NCHRP 20-07, Task 316


No visible crack developed at any
locations until after both the service live
load requirement and the ultimate live load
requirement, as defined by AASHTO
(2013) had been exceeded. The buried
test pipes did not reach their service live
load limit requirements until loads of 4.0
and 3.0 times greater than the calculated
0.01-inch crack load limit of the pipe, for
the pipes equivalent to Class IV and V,
respectively
24 inch pipe at 1 foot
www.concrete-pipe.org
11

Live Load Distribution Factor


12

Spread Through Pipe

W + LLDF*H

Elevation View

Dist = 0.06 * Di
13

0.06 X Di?
Pipe ID (in) Pipe OD (in) Old Distribution Current
1.75 x 0.75 x OD Distribution
0.06 x ID
12 16 21 0.72
24 30 39.375 1.44
36 44 57.75 2.16
48 58 76.125 2.88
60 72 94.5 3.6
72 86 112.875 4.32
14

Less Than 2 Feet

E = 96 + 1.44S (4.6.2.10.2-1) Espan

E = Distribution width perpendicular to span in inches


S = Clear Span in feet
15
Less Than 2 Feet

E E

E = 26 + 6.6S (Table 4.6.2.1.3-1)

E = Distribution width perpendicular to span in inches


S = Clear Span in feet
16

Live Load Distribution (Shallow)

www.concrete-pipe.org
ACPA Proposal
18

Interaction Depth for Wheels (Perpendicular)


W ws for a single wheel

sw

W ws for two wheels

Plan View

DTP/2 DTP/2
W + LLDF*H

Elevation View
19
20

How the Load was Applied


21

Coefficient of Distribution

Pipe Size (B-Wall) Old Coefficient Current Coefficient ASCE Coefficient


1.75 x 0.75 0.06

12 1.3125 0.06 1.8823


24 1.3125 0.06 1.1528
36 1.3125 0.06 0.995
48 1.3125 0.06 0.9363
60 1.3125 0.06 0.9081
72 1.3125 0.06 0.8924
84 1.3125 0.06 0.8828
96 1.3125 0.06 0.8765
22

Distribution (ft)
23

Depth and Size


Appropriate
Live Load Moment
P
OLD 24

CURRENT

www.concrete-pipe.org
25

Results

12 inch RCP D-Loads


AASHTO Fill Height (ft)
Standard 1 2 3 4 5 6 7 8
STD 1150 650 475 475 500 525 575 650
LRFD 2010 1700 1050 800 725 700 700 750 800
LRFD 2016 1492 1322 880 727 694 705 741 788
Proposed 1659 993 783 703 683 702 740 789
(Exist. LLDF)
Proposed 1177 717 584 562 585 630 681 738
(1.75 LLDF)
26

24 inch RCP D-Loads


AASHTO Fill Height (ft)
Standard 1 2 3 4 5 6 7 8
STD 950 575 450 450 475 525 575 650
LRFD 2010 1050 875 725 650 650 675 725 775
LRFD 2016 1202 1203 818 690 665 680 717 764
Prop. (Exist.) 1101 906 732 670 660 683 723 772
Prop. (1.75) 1036 667 560 547 574 620 672 728

36 inch RCP D-Loads


AASHTO Fill Height (ft)
Standard 1 2 3 4 5 6 7 8
STD 775 525 425 450 475 525 600 650
LRFD 2010 850 700 675 650 650 675 725 775
LRFD 2016 1244 1137 789 687 665 687 728 775
Prop. (Exist) 920 749 683 642 645 680 724 778
Prop. (1.75) 891 653 563 558 588 636 689 747
27

Results
48 inch RCP D-Loads
AASHTO Fill Height (ft)
Standard 1 2 3 4 5 6 7 8
STD 625 500 425 450 475 550 600 650
LRFD 2010 825 650 625 650 650 700 750 800
LRFD 2016 966 935 732 663 655 684 726 774
Prop. (Exist) 944 667 650 627 644 683 731 787
Prop. (1.75) 877 635 571 571 604 652 706 764
Box Culvert Shear
29

