Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
NAME:
REGISTRATION NO.:
o A. Phases
o B. Milestones
o C. Estimates
o D. Activities
2. Which of the following is not a key stakeholder in a project that creates a service internal to an
organization?
o B. External customers
o C. Project vendors
3. Of the following management skills, which will a project manager use most?
o A. Leading
o B. Communicating
o D. Negotiating
4. What are the Five Project Management Process Group in order?
5. You are a Project Manager currently. You have finalized the list of Stakeholders, Which
Process Group you are working in?
o A. Planning
o B. Executing
o D. Initiating
o A. Initiating
o B. Planning
o C. Executing
8. Which Process Group contains the Develop Project Charter Process and Identify Stake
Holders
o A. Initiating
o B. Executing
o D. Planning
o A. Initiating
o B. Planning
o C. Executing
o E. Closing
10. You are a Project Manager on a Highway Construction Project. You are now determining if
there are changes to the scope, schedule, budget of the project. These assignments are part of
which process
o A. Initiating
o B. Planning
o C. Executing
ANSWER
1. A
2. C
3. B
4. D
5. D
6. A
7. C
8. A
9. B
10. D
11. B
12. A
13. B
14. C
15. A
16. C
17. A
18. A
19. A
20. B