Sei sulla pagina 1di 22

Analysis of Relationship Between Time and Cost Overruns in some Infrastructure Projects 5

Analysis of Relationship between Time and


Cost Overruns in
some Infrastructure Projects
Hariharan S.* and P. H. Sawant**

Abstract : Projects undertaken in India have grown in size and large infrastructure
projects are being executed in various parts of the country. Indian construction
industry is expected to grow at 25-30% during 2010-2012. World Bank
estimates suggest that India's urban population will be close to 500
million by 2017, putting massive pressure on civic infrastructure. Risk
Management is gaining significance with increasing number of projects
and project complexities in Indian scenario. Risk level in a project varies
depending on the nature of the project and the parties that are involved
in the project. Impact of risk can be positive or negative and therefore
assessment of risk should be ongoing and dynamic. Previous research
findings related to risk management in Indian construction industry are
referred and significant findings are discussed. Researchers in the past
have identified schedule and cost over run as major problems associated
with Indian construction industry. Data related to schedule over run and
corresponding cost over run in Indian infrastructure projects of the past
20 years have been collected and presented in this paper. The paper
attempts to analyze whether the estimation of project time and cost is
realistic in Indian Infrastructure projects. Particular attention is paid to
schedule and cost over run in projects, associated risks and mitigation
measures. Pearson's correlation coefficient is used in understanding the
correlation between schedule and cost overrun. The result is confirmed
with the test findings using ANNOVA technique. Though there is a
strong correlation between time and cost over run the drivers of time
and cost overrun are not the same. While the time over run is attributed
to scope changes, delay in finalization of tender documents and short
bid submission time, lack of commitment of project participants, poor
coordination etc., cost overrun is attributed to more variations between
quantities estimated and actually executed. The research outcome suggests
that Indian construction industry needs to employ innovative technologies
and better contract management strategies to overcome surprises and
challenges as the project progresses. A shift from the current practices
towards electronic tendering process, online contract bidding document
etc can make the bidding process transparent and evaluation more realistic
in nature.

Keywords: Infrastructure Projects, Schedule Overrun, Cost Over Run, Pearson's Correlation,
Coefficient, Annova F-Test.

*Research Scholar and **Principal, Sardar Patel College of Engineering, Mumbai, India. Email : hari4444@yahoo.com
6 NICMAR-Journal of Construction Management, Vol. XXVII, No. 2&3, April-June & July-Sept. 2012

INTRODUCTION works by client were found to drive time and cost


Risk is not an entity to be managed separately overrun in projects (Satynarayana, K. N. & Iyer,
in a project as project management by itself is K. C., 1996).
risk management. In other words a good project
Studies show that financial performance indicators
management signifies the ability of project team
of a BOT project can be quite sensitive to the
to reasonably forecast uncertainties and develop
selected D/E ratio and decline rapidly as the
suitable mitigation measures as the project
promoter borrows more than the optimal amount
progresses. Risk level in a project varies at various
in an attempt to reach the project's debt capacity
stages depending on the nature of the project,
level (Dias and Ioannau 1995, Esther Malini 1996).
type of resources and the existing socio political
Any BOT project is considered financially viable
environment. Impact of risk can be positive or
when the following 3 conditions are simultaneously
negative and therefore assessment of risk should
satisfied. NPV should be positive for the project.
be ongoing and dynamic. Considerable research
Financial IRR should have a value greater than
has already been carried out related to
the discount rate. Cash flow (Liquidity) situation
performance of Indian construction industry.
in each year of concession period should be
Researchers in the past have identified schedule
satisfactory. In other words cash balance at the
and cost over run as major problems associated
end of every year should be positive. (Esther Malini
with Indian construction industry (K.C. Iyer &
1999). Iyer, K. C & Jha, K. N (2005) observed
Jha 2006). Many factors have been attributed to
effective monitoring, feedback of project manager
schedule and cost over run problems. Data related
and skills of PM as success attributes and negative
to schedule over run and corresponding cost over
attribute of PM and inadequate problem
run in Indian infrastructure projects of the past
formulation at the beginning of project as failure
20 years have been analyzed in this paper. The
attributes in a project. They concluded that it is
paper attempts to analyze whether the estimation
not sufficient to maximize the result of positive
of project cost & time is realistic in Indian
attribute but also important to minimize negative
Infrastructure projects. Particular attention is paid
impacts of failure factors. Sadi.A.Assaf and Sadiq.Al-
to schedule and cost over run in projects, associated
Hejji (2006) listed a number of factors influencing
risks and mitigation measures.
timely completion in large construction projects.
LITERATURE REVIEW Iyer & Jha (2006) reported that over 40% of Indian
In Indian construction sector, problems start with construction projects are facing time overrun
inception of the projects. Pre construction ranging from 1 to 252 months. 55 attributes were
planning, execution and post construction identified as factors responsible for impacting
planning in many cases are found to be unrealistic performance of the projects and were presented
where projects suffer from schedule related risk to Indian construction professionals in the form
and associated risk of cost escalation leading to of a questionnaire. Based on responses received
dispute. Various researchers have contributed to it is concluded that two success factors namely
construction risk management research in the past commitment of project participants; owner's
and their findings are listed in this section. competence and one failure factor namely conflict
Following sections describe factors identified by among project participants contribute significantly
researchers that drive schedule and cost over run in enhancement of performance level of the
in Indian infrastructure projects. Ambiguity in project.(Iyer and Jha 2006). In order to predict
specification and delay in approval of completed when and where the risk will reach its highest
Analysis of Relationship Between Time and Cost Overruns in some Infrastructure Projects 7

level, analysis should be performed based upon infrastructure projects. (Sawhney Anil et.al., 2011).
various information including statistical sources Experts in the construction industry believe that
such as accident histories and this should be done the traditional principle of choosing the lowest
in coordination with the activity scheduling. (Yi, possible price by adopting "hard bid" method carries
K.J., and Langford, D. 2006). The selection of a high degree of risk. Public work constructions
a lowest bidder is one of the major reasons for based on the hard bid method have experienced
project delivery problems as contractors, when a surge in litigation during the 1990s which tend
faced with shortage of work, desperately quoted to increase the risk of the project (Karam 1998).
a low bid price simply to remain in business with The selection of a lowest bidder is one of the major
the expectation to be offset through claims (Singh reasons for project delivery problems as contractors,
and Tiong 2006). M. Pilar de la Cruz et.al (2006) when faced with shortage of work, desperately
included a list of 96 risk events, categorized and quoted a low bid price simply to remain in business
prioritized first by impact, then by frequency. The with the expectation to be offset through claims
most relevant ones are related to issues such as (Singh and Tiong 2006). Project specific risk factors
an inadequate prequalification system, insufficient such as size of project, tender selection methods,
training of public servants, or political location uniqueness, regulatory approvals, land
considerations prevailing over real needs, among acquisition, utility shifting, flow of information
others. Much of the project scheduling literature & finance were found to influence infrastructure
treats task durations as deterministic. In reality, project completion to a greater extent in Indian
however, task durations are subject to considerable scenario. These risks shall be handled on a fair
uncertainty, and that uncertainty can be influenced basis by providing suitable built in mechanism in
by the resources assigned. (Vaziri, K., et al 2007). the contract. Climatic conditions, equipment
Construction projects and contracts have become breakdown and differing site conditions are very
complex with potentially greater risk. Project closely related and need to be assessed as a single
completion depends largely on competent project combined factor. i.e the adverse climatic condition
administration coupled with more accurately coupled with equipment breakdown or differing
worked out project risk management. Each one site condition can be serious and can increase the
is connected to the other through a network of project risk in geometric proportion. Therefore,
large number of activities creating rights and risk management is a dynamic process which
obligations. Uncertainty of performance by one continues as the project progresses. In broad sense
or the other agency has serious ripple effect parties should know the major risks that cannot
challenging project managers to find solutions be transferred and needs to be apportioned among
almost on continued basis to eliminate or minimize project participants. Risk shall be assigned to the
various risks. (Dave 2007). Construction activities party who has better ability to manage the risk.
can be categorized as procurement, design, Schedule and cost overrun factors can be best
construction and managerial but cannot be managed by project managers and hence project
standardized because each project is unique with manager specific risks and mitigation measures
its specified condition. (Okmen, O.,and Oztas, are discussed in this paper.
A. 2008). Lack of commitment, inefficient site
management, poor site coordination, improper SCOPE AND OBJECTIVES
planning, lack of clarity in project scope, lack of Project Managers have a critical role in estimating
communication and substandard contract are the project cost and completion time. Objective
found to drive schedule and cost over run in Indian of this paper is to explain the significance of project
8 NICMAR-Journal of Construction Management, Vol. XXVII, No. 2&3, April-June & July-Sept. 2012

