Sei sulla pagina 1di 27

IS 4682 (Part 1) : 1994

(Reaffirmed 1999)
Edition 2.1
(1996-08)

Indian Standard
CODE OF PRACTICE FOR LINING OF
VESSELS AND EQUIPMENT FOR
CHEMICAL PROCESSES
PART 1 RUBBER LINING

( First Revision )
(Incorporating Amendment No. 1)

UDC 66.023.3 : 621.642 : 678.4 : 006.76

BIS 2002

BUREAU OF INDIAN STANDARDS


MANAK BHAVAN , 9 BAHADUR SHAH ZAFAR MARG
NEW DELHI 110002

Price Group 9
Chemical Engineering Plants and Related Equipment Sectional Committee, HMD 17

CONTENTS
SECTION 1 GENERAL
PAGE
1 SCOPE 1
2 REFERENCES 1
3 TERMINOLOGY 1
4 EXCHANGE OF INFORMATION 1
5 COMPLIANCE 2
SECTION 2 DESIGN, FABRICATION AND SURFACE FINISH OF
EQUIPMENT TO BE LINED
6 GENERAL 2
7 DESIGN OF METAL EQUIPMENT TO BE LINED 2
8 FABRICATION OF METAL EQUIPMENT TO BE LINED 3
9 DESIGN OF CONCRETE EQUIPMENT TO BE LINED 6
10 CONSTRUCTION OF CONCRETE EQUIPMENT TO BE LINED 9
SECTION 3 SELECTION AND QUALITY OF LININGS
11 SELECTION OF LINING 9
12 QUALITY OF LINING 10
SECTION 4 METHOD OF LINING
13 SURFACE PREPARATION 10
14 ADHESION SYSTEM AND APPLICATION 11
15 PRODUCTION OF LINING MATERIAL 11
16 APPLICATION OF THE SHEET TO THE SUBSTRATE 11
17 VULCANIZATION 13
SECTION 5 INSPECTION AND TESTING
18 RESPONSIBILITY FOR INSPECTION AND TESTING 14
19 INSPECTION 14
20 TESTING 16
20.1 Hardness Tests 16
20.2 Continuity of Lining (High Frequency Spark Test) 16
20.3 Bond Strength Tests 16
20.4 Lining Thickness 17
20.5 Hydraulic Testing of Lined Equipment 17
20.6 Vacuum Testing of Lined Equipment 17
21 RECTIFICATION OF FAULTS IN FULLY CURED LININGS 17
SECTION 6 STORAGE, HANDLING, TRANSPORTATION,
INSTALLATION AND MAINTENANCE
22 GENERAL 17
23 MAINTENANCE 17
ANNEX A LIST OF REFERRED INDIAN STANDARDS 18
ANNEX B LINING OF USED EQUIPMENT 18
ANNEX C CHARACTERISTICS OF LINING MATERIALS 19
ANNEX D EFFECT OR MATERIALS ON WATER QUALITY 21
ANNEX E VULCANIZATION 21
ANNEX F METHOD OF TEST FOR CONTINUITY TESTING 22

FOREWORD

This Indian Standard (First Revision) was adopted by the Bureau of Indian Standards, after the
draft finalized by the Chemical Engineering Plants and Related Equipment Sectional Committee
had been approved by the Heavy Mechanical Engineering Division Council.

( Continued on third cover )


IS 4682 (Part 1) : 1994

Indian Standard
CODE OF PRACTICE FOR LINING OF
VESSELS AND EQUIPMENT FOR
CHEMICAL PROCESSES
PART 1 RUBBER LINING

( First Revision )
SECTION 1 GENERAL

1 SCOPE 3.4 Inspection Authority


1.1 This Indian Standard (Part 1) specifies The body or association appointed by the
requirements for the lining of equipment for the purchaser (or owner) to check that the design,
process industries using cold rubber. It applies fabrication and lining comply with this
to equipment fabricated in metal or concrete. standard.
1.1.1 It includes requirements for the choice of 3.5 Vulcanization
lining and its application and also requirements
for inspection of the lining and the rectification The chemical reaction resulting in the final
of faults. The materials considered include polymerized product.
natural and synthetic rubbers applied as
3.6 Pinhole
unvulcanized or prevulcanized sheet.
1.1.2 Brushed or sprayed rubber linings are not A small defect in the lining that would permit
included. corrosion of the substrate under the conditions
NOTE The linings may be applied at the applicators
for which the lining is designed.
works or on site. NOTE The word pinhole is synonymous with
holiday and pore.
1.2 It includes requirements for design and
fabrication of the equipment and the state of 3.7 Blister
preparation necessary for the surfaces to be
lined. It also includes requirements for storage, A gas or liquid filled cavity within the lining
handling, transportation and installation of the material or between the lining and substrate.
lined equipment. 3.8 Scarf Joint
2 REFERENCES A joint made between two adjacent sheets of
The Indian Standards listed in Annex A are rubber by bevelling the edges of the sheets and
necessary adjuncts to this standard. overlapping one prepared edge on the other
( see Fig. 7 ).
3 TERMINOLOGY
3.0 For the purpose of this standard 4 EXCHANGE OF INFORMATION
the definitions given in IS 7503 (Parts 1, 2, 3 4.1 Early consultation shall be arranged
and 4) : 1988 shall apply, together with the between all parties concerned with the
following. application of this standard, to establish the
3.1 Purchaser following information which shall be fully
The organization or individual who buys the documented:
lined equipment for its own use or as an agent i) Design and fabrication details of the
for the owner. equipment to be lined and provision of
3.2 Fabricator drawings ( see 7, 8, 9 and 10 ).
The organization or individual responsible for ii) Details of gasket materials ( see 7.9 and
the fabrication of the equipment to be lined. 7.10 ).
3.3 Applicator iii) Details of the contents of the vessels or
The organization or individual responsible for equipment, including trace materials
the application of the lining. [ see 11.13 (a) ].

1
IS 4682 (Part 1) : 1994

iv) The design temperature [ see 11.1.3 (b) ]. which are required for the correct
v) The design pressure [ see 11.1.3 (c) ]. application of the lining ( see 14 and 16 ).
xix) The minimum temperature required
vi) The details of any solids to be handled during the vulcanization of the lining
[ see 11.1.3 (e) ]. ( see 17 ).
vii) Any specific mechanical properties xx) The vulcanization schedule, where
required of the lining including applicable.
suitability for machining [ see 11.1.3 (g) ].
xxi) Inspection techniques/procedures to be
viii) The methods of heating and/or cooling employed, acceptance levels and stages
[ see 11.1.3 (b) ]. of inspection ( see 18 and 19 ).
ix) Cleaning methods, for example, water xxii) Handling, transport storage and
washing, solvent washing, boiling out or installation procedure [ see 11.1.3 (g)
steaming [ see 11.1.3 (a) ]. and 22.1 to 22.7 ].
x) Where the lining work will be done. 4.2 Both the definitive requirements specified
in this standard and the items documented
xi) Site conditions which may affect the
in 4.1 shall be satisfied before a claim of
work, for example, availability of
compliance with the standard can be made and
services.
verified.
xii) Any special requirements for materials
used in blast cleaning ( see 13.1.1 and 5 COMPLIANCE
13.1.2 ). 5.1 Fabricator
xiii) The rubber lining to be used ( see 11.1 ). The fabricator shall comply with the following:
xiv) The minimum thickness of the a) Section two [ see 4.1 (i) ];
vulcanized lining and where applicable b) Requirements given in 18.1 (a) and 18.1;
the maximum thickness ( see 12.2 ). and
xv) The provision of test plates [ see 12.1 (c) ]. c) Section six as agreed in 4.1 (xxii).
xvi) When the lining is to be applied outside 5.2 Applicator
the applicators works and the primers The applicator shall comply with the following:
and/or adhesives as applied contain
a) Section three ( see also 12.1 );
solvents, the types of solvents are to be
stated, together with their flash points b) Section four;
and threshold limit values. c) Requirements given in 18.1 (c), (d), (e) and
xvii) Specified adhesion system ( see 11.1, (f);
12.3 and 14 ). d) Requirements given in F-3;
xviii) The minimum and maximum allowable e) Requirements given in 21; and
temperature and allowable humidity f) Section six as agreed in 4.1 (xxii).

