CT Services Daily Operations Sheet

Date: 10-Feb-14
Activity Y/N
Well
Y
Number: RU-413z Stem 1 Done Well Start Date: 5-Feb-14
Company:Oilserv Tub. Size: 3 1/2'' Recorded on # of Personnel on loc: 9
Y
Job type:N2 lift Packer Y/N? N Orion? NPT: 0
Witness:Ali Abdul Khaliq Min Rest.: 2.72" Well Head Xover: 3 1/8 5k R-35
Y
OS Supervisor Naeem Bhatti Recorded in
TD (MVD): 3470m Real-time? CT Unit No.: Team-02
Depth Speed WHP Circ P Weight Pump Rate Tot Volume
TIME ACTIVITY
(m) (m/min) (psi) (psi) (lbs) (bpm/scfm) (bbl/gals)
5:30 Crew left from OS base to location RU-413z.
6:30 PA @ DS and crew arrived at location stand by for PTW.
6:45 PTW signed with # SDS-HWN-0003017 HITRA Ref: # RA0024906 and stand by for gas tester.
7:00 Gas tester arrived at location and perform gas test.
7:15 Hold safety meeting with crew on location and Roo witness.
7:30 Start rig up IH on well head.
7:45 Finished rig up IH on well head.
7:50 Set PRV to make pressure test 3000 psi.
8:00 Flush all service line CT,Stripper,Gate valve,Swab valve,BOP,Choke and flare line with fresh water.
8:05 Start cool down Ln2. 200 gal
8:10 Low P.Test to service line CT,Stripper,Gate valve,Swab valve,BOP,Choke 300 psi for 5/min. 300 300
8:15 Test ok holding accepted by Roo witness.
8:20 High P.Test to service line CT,Stripper,Gate valve,Swab valve,BOP,Choke 2700 psi for 10/min. 2700 2700
8:30 Test ok holding accepted by Roo witness.
8:35 Record shut in pressure Ann,A=204 psi.Ann,B=0 psi.Ann,C=0 psi.Tbg=200 psi.
8:40 Start displace CT by N2 @ 350/scfm. 0 0 0 1165 0 350/scfm
9:15 Stop displace CT by N2 while N2 @ surface. 0 0 0 0 0 0 12250
9:20 Open well and start CT to RIH(RTKB @ 6.75m) while take return via TBG annulus close choke full open. 6.75 6 116 0 0 0
9:28 CT @ 100m while start pumping N2 @ rate 300/scfm. 100 15 5 654 0 300/scfm
10:15 CT @ 1000m pull test while Continue pumping N2 @ rate 300/scfm. 1000 20 50 950 3300 300/scfm 14100
10:50 CT stop @ 1777m no return at surface while increased N2 rate to 500/scfm. 1777 0 6 1300 6220 500/scfm 24600
11:10 Continue CT RIH water at surface while pumping N2 @ rate 500/scfm. 1777 23 181 1500 4764 500/scfm 34600
11:25 CT @ 2000m pull test and stop CT while continue pumping N2 @ rate 500/scfm. 2000 0 49 1665 9020 500/scfm 42100
11:35 Cotninue CT RIH while water at surface pumping N2 @ rate 500/scfm. 2000 22 230 1700 7400 500/scfm 47100
12:40 CT @ 3000m pull test and continue N2 pumping @ rate 500/scfm. 3000 15 275 2628 11676 500/scfm 79600
12:45 CT @ 3107m at TBG shoe while close Tbg and open annulus choke full open N2 @ same rate 500/scfm. 3107 20 240 2741 7452 500/scfm 82100
12:55 CT stop @ 3276m top off perfration while continue pumping N2 @ rate 500/scfm. 3276 0 566 2924 14692 500/scfm 87100
14:15 Start CT POOH while continue pumping N2 rate 500/scfm. 3276 10 630 2790 15000 500/scfm 127100
14:30 CT @ 3107m in Tbg while close annulus and open TBG continue pumping N2 @ rate 500/scfm. 3107 20 820 2615 15000 500/scfm 134600
14:45 CT @ 2763m while decreased N2 @ rate 300/scfm. 2763 25 365 2513 11340 300/scfm 142100
15:55 CT @ 700m while stop pumping N2. 700 25 250 940 3000 0 163100
16:25 CT @ surface close master valve secure well and flush all line up to choke with fresh water.
16:40 Start rig down IH from well head.
16:55 Finished rig down IH from well head secure well and equipment done house keeping.
17:00 Crew let from location to OS base.
18:15 Crew arrived at OS base.

ANNULUS AVAILABLE? y/n


FUEL LEVELS ARE If unavailable, state reason
A
FULL?: Y/N Y
B Y
C Y
Fresh Water on Y Brine 1.1 Nitrogen 2550 gal Note: All depths are referenced to RTKB
Location 30 bbl Other chemical Diesel
COMMENTS CHEMICALS USED UNITS ON LOC.
NAME QTY UNIT 1.5'' CTU
LN2 0 gal Twin Pump Unit
TOTAL 0 gal Safety Caravan
Lab Container
FLUID/ Abrasive
Corrosive PUMPED - TOTALS CT STRING NUMBER 394210000 WC
(bbls) Job Total OD " 1.5 N2 Unit
Brine 1.03 SG Job Total LENGTH m 4568.4 Crane 50 Ton + Operator
Brine 1.1 SG Job Total MAX FATIGUE % 15% PSD/Team + Static/Team
WATER today (bbl) 5 bbl Job Total 35 bbl AT DEPTH 4056..9m Flow back Package, Choke .M
Nitrogen today Gal 2083 gal Job Total 2083 gal Generator
Service Pick up

ASSIGNED
PERSONNEL ASSIGNED ROLE PERSONNEL ROLE
Naeem Bhatti Job Sup Driver
Mazin Najem CT SUP
Ahmed Ramadan N2 Operator BOTTOM HOLE ASSEMBLY
Fadil Munther Eng Name OD" Ball size Length Inch
Bassam Abdali Driver Internal Dimple Connector 1.7'' 4.3"
Hareth Saad EO MHA 1.7'' 26"
Ezzat Mustafa EO Straight bar 1.7'' 35.8"
Ihsan jassim Crane Operator Full pore nozzle for CMT 1.7" 6"
Murtada Hadi Lab Tech Total 72.1"

Naeem Bhatti
Ali Abdul Khaliq OS - NAME OF SUPERVISOR