manager specific factors in smooth completion


% of Total Investment
of project in Indian scenario. The paper attempts 80
to analyze the relation between schedule and cost 70
overrun and evaluate whether the estimation of 60
project time & cost is realistic in Indian 50
68.01
Infrastructure projects. Particular attention is paid 40
to schedule and cost over run in projects, associated 30
risks and mitigation measures. 20
28.78
10 3.21
Infrastructure Project Scenario In India
0 Mega Major Medium
Projects undertaken in India have grown in size Projects Projects Projects
and large infrastructure projects are being executed % of Total Investment
in various parts of the country. Government is
Figure 2 : Percentage Of Total Investment
expected to spend more than one trillion dollars
on infrastructure upgrades between 2012 and 2017. The report covers a total of 951 projects which
Indian construction industry is expected to grow comprises of 112 mega projects (each costing
at 25-30% during 2010-2012. World Bank estimates ` 1,000 crore and above), 499 major projects (each
suggest that Indias urban population will be close costing between 100 crore and ` 1000 crore)
to 500 million by 2017, putting massive pressure and 340 medium projects (each costing between
on civic infrastructure. ` 20 crore and ` 100 crore). Major and Mega
projects account for about 62% of the total
Fig. 1 shows number of projects under various number of projects and about 96% of the total
groups as per the Quarterly Project Implementation anticipated cost.
Status Report on Central Sector Projects for the
quarter June, 2009 issued by the Ministry of Schedule And Cost Overrun Scenario In Indian
Infrastructure Projects
statistics & program implementation, Government
of India. The report reveals the status of various Cost is a primary measurement of the success of
infrastructure projects implemented in the country every project. Unrealistic cost estimates and
in the past two decades. Fig. 2 shows percentage unexpected expenditures can change an otherwise
of investments in these projects. successful capital investment into an investment
failure. The Status Report on Central Sector
Projects claims that a continuous decline in the
Number of Projects
600 extent of time and cost overruns which is attributed
500 to closer monitoring and system improvements
400 by the Ministries concerned. The recorded data
300 499 for the period between 1991 to 2009 shows that
200 340 the cost overrun has declined from 61.6% in
100 112 March, 1991 to 12.1% in June, 2009
0
Mega Major Medium (Refer Fig. 4) which claims to have resulted in
Projects Projects Projects substantial savings. Fig. 3 shows the variation in
Number of Projects time overrun during the same period.
Figure 1 : Number Of Mega,
Major & Medium Projects
Analysis of Relationship Between Time and Cost Overruns in some Infrastructure Projects 9

Factors Driving Delay In Indian Infrastructure coefficient (r) is a measure of the strength of the
Projects association between the two variables. Table 1 shows
Among all the cases discussed, Road Transport Pearson's correlation coefficient relating schedule
& Highway projects reported major schedule and cost overrun. Pearson's product moment
overrun. Out of 196 Road & Highway projects correlation coefficient for the given set of data
159 are found to be affected with schedule overrun is found to be 0.8146 indicating there is a strong
with delay ranging from 1 to 96 months. The positive correlation between the variables.
report also shows that only 12 of the 196 projects The above results were confirmed with ANNOVA
suffer a cost overrun of 22.54%. 67 out of 257 test. F Test using ANNOVA Technique is
railway projects reported time overrun with time performed on the above sample and the following
delays ranging from 8 - 180 months where 189 results were obtained. Table 2 shows F Test using
of 257 projects suffer a cost over run close to 129%. ANNOVA Technique. The calculation results in
Fig. 5 shows the details of major factors that drive F value for the analyzed data equal to 11.31 with
schedule overrun in Indian scenario. It is also found significance level of 0.0019 shows that correlation
that many of the large infrastructure projects suffer between factors is significant. As the value of
due to lack of planning and coordination resulting is 0.0019 is found to be less than 0.05, the variation
in claims and disputes. is realistic and not by chance. However, the question
RESEARCH METHODOLOGY that remains unanswered is the extent to which
schedule over run drives the cost over run. The
Research methodology involves analyzing the
drivers for schedule delays are not necessarily
statistical data related to schedule and cost over
contributing to cost over run in Indian
run in projects with Pearson's correlation
infrastructure projects. Some significant
coefficient and confirming the validity of the same
observations made by the authors are listed below.
using F-test. Correlation is a technique for
investigating the relationship between two Table 3 & Table 4 shows sector-wise total number
quantitative, continuous variables, for example, of projects & number of projects that reported
schedule and cost overrun. Pearson's correlation only cost overrun and only time overrun. Table

Trend of Time Overrn


% of Time Overrun

70
60
50
40
30
20
10
0
June, 2009
March, 93
March, 94
March, 95
March, 96
March, 97
March, 98
March, 99

March, 2003
March, 2004

March, 2006

March, 2009
March, 2001

March, 2008
March, 2000

March, 2005

March, 2007
March, 2002

Figure 3 : Trend Of Time Overrun


10 NICMAR-Journal of Construction Management, Vol. XXVII, No. 2&3, April-June & July-Sept. 2012

Trend Of Cost Overrun

% of Time Overrun
70
60
50
40
30
20
10
0

98

June, 2009
March, 91
March, 92
93
94
95
96
97

March, 2001
March, 2002

March, 2004

March, 2007
March, 2008
March, 2009
March, 99

March, 2006
March, 2003

March, 2005
March, 2000
March,
March,
March,
March,
March,
March,

Figure 4: Trend Of Cost Overrun

Major Drivers for Delay in Projects


70
123
123
123
123 Fund Constraints
60 123
123
123
123
123
50 123
123
123 123 Land Acquisition
123
123 123
123 123
40 123 Problems
123
123
123
123
123
30 123 123
123 123 Slow Progress in Works
123 123
123
123
20 123 Other than Civil Works
123
123
123
123
123
123
10 123
123
123
123
123 123 123 12 Delay in Supply of
123
123 123 123 123 12
123 123 123 123 12
123
123
123
123
123
12
123
123
123
123
123
123
123
123
123 12
12312
123 123123
123 123
123123
123
123 Equipment
0
Petroleum
Railways

Coal

Power

Steel

12
12 Environmental Clearance

Figure 5 : Major Drivers Of Delay In Infrastructure Projects


5 number of projects reported both time and cost overrun show value of 0.33 indicating that they
overrun. It is found that out of 951 projects 32.5% are driven by factors independent of each other.
of projects reported only time over run and 50% It is interesting to note that while a total of 334
of projects reported only cost overrun. However, projects were found to run under time over run
14.6% projects were found to be affected with with only 170 projects reporting cost over run.
both time and cost overrun. Though there is a
FINDINGS & DISCUSSION
strong correlation between time and cost overrun,
Pearsons moment correlation coefficient between Out of 951 projects 140 projects were found to
projects reported only time over run and only cost have both time and cost overrun. 334 projects
Analysis of Relationship Between Time and Cost Overruns in some Infrastructure Projects 11