SECTION 2 DESIGN, FABRICATION AND SURFACE FINISH OF


EQUIPMENT TO BE LINED

6 GENERAL rigid that there is no possibility of deformation


which would result in damage to the lining
6.1 The basic design, fabrication and testing for during transportation, installation and
mechanical reliability of the equipment to be lined operation. When stiffeners are required, they
shall be carried out to the appropriate Indian shall normally be applied to the unlined side of
Standard and shall comply with 7 and 8 or 9 and the equipment.
10 before the lining operation commences.
NOTE In the case of hard rubber and ebonite linings
NOTE Rubber lining will affect heat transfer and this requirement is of particular importance.
tolerances required for joints; both features need to be 7.2 The arrangements for the lifting of
considered at the design stage of the equipment.
equipment shall be determined at the design
6.2 For the lining of used equipment, refer stage.
Annex B. 7.3 The design of all equipment shall allow for
access during the preparation of the surface
7 DESIGN OF METAL EQUIPMENT TO and application of the lining and for venting of
BE LINED fumes evolved during the operation.
7.1 Equipment to be lined shall be sufficiently 7.3.1 In completely enclosed vessels there shall
2
IS 4682 (Part 1) : 1994

be at least one manhole that after lining NOTE Pipe systems made from straight lengths with
complies with IS 2825 : 1969 or IS 803 : 1976 separate standard bends and tees meet this
requirement. Bends should not be greater than 90.
and one additional branch of not less than
75 mm bore to permit adequate circulation of air. 7.13.1 Where pipe systems include
NOTE It is recommended that, where practicable, the non-standard fittings their suitability for
minimum diameter of a manhole should be 600 mm. lining shall be established [ see 4.1 (i) ].
7.4 Riveted constructions shall not be used. Suitable arrangements are illustrated in Fig. 2.
7.5 Bolted joints shall be permitted only if they 7.13.2 The maximum dimensions of pipes and
fittings which can be rubber lined shall be
can be dismantled for lining.
determined during the exchange of information
7.6 When calculating clearances, allowance [ see 4.1 (i) ]. Typical maximum lengths of
shall be made for the thickness of the lining. straight pipe which can be rubber lined are
7.7 Surfaces to be lined shall be of a smooth detailed in Table 1.
contour.
Table 1 Maximum Length Between Flanges
7.8 Discontinuities, crevices and sharp ( Clause 7.13.2 )
projections shall be avoided.
Nominal Pipe Maximum Length
7.9 Fittings which have to be installed after the Size Between Flanges
completion of the lining process shall be mm mm
designed to be lined or fabricated from
materials that will not be affected by the 25 2 000
process conditions. 32 2 500
40 3 000
7.10 Normally all connections to lined parts of
50 3 500
equipment shall be flanged. If for any reason
65 4 000
screwed connections are required, then these
80 to 600 6 000
parts shall be fabricated in corrosion-resistant
materials.
7.13.3 Pipes less than 25 mm diameter shall
7.11 Branches and outlets, except for plain not be rubber lined. Pipes less than 250 mm
ended pipes, shall be as short as possible and diameter shall be of seamless construction only.
flanged so that the lining may be taken over the Screwed fittings shall not be rubber lined.
flange face to prevent the ingress of process
7.13.4 Where flat face or raised face flanges are
fluid between the lining and the substrate.
used they shall be welded square to the pipe or
NOTE Acceptable flange systems are shown in Fig. 1. fitting according to normal manufacturing
7.11.1 Plain-ended pipes shall be designed so tolerances.
that the lining may be turned over the end and 7.13.5 Flanges which are attached to a pipe by
the outside of the pipe. fillet welding (for example slip-on flanges) shall
7.11.2 Where pads are required they shall be be suitably vented to allow any air trapped
designed as shown in Fig. 1 (d). Drilled and between fillet welds to escape to atmosphere
tapped holes in pads for studs shall not during lining and vulcanizing.
penetrate the shell of the equipment. NOTE This may be accomplished by using a vent hole
in the flange, providing this meets piping design
7.12 Heating coils, immersion heaters and standard requirements.
sparger pipes shall be installed after the
completion of the lining process and shall be 8 FABRICATION OF METAL EQUIPMENT
located so that no part is closer than 100 mm TO BE LINED
from a lined surface. In the case of nozzles 8.1 All welds shall be continuous on surfaces to
through which heating coils, etc, enter be lined.
equipment, a smaller clearance is permitted
NOTE Butt welds are preferred to fillet welds.
provided that the temperature of the pipe
through the nozzle does not exceed 80C. In no 8.1.1 Stitch welding, spot welding and other
case shall this clearance be less than 25 mm. non-continuous welding processes shall not be
Fluids introduced through sparger pipes or dip used.
pipes shall not impinge directly on to the lining. 8.2 Weld surfaces shall be smooth. Some
External heating of equipment shall not be welding procedures provide surfaces of
permitted without full consultation with the adequate smoothness but, in other cases
applicator of the lining. surfaces shall be ground wholly or partly to
7.13 The design of pipework shall be such as to remove weld ripples. The grinding process shall
allow ready access to welds and bends for weld be done so that the remaining weld does not
and surface preparation. have sharp edges.

3
IS 4682 (Part 1) : 1994

NOTE The details shown in (a), (b), (c), (d), (e) and (f) are all permissible, that shown in (g) is not permissible.

FIG. 1 WELD PROFILE DETAILS : FLANGES

4
IS 4682 (Part 1) : 1994

NOTE The details shown in (a), (b), (c) and (d) are all permissible, those shown in (e), (f), (g) and (h) are not
permissible.

FIG. 2 PIPEWORK DETAILS

5
IS 4682 (Part 1) : 1994

8.3 Welding procedures shall be chosen to avoid 8.10 Where there is a requirement that a rotat-
porosity on the side of the weld to be lined. ing part shall be balanced, then this balancing
NOTE It is preferable that capping runs are applied shall be done both before and after lining.
to the lining side in order to minimize this effect. 8.11 All slag, anti-spatter compounds or similar
8.3.1 All welds shall be free from the following materials shall be removed. All weld spatter
surface defects : shall be removed by chipping and/or grinding.
a) Undercutting, 8.12 Surface defects such as scores, pitting and
b) Cracks, rolling defects shall be removed by grinding, or
where necessary repaired by welding provided
c) Porosity, that the requirements of design and
d) Any other type of surface cavity, and construction are met.
e) Lack of fusion. 8.13 Surfaces shall be presented to the lining
8.3.2 Weld defects that are exposed either on applicator in a clean condition free of all
initial inspection or after blast cleaning shall be contamination, for example oil, grease,
repaired. temporary protective coating, such that no pre-
treatment is required other than any grit
8.3.3 Repairs shall be by grinding or by welding blasting which is to be part of the lining process.
(with or without subsequent grinding) provided
9 DESIGN OF CONCRETE EQUIPMENT
that the requirement for equipment design and
TO BE LINED
fabrication are met.
9.1 Whilst it is not possible to eliminate shrink-
8.4 Weld profile details shall be generally in age cracks in concrete, the design shall be such
accordance with Fig. 1 and Fig. 3 to 6. that structural cracking is eliminated. Particular
NOTE Incorrect details are also illustrated. attention shall be paid to avoiding cracking due
8.5 Filler materials, such as resin, putties, to thermal stresses. The ability of the lining to
fillers and low melting point solders and accommodate cracking of the concrete shall
brazes, shall not be used. determine the selection of the rubber. Equipment
shall be designed to IS 456 : 1978.
8.6 Before the equipment is passed for lining,
9.2 If necessary, extra reinforcements shall be
all attachments to be made by welding, for used and construction joints treated so as to
example lagging cleats and lifting lugs, shall be promote a bond between adjacent areas of
complete. concrete. Expansion joints create special
8.7 All drilling shall be completed before the problems in lining and shall not be used
equipment is passed for lining. Holes to be without consultation between the purchaser
lined shall have their edges radiused. and the applicator of the lining.
8.8 External corners and edges shall be 9.3 Pipes and fittings shall be designed with
furnished to a radius of minimum 3 mm or puddle flanges and cast into the concrete.
Where necessary such fittings shall be designed
equal to the thickness of the rubber, whichever
in a concrete resistant material. Pipes and
is higher. For internal corners and edges to a fittings shall normally be rubber lined before
radius of minimum 6 mm or twice the rubber being cast into the concrete.
thickness whichever is higher.
9.4 The arrangements for the blast of equipment
NOTE For typical edge configurations, see Fig. 4
and 5. shall be determined at the design stage.
8.9 Castings including cast iron shall be 9.5 The design of all equipment shall allow for
produced by foundry techniques which give access during the preparation of the surface
and application of the lining, and for venting of
dense smooth surfaces free from slag, sand and
fumes evolved during the operation. In
inclusions, shrinkage cavities, scabs, cracks, completely enclosed vessels there shall be at
porosity and burns and the entrapment of air in least one manhole complying, after lining, with
surface defects. IS 2825 : 1969 or IS 803 : 1976 and one
8.9.1 Removal of defects shall be by welding additional branch of not less than 75 mm bore
and grinding or by grinding alone. Grinding to permit adequate circulation of air.
alone shall be used only for small defects such NOTE It is recommended that, where practicable, the
that the ground cavity blends smoothly with the minimum diameter of a manhole should be 600 mm.
casting surface and does not reduce the sound 9.6 All corners shall be designed to be formed with
wall of the casting below the requirements of a 45 fillet with a minimum leg length of 20 mm.
the design standard. For larger defects welding 9.7 All equipment to be placed below ground
shall be used and the repair weld shall be level or subject to external water pressure shall
ground flush such that it does not impair the be provided with a waterproof barrier on the
requirements of the design standard. outside of the equipment.

6
IS 4682 (Part 1) : 1994

NOTE The details shown in (a), (b), (c), and (d) are all NOTE The details shown in (a), (b), (c), and (d) are all
permissible, those shown in (e), (f), and (g) are not permissible, that shown in (e) is not permissible.
permissible.

FIG. 3 WELD PROFILE DETAILS : BUTT WELDS FIG. 4 WELD PROFILE DETAILS : INTERNAL
CORNERS AND EDGES

7
IS 4682 (Part 1) : 1994

NOTE The details shown in (a), (b), (c), and (d) are all
permissible, that shown in (e) is not permissible.

