Sei sulla pagina 1di 93

SC342 Umoja Service Receipt

Process

Umoja Service Receipt Process Version 13


Last Modified:
Copyright 23-August-13
United Nations 1
Agenda

Course Introduction
Module 1: Service Receipt Process Overview
Module 2: Review Purchase Order
Module 3: Create Service Entry Sheet
Module 4: Approve Service Entry Sheet
Module 5: Reverse/Delete Service Entry Sheet
Module 6: Reporting
Course Summary
Course Assessment
Course Survey

Copyright United Nations 2


Course Overview
The purpose of the Umoja Service Receipt Process course is to explain how to create,
approve, reverse and delete Service Entry Sheets in Umoja.

Prerequisite Review
You should have completed the following prerequisite courses:
Umoja Overview
Umoja Master Data & Coding Block Overview
Umoja ECC Navigation
* Other prerequisites depend on your role, for example, Umoja Requisitioning.

Course Duration: 2 hours

Copyright United Nations 3


Course Objectives
After completing this course, you will be able to:
List the key roles and responsibilities involved in the Service Receipt process
Explain the steps involved in the Service Receipt process
Create a Service Entry Sheet (SES)
Recognize the additional data to be entered in order to create an SES against a
Legacy PO
Create a new SES from an existing SES for reoccurring service receipts
Approve an SES
Reverse an SES
Delete an SES

Copyright United Nations 4


Agenda

Course Introduction
Module 1: Service Receipt Process Overview
Module 2: Review Purchase Order
Module 3: Create Service Entry Sheet
Module 4: Approve Service Entry Sheet
Module 5: Reverse/Delete Service Entry Sheet
Module 6: Reporting
Course Summary
Course Assessment
Course Survey

Copyright United Nations 5


Module 1 Objectives
After completing this module, you will be able to:
Explain the Service Receipt process
List the important points to remember while creating and assigning an SES

Copyright United Nations 6


Key Terminology
Key Term Description
A buyer-generated document that authorizes a purchase
Purchase Order (PO) transaction. Any service line items on a PO will require a service
entry sheet to confirm receipt and enable invoice matching.
Similar to a Goods Receipt in purpose, a system document
Service Entry Sheet
generated to acknowledge receipt/delivery of services (also
(SES)
known as a material document in Umoja) .
A system document generated for receipt of listed items (goods or
services) in Umoja. The Goods Receipt and a Service Receipt
Material Document processes both generate and post a Material Document which is
used as a reference by many upstream and downstream activities
in Umoja (e.g. invoice processing).
An asset that is not physical in nature; for example, patents,
Intangible Asset
trademarks and software.

Copyright United Nations 7


Key Terminology
Key Term Description
A vendor-generated document that indicates the products,
Invoice
quantities and agreed prices for products delivered by the vendor.
A three-character field in the Umoja ECC system used to describe
the type of material movement that needs to be performed. It is
Movement Type
used for all types of goods movement in Umoja, such as receipts
and reversals.

Copyright United Nations 8


Roles & Responsibilities
The following Umoja Enterprise roles are involved in the Service Receipt process:

Creates purchase requisitions (shopping carts) for


goods or services, as needed
Requisitioner Acts as the Service Receiver, responsible for creating an
SES to confirm delivery of services that have been
contracted by UN

Reviews and approves or rejects supply chain


documents, such as shopping carts (purchase
Approver requisitions), or solicitation documents, POs and
contracts
Accepts/approves an SES created by the Requisitioner

Copyright United Nations 9


Service Receipt Process
Description
In Umoja, an Service Entry Sheet (SES) is used to confirm delivery of services that have
been contracted (i.e. a PO line item for services). It also captures other data,
information or attachments related to the service delivery within the system document,
for example: time sheets, flight completion reports, fuel delivery slips, etc.

Process
When services are received, the user creates an SES in order to confirm delivery of the
services. This process records the rendering of the services in Umoja. An approved SES
must be entered into Umoja before the invoice can be processed and the UN can pay
for the contracted services.

SESs are similar in nature to Goods Receipt documents used


for receipt of materials or goods.

In UN, all intangible goods (e.g. software) are contracted and


delivered as a service, and are therefore received using an SES.

