Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
of Steel Ships
NR 467
This document is an electronic consolidated edition of the Rules for the Classification of Steel Ships,
edition July 2014 with Amendments January 2016.
This document is for documentation only. The following published Rules and Amendments are the
reference text for classification:
Part A
Classification and Surveys
Chapters 1 2 3 4 5 6
7 Other notations 65
7.1
Appendix 2 CSM and PMS Systems: Surveys Carried out by the Chief Engineer
1 Conditions 98
1.1
2 Limits of the interventions 98
2.1
3 Procedure for carrying out surveys 98
3.1 General
3.2 Main diesel engines
3.3 Auxiliary diesel engines
3.4 Reciprocating compressors
3.5 Coolers, condensers, heaters
3.6 Electrical switchboard
3.7 a.c. and d.c. generators
3.8 Other items (pumps, electric motors, etc.)
4 Records of surveys carried out 99
4.1
5 Confirmatory survey 99
5.1
6 Suspension of the Chief Engineers authorization 100
6.1
Section 1 General
1 General 171
1.1
2 Service notations subject to additional surveys 171
2.1
1 General 254
1.1
Section 1 General
1 General 259
1.1
2 Additional class notations subject to additional surveys 259
2.1
Section 1 General
1 General 285
1.1
1.2 List of retroactive rule requirements
Chapter 1
PRINCIPLES OF CLASSIFICATION
AND CLASS NOTATIONS
If a contract for construction is later amended to include During periods of construction, modification or repair, the
additional ships or additional options, the date of contract unit is solely under the responsibility of the builder or the
for construction for such ships is the date on which the repair yard. As an example, the builder or repair yard is to
amendment to the contract is signed between the Owner ensure that the construction, modification or repair activi-
and the Shipbuilder. The amendment to the contract is to be ties are compatible with the design strength of the ship and
considered as a new contract to which the above applies. that no permanent deformations are sustained.
If a contract for construction is amended to change the ship Note 1: Refer to [3.3] as regards the Owners responsibility for
type, the date of contract for construction of this modified maintenance and operation of the ship in relation to the mainte-
ship or ships, is the date on which the revised contract or nance of class.
new contract is signed between the Owner, or Owners, and
the shipbuilder. 1.3.4 The class assigned to a ship by the Society following
its interventions is embodied in a Certificate of Classifica-
tion and noted in the Register of ships.
1.3 Meaning of classification, scope and At a certain date the class of a ship is maintained or regular
limits when no surveys are overdue, when the conditions for sus-
pension of class are not met and when the class is not with-
1.3.1 The classification process consists of: drawn nor suspended. Otherwise the class is irregular.
Attention is drawn on the fact that a ship holding a valid
the development of Rules, guidance notes and other
Certificate of Classification may be in an irregular class
documents relevant to the ship, structure, material,
position.
equipment, machinery and other items covered by such
documents
1.4 Request for services
the review of plans and calculations and the surveys,
checks and tests intended to demonstrate that the ship
1.4.1 Requests for interventions by the Society, such as sur-
meets the Rules (refer to Ch 2, Sec 1)
veys during construction, surveys of ships in service, tests,
the assignment of class (see Ch 2, Sec 1) and issue of a etc., are in principle to be submitted in writing and signed
Certificate of Classification, where compliance with the by the Interested Party. Such request implies that the appli-
above Rules is found cant will abide by all the relevant requirements of the Rules,
the periodical, occasional and class renewal surveys including the Marine & Offshore Division General Condi-
performed to record that the ship in service meets the tions.
conditions for maintenance of class (see Ch 2, Sec 2). The Society reserves the right to refuse or withdraw the class
of any ship for which any applicable requirement of the
1.3.2 The Rules, surveys performed, reports, certificates Rules is not complied with.
and other documents issued by the Society, are in no way
intended to replace or alleviate the duties and responsibili-
1.5 Register of ships
ties of other parties such as Administrations, Designers,
Shipbuilders, Manufacturers, Repairers, Suppliers, Contrac-
tors or Sub-contractors, actual or prospective Owners or 1.5.1 A Register of Ships is published periodically by the
Operators, Charterers, Brokers, Cargo-owners and Under- Society. This publication, which is updated by the Society,
writers. contains the names of ships which have received the Certif-
icate of Classification, as well as particulars of the class
The activities of such parties which fall outside the scope of assigned and information concerning each ship.
the classification as set out in the Rules, such as design,
engineering, manufacturing, operating alternatives, choice
of type and power of machinery and equipment, number 2 Rules
and qualification of crew or operating personnel, lines of
the ship, trim, hull vibrations, spare parts including their
2.1 Effective date
number, location and fastening arrangements, life-saving
appliances, and maintenance equipment, remain therefore
the responsibility of those parties, even if these matters may 2.1.1 The effective date of entry into force of any amend-
be given consideration for classification according to the ments to the Rules is indicated on the inside front page of
type of ship or additional class notation assigned. the Rules or in the relevant Section.
1.3.3 Unless otherwise specified, the Rules do not deal 2.1.2 In principle, the applicable Rules for assignment of
with structures, pressure vessels, machinery and equipment class to a new ship are those in force at the date of contract
which are not permanently installed and used solely for for construction.
operational activities such as dredging or heavy load lifting,
workshops or welding equipment, except for their effect on 2.1.3 Special consideration may be given to applying new
the classification-related matters, as declared by the Inter- or modified rule requirements which entered into force sub-
ested Party, such as fire protection and ships general sequent to the date of contract for construction, at the dis-
strength. cretion of the Society and in the following cases:
when a justified written request is received from the Free access is also to be given to auditors accompanying the
party applying for classification Surveyors of the Society within the scope of the audits as
when the keel is not yet laid and more than one year has required in pursuance of the Societys internal Quality Sys-
elapsed since the contract for construction was signed tem or as required by external organizations.
where it is intended to use existing previously approved
3.2.2 Interested Parties are to take the necessary measures
plans for a new contract.
for the Surveyors inspections and testing to be carried out
2.1.4 The above procedures for application of the Rules safely. Interested Parties - irrespective of the nature of the
are, in principle, also applicable to existing ships in the case service provided by the Surveyors of the Society or others
of major conversions and, in the case of alterations, to the acting on its behalf - assume with respect to such Surveyors
all the responsibility of an employer for his workforce such
altered parts of the ship.
as to meet the provisions of applicable legislation. As a rule,
2.1.5 The rule requirements related to assignment, mainte- the Surveyor is to be constantly accompanied during sur-
nance and withdrawal of the class of ships already in opera- veys by personnel of the Interested Party.
tion, as detailed in Part A, Chapter 2 to Part A, Chapter 5, Interested Parties are to inform promptly the Surveyor of
are applicable from the date of their entry into force. defects or problems in relation to class.
Refer also to Ch 2, Sec 2, [2.5] to Ch 2, Sec 2, [2.9].
2.2 Equivalence
3.2.3 The Certificate of Classification and/or other docu-
2.2.1 The Society may consider the acceptance of alterna- ments issued by the Society remain the property of the Soci-
tives to these Rules, provided that they are deemed to be ety. All certificates and documents necessary to the
equivalent to the Rules to the satisfaction to the Society. Surveyors interventions are to be made available by the
Interested Party to the Surveyor on request.
2.3 Novel features
3.2.4 During the phases of ship design and construction,
2.3.1 The Society may consider the classification of ships due consideration should be given to rule requirements in
based on or applying novel design principles or features, to respect of all necessary arrangements for access to spaces
which the Rules are not directly applicable, on the basis of and structures with a view to carrying out class surveys.
experiments, calculations or other supporting information Arrangements of a special nature are to be brought to the
provided to the Society. Specific limitations may then be attention of the Society.
indicated on a memoranda.
3.2 Surveyors intervention 3.3.3 Any document issued by the Society in relation to its
interventions reflects the condition of the ship as found at
3.2.1 Surveyors are to be given free access at all times to the time and within the scope of the survey. It is the Inter-
ships which are classed or being classed, shipyards and ested Partys responsibility to ensure proper maintenance of
works, to carry out their interventions within the scope of the ship until the next survey required by the Rules. It is the
assignment or maintenance of class, or within the scope of duty of the Interested Party to inform the Surveyor when he
interventions carried out on behalf of Administrations, boards the ship of any events or circumstances affecting the
when so delegated. class.
3.4 Flag and Port State Control inspections 3.6.2 As spare parts are outside the scope of classification,
the Surveyor will not check that they are kept on board,
3.4.1 Where defects are found further to an inspection by maintained in a satisfactory condition, or suitably protected
an Administration in pursuance of Port State Control or sim- and lashed.
ilar programmes, Owners are to: However, in the case of repairs or replacement, the spare
immediately report the outcome of this inspection to the parts used are to meet the requirements of the Rules as far
Society, and as practicable; refer to Ch 2, Sec 2, [6.4.2].
ask the Society to perform an occasional survey in order
to verify that the deficiencies, when related to the class 3.7 Quality system audits
of the ship or to the statutory certificates issued by the
Society on behalf of the flag Administration, are recti- 3.7.1 Attention is drawn to the possibility that auditors
fied and/or the necessary repair work is carried out external to the Society may attend surveys and audits car-
within the due time. ried out by the Society and that this attendance shall not be
obstructed.
3.5 Use of measuring equipment and of
service suppliers 4 Application of statutory requirements
3.5.1 General by the Society
Firms providing services on behalf of the Interested Party,
such as measurements, tests and servicing of safety systems 4.1 International and national regulations
and equipment, the results of which may form the basis for
the Surveyors decisions, are subject to the acceptance of 4.1.1 Where requirements of International Conventions,
the Society, as deemed necessary. such as SOLAS, ILLC, MARPOL, ILO or of IMO Assembly
The equipment used during tests and inspections in work- Resolutions, are quoted as excerpts, they are printed in italic
shops, shipyards and on board ships, the results of which type replacing the word Administration with Society.
may form the basis for the Surveyors decisions, is to be cus- These requirements are quoted for ease of reference.
tomary for the checks to be performed. Firms are to individ-
ually identify and calibrate to a national or international 4.1.2 When authorised by the Administration concerned,
standard each piece of such equipment. the Society will act on its behalf within the limits of such
Note 1: Refer to Rule Note NR 533 Approval of Service Suppliers. authorisation. In this respect, the Society will take into
account the relevant national requirements, survey the ship,
3.5.2 Simple measuring equipment report and issue or contribute to the issue of the corre-
The Surveyor may accept simple measuring equipment (e.g. sponding certificates.
rulers, tape measures, weld gauges, micrometers) without The above surveys do not fall within the scope of the classi-
individual identification or confirmation of calibration, pro- fication of ships, even though their scope may overlap in
vided it is of standard commercial design, properly main- part and may be carried out concurrently with surveys for
tained and periodically compared with other similar assignment or maintenance of class.
equipment or test pieces.
4.1.3 In the case of a discrepancy between the provisions
3.5.3 Shipboard measuring equipment of the applicable international and national regulations and
The Surveyor may accept measuring equipment fitted on those of the Rules, normally, the former take precedence.
board a ship (e.g. pressure, temperature or rpm gauges and However, the Society reserves the right to call for the neces-
meters) and used in examination of shipboard machinery sary adaptation to preserve the intention of the Rules or to
and/or equipment based either on calibration records or apply the provisions of [1.4.1].
comparison of readings with multiple instruments.
4.1.4 In statutory matters, when authorized by the Adminis-
3.6 Spare parts tration concerned and acting on its behalf, the Society
applies the available IACS Unified Interpretations (UIs),
3.6.1 It is the Owners responsibility to decide whether and unless provided with written instruction to apply a different
which spare parts are to be carried on board. interpretation by the flag Administration.
2 Class symbol
1.1.2 The classification notations assigned to a ship are
indicated on the Certificate of Classification, as well as in
the Register of Ships published by the Society. 2.1 General
1.1.3 The classification notations assigned to ships and 2.1.1 The class symbol expresses the degree of compliance
units, other than those covered in Parts B, C, D and E, which of the ship with the rule requirements as regards its con-
are to comply with specific Rules published by the Society struction and maintenance. There is one class symbol,
are given in Ch 1, App 1. which is compulsory for every classed ship.
a) class symbol
2.1.3 The class symbol II is assigned to ships which do not
b) construction marks meet all requirements for class symbol I, but are deemed
acceptable to be entered into the Register of Ships.
c) service notations with additional service features, as
applicable The period of class assigned to class symbol II ships is max-
imum 3 years, see Ch 2, Sec 2, [4].
d) navigation notations
e) operating area notations (optional) 2.1.4 Except for special cases, class is assigned to a ship
only when the hull, propulsion and auxiliary machinery
f) additional class notations (optional)
installations, and equipment providing essential services
The different classification notations and their conditions of have all been reviewed in relation to the requirements of
assignment are listed in [2] to [6], according to their types. the Rules.
3.2.1 The mark { is assigned to the relevant part of the 4.1.4 A service notation may be completed by one or more
ship, when it has been surveyed by the Society during its additional service features, giving further precision regard-
construction in compliance with the new building proce- ing the type of service of the ship, for which specific rule
dure detailed in Ch 2, Sec 1, [2.1], or when it is changing requirements are applied.
class from an IACS Society at ship's delivery or when class
is being added to an IACS Society's class at ship's delivery 4.1.5 The different service notations which may be
in accordance with specific procedures. assigned to a ship are listed in [4.2] to [4.16], according to
the category to which they belong. These service notations
are also listed in alphabetical order in Tab 1, where the cor-
respondence between the service notation assigned by the
3.2.2 The mark [ is assigned to the relevant part of the
Society and the type of ship defined by the International
ship, when the latter is classed after construction in compli-
Conventions is also given for information.
ance with the procedure detailed in Ch 2, Sec 1, [3.2] and it
is changing class from an IACS Society at the time of the As a rule, all notations in [4.2], [4.3], [4.4] and [4.5] are
only to be assigned to self-propelled units.
admission to class.
4.2.2 General cargo ship, for ships intended to carry gen- 4.2.5 Container ship, for ships specially intended to carry
eral cargo. containers in holds or on decks. The additional require-
ments of Ch 4, Sec 8, [2] and Part D, Chapter 2 are applica-
The service notation may be completed by the following ble to these ships.
additional service feature, as applicable: For container ships complying with the requirements of
NR583 Whipping and Springing Assessment, the service
equipped for carriage of containers, where the ships
notation is to be completed by the additional service fea-
fixed arrangements comply with the applicable rule tures WhiSp1 or WhiSp2.
requirements in Part D, Chapter 2
4.2.6 Livestock carrier, for ships specially intended to carry
heavycargo [AREA1, X1 kN/m2 - AREA2, X2 kN/m2 - ...],
livestock. The additional requirements of Ch 4, Sec 8, [3]
when the double bottom and/or hatch covers and/or and Part D, Chapter 3 are applicable to these ships.
other cargo areas designed to support heavy cargoes fulfil
the appropriate rule requirements. The values Xi indicate 4.2.7 Deck ship, for ships specially intended to carry cargo
the maximum allowable local pressures on the various exclusively on the deck.
zones AREAi where the cargo is intended to be stowed. Note 1: A ship with service notation deck ship is usually but not nec-
The requirements for the assignment of this additional essarily a self-propelled unit intended for unrestricted navigation.
The service notation bulk carrier ESP is always completed Note 1: Hybrid bulk carriers, where at least one cargo hold is con-
by one of the following additional service features, for bulk structed with hopper tank and topside tank, are covered by NR522.
The structural strength of members in holds constructed without
carriers of length greater than or equal to 150 m contracted
hopper tank and/or topside tank is to comply with the strength cri-
for new construction on or after 1 July 2003: teria defined in NR522.
BC-A, for bulk carriers designed to carry dry bulk car- Bulk carriers assigned with the additional service feature
goes of density 1.0 t/m3 and above with specified holds CSR and with holds designed for loading/unloading by
empty at maximum draught in addition to BC-B condi- grabs having a maximum specific weight up to [x] tons are
tions assigned the notation GRAB [X] according to NR522 (Com-
mon Structural Rules for Bulk Carriers), Ch 1, Sec 1, [3.2.1].
BC-B, for bulk carriers designed to carry dry bulk car- The requirements for GRAB [X] notation are given in
goes of density 1.0 t/m3 and above with all cargo holds NR522, Ch 12, Sec 1.
loaded in addition to BC-C conditions For bulk carriers assigned with the additional service feature
CSR, and one of the additional service features BC-A or BC-B,
BC-C, for bulk carriers designed to carry dry bulk car-
these additional service features are always completed by the
goes of density less than 1.0 t/m3. additional service feature GRAB [X]. For these ships, the
requirements for the GRAB [X] notation are to be complied
The additional service feature BC-A is completed with the with for an unladen grab weight X equal to or greater than
indication of the allowed combination of specified empty 20 tons.
holds, as follows: (holds a, b, .., ... may be empty).
For bulk carriers assigned with the additional service feature
If limitations are to be observed during operation: CSR others than above, the additional class notation
GRAB [X] may be assigned on a voluntary basis (refer to
the additional service features BC-A and BC-B are com- [6.13.2], item a)).
pleted, when the maximum cargo density is less than
Bulk carriers assigned with the additional service feature
3.0 t/m3, with the indication of the maximum density of
CSR are to comply with the requirements for maintenance
cargo that the ship is allowed to carry, as follows: of class, thickness measurements and acceptance criteria
(maximum cargo density x.y t/m3) given in NR522, Chapter 13.
the additional service features BC-A, BC-B and BC-C are For bulk carriers assigned with the additional service feature
completed by the following indication when the vessel CSR and contracted for construction on or after 8 Decem-
has not been designed for loading and unloading in ber 2006, this additional service feature is always com-
multiple ports: (no MP). pleted by the additional service feature CPS(WBT) for
which the rule requirements of NR530 Coating Performance
Examples: Standard, applicable to ships complying with the require-
ments of the Common Structural Rules for Bulk Carriers or
Bulk carrier BC-A (maximum cargo density 2.5 t/m3; holds the Common Structural Rules for Double Hull Oil Tankers
2, 4, 6 may be empty) ESP and related to protective coatings in dedicated seawater
ballast tanks of ships of not less than 500 gross tonnage and
Bulk carrier BC-B (maximum cargo density 2.5 t/m3; no double-side skin spaces arranged in bulk carriers of length
MP) ESP greater than or equal to 150 m, are applied.
Bulk carrier BC-C (no MP) ESP Example:
For ships contracted for new construction before 1 July 2003 Bulk carrier CSR CPS(WBT) BC-A (maximum cargo density
or for ships contracted for new construction on or after 2.5 t/m3; holds 2, 4, 6 may be empty) ESP GRAB [20]
1 July 2003 but less than 150 m in length, the service nota- Note 2: Attention is drawn on the coating condition which is sur-
tion bulk carrier ESP may be completed by the additional veyed as per the requirements of Ch 4, Sec 2 for ships in service.
service features heavycargo or nonhomload defined under
Bulk carriers assigned with the additional service feature
[4.2.2].
CSR contracted for new construction on or after 1 July 2015
The service notation bulk carrier ESP is always completed are to comply with the requirements of the Common Struc-
tural Rules for Bulk Carriers and Oil Tankers (Rule Note
by the additional service feature CSR for bulk carriers of
NR606).
length greater than or equal to 90 m contracted for new
construction on or after 1 April 2006. 4.3.3 Ore carrier ESP, for sea going self-propelled ships
which are constructed generally with single deck, two lon-
Bulk carriers assigned with the additional service feature
gitudinal bulkheads and a double bottom throughout the
CSR are to comply with the requirements of the Common cargo length area and intended primarily to carry ore car-
Structural Rules for Bulk Carriers (Rule Note NR522). The goes in the centre holds only. Typical midship sections are
elements not dealt with in NR522 are to comply with the illustrated in Fig 2, or a midship section deemed equivalent
requirements of Part B, Part C and Part D of the Rules for the by the Society. The additional requirements of Part D, Chap-
Classification of Steel Ships. ter 5 are applicable to these ships.
Figure 2 : Typical midship sections of ship Figure 4 : Typical midship sections of ships
with service notation ore carrier ESP with service notation combination carrier/OOC ESP
Figure 3 : Typical midship sections of ship 4.4.1 The service notations related to self-propelled ships
with service notation combination carrier/OBO ESP intended for the carriage of liquid cargo in bulk are listed in
[4.4.2] to [4.4.9].
Figure 5 : Typical midship sections of ships with service notation oil tanker ESP
The service notation oil tanker ESP is always completed by Oil Tanker assigned with the additional service feature CSR
the additional service feature CSR for double hull oil tank- contracted for new construction on or after 1 July 2015 are
ers of length greater than or equal to 150 m and contracted to comply with the requirements of the Common Structural
for new construction on or after 1 April 2006. Rules for Bulk Carriers and Oil Tankers (Rule Note NR606).
Oil tankers assigned with the additional service feature CSR
4.4.3 Asphalt carrier, for sea going self-propelled ships
are to comply with the requirements of the Common Struc-
which are constructed with independent (non-integral)
tural Rules for Double Hull Oil Tankers (Rule Note NR523).
cargo tanks, intended to carry only such type of products,
The elements not dealt with in NR523 are to comply with
under certain conditions. The additional requirements of
the requirements of Part B, Part C and Part D of the Rules for
Part D, Chapter 7 are applicable to these ships.
the Classification of Steel Ships.
The maximum cargo temperature is to be indicated on the
Oil tankers assigned with the additional service feature CSR Certificate of Classification.
are to comply with the requirements for ship in operation
renewal criteria given in NR523, Section 12, related to the
4.4.4 Chemical tanker, for sea going self-propelled ships
allowable thickness diminution for hull structure.
which are constructed generally with integral tanks and
For oil tankers assigned with the additional service feature intended primarily to carry chemicals in bulk. This notation
CSR and contracted for construction on or after 8 Decem- may be assigned to tankers of both single or double hull
ber 2006, this additional service feature is always com- construction, as well as tankers with alternative structural
pleted by the additional service feature CPS(WBT) for arrangements. Typical midship sections are illustrated in Fig
which the rule requirements of NR530 Coating Performance 6, or a midship section deemed equivalent by the Society.
Standard, applicable to ships complying with the require- The additional requirements of Part D, Chapter 8 are appli-
ments of the Common Structural Rules for Bulk Carriers or cable to these ships.
the Common Structural Rules for Double Hull Oil Tankers
The list of products the ship is allowed to carry is attached
and related to protective coatings in dedicated seawater
to the Certificate of Classification or the Certificate of Fit-
ballast tanks of ships of not less than 500 gross tonnage and
ness, where issued by the Society, including, where neces-
double-side skin spaces arranged in bulk carriers of length
sary, the maximum allowable specific gravity and/or
greater than or equal to 150 m, are applied.
temperature.
Example: For ships intended to carry only one type of cargo, the serv-
Oil tanker CSR CPS(WBT) ESP ice notation may be completed by the additional service
feature indicating the type of product carried.
Note 1: Attention is drawn on the coating condition which is sur-
veyed as per the requirements of Ch 4, Sec 3 for ships in service. For ships with integral cargo tanks, the service notation
Note 2: Ships assigned with the service notation oil tanker ESP that chemical tanker is always completed by the additional serv-
do not comply with MARPOL I/19 may be subject to International ice feature ESP (i.e. chemical tanker ESP), which means that
and/or National Regulations requiring phase out under MARPOL these ships are submitted to the Enhanced Survey Pro-
I/20 and/or MARPOL I/21. gramme as laid down in Ch 4, Sec 4.
Figure 6 : Typical midship sections of ships with service notation chemical tanker ESP
Container ship [4.2.5] Part D, Chapter 2 Cargo ship (SOLAS, Reg I/2(g))
WhiSp1 or WhiSp2 Rule Note NR 583
Crew boat [4.15.4] Rule Note NR 490
Deck ship [4.2.7] Cargo ship (SOLAS, Reg I/2(g))
Diving support-integrated [4.14] Rule Note NR 609
Diving support-capable [4.14]
Diving support-portable [4.14]
DD [4.14.3]
SD [4.14.3]
Dredger [4.6.2] Part D, Chapter 13 Cargo ship (SOLAS, Reg I/2(g))
Escort tug [4.7.2] Part D, Chapter 14 Cargo ship (SOLAS, Reg I/2(g))
barge combined Pt D, Ch 14, Sec 3
Fire-fighting ship [4.7.4] Part D, Chapter 16 Cargo ship (SOLAS, Reg I/2(g))
1, 2, 3 or E Pt D, Ch 16, Sec 3
water spraying Pt D, Ch 16, Sec 4
Fishing vessel [4.9.1] Part D, Chapter 20 Fishing vessel (SOLAS, Reg I/2(i)). To be noted that SOLAS
Convention does not apply to such ships
F Pt D, Ch 20, Sec 6
ED European Directive
97/70/EC as amended
TORRE Torremolinos Interna-
tional Convention for
the Safety of Fishing
Vessels as amended
Floating dock [4.7.8] Rule Note NR 475
FLS tanker [4.4.7] Part D, Chapter 7 Tanker (SOLAS, Reg I/2(h))
NLS Tanker (MARPOL, Annex II, Reg 1/16.2), when
flash point > 60C Part D, Chapter 7
noxious liquid substances are loaded
type of cargo (1)
General cargo ship [4.2.2] Cargo ship (SOLAS, Reg I/2(g))
equipped for carriage of containers Part D, Chapter 2
2
heavycargo [AREA1, X1 kN/m - ] Pt B, Ch 5, Sec 6
nonhomload (3) Pt D, Ch 4, Sec 3
occasional dry bulk cargo IMO Res.MSC 277(85)
para. 1.6 and 1.7
Hopper dredger, Hopper unit [4.6.2] Part D, Chapter 13 Cargo ship (SOLAS, Reg I/2(g))
HSC, HSC-CAT A, HSC-CAT B [4.10.1] (6) NR 396 UNITAS High-speed craft (SOLAS, Chapter X), 2000 HSC Code
Icebreaker z [4.12] Rule Note NR 527 z is equal to 1, 2, 3, 4, 5, 6 or 7
Launch, Seagoing launch [4.15.2] Rule Note NR 600 (non-convention ship)
Rule Note NR 566
lifting [4.7.9] Rule Note NR 608
Light ship [4.10.2] (6) Part B & Part C or
NR566, and NR396
UNITAS, Chapter 3 &
Chapter 6
Liquefied gas carrier [4.4.5] Part D, Chapter 9 Tanker (SOLAS, Reg I/2(h))
Gas carrier (SOLAS, Reg II-1/3.20, Reg II-2/3.25, Reg VII
RV Pt D, Ch 9, Sec 1, [5]
/11.2)
STL-SPM Pt D, Ch 9, Sec 1, [6]
Livestock carrier [4.2.6] Part D, Chapter 3 Cargo ship (SOLAS, Reg I/2(g))
LNG bunkering ship [4.4.6] Part D, Chapter 4 Tanker (SOLAS, Reg I/2(h))
Gas carrier (SOLAS, Reg II-1/3.20, Reg II-2/3.25,
RE Part D, Chapter 4
Reg VII /11.2)
Initial-CD Part D, Chapter 4
IG-Supply Part D, Chapter 4
BOG Part D, Chapter 4
Oil recovery ship [4.7.5] Part D, Chapter 17
OILTREAT
SECOND-LINE
Oil tanker [4.4.2] Part D, Chapter 7 Tanker (SOLAS, Reg I/2(h))
Oil tanker (MARPOL Annex I, Reg I/1.5)
ESP Part D, Chapter 7
SOLAS, Reg II-1/2.22
SOLAS, Reg XI-1/2
Tanker [4.4.8] (1) Part D, Chapter 10 Cargo ship (SOLAS, Reg I/2(g))
type of cargo
Tug [4.7.2] Part D, Chapter 14 Cargo ship (SOLAS, Reg I/2(g))
barge combined Pt D, Ch 14, Sec 3
Wind farms service ship - Xi [4.15.7] Guidance Note NI 589
X = S, M or L ; i = 0 , 1 or 2
Wind Turbines IMR Vessel [4.15.6] Rule Note NR 579
Yacht, Charter yacht [4.15.3] Rule Note NR 500
motor or sailing NR 500, Pt A, Ch 1
Sec 2, [1.5.1]
S (9) NR 500, Pt A, Ch 1
Sec 2, [1.5.1]
OTHER ADDITIONAL SERVICE FEATURES Remarks
no propulsion [4.8.3] Part D, Chapter 19 Any non-propelled units other than barge or pontoon
assisted propulsion [4.8.4]
WAP or EAWP [4.8.5] Rule Note NR 206
dualfuel or gasfuel [4.11.1] Rule Note NR 529
ESA [4.13.1] Rule Note NR 592
SPxxx [4.16.1] Pt B, Ch 2, Sec 1,
Pt B, Ch 2, Sec 2,
Pt B, Ch 3, Sec 1,
Pt B, Ch 3, Sec 3,
Pt B, Ch 3, App 2 and
Pt C, Ch 1, Sec 11
(1) For ships intended to carry only one type of cargo.
(2) Additional indications: for BC-A: (holds a, b, .., ... may be empty); for BC-A or BC-B and if x.y 3 t/m3: (maximum
cargo density x.y t/m3); for BC-A, BC-B or BC-C: (no MP) if applicable.
(3) Completed with indication of the different maximum loads allowed in each hold and which holds may be empty, if appropriate.
(4) Mandatory as an additional service feature for bulk carriers CSR BC-A or CSR BC-B.
(5) Mandatory for ships assigned with additional service feature CSR and contracted for construction on or after 8 December 2006.
(6) The type of service may be specified after the service notation, i.e. light ship/fast passenger vessel, light ship/fast cargo vessel,
light ship/fast patrol vessel.
(7) No additional requirements are specified in Part D for this service notation; however requirements of Part E, Chapter 7 for the
assignment of the additional class notation REF-CARGO are to be applied.
(8) These ships are considered on a case by case basis by the Society according to their type of service.
(9) Corresponding to hull made of steel material as per these Rules (NR 467).
(10) Bulk carriers and Oil tankers assigned with the additional service feature CSR contracted for new construction on or after 1 July
2015 are to comply with the requirements of NR 606 Common Structural Rules for Bulk Carriers and Oil Tankers.
4.4.5 Liquefied gas carrier, for ships specially intended to RV, where the ship is fitted with an installation for
carry liquefied gases or other substances listed in Pt D, Ch revaporisation of the liquefied natural gas. The require-
9, Sec 1 of the Rules. The additional requirements of Ch 4, ments for the assignment of this additional service fea-
ture are given in Pt D, Ch 9, Sec 1, [5]
Sec 5 and Part D, Chapter 9 are applicable to these ships.
STL-SPM, where the ship is used as re-gasification termi-
The list of products the ship is allowed to carry is attached nal and fitted forward with equipment for non perma-
to the Certificate of Classification or the Certificate of Fit- nent mooring or single buoy. The requirements for the
ness, where issued by the Society, including, where neces- assignment of this additional service feature are given in
sary, the conditions of transportation (pressure, temperature, Pt D, Ch 9, Sec 1, [6].
filling limits).
Example:
The service notation may be completed by the following Liquefied gas carrier RV STL-SPM
additional service feature, as applicable:
4.4.6 LNG bunkering ship, for ships carrying liquefied nat- 4.5 Ships carrying passengers
ural gas (LNG) and intended to ensure the transfer of LNG
to ships using LNG as fuel. 4.5.1 The service notations related to ships specially
The additional requirements of Rule Note NR620 LNG Bun- intended for the carriage of passengers are listed in [4.5.2]
kering Ship are applicable to these ships. to [4.5.3].
The additional requirements of Ch 4, Sec 8, [4] and Part D, a) Dredger, for ships specially equipped only for dredging
Chapter 7 are applicable to these ships. activities (excluding carrying dredged material)
4.4.8 Tanker, for ships intended to carry non-flammable b) Hopper dredger, for ships specially equipped for dredg-
liquid cargoes in bulk other than those covered by the serv- ing activities and carrying spoils or dredged material
ice notations in [4.4.2] to [4.4.7], such as water.
c) Hopper unit, for ships specially equipped for carrying
The list of cargoes the ship is allowed to carry may be spoils or dredged material
attached to the Certificate of Classification.
d) Split hopper unit, for ships specially equipped for carry-
For ships intended to carry only one type of cargo, the serv- ing spoils or dredged material and which open longitu-
ice notation may be completed by the additional service dinally, around hinges
feature indicating the type of product carried, e.g. tanker-
water. e) Split hopper dredger, for ships specially equipped for
dredging and for carrying spoils or dredged material and
The additional requirements of Part D, Chapter 10 are appli- which open longitudinally, around hinges.
cable to these ships.
4.6.3 These ships which are likely to operate at sea within
4.4.9 Refer also to [4.3.4] and [4.3.5] for combination car- specific limits may, under certain conditions, be granted an
rier intended to carry alternatively oil products and dry operating area notation. For the definition of operating area
cargo in bulk in cargo holds/tanks. notation, reference should be made to [5.3].
4.7 Working ships 4.7.4 The service notation fire-fighting ship is assigned to
ships specially intended and equipped for fighting fire. The
4.7.1 The service notations related to ships specially additional requirements of Ch 4, Sec 8, [8] and Part D,
intended for different working services are listed in [4.7.2] Chapter 16 are applicable to these ships.
to [4.7.7]. The service notation may be completed by the following
additional service features, as applicable:
4.7.2 The service notations for ships intended to tow and/or
push other ships or units are: 1 or 2 or 3, when the ship complies with the applicable
requirements of Pt D, Ch 16, Sec 3
a) Tug, for ships specially equipped for towing and/or
E, when the characteristics of the water fire-fighting sys-
pushing
tem are not those required for the assignment of the
b) Salvage tug, for ships specially equipped for towing additional service features 1, 2 or 3, and when the sys-
and/or pushing having specific equipment for salvage tem is specially considered by the Society
c) Escort tug, for ships specially equipped for towing water spraying, when the ship is fitted with a water-
and/or pushing having specific equipment for escorting spraying system complying with the applicable require-
ships or units during navigation. ments of Pt D, Ch 16, Sec 4, [3].
The additional requirements of Ch 4, Sec 8, [6] and Part D, 4.7.5 The service notation oil recovery ship is assigned to
Chapter 14 are applicable to these ships. ships specially equipped with fixed installations and/or
These service notations may be completed by the additional mobile equipment for the removal of oil from the sea sur-
service feature barge combined, when the units are face and its retention on board, carriage and subsequent
designed to be connected with barges and comply with the unloading. The additional requirements of Ch 4, Sec 8, [9]
relevant requirements of Pt D, Ch 14, Sec 3. The barges to and Part D, Chapter 17 are applicable to these ships.
which the tug can be connected are specified in a memo- The service notation may be completed by the following
randa. additional service features, as applicable:
4.7.3 The service notation supply vessel is assigned to ships OILTREAT may be assigned to ships designed and
specially intended for the carriage and/or storage of special equipped to recover polluted water which is subjected
material and equipment and/or which are used to provide to a chemical and/or a physical treatment, in order to
facilities and assistance for the performance of specified separate the oil from the polluted water. The separated
activities, such as offshore, research and underwater activi- oil is to be stored and transported in dedicated tanks
ties.
SECOND-LINE may be assigned to ships designed and
The service notation supply vessel is to be completed by the equipped to recover polluted water in the event of spills
following additional service features: of oils which have, at the time of recovery, a flash point
exceeding 60C (closed cup test). This service feature is
oil product, when the ship is also specially intended to not to be assigned to oil recovery ships carrying heated
carry oil products having any flash point and having a recovered oils within 15C of their flash point.
specified maximum cargo tank capacity.
The additional service feature oil product may be com- 4.7.6 The service notation anchor handling vessel is
pleted by the additional service feature FP>60C when assigned to towing vessels and/or supply vessels equipped
the supply vessel is intended to carry only oil products with winches for anchor handling, having an open stern to
having a flashpoint exceeding 60C (closed cup test). allow the decking of anchors and an appropriate thrust to
This additional service feature (FP>60C) is not to be perform the intended anchor handling operations. The addi-
assigned to units intended to carry oil products heated tional requirements of Ch 4, Sec 8, [10] and Pt D, Ch 14,
within 15C of their flash point. Sec 2, [5] are applicable to these ships.
4.7.9 The service notation lifting is assigned to ships 4.9 Fishing vessels
intended to perform lifting operations at sea.
The requirements for the assignment and maintenance of 4.9.1 The service notation fishing vessel is assigned to ships
this notation are given respectively in Rule Note NR608 specially equipped for catching and storing fish or other liv-
Classification of Lifting Units and in Ch 4, Sec 8, [12]. ing resources of the sea. The additional requirements of Ch
4, Sec 8, [14] and Part D, Chapter 20 are applicable to these
Note 1: For being eligible, at least one of the following additional
ships.
class notations is to be assigned:
The service notation may be completed by the following
ALM, ALS, OHS
additional service feature, as applicable:
F, when the ship complies with the requirements of Pt
4.8 Non-propelled units, units with sail
D, Ch 20, Sec 6 related to fire prevention, ventilation
propulsion and other units systems and means of escape
4.8.1 Barge TORRE, when the Society has verified the compliance
with the requirements for construction and equipment
The service notation barge is assigned to non-propelled
of fishing vessels of the Torremolinos International Con-
units intended to carry (dry or liquid) cargo inside holds or
vention for the Safety of Fishing Vessels, as amended
tanks. The additional requirements of Part D, Chapter 19 are
applicable to these ships. ED, when the Society has verified the compliance with
the requirements for construction and equipment of
For ships intended to carry only one type of cargo, the serv- fishing vessels of the European Directive 97/70/EC, as
ice notation may be completed by an additional service fea- amended.
ture indicating the type of product carried e.g. barge - oil,
barge - general cargo. Note 1: Units solely dedicated to service in a fishing flotilla by
means of cold storage and/or transformation of fish are not covered
This service notation may be completed by the additional by the service notation fishing vessel. They will be considered with
service feature tug combined when the units are designed the service notation special service.
to be connected with tugs and comply with the relevant
requirements of Pt D, Ch 14, Sec 3. The tugs to which the
barge can be connected are specified in a memoranda.
4.10 High Speed Crafts (HSC)
4.8.2 Pontoon 4.10.1 The high speed crafts meeting the requirements of
the Rules for the Construction and the Classification of High
The service notation pontoon is assigned to non-propelled Speed Craft (NR396 UNITAS) are assigned the following
units intended to carry cargo and/or equipment on deck service notations:
only. When a crane is permanently fitted on board, the
crane is to be certified and the service notation pontoon - HSC-CAT A (or high speed craft-CAT A) for passenger
crane is granted. The additional requirements of Part D, ships defined as Category A craft in respect of the
Chapter 19 are applicable to these ships. IMO International Code of Safety for High Speed Craft
HSC-CAT B (or high speed craft-CAT B) for passenger
4.8.3 Other units ships defined as Category B craft in respect of the
Any non-propelled units other than those covered by the IMO International Code of Safety for High Speed Craft
service notations listed above will be assigned the addi- HSC (or high speed craft) for ships other than the above;
tional service feature no propulsion, to be added to their in this case, the type of service may be specified after
own service notation, e.g. dredger - no propulsion. the notation, i.e. HSC/passenger carrier.
4.8.4 Assisted propulsion units 4.10.2 The service notation light ship is assigned to ships
Any units having a propulsion system not enabling them to subject to compliance both with Chapter 3 and Chapter 6 of
proceed at a speed greater than 7 knots, used for short tran- NR396 UNITAS Rules for the Classification of High Speed
sit voyages, will be assigned the additional service feature Craft, and with:
assisted propulsion to be added to their own service nota- for ships more than 500 GT: Part B and Part C of the
tion, e.g. dredger - assisted propulsion. present Rules, regarding stability and machinery instal-
lation
4.8.5 Units with a sail propulsion
for ships less than 500 GT: NR566 Hull Arrangement,
Ships fitted with a wind propulsion plant meeting the
Stability and Systems for Ships less than 500 GT.
requirements of the Rule Note Classification of wind pro-
pulsion plants onboard ships (NR206) may have their serv- The type of service may be specified after the service nota-
ice notation completed by the following additional service tion, i.e.:
feature:
light ship/fast passenger vessel
WAP for an auxiliary wind propulsion
light ship/fast cargo vessel
EAWP for a wind propulsion assisted by auxiliary
engine propulsion. light ship/fast patrol vessel
4.11 Ships with gas fuelled propulsion Icebreaker 6 for summer/autumn operations in medium
first-year ice with 1,0 m max ice thickness and for win-
ter/spring operations in medium first-year ice with 0,8 m
4.11.1 The service notation is completed by one of the fol-
max ice thickness
lowing additional service features, when the ship complies
with the requirements of NR529 Safety Rules for Gas- Icebreaker 7 for summer/autumn operations in medium
Fuelled Engine Installations in Ships or NR481 Design first-year ice with 0,8 m max ice thickness and for win-
and Installation of Dual Fuel Engines Using Low Pressure ter/spring operations in thin first-year ice with 0,6 m
Gas or Part D, Chapter 9 or a combination thereof, as max ice thickness.
applicable:
dualfuel for engines using both gas and fuel oil as fuel 4.13 Elastic shaft alignment for line shafting
and structure compatibility
gasfuel for engines using only gas as fuel.
4.13.1 Elastic Shaft Alignment (ESA)
The gas may be either compressed natural gas or liquefied
natural gas. The additional service feature ESA is to be assigned to new
ships designed with propulsion shaft line(s) falling into the
categories as defined in Rule Note NR592 Elastic Shaft
4.12 Icebreaker ships Alignment (ESA).
4.12.1 The service notation Icebreaker is assigned to ships The criteria and requirements for the assignment of this
having an operational profile that includes escort or ice additional service feature are given in Rule Note NR592.
management functions, having powering and dimensions
that allow them to undertake independent operations in ice 4.14 Diving support
covered waters.
The service notations dealt with under [4.12.2] are relevant 4.14.1 The service notations related to ships or offshore
to ships intended for navigation in ice-infested polar waters. units specially intended for support of diving operation are
listed in [4.14.2]. The requirements for the assignment of
The requirements for the assignment of these service nota- these service notations are given in Rule Note NR609 Clas-
tions are given in Rule Note NR527 Rules for the Classifica- sification of Diving Support Units.
tion of POLAR CLASS and ICEBREAKER Ships.
4.14.2 The following notations are to be assigned, as rele-
Ships complying with the requirements of Rule Note NR527 vant:
and assigned with one of the additional service notations
Icebreaker are also to comply with the requirements for the a) Diving support-integrated, for ships and units having a
assignment of the additional class notation defined in permanent diving system installed
[6.14.12]: COLD (H tDH , E tDE).
b) Diving support-capable, for ships and units having a
non-permanent diving system and when the diving
4.12.2 The following service notations are assigned: equipment is not installed
Icebreaker 1 for summer/autumn operations without c) Diving support-portable, for ships and units having a
restrictions and for winter/spring operations in multi- non-permanent diving system and when the diving
year ice with 3,0 m max ice thickness equipment is installed.
Icebreaker 2 for summer/autumn operations in multi- Note 1: For non-permanent diving systems, the notation diving sup-
year ice with 3,0 m max ice thickness and for win- port-capable is to be replaced by the temporary notation diving
ter/spring operations in second-year ice with 2,5 m max support-portable before conducting any diving operations. To this
ice thickness. end, requirements of NR609, Sec 9 are to be fulfilled allowing the
service to become fully effective.
Icebreaker 3 for summer/autumn operations in second-
year ice with 2,5 m max ice thickness and for win- 4.14.3 The service notations diving support-integrated and
ter/spring operations in thick first-year ice with 1,8 m diving support-portable are to be completed by the follow-
max ice thickness ing additional service features:
Icebreaker 4 for summer/autumn operations in thick a) DD, when the ship is equipped with a deep diving sys-
first-year ice with 1,8 m max ice thickness and for win- tem
ter/spring operations in medium first-year ice with 1,2 m
max ice thickness b) SD, when the ship is equipped with a shallow diving
system.
Icebreaker 5 for summer/autumn operations in medium
first-year ice with 1,2 m max ice thickness and for win- 4.14.4 The additional requirements of Ch 4, Sec 8, [13] are
ter/spring operations in medium first-year ice with 1,0 m applicable to ships or units assigned with the service nota-
max ice thickness tions diving support-integrated or diving-support-portable.