FIG. 5 WELD PROFILE DETAILS : INTERNAL FIG. 6 WELD PROFILE DETAILS : CONCAVE HEADS
CORNERS AND EDGES

8
IS 4682 (Part 1) : 1994

9.8 All equipment shall be designed with a bagged as the concrete leaves the formwork
minimum of 20 mm of concrete over before the curing membrane is applied.
reinforcement. NOTE This process will reduce the amount of laitance.
10 CONSTRUCTION OF CONCRETE 10.4 All surfaces not cast against shutters shall
EQUIPMENT TO BE LINED be finished with a wooden float. Curing
membranes shall be applied and not disturbed
10.1 Concrete equipment shall be constructed for 7 days.
in accordance with the requirements of IS 3370
10.5 Any steps in the concrete due to
(Parts 1, 2, 3 and 4) or IS 456 : 1978 as
appropriate. misalignment of shutters or surplus material
formed because of gaps at joints in shutters
10.2 Proper curing of the concrete shall be shall be dressed off and ground smooth.
ensured by the use of curing membranes. If 10.6 All holes left after removal of ties to secure
shuttering is removed in under 7 days a curing and align formers shall be filled. Any surface
membrane shall be applied. Concrete defects such that the aggregate is exposed shall
equipment shall be allowed to cure for 28 days be filled. The material used for filling shall be a
before the work of lining proceeds. Concrete sand/cement grout with a high cement content
hardening solutions shall not be used. or a sand/cement water miscible epoxy resin
10.3 Equipment which is slip formed shall be grout or an epoxy mortar.

SECTION 3 SELECTION AND QUALITY OF LININGS

11 SELECTION OF LINING present in small and trace quantities, and


11.1 Linings referred to in this standard shall details of cleaning operations.
include natural and synthetic rubbers which b) Temperature of materials to be handled :
shall be bonded to the substrate. 1) Normal operating temperatures;
NOTES 2) Maximum and minimum temperatures;
1 Rubber linings are used for a number of different and
duties including protection against corrosive
environments, protection against abrasion or erosion 3) Cycle of temperature variation.
and prevention of contamination of products.
c) Degree of vacuum or pressure :
2 The properties of lining materials depend not only
upon the type of rubber but upon the compounding 1) Normal operating pressure;
(mixing) with other ingredients, e.g. fillers, vulcanizing 2) Maximum and minimum pressure; and
agents, etc. Some applicators produce their own
compounds and sheet, others buy from external sources. 3) Cycle of pressure variation.
11.1.1 It shall be the responsibility of the d) Cycle of operations Whether batch or
applicator, unless otherwise agreed [ see 4.1 continuous process.
(xiii) ], to select a compound suitable for the duty e) Abrasion and erosion Details of
stated by the purchaser. In order to define the amount, particle size and physical
rubber used for a lining, a compound reference characteristics of the suspended matter
as well as the rubber type shall be stated by the together with rates of flow.
applicator during the exchange of information.
f) Mechanical damage Any difficulties
11.1.2 The adhesive system used for bonding expected in the handling and final siting
the rubber to the substrate shall depend upon of the equipment or any vibration of
the type of rubber and the method of equipment and the possibility of
vulcanization. It shall be the responsibility of mechanical damage.
the applicator to select an adhesive system
which will provide an adequate bond between g) Special requirements For example
rubber and substrate. extremes of weather likely to be
NOTE A description of the rubbers used for lining
encountered during the handling,
and a guide to their properties are given in Annex C. transport and storage of the equipment.
Applicators will have more extensive knowledge of
particular compounds and some purchasers will have 11.1.4 When selecting materials account shall
particular knowledge of past performance which will be taken of Annex D.
help in the selection of a suitable lining material.
11.2 Unless previous experience demonstrates
11.1.3 When an applicator is to select and that a lining will be suitable for a particular
apply the lining full details of the duties of the duty, appropriate testing shall be carried out.
equipment shall be supplied. The selection of NOTE Attention is drawn to the dangers of
the rubber lining shall be based on the short-terms testing and the need to reproduce service
following information: conditions accurately.
a) General Full analysis of the contents of 11.2.1 Where it is not possible to place samples
the equipment including constituents in process streams, service conditions shall be

9
IS 4682 (Part 1) : 1994
simulated. Where it is known that a lining has to 12.2 Thickness of the Lining
withstand an environment where heat transfer 12.2.1 The thickness of the lining shall be
is made through the lining, the heat transfer selected to suit the chemical and/or mechanical
condition shall be maintained during the test. duty during the exchange of information
11.2.2 Substances including dissolved gases between the applicator and the purchaser
present in a process stream in trace quantities [ see 4.1 (xiv) ].
only shall be added to the test liquors. NOTES
1 The minimum thickness which is acceptable is 3 mm,
12 QUALITY OF LINING but thickness of 4 mm, 5 mm or 6 mm should be chosen
as required to meet particular operating conditions.
12.1 General 2 Thicknesses greater than 6 mm are normally applied
in two or more layers.
When the applicator is responsible for selecting 12.2.2 Normally the thickness refers to the
the grade of lining to be applied, he shall verify rubber sheet as applied to the substrate. If the
that such a lining shall withstand the chemical purchaser requires the nominated thickness
and physical conditions specified in 11. When to apply to the finished lining this shall be
the purchaser selects the grade of lining to be stated during the exchange of information
applied, the applicator shall be responsible only [ see 4.1 (xiv) ].
for the correct application. The applicator shall
in either case : 12.3 Bonding of the Lining
The rubber lining shall be bonded to the
a) State the reference number of the rubber
substrate. The adhesive system shall be
to be used for the lining.
suitable for the type of rubber and for the
b) State the hardness of the rubber after service conditions. The applicator shall be
vulcanization. responsible for the selection of the adhesive
system and shall produce evidence that the
c) Supply test pieces such as panels to adhesive system will produce the bond required
which the rubber has been applied and
between rubber and substrate when the rubber
which will serve as reference samples
is applied under the conditions of vulcanization
[ see 4.1 (xv) ]. [ see 4.1 (xvii) ].
SECTION 4 METHOD OF LINING
13 SURFACE PREPARATION preparation and lining processes. If there is a
13.1 Metal risk that this condition will not be maintained
owing to ambient conditions, dehumidifying
13.1.1 All surfaces of carbon steel and cast iron and/or heating equipment shall be used.
to be lined shall be blast cleaned, unless
otherwise permitted by the purchaser. 13.2 Concrete

13.1.2 In the case of metals other than carbon 13.2.1 External corners not formed with a
steel and cast iron, methods of preparation of chamfer shall be rubbed down to a radius of at
the substrate shall promote an acceptable bond least 3 mm or the thickness of the rubber lining
between the substrate and the lining. The whichever is greater. For internal corners
appropriate technique of substrate preparation radius should be at least 6 mm or twice the
shall be established with the lining contractors rubber lining thickness whichever is greater.
[ see 4.1 (xii) ]. 13.2.2 Lining of concrete equipment shall not
13.1.3 All surface dust, residues and debris left proceed until at least 28 days after the concrete
on the surface after blast cleaning shall be was cast and when the free water content is
removed, thoroughly. down to a level specified in 4.1 (i).
NOTES
13.1.4 The lining process shall start as soon as
possible after blast cleaning is complete and 1 Satisfactory adhesion of rubber lining to concrete
before any visible rusting occurs. Unless depends upon the water content of the concrete. It is
desirable that the free water content is less than 5
maintained in a dehumidified atmosphere percent. If the concrete mix used is carefully controlled
application of the primer shall commence it is possible that after a curing period of 28 days the
within 4 hours. Should signs of rusting occur water content will be down to 5 percent but the required
then the surface shall be prepared again to the curing period may be longer.
required standard ( see 13.1.1 ). 2 There are no reliable methods for measuring the
absolute water content of concrete although moisture
13.1.5 All surfaces to be lined shall be meters may be useful in determining problem areas. It
maintained at a temperature of at least 3C is advisable to line a test area and measure the
above the dew point throughout the adhesion before proceeding with a complete lining.