Copyright United Nations 10


Service Receipt Process & Goods Receipt Process Comparison
The graphic below compares the Service Receipt process with the Goods Receipt process.
Note the similar function of the SES and the Goods Receipt documents.
Purchasing Process for Services Purchasing Process for Goods

Shopping Cart Shopping Cart

Purchase Order Purchase Order

Delivery of Service Delivery of Goods

Create SES
Visible in Goods Receipt
Accept SES PO history

Invoice Invoice
Payment Payment

Note: For service contracts requisitioned and arranged by HQ, but received in the mission,
the mission staff may be responsible for the Service Receipt/SES. Specific guidance/policy
on this will be issued for each business area in this regard.

Copyright United Nations 11


Tips for Working with Service Entry Sheets
Some important points to remember while creating and assigning an SES are :
Create a SES as soon as the service task is complete/received. Do not wait for the
vendor invoice to arrive as it may only be submitted much later, after the service
has been performed

Assign the SES creation (or at least the approval) to someone who is familiar and
involved with the service performed. Do not assign the SES creation or approval to
someone who is not knowledgeable about the service delivery

Any freight services, such as those contracted to deliver


goods from Systems or Local contracts (i.e. the freight line on
the shopping cart), will be received by the goods
requisitioning office, using an SES, created and approved
against either the freight service line on the goods PO or the
dedicated freight service PO

Lease In transactions in Real Estate also require an SES


transaction for receipt of those services

Copyright United Nations 12


Learning Checkpoint 1
A(n) _________ is used to confirm delivery of services that have been contracted and
must be entered and approved in Umoja prior to an invoice being processed.

Fill in the blank with the correct option.

A. Goods Receipt document


B. Material document
C. Invoice
D. Service Entry Sheet (SES)

Copyright United Nations 13


Learning Checkpoint 1
A(n) _________ is used to confirm delivery of services that have been contracted and
must be entered and approved in Umoja prior to an invoice being processed.

Fill in the blank with the correct option.

A. Goods Receipt document


B. Material document
C. Invoice
D. Service Entry Sheet (SES)

Option D is the correct answer. An SES is used to


confirm delivery of services that have been
contracted ,and must be entered and approved in
Umoja prior to an invoice being processed.

Copyright United Nations 14


Learning Checkpoint 2
An SES serves a similar function to a Goods Receipt that is used in the purchasing
process for goods?

Select the correct option.

A. True
B. False

Copyright United Nations 15


Learning Checkpoint 2
An SES serves a similar function to a Goods Receipt that is used in the purchasing
process for goods?

Select the correct option.

A. True
B. False

Option A is the correct answer. An SES is similar in


function to a Goods Receipt documents used for
receipt of materials or goods.

Copyright United Nations 16


Module 1 Summary
The key points covered in this module are listed below:
An SES is used to confirm delivery of services and record data related to a service
that was ordered using a PO
The Service Receipt process records the rendering of the services in Umoja
An approved SES must be entered into Umoja before the invoice can be processed
and the UN can pay for the contracted services

Copyright United Nations 17


Agenda

Course Introduction
Module 1: Service Receipt Process Overview
Module 2: Review Purchase Order
Module 3: Create Service Entry Sheet
Module 4: Approve Service Entry Sheet
Module 5: Reverse/Delete Service Entry Sheet
Module 6: Reporting
Course Summary
Course Assessment
Course Survey

Copyright United Nations 18


Module 2 Objectives
After completing this module, you will be able to:
Review a PO in Umoja ECC

Copyright United Nations 19


Review Purchase Order
Because the SES is created against the PO for the service, the SES creator in the
requisitioning office may wish to review the PO prior to confirming delivery. A PO
review is conducted in order to become familiar with the details of the services that
were specified and contracted in the PO.

It is therefore important to know how to review a PO to ensure that the PO matches the
services received, and so you can link the SES with the PO.

The PO contains information such as:


Vendor
Delivery date
Line item details including quantity & price

In the following scenario, it is the end of the month and the mission needs to
pay the monthly Security Guard Service invoice from our annual guard services
contract. In this example, these services have been contracted at a fixed price
of $10,000 per month, for 12 months.

Copyright United Nations 20


Review Purchase Order
The steps to review a PO in Umoja ECC are:
1 Type ME23N in the Command field. The screen displays the last PO that was being
processed
2 Click the Other PO icon (left of the Print Preview icon) to open a new PO
3 Enter the PO number
4 Click the Other Document button

Note: For additional details regarding the requisitioning of


service items, refer to the Umoja Requisitioning course.