Table 1: Pearson Correlation Table such poor estimation. Some of the projects were
reported as projects completed within estimated
% of Time % of Cost
Year
Overrun Overrun
cost in spite of a time over run of 9 to 33 months.
It is worth mentioning that during these years
March, 1993 62.22 56.80
(between years 2003 to 2010) the price of steel
March, 1994 58.22 57.50
and cement saw an increase of 60% and 76%
March, 1995 62.70 51.40 respectively. This raises a serious question whether
March, 1996 58.35 46.90 the cost arrived at originally was based on realistic
March, 1997 57.73 45.00 estimates. Out of total 146 contracts that were
March, 1998 46.94 37.30 considered for performance audit, 34 were found
March, 1999 53.11 40.90 to run under a time delay of 1 to 17 months. The
March, 2000 44.99 36.00 time over run was mainly attributed to delay in
March 2001 37.66 36.00 finalization of tender documents. In many of the
March, 2002 31.72 26.00 cases Notice Inviting Tender (NIT) were issued
close to the date of awarding of contract leaving
March, 2003 39.44 22.30
little scope for judiciously evaluating and finalizing
March, 2004 37.15 22.40
the bids. In-order to gain time for execution, it
March, 2005 39.02 17.70
is observed that bid preparation time is kept to
March, 2006 38.80 17.40 the minimum (Mithun K, 2010).
March, 2007 34.13 14.51
Single stage single envelope system is still followed
March 2008 41.91 12.06
in many of the cases where as the recommended
March, 2009 48.11 13.45
being single stage double envelope system. It is
June, 2009 40.84 12.10 also found in the present study that lowest bid
reported within cost but having time over run criteria in many of the cases resulted in contracts
(which comprises of 25 Mega Projects,209 major being awarded to those contractors who failed in
projects and 100 medium projects). 170 projects mobilizing adequate manpower and timely
were having only cost over run but were completed completion of work in the past. There is an urgent
within estimated time (which comprises of 7 Mega need in bringing qualitative change in project
Projects, 97 major projects and 64 medium planning, monitoring and control. More scientific
projects). and realistic methods need to be adopted while
estimating time & cost. The report on Delay
Many projects that reported cost over run either analysis of Narmada Valley dams and canal projects
directly or indirectly (Such as poor assessment of reveals the short bid preparation time lead to a
site conditions due to short bid time) refer to lack number of errors and omission on the part of
of time in preparing realistic estimates. It is found the contractor which they tried to settle through
that many companies do not have a mechanism claims, leading to disputes and schedule over runs.
of more realistically estimating the quantities. A Almost during all the tenders that were invited
recent performance audit of infrastructure by Narmada Valley Development Authority,
contracts revealed that out of 146 contracts, 57 contractors including HCC, L&T etc had
had variation of cost (positive or negative) that requested for time extension to extend submission
ranged between 10 to 54 percent supporting the date which was not entertained.
belief that cost estimates were not realistic. Lack
of time and tight schedules were found to drive From the above discussion, it is clear that there
12 NICMAR-Journal of Construction Management, Vol. XXVII, No. 2&3, April-June & July-Sept. 2012

Table 2 : F Test Using ANNOVA Technique

Group 1: Group 2:
% Time % Cost Group 1: x 2 Group 2: x 2 Details of Analysis for F- Test
Overrun Overrun
62.22 56.80 3871 3226 Sum of Group 1 Scores = 833
58.22 57.50 3390 3306 Sum of Group 2 Scores = 566
62.70 51.40 3931 2642 (x 2 ) for Group 1 = 40269.6512
58.35 46.90 3405 2200 (x 2 ) for Group 2 = 22029.5562
57.73 45.00 3333 2025 n = 18
46.94 37.30 2203 1391 N = 36
53.11 40.90 2821 1673 (x) = 1398.76
44.99 36.00 2024 1296 ((x 2)) = 62299.2074
37.66 36.00 1418 1296 ((x) 2 ) = 1013994.76
31.72 26.00 1006 676 -
39.44 22.30 1556 497 Sum of Squares Total = 7951.1646
37.15 22.40 1380 502 Sum of Squares Between = 1984.999
39.02 17.70 1523 313 Sum of Squares Within = 5966.165
38.80 17.40 1505 303 -
34.13 14.51 1165 211 Degrees of Freedom Between = 1
41.91 12.06 1756 145 Degrees of Freedom Within = 34
48.11 13.45 2315 181 MS Between = 1985
40.84 12.10 1668 146 MS Within = 175.475

is a scope for more realistically estimating both contractor installation policy, equipment/plant
time and cost involved in a project. While the consideration, etc. The manpower quantum is
time over run is attributed to delay in finalization defined based on project duration, client
of tender documents, cost overrun is attributed requirement, labor productivity, trade union
to more variations in quantities estimated and practices, expert requirement & labor department
actually executed. The basis of estimating cost of guidelines. Running cost or time related cost is
each item requires understanding of market options decided based on the previous job actual estimate,
and the new technologies available. The estimation present trend & practices, own resources
of cost also requires careful evaluation by project availability, etc. Due to schedule creep or extended
manager and better coordination with various completion, the time related cost will be increased
stakeholders. There are various components of proportionately. This covers expenses like salary,
cost such as material cost, installation cost, rent, travelling, postage, phone, electricity,
manpower cost, running cost, etc. In practice the stationary, watch & ward, insurance premium,
material quantities are verified with bill of quantities bank guarantee charges, interest, financial cost,
(BOQ) as per the drawings and specifications and increase in equipment hire charges etc. As the
the rates are worked out based on previous data bills of quantities of items are not exactly reflecting
available with the contractor. The installation cost in the construction schedule, estimating the actual
is decided based on methodology of job, job cost is found to be more challenging. While some
duration, job location & size, client requirement, of the items show negative variation, there are
Analysis of Relationship Between Time and Cost Overruns in some Infrastructure Projects 13

Table 3: Sectorwise Total Number Of Projects & Number Of Projects Reported Only Cost Overrun
No. of Range
Total
Original Anticipated Cost Projects Original Anticipated of
Sr. No.
Sector Cost Cost Overrun BOTH Cost Cost time
No. of
` Crore) (`
(` ` Crore) % TOR & (` ` Crore) (`
` Crore) in
Projects
COR months
1 ATOMIC ENERGY 5 25054.29 24123.29 -3.72 0 0.00 0.00 0.00
2 CIVIL AVIATION 31 5982.28 6015.24 0.55 6 300.16 333.12 10.98
3 COAL 129 30419.28 32126.93 5.61 19 6734 8777.73 30.35
4 I & B 1 35 35 0.00 0 0.00 0.00 0.00
5 MINES 1 4091.51 4091.51 0.00 0 0.00 0.00 0.00
6 STEEL 54 47321.43 50947.77 7.66 17 11252.27 15648.98 39.07
7 PETROLEUM 60 121711.09 130859.52 7.52 19 34415.76 48808.29 41.82
8 POWER 88 159797.95 165567.34 3.61 23 32477.98 38427.39 18.32
9 HEALTH & FW 1 71.18 443.15 522.58 1 71.18 443.15 522.58
10 RAILWAYS 257 45722.88 90228.82 97.34 189 34462.45 79028.38 129.32
11 ROAD & 196 54558.11 54874.45 0.58 12 2897.42 3550.58 22.54
HIGHWAYS
12 SHIPPING & 53 14952.89 15304.93 2.35 15 1963.29 2476.07 26.12
PORTS
13 TELE
COMMUNICATION 44 15663.41 15040.02 -3.98 4 1504.71 1775.02 17.96
14 URBAN 28 15659.58 16255.74 3.81 2 8201.67 8811.03 7.43
DEVELOPMENT
15 WATER RESOURCES 1 542.9 1187 118.64 1 542.9 1187 118.64
16 INFORMATION 2 64.9 86.86 33.84 1 20 41.96 109.8
TECHNOLOGY
Total 951 541648.68 607187.57 12.1 309 134843.79 209308.7 55.22