4.15 Miscellaneous units The service notation yacht is assigned to ships intended for
pleasure cruising other than charter yacht and complying
4.15.1 Special service with the applicable requirements of Rule Note NR500.
a) General Ships assigned with the service notation yacht and having a
length less than 24 m are not submitted to annual surveys
The service notation special service is assigned to ships
for hull and machinery.
which, due to the peculiar characteristics of their activ-
ity, are not covered by any of the notations mentioned The service notation yacht or charter yacht is always com-
above. The classification requirements of such units are pleted by one of the following additional service features, as
considered by the Society on a case by case basis. applicable:
This service notation may apply, for instance, to ships motor for units propelled by propulsion engine
engaged in research, expeditions and survey, ships for sailing for units with a sail propulsion, including those
training of marine personnel, whale and fish factory assisted by auxiliary propulsion engine.
ships not engaged in catching, ships processing other
living resources of the sea, and other ships with design Examples:
features and modes of operation which may be referred yacht-motor
to the same group of ships.
yacht-sailing
An additional service feature may be specified after the
notation (e.g. special service-training, special service- charter yacht-motor
fish factory, special service-standby rescue vessel) to charter yacht-sailing
identify the particular service in which the ship is
The service notation yacht or charter yacht is completed by
intended to trade. The scope and criteria of classifica-
the additional service feature S when the hull is made of
tion of such units are indicated in a memoranda.
steel material.
b) Special service - standby rescue vessel
Example:
Ships complying with the requirements of Rule Note
NR482 are eligible for the assignment of the service yacht-motor-S
notation special service - standby rescue vessel. When the hull is made of other material, additional service
This service notation may be completed by the number features are to be assigned in accordance with the require-
of survivors that the vessel is intended to carry. Depend- ments of Rule Note NR500.
ing on the vessel operation area, the Society may adapt Ships with service notation yacht or charter yacht are
the requirements regarding the survivors accommoda- assigned a navigation notation as listed in [5.2], except for
tion and/or the safety equipment. In such a case, this the navigation notations summer zone and tropical zone
service notation is to be completed by the number of which are not assigned.
survivors that the vessel is intended to carry and by the
For high speed motor yachts meeting the requirements of
vessel operation area, as for example: special service -
Rule Note NR500, Pt B, Ch 5, Sec 1, [2], the following
standby rescue vessel (150 survivors, Guinea Gulf).
applies:
The additional requirements of Ch 4, Sec 8, [15] are
As a rule, the navigation notation assigned to such unit
applicable to these ships.
is corresponding to sea areas where the significant wave
4.15.2 Launch height H.S. is not to exceed for more than 10 per cent of
the year the following values:
The launches or motorboats with a length not exceeding
24 m and meeting the requirements of both NR566 Hull - sheltered area: 0,5 m
Arrangement, Stability and Systems for Ships less than - coastal area: 2,5 m
500 GT and NR600 Hull Structure and Arrangement for the
- unrestricted navigation: no limitation.
Classification of Cargo Ships less than 65 m and Non Cargo
Ships less than 90 m are assigned the following service The table of the speed relative to the sea states, charac-
notations: terised by their significant wave height, is indicated in a
memoranda.
seagoing launch, for units intended for seagoing service,
limited at a wind force not exceeding 6 Beaufort scale 4.15.4 Crew boats
launch, for units intended for operation in ports, road- The service notation crew boat is assigned to ships less than
steads, bays and generally calm stretches of water, lim- 500 GT, dedicated to transport of offshore personnel from
ited at a wind force not exceeding 4 Beaufort scale. harbours to moored offshore installations or ships and meet-
Note 1: Ships that are assigned the service notation launch or sea-
ing the requirements of Rule Note NR490.
going launch are not assigned a navigation notation. Note 1: In NR490, Section 2, Section 5, Section 6 and Section 7
are to be replaced by the relevant sections of NR566.
4.15.3 Yacht and charter yacht Note 2: The limit of 45 m for service notation crew boat as speci-
The service notation charter yacht is assigned to ships fied in Sec 1, [1.1.1] of NR490 is no longer applicable
intended for pleasure cruising, engaged in commercial sail- Note 3: Ships which do not fulfil the minimum speed criteria given
ing and complying with the applicable requirements of Rule in Sec 1, [1.1.1] of NR490 are not to be assigned the above service
Note NR500. notation.
The service notation is to be completed by the additional 5 Navigation and operating area
service feature Xi, where: notations
X : Capacity parameter having one of the following
values: S, M, or L 5.1 Navigation notations
i : Type ship parameter having one of the following
5.1.1 Every classed ship is to be assigned one navigation
values: 0, 1 or 2.
notation as listed in [5.2], except those with the service
The requirements for the assignment of this service notation notations launch or seagoing launch.
are given in the Guidance note NI 589 Wind Farms Service
Ships.
5.1.2 The assignment of a navigation notation, including
4.15.8 Offshore Patrol Vessel (OPV) the reduction of scantlings or specific arrangements for
restricted navigation notations, is subject to compliance
The service notation OPV is assigned to ships dedicated to with the requirements laid down in Part B, Part C and Part D
patrol mission (i.e. smuggling, fishery inspection, customs- of the Rules and in NR216 Materials and Welding.
boarders protection...), with light weapon system and gen-
erally with no operational limit (neither weather condition 5.1.3 The assignment of a navigation notation does not
restriction nor HS restriction). These ships could patrol at absolve the Interested Party from compliance with any inter-
either low or high speed. national and national regulations established by the Admin-
The additional requirements of Part D, Chapter 21 are appli- istrations for a ship operating in national waters, or a
cable to these ships. specific area, or a navigation zone. Neither does it waive
Note 1: For patrol craft operating only at high speed, the service the requirements in Ch 1, Sec 1, [3.3.1].
notation light ship/fast patrol vessel is to be assigned in lieu of the
notation OPV and relevant rules as stated in [4.10.2] and [5.2.8] 5.2 List of navigation notations
apply
5.2.1 The navigation notation unrestricted navigation is
4.15.9 Other units assigned to a ship intended to operate in any area and any
For ships or other floating units intended to be classed with period of the year.
other service notations, reference is to be made to the spe-
cific Rules of the Society, and in particular: 5.2.2 The navigation notation summer zone is assigned to
Rules and Regulations for the Construction and Classifi- ships intended to operate only within the geographical lim-
cation of Wooden Fishing Vessels (NR219) its as defined in ILLC 1966 for the Summer zones.
Rules for the Classification of Offshore Units (NR445) 5.2.3 The navigation notation tropical zone is assigned to
Rules and Regulations for the Classification of Submers- ships intended to operate only within the geographical lim-
ibles (NR316). its as defined in ILLC 1966 for the Tropical zones.
5.2.4 The navigation notation coastal area is assigned to 5.3.2 The following operating area notations may be
ships intended to operate only within 20 nautical miles assigned:
from the shore and with a maximum sailing time of six dredging within 8 miles from shore,
hours from a port of refuge or safe sheltered anchorage. dredging within 15 miles from shore or within 20 miles
from port,
5.2.5 The navigation notation sheltered area is assigned to
dredging over 15 miles from shore.
ships intended to operate in sheltered waters, i.e. harbours,
estuaries, roadsteads, bays, lagoons and generally calm The operating area of the first two categories as specified in
stretches of water and when the wind force does not exceed [4.6] may be extended respectively over 8 or 15 miles. In
6 Beaufort scale. that case, the operating area notation is completed by the
maximum significant wave height during service, as follows:
5.2.6 In specific cases, the designation of the geographical dredging over 8 (or 15) miles from shore with H.S. ... m.
area and/or the most unfavourable sea conditions consid-
For ships being assigned the service notation split hopper
ered may be added to the navigation notation.
unit or split hopper dredger, the operating area notation
5.2.7 The navigation notation temporary unrestricted navi- may be completed by the maximum allowable significant
gation may be assigned, in addition to the navigation nota- height of waves during the service, being indicated between
tions defined in [5.2.2], [5.2.3], [5.2.4] and [5.2.5] to parenthesis, i.e. (H.S. ... m).
service ships for which the period of unrestricted navigation
may be chosen to satisfy the conditions defined in a memo- 6 Additional class notations
randa.
When a favourable weather situation is included amongst 6.1 General
these conditions, the voyages are to be such as the ship can
be put in a port or a sheltered anchorage in about 12 hours 6.1.1 An additional class notation expresses the classifica-
from any point of its route. tion of additional equipment or specific arrangement,
Note 1: Before any voyage covered by the navigation notation which has been requested by the Interested Party.
temporary unrestricted navigation, the ship is to be submitted to
an occasional survey, during which the Surveyor checks that the 6.1.2 The assignment of such an additional class notation is
intended voyage and the ships specific condition, if any, comply subject to the compliance with additional rule require-
with the conditions defined in a memoranda. ments, which are detailed in Part E of the Rules.
5.2.8 For ships assigned with the service notation: 6.1.3 Some additional class notations are assigned a con-
HSC-CAT A, HSC-CAT B, or HSC as defined in [4.10.1], struction mark, according to the principles given in [3.1.2].
This is indicated in the definition of the relevant additional
light ship, as defined in [4.10.2], or
class notations.
crew boat, as defined in [4.15.4],
6.1.4 The different additional class notations which may be
as a rule, one of the following navigation notations is to be
assigned to a ship are listed in [6.2] to [6.15], according to
assigned to such units and is corresponding to sea areas
the category to which they belong. These additional class
where the significant wave height H.S. is not to exceed for
notations are also listed in alphabetical order in Tab 2.
more than 10 per cent of the year the following values:
sea area 1: 0,5 m 6.2 VeriSTAR and STAR notations
sea area 2: 2,5 m
sea area 3: 4,0 m 6.2.1 General
VeriSTAR and STAR notations integrate rational analysis at
sea area 4: no limitation.
design stage or after construction and possibly with data
The shipyards table of the maximum allowed ship speed and records from ships-in-service concerning planned
relative to the sea states, characterised by their significant inspection and ship maintenance.
wave height, is indicated in a memoranda. In compliance with [6.1.3], these notations are assigned a
construction mark, as defined in [3].
5.3 Operating area notations The requirements for the assignment of these notations are
given in Part E, Chapter 1.
5.3.1 The operating area notation expresses the specified
area where some service units are likely to operate at sea 6.2.2 VeriSTAR-HULL CM and VeriSTAR-HULL
within specific restrictions which are different from normal The additional class notation VeriSTAR-HULL CM may be
navigation conditions. assigned to new ships, contracted for construction on or
The operating area notation is, in principle, solely granted after the 1st July 2015, the structural condition of which is
to ships for dredging activities. checked with 3D FEM calculation program at design stage,
according to the requirements of the Society for which the
This operating area notation is indicated after the navigation hull surveys for new construction are carried out according
notation. to the requirements of Ch 3, Sec 7 and for which the
Example: unrestricted navigation - operating area notation requirements of Pt E, Ch 1, Sec 1 are fulfilled.
Existing ships contracted for construction before the 1st July 6.2.6 STAR-MACH SIS
2015 and for which the structural condition is checked with
3D FEM calculation program at design stage according to The additional class notation STAR-MACH SIS is assigned to
the requirements of the Society may be assigned with the ships on which a Planned Maintenance Survey System for
notation VeriSTAR-HULL. machinery (PMS) is implemented as per the requirements of
Ch 2, Sec 2, [4.4]. In addition, the notation STAR-MACH
VeriSTAR-HULL CM and VeriSTAR-HULL encompass the SIS includes a risk analysis update of the ship's machinery
fatigue assessment carried out on selected structural details and other equipment (navigation instrumentation, anchor-
as per the requirements of Part B. ing and mooring arrangements, ...).
The requirements for the assignment of these notations are
The requirements for the assignment and maintenance of
given in Pt E, Ch 1, Sec 1.
this notation are given respectively in Pt E, Ch 1, Sec 3 and
The additional class notations VeriSTAR-HULL CM and Veri- in Ch 5, Sec 2.
STAR-HULL may be completed by DFL xx years, with xx
having values between 25 and 40, when a fatigue assessment 6.2.7 STAR SIS
has been carried out on selected structural details showing
that their evaluated design fatigue life is not less than xx When ships are assigned the notations STAR-HULL and
years. STAR-MACH SIS, the two separate notations are superseded
by the cumulative additional class notation STAR SIS.
The requirements for the assignment of DFL xx years are
given in Pt B, Ch 7, Sec 4.
6.2.8 STAR-REGAS
The additional class notations VeriSTAR-HULL CM, VeriSTAR-
HULL, VeriSTAR-HULL CM DFL xx years and VeriSTAR-HULL The additional class notation STAR-REGAS is assigned to
DFL xx years may be assigned to ships of less than 170 m in ships having both the service notation liquefied gas carrier
length, subject to special consideration by the Society. and the additional service feature RV (with or without the
additional service feature STL-SPM) and for which the
6.2.3 VeriSTAR-HULL SIS maintenance procedures for regasification installation and
The additional class notation VeriSTAR-HULL SIS may be associated systems have been approved by means of a risk
assigned to ships in place of notations VeriSTAR-HULL CM analysis.
and VeriSTAR-HULL when the structural condition is reas-
The requirements for the assignment of this notation are
sessed using survey data.
given in Pt E, Ch 1, Sec 4.
The requirements for the assignment and maintenance of
this notation are given respectively in Pt E, Ch 1, Sec 1 and
in Ch 5, Sec 2. 6.3 Availability of machinery (AVM)
This notation is not applicable to ships assigned with the
6.3.1 General
additional service feature CSR.
The notations dealt with under this heading are relevant to
This notation may be completed by DFL xx years as detailed
in [6.2.2]. systems and/or arrangements enabling the ship to carry on
limited operations when single failure affects propulsion or
6.2.4 STAR-HULL auxiliary machinery or when an external event such as fire
or flooding involving machinery spaces affects the availabil-
The additional class notation STAR-HULL is assigned to ity of the machinery.
ships for which, in addition to the requirements for assign-
ment of the additional class notation VeriSTAR-HULL SIS, In compliance with [6.1.3], these notations are assigned a
an Inspection and Maintenance Plan for the hull is imple- construction mark, as defined in [3].
mented by the Owner.
The requirements for the assignment and maintenance of
This notation is not applicable to ships assigned with the
these notations are given respectively in Part E, Chapter 2
additional service feature CSR.
and in Ch 5, Sec 3.
The requirements for the assignment and maintenance of
this notation are given respectively in Pt E, Ch 1, Sec 2 and 6.3.2 Alternative propulsion system (AVM-APS)
in Ch 5, Sec 2.
The additional class notation AVM-APS is assigned to ships
6.2.5 STAR-MACH which are fitted with systems and/or arrangements enabling
The additional class notation STAR-MACH is assigned to them to maintain operating conditions with some limita-
ships subject to compliance with the requirements for the tions in speed, range and comfort, in the case of single fail-
assignment of the notation and for which the requirements ure of items relative to the propulsion or power generating
for maintenance of the notation given in Ch 5, Sec 2 are not system.
applied.
The limitations in operation and the types of single failure
The requirements for the assignment of this notation are covered by this notation are specified in Pt E, Ch 2, Sec 1,
given in Pt E, Ch 1, Sec 3. [1.2].
Reference in NR 467 or
Additional class notation Definition in Remarks
to other Rule Notes
ACCESS [6.14.30] Pt E, Ch 10, Sec 19
ACCOMMODATION [6.14.27] Guidance Note NI 577
ALP (1) [6.12] Rule Note NR 526 for derricks including heavy derricks and derricks in
ALM (1) union purchase, see Rule Note NR 184
ALS (1)
(ALP) (1)
(ALM) (1)
(ALS) (1)
AUT-CCS (1) [6.4.3] Pt E, Ch 3, Sec 2
AUT-IMS (1) [6.4.5] Pt E, Ch 3, Sec 4
AUT-PORT (1) [6.4.4] Pt E, Ch 3, Sec 3
AUT-UMS (1) [6.4.2] Pt E, Ch 3, Sec 1
AVM-APS (1) [6.3.2] Pt E, Ch 2, Sec 1 AVM-DPS and AVM-IPS may be completed by the
additional suffix /NS
AVM-DPS (1) [6.3.3] Pt E, Ch 2, Sec 2
AVM-IPS (1) [6.3.4] Pt E, Ch 2, Sec 3
AVM-FIRE (1) [6.3.5] Pt E, Ch 2, Sec 4 AVM-FIRE is assigned alone or in addition to AVM-
APS or AVM-DPS
AWT [6.8.4] Part E, Chapter 9
BATTERY SYSTEM [6.14.37] Pt E, Ch 10, Sec 21
BLUS [6.14.25] Pt E, Ch 10, Sec 17
SLUS
BWE [6.8.5] Part E, Chapter 9
BWT [6.8.6] Part E, Chapter 9
CARGOCONTROL [6.14.9] Pt E, Ch 10, Sec 9
CLEANSHIP [6.8.2] Part E, Chapter 9
CLEANSHIP SUPER ( ) [6.8.3] between brackets, at least 3 eligible notations are to
be assigned among the following ones: AWT, BWT,
EGCS-SCRUBBER, GWT, HVSC, NDO -x days,
NOX-x%, OWS-x ppm, SOX-x%
COLD CARGO [6.14.13] Pt E, Ch 10, Sec 11
COLD DI [6.14.12] Pt E, Ch 10, Sec 11
COLD (H tDH, E tDE)
COMF+ [6.7.4] Part E, Chapter 6 COMF+ is to be completed by the selected perform-
ance indexes (Sound insulation index/ Impact index/
COMF-NOISE y [6.7.2]
Emergence/ Intermittent noise/ Intelligibility)
COMF-VIB y [6.7.3] grade y is equal to 1, 2, or 3
COMF-NOISE-Crew y [6.7.5] grade y is equal to 1, 2, 3, 1PK, 2PK or 3PK
COMF-NOISE-Pax y
COMF-VIB-Crew y
COMF-VIB-Pax y
COVENT [6.14.8] Pt E, Ch 10, Sec 8
CPS(COT) [6.15.6] Rule Note NR 530 cargo oil tanks of crude oil tankers of 5 000 tonnes
deadweight (DWT) and above
Reference in NR 467 or
Additional class notation Definition in Remarks
to other Rule Notes
DYNAPOS SAM (1) [6.14.6] Pt E, Ch 10, Sec 6 DYNAPOS AM and DYNAPOS AT may be com-
DYNAPOS AM (1) pleted by R or RS
DYNAPOS AT (1) DYNAPOS AM/AT may be completed by R or RS or
DYNAPOS AM/AT (1) (xx ; xx) (corresponding to the two-number vector
for the Environmental Station Keeping Index ESKI)
GAS-PREPARED [6.14.36] Rule Note NR 627 between brackets, the notation may be completed
GAS-PREPARED ( ) by one, more or all of the following notations: S, P,
ME-DF, AEB
GRAB [X] [6.14.2] Rule Note NR 606 (2) on a voluntary basis for bulk carriers other than
Rule Note NR 522, Ch 12 CSR BC-A or CSR BC-B
Reference in NR 467 or
Additional class notation Definition in Remarks
to other Rule Notes
LI-HG [6.14.28] Pt B, Ch 10, Sec 2
LI-S1
LI-S2
LI-S3
LI-HG-S1
LI-HG-S2
LI-HG-S3
MANOVR [6.14.10] Pt E, Ch 10, Sec 10 IMO Resolution MSC 137(76)
Reference in NR 467 or
Additional class notation Definition in Remarks
to other Rule Notes
SYS-COM (1) [6.5.4] Pt E, Ch 4, Sec 3 SYS-COM can only be assigned to ships which are
also assigned the notation AUT-IMS
SYS-IBS (1) [6.5.3] Pt E, Ch 4, Sec 2
SYS-IBS can only be assigned to ships which are also
SYS-IBS-1 assigned the notation SYS-NEQ
SYS-NEQ (1) [6.5.2] Pt E, Ch 4, Sec 1 SYS-IBS-1 can only be assigned to ships which are
SYS-NEQ-1 also assigned the notations SYS-NEQ-1 and AUT-UMS
6.3.3 Duplicated propulsion system (AVM-DPS) The additional suffix NS may be added to the notation when
the ship is intended for normal operation with one propul-
The additional class notation AVM-DPS is assigned to ships sion system out of service in accordance with the provisions
which are fitted with a duplicated propulsion system ena- of Pt E, Ch 2, Sec 3, [4].
bling them to maintain operating conditions with some lim-
itations in power (but 50% of the main power is to be Note 1: The loss of one compartment due to fire or flooding is con-
maintained), speed, range and comfort, in the case of single sidered as a single failure case.
failure of items relative to the propulsion or power generat-
ing system. 6.3.5 Fire mitigation for main diesel-generator
rooms (AVM-FIRE)
The limitations in operation and the types of failure which are The additional class notation AVM-FIRE is assigned to ships
covered by this notation are specified in Pt E, Ch 2, Sec 2, which are fitted with an electrical production plant distrib-
[1.2]. uted over minimum two main diesel-generator rooms ena-
bling to maintain sufficient operating functionality with
The additional suffix NS may be added to the notation when
respect to propulsion, safety, navigation and steering, and a
the ship is intended for normal operation with one propul-
minimum of 50% operability for defined habitability serv-
sion system out of service in accordance with the provisions
ices in case of loss of one main diesel-generator room due
of Pt E, Ch 2, Sec 2, [4].
to fire.
Note 1: The loss of one compartment due to fire or flooding is not The additional class notation AVM-FIRE is assigned alone or
considered as a single failure case. in addition to the additional class notation AVM-APS or
AVM-DPS.
6.3.4 Independent propulsion system (AVM-IPS)
6.4 Automated machinery systems (AUT)
The additional class notation AVM-IPS is assigned to ships
which are fitted with an independent propulsion system
6.4.1 General
enabling them to maintain operating conditions with some
limitations in power (but 50% of the main power is to be The notations dealt with under this heading are relevant to
maintained), speed, range and comfort, in the case of single automated machinery systems installed on board ships.
failure of items relative to the propulsion or power generat- In compliance with [6.1.3], these notations are assigned a
ing system. construction mark, as defined in [3].
The limitations in operation and the types of failure which are The requirements for the assignment and maintenance of
covered by this notation are specified in Pt E, Ch 2, Sec 3, these notations are given respectively in Part E, Chapter 3
[1.2]. and in Ch 5, Sec 4.
6.4.2 Unattended machinery space (AUT-UMS) 6.5.3 Integrated bridge system (SYS-IBS and
SYS-IBS-1)
The additional class notation AUT-UMS is assigned to ships
which are fitted with automated installations enabling The additional class notation SYS-IBS is assigned to ships
machinery spaces to remain periodically unattended in all fitted with an integrated bridge system which allows simpli-
sailing conditions including manoeuvring. fied and centralised bridge operation of the main functions
of navigation, manoeuvring and communication, as well as
6.4.3 Centralised control station (AUT-CCS) monitoring from bridge of other functions related to passage
execution, route control and monitoring and control and
The additional class notation AUT-CCS is assigned to ships monitoring of machinery installation according to Part C,
which are fitted with machinery installations operated and Chapter 3.
monitored from a centralised control station.
The notation SYS-IBS is assigned only to ships which are
6.4.4 Automated operation in port (AUT-PORT) also assigned the additional class notation SYS-NEQ.
The additional class notation AUT-PORT is assigned to ships
The additional class notation SYS-IBS-1 is assigned to ships
which are fitted with automated installations enabling the
fitted with an integrated bridge system which allows simpli-
ships operation in port or at anchor without personnel spe-
fied and centralised bridge operation of the main functions
cially assigned for the watch-keeping of the machinery in
of navigation, manoeuvring and communication, as well as
service.
monitoring from bridge of other functions related to passage
execution, route control and monitoring and control and
6.4.5 Integrated machinery system (AUT-IMS)
monitoring of machinery installation according to Part C,
The additional class notation AUT-IMS is assigned to ships Chapter 3 and Pt E, Ch 3, Sec 1 (AUT-UMS notation).
which are fitted with automated installations enabling
machinery spaces to remain periodically unattended in all In addition, the following functions may be part of the nota-
sailing conditions including manoeuvring, and additionally tion SYS-IBS-1:
provided with integrated systems enabling to handle con- external / internal communication system
trol, safety and monitoring of machinery.
monitoring of specific cargo operations
6.5.2 Centralised navigation equipment (SYS-NEQ 6.5.5 Bridge design and instrumentation
and SYS-NEQ-1) (SYS-NEQ-OSV)
The additional class notation SYS-NEQ is assigned to ships The additional class notation SYS-NEQ-OSV may be
which are fitted with a centralised navigation control system assigned to ships fulfilling specific requirements for bridge
so laid out and arranged that it enables normal navigation design and instrumentation, and, in addition, provided with
and manoeuvring operation of the ship by two persons in further means for safe operation in all the waters, including
cooperation. areas with harsh operational and environmental conditions
The additional class notation SYS-NEQ-1 is assigned when, such as the North Sea.
in addition to the above, the installation is so arranged that The aim of the additional class notation SYS-NEQ-OSV is to
the navigation and manoeuvring of the ship can be oper- reduce the risk, in bridge operation, of failure causing colli-
ated under normal conditions by one person, for periodical sion, contact and grounding.
one man watch. This notation includes specific require-
ments for prevention of accidents caused by the operators The requirements for the assignment of this notation are
unfitness. given in Rule Note NR633.
6.6 Monitoring equipment (MON) The requirements for the assignment and maintenance of
these notations are given respectively in Part E, Chapter 6
6.6.1 General and in Ch 5, Sec 10.
The notations dealt with under this heading are relevant to
hull and tailshaft monitoring equipment installed on board 6.7.2 Comfort with regard to noise (COMF-NOISE)
ships. The additional class notation COMF-NOISE is assigned to
ships satisfying levels of noise defined in Part E, Chapter 6.
6.6.2 Hull stress monitoring (MON-HULL) The assessment of noise levels is carried out through meas-
The additional class notation MON-HULL is assigned to urements during harbour and sea trials.
ships which are fitted with equipment continuously moni- The notation is completed by a grade 1, 2 or 3 which repre-
toring ships dynamic loads through measurements of sents the comfort level achieved for the assignment of the
motions in waves and stresses/deformations in the hull notation. The lower grade (1) corresponds to the higher
structure. class of comfort.
The requirements for the assignment and maintenance of Example:
this notation are given respectively in Pt E, Ch 5, Sec 1 and COMF-NOISE 2
in Ch 5, Sec 6.
6.7.3 Comfort with regard to vibration (COMF-VIB)
6.6.3 Tailshaft monitoring system (MON-SHAFT)
The additional class notation COMF-VIB is assigned to
The additional class notation MON-SHAFT is assigned to
ships satisfying levels of vibration defined in Part E, Chapter
ships fitted with oil or water lubricated systems for tailshaft
6. The assessment of vibration is carried out through meas-
bearings. The assignment of this notation allows the ship to
urements during harbour and sea trials.
be granted a reduced scope for complete tailshaft surveys,
see Ch 2, Sec 2, [5.5.3] and Ch 5, Sec 6, [3]. The notation is completed by a grade:
The requirements for the assignment and maintenance of 1, 2 or 3 for an evaluation based on overall frequency
this notation are given respectively in Pt E, Ch 5, Sec 2 and criteria, or
in Ch 5, Sec 6. 1PK, 2PK or 3PK for an evaluation based on single
amplitude peak criteria.
6.6.4 Ice load monitoring system (MON-ICE)
The grade represents the comfort level achieved for the
The additional class notation MON-ICE is assigned to ships assignment of the notation. The lower grade (1 or 1PK) cor-
which are fitted with equipment to continuously monitor responds to the higher class of comfort.
ice loads exerted on ships hull by ice formations.
Example:
The notation MON-ICE is to be completed by one of the cri-
teria L(i) and G, as follows: COMF-VIB 1PK
MON-ICE L(i) for ships equipped with a local ice load 6.7.4 High comfort level with regard to noise (COMF+)
monitoring system, where i is a (list of) Roman
numeral(s) from I to VII, depending on the design sce- The additional class notation COMF+ is assigned to yachts
nario satisfying levels of noise defined in Pt E, Ch 6, Sec 5.
MON-ICE G for ships intended to perform ramming and The requirements of notations COMF-NOISE have to be ful-
required to be equipped with a hull girder ice load filled prior to assigning the notation COMF+.
monitoring system. This notation COMF+ deals with additional criteria in view
Note 1: The above letters and numerals denote the location (i.e. to evaluate higher standard comfort level than COMF-
areas and regions) of the sensors and the interaction scenario, and NOISE. These additional criteria are to be selected among
the two notations are cumulative. the following performance indexes:
Examples: MON-ICE L(I, III, VI), MON-ICE G Sound insulation index
MON-ICE L(II), MON-ICE G Impact index
The requirements for the assignment and maintenance of Emergence
these notations are given respectively in NR616 Ice Load Intermittent noise
Monitoring System (MON-ICE) and in Ch 5, Sec 6. Intelligibility.
The additional class notation COMF+ is to be completed by
6.7 Comfort on board ships (COMF)
the selected performance indexes.
6.7.1 General Example:
The notations dealt with under this heading are relevant to COMF + /Impact index /Intermittent noise /Intelligibility
the assessment of comfort on board ships with regard to the
This notation is assigned only to ships having the service
noise and/or vibration.
notation yacht or charter yacht.
The parameters which are taken into consideration for the Note 1: The additional class notation COMF+ may also be applied
evaluation of the comfort, such as the level of noise, the to ships assigned with the service notation Passenger ship after spe-
level of vibration, is indicated in a memoranda. cial consideration.
6.7.5 Comfort for passenger and crew areas 6.8.7 Grey Water Treatment (GWT)
The additional class notations COMF-NOISE-Pax, COMF- The additional class notation GWT is assigned to ships fitted
NOISE-Crew, followed by grade 1, 2 or 3 and COMF-VIB- with a treatment installation for grey waters in accordance
Pax and COMF-VIB-Crew, followed by grade 1, 2 or 3 or with the provisions of Pt E, Ch 9, Sec 1 and Pt E, Ch 9, Sec 3.
1PK, 2PK or 3PK are assigned to ships satisfying levels of
noise / vibration defined in Part E, Chapter 6, for passenger 6.8.8 No Discharge Operation (NDO-x days)
or crew area, as applicable. The additional class notation NDO-x days is assigned to
Example: ships designed for no discharge operation during x days, in
accordance with the provisions of Pt E, Ch 9, Sec 1 and Pt
COMF-VIB-Crew 3
E, Ch 9, Sec 3.
Note 1: x days is the number of consecutive days the ship is able to
6.8 Pollution prevention operate with the full complement of on-board people, including crew
and passengers, without the need for discharging any substances into
6.8.1 General the sea. This number cannot be less than one day (24 hours).
6.9.1 General 6.10.1 The notations dealt with under [6.10.2] are relevant to
The notations dealt with under this heading are relevant to ships strengthened for navigation in ice in accordance with
refrigerating installations fitted on board ships, including the Finnish-Swedish Ice Class Rules 1985 as amended.
machinery and storing equipment or arrangements. The requirements for the assignment and maintenance of
these notations are given respectively in Part E, Chapter 8
In compliance with [6.1.3], these notations are assigned a
and in Ch 5, Sec 9.
construction mark, as defined in [3].
These requirements reproduce the provisions of the Finnish-
The requirements for the assignment and maintenance of Swedish Ice Class Rules cited above.
these notations are given respectively in Part E, Chapter 7
Note 1: These National requirements are applicable for ships trad-
and in Ch 5, Sec 8. ing in the Finnish/Swedish waters and other relevant areas of the
Baltic sea during the ice period.
6.9.2 Refrigerating installations for cargo
(REF-CARGO) 6.10.2 The following additional class notations are
The additional class notation REF-CARGO is assigned to assigned:
ships fitted with refrigerating plants and holds intended to ICE CLASS IA SUPER for ships with such structure,
carry cargoes, with the condition that the number and the engine output and other properties that they are nor-
power of the refrigerating units are such that the specified mally capable of navigating in difficult ice conditions
temperatures can be maintained with one unit on standby. without the assistance of icebreakers
The notation -AIRCONT is added when the refrigerating ICE CLASS IA for ships with such structure, engine out-
plant is equipped with controlled atmosphere installations. put and other properties that they are capable of navi-
gating in difficult ice conditions, with the assistance of
6.9.3 Refrigerating installations for insulated icebreakers when necessary
containers (REF-CONT)
ICE CLASS IB for ships with such structure, engine out-
The additional class notation REF-CONT is assigned to put and other properties that they are capable of navi-
ships fitted with refrigerating plants for insulated containers gating in moderate ice conditions, with the assistance of
carried in holds of container ships. icebreakers when necessary
The additional class notation REF-CONT is followed by a ICE CLASS IC for ships with such structure, engine out-
suffix: put and other properties that they are capable of navi-
(A) where the containers are cooled by a permanently gating in light ice conditions, with the assistance of
installed refrigerating plant designed to supply refriger- icebreakers when necessary.
ated air to insulated containers carried in holds of con-
tainer ships, with the condition that the number and the 6.10.3 The additional class notations ICE CLASS ID,
power of the refrigerating units are such that the speci- YOUNG ICE 1 and YOUNG ICE 2 are assigned to ships
fied temperatures can be maintained with one unit on whose reinforcements for navigation in ice are different
standby from those required for the assignment of the notations
(E) where the ship is intended only to supply electrical defined in [6.10.2] but who comply with the specific
power to self-refrigerated containers. requirements detailed in Part E, Chapter 8.
Note 1: No minimum engine output is required for these notations.
The notation -AIRCONT is added to the additional class
notation REF-CONT (A) when the refrigerating plant is 6.10.4 The additional class notation ICE is assigned to
equipped with controlled atmosphere installations. ships whose reinforcements for navigation in ice are similar
but not equivalent to those required for the assignment of
6.9.4 Refrigerating installations for domestic supplies the notations defined in [6.10.2] and [6.10.3], when this
(REF-STORE) has been specially considered by the Society.
The additional class notation REF-STORE is assigned to
ships fitted with refrigerating plants and spaces exclusively 6.11 Navigation in polar waters
intended for the preservation of ships domestic supplies.
6.11.1 The notations dealt with under [6.11.2] are relevant
6.9.5 The additional class notations REF-CARGO, REF- to ships intended for navigation in ice-infested polar waters,
CONT and REF-STORE may also be completed by the fol- except icebreakers.
lowing notations:
The requirements for the assignment of these notations are
a) -PRECOOLING when the refrigerating plants are given in Rule Note NR527 Rules for the Classification of
designed to cool down a complete cargo of fruit and/or POLAR CLASS and ICEBREAKER Ships.
vegetables to the required temperature of transportation Ships complying with the requirements of Rule Note NR527
b) -QUICKFREEZE for the refrigerating plants of fishing and assigned with one of the additional class notations
vessels and fish factory ships where the design and POLAR CLASS are also to comply with the requirements for
equipment of such plants have been recognised suitable the assignment of the additional class notation defined in
to permit quick-freezing of fish in specified conditions. [6.14.12]: COLD (H tDH , E tDE).
Note 1: Icebreaker refers to any ship having an operational profile 6.12.4 In compliance with [6.1.3], these notations are
that includes escort or ice management functions, having powering assigned a construction mark as defined in [3].
and dimensions that allow it to undertake independent operations
Note 1: Rules for the Classification and Certification of Lifting
in ice covered waters.
Appliances of ships and offshore units (NR184) are applicable to
derricks including heavy derricks and derricks in union purchase.
6.11.2 The following additional class notations are assigned:
POLAR CLASS 1 for year-round operations in all polar 6.12.5 The requirements for assignment and maintenance
waters of these notations are given in NR526 and NR184, as rele-
POLAR CLASS 2 for year-round operations in moderate vant.
multi-year ice conditions
POLAR CLASS 3 for year-round operations in second- 6.13 Emergency Response Service (ERS)
year ice which may include multi-year ice conditions
6.13.1 General
POLAR CLASS 4 for year-round operations in thick first- The notations dealt with under this Article are related to the
year ice which may include old ice inclusions provision of technical assistance in case of a maritime acci-
POLAR CLASS 5 for year-round operations in medium dent at sea by providing information on their remaining
first-year ice which may include old ice inclusions strength and stability in the resulting damaged condition.
POLAR CLASS 6 for summer/autumn operations in The requirements for the assignment and maintenance of
medium first-year ice which may include old ice inclu- these notations are given in NR556 (Emergency Response
sions Service).
POLAR CLASS 7 for summer/autumn operations in thin
6.13.2 ERS-S (Strength), ERS-H (Hydrodynamic),
first-year ice which may include old ice inclusions. ERS-M (Mooring), [ERS-S] (Strength-Partial),
[ERS-H] (Hydrodynamic-Partial) and [ERS-M]
6.12 Lifting appliances (Mooring-Partial) services
ERS-S corresponds to damage longitudinal strength and
6.12.1 Ships fitted with lifting appliances meeting the damage stability analyses. It aims at providing information
requirements of NR526 Rules for the Classification and the on the remaining hull strength and stability after the acci-
Certification of Cranes onboard Ships and Offshore Unit dent.
may be assigned the following additional class notations:
ERS-H aims at providing limits of navigation, based on
a) ALP for appliances intended to be used at harbour, for direct calculations of vertical wave bending moment and
loading or unloading cargoes, equipments, spare parts vertical wave shear force for the accidental site sea-states,
or consumable instead of empirical rule formulae. It is only applied in com-
b) ALM for appliances intended to be used in offshore con- plement to ERS-S. It aims at providing maximum environ-
ditions for various lifting operations exclusive of the mental conditions (Hs), heading restriction, or speed limit.
appliances mentioned in item a) These limits of navigation are given for hull girder strength
only.
c) ALS for lifting appliances intended to be used at sea for
ERS-M corresponds to damaged mooring analyses for per-
launching and recovering diving devices.
manently moored units. It aims at providing information on
Note 1: Ships fitted with lifting appliances used in harbour or in the remaining capacities of the mooring system after the
similar conditions for lifting operations other than ships loading or failure of one or several mooring lines and the potential fail-
unloading may be assigned the additional service notation ALP. ure of an additional mooring line.
6.12.2 The additional class notations (ALP), (ALM), (ALS) [ERS-S], [ERS-H] and [ERS-M] are assigned to ships until the
may be assigned by the Society in lieu of the notations ALP, respective ERS service becomes fully effective. The Society
ALM, ALS respectively, when the corresponding lifting will provide service in case of damage as far as possible
appliances meet the requirements of specific National Reg- depending on the available information.
ulations under the conditions defined in NR526. Note 1: The notations [ERS-S], [ERS-H] and [ERS-M] are replaced
respectively by ERS-S, ERS-H and ERS-M when all necessary infor-
mation has been made available to the Society allowing the service
6.12.3 The additional class notations ALP, ALM, ALS,
to become fully effective.
(ALP), (ALM) or (ALS) are optional. However, the Society
may require the compliance of lifting appliances with the
assigning conditions of one of the above mentioned addi- 6.14 Other additional class notations
tional class notations for the classification of ships, when
6.14.1 Strengthened bottom
one or several lifting appliances are of a primary impor-
tance for their operation, or when such appliances signifi- The additional class notation STRENGTHBOTTOM may be
cantly influence their structure. As a rule, such is the case assigned to ships built with specially strengthened bottom
for the shear leg pontoons, crane pontoons, crane vessels, structures so as to be able to be loaded and/or unloaded
supporting ships for diving devices and when the lifting when properly stranded.
appliances concerned have special high capacities, for The requirements for the assignment and maintenance of
example in case of ships specially equipped for handling this notation are given respectively in Pt E, Ch 10, Sec 1 and
very heavy loads. in Ch 5, Sec 10.
a) Loading by grabs for bulk carriers subject to NR522 The additional class notation LASHING may be assigned to
Common Structural Rules for Bulk Carriers ships initially fitted with mobile container lashing equip-
ment which has been documented, tested and checked.
The additional class notation GRAB [X] is assigned to
ships with holds designed for loading/unloading by The additional class notation LASHING-WW may be
grabs having a maximum specific weight up to [X] tons. assigned in lieu of the notation LASHING to any ship,
except if the intended navigation zone is identified as the
The requirements for the assignment and maintenance of
North-Atlantic or North-Pacific area.
this notation are given respectively in NR522 Common
Structural Rules for Bulk Carriers and in Ch 5, Sec 10. The additional class notation LASHING (restricted area)
may be assigned in lieu of the notation LASHING to ships
Note 1: It is reminded that for bulk carriers assigned with the addi- navigating only in specific restricted areas such as Baltic
tional service feature CSR, and one of the additional service Sea, Mediterranean Sea or South China Sea.
features BC-A or BC-B, GRAB [X] is assigned as a mandatory
additional service feature. These notations are assigned only to ships having the serv-
For bulk carriers assigned with the additional service feature ice notation container ship or the additional service feature
CSR others than above, GRAB [X] may be assigned on a volun- equipped for carriage of containers.
tary basis as an additional class notation.
This equipment, however, will not be verified any longer at
It is to be noted that this additional class notation does the periodical class surveys to which the ship is submitted.
not negate the use of heavier grabs, but the owner and
The requirements for the assignment of these notations are
operators are to be made aware of the increased risk of
given in Pt E, Ch 10, Sec 5.
local damage and possible early renewal of inner bot-
tom plating if heavier grabs are used regularly or occa-
6.14.6 Dynamic positioning
sionally to discharge cargo.
The additional class notation DYNAPOS may be assigned to
b) Loading by grabs for ships other than those subject to ships equipped with a dynamic positioning system.
NR522 Common Structural Rules for Bulk Carriers
In compliance with [6.1.3], this notation is assigned a con-
The additional class notation GRABLOADING may be struction mark, as defined in [3].
assigned to ships with hold tank tops specially rein-
forced for loading/unloading cargoes by means of grabs The scope of the notation, including the additional keys for
or buckets. the description of capability of the installation and The
requirements for the assignment and maintenance of this
The requirements for the assignment and maintenance
notation are given respectively in Pt E, Ch 10, Sec 6 and in
of this notation are given respectively in Pt E, Ch 10,
Ch 5, Sec 10.
Sec 2 and in Ch 5, Sec 10.
Note 2: This additional class notation may only be assigned to 6.14.7 Vapour control system
ships with the service notation general cargo ship (intended to
The additional class notation VCS (Vapour Control System)
carry dry bulk cargoes), ore carrier, combination car-
rier/OBO, combination carrier/OOC or bulk carrier not may be assigned to ships equipped with cargo vapour con-
assigned with the additional service feature CSR. trol systems. The notation -TRANSFER is added to the nota-
tion where, in addition, the ship is fitted with specific
However, this does not preclude ships not assigned with
arrangements for transferring cargo vapours to another ship.
this notation from being loaded/unloaded with grabs.
This notation is assigned only to ships having the service
6.14.3 In-water survey notation oil tanker, combination carrier/OBO ESP, combi-
The additional class notation INWATERSURVEY may be nation carrier/OOC ESP, liquefied gas carrier, chemical
assigned to ships provided with suitable arrangements to tanker or FLS tanker.
facilitate the in-water surveys as provided in Ch 2, Sec 2, The requirements for the assignment and maintenance of
[5.4.5]. this notation are given respectively in Pt E, Ch 10, Sec 7 and
The requirements for the assignment of this notation are in Ch 5, Sec 10.
given in Pt E, Ch 10, Sec 3.
6.14.8 Cofferdam ventilation
6.14.4 Single point mooring The additional class notation COVENT may be assigned to
The additional class notation SPM (Single Point Mooring) ships having cofferdams in the cargo area which can be
may be assigned to ships fitted with a specific mooring used as ballast tanks and which may be ventilated through a
installation. fixed ventilation system.
The requirements for the assignment and maintenance of This notation is assigned only to ships having the service
this notation are given respectively in Pt E, Ch 10, Sec 4 and notation bulk carrier, ore carrier, oil tanker, combination
in Ch 5, Sec 10. carrier/OBO, combination carrier/OOC, liquefied gas car-
rier, chemical tanker or FLS tanker.
These requirements reproduce the provisions of Recom-
mendations for Equipment Employed in the Mooring of The requirements for the assignment and maintenance of
Ships at Single Point Mooring (3rd edition 1993), issued by this notation are given respectively in Pt E, Ch 10, Sec 8 and
OCIMF (Oil Companies International Marine Forum). in Ch 5, Sec 10.