Copyright United Nations 21


Review Purchase Order
The PO screen displays. In the following slides, we will look at the different sections of the PO in
detail.

Copyright United Nations 22


Review Purchase Order
The PO screen contains the following fields:
1 Identifying Information for the PO such as PO number, vendor and document date
2 PO Header with several tabs of header level information

2
1

Copyright United Nations 23


Review Purchase Order
3 Item Overview: Note that for Service POs, the Item Overview displays a summary (e.g.
quantity and price) of the all of the services provided under each line item
4 Line Item Detail: Review the details of the line items to be received. Confirm the nature of
services, delivery date, quantity, supplier notes, and other information (refer to the Services
tab for the specific service details of each line item)

Copyright United Nations 24


Review Purchase Order
In the Line Item Detail section, click the Purchase Order History tab to view the history of service
receipts posted against the PO. Note that, the Purchase Order History tab is not visible if there has
not been any previous service receipt action against the PO (i.e. there is no history for the PO).

For each previous service receipt (i.e. an approved SES), an entry in the Purchase Order History tab
will be displayed. It will show the SES number, corresponding material document number (created
by the system after an SES is approved), posting date, quantity and value of the of the receipt
transaction.

The user can click any of the underlined fields to display the referenced document, such as SES
(#1000000202) or the material document (#5000000557).

Note: Movement Types (MvT) for Service POs indicate the type of receipt that was
posted. When an SES is approved, the service is automatically assigned a 101
movement type, which indicates that it has been successfully received and accepted.
Alternatively, if an SES was reversed a 102 movement type is displayed.
Copyright United Nations 25
Simulation Activities
Throughout this training, users will have the opportunity to
conduct activities in the form of simulations. Simulations
are interactive recordings of the Umoja system used to
help facilitate a hands-on learning experience. The
simulation links are provided on the corresponding activity
slides.

Users can access simulations in three different modes:


Show me: Users view a video of an entire transaction
being conducted
Lets do it together: Users will be prompted to input
data at key points during the transaction
(recommended)
Try it: Users can complete an entire transaction on
their own, with no additional instructions provided

Copyright United Nations 26


Activity 1
Click the link below to view a simulation of the Review
Purchase Order transaction.

Transaction Name: Review Purchase Order

Transaction Code: ME23N

Link to the uPerform simulation:


http://unsapuperform.umoja.un.org/gm/folder-
1.11.4522?mode=EU

Copyright United Nations 27


Learning Checkpoint 1
A user can view all previous service receipt actions performed against a PO by
navigating to the ________ tab in the Line Item Detail section of the PO.

Fill in the blank with the correct option.

A. Material Data
B. Invoice
C. Purchase Order History
D. Texts

Copyright United Nations 28


Learning Checkpoint 1
A user can view all previous service receipt actions performed against a PO by
navigating to the ________ tab in the Line Item Detail section of the PO.

Fill in the blank with the correct option.

A. Material Data
B. Invoice
C. Purchase Order History
D. Texts

Option C is the correct answer. All service receipt


actions performed against a PO are listed on the
Purchase Order History in the Line Item Detail
Section of the PO.

Copyright United Nations 29


Module 2 Summary
The key points covered in this module are listed below:
An SES is created against the service PO, therefore the SES creator in the
requisitioning office may wish to review the PO prior to confirming delivery
It is important to know how to review a PO to ensure that the PO matches the
services received and so you can link the SES with the PO
The PO contains information such as vendor, delivery date, line item details and
price
When an SES is approved, the service is automatically assigned a movement type
which indicates the type of receipt that was posted. A 101 movement type
indicates that the SES has been successfully received and accepted. Alternatively,
if an SES was reversed, a 102 movement type is displayed

Copyright United Nations 30


Agenda

Course Introduction
Module 1: Service Receipt Process Overview
Module 2: Review Purchase Order
Module 3: Create Service Entry Sheet
Module 4: Approve Service Entry Sheet
Module 5: Reverse/Delete Service Entry Sheet
Module 6: Reporting
Course Summary
Course Assessment
Course Survey

Copyright United Nations 31


Module 3 Objectives
After completing this module, you will be able to:
Identify the steps to create an SES
Recognize the additional data to be entered to create an SES against a Legacy PO
Create a new SES from an existing SES for reoccurring service receipts