many items that show positive variation throwing CONCLUSION


surprises to project managers as the project Though there is a strong correlation between time
progresses. Documents pertaining to Qualifying and cost over run, the drivers of time and cost
Requirements (QR) should serve as a mechanism overrun are not the same. While the time over
to promote more healthy competition and not run is attributed to scope changes, delay in
as a barrier for contractors to bid. For example, finalization of tender documents and short bid
the Delhi Metro Railway Project phase-I was submission time, lack of commitment of project
completed on schedule and within the budgeted participants, poor coordination etc., cost overrun
is attributed to more variations between quantities
cost. The Design Build Turnkey project involved
estimated and actually executed. The research
international contractors for construction of a total
outcome suggests that Indian construction industry
length of 6,569 m of metro rail and was completed
needs to employ innovative technologies and better
in a 5-year period at a total cost of ` 1,800 crores. contract management strategies to overcome
The success was attributed to transparency in the surprises and challenges. Conventional "Hard bid
tendering system and proper planning. methods" require a serious relook. It is also
14 NICMAR-Journal of Construction Management, Vol. XXVII, No. 2&3, April-June & July-Sept. 2012

Table 4: Sectorwise Total Number Of Projects & Number Of Projects Reported Only Time Overrun
No. of Range
Total
Original Anticipated Cost Projects Original Anticipated of
Sr. No.
Sector Cost Cost Overrun BOTH Cost Cost time
No. of
` Crore) (`
(` ` Crore) % TOR & (` ` Crore) (`
` Crore) in
Projects
COR months
1 ATOMIC ENERGY 5 25054.29 24123.29 -3.72 3 20456 19525 2 to22

2 CIVIL AVIATION 31 5982.28 6015.24 0.55 22 1824.33 1857.29 3 to 50

3 COAL 129 30419.28 32126.93 5.61 55 11438.92 13380.82 4 to 192

4 I & B 1 35 35 0.00 0 0.00 0.00 0

5 MINES 1 4091.51 4091.51 0.00 1 4091.51 4091.51 11

6 STEEL 54 47321.43 50947.77 7.66 37 45474.51 48602.96 2 to 28

7 PETROLEUM 60 121711.09 130859.52 7.52 33 78123.11 87629.27 1 to 74

8 POWER 88 159797.95 165567.34 3.61 33 70245.57 75475.06 1 to 68

9 HEALTH & FW 1 71.18 443.15 522.58 0 0.00 0.00 0

10 RAILWAYS 257 45722.88 90228.82 97.34 67 17338.07 39044.68 8 to 180

11 ROAD &
196 54558.11 54874.45 0.58 159 41422.50 41715.73 1 to 96
HIGHWAYS

12 SHIPPING &
53 14952.89 15304.93 2.35 24 3506.84 3751.32 1 to 94
PORTS

13 TELE
44 15663.41 15040.02 -3.98 27 7255.26 6925.54 1 to 62
COMMUNICATION

14 URBAN
28 15659.58 16255.74 3.81 12 8458.94 9006.02 4 to 71
DEVELOPMNT

15 WATER RESOURCES 1 542.9 1187 118.64 1 542.90 1187 60

16 INFO TECH 2 64.9 86.86 33.84 0 0.00 0.00 0

TOTAL 951 541648.68 607187.57 12.1 474 310178.46 352192.2

recommended that project managers obtain time REFERENCES


and cost variations experienced in projects executed Assaf, S.A. and Hejji, S. A., Causes of delay in
in the past to understand the gap and take large construction projects, International Journal
corrective action. A shift from the current practices of Project Management, 24, pp. 349-357, 2006.
towards electronic tendering process, online
Dave, K., Status of construction law in India
contract bidding document etc can make the
problems and prospects, Proceedings of
bidding process transparent and evaluation more
International conference on Risk Management
realistic in nature. Construction planning,
and Effective Implementation of Construction
scheduling and monitoring require minimum
Projects of IE, Ahmedabad, India,
functional specification and standardization to
pp. 5-14, Oct. 2007.
mitigate risks in projects.
Esther Malini, Build Operate Transfer Municipal
Bridge projects in India, Journal of Management
Engineering, Vol. 15, No. 4, 1999.
Analysis of Relationship Between Time and Cost Overruns in some Infrastructure Projects 15

Table 5 : Sectorwise Total Number Of Projects & Number Of Projects Reported Both
Time And Cost Overrun
No. of Range
Total
Original Anticipated Cost Projects Original Anticipated of
Sr. No.
Sector Cost Cost Overrun BOTH Cost Cost time
No. of
` Crore) (`
(` ` Crore) % TOR & (` ` Crore) (`
` Crore) in
Projects
COR months
1 ATOMIC ENERGY 5 25054.29 24123.29 -3.72 0 0 0 0
2 CIVIL AVIATION 31 5982.28 6015.24 0.55 6 300.16 333.12 5 to 19
3 COAL 129 30419.28 32126.93 5.61 16 6584.19 8592.17 4 to 72
4 I & B 1 35 35 0.00 0 0.00 0.00 0
5 MINES 1 4091.51 4091.51 0.00 0 0.00 0.00 0
6 STEEL 54 47321.43 50947.77 7.66 12 10405.10 14303.92 3 to 28
7 PETROLEUM 60 121711.09 130859.52 7.52 17 27570.76 41195.29 2 to 74
8 POWER 88 159797.95 165567.34 3.61 16 29290.60 34612.15 7 to 47
9 HEALTH & FW 1 71.18 443.15 522.58 0 0.00 0.00 0
10 RAILWAYS 257 45722.88 90228.82 97.34 48 12420.92 34152.86 9 to 180
11 ROAD & 196 54558.11 54874.45 0.58 11 2677.42 3307.47 10 to 85
HIGHWAYS
12 SHIPPING & 53 14952.89 15304.93 2.35 8 1645.04 1896.73 7 to 48
PORTS
13 TELE 44 15663.41 15040.02 -3.98 3 596.41 858.32 19 to 54
COMMUNICATION
14 URBAN 28 15659.58 16255.74 3.81 1 8118.00 8676.00 4
DEVELOPMENT
15 WATER RESOURCES 1 542.9 1187 118.64 1 542.90 1187.00 60
16 INFORMATION 2 64.9 86.86 33.84 0 0.00 0.00 0
TECHNOLOGY
TOTAL 951 541648.68 607187.57 12.1 139 100151.5 149115.03

Iyer, K. C. and Jha ,K.N, Critical factors affecting Okmen O. and Oztas, A., Construction project
cost performance: Evidence from Indian network evaluation with correlated schedule
Construction Projects, International Journal risk analysis model Journal of Construction
of Project Management, Vol. 23, Engineering and Management, Vol. 134,
pp. 283-295, 2005. No. 1, pp. 49-63, 2008.
Iyer, K.C. and Jha, K.N, Critical factors affecting Pilar, M. de la C., et. al, Downside risks in
schedule performance: Evidence from Indian construction projects developed by the civil
construction projects, Journal of Construction Service: The case of Spain, Journal of Construction
Engineering and Management, Engineering and Management, Vol. 132,
Vol. 132, No. 8, pp. 871-880, 2006. No. 8, pp. 844-851, 2006.
Mithun, K., Delay in construction of Dams and Satynarayana, K. N. and Iyer, K. C., Evaluation
Canals by NVDA 2010. Available: http:// of Delays in Indian Construction Contracts,
96.0.26.98/attachments/.../Mithun%20 Journal of The Institution of Engineers (India),
Kartikeyan_IIM_Indore.pdf Vol. 77, pp. 14-22, 1996.
16 NICMAR-Journal of Construction Management, Vol. XXVII, No. 2&3, April-June & July-Sept. 2012