10
IS 4682 (Part 1) : 1994

13.2.3 Surfaces to be lined shall be treated to a) When linings are produced by


remove laitance and shutter release agents. Of calendering, multiply construction shall
the two possible methods for this operation the be employed.
one preferred is blast cleaning. The blast
NOTE The minimum number of plies employed in
cleaning process shall be controlled so that all the manufacture of a finished sheet depends upon the
laitance is removed and exposure of the profile rubber compound. A guide to the number of plies related
of the aggregate kept to a minimum. After blast to a given thickness is given below :
cleaning all dust and debris shall be removed. Thickness Minimum Number
NOTE The alternative method of removing laitance of Lining, of Plies
is that of acid etching. The process is more difficult to mm
control on vertical and overhead surfaces and the
presence of shutter oils will reduce its effectiveness. The 3 to 5 3
thickness of the laitance of a concrete surface varies 6 4
considerably and it is very important that acid is
allowed to dwell on the surface a sufficient length of
time to remove all laitance. When acid etching is used b) When roller die or extrusion methods are
the next operation is water washing of the concrete, used for the production of lining materials
followed by a drying process. then single-ply or multi-ply sheets are
13.2.4 Unless the lining material will fill or permissible.
effectively bridge the large number of small holes
(of varying diameter and depth) that invariably 15.4 Pre-vulcanized Lining Materials
remain in the concrete surface following the
removal of laitance, then these holes shall be The unvulcanized lining sheet shall be
filled before the work of lining commences. prepared in accordance with 15.3 and shall
then be vulcanized by heating (normally under
NOTE One material recommended for this purpose is
a smooth paste made from a water miscible epoxy resin pressure in an autoclave) or by a rotary
and a fine filler and cement ( see 10.6 ). vulcanization process.
13.2.5 After removal of laitance all surfaces to
be lined shall be maintained at a temperature 16 APPLICATION OF THE SHEET TO
at least 3C above the dew point throughout the THE SUBSTRATE
preparation and lining processes. If there is a
risk that this condition will not be maintained 16.1 General
owing to ambient conditions or a change in
ambient conditions, dehumidifying and/or Detailed methods of working are not specified
heating equipment shall be used. in this standard but the requirements specified
in 16.2 to 16.5 shall be met according to
14 ADHESION SYSTEM AND whether unvulcanized sheet, pre-vulcanized
APPLICATION sheet or a combination of the two is being used.
14.1 The adhesive system shall be such that
the required level of adhesion between the 16.2 Preparation of Lining Sheet
lining and the substrate is achieved upon
completion of the lining process. 16.2.1 In the case of unvulcanized sheet any
preshrinking necessary shall be carried out as a
NOTE The adhesive system may consist of one or
more individual layers. The primer already applied to first step.
the substrate may also be considered as part of the
adhesive system. 16.2.2 Individual sheets shall be tailored to fit
14.2 The adhesives shall be applied to the primed the surface to be lined. Edges shall be prepared
substrate surface by brush, roller or spray, any according to the type of joint to be used. Types
solvents in the adhesive being allowed to of joints are illustrated in Fig. 7.
evaporate between the application of successive
16.2.2.1 The details of edge preparation shall
coats or subsequent application of the lining.
be as follows :
15 PRODUCTION OF LINING MATERIAL
a) Overlap scarf joint The edges shall be
15.1 Thickness Tolerance bevelled at 30 to 35.
The thickness tolerance on nominal dimensions b) Simple scarf joint The edges shall be
of the rubber sheet shall be 10 percent. bevelled at 40 to 50.
15.2 Freedom from Imperfections c) Cover straps The edges shall be bevelled
The sheet shall be free from blisters or other at 30 to 35.
imperfections which would adversely affect the
quality of the lining. 16.3 Joints
15.3 Unvulcanized Lining Materials Depending upon the type of sheet being applied
Lining materials shall be produced using a and the method of lining, one of the following
calender, extruder or roller die. types of joint shall be used.

11
IS 4682 (Part 1) : 1994

FIG. 7 TYPICAL JOINTS IN RUBBER LININGS

12
IS 4682 (Part 1) : 1994

a) Overlap scarf joint This type of joints is 17 VULCANIZATION


illustrated in Fig. 7(a). The total length of 17.1 General
the contacting surface between adjacent
sheets shall be a minimum of four times 17.1.1 Vulcanization of the lining shall be
the sheet thickness but shall not exceed carried out by one of the following methods :
32 mm at any point. Overlap scarf joints a) Autoclave vulcanization,
will tend to affect the flow in pipes and b) Using equipment as its own autoclave,
that effect may be significant in the case of
small bore pipes, a fact which shall be c) Steam or hot air vulcanization at ambient
considered when the equipment is pressure,
designed. Overlap scarf joints on mating d) Hot water vulcanization, and
surfaces shall be dressed as necessary to e) Self vulcanization at ambient
allow efficient sealing when assembled. temperature.
NOTE It is preferable that overlap scarf joints should NOTES
be made so that the overlap follows the direction of flow.
1 The method employed depends upon the design and
b) Straight scarf joints shall be made as size of the equipment. It may be necessary to shield the
illustrated in Fig. 7(b). equipment to reduce heat losses which would otherwise
lengthen the duration of vulcanization when using
c) Strapped joints shall be made as methods (b), (c) or (d) above.
illustrated in Fig. 7(c). The scarf joint in 2 The duration of vulcanization will depend upon the
the parent sheet shall pass a spark test method used and the composition of the lining material.
before the cover strap is fitted. The cover More information on vulcanization is provided in
strap with edges bevelled shall be aligned Annex E.
centrally over the joint. The maximum 17.1.2 With the agreement of the applicator
path from an edge of the strap to the [ see 4.1 (xx) and (xxi) ] interruption of
substrate shall not exceed 32 mm. vulcanization shall be permitted to detect and
NOTE The thickness of the strap may be less than repair any faults present. The equipment shall
the thickness of the lining. then undergo further heat treatment to
d) Joints in multiple layer linings shall be complete the vulcanization. An inspection for
scarfed as illustrated in Fig. 7 (b). Joints faults shall be carried out in accordance with
within one layer shall be offset relative to section five.
joints on adjacent layers. The distance 17.2 Methods of Vulcanization
between joints on adjacent layers shall be
a maximum consistent with the geometry 17.2.1 Autoclave Vulcanization
of the equipment. The equipment shall be placed in an autoclave
16.4 Pretreatment of Lining Sheets which is then heated to the required
temperature and pressure.
The contacting face of the lining sheet shall be
made tacky so as to adhere to the adhesive 17.2.2 Using Equipment as Its Own Autoclave
layer already on the substrate. Tackiness shall With all outlets sealed and a steam trap
be produced by either wiping with a suitable condensate drain attached to a convenient
solvent or the application of a coat of adhesive. outlet to ensure continuous removal of
In either case solvents shall be allowed to condensate, saturated stream shall be injected
evaporate before the sheet is applied to the until the equipment is pressurized to a
surface to be lined. predetermined pressure. The pressure shall be
within the design pressure limits of the
16.5 Fitting of Lining Sheet to the
equipment. Precautions shall be taken against
Substrate
failure of the steam supply since, in such cases,
16.5.1 Exclusion of Air condensation can cause a vacuum and collapse
In the application of lining air shall be excluded the vessel.
between the substrate and lining and between 17.2.3 Steam or Hot Air Vulcanization at
adjacent layers in multilayer linings. Ambient Pressure
NOTE Exclusion of air is achieved by pressing the With outlets covered to reduce steam losses and
lining against the substrate with a roller or by other
means in a systematic manner. Suitable tools should be provision made to drain condensate from the
used to ensure complete contact of rubber to substrate equipment, the steam shall be injected until the
at changes of direction and rubber to rubber at joints. vulcanization temperature is attained. This
16.5.2 Continuity of Lining temperature shall be maintained for the
required time period. Attention is drawn
When fitting of the sheet is complete all sheets to 17.2.2 regarding failure of steam supply.
and joints whether overlap, scarf, straight scarf
NOTE Hot air may be used as an alternative to
or strapped joints shall be free from pinholes steam in some cases provided that the temperature and
and other defects. heat input can be achieved.

13
IS 4682 (Part 1) : 1994

17.2.4 Hot Water Vulcanization 17.2.5 Self Vulcanization at Ambient


With all outlets below the top flange sealed off Temperature
and the equipment partially filled with water
steam shall then be injected into the water, Such rubber linings shall be specially designed
raising the water level and temperature. If the so that they are capable of vulcanizing under
water reaches boiling point before the ambient conditions.
equipment is full, further water shall be added NOTE The time to vulcanize is temperature-
to attain the required level. The temperature dependent and at temperatures below 15C it may be
shall then be maintained for the required time necessary to use supplementary heating in order to
period while maintaining the water level. reduce vulcanization times to an acceptable period.

SECTION 5 INSPECTION AND TESTING

18 RESPONSIBILITY FOR INSPECTION they are free from laitance and that surface
AND TESTING defects are properly filled.
18.1 The fabricator of the equipment and the 19.3 Quality of the Lining and Bonding
applicator of the lining when requested shall Materials
provide a certificate of inspection and testing. Before proceeding the applicator shall ensure
The stages of inspection shall be as follows: that all materials to be used in the lining
process are visually examined and, where
a) The equipment as fabricated. appropriate, physically and practically tested to
b) The equipment after preparation of welds confirm that they are in an acceptable
and edges in the case of metals; surfaces condition. For the unvulcanized rubber
and edges in the case of concrete. sheeting this shall include:
c) The equipment after blast cleaning. a) Visual examination to ensure that it has
no imperfection which could significantly
d) The materials to be used in the lining affect the performance of the finished
process. vulcanized lining.
e) After the lining has been applied and b) Visual and physical examination to
before vulcanization. ensure that it has been prepared in
accordance with section four and that the
f) When the arrangements are made to actual thickness is within 10 percent of
interrupt vulcanization. the specified thickness.
g) After vulcanization is complete. c) A test to ensure that the sample taken from
each roll achieves the correct hardness
h) Whenever remedial work is carried out. when vulcanized in accordance with the
18.2 In cases where the purchaser requires customary practice of the applicator.
independent inspection of the work (i.e. by the 19.4 Visual Appearances of the Lining
inspection authority) at various stages, those 19.4.1 Inspection for visible defects shall be
stages shall be defined [ see 4.1 (xxi) ]. carried out over the entire surface of the lining
in a good light, attention being paid to any
19 INSPECTION areas of mechanical damage, cuts, blisters, lack
of adhesion and poor jointing.
19.1 Surface Cleanliness and Profile of
Metal Surfaces 19.4.2 If the applicator finds a defect prior to
vulcanization it shall be removed and the area
19.1.1 Blast-cleaned surfaces shall be inspected overlaid with unvulcanized rubber of the same
to ensure that they comply with 13.1. type as the original unvulcanized rubber on to
which it is bonded. After subsequent
19.1.2 Reference photographs or plates shall be vulcanization the area concerned shall be
used to establish the level of surface cleanliness considered identical to a lap joint or seam and
( see 13.1.3 ). thus fully acceptable.
19.1.3 If inspection of equipment after blast 19.4.3 All scarf joints shall be closely inspected.
cleaning reveals defects in material or welds, Any separation of the joint shall be investigated
( see Fig. 8 ). If the extent of the separation is
the applicator shall inform the fabricator small then the rubber shall be ground back. If
and/or the purchaser and any remedial action the separation of the rubber is extensive then
shall be determined after consultation between the joint and rubber adjacent to the joint shall
the parties concerned [ see 4.1 (xxi) ]. be removed and replaced.
19.2 Concrete Surface 19.4.4 To repair defects found after
vulcanization, the surface of the lining local to
Concrete surfaces shall be inspected to see that the defect shall be prepared by abrading.