Copyright United Nations 32


Key Terminology
Key Term Description
International Public A set of accounting standards issued by the IPSAS Board for
Sector Accounting use by public sector entities around the world in the
Standards (IPSAS) preparation of financial statements
Refers to invoices or other financial/procurement documents
Workflow being automatically routed to the appropriate approvers based
on Delegation of Authority

Copyright United Nations 33


Create Service Entry Sheet
The steps to creates an SES by the
Requisitioner are as follows:
1
1 Enter ML81N in the
Command field. The screen 2
displays the last PO that was
being processed by the user
2 Click the Other Purchase
Order button to enter the 3
PO that you will be receiving
against. The Select Purchase
Order/Entry Sheet pop-up 4
window is displayed
3 Enter the PO number in the
Purchase Order field or
search using the matchcode
function
4 Click the Continue icon

Copyright United Nations 34


Create Service Entry Sheet
5 Click the Create Entry Sheet
icon

This creates a blank SES in the 5


system, and links it to the PO
that was entered in the
previous step. This also
adopts or copies the basic
information of the PO to the
SES (e.g. vendor information).

Copyright United Nations 35


Create Service Entry Sheet
To populate the SES with the details
6
of the service(s) that is to be received:
6 Click the Basic Data tab
7 Click the Service Sel. button. This
will display the services that are
listed on the PO and allow the
user to select which services are
to be received with this SES
transaction

Copyright United Nations 36


Create Service Entry Sheet
8 In the Service Selection pop-up window, confirm the corresponding PO number is listed in
the From Purchase Order field
9 Click the Continue icon

Copyright United Nations 37


Create Service Entry Sheet

10 Click the grey box on the left of each corresponding line item to select the specific services
from the PO that are to be received with this SES. More than one line can be selected and
the quantities received will be updated in subsequent steps

11 Click the Services button to adopt or copy the service details from the PO to the SES, and
to continue with the completion of the SES

11

10

Copyright United Nations 38


Create Service Entry Sheet

12 Confirm the quantity of services to be received for each line item in the Quantity column, and
adjust as required

13 Enter a description of this transaction/service receipt in the Short Text field as a reference (40
character limit). For example: HQ Guard Services for July 2013

13

12

Copyright United Nations 39


Create Service Entry Sheet

13 Click the Accept. Data tab

14 Populate the following fields:
Doc.: Ensure that the date is todays date (date that the SES is created)
Posting: In accordance with IPSAS requirements, the Posting date must be updated to
reflect the date when the services were actually received, or the last day they were
received in case of service delivery which takes place over a period of time

13

14

Copyright United Nations 40


Create Service Entry Sheet

15 Select Records Management Logistics from the Services for Object drop-down list, to add
an attachment
Attach any relevant supporting reference documents, for example time sheets for
consultant services, flight completion report, freight delivery note, fuel delivery note,
etc.
For more information on how to add attachments, please refer to the ECC Navigation
course

15

Copyright United Nations 41


Create Service Entry Sheet

16 Click the Save icon to finalize the 16
SES for acceptance/approval

The SES now needs to be accepted


or approved before the invoice can
be processed

There is currently no workflow


associated with SES approvals in
Umoja and the approver must be
notified offline

17 Take note of the SES document 17


number and communicate this
number, and the requirement to
have the SES approved, to the
applicable cost centre Approver

Copyright United Nations 42


Service Entry Sheets for Legacy POs
Within Umoja, there exists a group of POs that were converted from legacy systems
(e.g. from Mercury) during the missions cutover period during Umoja implementation.
These POs have the document type ZMIG and the PO number follows the format
24xxxxxxxx.

When creating an SES against a PO that has been converted from a legacy system (a
legacy PO), the user needs to manually enter the service line item details in the
following fields as this information will not be adopted from the legacy PO:
Quantity: This represents the quantity of the service received
Un: This represents the unit of measurement used when quantifying the service
Gross Price Fields: This represents the value of the service received, prior to
deductions
Short Text (of the Line Item): This provides the description of the service on the PO

Copyright United Nations 43


Service Entry Sheets for Legacy POs
Legacy PO numbers are also being maintained in Umoja ECC. The Legacy PO number will
be stored in the ECC PO header, under the Additional Data tab, in the Collective No.
field.

In cases when the Legacy PO number is greater than ten characters, the Collective No.
field will be populated by a * + the last 9 characters of the PO. The full legacy PO
number will be stored in a header text field, under the Texts tab of the PO header.