Table 6 : Sectorwise Comparison Of Total Projects & Number Of Projects Reported Only Time, Cost,
Time & Cost Overrun
Total No. of No. of No. of
No. of Projects Projects Projects
Sr. No Sector
Projects Only Only BOTH TOR
COR TOR & COR
1 ATOMIC ENERGY 5 0 3 0
2 CIVIL AVIATION 31 6 22 6
3 COAL 129 19 55 16
4 I&B 1 0 0 0
5 MINES 1 0 1 0
6 STEEL 54 17 37 12
7 PETROLEUM 60 19 33 17
8 POWER 88 23 33 16
9 HEALTH & FW 1 1 0 0
10 RAILWAYS 257 189 67 48
11 ROAD TRANSPORT & HIGHWAYS 196 12 159 11
12 SHIPPING & PORTS 53 15 24 8
13 TELECOMMUNICATION 44 4 27 3
14 URBAN DEVELOPMENT 28 2 12 1
15 WATER RESOURCES 1 1 1 1
16 INFORMATION TECHNOLOGY 2 1 0 0
Total 951 309 474 139

Singh, D. and Tiong, R.L.K., Contractor selection Vaziri, K. et.al, Project planning for construction
criteria: Investigation of opinions of Singapore under uncertainty with limited resources,
construction practitioners, Journal of Construction Journal of Construction Engineering and Management,
Engineering and Management, Vol. 132, No. Vol. 133, No. 4, pp. 268-275, 2007.
9, pp. 998-1006, 2006. Assaf, S.A. and Hejji, S. A., Causes of delay in
Abi-Karam, T., Editors Letter: The Professional large construction projects, International Journal
Services Race: Design/Build Reality Journal of Project Management, 24, pp. 349-357,
of Management in Engineering, Vol. 14, 2006.Engineering and Management,
No. 6, p. 3, 1998. Vol. 132, No. 9, pp. 998-1006, 2006.
Sawhney, Anil et.al, Latent Variables and Their
Impact on Time Performance of Indian
Construction Projects, PMI Conference,
Dec. 9-10, India. 2011.
Quarterly Project Implementation Status Report
on Central Sector Projects for the quarter
June, 2009 issued by the Ministry of statistics
& program implementation, Government
of India. Available : www.mospi.gov.in (Accessed
on 14 th Feb. 2012)

Importance of Cash Flow Hedging in Projects from Corporate Sustainability 17

Importance of Cash Flow Hedging in Projects


from Corporate Sustainability
Hiren Maniar*

Abstract : A cash flow hedge protects from the variability of cash flow of the hedged
item, variables such as a particular risk associated with an asset or liability
(such as interest payments on a variable rate debt) or the effects of profit
or loss, by offsetting such variability with the cash flow of the hedging
instrument. This paper studies the scenario of unrealized cash flow hedge
gains/losses for future profitability and project returns, which ultimately
decides in a longer run corporate sustainability of any project driven
company. An unrealized gain on a cash flow hedge suggests that the price
of the underlying hedged item (i.e. commodity price, foreign currency
exchange rate or interest rate) moved in a direction that negatively affects
the project firm. Based on this inverse relation, it is found that unrealized
cash flow hedge gains/losses are negatively associated with future gross
margin. This association is weaker for project firms that have the ability
to pass input price changes through to customers. Finally, it has been
observed that project companies do not immediately price the information
conveyed by cash flow hedges. Instead, project companies appear surprised
by future realizations of gross margin, consistent with the view that a
lack of transparent disclosure on future hedged transactions leads to a
delay in pricing.

Keywords : Cash flow, Hedging, Cash, Corporate Sustainability, Credit Line, Cash
Flow Risk, Project Companies

JEL Classification : G30; G31; G32

INTRODUCTAION purchases. This financial strategy uses derivative


A cash hedge is a type of investment strategy set instruments such as call options or put options
up to protect an individual against the risk of to help limit the individual's exposure to such risks.
variable cash flow of a specific hedged item. Such Specific information, such as the strategy and risk
a risk may be caused by particular assets or liabilities of the original hedge, must be documented before
that generate revenue differently than expected, a cash flow hedge can be properly established;
and are possibly reducing expected profits or in most cases, a financial advisor can help investors
increasing losses. For example, a cash flow hedge create financial protection for hedged items.
could protect against increases in the repayment A cash-flow hedge protects from the variability
installments of a variable rate loan, increases in of cash flow of the hedged item, variables such
the exchange rate of a foreign currency in which as a particular risk associated with an asset or liability
the individual expects to make a future transaction, (such as interest payments on a variable rate debt)
or increases in the prices of planned inventory or the effects of profit or loss, by offsetting such
*Corporate Trainer - Finance, L & T Institute of Project Management, Vadodara 390019, Gujarat, India.
Email. : hmaniar@lntipm.org
18 NICMAR-Journal of Construction Management, Vol. XXVII, No. 2&3, April-June & July-Sept. 2012

variability with the cash flow of the hedging forecasting is a recurring priority and pain point
instrument. In short cash flow hedge is a hedge for corporate treasurers. What is it that makes
of an upcoming, forecasted event. To qualify for this issue a constant 'top of mind' topic for
cash flow hedge treatment, a key requirement treasurers? So much is written and said about the
is that exposure involves the risk of an uncertain topic of cash flow forecasting and hedging that
(i.e., variable) cash flow. it can get confusing. Many companies thought
A cash flow hedge is a hedge of the exposure to that it is the single most important task a cash
the variability of cash flow that manager does. But this is not the case. The
consequences of getting cash forecasting wrong
1. Is attributable to a particular risk associated are all too clear. The project can lose money when
with a recognized asset or liability, such as project borrows more than what is actually needed
all or some future interest payments on variable or invest money project managers thought they
rate debt or a highly probable forecast transaction had but don't, due to poor forecasting. And therein
and lies the problem and the reason that some
2. Could affect profit or loss treasurers don't bother forecasting at all. So it
A cash flow hedge is a hedging relationship where seems there are a few issues to focus on here:
the variability of the hedged item's cash flows is z Getting the Project companies to forecast
offset by the cash flows of the hedging instrument. cash f low regularly.
Key aspects are:
z Getting the Project companies to forecast
z Hedged item may be a forecasted transaction cash f low accurately.
with no contracted future price (i.e., not a z Having the ability to control how forecasting
firm commit.) works.
z Effective portion of derivative's gain or loss A logical step by step approach may be what is
reported in firms' financial statements needed. Treasury, in theory, should have
z Earnings recognition matches hedged transaction knowledge of at least some of the line items that
z Ineffective gain or loss recorded in earnings go to make up a good forecast. Following point
The uncertainty of cash flows and the risk of should be considered for effective forecasting of
adverse cash flow shocks are central concerns in cash flow.
Projects, and are taken seriously by both project z Cash flows generated from financial transactions
managers and project companies. Theory suggests (e.g. foreign exchange (FX), debt and investment).
that corporate risk management in projects can z Possible mergers and acquisitions (M&A)
effectively mitigate cash f low risks. Yet, the or divestures.
empirical literature offers no conclusive evidence
z Treasury related transfers (e.g. tax and cash
on the overall value of risk management and cash
pooling).
flow hedging. Movements in external factors such
z Human resource transfers (e.g. tax and payroll).
as exchange rates, interest rates and commodity
prices can disrupt a project's internally generated z Bank fees.
cash flows. z Financial institution debt and credit line
issuance costs and fees.
Hence for good project cash flow hedging, one
needs to forecast cash flow in highly accurate z Accounts payable (A/P) accounts receivable
manner. Judging by industry surveys, cash flow (A/R) and forecast sales.
Importance of Cash Flow Hedging in Projects from Corporate Sustainability 19