14
IS 4682 (Part 1) : 1994

FIG. 8 UNACCEPTABLE-FAULTS IN JOINTS IN RUBBER LININGS

15
IS 4682 (Part 1) : 1994

Adhesive and a patch of unvulcanized rubber bond strength. If further evidence is required to
both of the same type as used for the lining show that the bond between the substrate and
shall then be applied. The size of this patch the rubber is satisfactory the provision of test
shall not be greater than 25 mm in any samples shall be specified during the relevant
direction beyond the defect. The patch shall discussions at an early stage [ see 4.1 (xvii) ].
then be vulcanized. After rectification, the NOTE Because there is no quantitative
repaired area shall be tested for pinholes. non-destructive test for assessing the bond strength
Minor wrinkles and surface markings which between a rubber lining and the substrate no routine
bond strength tests are specified for the actual lining as
have no significant effect on the performance of part of the inspection procedure. The bond strength for a
the lining shall be acceptable. particular combination of substrate, rubber and adhesive
system may be established by laboratory testing.
NOTE After vulcanization defects such as blisters,
blow holes, small cracks or scuffed areas in the lining 20.3.2 Test samples shall consist of pieces of
may be found. When such faults are discovered after substrate, similar to that used in the
vulcanization the defect may be patched.
manufacture of the equipment, to which has
20 TESTING been applied rubber of the same mix and
20.1 Hardness Tests thickness used for the main lining. The
adhesive system shall be the same as that used
20.1.1 Hardness testing shall be carried out on for lining. The conditions of application shall be
completion of vulcanization in accordance with the same. Vulcanization shall be carried out at
IS 3400 (Part 2) : 1980. If after initial testing the same time as the lining, in the same
any further vulcanization is required, the autoclave or inside the equipment when
lining shall be re-tested and shall meet the vulcanization takes place outside of an
agreed hardness (agreed by contractor and
autoclave.
user) at all points.
20.3.3 The bond strength between rubber and a
20.1.2 Hardness testing shall be carried out on
substrate shall be measured by method A
a flat smooth surface. In vessels where readings
cannot be taken on the surface of the lining, described in IS 3400 (Part 14) : 1984. Minimum
buttons shall be provided in positions to be load figures for bond strengths obtainable with
agreed between the purchaser and the lining various types of rubbers, vulcanized by
contractor. If the surface is too rough, a light different methods, shall be as given in Table 2.
local scraping or buffing may be carried out to NOTE There is no quantitative test for measuring
the bond strength of hard rubber or ebonite to
facilitate testing. substrates. A qualitative assessment of the bond can be
20.1.3 Readings obtained shall conform to the made by chipping the lining on a test plate with a chisel
25 mm wide when it should be possible to loosen only
specified hardness of the compound within 5. small pieces of hard rubber or ebonite at each blow.
A minimum of three hardness readings shall be
taken for each square metre of lining. Where a Table 2 Test Loads for Adhesion of Vulcanized
reading is outside the agreed range, further Soft Rubber to Carbon Steel and
readings shall be taken on the same panel to Concrete Substrates
ensure the general level of hardness. Where ( Clause 20.3.3 )
repairs have been carried out or where marking
Type of Rubber Carbon Steel Concrete
is feasible, the areas concerned shall be












separately tested. Pressure Vulcanization Self


Vulcani- by Hot Water Vulcaniza-
20.2 Continuity of Lining (High Frequency zation or Steam at tion at
Atmospheric Ambient
Spark Test) Pressure Temp
20.2.1 Testing for pinholes and other (1) (2) (3) (4) (5)
discontinuities shall be carried out : kN/m kN/m kN/m kN/m
Natural of synthetic 3.5 2.7 2.7 1.0
a) When the rubber has been applied and polyisoprene
before vulcanization. Styrene-butadiene 3.5 2.7 2.7 1.0
b) After interrupted vulcanization. Polychloroprene 3.5 2.7 2.7 1.0
c) After complete vulcanization. Butyl 3.5 2.7 2.7 1.0
d) After any remedial work. Ethylene-propylene 3.5 2.7 1.0
Nitrile 3.5 2.7 2.7 1.0
20.2.2 When tested in accordance with the
method described in Annex F, the linings shall Butadiene and/or 3.5 2.7
blends
be continuous i.e free from pin holes, crack and
Chlorosulphonated 2.7 2.7 1.0
lack of adhesion. polyethylene
20.3 Bond Strength Tests
20.3.4 The manner of stripping is of great
20.3.1 All open edges, for example flanges, significance. If the metal is clean or if failure
shall be examined by hand for evidence of poor has occurred at the rubber/adhesive interface

16
IS 4682 (Part 1) : 1994

this should be taken as an indication of an (normally one hour). The lining shall be
unsatisfactory bond. A properly bonded sample subsequently reinspected for defects.
should leave traces of rubber sheet adhering to
21 RECTIFICATION OF FAULTS IN
metal indicating failure within the rubber.
FULLY CURED LININGS
20.4 Lining Thickness Check
21.1 When rectification of faults is to be made
The thickness of the lining shall be checked. in linings which are fully vulcanized special
Where direct measurement is not possible a attention shall be paid to the problems of
suitable thickness metal shall be used. achieving adhesion between the new rubber
20.5 Hydraulic Testing of Lined Equipment and the vulcanized lining.
Normally pressure testing of equipment is 21.2 With all lining a patch which extends
completed before the commencement of the 25 mm beyond the area to be repaired shall be
lining operation. When specified, pressure tests abraded to promote adhesion.
shall be carried out [ see 4.1 (xxi) ]. The joint 21.3 When priming of the substrate is an
rings used for this test shall be of the same essential part of the system the first step after
material and the same dimensions as those preparation shall be to establish whether the
specified for the final service conditions. During primer is intact. If the primer is damaged when
a pressure test no leakage shall occur. The lining it shall be repaired before the rest of the work
shall be subsequently reinspected for defects. proceeds.
20.6 Vacuum Testing of Lined Equipment 21.4 Rectification of faults using other than the
When specified, a vacuum test within the original material used for the lining shall only
design limits of the equipment shall be carried be permitted with the written permission of the
out by evacuating the lined equipment with the purchaser.
appropriate joint rings in position, to a 21.5 After all rectification work the lining shall
specified vacuum [ see 4.1 (xxi) ]. The vacuum be subject to inspection as appropriate and in
shall be maintained for a specified period particular to continuity testing.
SECTION 6 STORAGE, HANDLING, TRANSPORTATION, INSTALLATION
AND MAINTENANCE
22 GENERAL 23 MAINTENANCE
22.1 Lined equipment shall be stored under 23.1 Maintenance of Rubber Lined
cover or in a protected compound. When Equipment
necessary, linings shall be shielded from direct 23.1.1 It is recommended that all rubber lined
sunlight. plant and equipment should be thoroughly
22.2 All branches, manholes and other inspected at the end of the first year of service.
openings shall be protected from mechanical If its condition is satisfactory and it is not
damage by using wooden blanks or other subject to statutory inspection after a lesser
suitable material. period some major users do not then inspect
again for a further 5 years. Others refer to
22.3 Lifting shall be arranged so that chains inspect at more frequent intervals.
and other lifting aids do not come into contact
23.1.2 When carrying out inspections it is
with lined surfaces.
normally sufficient if there are visual,
22.4 High local loads on lined surfaces shall be supplemented by hardness tests using a hand
avoided. meter. If blisters or other evidence of failure are
discovered then an electrical continuity test is
22.5 Loose fittings shall not be placed inside essential.
lined equipment whilst it is being transported.
23.1.3 It is essential that personnel be
22.6 Responsibility for arranging transport of instructed in the proper procedures to be
lined equipment will vary and whoever is adopted when entering rubber-lined vessels. A
responsible (purchaser, fabricator or clearance certificate should always be obtained
applicator) shall instruct the carrier about the from the appropriate authority before doing so.
precautions in handling [ see 4.1 (xxii) ]. The following points should be observed :
22.7 It is essential that the purchaser issues a) Personnel should not wear studded boots
instructions to those responsible for or other footwear likely to cause damage.
installation on the handling procedures and Rubber-soled shoes are to be preferred.
special reference is made to the need to wear b) In cases where solid deposits have to be
soft clean footwear when entering lined removed the use of metal spades or other
equipment and the need to protect lined tools is to be avoided. Wooden or lined
surfaces from ladders and scaffold poles. implements should be used.