Copyright United Nations 44


Create Service Entry Sheet Tip for a Reoccurring SES
If you have an identical, reoccurring service receipt requirement (against the same service PO) for
example a monthly service bill on an annual contract - it is possible to create new SES based on the
details of a previously created SES. This reduces the time required to complete the transaction each
time and data re-entry.
The steps to create a duplicate copy of a previous SES are as follows:
1 Open a previous SES
2 With the previous SES open on the screen, click the Copy Entry Sheet icon
3 Before saving the new SES, ensure that all relevant information (i.e. posting dates, description,
quantities, attachments etc) is updated to reflect the new service receipt transaction

Copyright United Nations 45


Activity 2
Click the link below to view a simulation of the Create
Service Entry Sheet transaction.

Transaction Name: Create Service Entry Sheet

Transaction Code: ML81N

Link to the uPerform simulation:


http://unsapuperform.umoja.un.org/gm/folder-
1.11.4530?mode=EU
For the purposes of demonstration, this
simulation will use a different type of service PO
formulation. By flipping the quantity and
price this formulation enables partial payments
and service delivery each period against the PO
(e.g. each month). For additional details regarding
the requisitioning of service items, refer to the
Umoja Requisitioning course.

Copyright United Nations 46


Learning Checkpoint 1
To comply with IPSAS guidelines, what date must be entered in the Posting date field of
the Accept Data tab?

Select the correct option.

A. The date the SES is created


B. The date the services were actually received
C. The date the PO was created
D. The date the services are billed

Copyright United Nations 47


Learning Checkpoint 1
To comply with IPSAS guidelines, what date must be entered in the Posting date field of
the Accept Data tab?

Select the correct option.

A. The date the SES is created


B. The date the services were actually received
C. The date the PO was created
D. The date the services are billed

Option B is the correct answer. To comply with


IPSAS guidelines, the Posting date must be
updated to the date when the services were
actually received.

Copyright United Nations 48


Learning Checkpoint 2
Umoja currently has workflow associated for SES approvals to ensure that the applicable
cost center Approver is automatically advised of an approval task.

Select the correct option.

A. True
B. False

Copyright United Nations 49


Learning Checkpoint 2
Umoja currently has workflow associated for SES approvals to ensure that the applicable
cost center Approver is automatically advised of an approval task.

Select the correct option.

A. True
B. False

Option B is the correct answer. There is currently


no workflow associated with SES approvals in
Umoja. The Approver must be advised by the SES
creator (offline) of the SES number and
requirement to approve a saved SES

Copyright United Nations 50


Module 3 Summary
The key points covered in this module are listed below:
An SES is created against the service PO, which allows data to be transferred
directly from the PO into the new SES
Details of the service(s) that is to be received can be copied from the linked PO or
entered manually
When creating an SES for a PO that has been converted from a legacy system, the
user needs to manually enter the details of the PO
A new SES form can be created from an existing SES, for reoccurring service
receipts
There is currently no workflow associated with SES approvals in Umoja. The
Approver must be advised by the SES creator (offline) of the SES number and
requirement to approve a saved SES

Copyright United Nations 51


Agenda

Course Introduction
Module 1: Service Receipt Process Overview
Module 2: Review Purchase Order
Module 3: Create Service Entry Sheet
Module 4: Approve Service Entry Sheet
Module 5: Reverse/Delete Service Entry Sheet
Module 6: Reporting
Course Summary
Course Assessment
Course Survey

Copyright United Nations 52


Module 4 Objectives
After completing this module, you will be able to:
Identify the steps to approve the SES

Copyright United Nations 53


Approve Service Entry Sheet
When advised by the Requisitioner (offline), the Approver enters into Umoja and approves the SES.
The steps to approve an SES are as follows:
1 Type ML81N in the Command field. The screen displays the last PO that was being
processed

Copyright United Nations 54


Approve Service Entry Sheet
2 Click the Other Purchase Order button to retrieve a saved SES for approval
3 In the pop-up window, type the Entry Sheet (SES) number that needs approval
4 Click the Continue icon

Copyright United Nations 55


Approve Service Entry Sheet
To approve the SES, it must be in the Edit mode.
5 Click the Entry Sheet menu
6 Select the Display Change menu item.
Alternatively, simply click the Display Change icon on the SES to change to Edit mode

Review all of the information in the entry sheet for accuracy (including any attachments using
the Services for Object icon) .