z Summary cash flows generated from quantitative by projects for company) and EBDITA (Gross Profit
modeling. Margin of projects for the company). However,
Technology can play a key role in the success or same also decides the corporate sustainability of
otherwise of cash flow forecasting from a number project companies in managing cash flow hedging
of perspectives including the gathering of cash for commodity, foreign exchange, interest rate
forecast data and the analysis of the data. Treasuries and credit flows.
who are successful in forecasting agree on one The majority of the project companies do cash
thing that project managers have to make it easy flow hedges related to exposure to variability in
for the suppliers (subsidiaries or business units) project's future payments and receipts on forecast
of the forecast to provide the forecast. But this transactions and on recognised financial assets and
is only one aspect of the issue. Project managers financial liabilities of projects. The project company
also need to compare the forecast with the actual hedges its international project net investments
for accuracy. It is this area that some project in foreign operations with currency borrowings
companies find most difficult and possibly why and forward foreign exchange contracts.
they give up or don't bother in the first place.
It is found that cash flow hedging reduces the
If group treasury does not have the power to
firm's precautionary demand for cash and allows
improve the accuracy then it can be a meaningless
it to rely relatively more on bank for lines of credit
task.
for liquidity provision. Furthermore, firm is able
RELEVANCE OF CASH FLOW HEDGING to identify a significant positive value effect of
IN PROJECTS FROM CORPORATE cash flow hedging as a result of facilitating a more
SUSTAINABILITY POINT OF VIEW cost efficient liquidity policy. Same is a driving
What are the financial consequences and value factor in today's economic turmoil era, where many
implications of corporate hedging? Clearly, the cash strapped companies are facing challenges for
uncertainty of cash flows and the risk of adverse managing of their cash flow.
cash flow shocks are central concerns in corporate
In the last couple of years (based on result analysis
finance, shareholders and managers take them
of several project companies in India), Indian
seriously. In today's economic turmoil
project companies incurred a huge foreign
environment, corporate sustainability for
exchange loss in running their project business;
companies is a difficult task due to volatility in
some envisaged the need of effective cash flow
commodity, equity, interest rate, inflation and
hedging of foreign exchange and other financial
foreign exchange markets. As per corporate
resources for corporate sustainability of project
sustainability practices, project companies are using
companies. This research article will give an idea
derivative instruments as hedging tools to manage
about why cash flow hedging is required for the
its balance sheet against impending risk due to
projects and how cash flow hedging can play an
volatility in commodity, foreign exchange, interest
important role in terms of corporate sustainability
rate and credit flows. Project companies enter into
for any project driven organisation.
fair value hedges, cash flow hedges and hedges
of net investments in foreign operations pertaining ROLE OF CASH FLOW HEDGING IN
to various domestic as well as international projects. PROJECTS
This really indicates in the economic performance The project cash flow hedge protects an individual
of various projects of project companies in terms from the risks of particular assets or liabilities
of Economic Value Generation (Revenue generated generating cash flows different from those he or
20 NICMAR-Journal of Construction Management, Vol. XXVII, No. 2&3, April-June & July-Sept. 2012

she expected, possibly reducing expected profits the firm's financial condition are left to make their
or increasing losses. There are various types of own judgments regarding the extent to which the
risk a project faces during its life cycle like currency reported gains or losses will reverse in the future.
risk, commodity risk, price risk, etc. Currency risks If the hedged item is denominated in a foreign
include those associated with a future transaction currency, an entity may designate any of the
in a foreign currency or a debt denominated in following types of hedges of foreign currency
a foreign currency. Price risks refer to the possibility exposure:
of the purchase price of non-financial goods
(a) A fair value hedge of an unrecognized firm
increasing or the sale price of non-financial goods
commitment or a recognized asset or liability
decreasing. It can also protect against increases
(including an available-for-sale security)
in the repayment installments of a variable rate
(b) A cash flow hedge of any of the following:
loan, increases in the exchange rate of a foreign
currency in which the individual expects to make 1. A forecasted transaction
a future transaction or increases in the prices of 2 . An unrecognized firm commitment
inventory to purchase. A cash flow hedge uses 3 . The forecasted functional currency equivalent
derivative instruments such as call options or put cash flows associated with a recognized
options to limit the individual's exposure to such asset or liability
risks. 4 . A forecasted intra-entity transaction
Cash flow effects of financial instruments for (c) A hedge of a net investment in a foreign
projects could be due to price changes, benchmark operation
interest rate changes, changes in the credit spread
LITERATURE REVIEW
between the interest rate of the hedged item and
There is a large literature which has studied cash
the benchmark interest rate, and defaults or
f low hedging in terms corporate of risk
changes in creditworthiness. In a cash flow hedge,
derivatives are used to offset the variability in cash management. Stulz (1984), Smith and Stulz (1985),
flows from a forecasted transaction for which there Stulz (1990), Bessembinder (1991), and Froot et.
is currently no legal commitment and which is al (1993) find that hedging increases firm value
too uncertain to be documented. Management in the presence of market imperfections such as
anticipates that a transaction is likely to occur in costs of external financing and a progressive tax
the future and hedges the associated price risk rate schedule. Given these frictions, the optimal
by taking a position in the derivatives market. hedging strategies are analyzed. Such studies of
The price of the derivative fluctuates during the optimal hedging strategies posit that the firm's
period interim to taking the derivative position cash flows are a deterministic function of some
and its settlement. common factors and the fluctuations in cash flow
come solely from the fluctuations of the factors.
The gains or losses arising from price fluctuations
In our framework, a firm's cash flow is uncertain
are reported in the earnings statement (or in "other
conditional on the common factor and it depends
comprehensive income"). However, the forecasted
on whether or not the firm has won the auction.
transaction, that is the basis for the hedge, is not
recognized until its realization in the future - hence, The relationship between hedging and project
during the interim period, there is no recognition market competition has been analyzed by Adam,
of an offset to the reported gains or losses on Dasgupta and Titman (2005). They characterize
derivatives. This implies that outsiders assessing Cournot equilibrium in which project firms may
Importance of Cash Flow Hedging in Projects from Corporate Sustainability 21

hedge input costs. They find that hedging strategy Eso and White (2003) examine the effect of
is jointly determined in equilibrium with the idiosyncratic risk on risk averse bidders. They find
project market competition and that there can that idiosyncratic risk can increase agents' expected
be asymmetric equilibrium. Mello and Ruckes utility. Rhodes-Kropf and Viswanathan (2005) also
(2005) also consider firms with financial consider bidders who are financially constrained.
constraints who compete in project markets. They In their framework, bidders with differing cash
find that even though reducing cash flow volatility positions raise money which may be conditional
may be desirable, project firms may choose not on the ex post value of the firm. They show that
to hedge for competitive reasons. In this research, capital markets may render the auction inefficient.
we find the reverse, that firms in active competition By contrast to their work, as we are interested
will always hedge and ex post those who lose the in how competition affects the investment
competition have too much exposure to the decisions of firms, was assume that the cost of
common factor. Loss (2002) demonstrates that accessing the financial market either through
a firm in competition chooses to hedge strategically, hedging or raising extra capital does not depend
in particular, hedging is valuable if investments on the bid or private information of the bidders.
are strategic substitute (as opposed to strategic The rest of the paper is organized as follows. Process
complements). Conceptually, this research differs of cash flow hedging in projects followed by the
from these papers in one important way. This research model to calculate Net Currency Project
research considers competition in indivisible Cash Flow for Hedging, and we also derive
projects. This means that only one firm will win." Sensitivity Analysis for Project Cash Flow Hedging.
The other firms will necessarily lose," which is the In the last section of how to hedge project cash
source of business risk. flow, we assessed the impact of changed debt
currency on Project Cash Flow.
A literature has considered the interaction between
hedging and bidding. Eaker and Grant (1985) PROCESS OF CASH FLOW HEDGING IN
model a project firm with an exogenous probability PROJECTS
of winning a project whose payoff is exposed to The value of the project has a private value
foreign exchange rate risk. They study the optimal component and a common value component. Both
exposure to a forward contract on the exchange are random, and therefore winning generates
rate. In a similar framework, Lien and Wong uncertain internal capital. As each project firm
(2004) incorporate a single bidder facing an faces financial constraints, and hence invests
exogenous function that links bids to winning internal capital in an ongoing growth opportunity,
probabilities. We extend this literature, by rendering all firms behave as if they are risk averse in the
the bids and hedging endogenous. Therefore, we auction stage. They thus have an incentive to hedge
can consider the interaction between financial cash flow risk. The random common value
markets on project firms bidding behavior. component of the project is correlated with
financial instruments which they can use to hedge
This paper also contributes to the auction literature it. However, by assumption, contracts are not
through the observation that, through financial written on who wins the auction, and markets
markets, agents may affect their valuations. The are necessarily incomplete so hedging with financial
incentive to hedge in this model arises because instruments cannot eliminate all cash flow
firms face a convex cost of capital. Thus, the model uncertainty. Thus, while all firms may find it
resembles auction models with risk averse bidders. optimal to hedge before the auction, all losers
22 NICMAR-Journal of Construction Management, Vol. XXVII, No. 2&3, April-June & July-Sept. 2012