6.14.9 Centralised cargo control The requirements for the assignment and maintenance of
The additional class notation CARGOCONTROL may be these notations are given respectively in Pt E, Ch 10, Sec 11
assigned to ships (carrying liquid cargo in bulk) equipped and in Ch 5, Sec 10.
with a centralised system for handling cargo and ballast
liquids. 6.14.13 Liquid cold cargoes (COLD CARGO)
In principle, this notation is assigned only to ships having The additional class notation COLD CARGO is assigned to
the service notation oil tanker, combination carrier/OBO, ships having one of the service notation oil tanker, product
combination carrier/OOC, chemical tanker or FLS tanker. tanker or chemical tanker intended to be loaded with liq-
The requirements for the assignment and maintenance of uid cargoes:
this notation are given respectively in Pt E, Ch 10, Sec 9 and having a cargo temperature below 10C, in particular
in Ch 5, Sec 10. when loading is from cold storage tanks (winter condi-
tions), and
6.14.10 Ship manoeuvrability
The additional class notation MANOVR may be assigned to not needing to be heated in normal operating condi-
ships complying with the requirements related to manoeu- tions.
vring capability defined in Pt E, Ch 10, Sec 10.
The requirements for the assignment and maintenance of
Note 1: According to Resolution MSC.137(76), these provisions are
this notation are given respectively in Pt E, Ch 10, Sec 11
to be applied to ships of all rudder and propulsion types, of 100 m in
and in Ch 5, Sec 10.
length and over, and to chemical tankers and gas carriers regardless
of the length, which were constructed on or after 1 January 2004.
6.14.14 Green passport for ship recycling
6.14.11 Ship subdivision and damage stability The additional class notation GREEN PASSPORT may be
The additional class notation SDS may be assigned to ships assigned to ships for which requirements intended to facili-
for which a damage buoyancy, subdivision and stability file tate ship recycling have been applied, encompassing the
has been examined and found to satisfy the requirements identification, quantification and localization of materials
given in Pt B, Ch 3, Sec 3. which may cause harm to the environment and people
when the fittings or equipment containing such materials
An attestation of compliance may be issued to the Interested
are removed, or when the ship is recycled.
Party, specifying the rules and criteria considered for the
examination of the file. The requirements for the assignment and maintenance of
Note 1: As a rule, class assigned to a ship does not cover require- this notation are given in NR528 Green passport.
ments applicable to the assignment of the notation SDS.
6.14.12 Ships operating in cold weather conditions 6.14.15 Efficient washing of cargo tanks
The additional class notations COLD DI and COLD (H tDH , The additional class notation EWCT may be assigned to
E tDE) are assigned to ships intended to operate in cold cli- ships fitted with washing arrangements complying with the
mate environments as specified in Note 1. requirements given in Pt E, Ch 10, Sec 12.
Note 1:
This notation may only be assigned to ships having the serv-
- sea water temperature: not below 2C ice notation oil tanker, FLS tanker, or chemical tanker.
- wind speed: not higher than 30 knots.
The additional class notation COLD DI is assigned to ships
6.14.16 Protected FO tank
operating in cold climate environments for shorter periods,
not necessarily including ice covered waters and fitted with The additional class notation PROTECTED FO TANK may
systems and equipment for de-icing. be assigned to ships with an aggregate oil fuel capacity of
less than 600 m3, fitted with oil fuel tanks complying with
The additional class notation COLD (H tDH , E tDE) is
the requirements given in Pt E, Ch 10, Sec 13.
assigned to ships operating in cold weather conditions and
which are built and fitted with systems and equipment for
de-icing where tDH and tDE are defined, respectively for hull 6.14.17 Sealed liquefied natural gas carriers
and equipment exposed to low air temperature, by:
The additional class notation IATP (increased admissible
tDH : Lowest mean daily average air temperature in cargo tank pressure) may be assigned to ships intended to
the area of operation, in C, to be considered carry methane (LNG) whose maximum cargo tank design
for the hull exposed to low air temperature, pro- pressure does not exceed 70 kPa and that are designed and
vided by the ship designer built so as to allow the pressure in the tanks to increase
tDE : Lowest design external air temperature in the above 25 kPa.
area of operation, in C, to be considered for
This notation may only be assigned to ships having the serv-
the equipment exposed to low air temperature,
ice notation liquefied gas carrier or LNG bunkering ship.
provided by the ship designer. This temperature
can be set to about 20C below the lowest The requirements for the assignment of this notation are
mean daily average air temperature if informa- given in Pt E, Ch 10, Sec 14.
tion for the relevant trade area is not available.
6.14.18 Enhanced fire protection for cargo ships and 6.14.20 Fast Oil Recovery System (FORS)
tankers (EFP-AMC) The additional class notation FORS may be assigned to
The additional class notation EFP-A or EFP-M or EFP-C or ships with oil fuel tanks and cargo tanks, as applicable, fit-
EFP-AMC may be assigned to ships fitted with enhanced fire ted with two (or more) connectors allowing the recovery of
safety protection in, respectively, accommodation spaces or the tank contents as follows:
machinery spaces or cargo areas or all these spaces and by injecting sea water through one connector, the tank
areas. contents being recovered through the other one, and
This notation is assigned only to ships having the service by introducing a submersible pump in the tank through
notations as per [4.2] (Cargo ships), or [4.3] (Bulk, ore and one of the connectors.
combination carriers), or [4.4] (Ships carrying liquid cargo
The requirements for the assignment of this notation are
in bulk).
given in NR553 Fast Oil Recovery System.
The requirements for the assignment of these notations are The additional class notation FORS may be completed by
given in Pt E, Ch 10, Sec 15. the notation -NS when the connectors are intended to be
used during the normal service of the ship and, for that pur-
pose, comply with the additional requirements given in
6.14.19 Design fatigue life for oil tankers subject to
NR523 Common Structural Rules for Double Article [3] of NR553 Fast Oil Recovery System.
Hull Oil tankers For ships not assigned with the notation -NS, the connectors
may be used only to facilitate the recovery of the tank con-
The additional class notations: tents when the ship is damaged or wrecked.
Fatigue PLUS 6.14.21 High-Voltage Shore Connection Systems
(HVSC)
Fatigue PLUS DFL xx
The additional class notation HVSC may be assigned to
Fatigue PLUS spectral ( ), and ships fitted with electrical and control engineering arrange-
Fatigue PLUS spectral ( ) DFL xx, ments allowing operation of services by connection to an
external high-voltage electrical power supply in port.
may be assigned to ships for which the Society proposes an The requirements for the assignment of this notation are
extended scope of critical details in addition to the details given in NR557 High-Voltage Shore Connection Systems.
required to be checked by NR523 Common Structural Rules
for Double Hull Oil Tankers. 6.14.22 SINGLEPASSLOADING
The requirements for the assignment of these notations are The additional class notation SINGLEPASSLOADING may
be assigned to ships having the service notation ore carrier
given in NR552 Additional Class Notations Fatigue PLUS
for Oil Tanker CSR. which are specially designed for single pass loading.
Note 1: This additional class notation may be completed by the
Note 1: The additional class notations Fatigue PLUS, Fatigue PLUS design loading rate, in tons per hour, for example:
DFL xx, Fatigue PLUS spectral ( ) and Fatigue PLUS spectral ( )
SINGLEPASSLOADING [xxxxx t/h]
DFL xx may be assigned only to ships with the service notation oil
tanker ESP CSR. The additional class notation SINGLEPASSLOADING only
covers the loading sequences provided to the Society, as
The additional class notation Fatigue PLUS is assigned if all
referred to in Pt E, Ch 10, Sec 16.
analysed details comply with a design fatigue life equal to
25 years. The requirements for the assignment of this notation are
given in Pt E, Ch 10, Sec 16.
The additional class notation Fatigue PLUS DFL xx corre-
sponds to the notation Fatigue PLUS with an extended 6.14.23 Helideck (HEL)
design fatigue life of xx years, with xx above 25. The additional class notation HEL may be assigned to ships
complying with chapter II-2 of SOLAS and Civil Aviation
The additional class notations Fatigue PLUS spectral ( ) and
Publication (CAP) 437 when they are fitted with helicopter
Fatigue PLUS spectral ( ) DFL xx are introduced to consider
facilities subject to design review and construction and
wave environment areas encountered during trading other
installation survey by the Society.
than that considered in NR523 Common Structural Rules
for Double Hull Oil Tankers (i.e. North Atlantic). The infor- The requirements for the assignment and maintenance of
mation between brackets is a short description of the route this notation are given respectively in Pt E, Ch 10, Sec 20
or areas encountered by the ship during its service life. and in Ch 5, Sec 10.
The additional class notation Fatigue PLUS spectral ( ) is 6.14.24 Helicopter facilities for yachts
assigned if all analysed details comply with a design fatigue The additional class notation HEL(Y) may be assigned to
life equal to 25 years. yachts fitted with helicopter facilities.
The additional class notation Fatigue PLUS spectral ( ) DFL xx The requirements for the assignment of this notation are
is assigned if all analysed details comply with a design fatigue given in NR500 Rules for Yachts, Part B and Part C, Ch 4,
life of xx years, with xx above 25. Sec 11.
6.14.25 Bow Loading/Unloading Systems (BLUS) 6.14.30 Permanent means of access (ACCESS)
Stern Loading/Unloading Systems (SLUS)
The additional class notation ACCESS may be assigned to
The additional class notations BLUS or SLUS may be ships constructed on or after 1 January 2006 and:
assigned to ships having the service notation oil tanker and assigned with service notations as specified in [4.4.2]
fitted with bow or stern loading/unloading systems. for ships carrying oil cargo in bulk and of 500 gross ton-
nage and over, having integral tanks, or
The requirements for the assignment of these notations are
given in Pt E, Ch 10, Sec 17. assigned with service notations as specified in [4.3] for
bulk, ore and combination carrier of 20 000 gross ton-
6.14.26 Supply At Sea (SAS) nage and over.
The additional class notation SAS may be assigned to ships The requirements for the assignment and maintenance of
having the service notation supply vessel and operated for this notation are given respectively in Pt E, Ch 10, Sec 19
underway ship-to-ship supply at sea (SAS) of liquid and and in Ch 5, Sec 10.
solid supplies.
6.14.31 Elastic Shaft Alignment (ESA)
The requirements for the assignment of this notation are
given in Pt E, Ch 10, Sec 18. The additional class notation ESA may be assigned to ships
other than those covered by the scope of the relevant addi-
Note 1: Application to other service notations may be considered tional service feature as referred to in [4.13.1].
on a case-by-case basis.
The requirements for the assignment of this additional class
notation are given in Rule Note NR592 Elastic Shaft Align-
6.14.27 ACCOMMODATION
ment (ESA).
The additional class notation ACCOMMODATION may be Note 1: The request and applicability for this notation are achieved
assigned to ships found to be in compliance with the crite- respectively on a voluntary basis from the interested parties and on
ria of the Maritime Labour Convention and with the provi- a case-by-case basis.
sions contained in the Information Note NI 577 Design and
Construction of Crew Accommodation in respect of Title 3 6.14.32 The additional class notation STAB-WIND may be
of Maritime Labour Convention 2006. assigned, to yacht having the service notation yacht or char-
ter yacht satisfying the intact stability and weather criterion
The requirements for the maintenance of this notation are
as defined in Pt B, Ch 3, Sec 2, [3] of Rule Note NR500
given in Ch 5, Sec 10.
Rules for the Classification and the Certification of Yachts.
6.14.28 Loading instrument (LI) Note 1: The attention of the Owner and the Shipyard is drawn to
the fact that the flag Administration may impose an intact stability
The additional class notations LI-HG, LI-S1, LI-S2, LI-S3 and weather criterion calculation.
and LI-HG-S1, LI-HG-S2, LI-HG-S3 may be assigned to
ships equipped with a loading instrument. 6.14.33 Spectral fatigue analysis
The additional class notation Spectral Fatigue ( ) may be
The requirement for the assignment of these notations are
assigned when the fatigue check of structural details is per-
given in Pt B, Ch 10, Sec 2.
formed through spectral fatigue techniques. The information
Note 1: When the ship is equipped with a loading instrument per- between brackets is a short description of routes and areas
forming: considered for this spectral fatigue analysis.
- only hull girder calculations, the additional class notation LI- Example:
HG is assigned
Spectral Fatigue (North Atlantic)
- only intact stability calculations (when the ship is not required
to meet damage stability requirements), the additional class The Guidance Note NI539, Spectral Fatigue Analysis Meth-
notation LI-S1 is assigned odology for Ships and Offshore Units, is to be used.
- intact stability calculations and damage stability on a basis of a Other methodology may be used, subject to approval by the
limit curve, the additional class notation LI-S2 is assigned Society.
- intact stability calculations and direct damage stability calcula- 6.14.34 Offshore Handling Systems (OHS)
tions based on pre-programmed damage cases, the additional
class notation LI-S3 is assigned. The additional class notation OHS may be assigned to ships
having offshore handling systems such as winches, strand
When the loading instrument performs hull girder and stability cal- jacks, chain jacks, sheaves and their foundations used for
culations, one of the additional class notations LI-HG-S1, LI-HG-S2
lifting/pulling of a load.
or LI-HG-S3 is assigned, as applicable.
The requirements for the assignment and maintenance of
6.14.29 The additional class notations WhiSp1, WhiSp2 this notation are given respectively in NR595 Classification
and WhiSp3 may be assigned to ships complying with the of Offshore Handling Systems and in Ch 5, Sec 10.
requirements of NR583 Whipping and Springing Assess- Note 1: Specific procedures for non-permanent equipment are not
ment. applicable for ships.
ME-DF, when the main engine(s) is (are) of the dual fuel This notation is assigned only to ships having the service
type notation:
AEB, when the auxiliary engines and oil-fired boilers are - oil tanker or FLS tanker, and of less than 20000 tonnes
either of the dual fuel type, or designed for future con- deadweight, or
version to dual-fuel operation.
- chemical tanker for which an inert gas system is not
Examples: required in pursuance of July 2014 edition of the
Rules, Pt D, Ch 8, Sec 9, [1.3.1].
GAS-PREPARED
GAS-PREPARED (P) The requirements for the assignment of the notation IG
are given in July 2014 edition of the Rules:
GAS-PREPARED (P, ME-DF)
- Pt D, Ch 7, Sec 6, [5.1.2], for oil tankers or FLS tank-
GAS-PREPARED (S, P, ME-DF) ers, and
Note 1: When the ship is effectively converted to dual-fuel opera- - Pt D, Ch 8, Sec 9, [2.5.3], for chemical tankers.
tion, the additional class notation GAS-PREPARED will be replaced
by the additional service feature dualfuel, provided that all the Ships contracted for construction on or after 1 January
applicable requirements given in [4.11.1] are complied with. 2016:
6.14.37 BATTERY SYSTEM This notation is assigned only to ships having the service
notation oil tanker, FLS tanker or chemical tanker, and
The additional class notation BATTERY SYSTEM may be of less than 8000 tonnes deadweight.
assigned to ships when batteries are used for propulsion
and/or electric power supply purpose during operation of The requirements for the assignment of the notation IG
the ship. This notation is mandatory when the ship is only are given in:
relying on batteries for propulsion and/or electrical power
supply for main sources. - Pt D, Ch 7, Sec 6, [5.1.3], for oil tankers or FLS
tankers, and
The requirements for the assignment of this notation are
given in Pt E, Ch 10, Sec 21. - Pt D, Ch 8, Sec 9, [2.3], for chemical tankers.
1 Application for surveys and Note 1: At Owners request, change over from former to current
notations may be performed before the next class renewal survey.
correspondence with current
notations
1.3 Application of scope of surveys
1.1 General 1.3.1 For periodicity and scope of surveys for maintenance
of class of ships being still assigned class notations accord-
1.1.1 The current edition of the Rules uses a different sys- ing to editions of the Rules former to June 2000 edition,
tem of class notations, in comparison with the one in force
tables given in [1.4] indicate which requirements are appli-
in the editions of the Rules former to June 2000 edition.
cable to such notations, with reference to class notations of
Subarticle [1.4] gives correspondence between the nota- the current Rules.
tions assigned to ships according to the editions of the Rules
former to June 2000 edition and the class notations
assigned according to the current edition. 1.4 Correspondence between former and
current notations
1.2 Phasing out from former to current
1.4.1 Tab 1 gives correspondence between former class
notations
symbols and construction marks and the current ones.
Chapter 2
1.1.1 Class is assigned to a ship upon a survey, with the asso- 2.1.5 Use of materials, machinery, appliances and
ciated operations, which is held in order to verify whether it is items
eligible to be classed on the basis of the Rules of the Society As a general rule, all materials, machinery, boilers, auxiliary
(see Ch 1, Sec 1, [1.3.2]). This may be achieved through: installations, equipment, items etc. (generally referred to as
the completion of the new building, during which a sur- "products") which are covered by the class and used or fitted
vey has been performed, on board ships surveyed by the Society during construction
are to be new and, where intended for essential services as
a survey carried out according to the agreement devel-
defined in Ch 1, Sec 1, [1.2.1], tested by the Society.
oped by the IACS Member Societies when ships change
class between members, or Second hand materials, machinery, appliances and items
a specific admission to class survey, in cases where a ship may be used subject to the specific agreement of the Soci-
is classed with a non-IACS Society or is not classed at all. ety and the Owner.
The requirements for the selection of materials to be used in
2 New building procedure the construction of the various parts of a ship, the character-
istics of products to be used for such parts and the checks
required for their acceptance are to be as stated in Part C of
2.1 Ships surveyed by the Society during
the Rules (NR467) and in NR216 Materials and Welding, as
construction applicable, or in other Parts of NR467, or as specified on
2.1.1 When a ship is surveyed by the Society during con- approved plans. In particular, the testing of products manu-
struction, it is to comply with those requirements of the factured according to quality assurance procedures
Rules which are in force and applicable depending on the approved by the Society and the approval of such proce-
class of the ship, taking into account the provisions of Ch 1, dures are governed by the requirements of NR216 Materials
Sec 1, [2.1] and Ch 1, Sec 1, [2.2]. and Welding, Ch 1, Sec 1, [3].
The hull surveys for new constructions are to be carried out Attention is drawn to the provisions of the EC Regulation
in accordance with the requirements of Ch 3, Sec 7. 391/2009, specifically Article 10.
for ships which are 20 years of age and above, the b) Hull structure plans:
survey is to have the scope of a class renewal survey Midship section
in the two latter cases, if a bottom survey in dry con- Scantling plan
dition is not due at the time of transfer, consideration Decks
can be given to carrying out a bottom in-water sur- Shell expansion
vey in lieu of bottom survey in dry condition.
Transverse bulkheads
c) Survey of machinery. A general examination of all Rudder and rudder stock
essential machinery is to be held including at least the Hatch covers
following:
For ship assigned with the additional service feature
Examination under working condition of oil fuel CSR, plans showing, for each structural element,
burning equipment, boilers, economizers and both as-built and renewal thicknesses and any thick-
steam/steam generators. The adjustment of safety ness for voluntary addition.
valves of this equipment is to be verified by check- c) Machinery plans:
ing the records on board ship
Machinery arrangement
All pressure vessels are to be examined Intermediate, thrust and screw shafts
Insulation resistance, generator circuit breakers, Propeller
preference tripping relays and generator prime Main engines, propulsion gears and clutch systems
mover governors are to be tested and paralleling and (or Manufacturers make, model and rating informa-
load sharing to be proved tion)
In all cases, navigating lights and indicators are to be For steam turbine ships, main boilers, superheaters
examined and their working and alternative sources and economisers (or Manufacturers make, model
of power verified and rating information) and steam piping
Bilge pumps, emergency fire pumps and remote Bilge and ballast piping diagram
controls for oil valves, oil fuel pumps, lubricating oil Wiring diagram
pumps and forced draught fans are to be examined Steering gear system piping and arrangements and
under working condition steering gear Manufacturers make and model infor-
Recirculating and ice clearing arrangements, if any mation
Torsion vibration calculations, for ships less than
The main and all auxiliary machinery necessary for two years old
operation of the ship at sea together with essential
Plans for flexible couplings and/or torque limiting
controls and steering gear is to be tested under
shafting devices in the propulsion line shafting (or
working conditions. Alternative means of steering
Manufacturers make, model and rating information),
are to be tested
for ships assigned with one of the ice class additional
A short sea trial is to be held, at the Surveyors dis- class notations described in Ch 1, Sec 2, [6.10.2]
cretion, if the ship has been laid up for a long period Pumping arrangements at the forward and after
Initial start arrangements are to be verified ends, drainage of cofferdams and pump rooms and
general arrangements of cargo piping in tanks and
In the case of oil tankers, the cargo oil system and on decks, for oil tankers.
electrical installations in way of hazardous spaces
are to be checked for compliance with rule require- d) Plans required for ships assigned one of the additional
ments. Where intrinsically safe equipment is class notations for Automated Machinery Systems:
installed, the Surveyors are to satisfy themselves that Instrument list
such equipment has been approved by a recognised Fire alarm system
authority. The safety devices, alarms and essential Plans for systematic maintenance and functioning
instruments of the inert gas system are to be verified tests.
and the plant generally examined to ensure that it Alternative technical data may be accepted by the Society
does not constitute a hazard to the ship.
in lieu of specific items of the listed documentation not
available at the time of the transfer of class.
3.2.3 Documentation
As a rule, the documentation to be supplied is the following. 3.2.4 For ships of less than 100 gross tonnage, special con-
sideration will be given to the scope of surveys and docu-
a) Main plans: mentation to be supplied.
General arrangement
Capacity plan
3.3 Ships not classed with an IACS Society
Hydrostatic curves 3.3.1 In this case, the class of the ship will be assigned
upon a preliminary review of the documentation listed in
Loading manual, where required
[3.3.3] and subsequent satisfactory completion of the sur-
Damage stability calculation, where required. veys, the extent and scope of which are given below.
1 General principles of surveys The surveys are to be carried out in accordance with the rel-
evant requirements in order to confirm that the hull,
machinery, equipment and appliances comply with the
1.1 Survey types applicable Rules and will remain in satisfactory condition
based on the understanding and assumptions mentioned in
1.1.1 Classed ships are submitted to surveys for the mainte- Ch 1, Sec 1, [3.3].
nance of class. These surveys include the class renewal sur-
vey, intermediate and annual survey, bottom survey (either Where the conditions for the maintenance of the class, serv-
survey in dry condition or in-water survey), tailshaft survey, ice notations and additional class notations are not com-
boiler survey, and surveys for the maintenance of additional plied with, the class and/or the service notation and/or the
class notations, where applicable. Such surveys are carried additional class notations as appropriate will be suspended
out at the intervals and under the conditions laid down in and/or withdrawn in accordance with the applicable Rules
this Section. In addition to the above periodical surveys, given in Ch 2, Sec 3.
ships are to be submitted to occasional surveys whenever
the circumstances so require; refer to [6], also when the Note 1: It is understood that requirements for surveys apply to
Owner requires a specific survey in case of sales; refer to those items that are required according to the Rules or, even if not
Article [7]. required, are fitted on board.
1.1.2 The different types of periodical surveys are summa- 1.1.3 Unless specified otherwise, any survey other than
rised in Tab 1. The intervals at which the periodical surveys bottom survey and tailshaft survey may be effected by carry-
are carried out are given in the items referred to in the sec- ing out partial surveys at different times to be agreed upon
ond column of Tab 1. The relevant extent and scope are with the Society, provided that each partial survey is ade-
given in Part A, Chapter 3 and Part A, Chapter 4 for all ships quately extensive. The splitting of a survey into partial sur-
and for service notations, respectively, while surveys related veys is to be such as not to impair its effectiveness.
to additional class notations are given in Part A, Chapter 5.
Where there are no specific survey requirements for addi- 1.1.4 Special consideration may be given in application of
tional class notations assigned to a ship, equipment and/or Ch 3, Sec 1 to Ch 3, Sec 6 to commercial ships owned or
arrangements related to these additional class notations are chartered by Administrations, which are utilized in support
to be examined, as applicable, to the Surveyors satisfaction of military operations or service.
at each class renewal survey for the class.
1.2 Change of periodicity, postponement or 1.4.2 When a survey results in the identification of signifi-
advance of surveys cant corrosion, structural defects or damage to hull,
machinery and/or any piece of its equipment which, in the
1.2.1 The Society reserves the right, after due considera- opinion of the Surveyor, affect the ships class, remedial
tion, to change the periodicity, postpone or advance sur- measures are to be implemented before the ship continues
veys, taking into account particular circumstances. in service (see also [2.11]).
Note 1: The Society's survey requirements cannot be considered as
1.2.2 When a survey becomes overdue during a voyage, a substitute for specification and acceptance of repairs and mainte-
nance, which remain the responsibility of the Owner.
the following applies:
Note 2: In accordance with the provisions of Ch 1, Sec 1, [4.1.3],
a) In the case of a class renewal survey, the Society may the Society will, at the request of the Owner, apply the regulations
grant an extension to allow for completion of the class of Administrations concerning the scope and periodicity of surveys
renewal survey, provided there is documented agree- when they differ from those laid down in [4] and [5].
ment to such an extension prior to the expiry date of the Note 3: During the surveys, the Surveyor does not check that the
Certificate of Classification, adequate arrangements spare parts are kept on board, maintained in working order and
have been made for attendance of the Surveyor at the suitably protected and lashed.
first port of call and the Society is satisfied that there is
technical justification for such an extension. Such an 1.5 Appointment of another Surveyor
extension will be granted only until arrival at the first
port of call after the expiry date of the Certificate of 1.5.1 In compliance with the provisions of Ch 1, Sec 1,
Classification. [2.4.1], should a disagreement arise between the Owner
and the Surveyor during a survey, the Society may, at the
However, if owing to exceptional circumstances as request of the Owner, designate another Surveyor.
defined in [2.1.7], the class renewal survey cannot be
completed at the first port of call, the Society may grant
an extension according to [4.1.1], but the total period of 2 Definitions and procedures related
extension shall in no case be longer than three months to surveys
after the original limit date of the class renewal survey.
b) In the case of annual and intermediate surveys, no post- 2.1 General
ponement is granted. Such surveys are to be completed
2.1.1 Period of class
within their prescribed windows; see [2.1.3].
Period of class means the period starting either from the date
c) In the case of all other periodical surveys and recom- of the initial classification, see Ch 2, Sec 1, [4], or from the
mendations, extension of class may be granted until the credited date of the last class renewal survey, and expiring at
arrival of the ship at the port of destination. the limit date assigned for the next class renewal survey.
1.4.1 The general procedure of survey consists in: Anniversary date: 15th April
The 2000 annual survey can be validly carried out from
an overall examination of the parts of the ship covered 16th January 2000 to 15th July 2000. If not completed by
by the rule requirements
15th July 2000, the annual survey becomes overdue.
checking selected items covered by the rule require- Last bottom survey 20th October 2000:
ments
If not completed by 20th October 2003 or end of the
attending tests and trials where applicable and deemed class period, whichever comes first, the bottom survey
necessary by the Surveyor. becomes overdue.
2.2.13 Corrosion prevention system 2.3.2 For all ships, the following applies:
A corrosion prevention system is normally considered a full thickness measurements required in the context of sur-
hard protective coating. veys of hull structure is to be witnessed by a Surveyor.
This requires the Surveyor to be on board while the
Hard protective coating is usually to be epoxy coating or gaugings are taken, enabling him at any time to inter-
equivalent. Other coating systems, which are neither soft vene and to control the process.
nor semi-hard coatings, may be considered acceptable as
alternatives, provided that they are applied and maintained prior to commencement of the intermediate or class
in compliance with the Manufacturer's specifications. renewal survey, a meeting is to be held between the
attending Surveyor(s), the master of the ship or an
appropriately qualified representative appointed by the
2.2.14 Coating condition master or Company, the Owners representative(s) in
Coating condition is defined as follows: attendance and the thickness measurement firms repre-
good: condition with only minor spot rusting sentative(s) so as to ensure the safe and efficient execu-
tion of the surveys and thickness measurements to be
fair: condition with local breakdown at edges of stiffen- carried out onboard.
ers and weld connections and/or light rusting over 20%
or more of areas under consideration, but less than as
2.3.3 In any kind of survey, i.e. class renewal, intermediate,
defined for poor condition
annual or other surveys having the same scope, thickness
poor: condition with general breakdown of coating over measurements of structures in areas where close-up surveys
20% or more or hard scale at 10% or more, of areas are required, are to be carried out simultaneously with
under consideration. close-up surveys.
2.2.15 Cargo area (ships carrying liquid cargo in bulk) 2.3.4 Thickness measurement is normally to be carried out
The cargo area is that part of the ship which contains cargo by means of ultrasonic test equipment. The accuracy of the
tanks, slop tanks and cargo/ballast pump rooms, compres- equipment is to be proven to the Surveyor as required. The
sor rooms, cofferdams, ballast tanks and void spaces adja- thickness measurements are to be carried out by a company
cent to cargo tanks and also deck areas throughout the authorised by the Society.
entire length and breadth of the part of the ship over the The Society reserves the right to limit the scope of authorisa-
above-mentioned spaces. tion of the Company.
Note 1: Rule Note NR533 Approval of Service Suppliers gives
2.2.16 Cargo length area (dry cargo ships) details about the authorisation.
The cargo length area is that part of the ship which includes
cargo holds and adjacent areas including fuel tanks, coffer- 2.3.5 A thickness measurement report is to be prepared.
dams, ballast tanks and void spaces. The report is to give the location of measurements, the
thickness measured and the corresponding original thick-
2.2.17 Prompt and thorough repair ness. Furthermore, the report is to include the date when
A Prompt and thorough repair is a permanent repair com- the measurements were carried out, the type of measuring
pleted at the time of survey to the satisfaction of the Sur- equipment, the names and the qualification of the operators
veyor, therein removing the need for the imposition of any and their signatures.
associated recommendation. See also [2.11]. The Surveyor is to review the final thickness measurement
report and countersign the cover page.
2.2.18 Special consideration
Special consideration or specially considered (in connec- 2.3.6 For acceptance criteria applicable to structural corrosion
tion with close-up surveys and thickness measurements) diminution levels, reference is to be made to Ch 2, App 3.
means sufficient close-up inspection and thickness meas-
urements are to be taken to confirm the actual average con- 2.4 Agreement of firms for in-water survey
dition of the structure under the coating.
2.4.1 The in-water surveys referred to in the Rules are to be
2.2.19 Air pipe head carried out by a certified company accepted by the Society.
Air pipe heads installed on the exposed decks are those Note 1: Rule Note NR533 Approval of Service Suppliers gives
extending above the freeboard deck or superstructure details about the certification.
decks.
2.5 Preparations and conditions for surveys 2.5.4 Explosimeter, oxygen-meter, breathing apparatus,
lifelines, riding belts with rope and hook and whistles
2.5.1 The Owner is to provide the necessary facilities for together with instructions and guidance on their use are to
the safe execution of the surveys, as per Ch 1, Sec 1, be made available during the survey. A safety check-list is to
[3.2.2]. be provided.
2.5.2 Cargo holds, tanks and spaces are to be safe for 2.5.5 Adequate and safe lighting is to be provided for the
access. Cargo holds, tanks and spaces are to be gas free and safe and efficient conduct of the survey.
properly ventilated. Prior to entering a tank, void or
enclosed space, it is to be verified that the atmosphere in
the tank or space is free from hazardous gas and contains 2.5.6 Adequate protective clothing is to be made available
sufficient oxygen. and used (e.g. safety helmet, gloves, safety shoes, etc.) dur-
ing the survey.
In preparation for survey and thickness measurements and
to allow for a thorough examination, all spaces are to be 2.5.7 Surveys of tanks or applicable holds by means of
cleaned including removal from surfaces of all loose accu- boats or rafts may only be undertaken with the agreement of
mulated corrosion scale. Spaces are to be sufficiently clean the Surveyor, who is to take into account the safety arrange-
and free from water, scale, dirt, oil residues, etc. to reveal ments provided, including weather forecasting and ship
corrosion, deformation, fractures, damages or other struc- response under foreseeable conditions and provided the
tural deterioration as well as the condition of the coating. expected rise of water within the tank does not exceed
However, those areas of structure whose renewal has 0,25m.
already been decided by the Owner need only be cleaned
and descaled to the extent necessary to determine the limits
of the areas to be renewed. 2.5.8 When rafts or boats will be used for close-up survey
the following conditions are to be observed:
Sufficient illumination is to be provided to reveal corrosion,
a) only rough duty, inflatable rafts or boats, having satisfac-
deformation, fractures, damages or other structural deterio-
tory residual buoyancy and stability even if one cham-
ration as well as condition of the coating.
ber is ruptured, are to be used
Where soft or semi-hard coatings have been applied, safe b) the boat or raft is to be tethered to the access ladder and
access is to be provided for the Surveyor to verify the effec- an additional person is to be stationed down the access
tiveness of the coating and to carry out an assessment of the ladder with a clear view of the boat or raft
conditions of internal structures which may include spot
removal of the coating. When safe access cannot be pro- c) appropriate lifejackets are to be available for all partici-
vided, the soft or semi-hard coating is to be removed. pants
Casings, ceilings or linings, and loose insulation, where fit- d) the surface of water in the tank or hold is to be calm
ted, are to be removed, as required by the Surveyor, for (under all foreseeable conditions the expected rise of
examination of plating and framing. Compositions on plat- water within the tank is not to exceed 0,25 m) and the
ing are to be examined and sounded, but need not be dis- water level stationary. On no account is the level of the
turbed if found adhering satisfactorily to the plating. water to be rising while the boat or raft is in use
In refrigerated cargo spaces the condition of the coating e) the tank, hold or space must contain clean ballast water
behind the insulation is to be examined at representative only. Even a thin sheen of oil on the water is not accept-
locations. The examination may be limited to verification able, and
that the protective coating remains effective and that there f) at no time is the water level to be allowed to be within
are no visible structural defects. Where POOR coating con- 1 m of the deepest under deck web face flat so that the
dition is found, the examination is to be extended as survey team is not isolated from a direct escape route to
deemed necessary by the Surveyor. The condition of the the tank hatch. Filling to levels above the deck trans-
coating is to be reported. If indents, scratches, etc., are verses is only to be contemplated if a deck access man-
detected during surveys of shell plating from the outside, hole is fitted and open in the bay being examined, so
insulations in way are to be removed as required by the Sur- that an escape route for the survey party is available at
veyor, for further examination of the plating and adjacent all times. Other effective means of escape to the deck
frames. may be considered.
g) if the tanks (or spaces) are connected by a common
2.5.3 A communication system is to be arranged between venting system, or Inert Gas system, the tank in which
the survey party in the cargo hold, tank or space being the boat or raft is to be used is to be isolated to prevent a
examined, the responsible officer on deck and, as the case transfer of gas from other tanks (or spaces).
may be, the navigation bridge. The communication arrange-
ments are to be maintained throughout the survey. This sys-
tem is also to include the personnel in charge of ballast 2.5.9 Rafts or boats alone may be allowed for inspection of
pump handling if boats or rafts are used. the under deck areas for tanks or spaces, if the depth of the
webs is 1,5 m or less.
Figure 1 : Platform position and ullage corresponding to the maximum water level
for oil tankers and chemical tankers
3,0 m
3,0 m
If the depth of the webs is more than 1,5 m, rafts or boats insulation of compartments intended for refrigerated
alone may be allowed only: cargoes is to be removed over the necessary extent for
examination by the Surveyor of the condition of the
when the coating of the under deck structure is in
structure, unless constructional arrangements make
GOOD condition and there is no evidence of wastage;
such inspections possible without removing the insula-
or
tion.
if a permanent means of access is provided in each bay
to allow safe entry and exit. This means: 2.6 Access to structures
- access direct from the deck via a vertical ladder and
a small platform fitted approximately 2 m below the 2.6.1 For overall survey, means are to be provided to ena-
deck in each bay; or ble the Surveyor to examine the hull structure in a safe and
practical way.
- access to deck from a longitudinal permanent plat-
form having ladders to deck in each end of the tank. 2.6.2 For close-up survey, one or more of the following
The platform shall, for the full length of the tank, be means for access, acceptable to the Surveyor, is to be pro-
arranged in level with, or above, the maximum vided:
water level needed for rafting of under deck struc-
permanent staging and passages through structures
ture. For this purpose, the ullage corresponding to
the maximum water level is to be assumed not more temporary staging and passages through structures
than 3 m from the deck plate measured at the mid- hydraulic arm vehicles such as conventional cherry
span of deck transverses and in the middle length of pickers, lifts and movable platforms
the tank (see Fig 1).
boats or rafts
If neither of the above conditions are met, then staging or an other equivalent means.
other equivalent means is to be provided for the survey of
the under deck areas.
2.7 Equipment for surveys
The use of rafts or boats as mentioned above does not pre-
clude the use of boats or rafts to move about within a tank 2.7.1 One or more of the following fracture detection pro-
during a survey. cedures may be required if deemed necessary by the Sur-
veyor:
2.5.10 When examination of associated structure is radiographic equipment
required, the following applies:
ultrasonic equipment
ceilings in holds and floors in the engine room are to be magnetic particle equipment
lifted to the necessary extent for examination of the
structure dye penetrant.
in the case of solid ballast spaces, the solid ballast is to 2.8.1 If breathing apparatus and/or other equipment is used
be partially removed for examination of the condition of as Rescue and emergency response equipment then it is
the structure in way. Should doubts arise, the Surveyor recommended that the equipment should be suitable for the
may require more extensive removal of the solid ballast configuration of the space being surveyed.
2.9 Surveys at sea and anchorage 2.11.2 For locations where adequate repair facilities are
not available, consideration may be given to allow the ship
2.9.1 Surveys at sea or at anchorage may be accepted pro- to proceed directly to a repair facility. This may require dis-
vided the Surveyor is given the necessary assistance by the charging the cargo and/or temporary repairs for the
personnel on board. Precautions and procedures for carry- intended voyage.
ing out the survey are to be in accordance with [2.5], [2.6]
and [2.7]. 2.11.3 Additionally, when a survey results in the identifica-
tion of structural defects or corrosion, either of which, in the
opinion of the Surveyor, will impair the vessels fitness for
2.10 Repairs and maintenance during voyage
continued service, remedial measures are to be imple-
2.10.1 Where repairs to hull, machinery or other equip- mented before the ship continues in service.
ment, which affect or may affect the class, are to be carried 2.11.4 Where the damage found on structure mentioned in
out by a riding crew during a voyage, they are to be [2.11.1] is isolated and of a localised nature which does not
planned in advance. A complete repair procedure including affect the ship's structural integrity, consideration may be
the extent of proposed repair and the need for the Sur- given by the Surveyor to allow an appropriate temporary
veyor's attendance during the voyage is to be submitted to repair to restore watertight or weathertight integrity and
the Society for approval sufficiently in advance. Failure to impose a Recommendation in accordance with the Rules,
notify the Society in advance of the repairs may result in the with a specific time limit.
suspension of class of the ship.
Where in any emergency circumstance, emergency repairs 3 Certificate of Classification: issue,
are to be effected immediately, the repairs should be docu-
mented in the ships log and submitted thereafter to the validity, endorsement and renewal
Society for use in determining further survey requirements.
3.1 Issue of Certificate of Classification
2.10.2 The above is not intended to include maintenance
to and overhaul of the hull, machinery and equipment in 3.1.1 A Certificate of Classification, bearing the class nota-
accordance with the Manufacturers recommended proce- tions assigned to the ship and an expiry date, is issued to
dures and established marine practice, which does not any classed ship.
require the Society's agreement. However, any repair result- 3.1.2 A Provisional Certificate of Classification may serve
ing from such maintenance and overhauls which affects or as a Certificate of Classification in some cases, such as after
may affect the class is to be noted in the ship's log and sub- an admission to class survey, after a class renewal survey, or
mitted to the attending Surveyor for use in determining fur- when the Society deems it necessary.
ther survey requirements.
The period of validity for the Provisional Certificate of Classi-
fication is not to exceed 6 months from the date of issuance.
2.11 Repairs
3.1.3 The Certificate of Classification is to be made availa-
2.11.1 Any damage in association with wastage over the ble to the Societys Surveyors upon request.
allowable limits (including buckling, grooving, detachment
or fracture), or extensive areas of wastage over the allowa- 3.2 Validity of Certificate of Classification,
ble limits, which affects or, in the opinion of the Surveyor,
will affect the ships structural, watertight or weathertight
maintenance of class
integrity, is to be promptly and thoroughly (see [2.2.17]) 3.2.1 According to Ch 1, Sec 1, [2.4], the Society alone is
repaired. qualified to confirm the class of the ship and the validity of
Areas to be considered include, as applicable for the differ- its Certificate of Classification.
ent ship types:
3.2.2 During the class period, a Certificate of Classification
side structure and side plating; side shell frames, their
is valid when it is not expired.
end attachments and adjacent shell plating; inner side
structure and inner side plating The class is maintained during a certain period or at a given
date, when during the said period or at such date the condi-
deck structure and deck plating
tions for suspension or withdrawal of class are not met.
bottom structure and bottom plating; inner bottom
Refer also to Ch 1, Sec 1, [1.3.4].
structure and inner bottom plating
longitudinal bulkheads structure and longitudinal bulk- 3.2.3 At the request of the Owner, a statement confirming
heads plating, where fitted the maintenance of class may be issued by the Society based
watertight or oiltight bulkheads structure and plating on the information in its records for that ship at the time.
This statement is issued on the assumption that the Owner
hatch covers or hatch coamings, where fitted
has complied with the Rules, in particular with [6].
weld connection between air pipes and deck plating
Should any information which would have prevented the
air pipe heads installed on the exposed decks Society from issuing the statement and which was not avail-
ventilators, including closing devices, if any; bunker able at the time subsequently come to light, the statement
and vent piping systems. may be cancelled.
Attention is drawn to Ch 2, Sec 3, [1.2], whereby the Soci- In cases where the vessel has been laid up or has been out
ety, upon becoming aware of a breach of the Rules, is of service for a considerable period because of a major
empowered to suspend class from the date of the breach, repair or modification and the Owner elects to carry out
which may be prior to the date of the statement. only the overdue surveys, the next period of class will start
from the expiry date of the renewal survey. If the Owner
3.2.4 According to the same conditions as in [3.2.3], a elects to carry out the next due renewal survey, the period
statement declaring that the class is maintained clean and of class will start from the survey completion date.
free from recommendation may be issued by the Society
when there is no pending recommendation at that date. 4.1.3 A new period of class is assigned to the ship after the
satisfactory completion of the class renewal survey, and a
3.2.5 Classification-related documents and information are new Certificate of Classification is issued for the new period
liable to be invalidated by the Society whenever their object of class.
is found to differ from that on which they were based or to
be contrary to the applicable requirements. The Owner is 4.1.4 Concurrent crediting to both Intermediate Survey and
liable for any damage which may be caused to any third Class Renewal Survey for surveys and thickness measure-
party from improper use of such documents and informa- ments of spaces are not acceptable.
tion.
4.2 Normal survey system (SS)
3.3 Endorsement of Certificate of
4.2.1 When the normal survey system is applied to ships
Classification
with a 5 years period of class, the class renewal survey may
3.3.1 Text of endorsement be commenced at the fourth annual survey and continued
during the following year with a view to completion by its
When surveys are satisfactorily carried out, the Certificate due date. In this case the survey may be carried out by par-
of Classification is generally endorsed accordingly, with the tial surveys at different times. The number of checks to be
relevant entries. performed at each partial survey and the interval between
partial surveys are to be agreed by the Society.
3.3.2 Possible modifications to endorsements
The Society reserves the right to modify the endorsements 4.2.2 A class renewal survey may be commenced before
made by Surveyors. the fourth annual survey at the request of the Owner. In this
case, the survey is to be completed within fifteen months.
3.4 Status of surveys and recommendations The conditions for the execution of partial surveys are the
same as those referred to in [4.2.1].
3.4.1 Information given in the Certificate of Classification,
associated endorsements, Rules and specific documents 4.3 Continuous survey system (CS)
enables the Owner to identify the status of surveys and rec-
ommendations. 4.3.1 The request by the Owner for admission to the con-
tinuous survey system will be considered by the Society and
3.4.2 The omission of such information does not absolve agreement depends on the type and age of hull and
the Owner from ensuring that surveys are held by the limit machinery. This system may apply to the class renewal sur-
dates and pending recommendations are cleared to avoid vey of hull (CSH), machinery (CSM) or other installations
any inconvenience which is liable to result from the suspen- such as refrigerating installations (CSR) covered by an addi-
sion or withdrawal of class; see Ch 2, Sec 3. tional class notation.