5 4
6

Copyright United Nations 56


Approve Service Entry Sheet
7 After verifying that all the information on the SES is accurate, click the Accept/Flag icon to
accept/approve the SES

The SES status will then change to Will be Accepted status.

Copyright United Nations 57


Approve Service Entry Sheet
8 Click the Save icon to save and post the accepted SES. A Material Document (a system term
for a Goods/Services Receipt) is created and the SES is also assigned a Material Document
number.
The status of the SES is now Accepted (i.e. Approved).

Copyright United Nations 58


Confirm Posting of Service Entry Sheet
To confirm posting of the SES, the user can return to the PO display screen and view the history of
service receipt actions performed against the PO. The steps to confirm posting of an SES are as
follows:
1 Type ME23N (or /nME23N from inside another transaction) in the Command field
2 Click the Purchase Order History tab to review the service receipt actions taken
3 Confirm a 101 movement type is displayed next to the Material Document number
created by the system, in reference to the SES. This indicates the SES successfully posted

Copyright United Nations 59


View Service Entry Sheets for Approval
The Approver can also view a list of SESs that require approval by use the T-code ML84 in the
Command field. This T-code will produce a report with all SESs that have not been accepted
(approved) indicated by a red traffic light icon. The steps to view service entry sheets for approval
are as follows:
1 This report can be generated using criteria to filter results. After entering PO or Entry Sheet
criteria (e.g. document date, plant, etc) click the Execute icon to run the report
2 The Approver can double click on the SES number (Entry Sh.) in the report to view the SES in
display mode (only). The Approver must still initiate the SES approval using the T-code ML81N

Copyright United Nations 60


Activity 3
Click the link below to view a simulation of the Approve
Service Entry Sheet transaction.

Transaction Name: Approve Service Entry Sheet

Transaction Code: ML81N

Link to the uPerform simulation:


http://unsapuperform.umoja.un.org/gm/folder-
1.11.4526?mode=EU

Copyright United Nations 61


Learning Checkpoint 1
What T-code is used to view a list of SESs requiring approval ?

Select the correct option.

A. ML84
B. ME2N
C. ME23N
D. ML81N

Copyright United Nations 62


Learning Checkpoint 1
What T-code is used to view a list of SESs requiring approval ?

Select the correct option.

A. ML84
B. ME2N
C. ME23N
D. ML81N

Option A is the correct answer. ML84 is used to


view a list of SESs requiring approval.

Copyright United Nations 63


Module 4 Summary
The key points covered in this module are listed below:
The Approver reviews the accuracy of the information in the entry sheet and then
accepts it, thereby approving the SES
When the SES is accepted, a Material Document is created
A user can display a list of SESs requiring approval using T-code ML84

Copyright United Nations 64


Agenda

Course Introduction
Module 1: Service Receipt Process Overview
Module 2: Review Purchase Order
Module 3: Create Service Entry Sheet
Module 4: Approve Service Entry Sheet
Module 5: Reverse/Delete Service Entry Sheet
Module 6: Reporting
Course Summary
Course Assessment
Course Survey

Copyright United Nations 65


Module 5 Objectives
After completing this module, you will be able to:
Identify the steps to reverse an SES

Copyright United Nations 66


Reverse Service Entry Sheet
A user can reverse an SES entry (e.g. received quantity on the SES incorrect, posting date incorrect,
other error that requires the SES to be reversed, edited and re-approved). The steps to reverse SES
are as follows:
1 Type ME23N (or /nME23N from inside another transaction) in the Command field
2 Click the Purchase Order History tab to review the data and confirm that a Service Receipt
needs to be reversed (note the SES number)

Copyright United Nations 67


Reverse Service Entry Sheet
3 Type ML81N (or /nML81N from inside another transaction) in the Command field
4 Click the Other Purchase Order button to retrieve the SES to reverse
5 In the pop-up window, type the Entry Sheet (SES) number that needs to be reversed
6 Click the Continue icon

Copyright United Nations 68


Reverse Service Entry Sheet
7 Click the Entry Sheet menu to edit the data in the SES
8 Select the Display Change menu item
Alternatively, simply click the Display Change icon on the SES to change to Edit mode
9 Click the Revoke Acceptance icon to reverse this SES. After clicking the icon, the
Approve button appears again and the status of the SES is changed from Accepted to
Acceptance Revoked

8 9

Copyright United Nations 69


Reverse Service Entry Sheet

10 Click the Save icon. A pop-up
window appears for the user to 10
add reference information (note
the reason of the reversal)

When the transaction has been saved,


the SES is saved with a No acceptance
status.