17
IS 4682 (Part 1) : 1994

c) The ends of ladders or scaffolding likely to d) In large ebonite-lined vessels precautins


come in contact with the rubber lining to avoid successive flexing should be taken
should be covered in such a way that and walkways laid if necessary.
damage is avoided. Swinging air lines or
hoses can also puncture rubber linings. 23.1.4 Inspection should always be carried out
Metallic ends should therefore be covered by two people unless the use of ladders or
to prevent this occurring. electrical equipment can be avoided.

ANNEX A
( Clause 2 )

LIST OF REFERRED INDIAN STANDARDS

IS No. Title IS No. Title


456 : 1978 Code of practice for plain and 3400 (Part 2) : Methods of test for vulcanized
reinforced concrete ( third 1980 rubbers : Part 2 Hardness
revision ) ( first revision )
803 : 1976 Code of practice for design,
fabrication and erection of 3400 (Part 14) : Method of test for vulcanized
vertical mild steel cylindrical 1984 rubbers : Part 14 Adhesion of
welded oil storage tanks ( first rubber to metal ( first revision )
revision )
1876 : 1961 Method for voltage 7503 (Part 1) : Glossary of terms used in
measurement by means of 1988 rubber industry : Part 1
sphere gaps (one sphere Definitions of basic terms ( first
earthed) revision )
2825 : 1969 Code for unfired pressure
vessels 7503 (Part 2) : Glossary of terms used in
1988 rubber industry : Part 2
3370 (Part 1) : Code of practice for concrete Definitions of additives ( first
1965 structures for the storage of revision )
liquids : Part 1 General
requirements 7503 (Part 3) : Glossary of terms used in
3370 (Part 2) : Code of practice for concrete 1988 rubber industry : Part 3
1965 structures for the storage of Definitions relating to
liquids : Part 2 Reinforced properties and testing ( first
concrete structures revision )
3370 (Part 3) : Code of practice for concrete
1967 structures for the storage of 7503 (Part 4) : Glossary of terms used in
liquids : Part 3 Prestressed 1988 rubber industry : Part 4
concrete structures Definitions relating to
3370 (Part 4) : Code of practice for concrete processing ( first revision )
1967 structures for the storage of
liquids : Part 4 Design tables 10500 : 1991 Drinking water ( first revision )

ANNEX B
( Clause 6.2 )

LINING OF USED EQUIPMENT


B-1 Provided that previously used plant and B-2 When it is necessary to replace a rubber
equipment is structurally sound and that it has lining in existing equipment the old lining shall
not been subjected to extensive corrosion, be removed by one of the following methods:
relining is normally possible. It is, however,
particularly important that the lining a) Burning Most rubbers may be removed
contractor should inspect such items and agree by this procedure but it is subject to
that they are in a suitable condition for him to certain disadvantages.
undertake the work.

18
IS 4682 (Part 1) : 1994

1) Metal structures may warp as a removed by application of a mechanical


result of the heat generated. chisel to the rubber/metal interface.
2) Noxious or toxic fumes will be B-3 After removal of the old lining the metal
generated and in the case of ebonites should be prepared in the normal way.
and the essentially non-combustible Inspection to check the vessels mechanical
poly-chloroprene these will be suitability for the duty should, if necessary, be
particularly objectionable and may also carried out at this stage.
constitute a health hazard. B-4 When the old lining has been removed and
inspection has confirmed that the item is
It is essential therefore that care be taken
mechanically sound and in a suitable condition
to ensure that anti-pollution laws are not
infringed by this procedure. for relining, the standard procedures outlined
in this specification should be followed.
b) Heating This is a more acceptable B-4.1 However, if there is any reason to suppose
alternative to burning and involves that there has been any impregnation of the
raising the temperature by externally metal by chemicals, it is sound practice to sweat
heating the equipment so that the bond to the metal in live steam before shot-blasting.
the metal is weakened. The heat process is
followed by mechanical removal of the B-4.2 Where noticeable corrosion has occurred
rubber. relining should be avoided. However, linings
can be applied when the surface to be protected
c) Mechanical Removal The most effective is additionally pretreated, for example by
method in instances where adhesion to the grinding, neutralizing, flame descaling or
metal is still good is to cut through the annealing, but the user should be warned of the
rubber so that it is divided into narrow likely risks entailed in obtaining a satisfactory
strips. These can then be most readily lining.

ANNEX C
( Clause 11.1.2 )
CHARACTERISTICS OF LINING MATERIALS
C-1 GENERAL C-1.5 The temperature range capability of a
C-1.1 Rubbers are elastomeric polymers particular rubber or compound lining will vary
consisting of long chain macromolecules which, depending upon the chemical environment to
on mixing with suitable reactants that form which it is exposed and the composition of the
strong chemical bonds, change from a soft rubber compound.
deformable substance into an elastic material. C-1.6 Soft rubber linings intended specifically
C-1.2 The chemical resistance and physical for conditions which are erosive or abrasive are
properties may vary widely according to the obtainable.
type of rubber, the amount and type of fillers,
C-2 TYPES OF RUBBER AND
processing aids, vulcanizing system and other
additives used. PROPERTIES OF LININGS

C-1.3 When the level of vulcanizing agents C-2.1 The types of linings produced from
used gives a low proportion of cross links then various rubbers are divided into two groups :
soft rubber linings are produced. Certain of the soft and hard. Soft rubber linings normally have
rubbers when saturated with a suitable a hardness range of 40 to 80 IRHD, and hard
vulcanization agent are converted into hard rubber linings and ebonites have a hardness
rubber or ebonites which are characterized by range of 25 to 80 on the Shore D scale.
high tensile strength, low elongation at break C-2.2 Because there are so many factors which
and generally enhanced chemical resistance govern the detailed properties of vulcanized
when compared to soft rubbers based on the rubbers it is not possible when describing
same type of rubber. individual types of rubber to be precise about
C-1.4 Rubber linings are generally designed for the chemical resistance and the temperature
vulcanization at elevated temperatures but range over which they may be used. Therefore
similar rubber linings containing accelerated the information in C-3 and C-4 about the
systems capable of promoting vulcanization at different rubbers is intended for guidance only
ambient temperatures are also available. and for more precise information on particular
Certain rubber linings can be applied in the linings advice should be sought from the
form of prevulcanized sheets or laminates. individual lining contractors.

19
IS 4682 (Part 1) : 1994
C-3 SOFT RUBBER LININGS carboxylated nitrile rubber (XNBR), have
C-3.1 Natural (NR) or Synthetic excellent resistance to swelling by mineral oils
and fuels. Polymers of high acrylonitrile to
Polyisoprene (IR) Rubber
butadiene ratios have the best resistance and
Lining compounds based on polyisoprene also have lower gas permeability. Higher
rubber are resistant to the majority of inorganic butadiene ratios have better low temperature
chemicals with the exception of strong oxidizing properties. The polymers should not be used with
agents. Resistance to organic chemicals is phenols, ketones, strong carboxylated acids,
limited with the rubber being unsuitable for aromatic hydrocarbons and nitrogen derivatives.
use with hydrocarbons, halogenated C-3.6.2 Carboxylated nitrile rubber is normally
hydrocarbons, mineral oils, many vegetable oils used for its outstanding abrasion resistance
and esters. When suitably compounded especially in combination with butadiene rubbers.
polyisoprene can be used over the temperature
range of 30C to +100C. C-3.6.3 Dependent on compounding
techniques, nitrile rubber linings with similar
C-3.2 Styrene-Butadiene Rubber (SBR) physical properties to polyisoprene rubbers can
Co-polymers of styrene-butadiene have be prepared suitable for use within the
properties broadly similar to those of the temperature range 20C to +110C.
polyisoprene rubbers, when compounded for C-3.7 Polybutadiene Rubber (BR)
the same duties.
Polybutadiene rubber is normally used in
C-3.3 Polychloroprene Rubber (CR) combination with polyisoprene or carboxylated
C-3.3.1 Polychloroprenes give lining compounds nitrile rubber to produce linings with superior
with greater resistance to heat, ozone, sunlight abrasion resistance compared to the individual
and many oils compared to polyisoprene rubbers. rubbers and to improve the lower temperature
They should not be used with halogenated properties of nitrile rubber.
hydrocarbons or aromatic hydrocarbons. C-3.8 Chlorosulphonated Polyethylene
C-3.3.2 Selected polymer grades can be used Rubber (CSM)
continuously within the temperature range
20C to +100C depending on the polymer Chlorosulphonated polyethylene rubber is a
crystallinity and compound design. synthetic polymer with excellent resistance to
heat, ozone and oxidizing chemicals. It can be
C-3.4 Butyl Rubber (IIR) compounded for resistance to chemicals such as
C-3.4.1 Butyl rubbers are co-polymers of sodium hypochlorite solutions and high
isobutylene with small proportions of isoprene. concentration sulphuric acid. It has good
Chlorinated or brominated butyl rubbers which resistance to many oils, lubricants and aliphatic
are generally easier to process are also available. hydrocarbons but is unsuitable for use with esters,
C-3.4.2 Lining compounds based on butyl ketones, chlorinated solvents and aromatic
rubbers have very good resistance to heat and hydrocarbons. Chlorosulphonated polyethylene
chemicals including some oxidizing chemicals may be used for linings operation continuously
and have low permeability to gases. They within the temperature range 5C to +105C.
should not be used in the presence of free C-4 HARD RUBBER AND EBONITE
halogens, petroleum oils, hydrocarbons and LININGS
halogenated hydrocarbons.
C-4.1 Hard rubber linings are usually produced
C-3.4.3 When a suitably compounded, linings
by incorporating higher levels of sulphur in the
based on butyl rubbers have a lower water
formulations, compared to those used in soft
absorption than most other rubbers and can be
rubber linings. As the level of sulphur used is
used within the temperature range 30C
increased the percentage of the residual
to +120C.
unsaturation in the polymer decreases thus
C-3.5 Ethylene Propylene Rubbers (EPR producing a harder lining. When highly
or EPDM) unsaturated rubbers are used with sulphur
C-3.5.1 Ethylene propylene rubbers are levels between 25 and 50 parts by weight per 100
available as the co-polymer (EPR) or the parts by weight of rubber then hard vulcanites,
ter-polymer (EPDM). Lining compounds based commonly called ebonites, are formed. These
on these polymers have a very good resistance ebonites can be produced from natural or
to acids, alkalis, salts, ozone and many organic synthetic polyisoprenes, styrene-butadiene,
chemicals but are not resistant to oils, acrylonitrile-butadiene and polybutadiene
hydrocarbons and chlorinated solvents. rubbers and blends of those rubbers.
C-3.5.2 The polymers may be compounded for use C-4.1.1 Some hard rubbers are produced with
within the temperature range 30C to +110C. relatively low sulphur levels by the incorporation
of various resins. When it is necessary to create
C-3.6 Nitrile Rubbers (NBR and XNBR)
flexible or impact-resistant ebonites then
C-3.6.1 Acrylonitrile butadiene co-polymer polymers with a limited liability to harden when
(nitrile rubber NBR) and its variant, vulcanized are added to formulations.
20
IS 4682 (Part 1) : 1994