4.3.3 For ships other than those referred to in [4.3.2], the con- 4.3.13 The continuous survey system may be discontinued
tinuous survey system is not applicable to the class renewal at any time at the discretion of the Society, or at the request
survey of the hull of ships over 20 years old. However, consid- of the Owner, and a specific arrangement devised.
eration may be given, at the discretion of the Society, to the
applicability of the continuous survey system to the class 4.4 Planned maintenance survey system for
renewal survey of the hull of ships over 20 years old.
machinery (PMS)
4.3.4 When the continuous survey system is applied, this is
4.4.1 A planned maintenance survey system may be con-
indicated in the Certificate of Classification and appropriate
sidered as an alternative to the continuous survey system for
notations as indicated in [4.3.1] are entered in the Register
machinery and is limited to components and systems cov-
of Ships.
ered by it. When such a system is implemented, a survey
4.3.5 Ships subject to the continuous survey system are system other than those normally adopted and with inter-
provided with lists of items to be surveyed under this sys- vals different from those of the continuous survey system as
tem. detailed in [4.3] may be accepted.
4.3.6 For items surveyed under the continuous survey sys- 4.4.2 The conditions for review of the planned mainte-
tem, the following requirements generally apply: nance survey system, the determination of survey item inter-
vals and the general scope of surveys are detailed in Ch 2,
a) the interval between two consecutive surveys of each App 1.
item is not to exceed five years
b) the items are to be surveyed in rotation, so far as practi- 4.4.3 The conditions related to Chief Engineers inspections
cable ensuring that approximately equivalent portions within the scope of PMS are given in Ch 2, App 2.
are examined each year
4.4.4 The planned maintenance survey system does not
c) the Society may credit for continuous survey results of
supersede the annual surveys and other periodical and
surveys carried out before the admission to the continu-
occasional surveys.
ous survey scheme
d) each item is to be surveyed at one time, as far as practi- 4.4.5 A general examination of the machinery, as detailed
cable; the Society may, however, allow possible repair in Ch 3, Sec 1 for annual surveys, is to be carried out.
work to be carried out within a certain period.
4.4.6 The planned maintenance survey system may be dis-
continued at any time at the discretion of the Society, or at
4.3.7 For ships more than ten years of age, the ballast tanks
the request of the Owner, and a specific arrangement
are to be internally examined twice in each five-year class
devised.
period, i.e. once within the scope of the intermediate sur-
vey and once within the scope of the continuous survey sys-
tem for the class renewal survey. 5 Other periodical surveys
4.3.8 For ships under continuous survey, items not
5.1 General
included in the continuous survey cycle are to be inspected
according to the provisions given in [4.2]. Bottom surveys 5.1.1 The different types of periodical surveys are summa-
are to be carried out according to the requirements of [5.4]. rised in Tab 1.
In addition, the bottom survey which is to be carried out in
conjunction with the end of class period is to be performed
within 15 months before the end of this class period. 5.2 Annual surveys
4.3.9 Upon application by the Owner, the Society may 5.2.1 Annual surveys are to be carried out within three
agree, subject to certain conditions, that some items of months before or after each anniversary date.
machinery which are included in the continuous survey
cycle are examined by the Chief Engineer where the Society 5.3 Intermediate surveys
is not represented. The Chief Engineers inspection is to be
followed by a confirmatory survey carried out by a Sur- 5.3.1 An intermediate survey, where applicable, is to be
veyor. The conditions for the application of this procedure carried out within the window from three months before the
are given in Ch 2, App 2. second to three months after the third anniversary date.
5.3.4 The intermediate survey is not applicable to ships 5.4.6 Ships with service notation HSC, HSC-CAT A, HSC-
with class symbol II. CAT B are to be submitted to a bottom survey in dry condi-
tion at each annual survey and each class renewal survey.
5.3.5 Concurrent crediting to both Intermediate Survey and
Class Renewal Survey for surveys and thickness measure-
ments of spaces are not acceptable. 5.4.7 The interval between examinations of the outside of
the ship's bottom and related items for ships operating in
fresh water and for certain harbour or non-self-propelled
5.4 Bottom survey craft may be greater than that given above, as approved by
the Society.
5.4.1 Bottom survey means the examination of the outside
of the ships bottom and related items. This examination
may be carried out with the ship either in dry dock (or on a 5.5 Tailshaft survey
slipway) or afloat: in the former case the survey will be
referred to as dry-docking survey, while in the latter case as
5.5.1 Definition
in-water survey.
Tailshaft survey means survey of propeller shafts and tube
5.4.2 The Owner is to notify the Society whenever the out- shafts (hereafter referred to as tailshafts) as well as survey of
side of the ships bottom and related items can be examined other propulsion systems.
in dry dock or on a slipway.
5.5.2 Tailshaft complete survey
5.4.3 For ships classed with the class symbol I, there are to
be two examinations of the outside of the ships bottom and Tailshafts are to be submitted to complete examination at
related items in each period of class of five years the periodicity specified below and summarised in Fig 2,
In all cases, the interval between any two such examina- based on the type of shaft and its design.
tions is not to exceed 36 months.
a) Where the tailshaft is fitted with continuous liners, or
Note 1: Compliance with the above does not absolve the Owner
approved oil sealing glands, or made of corrosion-resist-
from compliance with the requirements of SOLAS as amended,
especially when shorter intervals between examination of the ships
ant material, the periodicity of complete surveys is:
bottom for certain types of ships are required. Attention is also
3 years for single shafting arrangements
drawn to the relevant requirements of Ch 1, Sec 1, [3.1], concern-
ing application of national and international regulations. 4 years for multi-shafting arrangements.
An extension of examination of the ship's bottom of three
months beyond the due date can be granted in exceptional b) These periodicities may be increased to 5 years in the
circumstances, as defined in [2.1.7]. following cases:
5.4.5 For ships under the continuous survey system of hull where the propeller is fitted to a solid flange cou-
(CSH), one of the bottom surveys to be performed in each pling at the aft end of the shaft, the shaft and its fit-
period of class is to be carried out in conjunction with the tings are not exposed to corrosion, the design details
end of class period. are approved. Non-destructive examination of the
fillet radius of the aft propeller shaft flange may be
This bottom survey may be an in-water survey, subject to required if the visual examination of the area is not
the provisions of Ch 3, Sec 4 and provided that the previous
satisfactory.
bottom survey performed in the period of class was a dry-
docking survey. Special consideration is to be given to ships
of 15 years of age and over before being permitted to have c) In all other cases the periodicity of complete surveys is
such in-water examinations. two years and six months (2,5 years).
Start
3 years
YES YES
Notation NO Notation NO
10 years (a)
MON-SHAFT assigned MON-SHAFT assigned (c)
YES YES
(b)
10 years
(c)
(a) : with shaft withdrawn, subject to modified survey at 5 years plus or minus 6 months
(b) : with shaft in place, subject to modified survey at 5 years plus or minus 6 months
c) : the periodicity cannot exceed the maximum recommended by the designer and manufacturer of the tailshaft and bearing system.
Note 1: Shafts protected against corrosion are those:
made of corrosion resistant material, or
fitted with continuous liners or systems considered as equivalent, or
fitted with oil lubricated bearings and oil sealing glands.
Note 2: Suitable sealing glands are glands which are type-approved by the Society with regard to protection of the sterntube against ingress of
water.
- the shaft and its fittings are not exposed to corrosion Shafting system (including tightness system and connection
of the propeller to the shaft) of pod propulsion systems are
- the design details are approved to be submitted to complete or modified surveys, the perio-
- the clearances of the aft bearing are found to be dicity of which is determined in the same principle as for
within acceptable limits tailshafts described in [5.5.2], [5.5.3] and Fig 2.
- the oil and the oil sealing arrangements prove effective Propulsion motors, orientating devices and other arrange-
- lubricating oil analyses are carried out regularly at ment, are to be surveyed at each class renewal survey, see
intervals not exceeding six months and oil consump- Ch 3, Sec 3, [3.2.7].
tion is recorded at the same intervals.
For ships fitted with water lubricated tailshaft bearings: 5.6 Boiler survey
- the clearances of the aft bearing are found to be 5.6.1 There are to be two internal examinations of boilers
within acceptable limits
in each period of class of five years.
- the results of the endoscopic examination are found
satisfactory In all cases, the interval between any two such examina-
tions is not to exceed 36 months.
Note 1: The purpose of the endoscopic examination is to
check visually the condition of the shaft in particular in way
of bearings and at junction with sleeves (where provided) 5.6.2 The internal examination of thermal oil heaters is to
be carried out at maximum intervals of 5 years.
- in case of forced lubrication system, satisfactory
operation of water pumping and filtering system has
5.6.3 An extension of the internal examination of the boiler
been checked
up to three months beyond the due date can be granted in
- if applicable, water analyses have been carried out exceptional circumstances, as defined in [2.1.7]. The exten-
and recorded, at regular intervals not exceeding six sion may be granted by the Society after the following is sat-
months. isfactorily carried out:
The modified survey is to be carried out five years after the external examination of the boiler
last complete survey, with a window period of plus or
minus six months. examination and operational test of boiler safety valve
relieving gear (easing gear)
The next complete survey is to be carried out ten years after
the last complete survey. operational test of boiler protective devices
5.5.4 Survey of propeller shafts and tube shafts - review of the following records since the last boiler sur-
Applicable requirements from 1 January 2016 vey: operation, maintenance, repair history, feedwater
Reference is to be made to Ch 3, Sec 5, [3] for revised chemistry.
requirements applicable to all ships with conventional
shafting fitted with a propeller, unless alternative means are 5.6.4 Boilers are also submitted to an external examination
provided to assure the condition of the propeller shaft as a part of the annual survey of machinery.
assembly.
Such requirements are applicable: 5.7 Links between anniversary dates and
from 1 January 2016, for ships delivered on or after annual surveys, intermediate surveys
1 January 2016 and class renewal surveys
after the first shaft survey scheduled on or after 1 January
2016, for ships delivered before 1 January 2016. 5.7.1 The link between the anniversary dates, the class
renewal survey (when carried out according to the normal
On a case-by-case basis, these requirements may be system), and the annual and intermediate surveys is given in
applied before the above schedule. Fig 3.
Figure 3 : Links between anniversary dates and annual, intermediate and class renewal surveys
years 0 1 2 2.5 3 4 5
Annual survey
-,+ 3 m -,+ 3 m -,+ 3 m -,+ 3 m
Intermediate survey
-,+ 9 m
6 Occasional surveys 6.2.3 All repairs to hull, machinery and equipment which
may be required in order for a ship to retain its class are to
be to the satisfaction of the Surveyor.
6.1 General
During repairs or maintenance work, the Owner is to
6.1.1 An occasional survey is any survey which is not a arrange so that any damage, defects or non-compliance
periodical survey. The survey may be defined as an occa- with the rule requirements are reported to the Surveyor dur-
sional survey of hull, machinery, boilers, refrigerating ing his survey.
plants, etc., depending on the part of the ship concerned.
6.2.4 Damages and partial or temporary repairs considered
Where defects are found, the Surveyor may extend the
acceptable by the Surveyor for a limited period of time are
scope of the survey as deemed necessary.
the subject of an appropriate recommendation.
6.1.2 Occasional surveys are carried out at the time of, for
6.2.5 Damages or repairs required by the Surveyor to be re-
example: examined after a certain period of time are the subject of an
updating of classification documents (e.g. change of the appropriate recommendation.
Owner, name of the ship, flag)
damage or suspected damage 6.3 Port State Control survey
repair or renewal work
6.3.1 An occasional survey is to be requested by the
Port State Control inspections
Owner wherever deficiencies are found as a result of a Port
alterations or conversion State Control inspection, as described in Ch 1, Sec 1, [3.4].
quality system audits
postponement of surveys or recommendations. 6.4 Conversions, alterations and repairs
6.4.1 Conversions, alterations or repairs of/to structures
6.2 Damage and repair surveys
and arrangements affecting the class are to be carried out in
6.2.1 In the event of damage which affects or may affect accordance with the requirements of the Society and to its
the class of the ship, the Owner is to apply to the Society for satisfaction. Where necessary, documentation is to be sub-
a survey. Such application is to be made as soon as possible mitted to the Society and/or made available to the attending
to enable the Surveyor to ascertain the extent of the damage Surveyor.
and necessary repairs, if any.
6.4.2 Materials and equipment used for conversions, alter-
Note 1: Whenever a ship is fitted with an helicopter platform ations or repairs are generally to meet the requirements of
which is made in aluminium or other low melting metal construc-
the Rules for new ships built under survey; see Ch 2, Sec 1,
tion which is not made equivalent to steel, and a fire occurred on
the said platform or in close proximity, the platform is to be subject
[2.1.5].
to a structural survey to determine its suitability for further use.
6.5 Quality System audits
6.2.2 If, after sustaining damage, the ship calls at a port
where the Society is not represented, the Owner is to notify 6.5.1 The Society reserves the right to carry out occasional
the Society forthwith, supply all available information surveys in order to conduct audits either as deemed neces-
regarding the damage and make arrangements for the ship sary in pursuance of its internal Quality System or as
to be surveyed in the nearest port where the Society is rep- required by external organisations (e.g. IACS, flag Adminis-
resented. trations).
6.5.2 These surveys may also be attended by auditors exter- If the Owner does not notify the Society of the laying-up of
nal to the Society. the ship or does not implement the lay-up maintenance pro-
gram, the ships class may be suspended and/or withdrawn
6.5.3 The scope of these surveys is determined by the Soci- when the due surveys are not carried out by their limit dates
ety. in accordance with the applicable requirements given in
Ch 2, Sec 3.
7 Change of ownership 8.1.2 The lay-up maintenance program provides for a lay-
ing-up survey to be performed at the beginning of lay-up
7.1 and subsequent annual lay-up condition surveys to be
performed in lieu of the normal annual surveys which are
7.1.1 In the case of change of ownership, the ship retains no longer required to be carried out as long as the ship
its current class with the Society provided that: remains laid-up. The minimum content of the lay-up main-
the Society is informed of the change sufficiently in tenance program as well as the scope of these surveys are
advance to carry out any specific survey required by the given in Ch 3, App 1. The other periodical surveys which
Owner in view of the sale; refer to [1.1.1], and become overdue during the lay-up period may be post-
poned until the re-commissioning of the ship.
the new Owner signs the appropriate request, involving
acceptance of the Societys general conditions and 8.1.3 Where the ship has an approved lay-up maintenance
Rules. This request covers inter alia the condition of the program and its period of class expires, the period of class is
ship when changing ownership. extended until it is re-commissioned, subject to the satisfac-
tory completion of the annual lay-up condition surveys as
Note 1: The ships class is maintained without prejudice to those
described in [8.1.2].
provisions in the Rules which are to be enforced in cases likely to
cause suspension or withdrawal of the class such as particular dam-
8.1.4 The periodical surveys carried out during the lay-up
ages or repairs to the ship of which the Society has not been
period may be credited, either wholly or in part, at the dis-
advised by the former or, as the case may be, new Owner.
cretion of the Society, having particular regard to their
Note 2: No information whatsoever related to the class of the ship extent and dates. These surveys will be taken into account
will be provided or confirmed to any third party, unless the appro-
for the determination of the extent of surveys required for
priate request for information is duly completed and signed by the
the re-commissioning of the ship and/or the expiry dates of
party making the request and the authorisation of the current
Owner is obtained. the next periodical surveys of the same type.
Figure 4 : Survey scheme of a case of a lay-up going beyond the expiry date of the period of class
Period of class 1
Period of class 1 extended Period of class 2
0 5 0 5
LAY-UP PERIOD
Laying up Re-commissioning
survey &
Class renewal survey
8.1.6 Where the previous period of class expired before the 8.1.8 The scope of the laying-up survey and annual lay-up
re-commissioning and was extended as stated in [8.1.3], in condition surveys are described in detail in Ch 3, App 1.
addition to the provisions of [8.1.5] a complete class
renewal survey is to be carried out prior to re-commission- 9 Safety Management System
ing. Those items which have been surveyed in compliance
with the class renewal survey requirements during the
15 months preceding the re-commissioning may be cred-
9.1
ited. A new period of class is assigned from the completion 9.1.1 For all ships to which the ISM Code applies, the Soci-
of this class renewal survey. ety may have to report possible safety management system
shortcomings, on the occasion of the Annual Survey or
8.1.7 The principles of intervals or limit dates for surveys to Intermediate Survey or Class Renewal Survey or Occasional
be carried out during the lay-up period, as stated in [8.1.1] Surveys or Statutory Surveys, to the Organisation that has
to [8.1.6], are summarised in Fig 4. issued the Safety Management Certificate.
Suspension of class with respect to the above cases will 1.3 Withdrawal of class
remain in effect until such time as the cause giving rise to
suspension has been removed. Moreover, the Society may 1.3.1 The Society will withdraw the class of a ship in the
require any additional surveys deemed necessary taking following cases:
into account the condition of the ship and the cause of the at the request of the Owner
suspension.
as a rule, when the causes that have given rise to a sus-
1.2.3 In addition, the class is automatically suspended: pension currently in effect have not been removed
within six months after due notification of suspension to
when the class renewal survey has not been completed the Owner
by its limit date or within the time granted for the com-
when the ship is reported as a constructive total loss
pletion of the survey, unless the ship is under attendance
by the Societys Surveyors with a view to completion when the ship is lost
prior to resuming trading when the ship is reported scrapped.
Withdrawal of class may take effect from the date on which 1.4 Suspension / withdrawal of additional
the circumstances causing such withdrawal occur. class notations
The contract for the classification of the ship is terminated
as of right in the above cases. 1.4.1 If the survey requirements related to maintenance of
The class is also withdrawn according to the provisions of additional class notations are not complied with, the sus-
article 7 of the Marine & Offshore Division General Condi- pension or withdrawal may be limited to the notations con-
tions in case of contract termination. cerned.
1.3.2 When the withdrawal of class of a ship comes into The same procedure may apply to service notations of ships
effect, the Society will: which are assigned with more than one service notation.
forward the Owner written notice
delete the ship from the Register of Ships 1.4.2 The suspension or withdrawal of an additional class
notify the flag Administration notation or a service notation (where a ship is assigned with
make the information available to the Underwriters, at more than one service notation) generally does not affect
their request. the class.
f) the list and specifications of the condition monitoring 4.1.2 The survey arrangement for machinery according to
equipment, including the maintenance and condition the PMS may be withdrawn by the Society if the PMS is not
monitoring methods to be used, the time intervals for satisfactorily operated on account of either the maintenance
maintenance and monitoring of each item and accepta- records or the general condition of the machinery or the
ble limit conditions failure to observe the agreed intervals between overhauls.
g) the document flow and pertinent filing procedure.
4.1.3 The Owner may discontinue the PMS at any time by
informing the Society in writing. In this case, the items
2.3 Information on board
which have been inspected under the PMS since the last
2.3.1 The following information is to be available on board: annual audit will be credited for class at the discretion of
the attending Surveyor.
a) all the documentation listed in [2.2], duly updated
b) the maintenance instructions including routine tests and 4.1.4 In the case of sale or change of management of the
inspections for each item of machinery, as applicable ship or classification after construction, the assignment of
(supplied by the manufacturer or by the shipyard) the PMS will be reconsidered.
c) the condition monitoring data of the machinery, includ-
ing all data since the last dismantling and the original
reference data 5 Surveys
d) reference documentation (trend investigation proce-
dures etc.) 5.1 Implementation survey
e) the records of maintenance performed, including condi-
tions found, repairs carried out, spare parts fitted 5.1.1 The implementation survey is to be carried out by a
Surveyor of the Society, as stated in [3.1.1], within one year
f) the list of personnel on board in charge of the PMS man-
from the date of the documentation checking.
agement.
5.1.2 The scope of this survey is to verify that:
2.4 List of items
the PMS is implemented in accordance with the docu-
2.4.1 Ships subject to the planned maintenance survey sys- mentation which has been checked and is suitable for
tem are provided with lists of items to be surveyed under the type and complexity of the components and systems
this system, as indicated in [5.2.10]. on board
the documentation required for the annual audit is pro-
3 Implementation of the system duced by the PMS
the requirements of surveys and testing for retention of
3.1
class are complied with
3.1.1 When the documentation submitted has been the shipboard personnel are familiar with the PMS pro-
checked for consistency and the PMS system has been cedures.
implemented on board and used for a sufficient period
(which is not to exceed one year) so that all personnel Upon the successful outcome of the survey confirming the
become familiar with it, a survey is to be carried out in proper implementation of the PMS, the system is considered
order to start the system and make it officially operational. operational subject to the submission to the Society of a
The scope of this survey, referred to as Implementation Sur- report describing the system.
vey, is given in [5.1.1].
3.1.2 Upon the successful outcome of the Implementation 5.2 Annual audit and confirmatory surveys
Survey, the PMS is considered approved.
5.2.1 Once the PMS system is implemented, the continued
4 Retention and withdrawal of the compliance with the requirements for checks, overhauls
and repairs, where needed, indicated in [2] is to be verified
system
by means of annual audits and confirmatory surveys in
order to confirm the validity of the approved survey scheme
4.1 system.
4.1.1 The PMS system is retained throughout the class
5.2.2 The annual audit and confirmatory surveys are to be
period provided that:
carried out in conjunction with the annual class surveys.
an annual report covering the years service is supplied
to the Society in accordance with [5.2.9]
5.2.3 The purpose of this audit is to verify that the scheme
an annual audit in accordance with [5.2] is satisfactorily is being correctly operated, in particular that all items (to be
completed surveyed in the relevant period) have actually been sur-
any change to the approved PMS is submitted to the veyed in due time. A general examination of the items con-
Society for agreement. cerned is carried out.
5.2.4 The maintenance and performance records are exam- 5.3.2 All parts of machinery or components which need to
ined to verify that the machinery has been functioning satis- undergo substantial repairs are to be surveyed before, dur-
factorily since the previous survey or audit or, if necessary, ing and after the repairs, as deemed appropriate by the Sur-
that the necessary measures have been taken in response to veyor. Any repair and corrective action regarding
machinery operating parameters exceeding acceptable tol- machinery under PMS system shall be recorded in the PMS
erances, and that the overhaul intervals have been logbook.
observed.
5.3.3 In the case of overdue recommendations or records
of unrepaired damage which may affect the PMS, the rele-
5.2.5 Written reports of breakdown or malfunction are to
be made available. vant items are to be taken out of the PMS until the recom-
mendations have been fulfilled or the repairs carried out.
5.2.6 The description of the repairs, if any, carried out is to
be examined. Any machinery part or component which has 6 Machinery items surveyed on the
been replaced by a spare due to damage is to be retained basis of condition monitoring
on board, where possible. On this occasion such replaced
parts are to be submitted to the examination of the Sur- 6.1
veyor.
6.1.1 The extent of condition-based maintenance and asso-
5.2.7 Where condition monitoring equipment is in use, ciated monitoring equipment to be included in the mainte-
functions tests, confirmatory surveys and random check nance scheme is decided by the Owner. The minimum
readings are to be carried out as far as practicable and rea- parameters to be checked in order to monitor the condition
sonable, at the discretion of the Surveyor. of the various machinery for which this type of maintenance
is accepted are indicated in [6.1.2] to [6.1.6].
5.2.8 The Surveyor also checks that the personnel on board
6.1.2 For electric propulsion motor the parameters to be
in charge of the PMS have the appropriate authorisation
checked are the following, as applicable:
(see Ch 2, App 2).
vibrations and noise of electric motor where applicable
5.2.9 An annual report covering the years service is to be temperature of windings
supplied to the Society. It is to include the following infor- temperature of built-in coolers
mation: temperature of bearings
the list of items of machinery and components (item b) temperature of cooling air
in [2.2.1]) and the procedures for their identification insulation measurement
the preventive maintenance sheets winding resistance
speed of electric motor
the condition monitoring data, including all data since
the last dismantling and the original reference data of current of electric motor
the machinery checked trough condition monitoring voltage of electric motor in each phase
current on field windings if applicable.
any changes to the other documentation in [2.2.1]
full trend analysis (including spectrum analysis for 6.1.3 For the main diesel engine the parameters to be
vibrations) of machinery displaying operating parame- checked are the following:
ters exceeding acceptable tolerances. power output
rotational speed
The Surveyor is to review this annual report or verify that it indicator diagram (where possible)
has been reviewed by the Society.
fuel oil temperature and/or viscosity
5.2.10 The Surveyor carries out a confirmatory survey of charge air pressure
the items which have been surveyed by the Chief Engineer exhaust gas temperature for each cylinder
and decides which items can be confirmed for classifica- exhaust gas temperature before and after the turbo-
tion, on the PMS list of items. chargers
temperatures and pressure of engine cooling systems
5.3 Damage and repairs temperatures and pressure of engine lubricating oil sys-
tem
5.3.1 Damage to components or items of machinery cov- rotational speed of turbochargers
ered by the PMS which may affect the class is to be reported vibrations of turbochargers
to the Society. Where applicable, a Surveyor will attend on
results of lubricating oil analysis
board, survey the damaged items and, on the basis of the
survey results, decide whether recommendations are to be crankshaft deflection readings
imposed. temperature of main bearings.
6.1.4 For the main and auxiliary steam turbines the param- exhaust gas temperature before and after the turbo-
eters to be checked are the following: chargers
temperatures and pressure of engine cooling systems
turbine bearing vibrations
temperatures and pressure of engine lubricating oil sys-
power output tem
rotational speed of turbochargers
rotational speed
crankshaft deflection readings.
plant performance data, i.e. steam conditions at the
inlet and outlet of each turbine, saturated, superheated 6.1.6 For other auxiliary machinery the parameters to be
and desuperheated steam conditions at the outlet of checked are the following, as applicable:
boilers, condenser vacuum, sea temperature. inlet and outlet temperatures of cooling systems
inlet and outlet temperatures of heating systems
6.1.5 For the auxiliary diesel engines the parameters to be vibrations and performance data of pumps and fans
checked are the following: differential pressure at filters.
3.3 Auxiliary diesel engines 3.8 Other items (pumps, electric motors, etc.)
3.3.1 The survey generally consists of the complete dis- 3.8.1 The survey is generally to include the complete dis-
mantling of the engine and a careful examination of those mantling for inspection of the main parts exposed to wear
items most liable to be exposed to wear or operating inci- or operating incidents, such as bearings, casings, impellers
dents. In particular: and rotors.
crankshaft deflections and wear of cylinder liners are to
be measured 4 Records of surveys carried out
the crankshaft is to be checked by means of dye pene-
trant in way of fillets and lubricating oil holes 4.1
all top halves of the main bearings together with at least
4.1.1 The surveys carried out by the Chief Engineer are to
two bottom halves are to be dismantled
be recorded in the engine/machinery log-book and a survey
crankcase explosion relief valves, if fitted, are to be report is to be prepared for each item surveyed.
checked. The report is generally to be drawn up in English; however,
for ships trading in specific restricted areas the use of the
3.4 Reciprocating compressors language of the country concerned will be accepted.
The report may be provided in hard copy or using a compu-
3.4.1 The survey is to include:
terised recording system.
the dismantling of pistons and valves for inspection
the examination and testing of the nest of cooler tubes 4.1.2 The report is to indicate the following information:
identification data:
the verification of safety relief valves after reassembling.
- name of ship and register number
3.5 Coolers, condensers, heaters - name of Chief Engineer and Owners attestation
- date and place (port or voyage leg) of the survey
3.5.1 The survey is to include: - reference of the item in the CSM or PMS list, and
the dismantling of the covers description of the item
the examination of the nest of tubes inspection conducted:
the testing of the nest of tubes, if necessary. - the type of inspection carried out: visual external
examination, internal examination after dismantling,
overhaul
3.6 Electrical switchboard
- readings performed, when applicable: clearances,
3.6.1 The survey is to include: measurements, working pressure, or other working
parameters of the equipment
the cleaning of the switchboard
- inspection findings: corrosion, fractures, pieces of
the verification of the connection assemblies, locking
equipment worn out, broken or missing
device tightening and busbar tightening
maintenance and repairs carried out and parts replaced
the examination of the condition of the circuit-breakers,
switches and fuses results of tests performed after the inspection, such as
working test, pressure test.
the verification of the contacts and screens
For sake of completeness, other documentation such as
the checking of the measuring instruments, which are to
sketches, photos, measurement reports may be attached to
be re-calibrated or replaced, if inaccurate
the report.
the insulation resistance test.
The report is to be signed by the Chief Engineer.
5.1.2 The Surveyor is to be supplied with a copy of this sur- 5.1.5 Where the confirmatory survey is performed with an
vey report and also shown the engine log-book. abnormal delay, the inspection is to be more extensive and,
if necessary, the due surveys are to be completely repeated.
5.1.3 The Surveyor carries out an external examination of
the relevant items and parts replaced and, if applicable,
attends running tests. If doubts arise, the Surveyor may 5.1.6 The date of the execution of the surveys will be
request dismantling as deemed necessary. assumed to be the date of the confirmatory survey.
2.2 Class renewal survey: all ships except Due to the various designs of the other ship types, figures
those submitted to ESP or equivalent are not given to cover all the different cases. However, the
figures provided here may be used as guidance for ships
2.2.1 The thickness measurements required by the Rules other than those illustrated.
consist of:
systematic thickness measurements, i.e. measurements 4 Acceptance criteria for thickness
of different parts of the structure, in order to assess the
measurements
overall and local strength of the ship
measurements of suspect areas as defined in Ch 2, Sec
2, [2.2.11] 4.1 General
additional measurements on areas determined as affected
4.1.1 Acceptance criteria stipulate limits of wastage which
by substantial corrosion as defined in Ch 2, Sec 2,
are to be taken into account for reinforcements, repairs or
[2.2.7].
renewals of steel structure. These limits are generally
expressed for each structural item as a maximum percent-
2.3 Class renewal survey: ships submitted age of acceptable wastage (W). When the maximum per-
to ESP or equivalent centage of wastage is indicated, the minimum acceptable
thickness (tmin) is that resulting from applying this percent-
2.3.1 The thickness measurements required by the Rules age to the rule thickness (trule), according to the following
consist of: formula:
systematic thickness measurements in order to assess
t min = 1 ---------- t rule
the overall and local strength of the ship W
100
thickness measurements as indicated in the program of
close-up survey However, when the rule thickness is not available, the as-
measurements of elements considered as suspect areas built thickness can be used.
as defined in Ch 2, Sec 2, [2.2.11] Only for criteria related to an item (see [4.3.4] b), the Soci-
additional measurements on areas determined as ety may establish a list of renewal thicknesses tailored to the
affected by substantial corrosion as defined in Ch 2, Sec different structural items. In such a case these thicknesses
2, [2.2.7]. are used in lieu of the minimum thicknesses calculated
from the percentage of wastage.
2.3.2 For the determination of close-up surveys and rele-
vant thickness measurements as well as the areas consid- Note 1: In any case, at the request of the Owner, the Society may
perform a direct calculation based on the current measurements.
ered as suspect areas, reference is to be made to the
relevant Sections of Part A, Chapter 4 according to the dif-
4.1.2 In cases where the ship has some structural elements
ferent service notations of the ships.
with reduced wear margins (e.g. due to ship conversion,
increase of draught), the minimum acceptable thickness for
3 Number and locations of these elements is to be calculated with reference to the rule
measurements scantlings without taking account of any reduction origi-
nally agreed.
3.1 General
4.1.3 Decisions on steel renewals are taken by the attend-
3.1.1 Considering the extent of thickness measurements as ing Surveyor applying the criteria given in this Article and
required by the Rules and indicated in [2], the locations of based on his judgment and the actual condition of the ship.
the points to be measured are given here for the most Should advice be needed to support his decision, the Sur-
important items of the structure. Thus the number of points veyor may refer to the relevant technical office of the Soci-
can be estimated. ety.
Note 1: This Article applies to ships built under the Common Struc-
tural Rules as well as ships not built under the Common Structural 4.2 Criteria
Rules, as specified.
4.2.1 The acceptance criteria for the minimum thicknesses
3.2 Locations of points are divided into:
criteria on local and global strength, given in [4.3]
3.2.1 Tab 2 provides explanations and/or interpretations for
the application of those requirements indicated in the Rules criteria on buckling strength, given in [4.4]
which refer to both systematic thickness measurements criteria on pitting, given in [4.5].
related to the calculation of global hull girder strength and
specific measurements connected to close-up surveys. 4.2.2 Each measured structural item is to be checked
Figures are also given to facilitate the explanations and/or against these four criteria, as far as applicable. When the
interpretations given in the table. These figures show typical criteria are not met, reinforcements, repairs and renewals
arrangements of cargo ships, bulk carriers and oil tankers. are to be carried out as appropriate.
Table 2 : Interpretations of rule requirements for the locations and number of points to be measured
A) SYSTEMATIC MEASUREMENTS
ITEM INTERPRETATION FIGURE
Selected plates on deck, tank top, Selected means at least a single point on one out of No figure
bottom, double bottom and wind- three plates, to be chosen on representative areas of
and-water (for all ship types average corrosion
including CSR ships)
All deck, tank top and bottom At least two points on each plate to be taken either at No figure
plates and wind-and-water strakes each 1/4 extremity of plate or at representative areas of
(for all ship types including CSR average corrosion
ships)
Transverse section (for all ship Refer to the definition given in Ch 2, Sec 2, [2.2.5] Fig 1 for general cargo ships
types including CSR ships) One point to be taken on each plate. Both web and Fig 2 for bulk carriers including CSR
flange to be measured on longitudinals, if applicable (for bulk carriers
CSR double hull oil tankers) Fig 3 for oil tankers
For tankers older than 10 years of age: Fig 15 for CSR double hull oil tankers
within 0,1D (where D is the ships moulded depth) of the For other ship types, see [3.2.1]
deck and bottom at each transverse section to be meas-
ured, every longitudinal and girder is to be measured on
the web and face plate, and every plate is to be meas-
ured at one point between longitudinals (for CSR double
hull oil tankers)
All cargo hold hatch covers and Including plates and stiffeners (for CSR single skin and Fig 4 for ships fitted with hold hatch
coamings (for all ship types except double skin bulk carriers) covers and coamings
CSR double hull oil tankers)
Bulkheads on ships other than Selected bulkheads means at least 50% of the bulk- Fig 5 for general cargo ships. It may
bulk carriers, oil tankers, chemical heads also apply to other ship types (see
tankers, liquefied gas carriers and [3.2.1])
CSR ships (for these ships refer to
B) and C): CLOSE-UP SURVEYS
AND RELATED MEASUREMENTS)
Selected internal structure such as The internal structural items to be measured in each Fig 6 for general cargo ships. It may
floors and longitudinals, transverse space internally surveyed are to be at least 20% within also apply to other ship types (see
frames, web frames, deck beams, the cargo area and 10% outside the cargo area [3.2.1])
tweendecks, girders (for all ship
types other than CSR ships)
Transverse section of deck plating Two single points on each deck plate (to be taken either No figure
outside line of cargo hatch open- at each 1/4 extremity of plate or at representative areas
ings (for bulk carriers, ore carriers, of average corrosion) between the ship sides and hatch
combination carriers and CSR sin- coamings in the transverse section concerned
gle skin bulk carriers)
Transverse rings (1) in cargo and At least two points on each plate in a staggered pattern Fig 16 for CSR double hull oil tankers
ballast tanks (for CSR double hull and two points on the corresponding flange where appli-
oil tankers) cable. Minimum 4 points on the first plate below deck.
Additional points in way of curved parts. At least one
point on each of two stiffeners between stringers / longi-
tudinal girders
One section of deck plating for the Two single points on each deck plate (to be taken either No figure
full beam of the ship within the at each 1/4 extremity of plate or at representative areas
cargo area (for oil tankers, chemi- of average corrosion) in the transverse section concerned
cal tankers and liquefied gas carri-
ers, other than CSR ships)
All deck plating and underdeck All deck plating means at least two points on each Fig 10 for CSR single skin and double
structure inside line of hatch open- plate to be taken either at each 1/4 extremity of plate or skin bulk carriers
ings between cargo hold hatches at representative areas of average corrosion. Under Extent of areas is shown in Ch 4, Sec
(for CSR single skin and double deck structure: at each short longitudinal girder: three 2, Fig 1 and Ch 4, Sec 2, Fig 3
skin bulk carriers) points for web plating (fwd/middle/aft), single point for
face plate, one point for web plating and one point for
face plating of transverse beam in way. At each ends of
transverse beams, one point for web plating and one
point for face plating
B) CLOSE-UP SURVEYS AND RELATED MEASUREMENTS (oil tankers, chemical tankers, liquefied gas carriers and combination carriers)
ITEM INTERPRETATION FIGURE
Web frame ring Refer to the definition given in Ch 4, Sec 3, Tab 1 Extent of areas is shown as in Ch 4,
(for oil tankers and combination Adjacent structural members means plating and stiff- Sec 3, Fig 1
carriers other than CSR ships) eners of deck, bottom, double bottom, sides and longitu- Locations of points are given in Fig 13
dinal bulkheads in the vicinity of the web frame ring
Transverse section Refer to the definitions given in Ch 4, Sec 4, Tab 1 and No figure
(for chemical tankers and liquefied Ch 4, Sec 5, Tab 2
gas carriers) Adjacent structural members means plating and stiff-
eners of deck, bottom, double bottom, sides and longitu-
dinal bulkheads in the vicinity of the web frame ring
Deck transverse (for all ships other This is the upper part of the web frame ring including the Extent of areas is shown as in Ch 4,
than CSR ships) adjacent structural members (see meaning given above). Sec 3, Fig 1
For chemical tankers it may be fitted on deck, i.e. outside Locations of points are given in Fig 13
the tank
Deck and bottom transverses Refer to the definition given in Ch 4, Sec 3, Tab 1 Extent of areas is shown as and
(for oil tankers other than CSR in Ch 4, Sec 3, Fig 1
ships) Locations of points are given in Fig 13
Transverse bulkheads (for all ships Complete means the whole bulkhead including string- Extent of areas is shown as in Ch 4,
other than CSR ships) ers and stiffeners and adjacent structural members as Sec 3, Fig 1
defined above Locations of points are given in Fig 14
Lower part means lower part of bulkhead up to 1/4 of Extent of areas is shown as in Ch 4,
ships depth or 2 metres above the lower stringer, which- Sec 3, Fig 1
ever is the greater (stringers, stiffeners and adjacent Locations of points are given in Fig 14
structural members included)
Transverse bulkheads in cargo tanks At least two points on each plate. Minimum 4 points on Fig 17 for CSR double hull oil tankers
(for CSR double hull oil tankers) the first plate below main deck
At least one point on every third stiffener to be taken
between each stringer
At least two points on each plate of stringers and girders,
and two points on the corresponding flange. Additional
points in way of curved part
Two points of each diaphragm plate of stools, if fitted.
Transverse bulkheads in ballast tanks At least 4 points on plates between stringers / longitudi- Fig 18 for CSR double hull oil tankers
(for CSR double hull oil tankers) nal girders, or per plate if stringers/girders not fitted
At least two points on each plate of stringers and girders,
and two points on the corresponding flange. Additional
points in way of curved part
At least one point on two stiffeners between each
stringer / longitudinal girder
Adjacent structural members (for On adjacent structural members one point per plate and No figure
CSR double hull oil tankers) one point on every third stiffener/longitudinal
All plating and internal structures Refer to the definitions given in Ch 4, Sec 4, Tab 1 and No figure
(for chemical tankers and liquefied Ch 4, Sec 5, Tab 2
gas carriers)
C) CLOSE-UP SURVEYS AND RELATED MEASUREMENTS (bulk carriers and ore carriers)
ITEM INTERPRETATION FIGURE
Frames in cargo holds (for bulk 25% of frames: one out of four frames should preferably Extent of areas is shown as in Ch 4,
carriers and ore carriers other than be chosen throughout the cargo hold length on each side Sec 2, Fig 1
CSR ships) Selected frames means at least 3 frames on each side Locations of points are given in Fig 7
of cargo holds
Selected side shell frames in cargo Includes side shell frame, upper and lower end attach- Fig 11 for CSR single skin bulk carriers
holds (for CSR single skin bulk ments and adjacent shell plating Extent of areas is shown in Ch 4, Sec
carriers) 25% of frames: one out of four frames should preferably 2, Fig 1
be chosen throughout the cargo hold length on each side
50% of frames: one out of two frames should preferably
be chosen throughout the cargo hold length on each side
Selected frames means at least 3 frames on each side
of cargo holds
Transverse frame in double skin tank Fig 2
(for CSR double skin bulk carriers)
Transverse bulkheads in cargo Refer to the definition given in Ch 4, Sec 2, Tab 8 foot- Areas of measurements are shown in
holds (for bulk carriers, ore carriers note (3) Ch 4, Sec 2, Fig 1 and Ch 4, Sec 2,
and CSR single skin and double Two selected bulkheads: one is to be the bulkhead Fig 3
skin bulk carriers) between the two foremost cargo holds and the second Locations of points are given in Fig 8
may be chosen in other positions (for CSR single skin
and double skin bulk carriers)
One transverse bulkhead in each This means that the close-up survey and related thick- Areas of measurements are shown in
cargo hold (for bulk carriers, ore ness measurements are to be performed on one side of Ch 4, Sec 2, Fig 1 and Ch 4, Sec 2,
carriers and CSR single skin and the bulkhead; the side is to be chosen based on the out- Fig 3
double skin bulk carriers) come of the overall survey of both sides. In the event of Locations of points are given in Fig 8
doubt, the Surveyor may also require (possibly partial)
close-up survey on the other side
Transverse bulkheads in one top- Includes bulkhead and stiffening systems (for CSR single Locations of points are given in Fig 9
side/side, hopper and double bot- skin and double skin bulk carriers)
tom ballast tank (for bulk carriers, The ballast tank is to be chosen based on the history of
ore carriers and CSR single skin ballasting among those prone to have the most severe
and double skin bulk carriers) conditions
Transverse webs in ballast tanks Either one of the representative tanks of each type (i.e. Extent of areas is shown as in Ch 4,
(for bulk carriers, ore carriers and topside or hopper or side tank) is to be chosen in the for- Sec 2, Fig 1 and Ch 4, Sec 2, Fig 3
CSR single skin and double skin ward part Locations of points are given in Fig 7
bulk carriers) Includes web plating, face plates, stiffeners and associ- Locations of points are given in Fig 11
ated plating and longitudinals (for CSR single skin and for CSR single skin bulk carriers and
double skin bulk carriers)
in Fig 12 for CSR double skin bulk
Associated plating and longitudinals means adjacent
carriers
plating and longitudinals of deck, bottom, side shell,
slope, hopper and longitudinal bulkhead, as applicable
Areas of deck plating inside line of Selected means at least a single point on one out of Extent of areas is shown as in Ch 4,
hatch openings (for bulk carriers three plates, to be chosen on representative areas of Sec 2, Fig 1
and ore carriers other than CSR average corrosion
ships) All deck plating means at least two points on each
plate to be taken either at each 1/4 extremity of plate or
at representative areas of average corrosion
(1) Transverse rings means all transverse material appearing in a cross-section of the ship's hull, in way of a double bottom floor,
vertical web and deck transverse (definition from the Common Structural Rules).
$ $ $
$
$
$
$ $ $
$
$
30 mm
$
$
$ $ $ $ $ $ $
$
$ $ $ $ $ $
Measurements are to be taken on both port and starboard sides of the selected transverse section
30 mm
Measurements are to be taken on both port and starboard sides of the selected transverse section
30 mm
Measurements are to be taken on both port and starboard sides of the selected transverse section
1 1 1
2 2
2 2
$ $ $ $
2 3
50 mm
(1) Three sections at L/4, L/2, 3L/4 of hatch cover length, including:
one measurement of each hatch cover plate and skirt plate
measurements of adjacent beams and stiffeners
one measurement of coaming plates and coaming flange, each side
(2) Measurements of both ends of hatch cover skirt plate, coaming plate and coaming flange
(3) One measurement of one out of three hatch coaming brackets and bars, on both sides and both ends
30 mm
A 30 mm
30 mm
30 mm
A A-A
Figure 6 : Locations of measurements on selected internal structural elements of general cargo ships
30 mm 30 mm
30 mm
30 mm
30 mm
Figure 7 : Locations of measurements on structural members in cargo holds and ballast tanks of bulk carriers
30 mm
x
x x
x
x x
x
x x x
x x
x
x
x
x
x x
x
30 mm
xx
A xx
A
A-A
xx
x
x
x x
x
x x x x x x x
x
x x x x x x x
B B
A A-A
B-B
Measurements to be taken in each shaded area as per views A - A and B - B
Figure 10 : Location of measurements on underdeck structure of CSR single skin and double skin bulk carriers
A-A
v
v
v
v
v
v
A A x x x
v
v
v
v v v
v
v
v
v
Figure 11 : Location of measurements on structural members in cargo holds and ballast tanks of
CSR single skin bulk carriers
30 mm
x
x x
x
x x
x
x x x
x x
x
x
x
x D 0,25h
x x 30 mm
x
xx
A A h
xx
C
30 mm
xx
h'
x
x A-A B
x x Lower part of 0,25h
side frame A
x
x x x x x x x
x
x x x x x x x
The gauging pattern for web plating is to be a three-point pattern for zones A, C and D, and a two-point pattern for zone B (see Figure). The
gauging report is to reflect the average reading. The average reading is to be compared with the allowable thickness.