The POs history would now display a


102 movement type against a new
Material Document number to show
that the SES has been reversed in a
separate transaction.

The SES can also now be


edited/corrected, saved, and re-
Note: If an invoice has already been posted for the
approved, and will retain the same SES
approved SES, the SES cannot be reversed, acceptance
document number.
cannot be revoked and an error will be generated.

Copyright United Nations 70


Delete Service Entry Sheet
The steps to delete SES (inadvertently received services) are as follows:
1 Type ML81N (or /nML81N from inside another transaction) in the Command field to open
the SES
2 Click the Entry Sheet menu and select the Display Change menu item/icon
3 Click the Delete icon to delete the SES
2
1

Copyright United Nations 71


Delete Service Entry Sheet
The status is now Deleted. The SES still appears on the POs Purchase Order History screen.
However, the amount now shows $0.

While the SES has been deleted, the original SES document and number will remain in the
Purchase Order History, along with the posting date for historical reference/auditing.

An associated Material Document is also generated by the system with a Movement Type 102 to
show the deletion/reversal of receipt and is also now displayed in the PO history.

Copyright United Nations 72


Activity 4
Transaction Name: Reverse Service Entry Sheet

Transaction Code: ML81N

Link to the uPerform simulation:


http://unsapuperform.umoja.un.org/gm/folder-
1.11.4534?mode=EU

Copyright United Nations 73


Learning Checkpoint 1
When an SES is reversed, what movement type is displayed in the Purchase Order
History tab?

Select the correct option.

A. 101
B. 102
C. 103
D. 104

Copyright United Nations 74


Learning Checkpoint 1
When an SES is reversed, what movement type is displayed in the Purchase Order
History tab?

Select the correct option.

A. 101
B. 102
C. 103
D. 104

Option B is the correct answer. When an SES is


reversed, 102 movement type is displayed in the
Purchase Order History tab.

Copyright United Nations 75


Module 5 Summary
The key points covered in this module are listed below:
In the event of an incorrect entry or other such circumstances, an SES Entry can be
reversed using the T-code ML81N
An SES can also be deleted completely if services were inadvertently received.
Though an SES can be deleted, the SES document and number always remains in
the Purchase Order History of the PO

Copyright United Nations 76


Agenda

Course Introduction
Module 1: Service Receipt Process Overview
Module 2: Review Purchase Order
Module 3: Create Service Entry Sheet
Module 4: Approve Service Entry Sheet
Module 5: Reverse/Delete Service Entry Sheet
Module 6: Reporting
Course Summary
Course Assessment
Course Survey

Copyright United Nations 77


Module 6 Objectives
After completing this module, you will be able to:
List the types of reports available for the Service Receipt process and their T-Codes

Copyright United Nations 78


Reporting
The following reports are available for SES Reporting:
List of Service Entry Sheets
Purchase Order Report
Purchasing Documents Report

T-Codes: Reports

List of Service Entry Purchasing Documents


Purchase Order Report
Sheets Report
ML84 ME2K ME80FN

Copyright United Nations 79


List of Service Entry Sheets Report
As previously mentioned, the List of Service Entry Sheets report is a useful report for
monitoring SESs and their approval status. There is a radio button at the bottom of the
report which allows you to report on all SESs which have not been accepted (default
setting).

Other useful parameters can also be


maintained, for example, plant and
purchasing groups.

T-Code: ML84

Copyright United Nations 80


Purchase Order Report
The user can generate a list of POs by PO number for a mission/location. This allows the
user to find the status/details of a particular PO. Other variations of this report allow
views by vendor, material and others.

In the report below, you can populate


any of the search fields to customize
the report. The report allows the user
to search for all documents matching
each criteria, or the user can choose a
range for example, delivery date, to
search by. The fields in the red boxes
are the most commonly filtered fields.

T-Code: ME2K

Tip: Insert a D in the Item


Category filter field to ensure
that you only see POs that
contain service line items.