in the auction find themselves exposed to the the seller also faces financing constraints and
common risk factor after the auction. This effect therefore does not provide the hedge or finds it
may be termed as "business risk". optimal for bidders to retain some risk.
The incompleteness in projects requires that a RESEARCH METHODOLOGY OF PROJECT
project firm hedges before the winner of the project CASH FLOW HEDGING CALCULATION
is announced. This timing friction is called "the In order to calculate project cash flow exposure
bid to award period." It arises from two sources. and hedging requirements, we need to construct
First, bids for complicated projects can take a long a research model for calculating project cash flow
time to evaluate because factors other than price exposure in multiple currencies (depends on
such as political considerations, a bidder's technical number of currencies being used in any project
credentials, and the payment schedule are relevant. as per the project bid document) for three crucial
For large and complex projects, a two-stage bidding stages of project like pre award stage, post award
process may even be employed where bidders are stage and execution stage. After calculating net
first invited to submit technical offers without
project cash flow per currency for three stages,
prices, which are then evaluated to set an acceptable
we need to make sensitivity analysis (main purpose
technical standard for all bidders, and then bidders
of sensitivity analysis is to check impact of exchange
are asked to resubmit bids with prices (Asian
rate movements on cash flow valuation to
Development Bank, April 2006). Second, the bid
understand hedging requirements) for project cash
to award period also includes the time in which
flow hedging in terms of pre-interest cash flow
the auction is anticipated but has not yet taken
per currency and consider project net average
place.
interest expense (or income) per currency to get
It has been found that this friction and the existence a final net cash flow per currency. Then add on
of financial instruments make firms compete more a simple sensitivity analysis to show the effects
aggressively because by entering into a hedging of exchange rate movements.
position, bidders run the risk of being over hedged
Finally to achieve cash flow hedging aim of
if they lose. It has been observed that the spillover
minimise net foreign currency cash flow and
between projects can affect firms' investment in
maximise net base currency (local currency) cash
projects that they do not compete over. The
flow, we need to change the currency of the debt
existence of hedging instruments increases the
and hence the interest expense to local currency.
variability of industry wide investment and returns
Main purpose of this research exercise is to calculate
of the firm because even though ex ante firms
interest rate impact on overall project cash flow
are identical, their hedging positions vary and thus
if we charge the debt currency. Crux of this research
make them all different ex post. It has been found
exercise is to compare project cash flow fluctuation
that even though the hedging instruments make based on currency fluctuation against change in
bidding more aggressive and thus increase seller's debt currency. Let us understand utility of above
profit, business risk reduces it. The seller suffers research model given in below sections.
a loss because bidders have to make hedging
decisions prior to knowing the auction outcome, HOW TO CALCULATE NET CURRENCY
and the loss increases with bid-to-award length. PROJECT CASH FLOW FOR HEDGING?
Thus, it is to the seller's advantage to accelerate In order to calculate net currency project cash flow
the evaluation process. This suggests that the for hedging, first of all draw up one Table 1 showing
framework is most appropriate in markets in which project net cash flows per annum in various key
Importance of Cash Flow Hedging in Projects from Corporate Sustainability 23

operating currencies (for three crucial stages of cash flow estimation, here the project cash flow
project: Pre Award stage, Post Award stage and has been split between the three currencies. There
Execution stage) before interest payments but after will undoubtedly be required some numbers that
tax. To get better project cash flow picture some cannot be taken straight from the management
care has to be taken in collating these numbers. or statutory accounts, but generally some informed
Sometimes there are significant foreign currency and reasoned judgments will give sufficient accuracy.
cash flows taking place in US $, , etc., which Table 2 : Net Project Cash Flow
depend on project location (i.e. country) and in Per Currency
which currency cash flow is taking place. Also cash
Project Cash Flow Factors Average of Three Stages
tax is often not the same as the tax shown in the (All figures in millions) INR US $ Total in INR
statutory accounts. Foreign currency debt
Net Cash Flow Pre Interest
repayments or planned material acquisitions or
Interest
disposals must also be included in an appropriate Net Cash Flow
manner. Table 1 indicates the format to be used
while calculating net currency (net cash flow being The next thing to do is to average the project
calculated after considering three currencies cash flow numbers per currency across the three
(Indian Rupees INR, US Dollar $, Euro , being stages of project. If there is a trend over time then
widely used by Indian project companies). some weighting of the average is appropriate.
Table 1: Estimated Net Cash Flow Per Annum During Various Stages Of Project
(In Multiple Currencies)

* Total can be calculated after converting foreign currency in INR based on respective date conversion rates.

To calculate the same; some forward looking Having got an average for the pre-interest cash
numbers are required, so some judgment is needed flow per currency, next consider project net average
(and no reason to limit up to three stages of project. interest expense (or income) per currency, to give
For minute prediction of project net cash flow, final net cash flow per currency. Then add on
further split in multiple stages as per WBS (Work a simple sensitivity analysis to show the effects
Breakdown Structure) of project is possible). To of exchange rate movements as shown in
illustrate the importance of project cash flow Table 3. To understand sensitivity analysis for project
hedging and for broad-brush accuracy of project cash flow hedging let us consider following case.
24 NICMAR-Journal of Construction Management, Vol. XXVII, No. 2&3, April-June & July-Sept. 2012