If the web plating has general corrosion, then this pattern is to be expanded to a five-point pattern.
30 mm
x
x x
x
x x
x
x x x
x x
x
x
x
x
x x
x
30 mm
xx
A xx
A
A-A
xx
x
x
x x
x
x x x x x x x
x
x x x x x x x
4.3 Local and global strength criteria 4.3.4 Each structural item is to be assessed according to
four different criteria which vary with regard to the domain
4.3.1 Local and global strength criteria are given for the fol- under which it is considered, namely:
lowing ship types: a) an isolated area, which is meant as a part of a single
general cargo ships structural item. This criterion takes into consideration
very local aspects such as grooving of a plate or web, or
bulk carriers local severe corrosion; however, it is not to be used for
pitting for which separate criteria are considered (see
oil tankers. [4.5])
These criteria may also be used for other ship types taking b) an item, which is meant as an individual element such
into consideration the equivalence or similarity of structural as a plate, a stiffener, a web, etc. This criterion takes into
elements and their contribution to local and/or global consideration the average condition of the item, which
strength. is assessed by determining its average thickness using
the various measurements taken on the same item
4.3.2 For the evaluation of the ship longitudinal strength, it c) a group of items, which is meant as a set of elements of
is a prerequisite that fillet welding between longitudinal the same nature (plates, longitudinals, girders) contrib-
members and deck, side and bottom plating is maintained uting either to the longitudinal global strength of the
effective so as to keep continuity of hull structures. ship in a given zone or to the global strength of other
primary transverse elements not contributing to the ship
longitudinal strength, e. g. bulkheads, hatch covers,
4.3.3 Each structural item to be assessed is illustrated in a
web frames
typical transverse section (see Fig 20 for general cargo
ships, Fig 21 for bulk carriers, Fig 22 for oil tankers). d) a zone, which is meant as all and only longitudinal ele-
ments contributing to the longitudinal strength of the
These structural items are also listed in a table (Tab 5 for
ship; in this regard, the three main zones are defined as
general cargo ships, Tab 6 for bulk carriers, Tab 7 for oil deck zone, neutral axis zone and bottom zone. This cri-
tankers) grouped according to their position and contribu- terion takes into consideration the average condition of
tion to the local or global strength of the ship. all groups of items belonging to the same zone.
Figure 13 : Locations of measurements on web frame rings and longitudinal elements of oil tankers
A
A -A
A
30 mm
A A
B B
30 mm
A-A
B-B
(1) : Corrugated bulkhead
(2) : Plane bulkhead
Measurements are to be taken in a similar way on the centre tank bulkheads
Measurements are to cover the different thicknesses of strakes over the height of the bulkhead
Measurements are to be taken of the adjacent structural members
N N
N
v
v
vv N
N N
5
5 v 5
N
N
v
N
N
5
v D N N N
vv N N
v
v
N N N N
5 v 5
5
N N
v
N N N N
5
N N
vv N
v
N
v
N N N
5
N
5v
5 v 5 v 5 v 5 v N N
N N N N N N N N N
N N
5 v 5 v 5 v 5 v 5 v5 N N N N N N N
v
0,1 D
Figure 17 : Location of measurements on transverse bulkheads in cargo tanks of CSR double hull oil tankers
MATERIAL (ReH)
ITEMS RATIO
235 315 355 and 390
Bottom and deck plates s/t 56,0 51,0 49,0
Longitudinals flat bar web hw / tw 20,0 18,0 17,5
Flanged longitudinals / girders web hw / tw 56,0 51,0 49,0
symmetrical flange bf / tf 34,0 30,0 29,0
asymmetrical flange bf / tf 17,0 15,0 14,5
Symbols:
ReH : minimum yield stress of the material, in N/mm2; s : longitudinal spacing, in mm; t : actual plate thickness, in mm;
hw : web height, in mm; tw : web thickness, in mm; bf : flange breadth, in mm; tf : flange thickness, in mm;
4.3.6 These criteria take into consideration two main Table 4 : Pitting intensity and
aspects: corresponding maximum average depth of pitting
the overall strength of the hull girder
the local strength and integrity of the hull structure, such MAXIMUM AVERAGE
PITTING INTENSITY
as hatch covers, bulkheads, etc. PITTING DEPTH
(%)
(% of the as-built thickness)
As a rule, they are applicable to the structure within the
cargo area of ships having a length greater than 90 metres. Isolated 35,0
However, they may also be used for smaller ships and for 5 33,5
structure outside the cargo area according to the following
10 32,0
principles:
for ships having a length less than 90 metres, the per- 15 30,5
centages of acceptable wastage given in the tables can 20 29,0
be increased by 5 (%) (e.g. 15% instead of 10%, etc.),
25 27,5
except for those of deck and bottom zones
30 26,0
for structure outside the cargo area, the same 5 (%)
increase can be applied, 40 23,0
4.4.1 This criterion is applicable to ships having a length Note 1: Application of filler material (plastic or epoxy compounds)
greater than 120 metres. is recommended as a means to stop or reduce the corrosion proc-
The structural items contributing to the longitudinal strength ess, but it is not considered an acceptable repair for pitting exceed-
of the ship, such as deck and bottom plating, deck and bot- ing the maximum allowable wastage limits. Welding repairs may
tom girders, etc., are to be assessed with regard to their buck- be accepted when performed in accordance with procedures
agreed with the society.
ling strength, as deemed necessary by the Surveyor. In such a
case, the values shown in Tab 3 are not to be exceeded.
Note 1: The minimum thickness will be specially considered for 4.6 Hull supporting structure of shipboard
ships built with excess hull girder section modulus.
fittings associated with towing and
mooring
4.5 Pitting
4.5.1 The maximum acceptable depth for isolated pits is 4.6.1 For ships contracted for construction on or after the
35% of the as-built thickness. 1st January 2007, the allowable wastage of the hull support-
ing structure of shipboard fittings associated with towing
4.5.2 For areas with different pitting intensity, the intensity
and mooring is not to exceed:
diagrams shown in Fig 19 are to be used to identify the per-
centage of affected areas. the total corrosion addition defined in NR522 or NR523
For areas having a pitting intensity of 50% or more, the for ships covered by the Common Structural Rules for
maximum average depth of pits is 20% of the as-built thick- Bulk Carriers or the Common Structural Rules for Dou-
ness. For intermediate values between isolated pits and ble Hull Oil Tankers, or
50% of affected area, the interpolation between 35% and
20% is made according to Tab 4. 2,0 mm for other ships.
16 13 15 1 2
14
DECK
ZONE
3
17
19 6
20
NEUTRAL
AXIS
4
18 7 ZONE
5
20
9
19 21 11 12
BOTTOM
ZONE
10 8
Table 5 : Local and global acceptance criteria for general cargo ships (given in % of wastage)
Group of 1 2 3 4
Description of items
items Isolated area Item Group Zone
ITEMS CONTRIBUTING TO THE LONGITUDINAL STRENGTH (TRANSVERSE SECTION)
DECK ZONE (1) 10
1 Hatch coaming 10
underdeck girder web 25 20
underdeck girder flange 20 15
2 Upperdeck plating, deck stringer plates and sheer strakes 30 20 10
3 Deck longitudinals 10
web 30 20
flange 25 15
NEUTRAL AXIS ZONE (1) 15
4 Side shell plating 25 20 15
5 Tweendeck hatch girder 15
web 25 20
flange 20 15
6 Tweendeck plating 30 20 15 -
7 Tweendeck longitudinals 15
web 30 20
flange 25 15
Group of 1 2 3 4
Description of items
items Isolated area Item Group Zone
BOTTOM ZONE (1) 10
8 Bilge and bottom strakes and keel plate 25 20 10
9 Bottom girders 25 20 10
10 Bilge and bottom longitudinals 10
web 30 20
flange 25 15
11 Inner bottom plating 30 20 10
12 Inner bottom longitudinals 10
web 30 20
flange 25 15
OTHER ITEMS
13 Hatch coaming plating (2) 25 20
14 Hatch coaming brackets 30 25
15 Hatch cover top plating (4) 25 20 15
16 Hatch cover skirt plating (4) 30 20
17 Hatch cover stiffeners (4) 30 20
18 Transverse bulkheads (3)
plating 30 20 15
stringer web 30 20
stringer flange 25 15
stiffener web 30 20
stiffener flange 25 15
brackets 30 20
19 Side frames
web 30 20
flange 25 15
brackets 30 20
20 Deck/tweendeck beams
web 30 20
flange 25 15
21 Floors
plating 30 20
22 Forward and aft peak bulkheads
plating 30 20 15
stiffener web 30 20
stiffener flange 25 15
(1) Each zone is to be evaluated separately.
(2) If continuous, to be included in item 1.
(3) For deep tank bulkheads, the values average of item and average of group are to be increased by 5 (%).
(4) For cargo ships constructed (i.e. keel laid) from 1st January 2005:
for single skin hatch covers and for the plating of double skin hatch covers, steel renewal is required where the gauged
thickness is less than (tnet + 0,5) mm. Where the gauged thickness is within the range (tnet + 0,5) mm and (tnet + 1) mm, coat-
ing (applied in accordance with the coating manufacturer's requirements) or annual gauging may be adopted as an alterna-
tive to steel renewal. Coating is to be maintained in good condition. If t net is not available, the as-built thickness minus the
total corrosion addition can be used.
for the internal structures of double skin hatch covers, thickness gauging is required when plating renewal is to be carried
out or when this is deemed necessary, at the discretion of the Society's Surveyor, on the basis of the plating corrosion or
deformation condition. In these cases, steel renewal for the internal structures is required when the gauged thickness is less
than tnet. If tnet is not available, the as-built thickness minus the total corrosion addition can be used.
for hatch covers in way of cellular cargo holds intended for containers (plating, stiffeners and internals), steel renewal is
required where the gauged thickness is less than tnet. Where the gauged thickness is within the range tnet and (tnet + 0,5) mm,
coating (applied in accordance with the coating manufacturer's requirements) or annual gauging may be adopted as an
alternative to steel renewal. Coating is to be maintained in good condition. If tnet is not available, the as-built thickness
minus the total corrosion addition can be used.
13 15 14 16 12 2
DECK
ZONE
3
4
17
5 6
19
NEUTRAL
18
AXIS
10 11 9 ZONE
BOTTOM
ZONE
20 8 7
Table 6 : Local and global acceptance criteria for bulk carriers (given in % of wastage)
Group of 1 2 3 4
Description of items
items Isolated area Item Group Zone
ITEMS CONTRIBUTING TO THE LONGITUDINAL STRENGTH (TRANSVERSE SECTION)
DECK ZONE (1) 10
1 Strength deck plating, deck stringer, sheer strake and part of 25 20 10
side shell plating in way of top side tanks
2 Deck longitudinals 10
web 25 20
flange 20 15
3 Side shell longitudinals in way of top side tanks 10
web 25 20
flange 20 15
4 Top side tank sloped plating, including horizontal and verti- 25 20 10
cal strakes
5 Longitudinals connected to top side tank sloped plating 10
web 25 20
flange 20 15
NEUTRAL AXIS ZONE (1) 15
6 Side shell plating 25 20 15
BOTTOM ZONE (1) 10
7 Bilge and bottom plating and keel plate 25 20 10
8 Bilge and bottom longitudinals 10
web 25 20
flange 20 15
9 Bottom girders 25 15 10
10 Inner bottom plating and hopper tank sloped plating 25 20 10
11 Longitudinals connected to inner bottom and hopper tank 10
sloped plating
web 25 20
flange 20 15
Group of 1 2 3 4
Description of items
items Isolated area Item Group Zone
OTHER ITEMS
12 Hatch coaming plating (2) (6) 25 20
13 Hatch coaming brackets (6) 30 25
14 Hatch cover top plating (5) (6) 25 20 15
15 Hatch cover skirt plating (5) (6) 25 20
16 Hatch cover stiffeners (5) (6) 25 20
17 Transverse bulkheads (3)
plating 25 20 15
stiffener web 25 20
stiffener flange 20 15
18 Side shell frames (4)
web 25 20
flange 20 15
brackets 20 15
19 Topside and hopper tank web frames
web 25 20
flange 20 15
20 Floors
plating 25 15
21 Forward and aft peak bulkheads
plating 25 20 15
stiffener web 25 20
stiffener flange 20 15
(1) Each zone is to be evaluated separately.
(2) If continuous, to be included in item 1.
(3) For vertically corrugated transverse bulkheads in cargo holds:
For ships indicated in Ch 6, Sec 2, [1.1] which are to comply with the retroactive requirements according to the schedule
given in Ch 6, Sec 2, [1.2], the bulkhead between the two foremost cargo holds is to be assessed based on the criteria given
in Ch 6, Sec 2, [1.3].
For ships indicated in Pt D, Ch 4, Sec 3, [6.1.1], contracted for construction on or after 1 July 1998, all bulkheads are to be
repaired by steel renewal where the gauged thickness is less than (tnet + 0,5) mm, where tnet is the thickness obtained by
applying the strength criteria given in Pt D, Ch 4, Sec 3, [6.1]. However, where the gauged thickness is within the range
(tnet + 0,5) mm and (tnet + 1,0) mm, coating (applied in accordance with the coating Manufacturers requirements) or annual
gauging may be adopted as an alternative to steel renewal.
(4) Steel renewal criteria or other measures (reinforcement or coating) to be taken for the side shell frames and brackets in single
side skin ships with service notation bulk carrier ESP not built in accordance with Part II, Chapter 08, Section 8-03 of the 1st
April 1998 edition of the Rules or subsequent editions are given in Ch 6, Sec 2, [5] and Ch 6, App 1, [5]. However, for such
ships which are to comply with Ch 6, Sec 2, [5], the thickness measurements of flanges and side shell plating not covered in Ch
6, Sec 2, [5.3], as well as the thickness measurements of additional intermediate frames fitted for reinforcement in order to com-
ply with an ice class notation (ice strengthening structure), are to be carried out in accordance with Article [3] and the meas-
ured thicknesses assessed against the criteria indicated in Article [4] and the present Table.
(5) For ships which are assigned one of the service notations bulk carrier ESP, bulk carrier BC-A ESP, bulk carrier BC-B ESP or bulk
carrier BC-C ESP, contracted for construction on or after the 1st July 1998 and for hatch covers on exposed decks:
for single skin hatch covers and for the plating of double skin hatch covers, steel renewal is required where the gauged
thickness is less than (tnet + 0,5) mm. Where the gauged thickness is within the range (tnet + 0,5) mm and (tnet + 1,0) mm,
coating (applied in accordance with the coating manufacturers requirements) or annual gauging may be adopted as an
alternative to steel renewal. If tnet is not available, the as-built thickness, minus the total corrosion addition, can be used.
for the internal structures of double skin hatch covers, thickness gauging is required when plating renewal is to be carried
out or when this is deemed necessary, at the discretion of the Societys Surveyor, on the basis of the plating corrosion or
deformation condition.In these cases, steel renewal for the internal structures is required where the gauged thickness is less
than tnet. If tnet is not available, the as-built thickness, minus the total corrosion addition, can be used.
(6) For ships which are assigned one of the service notations bulk carrier BC-A ESP, bulk carrier BC-B ESP, bulk carrier BC-C ESP, ore
carrier ESP, combination carrier/OBO ESP or combination carrier/OOC ESP, contracted for construction on or after 1 January
2004 and for all cargo hatch covers and hatch forward and side coamings on exposed decks in position 1 as defined in ILLC:
for single skin hatch covers and for the plating of double skin hatch covers, steel renewal is required where the gauged
thickness is less than (tnet + 0,5) mm. Where the gauged thickness is within the range (tnet + 0,5) mm and (tnet + 1,0) mm,
coating (applied in accordance with the coating manufacturers requirements) or annual gauging may be adopted as an
alternative to steel renewal. Coating is to be maintained in good condition. If tnet is not available, the as-built thickness,
minus the total corrosion addition, can be used.
for the internal structures of double skin hatch covers, thickness gauging is required when plating renewal is to be carried
out or when this is deemed necessary, at the discretion of the Societys Surveyor, on the basis of the plating corrosion or
deformation condition. In these cases, steel renewal for the internal structures is required where the gauged thickness is less
than tnet. If tnet is not available, the as-built thickness, minus the total corrosion addition, can be used.
for hatch coamings, steel renewal is required where the gauged thickness is less than (tnet + 0,5) mm. Where the gauged
thickness is within the range (tnet + 0,5) mm and (tnet + 1,00) mm, coating (applied in accordance with the coating manufac-
turers requirements) or annual gauging may be adopted as an alternative to steel renewal. Coating is to be maintained in
good condition. If tnet is not available, the as-built thickness, minus the total corrosion addition, can be used.
13 3 2
DECK ZONE
15
4 1
NEUTRAL AXIS
ZONE
17 18 7
14 6 5
8
12 10 9
16
BOTTOM ZONE
11
Table 7 : Local and global acceptance criteria for oil tankers (given in % of wastage)
Group of 1 2 3 4
Description of items
items Isolated area Item Group Zone
ITEMS CONTRIBUTING TO THE LONGITUDINAL STRENGTH (TRANSVERSE SECTION)
DECK ZONE (1) 10
1 Deck plating, deck stringer, sheer strake and longitudinal 25 20 10
bulkhead upper strake (2)
2 Deck and sheer strake longitudinals 10
web 25 20
flange 20 15
3 Deck longitudinal girders 10
web 25 20
flange 20 15
4 Longitudinals connected to long. bulkhead upper strake (2) 10
web 25 20
flange 20 15
NEUTRAL AXIS ZONE (1) 15
5 Side shell plating (2) 25 20 15
6 Side shell longitudinals and stringers (2) 15
web 25 20
flange 20 15
7 Longitudinal bulkhead plating 25 20 15
8 Longitudinal bulkhead longitudinals and stringers 15
web 25 20
flange 20 15
Group of 1 2 3 4
Description of items
items Isolated area Item Group Zone
BOTTOM ZONE (1) 10
9 Bilge and bottom strakes, longitudinal bulkhead lower strake 25 20 10
and keel plate (2)
10 Bilge and bottom longitudinals (2) 10
web 25 20
flange 20 15
11 Longitudinals connected to longitud. bulkhead lower strake 10
web 25 20
flange 20 15
12 Bottom girders 10
web 25 20
flange 20 15
OTHER ITEMS
13 Deck transverse web frame
web 25 20
flange 20 15
brackets / stiffeners 25 20
14 Side shell web frame
web 25 20
flange 20 15
brackets / stiffeners 25 20
15 Longitudinal bulkhead web frame
web 25 20
flange 20 15
brackets / stiffeners 25 20
16 Bottom transverse web frame
web 25 20
flange 20 15
brackets / stiffeners 25 20
17 Cross tie
web 25 15
flange 20 15
brackets / stiffeners 20 15
18 Transverse bulkheads (3)
plating 25 20 15
stringer web 25 20
stringer flange 20 15
stiffener web 30 20
stiffener flange 25 15
(1) Each zone is to be evaluated separately.
(2) For double hull oil tankers, the structural elements of the inner skin (plating, longitudinals, girders, bulkheads) are to be
included in the corresponding elements of the outer skin.
(3) Including swash bulkheads, forward and aft peak bulkheads.
4.7 Ice strengthened structures for ships tren : Renewal thickness, namely minimum allowable
assigned with additional class notation thickness, in mm, below which renewal of
for navigation in polar waters structural members is to be carried out (see also
NR523 CSR for Double Hull Oil Tankers,
4.7.1 For ships assigned with one of the additional class Section 12)
notations POLAR CLASS as defined in Ch 1, Sec 2, [6.11], tC : Total corrosion addition, in mm, defined in
steel renewal for ice strengthened structures as defined in NR522 CSR for Bulk Carriers, Ch 3, Sec 3
NR527 is required when the gauged thickness is less than tm : Measured thickness, in mm, on one item, i.e.
tnet + 0,5 mm. average thickness on one item using the various
measurements taken on this same item during
4.8 Acceptance criteria for CSR ships periodical ships in service surveys.
The average thickness across any cross-section
4.8.1 General in the plating is not to be less than the renewal
For ships built under the Common Structural Rules, the thickness for general corrosion given in NR522
acceptance criteria are according to the following rules: CSR for Bulk Carriers, Chapter 13 and in NR523
Chapter 13, Ships in Operation, Renewal Criteria, of CSR for Double Hull Oil Tankers, Section 12.
NR522 CSR for Bulk Carriers
4.8.4 Edge corrosion of CSR ships
Section 12, Ship in Operation Renewal Criteria, of Provided that the overall corroded height of the edge corro-
NR523 CSR for Double Hull Oil Tankers, sion of the flange, or web in the case of flat bar stiffeners, is
and as specified in [4.8.2], [4.8.3], [4.8.4] and [4.8.5]. less than 25% of the stiffener flange breadth or web height,
as applicable (see Fig 23), the measured thickness tm , in
4.8.2 Pitting corrosion: side structures (CSR bulk mm, is to meet the lesser of the following criteria:
carriers)
tm 0,7 (tas-built tvol add)
If pitting intensity, in an area where coating is required
according to NR522 CSR for Bulk Carriers, Ch 3, Sec 5, is tm tren 1,0
higher than 15% (see Fig 19), thickness measurements are where:
to be performed to check the extent of pitting corrosion. The tas-built , tvol add , tren : As defined in [4.8.3].
15% is based on pitting or grooving on only one side of a
plate. In cases where pitting is exceeding 15%, as defined Figure 23 : Edge corrosion
above, an area of 300 mm or more, at the most pitted part
of the plate, is to be cleaned to bare metal and the thickness
is to be measured in way of the five deepest pits within the
cleaned area. The least thickness measured in way of any of
these pits is to be taken as the thickness to be recorded. The
minimum remaining thickness in pits, grooves or other local
areas is to be greater than the following values:
for CSR single and double skin bulk carriers: 70% of the
as-built thickness, in the side shell, hopper tank and top-
side tank plating attached to the each side frame, over a
width up to 30 mm on either side of it
for CSR single skin bulk carriers: 75% of the as-built
thickness, in the frame and end bracket webs and The average measured thickness tm across the breadth or
flanges, height of the stiffener is not to be less than the one defined
without being greater than the renewal thickness tren as in NR522 CSR for Bulk Carriers, Chapter 13 and in NR523
defined in [4.8.3]. CSR for Double Hull Oil Tankers, Section 12.
Plate edges at openings for manholes, lightening holes, etc.
4.8.3 Pitting corrosion: other structures (CSR bulk may be below the minimum thickness given in NR522 CSR
carriers and CSR oil tankers) for Bulk Carriers, Chapter 13 and in NR523 CSR for Double
For plates with pitting intensity less than 20% (see Fig 19), Hull Oil Tankers, Section 12, provided that:
the measured thickness tm , in mm, of any individual meas- a) the maximum extent of the reduced plate thickness,
urement is to meet the lesser of the following criteria: below the minimum given in NR522 CSR for Bulk Carri-
tm 0,7 (tas-built tvol add) ers, Chapter 13 and in NR523 CSR for Double Hull Oil
tm tren 1,0 Tankers, Section 12, from the opening edge is not more
than 20% of the smallest dimension of the opening and
where: does not exceed 100 mm
tas-built : As-built thickness of the member, in mm b) rough or uneven edges may be cropped-back provided
tvol add : Voluntary thickness addition, namely thickness, that the maximum dimension of the opening is not
in mm, voluntarily added as the Owners extra increased by more than 10% and the remaining thick-
margin for corrosion wastage in addition to tC ness of the new edge is not less than tren 1 mm.
Chapter 3
1 General all air pipe heads installed on the exposed decks (i.e.
those extending above the freeboard deck or superstruc-
ture decks)
1.1
weld connection between air pipes and deck plating
1.1.1 The requirements of this Section apply to annual sur- fittings and appliances for timber deck cargoes, where
veys of all ships. The specific requirements for annual sur- applicable
veys related to service notations and additional class
freeboard marks on the ships sides
notations assigned to ships are addressed in Part A, Chapter
4 and Part A, Chapter 5, respectively. deck equipment such as lifeboat davit foundations, bol-
lards, fairleads, hawse pipes, etc., masts and associated
Note 1: Ships assigned with the service notation yacht and having
rigging, including lightning conductors
a length less than 24 m are not submitted to annual surveys for hull
and machinery. windlass and equipment of chain cables or wire ropes
for anchors
1.1.2 At the time of annual surveys, the ship is to be gener- watertight bulkheads, their watertight doors and associ-
ally examined. The survey is to include a visual inspection ated local and remote controls, and their watertight pen-
of the hull, equipment and machinery of the ship and some etrations
tests thereof, so far as necessary and practicable in order to
main and auxiliary steering arrangements, including
verify that the ship is in a acceptable general condition and
their associated equipment and control systems, and
is properly maintained.
manoeuvring gear
1.1.3 Owners are reminded that, in compliance with the fire divisions and fire doors, dampers in ventilation
requirements in Ch 2, Sec 2, [6.4], any modification to the ducts, means of closure of skylights and other openings
ships hull, equipment and machinery affecting its classifi- confirmation that emergency escape routes from
cation is to be made known to the Society. accommodation and service spaces are satisfactory
accessible cargo holds, in particular in areas likely to be
2 Hull damaged by cargo handling
confirmation that the drainage from enclosed cargo
spaces situated on the freeboard deck is satisfactory
2.1 Hull and hull equipment
engine room
2.1.1 The survey is to include a general external examina- where fitted, helicopter deck and its supporting structure,
tion and testing, where appropriate, of the following items, safety net and arrangements for the prevention of sliding
as applicable:
availability of loading manual
outer shell plating above the waterline, relevant shell
doors and accessible parts of the rudder(s) availability of electronic loading instrument, where
required, and verification with standard test
plating of freeboard deck and exposed decks, super-
structures, with their openings and means of closure availability of approved stability documentation.
cargo hatchways and other openings on exposed decks, Note 1: Due attention is also to be given to fuel oil piping passing
with their coamings and their means of closure and through ballast tanks, which is to be pressure tested where doubts
securing arrangements (for details see [2.2]) arise.
sidescuttles and deadlights, chutes and other openings
2.1.2 Suspect areas identified at previous surveys are to be
with their means of closure
examined. Thickness measurements are to be taken of the
bulwarks, guard rails, freeing ports, gangways and life- areas of substantial corrosion and the extent of thickness
lines, ladders measurements is to be increased to determine areas of sub-
scuppers and sanitary discharges, valves on discharge stantial corrosion, in accordance with the requirements of
lines and their controls Ch 3, Sec 3, Tab 4. These extended thickness measurements
are to be carried out before the annual survey is credited as
ventilators, air pipes, overflow pipes and gas vent pipes, completed.
with their means of closure and flame screens, where
Note 1: These requirements are not applicable to cargo tanks of oil
required
tankers, chemical tankers and double hull oil tankers surveyed in
flame screens on vents to all bunker tanks accordance with the requirements of Ch 4, Sec 3 and Ch 4, Sec 4.
2.1.3 Examination of ballast tanks when required as a con- c) checking of the satisfactory condition of hatch coaming
sequence of the results of the class renewal survey and plating and its stiffeners, where applicable.
intermediate survey is to be carried out. When considered
necessary by the Surveyor, or where extensive corrosion 3 Machinery and systems
exists, thickness measurement is to be carried out. If the
results of these thickness measurements indicate that Sub-
stantial Corrosion is found, then the extent of thickness 3.1 General machinery installations
measurements is to be increased to determine areas of sub-
3.1.1 The survey of general machinery installations is to
stantial corrosion, in accordance with the requirements of
cover the following items:
Ch 3, Sec 3, Tab 4. These extended thickness measurements
are to be carried out before the annual survey is credited as general examination of machinery and boiler spaces
completed. with particular attention to the fire and explosion haz-
ards; confirmation that emergency escape routes are
practicable and not blocked
2.2 Hatch covers and coamings
general examination of the machinery, steam, hydraulic,
2.2.1 The Owner or his representative is to declare to the pneumatic and other systems and their associated fit-
attending Surveyor that no significant changes have been tings, for confirmation of their proper maintenance
made to the hatch covers, hatch coamings and their securing testing of the means of communication and order trans-
and sealing devices without prior approval of the Society. mission between the navigating bridge and the machin-
ery control positions and other control stations
The survey of hatch covers and coamings is to include:
confirmation that the rudder angle indicator on the
a) when fitted with portable covers, or wooden or steel bridge is in working order
pontoons, checking of the satisfactory condition, where
examination, as far as practicable, of the bilge pumping
applicable, of:
systems and bilge wells, including operation of the
wooden covers and portable beams, carriers or pumps, remote reach rods and level alarms, where fitted
sockets for the portable beams, and their securing visual examination of the condition of any expansion
devices joints in sea water systems
steel pontoons external examination of pressure vessels other than boil-
tarpaulins ers and their appurtenances, including safety devices,
foundations, controls, relieving gear, high pressure pip-
cleats, battens and wedges
ing, insulation and gauges.
hatch securing bars and their securing devices
3.1.2 When the ship is equipped with a refrigerating plant
loading pads/bars and the side plate edge
(whether or not covered by an additional class notation),
guide plates and chocks the annual survey is to include the external examination of:
compression bars, drainage channels and drain pressure vessels of the installation to the same extent as
pipes (if any) indicated in [3.1.1]
b) when fitted with mechanically operated steel covers, refrigerant piping, as far as practicable
checking of the satisfactory condition, as applicable, of: for refrigerating machinery spaces using ammonia as
hatch covers refrigerant:
- ventilation system including functional test
tightness devices of longitudinal, transverse and
intermediate cross junctions (gaskets, gasket lips, - water-spraying fire-extinguishing system; see [3.4.2]
compression bars, drainage channels and, if any, item d)
drain pipes) - bilge system including functional test
clamping devices, retaining bars, cleating - electrical equipment, confirming its proper mainte-
nance
chain or rope pulleys
- gas detection system
guides
- breathing apparatus and protective clothing.
guide rails and track wheels
stoppers, etc. 3.1.3 When the ship is equipped with thruster installations,
the annual survey is to include:
wires, chains, gypsies, tensioning devices
an external examination of the machinery installation
hydraulic system essential to closing and securing an operating test of the complete installation.
safety locks and retaining devices
3.1.4 For ships subject to compliance with the require-
the operation of hatch covers, by means of random ments laid down in Ch 6, Sec 2, [6], or in Ch 6, Sec 4, [2],
examination: stowage and securing in open condi- or in Pt B, Ch 2, Sec 1, [2.2], the annual survey is to include
tion, proper fit, locking and efficiency of sealing in
an examination and a test of the water ingress detection sys-
closed position, operational testing of hydraulic and tems and of their alarms at random.
power components, wires, chains and link drives
3.1.5 For ships subject to compliance with the require- checking, as far as practicable, the operation of emer-
ments laid down in Ch 6, Sec 2, [7], or in Pt C, Ch 1, Sec gency sources of power and, where they are automatic,
10, [6.6.3], item e), the annual survey is to include an also including the automatic mode.
examination and a test of the means for draining and pump-
ing ballast tanks forward of the collision bulkhead and 3.3.2 The survey is also to cover the bridge control of pro-
bilges of dry spaces any part of which extends forward of pulsion machinery, and related arrangements (alarms and
the foremost cargo hold, and of their controls. safety devices), when fitted.
The survey of an automated installation covered by an addi-
3.2 Boilers tional class notation is detailed in Part A, Chapter 5.
3.2.1 For main and auxiliary steam boilers, the annual sur- 3.4 Fire protection, detection and extinction
vey consists of an external examination of boilers and their
appurtenances, including safety devices, foundations, con- 3.4.1 The survey of fire prevention and other general
trols, relieving, high pressure and steam escape piping, arrangements is to cover the following items:
insulation and gauges. checking that fire control plans are properly posted
The annual survey is to include test of safety and protective examination and testing, as feasible, of the operation of
devices and test of safety valve using its relieving gear. manual and/or automatic fire doors, where fitted
checking, as far as practicable, that the remote controls
For exhaust gas heated economizers, the safety valves are to
for stopping fans and machinery and shutting off fuel
be tested by the Chief Engineer at sea within the annual sur-
supplies in machinery spaces and, where fitted, the
vey window. This test is to be recorded in the log book for
remote controls for stopping fans in accommodation
review by the attending Surveyor prior to crediting the
spaces and the means of cutting off power to the galley
Annual Survey of Machinery.
are in working order
3.2.2 For thermal oil heaters, a functional test while in examination and testing of the closing arrangements of
operation is to be carried out, during which the following ventilators, funnel annular spaces, skylights, doorways
items are checked: and tunnel, where applicable
examination, as far as practicable, and testing, as feasi-
the heater for detection of leakages
ble and at random, of the fire and/or smoke detection
the condition of the insulation systems.
the operation of indication, control and safety devices
3.4.2 The operational readiness and maintenance of fire-
the condition of remote controls for shut-off and dis- fighting systems is to be checked. The survey requirements
charge valves. for all types of fire-fighting systems that are usually found on
board ships related either to machinery spaces or cargo
A satisfactory analysis of the quality of oil is to be made spaces or vehicle spaces or special category spaces or ro-ro
available to the Surveyor. spaces or accommodation spaces, irrespective of the serv-
ice notation assigned, are the following:
3.2.3 For exhaust gas thermal oil heaters, in addition to the
requirements of [3.2.2], a visual examination and a tight- a) water fire system
ness testing to the working pressure of the heater tubes are examination of the fire main system and confirma-
to be carried out. tion that each fire pump including the emergency
fire pump can be operated separately so that the two
3.2.4 For electrical steam generators, a functional test required powerful jets of water can be produced
while in operation is to be carried out, during which the fol- simultaneously from different hydrants, at any part of
lowing items are checked: the ship whilst the required pressure is maintained
the heater system for detection of leakages in the fire main
checking that fire hoses, nozzles, applicators, span-
the operation of indication, control, alarm and safety
ners and international shore connection (where fit-
devices.
ted) are in satisfactory working condition and
situated at their respective locations
3.3 Electrical machinery and equipment b) fixed gas fire-extinguishing system
3.3.1 The survey of electrical machinery and equipment is external examination of receivers of CO2 (or other
to cover the following items: gas) fixed fire-extinguishing systems and their acces-
sories, including the removal of insulation for insu-
general examination, visually and in operation, as feasi- lated low pressure CO2 containers
ble, of the electrical installations for power and lighting,
in particular main and emergency generators, electric examination of fixed fire-fighting system controls,
motors, switchboards, switchgears, cables and circuit piping, instructions and marking; checking for evi-
protective devices, indicators of electrical insulation dence of proper maintenance and servicing, includ-
and automatic starting, where provided, of emergency ing date of last system tests
sources of power test of the alarm triggered before the CO2 is released
(3) For ballast tanks, excluding double bottom ballast tanks, if there is no hard protective coating, soft or semi-hard coating or poor
coating condition and it is not renewed, the spaces in question are to be internally examined at annual intervals.
When such conditions are found in water ballast double bottom tanks, the spaces in question may be examined at annual inter-
vals.
Note 1: Due attention is also to be given to fuel oil piping passing through ballast tanks, which is to be pressure tested should doubts
arise.
1 General
2 Hull and hull equipment
1.1
1.1.1 The requirements of this Section apply to class 2.1 Bottom survey in dry condition
renewal surveys of all ships. The specific requirements for
class renewal surveys related to service notations and addi- 2.1.1 A bottom survey in dry condition is to be carried out,
tional class notations assigned to ships are addressed in Part as detailed in Ch 3, Sec 4, [2], and in addition the require-
A, Chapter 4 and Part A, Chapter 5, respectively. ments given in [2.1.3] to [2.1.5] are to be complied with.
1.1.2 A survey planning meeting is to be held prior to the 2.1.2 For ships of unusual characteristics or engaged on
commencement of the survey. special services, means of underwater inspection equivalent
to the bottom survey in dry condition may be considered as
1.1.3 Concurrent crediting to both Intermediate Survey and
an alternative by the Society, particularly when a suitable
Class Renewal Survey for surveys and thickness measure-
high resistance paint is applied to the underwater portion of
ments of spaces are not acceptable.
the hull or an approved system of impressed current for
external cathodic protection is fitted.
1.1.4 In addition to the requirements of the annual survey,
the class renewal survey is to include sufficiently extensive
2.1.3 Anchors, windlass(es) and chain cables are to be
examination and checks to show that the structures, main
ranged and examined, and the required complement and
and auxiliary machinery, systems, equipment and various
condition are to be checked. When the ship is more than 5
arrangements of the ship are in satisfactory condition or
years old, chain cables are to be gauged.
restored to such condition as to allow the ship to operate for
the new period of class of five years to be assigned, pro- Any length of chain cable which is found to be damaged or
vided that the ship is properly maintained and operated and excessively worn is to be renewed.
other surveys for maintenance of class are duly carried out
during this period. 2.1.4 Sea valves and cocks are to be opened up for internal
The examinations of the hull are to be supplemented by examination.
thickness measurements and testing as required in [2.4] and
[2.5], to ensure that the structural integrity remains effec- 2.1.5 Thickness measurements of the outer shell plating, as
tive. The aim of the examination is to discover substantial and if required within the scope of the related class renewal
corrosion, significant deformation, fractures, damages or survey, are to be carried out (refer to [2.5]), if not already
other structural deformation that may be present. done within 15 months before the end of class period.
checking of the satisfactory operation of all mechani- 2.3 Holds and other dry compartments
cally operated hatch covers is to be made, including
stowage and securing in open condition, proper fit, 2.3.1 Holds, tweendecks, cofferdams, pipe tunnels and
locking and efficiency of sealing in closed position,
duct keels, void spaces and other dry compartments which
operational testing of hydraulic and power components,
are integral to the hull structure are to be internally exam-
wires, chains and link drives
ined, ascertaining the condition of the structure, bilges and
checking the effectiveness of sealing arrangements of all drain wells, sounding, venting, pumping and drainage
hatch covers by hose testing or equivalent is to be car- arrangements.
ried out
thickness measurements of coaming and attached stiff- 2.3.2 Machinery and boiler spaces, pump rooms and other
eners, hatch cover plating and stiffeners (see Tab 3). spaces containing machinery are to be internally examined,
ascertaining the condition of the structure. Particular atten-
2.2.3 The survey of hull equipment is to cover the follow- tion is to be given to tank tops, shell plating in way of tank
ing points: tops, brackets connecting side shell frames and tank tops,
windlass and chain stoppers, with disassembly as and bulkheads in way of tank tops and bilge wells. Particu-
deemed necessary to verify the condition of the equip- lar attention is to be given to the sea suctions, sea water
ment and control and safety devices, hawse pipes cooling pipes and overboard discharge valves and their
steering arrangements, including steering gear, control connections to the shell plating. Where wastage is evident
and indication devices, operational tests and disassem- or suspected, thickness measurements are to be carried out,
bly as deemed necessary; in the case of chain and rod and renewals or repairs effected when wastage exceeds
gears, chains, rods, sheaves, pins and rollers are to be allowable limits.
examined for wear
Piping systems inside these spaces are to be dealt with
connection of masts and standing rigging to the hull according to [3.5].
structure as well as condition of structure underneath.
2.2.4 All bilge and ballast piping systems are to be exam- 2.3.3 Chain lockers are to be internally examined, while
ined and operationally tested to working pressure to attend- the anchor chains are ranged as required for the bottom sur-
ing Surveyors satisfaction to ensure that tightness and vey in dry condition (see [2.1.3]). The pumping arrange-
condition remain satisfactory; see also [3.5]. ment of the chain lockers is to be tested.
2.2.5 For all ships, except ships having the service notation
passenger ship or ro-ro passenger ship, automatic air pipe
2.4 Tanks
heads installed on the exposed decks (i.e. those extending
above the freeboard deck or superstructure decks) are to be 2.4.1 The type and number of tanks to be internally exam-
completely examined, both externally and internally, in ined at each class renewal survey are detailed in Tab 2,
accordance with the requirements given in Tab 1. according to the age of the ship.
Table 1 : Requirements for internal and external examination of automatic air pipe heads at class renewal survey
of all ships, except ships with service notation passenger ship or ro-ro passenger ship
Table 2 : Requirements for internal examination of integral (structural) tanks at class renewal survey
This internal examination is to ascertain the condition of the 2.4.4 Boundaries of fuel oil, lube oil and fresh water tanks
structure, bilges and drain wells, sounding, venting, pumping are to be tested with a head of liquid to the highest point
and drainage arrangements, including piping systems and that liquid will rise under service conditions. Tank testing of
their fittings. Due attention is to be given to plating or double fuel oil, lube oil and fresh water tanks may be specially con-
plates below the lower end of sounding and suction pipes. sidered based on a satisfactory external examination of the
Where the inner surface of the tanks is covered with cement tank boundaries, and a confirmation from the Master stating
or other compositions, the removal of coverings may be that the pressure testing has been carried out according to
waived provided they are examined, found sound and the requirements with satisfactory results. The surveyor may
adhering satisfactorily to the steel structures. extend the testing as deemed necessary.
Note 1: For examination of independent (non-structural) tanks,
refer to [3.5.9]. 2.4.5 For integral tanks which are intended to contain liq-
Note 2: Due attention is also to be given to fuel oil piping passing uid cargoes such as edible oil, the Surveyor may waive the
through ballast tanks, which is to be pressure tested when the ship requirement specified in [2.4.4] subject to a satisfactory
is more than 10 years old. internal examination.
Table 4 : Guidance for additional thickness measurements in way of substantial corrosion areas
3 Machinery and systems of rotor bearings, thrust bearings and flexible couplings,
provided the Surveyor is satisfied from operation service
records and power trials subsequent to the survey, that the
3.1 General turbine plant is in good working condition.
3.1.1 The survey items listed below are to be covered to the 3.2.4 Gas turbines
satisfaction of the Surveyor. However, other survey alterna-
tives deemed equivalent by the Surveyor in relation to the a) Casings, rotors and disks, impellers and blading of all
characteristics and general condition of the ship concerned turbines and compressors, combustion chambers, burn-
may also be accepted. ers, heat exchangers, gas piping, compressed air piping
with fittings, starting and reverse arrangements
As part of the Class Renewal Survey of Machinery, a dock
trial is to be carried out, to the satisfaction of the attending b) Shafts and their flexible couplings.
Surveyor, to confirm satisfactory operation of main and aux-
iliary machinery. If significant repairs are carried out to 3.2.5 Electric propulsion
main or auxiliary machinery or steering gear, consideration Where the propulsion machinery consists of an electrical
is to be given to a sea trial, to the satisfaction of the attend- system, the propulsion motors, generators, cables and all
ing Surveyor. ancillary electrical gear, exciters and ventilating plant
Note 1: Attention is drawn to the requirement Ch 2, Sec 2, [2.5.1] (including coolers) associated therewith are to be examined
regarding safe execution of surveys, in particular as regards health and the insulation resistance to earth tested. Due attention
hazards related to asbestos. is to be given to windings, commutations and sliprings. The
operation of protective gear and alarm devices is to be
3.2 Main and auxiliary engines and turbines checked, as far as practicable. Interlocks intended to pre-
vent unsafe operations or unauthorised access are to be
3.2.1 General checked to verify that they are functioning correctly.
Depending on the type of machinery, the following parts 3.2.6 Thruster installations
are to be opened up as necessary for inspection. Parts and
components are to be pressure tested as appropriate or as When the ship is equipped with thruster installations, the
deemed necessary by the Surveyor. A working test is also to class renewal survey is also to include:
be carried out, including testing of alarms and safety an examination of the machinery and electrical installa-
devices. tion, as applicable
3.2.2 Internal combustion engines an external examination of the propulsive part of the
installation to be carried out at the dry dock survey due
a) Columns and entablature as part of the class renewal survey. During this examina-
b) Cylinders with their liners, cylinder covers (together tion other checks such as clearance readings, tightness
with valves and valve gear), pistons with their rods, of hub and blade sealing for controllable pitch propel-
crossheads, slippers and guides (or gudgeon pins), con- lers are to be verified. Locking arrangements for bolts, if
necting rods (with their top and bottom end bearings), fitted, are to be checked. Results of lubricating oil analy-
control gear, driven scavenge pumps, driven air com- sis to detect possible deterioration of internal gears and
pressors, driven fuel pumps, supercharging blowers, fuel bearings or the presence of water are to be confirmed as
injection pumps, turning gear, etc. acceptable. The Manufacturers requirements may be
taken into account. Dismantling of the assembly for the
c) Crankshafts (together with their main bearings) examination of internal parts may be required if the
d) Reverse gear, reduction gear and clutches, if fitted. foregoing checks are not satisfactory
a running test of the system under operating conditions.