C-4.2 Hard rubbers and ebonites generally have a low elongation at break of 2 percent to
have a higher resistance to chemicals than soft 10 percent. Hence they are brittle compared to
rubbers based on the same polymer types. This soft rubber lining materials at ambient
resistance again generally increases with temperatures. This brittleness can be reduced
decrease in unsaturation of the vulcanized by using flexibilizing additives. Ebonites are
polymer. Resistance to chlorine gas and most thermoplastic materials.
aliphatic carboxylic acids is particularly C-4.3.1 Ebonites are normally used within the
improved. temperature range 0C to 100C. For lower
operating temperatures, ebonites modified with
C-4.3 Due to the increase in saturation when flexibilizers or non-ebonite hard rubbers are
high levels of sulphur are used ebonites usually often used.

ANNEX D
( Clause 11.1.4 )
EFFECT OF MATERIALS ON WATER QUALITY
D-1 When used under the conditions for which D-2 Concentrations of substances, chemicals
they are designed, materials in contact with or and biological agents leached from materials in
likely to come into contact with potable water contact with potable water, and measurements
shall not constitute a toxic hazard, shall not of the relevant organoleptic/physical
support microbial growth and shall not give parameters shall not exceed the maximum
rise to unpleasant taste or odour, cloudiness or values as given in IS 10500 : 1991.
discoloration of the water.

ANNEX E
( Clause 17.1.1 )
VULCANIZATION
E-1 Rubbers are made up of long chain depends upon the thickness of the lining, its
molecules. Within these molecules chemically formulation and the mass of the substrate.
active sites exist by means of which the chains
can be interlinked. This process is known as E-6 Containers and equipment which because
vulcanization and the most common of transport difficulties or because of their
vulcanizing agent is sulphur. dimensions cannot be vulcanized in and
E-2 Vulcanization is effected either by means of autoclave, are lined and vulcanized on site.
heat and pressure or by the application of heat Under such circumstances self-vulcanizing
alone (i.e. without pressure) or in the case of rubber formulations or prevulcanized rubber
self-vulcanizing rubber compounds by allowing sheets may be used, but where these are not
a sufficient period of time to elapse at ambient considered to be suitable the following methods
temperature. of effecting vulcanization are available:
E-3 Depending on the type of elastomer and a) Pressure vessles or others capable of
formulation used elastic compositions of withstanding pressure are normally
varying hardness may be obtained. If sufficient vulcanized by the injection of saturated
sulphur to substantially saturate the sites steam under pressure.
available for cross linking is added then
ebonites are formed. These are very hard b) Non-pressure vessels may be vulcanized
thermoplastic materials. with hot water, hot air or low pressure
steam. When vulcanizing with low
E-4 When heat is necessary to promote pressure steam, sudden changes of
vulcanization and the size of the metal pressure should be avoided.
equipment permits, the use of an autoclave is to
be preferred. Saturated steam or hot air E-7 When vulcanizing on site, insulation or
normally within the temperature range 125C covering of the vessel is recommended,
to 160C are usually employed as heat-transfer particularly in the event of low ambient
agents and the pressure can be up to 4.2 bar. temperatures. It should be noted that
E-5 After loading the equipment to be vulcanization times of one or more days will be
vulcanized the autoclave is heated under required when the application of steam
pressure to the vulcanizing temperature. The pressure is not possible. For self-vulcanizing
rate of beating to the vulcanizing temperature compounds, vulcanization time may extend to
and the time for which the latter is maintained several weeks at ambient temperature.

21
IS 4682 (Part 1) : 1994

E-8 It should be noted that the shelf life of the refrigerated transport and storage of the sheet
unvulcanized sheet will be shorter in the case may be necessary. In the case of prevulcanized
of rapidly vulcanizing rubbers, self-vulcanizing rubber sheet refrigerated transport and storage
compounds having the shortest storage lives. are not necessary, but it should be protected
When high ambient temperatures are expected, from direct sunlight.

ANNEX F
( Clause 20.2.2 )
METHOD OF TEST FOR CONTINUITY TESTING
F-1 INTRODUCTION F-2.2.2 It is essential for proper testing that
spark length exceeds the length of any scarfed
F-1.1 It is essential that linings provide joint which a particular lining may contain. A
adequate protection to equipment under the practical and useful method of adjusting an
conditions for which they are designed. instrument to the correct voltage for testing a
Therefore, there is a requirement that a lining lining is by one of the following methods :
is continuous, i.e. free from pinholes and a) If possible place the probe(s) to be used for
cracks; tests which prove the continuity of the the inspection on top of the rubber in a
lining are necessary. part of the equipment where metal is
F-1.2 The approach to continuity testing is to exposed, e.g. a flange face with an unlined
consider the lining as an electrical insulator bolt hole. The distance between the
and search for holes by trying to make probe(s) and the exposed metal should be
electrical contact to the substrate through the 2 mm to 3 mm longer than the scarf joint
lining. There are two possible methods of length. With the probe(s) in this position
searching : adjust the voltage until the spark just
bridges the gap.
a) Spark testing in which a discharge from a b) Where there is not a convenient position
high frequency source or a direct current where the metal of the equipment is
spark is used to find the fault; exposed then a similar procedure to (a)
b) Wet sponge testing which consists of a wet should be employed using a steel plate
sponge soaked in an electrolyte as one placed on top of the rubber at the correct
probe of a low voltage circuit, the other distance away from the probe(s). The
being the earth return. thickness of the plate should be 3 mm and
the size at least 75 mm 150 mm. All
F-2 SPARK TESTING edges and corners should have a radius of
approximately 3 mm.
F-2.1 Test Equipment c) There may be occasions when the lining
and covering to a tube have to be tested
There are two types of spark testing equipment and there is no metal exposed. In this case
in general use. The mode of operation of the two the setting up procedure should be similar
types is quite different. These are : to (b) but using a piece of metal (rod or
a) High frequency with an a.c. source; and tube) inside the lined tube. The actual size
and shape of this piece of metal should be
b) Direct current (high voltage). agreed when the details of the inspection
procedure are discussed. The radius of
F-2.2 High Frequency Test Equipment curvature of the ends of the rod or tube
should be approximately 3 mm.
F-2.2.1 In these instruments a Tesla coil is
used to generate a high frequency discharge. F-2.2.3 These methods of adjusting the test
Models are available which operate on supply voltage have the advantage that loss of power
voltages of 240 V, 110 V or 50 V. The voltages of the discharge through the body of the rubber
at which they discharge can be varied between is taken into account.
5 000 V and 50 000 V. Normally output is F-2.2.4 These instruments have a single
controlled but the actual output cannot be electrode. The form of the electrode should be
recorded on a meter. However, it is possible to chosen bearing in mind the size and contour of
measure the voltage for any set position of the the surface to be tested. In the case of small
control by the method laid down in IS 1876 : areas with a complex contour a short, straight,
1961 namely measuring the gap the spark will pointed probe may be appropriate. When a
jump between 20 mm diameter spheres. The large area such as a tank lining is to be
voltage of the discharge does vary but the peak surveyed it is useful to use an L-shaped
voltage for any setting of the instrument will electrode. The length of the leg which is used to
not be exceeded. cover surface of the rubber should not exceed
22
IS 4682 (Part 1) : 1994