Copyright United Nations 81


Purchasing Documents Report
The user can generate an overall purchasing report to view details of documents related
to supply chain transaction, such as, Purchase Orders, Material Documents and others.
Report is very customizable to include fields that a user may need and assists with
further analysis.

In the report below, populate any of the search fields to customize the report. The
report allows the user to search for all documents matching each criteria, or the user
can choose a range, for example, delivery date to search by. The fields in the red boxes
are the most commonly filtered fields.

T-Code: ME80FN

Copyright United Nations 82


Learning Checkpoint 1
Which of the following report is useful for monitoring SESs in Umoja?

Select the correct option.

A. List of Service Entry Sheets


B. Purchase Order
C. Material Document
D. Purchasing Documents

Copyright United Nations 83


Learning Checkpoint 1
Which of the following report is useful for monitoring SESs in Umoja?

Select the correct option.

A. List of Service Entry Sheets


B. Purchase Order
C. Material Document
D. Purchasing Documents

Option A is the correct answer. The List of Service


Entry Sheets report is useful for monitoring SESs in
Umoja.

Copyright United Nations 84


Module 6 Summary
The key points covered in this module are listed below:
There are three types of reports used for SES reporting: List of Service Entry
Sheets, Purchase Order Report, and Purchasing Documents Report
All of these reports are customizable

Copyright United Nations 85


Agenda

Course Introduction
Module 1: Service Receipt Process Overview
Module 2: Review Purchase Order
Module 3: Create Service Entry Sheet
Module 4: Approve Service Entry Sheet
Module 5: Reverse/Delete Service Entry Sheet
Module 6: Reporting
Course Summary
Course Assessment
Course Survey

Copyright United Nations 86


Course Summary
The key points covered in this course are listed below:
An SES is used to confirm delivery of services and record data related to a service
that was ordered using a PO line item for services
The Service Receipt process records the rendering of the services in Umoja
An approved SES must be entered into Umoja before the invoice can be processed
and the UN can pay for the contracted services
Before creating an SES to receive services, the Requisitioner reviews the PO to
confirm the services and quantity to be received
The SES creator used the T-code ML81N to create an SES against a PO line item for
services

Copyright United Nations 87


Course Summary
The key points covered in this course are listed below:
An Approver reviews the accuracy of the information in the entry sheet and then
approves it using the T-code ML81N
There is currently no workflow associated with SES approvals in Umoja.
In the event of an entry error an SES Entry can be reversed using the T-code ML81N
The T-code ML81N is also used for delete an SES, however, the related SES system
document will remain associated with the PO
There are three types of reports used for SES reporting: List of Service Entry Sheets,
Purchase Order Report, and Purchasing Documents Report

Copyright United Nations 88


Agenda

Course Introduction
Module 1: Service Receipt Process Overview
Module 2: Review Purchase Order
Module 3: Create Service Entry Sheet
Module 4: Approve Service Entry Sheet
Module 5: Reverse Service Entry Sheet
Module 6: Reporting
Course Summary
Course Assessment
Course Survey

Copyright United Nations 89


Course Assessment
Now that you have completed all the modules in this course, you can test your
knowledge by completing the Course Assessment.

To receive credit for completing this course, you must pass this assessment with a
minimum score of 90%.

To complete the assessment you must return to the Learning Management System:
1. Log into Inspira
2. Navigate to Main Menu -> Self-Service -> Learning -> My Learning
3. Search for the name of the course under the My Learning Activities section
4. Click the Start link of the course assessment
5. Click the Submit button once you have completed the assessment

Copyright United Nations 90


Agenda

Course Introduction
Module 1: Service Receipt Process Overview
Module 2: Review Purchase Order
Module 3: Create Service Entry Sheet
Module 4: Approve Service Entry Sheet
Module 5: Reverse/Delete Service Entry Sheet
Module 6: Reporting
Course Summary
Course Assessment
Course Survey

Copyright United Nations 91


Course Survey
Your feedback is important to the continuous improvement of our training program.

Please complete the evaluation for this course using the following steps:
1. Log into Inspira
2. Navigate to Main Menu -> Self-Service -> Learning -> My Learning
3. Search for the name of the course under the My Learning Activities section
4. Click the Start link of the course survey
5. Click the Submit button once you have completed the course survey

Copyright United Nations 92


Congratulations! You have successfully completed the
Umoja Service Receipt Process course.

Copyright United Nations 93

Potrebbero piacerti anche