3.2.3 Steam turbines
a) Condensers and their cooling water and condensate 3.2.7 Pod propulsion systems
extraction pumps When the ship is equipped with pod propulsion systems,
b) Casings and rotors (including their blading), impulse the class renewal survey is to include the examination of:
wheels (including guide blading and diaphragms), noz- electric propulsion motors and associated equipment,
zles and nozzle boxes, journals and bearings, dummy see [3.2.5]
pistons, labyrinths, external glands, etc.
pod orientation device (gears and wheels, hydraulic/
c) Shafts, including their flexible couplings. electric system, sealing arrangements)
Where the propulsion steam turbines are of a well-known oil lubricating system of shaft bearings
type, and fitted with rotor position indicators and vibration
indicators of an approved type, as well as measuring equip- bilge system inside pod
ment of steam pressure at proper locations along the steam ventilation and cooling system
flow, and the arrangements for change-over in the event of
rotating commutator
emergency operation of the plant are readily operable, the
first class renewal survey may be limited to the examination alarm system.
3.3 Reduction gears, main thrust and 3.5.6 Steel pipes for saturated steam or superheated steam
intermediate shaft(s) having a temperature of the steam at the superheater outlet
not exceeding 450C are to be examined and tested in
3.3.1 Reduction gears complete with all wheels, pinions, accordance with [3.5.7] to [3.5.8] at each class renewal
shafts, couplings, bearings and gear teeth, including incor- survey for ships over 5 years of age. When the ship is
porated clutch arrangements, are to be opened up, as 5 years of age or less, the inspection may be limited to a
deemed necessary by the Surveyor, for visual inspection. check of the satisfactory general condition of pipes.
For complicated assemblies, gears and roller bearings may
be surveyed without dismantling. 3.5.7 The examination and hydrostatic test of steel pipes for
main steam machinery, and steel pipes for auxiliary steam
3.3.2 All shafts, thrust blocks and bearings are to be exam- machinery having internal diameter 75 mm and over, are to
ined. be carried out on a number of pipes selected by the Sur-
veyor after the lagging in way is removed.
3.4 Pumps and other machinery items
3.5.8 Representative pipe lengths connected with bolted
3.4.1 General flanges are to be internally and externally examined, and
The items listed in [3.4.2] are to be opened up, as deemed hydrostatically tested to 1,1 times the working pressure at
necessary by the Surveyor, for visual inspection. Their parts ambient temperature. Bolts and butt-welded joints between
and components are to be pressure tested as appropriate flanges and pipes are to be submitted to a non-destructive
and considered necessary by the Surveyor. A working test is test for crack detection.
also to be carried out, including testing of alarms and safety
devices if deemed necessary by the Surveyor. 3.5.9 Non-structural tanks located in machinery spaces are
to be externally examined; the relevant fittings, with partic-
3.4.2 Items to be surveyed ular regard to the remote control shut-off valves under
a) Air compressors with their intercoolers, filters and/or oil hydrostatic head, are to be externally examined to check
separators and safety devices the efficiency of manoeuvres and the absence of cracks or
leakage.
b) Heat exchangers, ventilation fans for boilers and other
equipment used for essential services
3.5.10 When the ship is equipped with a refrigerating plant
c) Piston pumps and centrifugal pumps for sea water, bilge (whether or not covered by an additional class notation),
and salt water ballast the class renewal survey is to include:
d) Screw pumps, gear pumps and centrifugal pumps other examination and test at the design pressure of the parts
than those listed in c) above (opening up is not required). of the plant under pressure
for refrigerating machinery spaces using ammonia as
3.5 Systems in machinery spaces refrigerant:
3.5.1 Valves, cocks and strainers of the bilge and ballast - examination and test of the water-spraying fire-extin-
systems are to be opened up, as deemed necessary by the guishing system to the same extent as indicated in
Surveyor, for visual inspection, and, together with the pip- [3.8.3], item d)
ing and safety devices, examined and tested under working - examination of valves and pumps of the bilge sys-
conditions. tem to the same extent as indicated in [3.4]
3.5.2 The fuel oil, lubricating oil, hydraulic oil, thermal oil, - examination and test of the electrical equipment to
and feed and cooling water systems, together with pressure the same extent as indicated in [3.6.11]
filters, heaters and coolers used for essential services, are to
- test of the gas detection system.
be opened up and examined or tested, as considered neces-
sary by the Surveyor. Safety devices for the foregoing items
are to be examined. 3.6 Electrical equipment and installations
3.5.3 The compressed air system together with its valves, 3.6.1 An electrical insulation resistance test is to be per-
fittings and safety devices is to be examined, as considered formed on the electrical equipment and cables. If needed,
necessary by the Surveyor. for the purpose of this test, the installation may be subdi-
vided or equipment which may be damaged disconnected.
3.5.4 Compressed air receivers and other pressure vessels for
essential services are to be cleaned internally and examined 3.6.2 The following minimum values, when performing the
internally and externally. Their fittings, valves and safety insulation test, are to be considered:
devices are to be opened up, as deemed necessary by the Sur-
veyor, for visual inspection and pressure tested as appropriate. for main and emergency switchboards, feeder circuit
breakers being open, busbar circuit closed, measuring
3.5.5 Steel pipes for superheated steam having a tempera- and monitoring instruments disconnected, the resist-
ture of the steam at the superheater outlet exceeding 450C ance of insulation measured across each insulated bus-
are to be examined and tested in accordance with [3.5.7] to bar and the hull, and across insulated busbars, should
[3.5.8] at each class renewal survey. not be less than 1 megohm
for generators, the equipment and circuits normally 3.6.11 A general examination of the electrical equipment
connected between the generator and the first circuit in areas where there may be flammable gas or vapour
breaker being connected, the resistance of insulation and/or combustible dust is to be carried out to ensure that
(preferably at working temperature whenever possible), the integrity of the electrical equipment of a safety type has
in ohms, is to be greater than 1 000 times the rated volt- not been impaired owing to corrosion, missing bolts, etc.,
age, in volts. If appropriate, the Surveyor checks also and that there is not an excessive build-up of dust on or in
that the insulation resistance of generators separate dust-protected electrical equipment. Cable runs are to be
exciter gear is not less than 1 megohm examined for sheath and armouring defects, where practi-
cable, and to ensure that the means of supporting the cables
the insulation resistance of the entire electrical system is are in satisfactory condition. The proper condition of bond-
to be checked with all circuit breakers and protective ing straps for the control of static electricity is to be
devices closed, except for generators; in general, the checked. Alarms and interlocks associated with pressurised
resistance should not be less than 100 000 ohms. How- equipment or spaces are to be tested for correct operation.
ever, the variation of the resistance with time is to be Note 1: Owners are reminded that maintenance, repairs or renewal
checked, comparing the current figure with previous of certified electrical equipment of a safe type remains their respon-
readings. If the insulation resistance was to drop sud- sibility or that of their representatives.
denly or be insufficient, the defective circuits are to be
traced, disconnecting the circuits as much as necessary.
3.7 Controls
3.6.3 The prime movers of generators are to be surveyed in
3.7.1 Where remote and/or automatic controls, not cov-
accordance with [3.2] and their governors tested. All gener-
ered by an additional class notation related to automated
ators are to be presented for inspection, clean and with cov-
installation, are fitted for essential machinery, they are to be
ers opened and examined under working conditions.
tested to demonstrate that they are in satisfactory condition.
3.8.3 The survey requirements for all types of fire-fighting f) dry powder system
systems that are usually found on board ships related either it is to be verified that the propelling inert gas bottles
to machinery spaces or to cargo areas and/or spaces or to have been hydrostatically tested. The same applies
accommodation spaces, irrespective of the service notation to bottles disembarked for refilling or embarked for
assigned, are the following: replacement.
a) water fire system
3.8.4 As far as other fire-fighting equipment is concerned,
the associated pumps are to be opened up and the following items are to be hydrostatically tested, at inter-
examined at the Surveyors discretion vals not exceeding 10 years:
the fire main is to be hydrostatically tested to the any CO2 bottles of extinguishers
working pressure at the Surveyors discretion
shells of foam extinguishers
b) fixed gas fire-extinguishing system
shells of powder extinguishers
Receivers of CO2 (or other gas) fixed fire-extinguishing
air or gas bottles associated with fire extinguishers
systems are to be externally examined together with all
whose shells are not kept under pressure (if internally
stationary fittings and devices. In addition, the following
examined, the test need not be performed).
applies:
the total loss of CO2 is not to exceed 10% of the 3.8.5 Where a helideck is fitted, the following is to be
installed quantity (5% for Halon) checked, as far as appropriate:
after being repaired or discharged, containers are to drainage arrangements around the landing area
be subjected to a hydrostatic test fire fighting appliances and arrangements (to be sur-
hydrostatic testing of high pressure CO2 containers is veyed as per [3.8.3] and [3.8.4], according to the equip-
to be carried out at intervals not exceeding 10 years; ment installed)
the number of the tested containers is to be not less other arrangements for helicopter refuelling and hangar
than 10% of the total number facilities (fuel system, ventilation, fire protection and
low pressure CO2 containers are to be internally sur- detection).
veyed if the content has been released and the con-
tainer is older than five years; depending upon the 3.9 Hold, ballast and dry spaces water level
result of the internal examination, the Surveyor may detectors
require the container to be hydrostatically tested.
3.9.1 For ships subject to compliance with the require-
It is to be checked that the distribution pipework is
proved clear. ments laid down in Ch 6, Sec 2, [6], or in Ch 6, Sec 4, [2],
or in Pt B, Ch 2, Sec 1, [2.2], the class renewal survey is to
c) sprinkler system include an examination and a test of the water ingress
the associated pumps are to be opened up and detection systems and of their alarms.
examined at the Surveyors discretion
d) water spraying system 3.10 Availability of pumping systems
the associated pumps are to be opened up and
examined at the Surveyors discretion 3.10.1 For ships subject to compliance with the require-
ments laid down in Ch 6, Sec 2, [7], or in Pt C, Ch 1, Sec
a working test is to be carried out as far as reasona-
10, [6.6.3], item e), the class renewal survey is to include an
ble and appropriate
examination and a test of the means for draining and pump-
e) fixed foam systems (low or high expansion) ing ballast tanks forward of the collision bulkhead and
the associated pumps are to be opened up and bilges of dry spaces any part of which extends forward of
examined at the Surveyors discretion the foremost cargo hold, and of their controls.
3.1.4 The in-water survey is to be carried out by one or bearing clearances and stern bush clearances of oil stern
more qualified divers under surveillance of a Surveyor. The bearings based on a review of the operating history, on
diver(s) is (are) to be employed by a firm approved as serv- board testing and stern oil sample reports. These considera-
ice supplier by the Society according to Ch 2, Sec 2, [2.4]. tions are to be included in the proposals for in-water survey
The Surveyor is to be satisfied with the methods of orienta- as required in [3.1.3].
tion of the diver(s) on the plating, which should make use Upon completion of the survey, the approved diving firm is
where necessary of permanent markings on the plating at to submit to the attending Society Surveyor a detailed report
selected points and with the method of pictorial representa- including video tapes, as well as a photographic documen-
tion. An efficient two-way communication between the Sur- tation of the main parts inspected.
veyor and the diver(s) is to be provided.
3.1.6 If the in-water survey reveals damage or deterioration
3.1.5 The in-water survey is to provide the information nor- that requires immediate attention, the Surveyor may require
mally obtained from a bottom survey in dry condition. Spe- that the ship be drydocked in order that a detailed survey
cial consideration shall be given to ascertaining rudder can be undertaken and the necessary repairs carried out.
1 Survey of tailshafts 1.2.2 Where the notation MON-SHAFT has been assigned
as specified in Ch 1, Sec 2, [6.6.3], the tailshaft need not be
withdrawn at the complete survey and items b) and d) of
1.1 General [1.2.1] need not be covered provided that all condition
monitoring data (aft bearing temperature, consumption and
1.1.1 The different types of surveys to which tailshafts may analysis of lubricating oil) is found to be within permissible
be subjected and the intervals at which they are to be car- limits and the remaining requirements for the complete sur-
ried out are given in Ch 2, Sec 2, [5.5]. These surveys are: vey are complied with.
complete survey Where the Surveyor considers that the data presented is not
modified survey. entirely to his satisfaction, the shaft is to be withdrawn.
The requirements to be complied with at each survey are 1.3 Modified survey
listed in [1.2] and [1.3].
1.3.1 A modified survey may be carried out for those
1.2 Complete survey tailshafts which fulfil the conditions described in Ch 2, Sec 2,
[5.5.3], where the periodicity of this type of survey is also
1.2.1 The complete survey of tailshafts consists of the fol- shown.
lowing, as applicable: The modified survey of water lubricated systems is eligible
a) removal of propeller and key, where fitted, and their under the condition that the additional class notation
examination MON-SHAFT has been assigned as specified in Ch 1, Sec 2,
[6.6.3].
Note 1: Where the propeller is fitted keyless to the shaft taper and
where the additional class notation MON-SHAFT has been
1.3.2 General
assigned, refer to item c), Note 3.
For the different types of shafts, the following is required:
b) complete withdrawal of shaft to permit the examination
of sterntube bearings (outboard or inboard depending a) for shafts with keyed propeller coupling:
on the type of shaft)
removal of propeller and key, and their examination
c) examination by an appropriate crack detection method in way of the connection area
of the after end of the cylindrical part of the shaft and
examination by an appropriate crack detection
forward one third of shaft cone, or the fillet of the flange
method of the after end of the cylindrical part of
in the case of a flanged coupling
shaft and forward one third of shaft cone
Note 2: Refer also to Ch 2, Sec 2, [5.5.2], item b) where the crack
detection test of the aft flange fillet area may be dispensed with b) for shafts with keyless type propeller coupling:
for the solid flange couplings fitted at the end of the shaft.
check of the tightness of the propeller hub (propeller
Note 3: Refer also to Ch 2, Sec 2, [5.5.2], item b) where the propel- hood, fore gland)
ler is fitted keyless to the shaft taper, and, where the additional
class notation MON-SHAFT has been assigned, the non- c) for shafts with a solid flange coupling at the aft end and
destructive examination is carried out at intervals not exceeding variable pitch propeller:
15 years.
check of tightness in way of blade glands and distri-
bution box
d) examination of shaft bearing surfaces, liners, joints,
threaded end and nut check of analysis of hydraulic oil
e) examination of oil sealing glands with the necessary dis- working test, as far as practicable, of the blade
mantling manoeuvring.
f) measurements of clearances and/or weardown (prior to 1.3.3 See also Ch 2, Sec 2, [5.5.3] and Ch 5, Sec 6, [3], as
and after the survey) and their recording relevant.
g) opening-up of controllable pitch propellers and exami-
nation of their working parts and control gear, if consid- 1.3.4 Where the Surveyor considers that the data presented
ered necessary. is not entirely to his satisfaction, further dismantling may be
required, including withdrawal of the tailshaft.
2 Periodical survey of other propulsion 2.4.2 Where the system is fitted with:
systems a vibration monitoring of roll bearings
a temperature monitoring of bearings, and
2.1 Rotating and azimuth thrusters a monitoring of automatic bilge pumping system,
2.1.1 The periodical survey of rotating and azimuth thrust- the shaft need not be withdrawn at the complete survey and
ers consists of: items b) and d) of [1.2.1] need not be covered provided that
a) removing the propeller(s) in order to examine the fol- all condition monitoring data (vibrations and temperatures
lowing items, as applicable: in way of bearings, consumption and analysis of lubricating
oil, running rate of bilge system) are found to be within per-
exposed parts missible limits and the remaining requirements for the com-
cone and keyway to be checked by an appropriate plete survey are complied with.
crack detection method
Where the Surveyor considers that the data presented is not
sealing glands to his satisfaction, further dismantling are to be required.
threaded end and nut
b) examining the results of a lubricating oil analysis (water 3 Survey of propeller shafts and tube
content and presence of material particles) to detect shafts
possible deterioration of internal gears and bearings
c) examining the orientation device. 3.1 General
If the foregoing checks are not satisfactory, dismantling of
the internal parts may be required. 3.1.1 Application
Unless alternative means are provided to assure the condi-
2.2 Vertical axis propellers tion of the propeller shaft assembly, these requirements
apply to all ships with conventional shafting fitted with a
2.2.1 The periodical survey of vertical axis propeller sys- propeller, as follows:
tems consists of: from 1 January 2016, for ships delivered on or after
checking the tightness of the oil glands and the backlash 1 January 2016
of the gears from outside by action on the blades after the first shaft survey scheduled on or after 1 January
checking the condition of gears and couplings from 2016, for ships delivered before 1 January 2016.
inside the ship Note 1: Upon the completion of the first shaft survey scheduled
examining the results of a lubricating oil analysis (water on or after 1 January 2016, the designation of dates for the next
shaft survey is to be made based upon the requirements of this
content and presence of material particles) to detect
Article.
possible deterioration of internal gears and bearings.
Propeller
Crankshaft
Tube or pipe fitted in the shell of a ship at the stern (or multiple layer synthetic coating
rear part of the ship), below the waterline, through
which passes the tube shaft or the aftermost section of multiple layer of fibreglass
the propeller shaft.
combinations of above mentioned
Sterntube is the housing of the shaft bearings, generally
rubber/elastomer covering coating.
two (one aft and one fore), that sustain the shaft and
allow its rotation with less frictional resistance. The The means for protection against corrosion are installed/
sterntube also accommodates the shaft sealing arrange- applied according to class approved procedures.
ment.
j) Corrosion resistant shaft
e) Closed loop (system) oil lubricated bearing
Corrosion resistant shaft is made in approved corrosion
Closed loop oil lubricating systems use oil to lubricate resistant steel as core material for the shaft.
the bearings and are sealed against the environment
(seawater) by adequate sealing/gland devices. k) Sterntube sealing system
Typical means are, for example: Oil sample examination is a visual examination of the
sterntube lubricating oil taken in the presence of the
continuous metallic, corrosion resistant liners Surveyor, with a focus on water contamination.
Keyless connection is the forced coupling methodology, Verifying the satisfactory conditions of inboard and out-
between the shaft and the propeller without a key, board seals during reinstallation of the shaft and the pro-
achieved through the interference fit of the propeller peller
boss on the shaft tapered end.
Recording the bearing weardown measurements (after
q) Keyed connection reinstallation).
Checking and recording of the bearing weardown meas- Oil sample examination (for oil lubricated shafts), or
urements fresh water sample test (for closed system fresh water
lubricated shafts)
Visual inspection of all the accessible parts of the shaft-
ing system Verification of no reported repairs by grinding or weld-
ing of shaft and/or propeller.
Verification that the propeller is free of damages which
may cause the propeller to be out of balance 3.2.4 Shaft extension surveys - Extension types
Seal liner found to be or placed in a satisfactory condi- a) Extension up to 2,5 years
tion
The survey is to consist of:
Verification of the satisfactory reinstallation of the pro-
peller, including verification of the satisfactory condi- Checking and recording of the bearing weardown
measurements, as far as practicable
tions of inboard and outboard seals.
Visual inspection of all the accessible parts of the
Prerequisites, to satisfactorily verify in order to apply shafting system
method 2, are the following ones:
Verification that the propeller is free of damages
Review of service records which may cause the propeller to be out of balance
Review of test records of: Verification of the effectiveness of the inboard seal
and outboard seals.
- lubricating oil analysis (for oil lubricated shafts), or
Prerequisites, to satisfactorily verify in order to apply
- fresh water sample test (for closed system fresh water extension up to 2,5 years, are the following ones:
lubricated shafts)
Review of service records
Oil sample examination (for oil lubricated shafts), or
fresh water sample test (for closed system fresh water Review of test records of:
lubricated shafts) - lubricating oil analysis (for oil lubricated shafts),
Verification of no reported repairs by grinding or weld- or
ing of shaft and/or propeller. - fresh water sample test (for closed system fresh
water lubricated shafts)
3.2.3 Shaft survey - Method 3
Oil sample examination (for oil lubricated shafts), or
The survey is to consist of: fresh water sample test (for closed system fresh water
lubricated shafts)
Checking and recording of the bearing weardown meas-
urements Verification of no reported repairs by grinding or
welding of shaft and/or propeller
Visual inspection of all the accessible parts of the shaft-
ing system Confirmation from the Chief Engineer that the shaft-
ing arrangement is in good working condition.
Verification that the propeller is free of damages which
may cause the propeller to be out of balance b) Extension up to 1 year
Seal liner found to be or placed in a satisfactory condi- The survey is to consist of:
tion Visual inspection of all the accessible parts of the
Verification of the satisfactory conditions of inboard and shafting system
outboard seals. Verification that the propeller is free of damages
which may cause the propeller to be out of balance
Prerequisites, to satisfactorily verify in order to apply
method 3, are the following ones: Verification of the effectiveness of the inboard seal
and outboard seals.
Review of service records
Prerequisites, to satisfactorily verify in order to apply
Review of test records of: extension up to 1 year, are the following ones:
- lubricating oil analysis (for oil lubricated shafts), or Review of the previous weardown and/or clearance
recordings
- fresh water sample test (for closed system fresh water
lubricated shafts) Review of service records
Verification of the effectiveness of the inboard seal. method 2 every 5 years (prerequisites have to be
fulfilled).
Prerequisites, to satisfactorily verify in order to apply
extension up to 3 month, are the following ones: b) Survey extensions (see Tab 1)
Review of the previous weardown and/or clearance For all types of propeller connections, the interval
recordings between two consecutive surveys may be extended after
Review of service records execution of the extension survey, as follows:
Flanged propeller coupling Keyless propeller coupling Keyed propeller coupling (2)
Every five years (1) method 1 or method 2 or method 3 method 1 or method 2 or method 3 (3) method 1 or method 2
Extension 2,5 Y yes (4) yes (4) yes (4)
Extension 1 Y yes (5) yes (5) yes (5)
Extension 3 M yes (6) yes (6) yes (6)
Note 1: For surveys (method 1, or method 2, or method 3) completed within 3 months before the shaft survey due date, the next
period will start from the shaft survey due date.
The extension survey should normally be carried out within 1 month of the shaft survey due date and the extension counts from the
shaft survey due date. If the extension survey is carried out more than 1 month prior to the shaft survey due date, then the period of
extension counts from the date the extension survey was completed.
(1) Unless an extension type (extension 2,5 Y, or extension 1 Y, or extension 3 M) is applied in between.
(2) Method 3 is not allowed.
(3) The maximum interval between two surveys carried out according to method 1 or method 2 shall not exceed 15 years, except
in the case when one extension for no more than three months is granted.
(4) No more than one 2,5 year extension can be granted. No further extension, of other type, can be granted.
(5) No more than two consecutive one year extension can be granted. In the event an additional extension is requested, the
requirements of the 2,5 year extension are to be carried out and the shaft survey due date, prior to the previous extension(s),
is extended for a maximum of 2,5 years.
(6) No more than one three month extension can be granted. In the event an additional extension is requested, the requirements
of the one year extension or 2,5 year extension are to be carried out and the shaft survey due date, prior to the previous
extension, is extended for a maximum of one year or 2,5 years.
3.2.6 Closed loop system fresh water lubricated b) Survey extensions (see Tab 2)
shafts For all types of propeller connections, the interval
The maximum interval between two surveys carried out between two consecutive surveys may be extended after
according to method 1 shall not exceed 15 years. An exten- execution of the extension survey, as follows:
sion for no more than three months can be granted. Extension up to a maximum of 2,5 years
a) Survey intervals (see Tab 2) No more than one 2,5 year extension can be
granted. No further extension, of other type, can be
For surveys completed within 3 months before the shaft granted.
survey due date, the next period will start from the shaft
Extension up to a maximum of 1 year
survey due date.
No more than two consecutive one year extension
1) Flanged propeller connection can be granted. In the event an additional extension
The following methods are applicable: is requested, the requirements of the 2,5 year
extension are to be carried out and the shaft survey
method 1 every 5 years, or due date, prior to the previous extension(s), is
method 2 every 5 years (prerequisites have to be extended for a maximum of 2,5 years.
fulfilled), or Extension up to a maximum of 3 months
method 3 every 5 years (prerequisites have to be No more than one three month extension can be
fulfilled). granted. In the event an additional extension is
requested, the requirements of the one year exten-
2) Keyless propeller connection sion or 2,5 year extension are to be carried out
The following methods are applicable: and the shaft survey due date, prior to the previous
extension, is extended for a maximum of one year or
method 1 every 5 years, or 2,5 years.
method 2 every 5 years (prerequisites have to be The extension survey should normally be carried out
fulfilled), or within 1 month of the shaft survey due date and the
extension counts from the shaft survey due date.
method 3 every 5 years (prerequisites have to be
fulfilled). If the extension survey is carried out more than 1 month
prior to the shaft survey due date, then the period of
3) Keyed propeller connection extension counts from the date the extension survey was
The following methods are applicable: completed.
The maximum interval between two surveys carried out
method 1 every 5 years, or
according to method 1 shall not exceed 15 years,
method 2 every 5 years (prerequisites have to be except in the case when one extension for no more than
fulfilled). three months is granted.
Table 2 : Survey intervals for closed loop system fresh water lubricated shafts (closed systems)
Flanged propeller coupling Keyless propeller coupling Keyed propeller coupling (2)
Every five years (1) method 1 (3) or method 2 or method 3 method 1 (3) or method 2 or method 3 method 1 (3) or method 2
Extension 2,5 Y yes (4) yes (4) yes (4)
Extension 1 Y yes (5) yes (5) yes (5)
Extension 3 M yes (6) yes (6) yes (6)
Note 1: For surveys (method 1, or method 2, or method 3) completed within 3 months before the shaft survey due date, the next
period will start from the shaft survey due date.
The extension survey should normally be carried out within 1 month of the shaft survey due date and the extension counts from the
shaft survey due date. If the extension survey is carried out more than 1 month prior to the shaft survey due date, then the period of
extension counts from the date the extension survey was completed.
(1) Unless an extension type (extension 2,5 Y, or extension 1 Y, or extension 3 M) is applied in between.
(2) Method 3 is not allowed.
(3) The maximum interval between two surveys carried out according to method 1 shall not exceed 15 years.
(4) No more than one 2,5 year extension can be granted. No further extension, of other type, can be granted.
(5) No more than two consecutive one year extension can be granted. In the event an additional extension is requested, the
requirements of the 2,5 year extension are to be carried out and the shaft survey due date, prior to the previous extension(s),
is extended for a maximum of 2,5 years.
(6) No more than one three month extension can be granted. In the event an additional extension is requested, the requirements
of the one year extension or 2,5 year extension are to be carried out and the shaft survey due date, prior to the previous
extension, is extended for a maximum of one year or 2,5 years.
3.3 Water lubricated shafts (open systems) 3.3.2 Shaft extension surveys - Extension types
a) Extension up to 1 year
3.3.1 Shaft survey - Method 4 The survey is to consist of:
The survey is to consist in: Visual inspection of all the accessible parts of the
shafting system
Drawing the shaft and examining the entire shaft Verification that the propeller is free of damages
(including liners, corrosion protection system and stress which may cause the propeller to be out of balance
reducing features, where provided), inboard seal system Checking and recording of the clearances of bearing
and bearings
Verification of the effectiveness of the inboard seal.
For keyed and keyless connections: Prerequisites, to satisfactorily verify in order to apply
extension up to 1 year, are the following ones:
- removing the propeller to expose the forward end of
Review of the previous clearance recordings
the taper
Service records
- performing a non-destructive examination (NDE) by Verification of no reported repairs by grinding or
an approved surface crack detection method all welding of shaft and/or propeller
around the shaft in way of the forward portion of the
Confirmation from the Chief Engineer that the shaft-
taper section, including the keyway (if fitted). For
ing arrangement is in good working condition.
shaft provided with liners, the NDE shall be
extended to the after edge of the liner b) Extension up to 3 months
The survey is to consist of:
For flanged connection:
Visual inspection of all the accessible parts of the
Whenever the coupling bolts of any type of flange-con- shafting system
nected shaft are removed or the flange radius is made Verification that the propeller is free of damages
accessible in connection with overhaul, repairs, or which may cause the propeller to be out of balance
when deemed necessary by the Surveyor, the coupling Verification of the effectiveness of the inboard seal.
bolts and the flange radius are to be examined by means Prerequisites, to satisfactorily verify in order to apply
of an approved surface crack detection method extension up to 3 months, are the following ones:
Checking and recording the bearing clearances Review of the previous clearance recordings
Service records
Verifying that the propeller is free of damages which
Verification of no reported repairs by grinding or
may cause the propeller to be out of balance
welding of shaft and/or propeller
Verifying the satisfactory conditions of inboard seal dur- Confirmation from the Chief Engineer that the shaft-
ing reinstallation of the shaft and the propeller. ing arrangement is in good working condition.
1 Steam boilers Boiler safety valve and its relieving gear are to be examined
and tested to verify satisfactory operation.
However, for exhaust gas heated economizers, if steam can-
1.1 not be raised at port, it is the Chief Engineers responsibility
to set the safety valves at sea and the results are to be
1.1.1 Steam boilers, superheaters and economisers are to recorded in the log book for review by the Society.
be examined internally on water-steam side and fire side
and externally with the periodicity given in Ch 2, Sec 2, 1.1.6 Review of the following records since the last boiler
[5.6]. To this end, boilers are to be emptied and suitably survey is to be carried out as part of the survey:
prepared for the examination, and the water-steam side and operation
fire side are to be cleaned and cleared of soot. Where nec-
essary, the external surfaces are to be made accessible for maintenance
inspection by removal of insulation and lining. repair history
feedwater chemistry.
1.1.2 Subject to the results of this visual examination, the
Surveyor may require: 1.1.7 In addition to the above requirements, in exhaust gas
heated economizers of the shell type, accessible welded
non-destructive tests for detection of possible defects in joints are to be subjected to a visual examination for crack-
critical areas of plating and shells, pipes and stays ing. Non-destructive testing may be required for this pur-
pose.
thickness measurements of plating and shells, furnaces,
pipes and stays.
1.1.8 For electrical steam generators, in addition to the
above requirements on the water-steam side, the following
If appropriate, a new working pressure may be fixed by the items are to be verified:
Society.
condition of the electrical insulation resistance of the
When situated inside boiler combustion chambers, steam heating elements
pipes of cylindrical boilers are to be examined at their ends, verification of proper operation and functioning of indi-
and if deemed necessary by the Surveyor, a sample pipe is cation, remote control, automatic alarm and safety
to be removed for examination. devices
verification of absence of signs of corrosion and leakage
1.1.3 If the internal examination is not carried out for prac- of water
ticable reasons, the parts subject to pressure are to be sub-
mitted to a hydraulic test. opening-up of forced circulation pumps, wherever pos-
sible.
1.1.4 Boiler supports and securing arrangements (fixed and
sliding seating, chocks, rolling stays, if any, etc.) are to be 2 Thermal oil heaters
examined.
Fuel supply pipes between pumps and burners, fuel tank 2.1.2 Thermal oil heater supports and securing arrange-
valves, pipes and deck control gear are to be examined. ments are to be examined.
Heater accessories and mountings are to be externally and
1.1.5 Upon completion of the internal survey, the boiler is (as needed) internally examined.
to be examined under steam and fuel oil burners and safety Forced circulation pumps are, wherever possible, to be
devices checked under working conditions. opened up.
The adjustment of the safety valves is to be verified during Fuel supply pipes between pumps and burners, fuel tank
each boiler internal examination. valves, pipes and deck control gear are to be examined.
2.1.3 The following safety devices and instrumentation are 2.1.4 Where repairs and/or renewal of components
to be examined and tested: exposed to pressure are performed, a pressure test is to be
thermal fluid temperature safety device and control carried out to 1,5 times the working pressure.
thermal fluid flow meter
2.1.5 Upon completion of the survey, the thermal oil heater
device for low thermal fluid level in the expansion tank is to be examined under working conditions, with particular
other regulation and safety systems. attention to safety devices and controls of the plant.
that the material and equipment supplied to the ship has been
1 General built or manufactured under survey relevant to the classifica-
tion rules and delegated statutory requirements.
1.1
3 Ship construction file
1.1.1 In this Section, the Shipbuilder is understood as act-
ing directly or on behalf of the Party requesting classifica- 3.1 Ship Construction File (SCF) for all ships,
tion. except those specified in [1.1.3]
1.1.2 When a hull construction is surveyed by the Society 3.1.1 The Shipbuilder is to deliver documents for the Ship
the Shipbuilder is to provide all appropriate evidence Construction File. In the event that items have been pro-
required by the Society that the hull is built in compliance vided by another Party such as the Shipowner and where
with the rules and regulations, taking account of the rele- separate arrangement have been made for document deliv-
vant approved drawings. ery which excludes the Shipbuilder, that Party has the
responsibility.
1.1.3 For oil tankers and bulk carriers subject to SOLAS The Ship Construction File shall be reviewed for content in
Chapter II-1, Part A-1, Regulation 3-10 (goal-based ship accordance with the requirements of [3.1.3].
construction standards for bulk carriers and oil tankers), the
requirements as referred to in Article [6] and sub-articles 3.1.2 The Ship Construction File is to be placed on board
[3.2] and [5.2] are applicable. the ship by the Shipbuilder to facilitate operation, mainte-
nance, survey and repair.
2 Documentation to be available for 3.1.3 The Ship Construction File is to include but not lim-
the Surveyor during construction ited to:
as-built structural drawings including scantling details,
2.1 material details, and, as applicable, wastage allow-
ances, location of butts and seams, cross section details
2.1.1 During the construction, the Shipbuilder is to provide and locations of all partial and full penetration welds,
the Surveyors access to documentation required by the areas identified for close attention and rudders (Refer to
Society; this includes documentation retained by the Ship- Part A, Chapter 3 and Part A, Chapter 4)
builder or other third parties. manuals required for classification and statutory
requirements, e.g. loading and stability, bow doors and
2.1.2 The list of documents approved or reviewed by the
inner doors and side shell doors and stern doors oper-
Society for the specific new construction are to be made
ations and maintenance manuals (Refer to Pt B, Ch 8,
available by the Shipbuilder in due time for the Society dur-
Sec 5, [8] and Pt B, Ch 8, Sec 6, [7]
ing the construction as follows:
ship structure access manual, as applicable
a) plans and supporting documents required in Ch 2, Sec 1,
copies of certificates of forgings and castings welded
[2.3]
into the hull (Refer to NR 216 Materials and Welding)
b) examination and testing plans details of equipment forming part of the watertight and
c) NDE plans weather tight integrity of the ship
d) welding consumable details tank testing plan including details of the test require-
ments (Refer to Pt B, Ch 11, Sec 3)
e) welding procedures specifications & welding proce-
dures qualification records corrosion protection specifications (Refer to Ch 4, Sec 2,
Pt B, Ch 10, Sec 1 and Pt D, Ch 4, Sec 3)
f) welding plan or details
details for the in-water survey, if applicable, information
g) welders qualification records for divers, clearances measurements instructions etc.,
h) NDE operators qualification records tank and compartment boundaries
i) hot spot map of the structure, when additional class docking plan and details of all penetrations normally
notation VeriSTAR-HULL CM is assigned. examined at drydocking
Coating Technical File, for ships subject to compliance
2.1.3 As required, evidence of compliance with Ch 2, Sec 1, with the IMO Performance Standard for Protective Coat-
[2.1.5] is also to be made available by the Shipbuilder to the ings (PSPC) and for ships assigned with the additional
Surveyor whilst the construction process proceeds to prove service feature/additional class notation CPS(WBT).
3.2 Ship Construction File (SCF) for ships 3.2.3 Refer to Tab 1 for details of information to be further
as specified in [1.1.3] included. This information is to be kept on board the ship
and/or ashore and updated as appropriate, throughout the
3.2.1 A Ship Construction File (SCF) with specific informa- ships life, in order to facilitate safe operation, maintenance,
tion on how the functional requirements of the goal-based survey, repair and emergency measures.
ship construction standards for bulk carriers and oil tankers
have been applied in the ship design and construction is to 3.2.4 It is to be noted that parts of the SCF content may be
be provided upon delivery of a new ship, and kept on board subject to various degrees of restricted access and that such
the ship and/or ashore and updated as appropriate through- documentation may be appropriately kept ashore.
out the ships service. The content of the Ship Construction 3.2.5 The SCF is to include the list of the documents consti-
File is to conform to the requirements as specified in tuting the SCF and all information, listed in Tab 1, which is
[3.2.2]. required for a ships safe operation, maintenance, survey,
repair and in emergency situations. Details of specific infor-
3.2.2 The following design specific information is to be
mation that is not considered to be critical to safety might be
included in the Ship Construction File (SCF):
included, directly or by reference, to the other documents.
areas requiring special attention throughout the ships
life (including the critical structural areas) 3.2.6 When developing a SCF, all the columns in Tab 1 are
all design parameters limiting the operation of a ship to be reviewed to ensure that all necessary information has
been provided.
any alternatives to the rules, including structural details
and equivalency calculations 3.2.7 It may be possible to provide information listed in this
as-built drawings and information which are verified sub-article under more than one Tier II item (see Note 1) as a
to incorporate all alterations approved by the recog- single item within the SCF; for example, the Coating Techni-
nized organization or flag State during the construction cal File required by the PSPC (see Note 1 of [3.2.2]) is rele-
process including scantling details, material details, vant for both Coating life and Survey during construction.
location of butts and seams, cross-section details and Note 1: Tier II items means the functional requirements included in
locations of all partial and full penetration welds the International Goal-based Ship Construction Standards for Bulk
Carriers and Oil Tankers (GBS), adopted by IMO Res.
net (renewal) scantlings for all the structural constituent
MSC.287(87).
parts, as-built scantlings and voluntary addition thick-
nesses (refer to Part A, Chapter 3 and Part A, Chapter 4) 3.2.8 The SCF is to remain with the ship and, in addition,
minimum hull girder section modulus along the length be available to the Society and flag State throughout the
of the ship which has to be maintained throughout the ships life. Where information not considered necessary to
ships life, including cross-section details such as the be on board is stored ashore, procedures to access this
value of the area of the deck and bottom zones, the information are to be specified in the onboard SCF. The
renewal value for the neutral axis zone (refer to Part A, intellectual property provisions within the SCF are to be
Chapter 3) duly complied with.
a listing of the materials used for construction of the hull
structure and provisions for documenting changes to 4 Newbuilding survey planning
any of the above during the ships service life
copies of the certificates of forgings and castings welded 4.1
into the hull (refer to NR216 Materials and Welding)
4.1.1 Prior to commencement of surveys for any newbuild-
details of the equipment forming part of the watertight
ing project, the Shipbuilder is to discuss with the Society at
and weathertight integrity of the ship
a kick-off meeting the items of specific activities which are
tank testing plan, including details of the test require- relevant to the shipbuilding functions listed in the kick-off
ments (refer to Pt B, Ch 11, Sec 3) meeting templates given in NR540 Kick-off Meeting Tem-
details for the in-water survey, when applicable, infor- plates for Newbuilding. The purpose of the meeting is to
mation for the divers, clearance measurement instruc- review how the listed items are to be addressed. The meet-
tions etc., tank and compartment boundaries ing is to take into account the Shipbuilder construction
facilities and ship type including the list of proposed sub-
docking plan and details of all penetrations normally
contractors. This list is not exhaustive and can be modified
examined at drydocking
to reflect the construction facilities or specific ship type. A
Coating Technical File, for ships subject to compliance record of the meeting is normally to be prepared and
with the IMO Performance Standard for Protective Coat- updated by the Shipbuilder, based upon the content of the
ings (PSPC), see Note 1. kick-off meeting templates. The Shipbuilder is to agree to
Note 1: PSPC means Performance Standard for Protective Coatings: undertake ad hoc investigations during construction where
areas of concern arise and to keep the Society advised of
- for dedicated seawater ballast tanks in all types of ships and
the progress of any investigation. Whenever an investiga-
double-side skin spaces of bulk carriers, adopted by IMO Res.
MSC.215(82), as amended, and
tion is undertaken, the Shipbuilder is, in principle, to agree
to suspend relevant construction activities if warranted by
- for cargo oil tanks of crude oil tankers, adopted by IMO Res.
the severity of the problem.
MSC.288(87), as amended.
Normal
Tier II Information Further explanation Example
storage
items to be included of the content documents
location*
DESIGN
1 Design life assumed design life, in years statement or note on midship SCF-specific (1) on board
section midship section plan on board
2 Environmental assumed environmental statement referencing data SCF-specific (1) on board
conditions conditions source or Rule (specific rule
and data), or
in accordance with Rule (date
and revision)
3 Structural strength
3.1 General applied Rule applied design method alter- SCF-specific (1) on board
design (date and revision) native to Rule and subject
applied alternative to Rule structure(s) capacity plan on board
3.2 Deformation calculating conditions and allowable loading pattern loading manual on board
and results;
failure modes assumed loading conditions maximum allowable hull girder trim and stability booklet on board
bending moment and shear
force
3.3 Ultimate operational restrictions due maximum allowable cargo loading instrument on board
strength to structural strength density or storage factor instruction manual
operation and on board
maintenance manuals
3.4 Safety strength calculation results bulky output of strength strength calculation on shore
margins calculation
plan showing highly stressed areas prone to yielding on board
areas (e.g. critical structural and/or buckling
areas) prone to yielding and/or
buckling
gross hull girder section
modulus
minimum hull girder section general arrangement on board
modulus along the length of plan
the ship to be maintained
throughout the ship's life,
including cross section details
such as the value of the area of
the deck zone and bottom
zone, the renewal value for
the neutral axis zone
gross scantlings of structural structural drawings key construction plans on board
constituent parts (2)
net scantlings of structural rudder and stern frame
constituent parts, as built structural details of typical rudder and rudder stock on board
scantlings and voluntary members plans
addition thicknesses
structural details on board
yard plans (3) on shore
dangerous area plan on board
hull form (4) hull form information indicated lines plan (5), on shore
in key construction plans (2) or
hull form data stored within an
onboard computer necessary
for trim and stability and longi-
tudinal strength calculations
equivalent (6) on board
Normal
Tier II Information Further explanation Example
storage
items to be included of the content documents
location*
4 Fatigue applied Rule applied design method alter- SCF-specific (1) on board
life (date and revision) native to Rule and subject
applied alternative to Rule structure(s)
Normal
Tier II Information Further explanation Example
storage
items to be included of the content documents
location*
CONSTRUCTION
11 Construction applied construction quality recognized national or inter- SCF-specific (1) on board
quality standard national construction quality
procedures standard
12 Survey survey regime applied during applied Rules SCF-specific (1) on board
during construction (to include all (date and revision) tank testing plan
construction owner and class scheduled
inspections during construc- copies of certificates of forg- on board
tion) ings and castings welded into
the hull
information on non-destruc- non-destructive testing on board
tive examination plan
Coating Technical File on board
required by PSPC (7)
IN-SERVICE CONSIDERATIONS
13 Survey maintenance plans specific to plan showing highly stressed SCF-specific (1) on board
and the structure of the ship where areas (e.g. critical structural operation and mainte- on board
maintenance higher attention is called for areas) prone to yielding, buck- nance manuals (e.g.
ling, fatigue and/or excessive hatch covers and doors)
corrosion
preparations for survey arrangement and details of all docking plan on board
penetrations normally exam-
ined at dry-docking
gross hull girder section details for dry-docking dangerous area plan on board
modulus
minimum hull girder section details for in-water survey Ship Structure Access on board
modulus along the length of Manual
the ship to be maintained
throughout the ship's life,
including cross-section details
such as the value of the area of
the deck zone and bottom
zone, the renewal value for
the neutral axis zone
means of access to other on board
structure-integrated deep
tanks
Coating Technical File on board
required by PSPC (7)
gross scantlings of structural key construction plans on board
constituent parts (2)
net scantlings of structural rudder and rudder stock on board
constituent parts, as built
scantlings and voluntary
addition thicknesses
structural details on board
yard plans (3) on shore
hull form (4) hull form information indi- lines plan (5), on shore
cated in key construction or
plans (2)
equivalent (6) on board
Normal
Tier II Information Further explanation Example
storage
items to be included of the content documents
location*
14 Structural means of access to holds, plans showing arrangement Ship Structure Access on board
accessibility cargo and ballast tanks and and details of means of access Manual
other structure-integrated deep
tanks
means of access to other on board
structure-integrated deep
tanks
RECYCLING CONSIDERATIONS
15 Recycling identification of all materials list of materials used for the SCF-specific (1) on board
that were used in construction construction of the hull
and may need special structure
handling due to environmental
and safety concerns
* Normal storage location means a standard location where each SCF information item should be stored. However, those items
listed as being on board should be on board as a minimum to ensure that they are transferred with the ship on a change of
owner.
on board = on board ship; on shore = on shore archive. Shore archive is to be operated in accordance with applicable interna-
tional standards.