150 mm. In the case of linings to pipes, the end frequency spark tester and the voltage shall be
of the electrode should be shaped to fit loosely adjusted to that agreed under 4.1 (xxi).
the inside circumference of the pipe. The rods NOTE Normally the spark length should not be less
leading down the probe have to be insulated. than 32 mm when applied across the surface of the
F-2.2.5 When the electrode is held on, or close to rubber. Very thin linings or linings where the rubber
has a high conductivity may require the test to be
an insulating material there is a corona modified.
discharge. When an insulating material
containing a fault is covering a substrate which F-3.2 The testing of linings shall be done in a
is conducting then the discharge concentrates at systematic way. The surface of all but small
that point and the fault is located. Some rubbers equipment shall be divided up by chalk line or
are compounded so that they have a much lower other suitable marks into smaller areas of
resistivity than those in common use. These about 1 m2.
rubbers are sometimes referred to as conducting NOTE By these means it is possible to check that the
rubber. When a high frequency spark test is whole of the lining has been examined.
applied to such rubbers the nature of the
discharge is different and will concentrate in F-3.3 Before testing begins the surface shall be
such a way that it may be thought that the made dry and free from dirt.
rubber contains faults. A very experienced F-3.4 The probe shall be moved continuously
operator can detect the difference, but over the surface of the lining at a speed not
nevertheless the use of such rubbers for lining exceeding 100 mm/s. Applying the spark to one
equipment intended for corrosive duties is not spot for any appreciable length of time shall be
recommended because of the difficulty in testing. avoided.
F-2.2.6 Tests have shown that the risk of
damage to most rubber linings by high F-3.5 When a defect in the lining is discovered
frequency spark testing is remote if the time it shall be clearly marked.
the probe is allowed to dwell on any place is
short. F-3.6 If it is necessary to carry out any
machining of hard rubber or ebonite linings,
F-2.2.7 Breakdown of most linings by spark the spark test shall be applied again to the
testing is by erosion until a critical thickness is lining to ensure that it has not been damaged
reached. During the time that the surfaces in any way.
exposed to a spark in test conditions the
material lost by spark erosion is negligible. F-3.7 It is essential that inspectors have an
However there are some rubbers which, understanding of how the instruments work
because of the way they are compounded can be and the need to survey the linings in controlled
damaged by the spark concentrating through to fashion.
the carbon black, causing local burning of the
rubber. Adequate testing of such linings is not F-3.8 Because of the need to ensure that
possible and they should not be used for continuity testing is carried out to the required
equipment intended for a corrosive duty. standard it is preferable that the test work is
done by a person other than the operator(s) who
F-2.3 Direct Current Spark Testers applied the lining.
F-2.3.1 This type of instrument may be
powered by mains or a rechargeable battery. F-3.9 The rectification of faults discovered
The output voltage varies with the make but a before vulcanization shall be a normal part of
common range is 1 000 V to 20 000 V. Most the lining procedure.
instruments do have a voltage control and a
built-in voltmeter and this is the model F-4 WET SPONGE TESTING
recommended for use. In the case of rubber linings which are
F-2.3.2 With DC instruments it is necessary to normally at least 3 mm thick and may contain
have an earth return. Unlike the high scarf joints to 32 mm in length wet sponge
frequency instrument there is only a discharge testing is not recommended. This is because the
when the electrode is close enough to a defect time that may be required for the electrolyte to
for the DC spark to bridge the gap to earth. The penetrate the hole in the rubber, or a leak in a
length of that gap is limited and is generally joint may be rather long. By the time the
less than the length of the scarfed joints used in electrolyte reaches the substrate the probe may
lining and therefore this type of instrument is no longer be in a position to complete the
unsuitable for testing rubber lining. circuit. Furthermore, in some cases when the
rubber contains a cut it is possible the
F-3 TESTING electrolyte will not penetrate that cut under the
F-3.1 The equipment used shall be an a.c. high conditions of test.

23
( Continued from second cover )

This Indian Standard was first published in 1968. This revision of the standard has been brought
out to incorporate the latest developments that have taken place in the country in the lining of
process vessels and other equipments used in the field of chemical processes. Important
modifications done in this standard being:
i) Information to be exchanged between the two parties more elaborated;
ii) More lining materials, such as, polybutadiene rubbers (BR), developed recently, have been
covered;
iii) Many more methods of vulcanization like autoclave vulcanization, included;
iv) More information provided on spark testing;
v) Requirements of storage, handling transportation and installation of the lined equipment
included; and
vi) Guidelines given for lining of old equipment.
The use of linings of rubber and rubber like materials as a protection against corrosion has been
the normal industrial practice for nearly half a century. A bond is developed between the applied
lining and the metal and any attempt to pull them apart will normally result in the lining tearing
before the bond yields. Thus the lined vessels are quite suitable for use either under vacuum
conditions or under pressure conditions. While it is normal to use the lining on a metal surface,
non-metallic surfaces like wood and concrete are also often lined.
The linings referred to in this standard, which are based on natural and synthetic rubbers, are
used for a number of different duties including protection against corrosion environments and
prevention of contamination of products. Specific linings are used for protection against abrasion
or erosion.
This standard is issued in several parts. The other parts of the standard are:
IS No. Title
4682 (Part 2) : 1969 Code of practice for lining of vessels and equipment for chemical
processes : Part 2 Glass enamel lining
(Part 3) : 1969 Part 3 Lead lining
(Part 4) : 1969 Part 4 Plasticised PVC lining
(Part 5) : 1970 Part 5 Epoxide resin lining
(Part 6) : 1970 Part 6 Phenolic resin lining
(Part 7) : 1974 Part 7 Corrosion and heat resistant metals
(Part 8) : 1974 Part 8 Precious metal
(Part 9) : 1974 Part 9 Titanium
(Part 10) : 1974 Part 10 Brick and tile
In the preparation of this standard, assistance has been derived from BS 6374 (Part 5) : 1985
Lining of equipment with polymeric materials for the process industries : Part 5 Specification for
lining with rubbers, issued by the British Standards Institution.
Linings may be applied either by brushing, spraying or applied in the form of a sheet. This
standard covers only the rubber linings applied in the sheet form.
This edition 2.1 incorporates Amendment No. 1 (August 1996). Side bar indicates modification of
the text as the result of incorporation of the amendment.
For the purpose of deciding whether a particular requirement of this standard is complied with,
the final value, observed or calculated, expressing the result of a test or analysis, shall be rounded
off in accordance with IS 2 : 1960 Rules for rounding off numerical values ( revised ). The number
of significant places retained in the rounded off value should be the same as that of the specified
value in this standard.
Bureau of Indian Standards
BIS is a statutory institution established under the Bureau of Indian Standards Act, 1986 to promote
harmonious development of the activities of standardization, marking and quality certification of goods and
attending to connected matters in the country.

Copyright
BIS has the copyright of all its publications. No part of these publications may be reproduced in any form
without the prior permission in writing of BIS. This does not preclude the free use, in the course of
implementing the standard, of necessary details, such as symbols and sizes, type or grade designations.
Enquiries relating to copyright be addressed to the Director (Publications), BIS.

Review of Indian Standards


Amendments are issued to standards as the need arises on the basis of comments. Standards are also
reviewed periodically; a standard along with amendments is reaffirmed when such review indicates that no
changes are needed; if the review indicates that changes are needed, it is taken up for revision. Users of
Indian Standards should ascertain that they are in possession of the latest amendments or edition by
referring to the latest issue of BIS Catalogue and Standards : Monthly Additions.
This Indian Standard has been developed from Doc : No. HMD 17 (0270).

Amendments Issued Since Publication


Amend No. Date of Issue
Amd. No. 1 August 1996

BUREAU OF INDIAN STANDARDS


Headquarters:
Manak Bhavan, 9 Bahadur Shah Zafar Marg, New Delhi 110002. Telegrams: Manaksanstha
Telephones: 323 01 31, 323 33 75, 323 94 02 (Common to all offices)
Regional Offices: Telephone
Central : Manak Bhavan, 9 Bahadur Shah Zafar Marg 323 76 17

NEW DELHI 110002 323 38 41
Eastern : 1/14 C. I. T. Scheme VII M, V. I. P. Road, Kankurgachi 337 84 99, 337 85 61

KOLKATA 700054 337 86 26, 337 91 20
Northern : SCO 335-336, Sector 34-A, CHANDIGARH 160022 60 38 43

60 20 25
Southern : C. I. T. Campus, IV Cross Road, CHENNAI 600113 235 02 16, 235 04 42

235 15 19, 235 23 15
Western : Manakalaya, E9 MIDC, Marol, Andheri (East) 832 92 95, 832 78 58

MUMBAI 400093 832 78 91, 832 78 92
Branches : A H M E D A B A D . B A N G A L O R E . B H O P A L . B H U B A N E S H W A R . C O I M B A T O R E .
FARIDABAD. GHAZIABAD. GUWAHATI. HYDERABAD. JAIPUR. KANPUR.
LUCKNOW. NAGPUR. NALAGARH. PATNA. PUNE. RAJKOT. THIRUVANANTHAPURAM.
VISHAKHAPATNAM.

Potrebbero piacerti anche