Equation for Beta


30

Crack Spacing Parameter


31
Crack Spacing Parameter

Add:

sxe = the incorporation of the effect of maximum aggregate size into the
crack spacing parameter. The requirement that sxe equal or exceed
12 inches need not apply to slabs.
33

Equation for Beta


34

Calculation of Strain 5.8.3.3

www.concrete-pipe.org
35

Moment at the Location Being


Checked for Shear
36

Earth Load

LRFD 12.10
s 110 pcf

Standard 6.2.1
s = 120 pcf
37

Top Slab
12X12 @20
38

Moment at the Location Being


Checked for Shear
Add:

In continuous slabs not containing


prestressing, the value of |Mu| for the
location being analyzed may be utilized
without consideration of the
|Mu|min = |Vu Vp|dv limitation.
39

Why the Vu x dv requirement?

Tension Face

Compression Face

If Mv = 0, and Nv = 0

Tension in the Entire Element

www.concrete-pipe.org
40

Never without Thrust

Lateral Earth
Pressure
41

Is the Top Slab in Tension?


Depth = 5 ft. t = 12 inches
Size (span x rise) Nu (lbs/ft) Vu (lbs/ft)
12 x 3 400 2674
12 x 6 805 2674
12 x 9 1300 2674
12 x 12 1885 2674

Depth = 20 ft. t = 12 inches


Size (span x rise) Nu (lbs/ft) Vu (lbs/ft)
12 x 3 1300 11481
12 x 6 2380 11481
12 x 9 3550 11481
12 x 12 4810 11481
www.concrete-pipe.org
Precast Concrete Pipe
43

Incorporation of Current Precast


Concrete Pipe Options

www.concrete-pipe.org
44

www.concrete-pipe.org
The End
Basics under the
AASHTO Standard
Specifications for
Highway Bridges
Footprint (Has stayed the same)

Spread a = a + 1.75*H Spread b = b + 1.75*H


48

Passing Wheels (two separate


axles)
49

Interstate (Tandem Axles)


50

Spread Through Pipe


51

Critical Depths for Governing


Loads
(In the Old Days)
Passing Wheels (two separate
axles)

1.67 + 1.75*H = 4 ft
H = 1.33 ft
53
54

Divide the Total Load by an


Effective Length to get (lbs/ft)
55

Live Load has its own bedding


factor (pressure distribution)
56

Affect of Concentrated Live


Load
Latest AASHTO
Footprint Has stayed the Same)
Spread is Different

Spread a = a + LLDF*H Spread b = b + LLDF*H


59

Interaction Depth for Tandem Axles


PRdist < 0
(Perpendicular)

sa

sa

Hintd
lws when H<Hintd

lws lws
lwtwhen
whenH>H
H>Hintd
intd

lwt

Elevation View
Plan View
60

Interaction Depth (Wheels)

sw = wheel spacing, 6.0 ft


wt = tire patch width, 20 in.
Di = inside diameter or clear span of the culvert (in)
61

Interaction Depth (Axles)

sa = axle spacing, 4.0 ft


lt = tire patch width, 10 in.
* No Di
62

Strip Widths
4.6.2.1.3 The width of the
equivalent strip of a deck may be
taken as specified in Table 4.6.2.1.3-
1
C4.6.2.1.3 To get the load per unit
width of the equivalent strip, divide
the total load on one design traffic
lane by the calculated strip width
26 + 6.6 (1) = 32.6 in.
26 + 6.6 (10) = 92 in > 72 in.
www.concrete-pipe.org
63

Temporary Fix

www.concrete-pipe.org
Footprint (Keep it the Same)

Spread a = a + LLDF*H Spread b = b + LLDF*H


65

Live Load Distribution Factor


(Keep it the Same?)

1.75 across the board for pipe?


66

Passing Wheels (two separate


axles)
67

At Top of Pipe
68

Box Under Shallow Fill


Distribution Width
69

Concentrated Load
70

Crown
Governed
71

www.concrete-pipe.org