(1) SCF-specific means documents to be developed especially to meet the requirements of these GBS guidelines (MSC.1/Circ.1343).
(2) Key construction plans means plans such as midship section, main O.T. and W.T. transverse bulkheads, construction profiles/
plans, shell expansions, forward and aft sections in cargo tank (or hold) region, engine-room construction, forward construction
and stern construction drawings.
(3) Yard plans means a full set of structural drawings, which include scantling information of all structural members.
(4) Hull form means a graphical or numerical representation of the geometry of the hull. Examples would include the graphical
description provided by a lines plan and the numerical description provided by the hull form data stored within an onboard
computer.
(5) Lines plan means a special drawing which is dedicated to show the entire hull form of a ship.
(6) Equivalent (to Lines plan) means a set of information of hull form to be indicated in key construction plans for SCF purposes. Suf-
ficient information should be included in the drawings to provide the geometric definition to facilitate the repair of any part of
the hull structure.
(7) PSPC means Performance Standard for Protective Coatings for dedicated seawater ballast tanks in all types of ships and double-
side skin spaces of bulk carriers, adopted by IMO Resolution MSC.215(82), as amended and Performance Standard for Protective
Coatings for cargo oil tanks of crude oil tankers, adopted by IMO Resolution MSC.288(87), as amended.
4.1.2 The shipyard shall be requested to advise of any 5 Examination and test plan for
changes to the activities agreed at the kick off meeting and newbuilding activities
these are to be documented. E.g. if the Shipbuilder chooses
to use or change sub-contractors, or to incorporate any
5.1 Applicable for all ships except those
modification necessitated by changes in production or
specified in [1.1.3]
inspection methods, rules and regulations, structural modi-
fications, or in the event where increased inspection 5.1.1 The Shipbuilder is to provide to the Surveyor plans of
requirements are deemed necessary as a result of a substan- the items which are intended to be examined and tested.
tial non-conformance or otherwise. These plans need not be submitted for approval and examina-
tion at the time of the kick-off meeting. They are to include:
proposal for the examination of completed steelwork
4.1.3 Shipbuilding quality standards for hull structure dur- generally referred to as the block plan and are to
ing new construction are to be reviewed and agreed during include details of joining blocks together at the pre-
the kick-off meeting. Structural fabrication is to be carried erection and erection stages or at other relevant stages
out in accordance with IACS Recommendation 47, Ship- proposal for fit up examinations where necessary
building and Repair Quality Standard, or a recognized fab- proposal for testing of the structure (leak and hydro-
rication standard which has been accepted by the Society static) as well as for all watertight and weathertight clos-
prior to the commencement of fabrication/construction ing appliances
(Refer to Pt B, Ch 11, Sec 1, [1.1.4]). The work is to be car- proposal for non-destructive examination
ried out in accordance with these Rules and under survey of any other proposal specific to the ship type or to the del-
the Society. egated statutory requirements.
1.1.3 The lay-up maintenance program includes: Hot work is not be carried out during lay-up, unless special
precautionary measures are taken.
the safety conditions to be kept throughout the lay-up
period
2.1.5 Safety equipment
the measures taken to preserve the maintenance of the
ship throughout the lay-up period All the equipment usually recommended for the safety of
the watch personnel is to be provided, kept in working
the survey requirements to be complied with for lay-up,
order and tested regularly.
maintenance of class in lay-up and re-commissioning.
The usual life-saving equipment such as liferafts, life-buoys,
2 Safety conditions breathing apparatus, oxygen masks and distress signals is to
be provided and made accessible.
3.8.4 Boilers may also be preserved sealed with inert gas 4.3.2 Ships should normally be moored singly. However,
(nitrogen), provided that cocks and valves are tight and the when several ships are moored together, the following pro-
installation allows an internal pressure of at least 0,05 bar to visions are to be made:
be maintained to prevent air penetration. Regular checks of
ships are to be moored bow to stern
the overpressure are to be carried out and results recorded
in the log-book. ships are to be of approximately the same size
the number of ships moored together is, in principle, not
3.9 Automated installation to exceed six
3.9.1 Recommendations for electronic components are the breast-lines are to be of similar elasticity
same as those given for electrical installations. fenders are to be provided.
For pneumatic parts the manufacturers recommendations
are to be followed and the system is to be checked regu-
larly. 4.4 Review of the mooring arrangements
Pressure, temperature or level sensors are generally not 4.4.1 As indicated in [4.1.1], at the Owners request, the
affected by damage when not used. However, when availa- mooring arrangements may be reviewed by the Society.
ble, the manufacturers recommendations are to be followed.
4.4.2 The proposal for the mooring arrangements is in such
4 Lay-up site and mooring case to be submitted by the Owner and is to include the fol-
arrangements lowing information.
a) Mooring site:
4.1 General
geographical area (to be specified on a map)
4.1.1 The choice and suitability of the lay-up site, as well characteristics of the sea bottom
as the type of mooring conditions, the mooring arrange-
ments and their efficiency during the lay-up period remain water depth
the responsibility of the Owner. preferential angular sectors (effects of wind / tide /
However, at the Owners request, the mooring arrangement current) indicated according to statistical studies
may be reviewed by the Society. wave characteristics (amplitude, periods)
5.2.3 Upon satisfactory completion of the survey, the Cer- the crankshaft deflections of diesel engines. In addition
tificate of Classification is endorsed. when engines have been laid-up for more than two
years, one piston is to be disconnected and one liner is
to be removed for examination. Dismantling is to be
5.3 Re-commissioning survey extended if deemed necessary
the condition of blades of turbines through the inspec-
5.3.1 Owners are to make the necessary arrangements to tion doors
remove the temporary lay-up installations provided for pres-
ervation measures and the protective materials and coatings the condition of the water side of condensers and heat
(oil, grease, inhibitors, desiccants), before the survey is exchangers
commenced. the condition of expansion arrangements
It is the Owners responsibility to verify that the ship parts the condition of reduction gears through the inspection
that are not covered by class are reactivated in satisfactory doors
operational condition.
the condition after overhauling of pressure relief devices
5.3.2 The scope of the re-commissioning survey is to the test of bilge level alarms, when fitted.
include:
5.3.6 The main and emergency electrical installations are
a general examination of the hull, deck fittings, safety to be tested. The parallel shedding of main generators and
systems, machinery installations (including boilers main switchboard safety devices are to be checked. An
whose survey is not due) and steering gear insulation resistance test of the electrical installation is to be
performed.
all periodical surveys due at the date of re-commission-
ing or which became overdue during the lay-up period
5.3.7 For the fire prevention, detection and fire-fighting sys-
dealing with the recommendations due at the date of re-
tems, the following is to be examined and/or tested:
commissioning or which became due during the lay-up
period. remote control for quick closing of fuel oil valves, stop-
ping of fuel oil pumps and ventilation systems, closing
5.3.3 For the hull the following is to be carried out: of fire doors and watertight doors
fire detectors and alarms
examination of shell plating above the waterline, deck
plating, hatch covers and coamings fire-fighting equipment.
5.3.8 The automated installation is to be checked for 5.3.11 For other specific classed installations, the Owners
proper operation. are to submit a survey program to the Society.
5.3.9 When classed, the installations for refrigerated cargo 5.3.12 On completion of the above surveys, sea trials are to
are to be examined under working conditions. Where the be performed in the presence of a Surveyor of the Society.
lay-up period exceeds two years, representative compo- The sea trials are to include:
nents of the installation are to be dismantled. verification of the satisfactory performance of the deck
installations, main propulsion system and essential aux-
5.3.10 For cargo installations on liquefied gas carriers, the iliaries, including a test of the safety devices
following is to be carried out:
an anchoring test
inspection of the primary barrier in tanks complete tests of steering gear
for membrane tanks, a global gas test of tanks whose full head and full astern tests
results are to be compared with those obtained at ships tests of automated machinery systems, where applica-
delivery ble.
testing of gas piping at working pressure using inert gas.
5.3.13 Upon satisfactory completion of the surveys, a
A Surveyor of the Society is to attend the first cooling down memoranda is issued to confirm the carrying out of all rele-
and loading of the ship. vant surveys and the recommissioning of the ship.
Chapter 4
SECTION 1 GENERAL
SECTION 2 SINGLE SKIN AND DOUBLE SKIN BULK CARRIERS
SECTION 1 GENERAL
1.1.3 Owners are reminded that a general examination of 2.1.2 Tab 1 indicates which service notations are subject to
the ship having the same scope of an annual survey is to be specific requirements, and in which Section or Article they
carried out at the completion of the class renewal survey, are specified.
1.2 Documentation on board 1.2.6 For bulk carriers subject to SOLAS Chapter II-1 Part
A-1 Regulation 3-10, on completion of the survey, the Sur-
1.2.1 The Owner is to obtain, supply and maintain docu- veyor is to verify that the update of the Ship Construction
mentation on board as specified in [1.2.2] and [1.2.3], File (SCF) has been done whenever a modification of the
which is to be readily available for examination by the Sur- documentation included in the SCF has taken place.
veyor.
The documentation is to be kept on board for the lifetime of 1.2.7 For bulk carriers subject to SOLAS Chapter II-1 Part
the ship. A-1 Regulation 3-10, on completion of the survey, the Sur-
veyor is to verify that any addition and/or renewal of materi-
For bulk carriers subject to SOLAS Chapter II-1 Part A-1 als used for the construction of the hull structure is/are
Regulation 3-10, the Owner is to arrange the updating of documented within the SCF list of materials.
the Ship Construction File (SCF) throughout the ships life
whenever a modification of the documentation included in
the SCF has taken place. Documented procedures for 1.3 Reporting and evaluation of surveys
updating the SCF are to be included within the Safety Man-
agement System. 1.3.1 The data and information on the structural condition
of the ship collected during survey are evaluated for accept-
1.2.2 A survey report file is to be a part of the documenta- ability and structural integrity of the ship's cargo area.
tion on board consisting of:
reports of structural surveys 1.3.2 For CSR bulk carriers, the ship longitudinal strength is
to be evaluated, using thickness of the structural members
hull condition evaluation report (summarising the measured, renewed and reinforced, as appropriate, during
results of class renewal surveys)
the renewal surveys carried out after the ship reached
thickness measurement reports. 15 years of age (or during the 3rd renewal survey, if this one
The survey report file is also to be available in the Owner's is carried out before the ship reaches 15 years), in accord-
management office. ance with the criteria for longitudinal strength of the ship
hull girder for CSR bulk carriers specified in NR522 CSR for
1.2.3 The following additional supporting documentation Bulk Carriers, Chapter 13.
is to be available on board:
1.3.3 The final result of evaluation of the ship longitudinal
survey programme as required by [4.1.1] until such time
as the class renewal survey or intermediate survey, as strength required in [1.3.2], after renewal or reinforcement
applicable, has been completed work of structural members, if carried out as a result of ini-
tial evaluation, is to be reported as a part of the hull condi-
main structural plans of cargo holds and ballast tanks
tion evaluation report.
(for CSR ships, these plans are to include, for each struc-
tural element, both the as-built and the renewal thick-
1.3.4 When a survey is split between different survey sta-
nesses. Any thickness for voluntary addition is also to be
tions, a report is to be made for each portion of the survey.
clearly indicated on the plans. The midship section plan
A list of items examined and/or tested (pressure testing,
to be supplied on board the ship is to include the mini-
thickness measurement etc.) and an indication of whether
mum allowable hull girder sectional properties for hold
the item has been credited, are to be made available to the
transverse section in all cargo holds)
next attending Surveyor(s), prior to continuing or complet-
previous repair history ing the survey.
cargo and ballast history
1.3.5 A hull condition evaluation report (summarising the
extent of use of inert gas plant and tank cleaning proce-
results of class renewal surveys) is issued by the Society to
dures
the Owner, who is to place it on board the ship for refer-
ships personnel reports on: ence at future surveys. The hull condition evaluation report
- structural deterioration/defects in general is endorsed by the Society.
- leakage in bulkheads and piping systems
- condition of corrosion prevention system, if any 1.4 Conditions for survey
any other information that may help to identify critical
structural areas and/or suspect areas requiring inspection. 1.4.1 In order to enable the attending surveyors to carry out
the survey, provisions for proper and safe access are to be
1.2.4 For bulk carriers subject to SOLAS Chapter II-1 Part agreed between the Owner and the Society.
A-1 Regulation 3-10, the Ship Construction File (SCF), lim- Details of the means of access are to be provided in the sur-
ited to the items to be retained onboard, is to be available vey planning questionnaire.
on board.
In cases where the provisions of safety and required access
1.2.5 Prior to survey, the Surveyor examines the documen- are judged by the attending surveyor(s) not to be adequate,
tation on board and its contents, which are used as a basis the survey of the spaces involved is not to proceed.
for the survey.
1.5.4 For close-up surveys of the cargo hold shell frames of 2.1.2 A thorough survey of cargo hatch covers and coam-
bulk carriers 100,000 dwt and above, the use of portable ings is only possible by examination in the open as well as
ladders is not accepted, and one or more of the following closed positions and is to include verification of proper
means for access, acceptable to the Surveyor, is/are to be opening and closing operation. As a result, the hatch cover
provided: sets within the forward 25% of the ship's length and at least
a) Annual surveys, intermediate surveys for ships less than one additional set, such that all sets on the ship are assessed
ten years of age and class renewal surveys for ships five at least once in every five year period, are to be surveyed
years of age or less: open, closed and in operation to the full extent on each
permanent staging and passages through structures direction, including:
temporary staging and passages through structures a) stowage and securing in open condition
hydraulic arm vehicles such as conventional cherry b) proper fit and efficiency of sealing in closed condition,
pickers, lifts and movable platforms and
boats or rafts provided the structural capacity of the c) operational testing of hydraulic and power components,
hold is sufficient to withstand static loads at all lev- wires, chains, and link drives.
els of water
The closing of the covers is to include the fastening of all
other equivalent means.
peripheral, and cross joint cleats or other securing devices.
b) Subsequent intermediate surveys and class renewal sur- Particular attention is to be paid to the condition of the
veys: hatch covers in the forward 25% of the ship's length, where
either permanent or temporary staging and passages sea loads are normally greatest.
through structures for close-up survey of at least the
upper part of hold frames 2.1.3 If there are indications of difficulty in operating and
hydraulic arm vehicles such as conventional cherry securing hatch covers, additional sets above those required
pickers for surveys of lower and middle part of shell by [2.1.2], at the discretion of the Surveyor, are to be tested
frames as alternative to staging in operation.
2.1.4 Where the cargo hatch securing system does not 2.1.6 At each hatchway, the coamings, with panel stiffeners
function properly, repairs are to be carried out under the and brackets, are to be checked for corrosion, cracks and
supervision of the Society. deformation, especially of the coaming tops, including
close-up survey.
2.1.5 For each cargo hatch cover set, the following items
are to be surveyed: 2.1.7 Where considered necessary, the effectiveness of
sealing arrangements may be proved by hose or chalk test-
a) cover panels, including side plates, and stiffener attach- ing supplemented by dimensional measurements of seal
ments that may be accessible in the open position by compressing components.
close-up survey (for corrosion, cracks, deformation)
2.1.8 Where portable covers, wooden or steel pontoons are
b) sealing arrangements of perimeter and cross joints (gas- fitted, checking the satisfactory condition, where applica-
kets for condition and permanent deformation, flexible ble, of:
seals on combination carriers, gasket lips, compression
bars, drainage channels and non return valves) wooden covers and portable beams, carriers or sockets
for the portable beam, and their securing devices
c) clamping devices, retaining bars, cleating (for wastage, steel pontoons, including close-up survey of hatchcover
adjustment, and condition of rubber components) plating
d) closed cover locating devices (for distortion and attach- tarpaulins
ment) cleats, battens and wedges
e) chain or rope pulleys hatch securing bars and their securing devices
loading pads/bars and the side plate edge
f) guides
guide plates and chocks
g) guide rails and track wheels
compression bars, drainage channels and drain pipes (if
h) stoppers any).
i) wires, chains, tensioners, and gypsies 2.1.9 The annual survey is also to include:
examination of flame screens on vents to all bunker
j) hydraulic system, electrical safety devices and inter-
tanks
locks, and
examination of bunker and vent piping systems, includ-
k) end and interpanel hinges, pins and stools where fitted. ing ventilators.
Table 1 : Annual survey of cargo holds for single skin bulk carriers
(1) Where this level of survey reveals the need for remedial measures, the survey is to be extended to include a close-up survey of
all of the shell frames and adjacent shell plating of that cargo hold as well as a close-up survey of sufficient extent of all remain-
ing cargo holds.
(2) When considered necessary by the Surveyor or where extensive corrosion exists, thickness measurements are to be carried out.
If the results of these thickness measurements indicate that substantial corrosion is present, the extent of thickness measure-
ments is to be increased in accordance with Tab 12 to Tab 16. These extended thickness measurements are to be carried out
before the annual survey is credited as completed. Suspect areas identified at previous surveys are to be examined. Areas of
substantial corrosion identified at previous surveys are to have thickness measurements taken.
For ships built under the Common Structural Rules, the annual thickness gauging may be omitted where a protective coating
has been applied in accordance with the coating manufacturers requirements and is maintained in good condition.
(3) Where a hard protective coating in cargo holds as provided in [1.1.7] is found in good condition, the extent of close-up survey
and thickness measurements may be specially considered.
Table 2 : Annual survey of cargo holds for double skin bulk carriers
(1) When considered necessary by the Surveyor, or where extensive corrosion exists, thickness measurements are to be carried out.
If the results of these thickness measurements indicate that substantial corrosion is found, the extent of thickness measurements
is to be increased in accordance with Tab 17 to Tab 20. These extended thickness measurements are to be carried out before
the survey is credited as complete. Suspect areas identified at previous surveys are to be examined. Areas of substantial corro-
sion identified at previous surveys are to have thickness measurements taken.
For ships built under the Common Structural Rules, the annual thickness gauging may be omitted where a protective coating
has been applied in accordance with the coating manufacturers requirements and is maintained in good condition.
2.2.1 The requirements given in Tab 1 for single skin bulk 3.1 Ships 10 years of age or less
carriers or Tab 2 for double skin bulk carriers are to be com-
plied with.
3.1.1 The requirements for survey of cargo holds given in
Tab 3 for single skin bulk carriers or Tab 5 for double skin
2.2.2 For ships which are exempted, as per Ch 6, Sec 2, bulk carriers are to be complied with.
[1.6], from the application of the retroactive requirements
given in Ch 6, Sec 2, [1.3], Ch 6, Sec 2, [1.4] and Ch 6, Sec 3.1.2 The requirements for survey of salt water ballast tanks
2, [1.5], the scope of the annual survey for the foremost given in Tab 4 for single skin bulk carriers or Tab 6 for dou-
cargo hold is to be replaced by the scope of the intermedi- ble skin bulk carriers are to be complied with.
ate survey for the foremost cargo hold.
Table 3 : Intermediate survey of cargo holds for single skin bulk carriers
Ships 10 years of age or less at time of the intermediate survey
Table 4 : Intermediate survey of salt water ballast spaces for single skin bulk carriers
Ships 10 years of age or less at time of the intermediate survey
Overall survey of representative water ballast spaces selected by the Surveyor. The selection is to include fore and aft peak tanks and
a number of other tanks, taking into account the total number and type of ballast tanks. See (1), (2) and (3)
Overall and close-up survey of suspect areas identified at previous surveys
The minimum requirements for thickness measurements are areas found to be suspect areas at previous surveys. See (4) and (5)
(1) If such overall survey reveals no visible structural defects, the examination may be limited to verification that the corrosion pre-
vention system remains efficient.
(2) Where poor coating condition, corrosion or other defects are found in water ballast tanks or where a hard protective coating
was not applied from the time of construction, the examination is to be extended to other ballast tanks of the same type.
(3) For ballast tanks other than double bottom tanks, where a hard protective coating is found in poor condition, and it is not
renewed, or where soft or semi-hard coating has been applied or where a hard protective coating was not applied from the time
of construction, the tanks in question are to be internally examined and thickness measurement carried out as considered nec-
essary at annual surveys.
When such breakdown of hard protective coating is found in ballast double bottom tanks or where a soft or semi-hard coating
has been applied or where a hard protective coating has not been applied, the tanks in question may be internally examined at
annual surveys. When considered necessary by the Surveyor, or where extensive corrosion exists, thickness measurements are
to be carried out.
(4) The extent of thickness measurements may be specially considered provided the Surveyor is satisfied by the close-up survey,
that there is no structural diminution and the hard protective coatings are found to be in a good condition.
(5) Where substantial corrosion is found, the extent of thickness measurements is to be increased in accordance with the require-
ments of Tab 12 to Tab 16. These extended thickness measurements are to be carried out before the survey is credited as com-
pleted. Suspect areas identified at previous surveys are to be examined. Areas of substantial corrosion identified at previous
surveys are to have thickness measurements taken.
Table 5 : Intermediate survey of cargo holds for double skin bulk carriers
Ships 10 years of age or less at time of the intermediate survey
Table 6 : Intermediate survey of ballast tanks for double skin bulk carriers
Ships 10 years of age or less at time of the intermediate survey
Overall survey of representative water ballast tanks selected by the Surveyor. The selection is to include fore and aft peak tanks and a
number of other tanks, taking into account the total number and type of ballast tanks. See (1), (2) and (3)
Overall and close-up survey of suspect areas identified at previous surveys.
Thickness measurements to an extent sufficient to determine both general and local corrosion levels at areas subject to close-up sur-
vey. See (4) and (5)
(1) If such overall survey reveals no visible structural defects, the examination may be limited to verification that the corrosion pre-
vention system remains efficient.
(2) Where poor coating condition, corrosion or other defects are found in water ballast tanks or where a hard protective coating
was not applied from the time of construction, the examination is to be extended to other ballast tanks of the same type.
(3) In ballast tanks other than double bottom tanks, where a hard protective coating is found in poor condition and it is not
renewed, or where soft or semi-hard coating has been applied, or where a hard protective coating was not applied from the
time of construction, the tanks in question are to be examined and thickness measurements carried out as considered necessary
at annual surveys. When such breakdown of hard protective coating is found in ballast double bottom tanks, or where a soft or
semi-hard coating has been applied, or where a hard protective coating has not been applied, the tanks in question may be
examined at annual surveys. When considered necessary by the Surveyor, or where extensive corrosion exists, thickness meas-
urements are to be carried out.
(4) The extent of thickness measurements may be specially considered provided the Surveyor is satisfied by the close-up survey that
there is no structural diminution and the hard protective coatings are found to be in a good condition.
(5) Where substantial corrosion is found, the extent of thickness measurements is to be increased in accordance with Tab 17 to Tab
20. These extended thickness measurements are to be carried out before the survey is credited as completed. Suspect areas
identified at previous surveys are to be examined. Areas of substantial corrosion identified at previous surveys are to have thick-
ness measurements taken.
4 Class renewal survey The survey programme is to be in a written format. The sur-
vey is not to commence until the Survey Programme has
been agreed.
4.1 Survey programme and preparation for
survey Prior to the development of the Survey Programme, the sur-
vey planning questionnaire is to be completed by the
4.1.1 The Owner in cooperation with the Society is to work
Owner and forwarded to the Society.
out a specific Survey Programme prior to the commence-
ment of any part of:
The survey programme at intermediate survey may consist
the class renewal survey of the survey programme at the previous class renewal sur-
the intermediate survey for bulk carriers over 10 years of vey supplemented by the hull condition evaluation report of
age. that class renewal survey and later relevant survey reports.
4.3.4 The survey extent of ballast tanks converted to void Table 7 : Requirements for internal examination
spaces will be specially considered by the Society in rela- of fuel oil tanks in the cargo length area
tion to the requirements for ballast tanks.
Age of ship (in years at time of class renewal survey)
4.3.5 As indicated in Ch 3, Sec 3, [2.1.1], a bottom survey Class renewal
in dry condition is to be a part of the class renewal survey. Class renewal Class renewal Class renewal
survey No.4
The overall and close-up surveys and thickness measure- survey No.1 survey No.2 survey No.3
& subsequent
age 5 5 < age 10 10 < age 15
ments, as applicable, of the lower portions of the cargo age > 15
holds and ballast tanks are to be carried out during this bot- half (min. two)
tom survey in accordance with the applicable requirements none one two (1)
(1)
for class renewal surveys, if not already performed.
(1) One deep tank for fuel oil in the cargo area is to be
Note 1: Lower portions of the cargo holds and ballast tanks are included, if fitted.
considered to be the parts below light ballast water line. Note 1: Tanks considered are of the integral (structural) type.
Note 2: If a selection of tanks is accepted to be examined,
4.3.6 Where provided, the condition of the corrosion pre- then different tanks are to be examined at each class renewal
vention system of ballast tanks is to be examined. survey, on a rotational basis.
For ballast tanks, excluding double bottom tanks, where a Note 3: Peak tanks (all uses) are subject to internal examina-
hard protective coating is found in poor condition, and it is tion at each class renewal survey.
not renewed, where soft or semi-hard coating has been
applied, or where a hard protective coating has not been 4.5.2 The minimum requirements for close-up surveys are
applied from the time of construction, the tanks in question given in Tab 8 for single skin bulk carriers, in Tab 9 for dou-
are to be examined at annual surveys. Thickness measure- ble skin bulk carriers excluding ore carriers and in Tab 10
ment are to be carried out as deemed necessary by the Sur- for ore carriers.
veyor.
4.5.3 The Surveyor may extend the close-up survey as
When such a breakdown of hard protective coating is found deemed necessary taking into account the maintenance of
in water ballast double bottom tanks and it is not renewed, the spaces under survey, the condition of the corrosion pre-
where a soft or semi-hard coating has been applied, or vention system and where spaces have structural arrange-
where a hard protective coating has not been applied from ments or details which have suffered defects in similar spaces
the time of construction, the tanks in question may be or on similar ships according to available information.
examined at annual surveys. When considered necessary
by the Surveyor, or where extensive corrosion exists, thick- 4.5.4 For areas in spaces where hard protective coatings
ness measurement are to be carried out. are found to be in a good condition, the extent of close-up
surveys according to Tab 8 for single skin bulk carriers, Tab
4.3.7 Where hard protective coating in cargo holds, as pro- 9 for double skin bulk carriers excluding ore carriers and
vided in [1.1.7], is found in good condition, the extent of Tab 10 for ore carriers, may be specially considered. Refer
close-up surveys and thickness measurements may be spe- also to [4.3.7].
cially considered.
4.6 Thickness measurements
4.4 Hatch covers and coamings
4.6.1 The minimum requirements for thickness measure-
4.4.1 A survey of the items listed in [2.1] is to be carried ments at class renewal survey are given in Tab 11.
out, in addition to all hatch covers and coamings.
Note 1: Attention is drawn to specific thickness measurements to
be carried out on the bulkhead between the two foremost cargo
4.4.2 Checking of the satisfactory operation of all mechani- holds for ships which are to comply with retroactive requirements
cally operated hatch covers is to be made, including: as detailed in Ch 6, Sec 2, [1.3] and to additional thickness meas-
stowage and securing in open condition urements applicable to the side shell frames and brackets on ships
proper fit and efficiency of sealing in closed condition subject to compliance with Ch 6, Sec 2, [5].
operational testing of hydraulic and power components, 4.6.2 Provisions for extended measurements for areas with
wires, chains, and link drives. substantial corrosion are given in Tab 12 to Tab 20 and as
may be additionally specified in the survey programme as
4.4.3 Checking the effectiveness of sealing arrangements of required by [4.1]. These extended thickness measurements
all hatch covers by hose testing or equivalent. are to be carried out before the survey is credited as com-
pleted. Suspect areas identified at previous surveys are to be
4.4.4 The close-up survey and thickness measurements in examined. Areas of substantial corrosion identified at previ-
accordance with the requirements given in Tab 8, Tab 9, ous surveys are to have thickness measurements taken.
Tab 10 and Tab 11, respectively, are to be carried out. Note 1: For ships built under the Common Structural Rules, the
identified substantial corrosion areas may be:
4.5 Overall and close-up surveys protected by coating, applied in accordance with the coating
manufacturers requirements and examined at annual intervals
4.5.1 An overall survey of all tanks and spaces is to be car- to confirm the coating in way is still in good condition, or,
ried out at each class renewal survey. Fuel oil tanks in the alternatively
cargo length area are to be surveyed as per Tab 7. required to be measured at annual intervals.
4.6.3 The Surveyor may further extend the thickness meas- pitting is 1/3 or more of the actual plate thickness, the pitted
urements as deemed necessary. plate is to be considered as a substantially corroded area.
4.6.4 When pitting is found on bottom plating and its 4.6.5 For areas in tanks where hard protective coatings are
intensity is 20% or more, thickness measurements are to be found to be in a good condition (see Ch 2, Sec 2, [2.2.14]),
extended in order to determine the actual plate thickness the extent of thickness measurements according to Tab 11
out of the pits and the depth of the pits. Where the wastage may be specially considered by the Society. Refer also to
is in the substantial corrosion range or the average depth of [4.3.7].
Table 8 : Requirements for close-up survey at class renewal survey of single skin bulk carriers
One transverse web with One transverse web with associated All transverse webs with Areas to as for class
associated plating and longi- plating and longitudinals in each associated plating and longi- renewal survey for ships
tudinals in two representa- water ballast tank tudinals in each water ballast between 10 and 15 years of
tive water ballast tanks of tank age
each type (i.e. topside or
hopper side tank)
Forward and aft transverse bulkheads All transverse bulkheads in
in one ballast tank, including stiffen- ballast tanks, including stiff-
ing system ening system
Two selected cargo hold All cargo hold transverse bulkheads All cargo hold transverse
transverse bulkheads bulkheads
All cargo hold hatch covers All cargo hold hatch covers and All cargo hold hatch covers
and coamings coamings and coamings
All deck plating and underdeck struc- All deck plating and under-
ture inside line of hatch openings deck structure inside line of
between all cargo hold hatches hatch openings between all
cargo hold hatches
Note 1: See Fig 1 for areas , , , and . See also Ch 6, Sec 2, Fig 3 for zones of side shell frames for ships subject to com-
pliance with Ch 6, Sec 2, [5].
Cargo hold transverse frames.
Transverse web frame or transverse watertight bulkhead in water ballast tanks.
Cargo hold transverse bulkhead plating, stiffeners and girders, including internal structure of upper and lower stools, where fitted.
Cargo hold hatch covers and coamings (plating and stiffeners).
Deck plating and under deck structure inside line of hatch openings between cargo hold hatches.
Note 2: Close-up survey of transverse bulkheads to be carried out at four levels (see Fig 2):
- immediately above the inner bottom and immediately above the line of gussets (if fitted) and shedders for bulkheads without
lower stool
- immediately above and below the lower stool shelf plate (for bulkheads fitted with lower stools), and immediately above the line
of the shedder plates
- about mid-height of the bulkhead
- immediately below the upper deck plating and immediately adjacent to the upper wing tank, and immediately below the upper
stool shelf plate for bulkheads fitted with upper stools, or immediately below the top side tanks.
Figure 1 : Close-up surveys and thickness measurement areas for single skin and double skin bulk carriers
4 Upper
stool
Topside
tank
2
1
3
Lower
2 stool Hopper
Double bottom side tank
level 4
Upper stool
Topside tank
level 4
level 3
level 2
Lower stool
level 1 Hopper
side tank
Double bottom
Table 9 : Requirements for close-up survey at class renewal survey of double skin bulk carriers, excluding ore carriers
Table 10 : Requirements for close-up survey at class renewal survey of ore carriers
Note 1: See Fig 3 and Fig 4 for areas , , and (area not used).
Transverse web frame or watertight transverse bulkhead in ballast wing tanks and void spaces. In fore and aft peak tanks, trans-
verse web frame means a complete transverse web frame ring including adjacent structural members.
(not used in this Table).
Cargo hold transverse bulkheads plating, stiffeners and girders.
Cargo hold hatch covers and coamings.
Deck plating and underdeck structure inside line of hatch openings between cargo hold hatches.
Note 2: Close-up survey of transverse bulkheads to be carried out at four levels (see Fig 2):
Level 1 : Immediately above the inner bottom and immediately above the line of gussets (if fitted) and shedders for ships without
lower stool.
Level 2 : Immediately above and below the lower stool shelf plate (for those ships fitted with lower stools), and immediately
above the line of the shedder plates.
Level 3 : About mid-height of the bulkhead.
Level 4 : Immediately below the upper deck plating and immediately adjacent to the upper wing tank, and immediately below
the upper stool shelf plate (for those ships fitted with upper stools), or immediately below the topside tanks.
Figure 3 : Areas subject to close-up surveys and thickness measurements for double skin bulk carriers
Upper stool
Topside tank
Lower stool
Hopper
Double bottom tank side tank
Figure 4 : Areas subject to close-up surveys and thickness measurements for ore carriers
Upper stool
Lower stool
Double
bottom tank
Table 11 : Requirements for thickness measurements at class renewal survey of bulk carriers
Table 12 : Requirements for extent of thickness measurements at those areas of substantial corrosion
Class renewal survey of single skin bulk carriers within the cargo area
Table 13 : Requirements for extent of thickness measurements at those areas of substantial corrosion
Class renewal survey of single skin bulk carriers within the cargo area
Table 14 : Requirements for extent of thickness measurements at those areas of substantial corrosion
Class renewal survey of single skin bulk carriers within the cargo area
Table 15 : Requirements for extent of thickness measurements at those areas of substantial corrosion
Class renewal survey of single skin bulk carriers within the cargo area
Table 16 : Requirements for extent of thickness measurements at those areas of substantial corrosion
Class renewal survey of single skin bulk carriers within the cargo area
CARGO HOLDS
Structural member Extent of measurement Pattern of measurement
Side shell frames Suspect frame and each adjacent (a) At each end and mid-span: 5-point pattern of both web
and flange
(b) 5-point pattern within 25 mm of welded attachment to
both shell and lower sloped plate
Table 17 : Requirements for extent of thickness measurements at those areas of substantial corrosion
Class renewal survey of double skin bulk carriers within the cargo length area
4.6.6 For single skin bulk carriers, representative thickness 4.7.2 The Surveyor may extend the tank testing as deemed
measurements to determine both general and local levels of necessary.
corrosion in the shell frames and their end attachments in
all cargo holds and water ballast tanks is to be carried out. 4.7.3 Boundaries of ballast tanks are to be tested with a
For double skin bulk carriers, representative thickness meas- head of liquid to the top of air pipes.
urement to determine both general and local levels of cor-
rosion in the transverse web frames in all water ballast tanks Boundaries of ballast holds are to be tested with a head of
is to be carried out. liquid to near to the top of hatches.
Thickness measurements is also to be carried out to deter-
mine the corrosion levels on the transverse bulkhead plat- Boundaries of fuel oil tanks are to be tested with a head of
ing. The extent of thickness measurements may be specially liquid to the highest point that liquid will rise under service
considered provided the Surveyor is satisfied by the close- conditions. Tank testing of fuel oil tanks may be specially
up survey, that there is no structural diminution, and the considered based on a satisfactory external examination of
hard protective coating where applied remains efficient. the tank boundaries, and a confirmation from the Master
stating that the pressure testing has been carried out accord-
ing to the requirements with satisfactory results.
4.7 Tank testing
4.7.1 All boundaries of water ballast tanks, deep tanks and 4.7.4 The testing of double bottom tanks and other spaces
cargo holds used for water ballast within the cargo length not designed for the carriage of liquid may be omitted, pro-
area are to be pressure tested. For fuel oil tanks, only repre- vided a satisfactory internal examination together with an
sentative tanks are to be pressure tested. examination of the tanktop is carried out.
Table 18 : Requirements for extent of thickness measurements at those areas of substantial corrosion
Class renewal survey of double skin bulk carriers within the cargo length area
Table 19 : Requirements for extent of thickness measurements at those areas of substantial corrosion
Class renewal survey of double skin bulk carriers within the cargo length area
STRUCTURE IN DOUBLE SIDE SPACES OF DOUBLE SKIN BULK CARRIERS INCLUDING WING VOID SPACES OF ORE CARRIERS
Table 20 : Requirements for extent of thickness measurements at those areas of substantial corrosion
Class renewal survey of double skin bulk carriers within the cargo length area
1.2.4 For oil tankers subject to SOLAS Chapter II-1 Part A-1 In cases where the provisions of safety and required access
Regulation 3-10, the Ship Construction File (SCF), limited to are judged by the attending surveyor(s) not to be adequate,
the items to be retained onboard, is to be available on the survey of the spaces involved is not to proceed.
board.
1.2.5 Prior to survey, the Surveyor examines the documen- 1.5 Access to structures
tation on board and its contents, which are used as a basis
for the survey. 1.5.1 For overall survey, means are to be provided to ena-
ble the surveyor(s) to examine the hull structure in a safe
1.2.6 For oil tankers subject to SOLAS Chapter II-1 Part A-1 and practical way.
Regulation 3-10, on completion of the survey, the Surveyor
is to verify that the update of the Ship Construction File 1.5.2 For close-up survey, one or more of the following
(SCF) has been done whenever a modification of the docu- means for access, acceptable to the Surveyor, is to be pro-
mentation included in the SCF has taken place. vided:
permanent staging and passages through structures
1.2.7 For oil tankers subject to SOLAS Chapter II-1 Part A-1
Regulation 3-10, on completion of the survey, the Surveyor temporary staging and passages through structures
is to verify that any addition and/or renewal of materials hydraulic arm vehicles such as conventional cherry
used for the construction of the hull structure is/are docu- pickers, lifts and movable platforms
mented within the SCF inventory list.
boats or rafts
portable ladders
1.3 Reporting and evaluation of surveys
other equivalent means.
1.3.1 The data and information on the structural condition
of the ship collected during survey are evaluated for accept- 2 Annual survey - Hull items
ability and structural integrity of the ship's cargo area.
1.3.2 In case of oil tankers of 130 m in length and upwards 2.1 Weather decks
(as defined in the International Convention on Load Lines in
force), the ship's longitudinal strength is to be evaluated by 2.1.1 The survey is to include:
using the thickness of structural members measured, examination of cargo tank openings, including gaskets,
renewed and reinforced, as appropriate, during the class covers, coamings and screens
renewal survey carried out after the ship reached 10 years examination of cargo tank pressure/vacuum valves and
of age in accordance with the criteria for longitudinal flame screens
strength of the ship's hull girder for oil tankers specified in
Ch 4, App 1. examination of flame screens on vents to all bunker,
oily-ballast and oily slop tanks and void spaces
The final result of evaluation of the ship's longitudinal
strength, after renewal or reinforcement work of structural examination of cargo, crude oil washing, bunker, ballast
members, if carried out as a result of initial evaluation, is to and vent piping systems, including remote control
be reported as a part of the hull condition evaluation report. valves, safety valves and various safety devices, as well
as vent masts and headers
1.3.3 When a survey is split between different survey sta- confirmation that wheelhouse doors and windows, side-
tions, a report is to be made for each portion of the survey. scuttles and windows in superstructure and deckhouse
A list of items examined and/or tested (pressure testing, ends facing the cargo area are in satisfactory condition.
thickness measurements etc.) and an indication of whether
the item has been credited, are to be made available to the 2.2 Cargo pump rooms and pipe tunnels
next attending Surveyor(s), prior to continuing or complet-
ing the survey. 2.2.1 The survey is to include:
1.3.4 A hull condition evaluation report (summarizing the examination of all pump room bulkheads and pipe tun-
results of class renewal surveys) is issued by the Society to nels (if any) for signs of oil leakage or fractures and, in
the Owner, who is to place it on board the ship for refer- particular, the sealing arrangements of penetrations in
ence at future surveys. The hull condition evaluation report these bulkheads
is endorsed by the Society. examination of the condition of all piping systems, in
cargo pump rooms and pipe tunnels (if any)
1.4 Conditions for survey examination of the bilge and ballast arrangements.
2.3.2 When considered necessary by the Surveyor, or when examination of the emergency lighting in cargo pump
extensive corrosion exists, thickness measurements are to rooms of ships constructed after 1st July 2002
be carried out and if the results of these thickness measure- confirmation that potential sources of ignition in or near
ments indicate that substantial corrosion is found, the extent the cargo pump rooms, such as loose gear, excessive
of thickness measurements is to be increased in accordance product in bilge, excessive vapours, combustible mate-
with the requirements of Tab 4 or Tab 5. These extended rials, etc., are eliminated and that access ladders are in
thickness measurements are to be carried out before the satisfactory condition
survey is credited as completed. Suspect areas identified at
previous surveys are to be examined. Areas of substantial examination, as far as practicable, of cargo, bilge, bal-
corrosion identified at previous surveys are to have thick- last and stripping pumps for excessive gland seal leak-
ness measurements taken. age, verification of proper operation of electrical and
mechanical remote operating and shutdown devices
and operation of the pump room bilge system, and
2.3.3 For ships built under the Common Structural Rules, checking that pump foundations are intact
the identified substantial corrosion areas are required to be
confirmation that the ventilation system, including port-
examined and additional thickness measurements are to be
able equipment, if any, of all spaces in the cargo area
carried out.
(including cargo pump rooms) is operational, ducting is
intact, dampers are operational and screens are clean
2.4 Emergency towing arrangement
confirmation that electrical equipment in dangerous
zones, cargo pump rooms and other spaces is in satis-
2.4.1 The Owner or his representative is to declare to the
factory condition and has been properly maintained
attending Surveyor that no significant alterations have been
made, without prior approval from the Society, to the equip- confirmation that the remote operation of the cargo
ment and arrangements fitted on board in accordance with pump room bilge system is satisfactory
the provisions given in Pt B, Ch 9, Sec 4, [4]. examination of the cargo heating system, as appropriate
examination of the cargo-transfer arrangement and con-
2.4.2 The survey is to include:
firmation that the ship's cargo hoses are suitable for
an examination, as far as practicable, of the emergency their intended purpose and in satisfactory condition
towing arrangement confirmation that any special arrangement made for
confirmation that the aft towing arrangement is pre- bow or stern loading/unloading is in satisfactory condi-
rigged and forward chafing gear is secured to the strong- tion and test of the means of communication and
point remote shutdown of the cargo pumps.
confirmation of the proper functioning of the light,
where it is provided, on the pick-up gear marker buoy. 3.2 Instrumentation and safety devices
3.2.1 The survey is to include:
2.5 Safe access to tanker bows
examination of cargo tank gauging devices, high level
2.5.1 The access to bow arrangement is to be examined, as alarms and valves associated with overflow control
applicable. verification that installed pressure gauges on cargo dis-
charge lines are properly operational
3 Annual survey - Cargo machinery confirmation that the required gas detection instruments
are on board and satisfactory arrangements have been
items made for the supply of any required vapour detection
tubes
3.1 Cargo area and cargo pump rooms confirmation that devices provided for measuring the
temperature of the cargo, if any, operate satisfactorily.
3.1.1 The Owner or his representative is to declare to the
attending Surveyor that no modifications or alterations
which might impair safety have been made to the various
3.3 Fire-fighting systems in cargo area
installations in dangerous zones without prior approval
3.3.1 The survey is to include:
from the Society.
external examination of piping and cut-out valves of
The survey is to include: fixed fire-fighting systems related to cargo tanks and
check of the protection of cargo pump room, as applica- cargo pump rooms
ble, and in particular, check of: confirmation, as far as practicable and when appropri-
- temperature sensing devices for bulkheads glands ate, that the remote means for closing the various open-
and alarms ings are operable
- interlock between lighting and ventilation examination of the appropriate portable fire-extinguish-
ing equipment for the cargoes to be carried in accord-
- gas detection system ance with the relevant requirements given in Ch 3, Sec
- bilge level monitoring devices and alarms 1, [3.4.3]
examination of fire-fighting systems of any type fitted on 4 Intermediate survey - Hull items
board such as deck foam, water-spraying, etc., as appli-
cable in accordance with the relevant requirements
4.1 General
given in Ch 3, Sec 1, [3.4].