PROJECT CASE FOR CALCULATING Corporate treasury will mark down the cash flow
SENSITIVITY ANALYSIS FOR PROJECT for the uncertainty, and of course if INR does
CASH FLOW HEDGING
appreciate, then treasury will mark down the cash
In order to understand sensitivity analysis for flow for the fact. Now the question is how can
project cash flow hedging, assume one project project company hedge against these potentially
which has average net cash flow pre interest (for substantial value impacts?
three crucial stages of project: Pre Award stage,
Post Award stage and Execution stage) in three HOW TO HEDGE PROJECT CASH FLOW?
different currencies (INR, $ and which includes Main objective behind this exercise is to minimise
local currency (INR)) are 30,10 and 7 million net foreign currency cash flow and maximise net
respectively. Borrowing cost (i.e. Interest base currency cash flow. The less foreign currency
applicable) for raising fund in $ and are 3 and cash flow project has as a part of the total cash
2 million respectively. After plugging above values f low, the less the impact of exchange rate
in Table 3 of sensitivity analysis for project cash movements on value. The answer in most real-
flow hedging, we can calculate net cash flow in life projects is to look at the only thing that project
INR which is coming to 42 million. In this scenario has to play with i.e. the currency of the interest
if we assume INR depreciation & appreciation expense (or income) on debt (or cash).
by 5%, then we can find that net cash flow is
fluctuating between 40.5 to 43.5 million for 42 PROJECT CASE FOR CALCULATING
million base figures with a fluctuation rate of 3.57%. IMPACT OF CHANGED DEBT CURRENCY
ON PROJECT CASH FLOW
Table 3 : Sensitivity Analysis For
To understand impact of change in debt currency
Project Cash Flow Hedging
on project cash flow let us assume following scenario.
Project Cash Flow Factors Average of Three Stages In the continuation of above project cash flow
(All figures in millions) INR US $ Total in INR
Net Cash Flow Pre Interest 30 10 7 47 example (as mentioned above for calculating
Interest -3 -2 -5 Sensitivity Analysis for Project Cash Flow Hedging),
Net Cash Flow 30 7 5 42 look at what happens if we change the currency
INR Depreciate by 5 % 31.5 7 5 43 .5 of the debt from foreign currencies $ and to
INR Appreciate by 5 % 28.5 7 5 40 .5
local currency INR and hence the interest expense
Fluctuation *+/-3. 57%
to INR. If we assume for the sake of simplicity
Now to understand foreign exchange fluctuation roughly similar interest rate expense (i.e. 5 million
and its impact on cash flow of project and what as mentioned in Table 3) as indicated in Table 4.
if projections, there is need to calculate the current
Table 4 : Impact Of Changed Debt Currency On
value of the project based on its potential future Project Cash Flow
performance and especially its potential future net
Project Cash Flow Factors Average of Three Stages
cash flows. In this case, suppose if both foreign
(All figures in millions) INR US $ Total in INR
currencies $ and appreciates against local currency Net Cash Flow Pre Interest 30 10 7 47
INR by 5 % then the project is going to be worth Interest -5 -5
some 3.57 % less to its company and vice-versa Net Cash Flow 25 10 7 42
if both currencies $ and depreciates against INR INR Depreciate by 5 % 26.25 10 7 43 .25
by 5 % then the project is going to be worth some INR Appreciate by 5 % 23.75 10 7 40 .75
Fluctuation *+/-2. 98 %
3.57 % more to its company.
In this case, project company treasury is going to If we go ahead with similar depreciation and
see that this exposure (i.e. 42 million) is unhedged. appreciation of INR by 5% then we can find that
Importance of Cash Flow Hedging in Projects from Corporate Sustainability 25

the net cash flow is fluctuating between 40.75 cash flow as they bid. Because the bidders' hedging
to 43.25 million for 42 million base figures with decisions are made prior to the award
a fluctuation rate of 2.98%. Hence as we can announcement, they face a basic tradeoff between
observed in Table 3 & 4 that the sensitivity (after maximally hedging the cash flow in the event of
comparing Table-3 & 4) has been come down by winning the auction and not hedging any amount
0.59% (3.57% - 2.98%) between both the scenario. in the case of losing. Their optimal hedging strategy
This will reduce the current value mark-down due depends on their winning probability. Indeed,
to uncertainty, and will reduce the actual value research has established that the larger the bidder's
mark-down if an adverse change actually occurs winning probability, the more complete the
a significant enhancement to company valuation. hedging will be. The increase in hedging coverage
However, in real-life scenario, situations are rarely depends on how sensitive the firm's overall payoffs
quite simple like above. Usually, company treasury are to changes in internal capital. For Project cash
cell will ask to undertake currency exposure reviews flow hedging relationships, the initial and ongoing
often by FDs and treasurers because they suspect prospective effectiveness is assessed by comparing
that the company is misaligned but they haven't movements in the fair value of the expected highly
quite put their finger on the problem, or they probable forecast interest cash flows with
want an independent recommendation to support movements in the fair value of the expected
a proposal to the management. Often project changes in cash flows from the hedging interest
companies do have significant unhedged net rate swap or by comparing the respective changes
currency cash flow exposure, and they also have in the price value of a basis point.
the means of reducing the exposure, sometimes
quite dramatically. Further, the fact that project firms can hedge makes
them bid more aggressively. After a project firm
CONCLUSION commits to a hedging position, it has more to
There can be no doubt that, alongside the lose because of the business risk that it faces: it
traditional Profit & Loss account and balance sheet is over hedged if it does not win the project. Indeed,
views of currency exposure, treasurers should also the hedging position for a project firm with a large
obtain a net currency cash flow exposure analysis. probability of winning can be large enough such
Suggested outcome of this research can strongly that the bid will even exceed that when contracts
influence aspects of the project treasurer's currency can be written contingent on winning the auction
hedging activity, and in particular lead to a change such that the variation in cash flow can be
in the currency of the project's debt or cash. Failure completely removed. As a result, hedging
to include the results of a net currency cash flow instruments increase a seller's profit.
exposure analysis in currency exposure Overall, this research paper presents a framework
management decisions means that exposure of in which the effect of a financing friction is
the project company's value to currency movements magnified in project business due to competition.
has been overlooked, and its management may All Project firms hedge as they anticipate future
well not be optimized. cash flow constraints. Due to competition, project
This research has exhibited cash flow hedging firms bid away benefits to hedging and in aggregate
strategies during the three crucial stages (Pre-Award, exacerbate the project industry's constraints. Last
Post-Award and Execution) of project. Project but not least effective cash flow hedging strategies
bidders know they will face a convex cost of capital will decide any project company's corporate
in the future, and have an incentive to hedge the sustainability in a longer run of the firm.
26 NICMAR-Journal of Construction Management, Vol. XXVII, No. 2&3, April-June & July-Sept. 2012

REFERENCES Mello, A., and J. Parsons, Hedging and liquidity,


Adam, Tim, Sudipto, Dasgupta, and Sheridan, Review of Financial Studies, Vol. 13, pp. 127-
Titman, Financial constraints, competition, 153, 2000.
and hedging in industry equilibrium, Journal Mian, Shehzad, Evidence on corporate hedging
of Finance, pp. 2445-2473, 2007. policies, Journal of Financial and Quantitative
Allayannis, G. and J. Weston, The use of foreign Analysis, Vol. 31, pp. 419-439, 1996.
currency derivatives and firm market value, Michael, Turner-Samuels, Currency hedging
Review of Financial Studies, Vol. 14, pp. 243- protecting value not just numbers, Treasury
276, 2001. Management International, 2001.
Almeida, Heitor, Murillo, Campello, and Michael, Nance, Deana, Clifford Smith, and Charles Smithson,
Weisbach, The cash flow sensitivity of cash, On the determinants of corporate hedging,
Journal of Finance, Vol. 59, pp. 1777-1804, Journal of Finance, Vol. 48, pp. 267-284,
2004. 1993.
Froot, K., David, S., and Jeremy, S., Risk Stulz, R. M., Optimal Hedging Policies, Journal
management: Coordinating corporate of Financial and Quantitative Analysis, pp.
investments and financing policies, Journal 127-140, June 1984.
of Finance, Vol. 48, pp. 1629-1658, 1993.
Stulz, R.M., Managerial Discretion and Optimal
Gilchrist, Simon, and Charles Himmelberg, Evidence Hedging Policies, Journal of Financial Economics,
on the role of cash f low for investment, Vol. 26, No. 1, pp. 3-27, 1990
Journal of Monetary Economics, Vol. 36, pp.
Smith, S. M. and R. M. Stulz, The Determinants
541-572, 1995.
of Firms Hedging Policies, Journal of Financial
Kaplan, Steven, and Luigi, Zingales, Do investment-
and Quantitative Analysis, pp. 391-405, Dec.
cash flow sensitivities provide useful measures
1985.
of financing constraints, Quarterly Journal
Whited, Toni, and Guojun Wu, Financial constraints
of Economics, Vol. 112, pp. 169-215, 1997.
risk, Review of Financial Studies, Vol. 19,
Lidbark, Joacim, Hedging Bid-to-Award Risk,
pp. 531-559, 2006.
Bank of America Global Corporate and
Investment Bank, Monograph, 2003.

Potrebbero piacerti anche