4.1.1 The survey of weather decks is to include:
3.4 Inert gas system examination, as far as applicable, of cargo, crude oil
washing, bunker, ballast, steam and vent piping systems
3.4.1 The survey is to include:
as well as vent masts and headers. If upon examination
external examination of the whole system, to check the there is any doubt as to the condition of the piping, the
condition of all piping, including vent piping above the piping may be required to be pressure tested, thickness
upper deck in the cargo tank area and overboard dis- measured or both
charges through the shell so far as practicable, and asso-
confirmation, if applicable, that cargo pipes are electri-
ciated components to verify, in particular, the absence
cally bonded to the hull
of signs of corrosion and leakage of gas, water or other
liquid from inert gas and water piping systems or from examination of vent line drainage arrangements.
the pressure/vacuum breaking device
4.1.2 For ships built under the Common Structural Rules,
check of proper operation of both inert gas blowers the identified substantial corrosion areas are required to be
check of proper operation of ventilation system required examined and additional thickness measurements are to be
for scrubber room (if any) carried out.
check of deck water seal for automatic water filling and
draining 4.2 Ships between 5 and 10 years of age
check of absence of water carry over in the inert gas
4.2.1 For single hull oil tankers and combination carriers,
from the deck water seal and check of the condition of
all ballast tanks are to be examined.
the non-return valve
When considered necessary by the Surveyor, thickness
check of proper operation of all remotely operated or
measurements and testing are to be carried out to ensure
automatically controlled valves and, in particular, of the
that the structural integrity remains effective.
flue gas isolating valve located on the inert gas supply
main after the blowers 4.2.2 For double hull oil tankers, an overall survey of repre-
check of proper operation of the interlocking feature fit- sentative salt water ballast tanks selected by the Surveyor is
ted to prevent soot blowers from operating when the to be carried out.
inert gas system is working If such overall survey reveals no visible structural defects,
check that the gas pressure regulating valve automati- the examination may be limited to a verification that the
cally closes when gas blowers are stopped hard protective coating remains in good condition.
check, as far as practicable and using simulated condi-
4.2.3 A ballast tank is to be examined at subsequent annual
tions where necessary, of the following alarms and
surveys where:
safety devices of the inert gas system:
a hard protective coating has not been applied from the
- high oxygen content of gas in the inert gas main
time of construction, or
- low gas pressure in the inert gas main a soft or semi-hard coating has been applied, or
- low pressure in the supply to the deck water seal
substantial corrosion is found within the tank, or
- high temperature of gas in the inert gas main, the hard protective coating is found to be in less than
including automatic shutdown devices good condition and the hard protective coating is not
- low water pressure to the scrubber, including auto- repaired to the satisfaction of the Surveyor.
matic shutdown devices
Thickness measurement is to be carried out as deemed nec-
- accuracy of portable and fixed oxygen measuring
essary by the Surveyor.
equipment by means of calibration gases
- high water level in the scrubber, including auto- 4.2.4 In addition to the requirements above, suspect areas
matic shutdown devices identified at previous surveys are to be examined.
- failure of the inert gas blowers
- failure of the power supply to the automatic control 4.3 Ships between 10 and 15 years of age
system for the gas regulating valve and to the instru-
4.3.1 The scope of intermediate survey of ships between 10
mentation for continuous indication and permanent
and 15 years of age is the scope of the preceding class
recording of pressure and oxygen content in the
renewal survey of hull, as detailed in [6] with bottom survey
inert gas main
in dry condition or bottom in water survey as applicable.
- high pressure of gas in the inert gas main However, pressure testing of all cargo and ballast tanks and
check, when practicable, of the proper operation of the the requirements for longitudinal strength evaluation of hull
inert gas system on completion of the checks listed girder as required in [6.5.5] are not required unless deemed
above. necessary by the attending Surveyor.
4.4 Ships over 15 years of age 6 Class renewal survey - Hull items
4.4.1 The scope of intermediate survey of ships over 15 6.1 Survey programme and preparation for
years of age is the scope of the preceding class renewal sur- hull survey
vey of hull, as detailed in [6] with bottom survey in dry con-
dition, except that pressure testing of ballast and cargo 6.1.1 The Owner in cooperation with the Society is to work
tanks and the requirements for longitudinal strength evalua- out a specific Survey Programme prior to the commence-
tion of hull girder as required in [6.5.5] is not required ment of any part of:
unless deemed necessary by the Surveyor. the class renewal survey
The overall and close-up surveys and thickness measure- the intermediate survey for oil tankers over 10 years of
ments, as applicable, of the lower portions of the cargo age.
tanks and water ballast tanks are to be carried out during
The survey programme is to be in a written format. The sur-
the bottom survey in accordance with the applicable
vey is not to commence until the Survey Programme has
requirements for intermediate surveys, if not already per-
been agreed.
formed.
Prior to the development of the Survey Programme, the sur-
Lower portions of the cargo and ballast tanks are consid- vey planning questionnaire is to be completed by the
ered to be the parts below light ballast water line. Owner and forwarded to the Society.
The requirements of [6.8] are not applicable. The survey programme at intermediate survey may consist
of the survey programme at the previous class renewal sur-
vey supplemented by the hull condition evaluation report of
5 Intermediate survey - Cargo that class renewal survey and later relevant survey reports.
machinery items The survey programme is to be worked out taking into
account any amendments to the survey requirements after
the last class renewal survey carried out.
5.1 Cargo area and cargo pump rooms
6.1.2 In developing the survey programme, the following
5.1.1 A general examination of the electrical equipment documentation is to be collected and consulted with a view
and cables in dangerous zones such as cargo pump rooms to selecting tanks, areas and structural elements to be exam-
and areas adjacent to cargo tanks is to be carried out for ined:
defective and non-certified safe type electrical equipment a) survey status and basic ship information
and fixtures, non-approved lighting and fixtures, and
b) documentation on board, as described in [1.2.2] and
improperly installed or defective or dead-end wiring. [1.2.3]
c) main structural plans of cargo and ballast tanks (scant-
5.1.2 The electrical insulation resistance of the electrical
lings drawings), including information regarding use of
equipment and circuits terminating in or passing through
high-tensile steels (HTS)
the dangerous zones is to be tested; however, in cases
where a proper record of testing is maintained, considera- d) Hull Condition Evaluation Report
tion may be given to accepting recent test readings effected e) relevant previous damage and repair history
by the ships personnel.
f) relevant previous survey and inspection reports from
both the Society and the Owner
5.1.3 The satisfactory condition of the cargo heating system
is to be verified. g) cargo and ballast history for the last 3 years, including
carriage of cargo under heated conditions
h) details of the inert gas plant and tank cleaning proce-
5.2 Inert gas system dures
i) information and other relevant data regarding conver-
5.2.1 The following is to be carried out:
sion or modification of the ships cargo and ballast tanks
main parts such as the scrubber, washing machines, since the time of construction
blowers, deck water seal and non-return valve are to be j) description and history of the coating and corrosion
opened out as considered necessary and examined protection system (including previous class notations), if
any
gas distribution lines and shut-off valves, including soot
blower interlocking devices, are to be examined as k) inspections by the Owners personnel during the last 3
deemed necessary years with reference to structural deterioration in gen-
eral, leakages in tank boundaries and piping and condi-
all automatic shutdown devices and alarms are to be tion of the coating and corrosion protection system if
examined and tested. any
l) information regarding the relevant maintenance level 6.2.3 The following is an indicative list of items that are to
during operation including port state control reports of be addressed in the meeting:
inspection containing hull related deficiencies, Safety a) schedule of the ship (i.e. the voyage, docking and
Management System non-conformities relating to hull undocking manoeuvres, periods alongside, cargo and
maintenance, including the associated corrective ballast operations, etc.)
action(s), and
b) provisions and arrangements for thickness measure-
m) any other information that will help identify suspect ments (i.e. access, cleaning/de-scaling, illumination,
areas and critical structural areas. ventilation, personal safety)
6.1.3 The submitted survey programme is to account for c) extent of the thickness measurements
and comply, as a minimum, with the requirements of Tab 1 d) acceptance criteria (refer to the list of minimum thick-
or Tab 2, Tab 3 and Tab 6, for close-up survey, thickness nesses)
measurements and tank testing, respectively, and is to
e) extent of close-up survey and thickness measurements
include relevant information including at least:
considering the coating condition and suspect
a) basic ship information and particulars areas/areas of substantial corrosion
b) main structural plans of cargo and ballast tanks (scant- f) execution of thickness measurements
ling drawings), including information regarding use of
high tensile steels (HTS) g) taking representative readings in general and where
uneven corrosion/pitting is found
c) arrangement of tanks
h) mapping of areas of substantial corrosion, and
d) list of tanks with information on their use, extent of
coatings and corrosion protection systems i) communication between attending surveyor(s), the
thickness measurement company operator(s) and owner
e) conditions for survey (e.g., information regarding tank
representative(s) concerning findings.
cleaning, gas freeing, ventilation, lighting, etc.)
f) provisions and methods for access to structures 6.3 Scope of survey
g) equipment for surveys
h) identification of tanks and areas for close-up survey (see 6.3.1 In addition to the requirements of annual surveys, the
[6.4]) class renewal survey is to include examination, tests and
checks of sufficient extent to ensure that the hull and related
i) identification of areas and sections for thickness meas- piping are in satisfactory condition for the new period of
urement (see [6.5]) class to be assigned, subject to proper maintenance and
j) identification of tanks for tank testing (see [6.6]) operation and to periodical surveys being carried out at the
k) identification of the thickness measurement company due dates.
l) damage experience related to the ship in question, and 6.3.2 All cargo tanks, ballast tanks, including double bot-
m) critical structural areas and suspect areas, where rele- tom tanks, pump rooms, pipe tunnels, cofferdams and void
vant. spaces bounding cargo tanks, decks and outer hull are to be
examined, and this examination is to be supplemented by
6.1.4 The Society is to advise the Owner of the maximum thickness measurement and testing as required in [6.5] and
acceptable structural corrosion diminution levels applicable [6.6], to ensure that the structural integrity remains effec-
to the ship. tive. The aim of the examination is to discover substantial
corrosion, significant deformation, fractures, damages or
6.2 Survey planning meeting other structural deterioration, that may be present.
6.2.1 The establishment of proper preparation and the 6.3.3 As indicated in Ch 3, Sec 3, [2.1.1], a bottom survey
close co-operation between the attending surveyor(s) and in dry condition is to be a part of the class renewal survey.
the owner's representatives onboard prior to and during the The overall and close-up surveys and thickness measure-
survey are an essential part in the safe and efficient conduct ments, as applicable, of the lower portions of the cargo
of the survey. During the survey on board, safety meetings tanks and ballast tanks are to be carried out during this bot-
are to be held regularly. tom survey in accordance with the applicable requirements
for class renewal surveys, if not already performed.
6.2.2 Prior to commencement of any part of the renewal Lower portions of the cargo and ballast tanks are consid-
and intermediate survey, a survey planning meeting is to be ered to be the parts below light ballast water line.
held between the attending surveyor(s), the owner's repre-
sentative in attendance, the thickness measurement com- 6.3.4 Where provided, the condition of the corrosion pre-
pany representative, where involved, and the master of the vention system of cargo tanks is to be examined.
ship or an appropriately qualified representative appointed A ballast tank is to be examined at subsequent annual sur-
by the master or Company for the purpose to ascertain that veys where:
all the arrangements envisaged in the survey programme are a hard protective coating has not been applied from the
in place, so as to ensure the safe and efficient conduct of time of construction, or
the survey work to be carried out. See also [1.1.6].
a soft or semi-hard coating has been applied, or
substantial corrosion is found within the tank, or 6.4.3 The Surveyor may extend the close-up survey as
the hard protective coating is found to be in less than deemed necessary, taking into account the maintenance of
good condition and the hard protective coating is not the tanks under survey, the condition of the corrosion pre-
repaired to the satisfaction of the Surveyor. vention system and also in the following cases:
Thickness measurement is to be carried out as deemed nec- where tanks have structural arrangements or details
essary by the Surveyor. which have suffered defects in similar tanks or on simi-
lar ships according to available information
6.4 Overall and close-up surveys where tanks have structures approved with reduced
scantlings.
6.4.1 Each class renewal survey is to include an overall sur-
vey of all tanks and spaces.
6.4.4 For areas in tanks where hard protective coatings are
6.4.2 The minimum requirements for close-up surveys are found to be in good condition, as defined in Ch 2, Sec 2,
given in Tab 1 for single hull oil tankers and combination [2.2.14], the extent of close-up surveys required according
carriers or Tab 2 for double hull oil tankers. to Tab 1 or Tab 2 may be specially considered.
Table 1 : Close-up survey at class renewal survey of single hull oil tankers and combination carriers
Figure 1 : Areas subject to close-up surveys and thickness measurements - Single hull oil tanker
Typical transverse section Typical transverse bulkhead
3 3
2 2
Girder
5 Girder
Girder
1 4
4
Table 2 : Close-up survey at class renewal survey of double hull oil tankers
Figure 2 : Areas subject to close-up surveys and thickness measurements - Combination carrier / OOC
2 3
2 and 5
Upper stool
4
Lower stool
Double
bottom tank
4
1
Figure 3 : Areas subject to close-up surveys and thickness measurements - Double hull oil tanker
2
6
2 7
6
1
3 3
5 5
Table 3 : Thickness measurements at class renewal survey of oil tankers and combination carriers
BOTTOM STRUCTURE
Structural member Extent of measurement Pattern of measurement
Bottom plating Minimum of 3 bays across tank, including aft 5-point pattern for each panel between longi-
bay tudinals and webs
Measurements around and under all suction
bell mouths
Bottom longitudinals Minimum of 3 longitudinals in each bay where 3 measurements in line across flange and
bottom plating measured 3 measurements on vertical web
Bottom girders and brackets At fore and aft transverse bulkhead, bracket Vertical line of single measurements on web
toes and in centre of tanks plating with one measurement between each
panel stiffener, or a minimum of 3 measure-
ments.
2 measurements across face flat.
5-point pattern on girder/bulkhead brackets.
Bottom transverse webs 3 webs in bays where bottom plating measured, 5-point pattern over 2 square metre area.
with measurements at both ends and middle Single measurements on face flat.
Panel stiffening Where provided Single measurements
DECK STRUCTURE
Structural member Extent of measurement Pattern of measurement
Deck plating 2 bands across tank Minimum of 3 measurements per plate per
band
Deck longitudinals Minimum of 3 longitudinals in each of 2 bays 3 measurements in line vertically on webs and
2 measurements on flange (if fitted)
Deck girders and brackets At fore and aft transverse bulkhead, bracket Vertical line of single measurements on web
toes and in centre of tanks plating with one measurement between each
panel stiffener, or a minimum of 3 measure-
ments.
2 measurements across face flat.
5-point pattern on girder/bulkhead brackets.
Deck transverse webs Minimum of 2 webs, with measurements at 5-point pattern over 2 square metre area.
both ends and middle of span Single measurements on face flat.
Panel stiffening Where provided Single measurements
SIDE SHELL AND LONGITUDINAL BULKHEADS
Structural member Extent of measurement Pattern of measurement
Deckhead and bottom strakes and Plating between each pair of longitudinals in a Single measurement
strakes in way of stringer platforms minimum of 3 bays
All other strakes Plating between every third pair of longitudi- Single measurement
nals in same 3 bays
Longitudinals on deckhead and Each longitudinal in same 3 bays 3 measurements across web and 1 measure-
bottom strakes ment on flange
All other longitudinals Every third longitudinal in same 3 bays 3 measurements across web and 1 measure-
ment on flange
Longitudinal brackets Minimum of 3 at top, middle and bottom of 5-point pattern over area of bracket
tank in same 3 bays
Web frames and cross ties 3 webs with minimum of 3 locations on each 5-point pattern over approximately 2 square
web, including in way of cross tie connections metre area, plus single measurements on web
frame and cross tie face flats
TRANSVERSE BULKHEADS AND SWASH BULKHEADS
Structural member Extent of measurement Pattern of measurement
Deckhead and bottom strakes, and Plating between pair of stiffeners at 3 locations: 5-point pattern between stiffeners over 1 metre
strakes in way of stringer platforms approximately 1/4, 1/2 and 3/4 width of tank length
All other strakes Plating between pair of stiffeners at middle Single measurement
location
Strakes in corrugated bulkheads Plating for each change of scantling at centre 5-point pattern over about 1 square metre of
of panel and at flange of fabricated connection plating
Stiffeners Minimum of 3 typical stiffeners For web, 5-point pattern over span between
bracket connections (2 measurements across
web at each bracket connection and one at
centre of span). For flange, single measure-
ments at each bracket toe and at centre of span
Brackets Minimum of 3 at top, middle and bottom of 5-point pattern over area of bracket
tank
Deep webs and girders Measurements at toe of bracket and at centre For web, 5-point pattern over about 1 square
of span metre
3 measurements across face flat
Stringer platforms All stringers with measurements at both ends 5-point pattern over 1 square metre of area
and middle plus single measurements near bracket toes
and on face flats
6.5.4 For areas in tanks where hard protective coatings are Boundaries of cargo tanks are to be tested to the highest
found to be in good condition as defined in Ch 2, Sec 2, point that liquid will rise under service conditions
[2.2.14], the extent of thickness measurements according to
Tab 3 may be specially considered. For double hull oil tankers, the testing of double bottom
tanks and other spaces not designed for the carriage of liq-
6.5.5 On oil tankers of 130 m in length and upwards (as uid may be omitted, provided a satisfactory internal exami-
defined in the International Convention on Load Lines in nation together with an examination of the tanktop is
force) and more than 10 years of age, the longitudinal carried out.
strength of the ship's hull girder is to be evaluated in com-
pliance with the requirements of Ch 4, App 1 on the basis of
the thickness of the structures measured, renewed or rein- 6.7 Cargo piping, area and pump rooms
forced, as appropriate, during the class renewal survey.
6.7.1 Cargo and crude oil washing piping on deck and
6.6 Tank testing cargo and ballast piping systems within the cargo area are
to be examined and operationally tested to working pres-
6.6.1 The requirements for tank testing at class renewal sur- sure to the attending Surveyors satisfaction to ensure that
vey are given in Tab 6. their tightness and condition remain satisfactory. Special
6.6.2 The Surveyor may extend the tank testing as deemed attention is to be given to any ballast piping in cargo tanks
necessary. and cargo piping in ballast tanks and void spaces. Surveyors
are to be advised on all occasions when this piping, includ-
6.6.3 Boundaries of ballast tanks are to be tested with a ing valves and fittings, is opened during repair periods and
head of liquid to the top of air pipes. can be examined internally.
Table 6 : Tank testing at class renewal survey of oil tankers and combination carriers
The surveyor may require dismantling and/or thickness 7.1.3 The satisfactory condition of the cargo heating system
measurements of piping. A hydraulic test is to be carried out is to be verified and, if deemed necessary by the Surveyor,
in the event of repair or dismantling or cargo, crude oil the system is to be pressure tested.
washing, or ballast piping, or where doubts arise.
7.1.4 An operating test of the remote control of pumps and
6.7.2 All safety valves on cargo piping and of cargo tanks valves and of automatic closing valves is to be carried out.
are to be dismantled for examination, adjusted and, as
applicable, resealed. 7.1.5 A general examination of the electrical equipment
6.7.3 All cargo pump room boundaries are to be generally and cables in dangerous zones such as cargo pump rooms
examined. All gas-tight shaft sealing devices are to be and areas adjacent to cargo tanks is to be carried out for
examined. The bottom of cargo pump rooms is to be pre- defective and non-certified safe type electrical equipment
sented clean for the examination of stripping devices and and fixtures, non-approved lighting and fixtures, and
gutters. improperly installed or defective or dead-end wiring.
The electrical insulation resistance of the electrical equip-
6.8 Emergency towing arrangement ment and circuits terminating in or passing through the dan-
gerous zones is to be tested; however, in cases where a
6.8.1 The survey is to include: proper record of testing is maintained, consideration may
an examination of the emergency towing arrangement be given to accepting recent test readings effected by the
confirmation that the arrangement is readily available ships personnel.
with aft towing arrangement pre-rigged and forward
chafing gear secured to the strong-point 7.2 Fire-fighting systems in cargo area
an examination of the pick-up gear, towing pennant and
chafing gear over the full length for possible deteriora- 7.2.1 The survey is to include the examination of fire-fight-
tion. Where the pennant line is stored in a watertight ing systems of any type fitted on board for the protection of
condition and can be confirmed as being maintained, the cargo area, cargo pump room and other dangerous
consideration may be given to waiving the requirement spaces, such as deck foam, water-spraying systems, etc., as
to examine the pennant line over the full length applicable in accordance with the relevant requirements
an examination of the strong-points, fairleads and ped- given in Ch 3, Sec 3, [3.8].
estal roller together with their attachments to the hull
structure. 7.3 Inert gas system
7 Class renewal survey - Cargo 7.3.1 In addition to the inspections required at the interme-
machinery items diate survey, the following is to be carried out:
a) an internal examination of:
7.1 Cargo area and cargo pump rooms
the inert gas generator, where fitted
7.1.1 Ballast and stripping pumps are to be internally
the scrubber
examined and prime movers checked. A working test is to
be carried out, as far as practicable. the deck water seal including the non-return valve
Maintenance records of cargo pumps are to be made availa- the pressure/vacuum breaking device
ble to the Surveyor.
the cooling water systems including overboard dis-
7.1.2 Where a crude oil washing system is fitted, piping, charge from the scrubber
pumps, valves and deck-mounted washing machines are to
all valves
be examined and tested for signs of leakage, and anchoring
devices of deck-mounted washing machines are to be b) a test to verify the proper operation of the system upon
checked to the Surveyor's satisfaction. completion of all survey checks.
1 General
1.2.2 A survey report file is to be a part of the documenta-
tion on board consisting of:
1.1 Application
reports of structural surveys
1.1.1 The requirements of this Section apply to all self-pro- hull condition evaluation report (summarising the
pelled ships which have been assigned the service notation results of class renewal surveys)
chemical tanker ESP. If such a ship is constructed with both thickness measurement reports.
integral and independent tanks, these requirements are
applicable only to that portion of the cargo length contain- The survey report file is also to be available in the Owner's
ing integral tanks. Combined gas carriers/chemical tankers management office.
with independent tanks within the hull are to be surveyed
as gas carriers. 1.2.3 The following additional supporting documentation
is to be available on board:
1.1.2 The requirements apply to the surveys of the hull survey program, as required in [6.1], until such time as
structure and piping systems in way of cargo tanks, pump the class renewal survey or intermediate survey, as
rooms, cofferdams, pipe tunnels and void spaces within the applicable, has been completed
cargo area and all ballast tanks. These requirements, how-
main structural plans of cargo and ballast tanks
ever, do not apply to independent tanks on deck. They are
additional to the requirements applicable to the remainder previous repair history
of the ship, given in Part A, Chapter 3 according to the rele- cargo and ballast history
vant surveys. extent of use of inert gas system and tank cleaning pro-
cedures
1.1.3 The requirements contain the minimum extent of
examination, thickness measurements and tank testing. ships personnel reports on:
When substantial corrosion and/or structural defects are - structural deterioration/defects in general
found, the survey is to be extended and is to include addi- - leakage in bulkheads and piping systems
tional close-up surveys when necessary.
- condition of coatings or corrosion prevention sys-
1.1.4 Thickness measurements of structures in areas where tems, if any
close-up surveys are required are to be carried out simulta- any other information that may help identify critical
neously with close-up surveys. structural areas and/or suspect areas requiring inspec-
tion.
1.1.5 In all cases the extent of the thickness measurements
are to be sufficient as to represent the actual average condi- 1.2.4 Prior to survey, the Surveyor examines the documen-
tion. tation on board and its contents, which are used as a basis
for the survey.
1.1.6 When, in any survey, thickness measurements are
required:
1.3 Reporting and evaluation of surveys
the procedure detailed in Ch 2, Sec 2, [2.3] is to be
applied 1.3.1 The data and information on the structural condition
the thickness measurement operator is to attend the sur- of the ship collected during survey are evaluated for accept-
vey planning meeting held prior to commencing the ability and structural integrity of the ship's cargo area.
survey.
1.3.2 A hull condition evaluation report (summarising the
1.1.7 The requirements for machinery surveys apply to sur- results of class renewal surveys) is issued by the Society to
veys of the machinery and equipment in the cargo area or the Owner, who is to place it on board the ship for refer-
dedicated to cargo service systems and are additional to ence at future surveys. The hull condition evaluation report
those given in Part A, Chapter 3 for all ships. is endorsed by the Society.
1.2 Documentation on board 1.3.3 When a survey is split between different survey sta-
tions, a report is to be made for each portion of the survey.
1.2.1 The Owner is to obtain, supply and maintain docu- A list of items examined and/or tested (pressure testing,
mentation on board as specified in [1.2.2] and [1.2.3], thickness measurements, etc.) and an indication of whether
which is to be readily available for examination by the Sur- the item has been credited, are to be made available to the
veyor. The documentation is to be kept on board for the life- next attending Surveyor(s), prior to continuing or complet-
time of the ship. ing the survey.
1.4 Conditions for survey 2.2 Cargo pump rooms and pipe tunnels
1.4.1 In order to enable the attending surveyors to carry out 2.2.1 The survey is to include:
the survey, provisions for proper and safe access are to be examination of all pump room bulkheads and pipe tun-
agreed between the Owner and the Society. nels (if any) for signs of chemical cargo leakage or frac-
tures and, in particular, the sealing arrangements of
Details of the means of access are to be provided in the sur- penetrations in pump room bulkheads
vey planning questionnaire.
examination of the condition of all piping systems, in
In cases where the provisions of safety and required access cargo pump rooms and pipe tunnels (if any)
are judged by the attending surveyors not to be adequate, examination of the bilge and ballast arrangements and
the survey of the spaces involved is to not proceed. confirmation that pumps and pipelines are identified.
1.5.2 For close-up survey, one or more of the following 2.3.2 When considered necessary by the Surveyor or when
means for access, acceptable to the Surveyor, is to be pro- extensive corrosion exists, thickness measurements are to
vided: be carried out and if the results of these thickness measure-
ments indicate that substantial corrosion is found, the extent
permanent staging and passages through structures of thickness measurements is to be increased in accordance
with Tab 4. These extended thickness measurements are to
temporary staging and passages through structures
be carried out before the survey is credited as completed.
hydraulic arm vehicles such as conventional cherry Suspect areas identified at previous surveys are to be exam-
pickers, lifts and movable platforms ined.
boats or rafts Areas of substantial corrosion identified at previous surveys
are to have thickness measurements taken.
portable ladders
other equivalent means. 2.4 Emergency towing arrangement
3.2.1 The survey is to include the following items, as far as 4.1 General
required or fitted:
4.1.1 For weather decks, an examination as far as applica-
confirmation that installed pressure gauges on cargo dis- ble of cargo, bunker, ballast, steam and vent piping systems
charge lines are properly operational as well as vent masts and headers is to be carried out. If
examination of gauging devices, high level alarms and upon examination, there is any doubt as to the condition of
valves associated with overflow control the piping, the piping may be required to be pressure tested,
thickness measured or both.
confirmation that devices provided for measuring the
temperature of the cargo and associated alarms operate The survey is also to include:
satisfactorily
confirmation that the pipelines and independent cargo
confirmation that the required gas detection instruments tanks where applicable, are electrically bonded to the
are on board and satisfactory arrangements have been hull
made for the supply of any required vapour detection
tubes. examination of vent line drainage arrangements.
4.2 Ships between 5 and 10 years of age 5.1.2 The electrical insulation resistance of the electrical
equipment and circuits terminating in or passing through
4.2.1 For ballast tanks, an overall survey of representative the dangerous zones is to be tested; however, in cases
tanks selected by the Surveyor is to be carried out. If such where a proper record of testing is maintained, considera-
inspection reveals no visible structural defects, the exami-
tion may be given to accepting recent test readings effected
nation may be limited to a verification that the hard protec-
by the ships personnel.
tive coating remains in good condition.
4.2.2 A ballast tank is to be examined at subsequent annual 5.1.3 The satisfactory condition of the cargo heating/cool-
surveys where: ing system is to be verified.
a hard protective coating has not been applied from the
time of construction, or 5.1.4 The spares for cargo area mechanical ventilation fans
a soft or semi-hard coating has been applied, or are to be available on board.
substantial corrosion is found within the tank, or
the hard protective coating is found to be in less than 5.2 Inert gas system
good condition and the hard protective coating is not
repaired to the satisfaction of the Surveyor. 5.2.1 If an inert gas system such as that installed on board
4.2.3 In addition to the requirements above, suspect areas oil tankers is fitted, the requirements given in Ch 4, Sec 3,
identified at previous surveys are to be examined. [5.2] for intermediate survey of oil tankers are to be com-
plied with.
4.3 Ships between 10 and 15 years of age
5.2.2 For ships fitted with another type of inert gas produc-
4.3.1 The scope of intermediate survey of ships between 10 ing system, the main parts such as the inert gas generator,
and 15 years of age is the scope of the preceding class deck water seal or equivalent back flow arrangement, segre-
renewal survey of hull, as detailed in [6] with bottom survey gation devices, as fitted are to be overhauled for examina-
in dry condition or bottom in water survey as applicable.
tion and alarms are to be tested.
However, pressure testing of all cargo and ballast tanks are
not required unless deemed necessary by the attending Sur- Inert gas producer isolating valves, when fitted, are to be
veyor. dismantled for examination.
5 Intermediate survey - Cargo confirmation that arrangements have been made for the
antidotes for the cargoes actually carried to be on board
machinery items
confirmation that decontamination arrangements and
5.1 Cargo area and cargo pump rooms eyewashes are operational
5.1.1 A general examination of the electrical equipment confirmation that the required gas detection instruments
and cables in dangerous zones such as cargo pump rooms are on board and that arrangements have been made for
and areas adjacent to cargo tanks is to be carried out for the supply of the appropriate vapour detection tubes
defective and non-certified safe type electrical equipment,
non-approved lighting and fixtures, and improperly confirmation that the arrangements for the stowage of
installed or defective or dead-end wiring. cargo samples are satisfactory.
6 Class renewal survey - Hull items c) main structural plans of cargo and ballast tanks (scant-
ling drawings), including information on use of high ten-
sile steels (HTS), clad steel and stainless steel
6.1 Survey program and preparation for
survey d) hull condition evaluation report
e) relevant previous damage and repair history
6.1.1 The Owner in cooperation with Society is to work out
a specific Survey Programme prior to the commencement of f) relevant previous survey and inspection reports from
any part of: both the Society and the Owner
the class renewal survey g) information regarding the use of the ship's tanks, typical
the intermediate survey for chemical tankers over cargoes and other relevant data
10 years of age. h) details of the inert gas plant and tank cleaning proce-
dures
The survey programme is to be in a written format.
i) information and other relevant data regarding conver-
Prior to the development of the survey programme, the sur-
sion or modification of the ship's cargo and ballast tanks
vey planning questionnaire is to be completed by the
since the time of construction
Owner, and forwarded to the Society.
The survey programme at intermediate survey may consist j) description and history of the coating and the corrosion
of the survey programme at the previous class renewal sur- prevention system (previous class notations), if any
vey supplemented by the hull condition evaluation report of k) inspections by the Owner's personnel during the last
that class renewal survey and later relevant survey reports. three years with reference to structural deterioration in
The survey program is to be worked out taking into account general, leakages in tank boundaries and piping and
any amendments to the survey requirements after the last condition of the coating and corrosion prevention sys-
class renewal survey carried out. tem, if any
l) information regarding the relevant maintenance level
6.1.2 In developing the Survey Programme, the following during operation including port state control reports of
documentation is to be collected and consulted with a view inspection containing hull related deficiencies, Safety
to selecting tanks, areas, and structural elements to be Management System non-conformities relating to hull
examined: maintenance, including the associated corrective
a) survey status and basic ship information action(s); and
b) documentation on board, as described in [1.2.2] and m) any other information that will help identify suspect
[1.2.3] areas and critical structural areas.
// // // //
Increased thickness
Table 1 : Requirements for close-up survey at class renewal survey of single skin chemical tankers
6.1.3 The submitted Survey Programme is to account for i) nomination of sections and areas for thickness measure-
and comply, as a minimum, with the requirements for ments according to [6.5]
close-up surveys, thickness measurements, tank testing and j) nomination of tanks for tank testing according to [6.6],
pipe testing given in Tab 1, Tab 2, Tab 3, [6.6] and [6.7.3], and the pipes that are to undergo pipe testing according
respectively and is to include relevant information includ- to [6.7.3]
ing at least:
k) identification of the thickness measurement company
a) basic ship information and particulars l) damage experience related to the ship in question.
b) main structural plans (scantling drawings), including m) critical structural areas and suspect areas, where rele-
information on the use of high tensile steels (HTS), clad vant.
steel and stainless steel
6.1.4 The survey program is also to include the maximum
c) plan of tanks acceptable structural corrosion diminution levels applicable
to the ship. The Society will advise the Owner of this infor-
d) list of tanks with information on their use, corrosion pre-
mation.
vention and condition of coating
e) conditions for survey (e.g., information regarding tank 6.2 Survey planning meeting
cleaning, gas freeing, ventilation, lighting, etc.)
6.2.1 Proper preparation and close co-operation between
f) provisions and methods for access to structures
the attending surveyor(s) and the Owner's representatives
g) equipment for surveys onboard prior to and during the survey are an essential part
in the safe and efficient conduct of the survey. During the
h) nomination of tanks and areas for close-up surveys
survey on board safety meetings are to be held regularly.
according to [6.4]
Access trunk
to stool space
C C
5
A B D
Sec C
Sec D
Additional floor
6.2.2 Prior to the commencement of any part of the Class provisions and arrangements for thickness measure-
Renewal and Intermediate Survey a survey planning meet- ments (i.e. access, cleaning/descaling, illumination,
ing is to be held between the attending Surveyor(s), the ventilation, personal safety)
Owner's Representative in attendance and the Thickness extent of the thickness measurements
measurement company representative, where involved, and
acceptance criteria (refer to the list of minimum thick-
the master of the ship or an appropriately qualified repre-
nesses)
sentative appointed by the master or Company for the pur-
pose of ascertaining that all the arrangements envisaged in extent of close-up survey and thickness measurement
the survey programme are in place, so as to ensure the safe considering the coating condition and suspect
and efficient conduct of the survey work to be carried out. areas/areas of substantial corrosion
See also Ch 2, Sec 2, [2.3.2]. execution of thickness measurements
taking representative readings in general and where
6.2.3 The following is an indicative list of items that are to uneven corrosion/pitting is found
be addressed in the meeting:
mapping of areas of substantial corrosion; and
schedule of the ship (i.e. the voyage, docking and communication between attending surveyor(s) the thick-
undocking manoeuvres, periods alongside, cargo and ness measurement company operator(s) and owner rep-
ballast operations etc.) resentative(s) concerning findings.
6.3 Scope of survey 6.3.4 Where provided, the condition of the corrosion pre-
vention system of cargo tanks is to be examined. A ballast
6.3.1 In addition to the requirements of annual surveys, the tank is to be examined at subsequent annual surveys where:
class renewal survey is to include examination, tests and a hard protective coating has not been applied from the
checks of sufficient extent to ensure that the hull and related time of construction, or
piping are in satisfactory condition for the new period of
class to be assigned, subject to proper maintenance and a soft or semi-hard coating has been applied, or
operation and to periodical surveys being carried out at the
due dates. substantial corrosion is found within the tank, or
6.3.2 All cargo tanks, ballast tanks, including double bot- the hard protective coating is found to be in less than
tom tanks, pump rooms, pipe tunnels, cofferdams and void good condition and the hard protective coating is not
spaces bounding cargo tanks, decks and outer hull are to be repaired to the satisfaction of the Surveyor.
examined, and this examination is to be supplemented by
thickness measurement and testing as required in [6.5] and Thickness measurements are to be carried out as considered
[6.6] to ensure that the structural integrity remains effective. necessary by the Surveyor.
The aim of the examination is to discover substantial corro-
sion, significant deformation, fractures, damages or other 6.3.5 In the case of independent cargo tanks, the survey
structural deterioration that may be present. consists of:
6.3.3 As indicated in Ch 3, Sec 3, [2.1.1], a bottom survey an external examination of cargo tanks
in dry condition is to be a part of the class renewal survey. an examination of cargo tank supports, chocks, keys
The overall and close-up surveys and thickness measure- and the adjacent hull structure with non-destructive
ments, as applicable, of the lower portions of the cargo testing if deemed necessary.
tanks and ballast tanks are to be carried out during this bot-
tom survey in accordance with the applicable requirements
for class renewal surveys, if not already performed. 6.3.6 The Owner or his representative is to declare to the
attending Surveyor that the arrangements in cargo tanks
Lower portions of the cargo and ballast tanks are consid- (including coating) related to the transported products are
ered to be the parts below light ballast water line. suitable for the purpose.
// // // //
6
7
Increased thickness
Table 2 : Requirements for close-up survey at class renewal survey of double skin chemical tankers
6.4 Overall and close-up surveys the tanks under survey, the condition of the corrosion pre-
vention system and also in the following cases:
6.4.1 Each class renewal survey is to include an overall sur-
vey of all tanks and all spaces. where tanks have structural arrangements or details
which have suffered defects in similar spaces or on sim-
6.4.2 The minimum requirements for close-up surveys are ilar ships according to available information
given in Tab 1 and Tab 2.
where tanks have structures approved with reduced
scantlings.
6.4.3 The survey of stainless steel tanks may be carried out
as an overall survey supplemented by close-up survey as
deemed necessary by the Surveyor. 6.4.5 For areas in tanks where hard protective coatings are
found to be in good condition, as defined in Ch 2, Sec 2,
6.4.4 The Surveyor may extend the close-up survey as [2.2.14], the extent of close-up surveys required according
deemed necessary, taking into account the maintenance of to Tab 1 and Tab 2 may be specially considered.
Table 3 : Requirements for thickness measurements at class renewal survey of chemical tankers
DECK STRUCTURE
Structural member Extent of measurement Pattern of measurement
Deck plating 2 transverse bands across tank Minimum of 3 measurements per plate per band
Deck longitudinals Every third longitudinal in each of 2 bands 3 measurements in line vertically on webs and
with a minimum of one longitudinal 2 measurements on flange (if fitted)
Deck girders and brackets At fore and aft transverse bulkhead, bracket Vertical line of single measurements on web
toes and in centre of tanks plating with one measurement between each
panel stiffener, or a minimum of 3 measure-
ments
2 measurements across flange
5-point pattern on girder/bulkhead brackets
Deck transverse webs Minimum of 2 webs, with measurements at 5-point pattern over 1 m2 area
both ends and middle of span Single measurements on flange
Vertical web and transverse bulk- Minimum of 2 webs, and both transverse bulk- 5-point pattern over 1 m2 area
head in wing ballast tank for double heads
hull design (2 metres from deck)
Panel stiffening Where applicable Single measurements
SIDE SHELL AND LONGITUDINAL BULKHEADS
Structural member Extent of measurement Pattern of measurement
Side shell and longitudinal bulk-
head plating:
deckhead and bottom strakes Plating between each pair of longitudinals Single measurement
and strakes in way of the hori- in a minimum of 3 bays (along the tank)
zontal girders
all other strakes Plating between every third pair of longitu-
dinals in same 3 bays
Side shell and longitudinal bulk-
head longitudinals on:
deckhead and bottom strakes Each longitudinal in same 3 bays 3 measurements across web and 1 measure-
ment on flange
all other strakes Every third longitudinal in same 3 bays
Longitudinals - brackets Minimum of 3 at top, middle and bottom of 5-point pattern over area of bracket
tank in same 3 bays
Vertical web and transverse bulk-
heads of double side tanks
(excluding deck area):
strakes in way of horizontal Minimum of 2 webs and both transverse 5-point pattern over approximately 2 m2
girders bulkheads area
other strakes Minimum of 2 webs and both transverse 2 measurements between each pair of ver-
bulkheads tical stiffeners
Web frames and cross ties for 3 webs with minimum of 3 locations on each 5-point pattern over approximately 2 m2 area
other tanks than double side tanks web, including in way of cross tie connections of webs, plus single measurements on flanges
and lower end bracket of web frame and cross ties
Horizontal girders Plating on each girder in a minimum of 3 bays 2 measurements between each pair of longitu-
dinal girder stiffeners
Panel stiffening Where applicable Single measurements
6.5.3 When pitting is found on bottom plating and its 6.6.2 The Surveyor may extend the tank testing as deemed
intensity is 20% or more, thickness measurements are to be necessary.
extended in order to determine the actual plate thickness
out of the pits and the depth of the pits. Where the wastage 6.6.3 Boundaries of ballast tanks are to be tested with a
is in the substantial corrosion range or the average depth of head of liquid to the top of air pipes.
pitting is 1/3 or more of the actual plate thickness, the pitted
Boundaries of cargo tanks are to be tested to the highest
plate is to be considered as a substantially corroded area.
point that liquid will rise under service conditions.
6.5.4 For areas in tanks where hard protective coatings are The testing of double bottom tanks and other spaces not
found to be in good condition, the extent of thickness meas- designed for the carriage of liquid may be omitted, provided
urements according to Tab 3 may be specially considered a satisfactory internal examination together with an exami-
by the Society. nation of the tank top is carried out.
6.6 Tank testing 6.7 Cargo piping, cargo pump rooms and
cargo tanks
6.6.1 The requirements for tank testing at class renewal sur-
vey are given in Tab 5. 6.7.1 Cargo piping on deck and cargo and ballast piping
Pressure testing of cargo tanks may be accepted based on within the tanks specified in [6.3.2] are to be examined and
confirmation from the Master stating that the pressure test- operationally tested to working pressure to attending Sur-
ing has been carried out according to the requirements with veyors satisfaction to ensure that tightness and condition
a satisfactory result. remain satisfactory. Special attention is to be given to any bal-
last piping in cargo tanks and cargo piping in ballast tanks
Table 5 : Requirements for tank testing and void spaces. Surveyors are to be advised on all occasions
at class renewal survey of chemical tankers when this piping, including valves and fittings, is opened dur-
ing repair periods and can be examined internally.
Age of ship (in years at time of class renewal survey) The Surveyor may require dismantling and/or thickness
Class renewal survey No.2 measurements of piping. A hydraulic test is to be carried out
Class renewal survey No.1 in the event of repair or dismantling of cargo or ballast pip-
and subsequent
age 5 ing, or where doubts arise.
age >5
All ballast tank boundaries All ballast tank boundaries Vent line drainage arrangements are to be examined.
Cargo tank boundaries facing All cargo tank bulkheads
ballast tanks, void spaces, 6.7.2 It is to be verified that cargo piping and independent
pipe tunnels, pump rooms or cargo tanks, where applicable, are electrically bonded to
cofferdams the hull.
6.7.3 For ships over 10 years of age, selected steel cargo 7.1.3 The satisfactory condition of the cargo heating/cool-
pipes outside cargo tanks, cargo/slop discharge pipes pass- ing system is to be verified and, if deemed necessary by the
ing through ballast tanks and void spaces and ballast pipes Surveyor, the system is to be pressure tested.
passing through cargo tanks are to be:
subjected to thickness measurement at random, or 7.1.4 Spares for cargo area mechanical ventilation fans are
selected pipe lengths are to be opened for internal to be available on board.
inspection
pressure tested to the maximum working pressure. 7.1.5 Heat exchangers and anti-sparking fans are to be
examined.
6.7.4 All safety valves on cargo piping and of cargo tanks
are to be dismantled for examination, adjusted and, as
7.1.6 An operating test of the remote control of pumps and
applicable, resealed.
valves and of automatic closing valves is to be carried out.
6.7.5 All cargo pump room boundaries are to be generally
examined. All gas-tight shaft sealing devices are to be 7.1.7 A general examination of the electrical equipment
examined. The bottom of cargo pump rooms is to be pre- and cables in dangerous zones such as cargo pump rooms
sented clean for the examination of stripping devices and and areas adjacent to cargo tanks is to be carried out for
gutters. defective and non-certified safe type electrical equipment,
non-approved lighting and fixtures, and improperly
6.8 Emergency towing arrangement installed or defective or dead-end wiring.
7.1 Cargo area and cargo pump rooms 7.3.1 The requirements given in [5.2] for intermediate sur-
vey are to be complied with.
7.1.1 Ballast and stripping pumps are to be internally
examined and prime movers checked. A working test is to 7.3.2 If an inert gas system such as that installed on board
be carried out. oil tankers is fitted, the requirements given in Ch 4, Sec 3,
Maintenance records of cargo pumps are to be made availa- [7.3] for class renewal survey of oil tankers are to be com-
ble to the Surveyor. plied with.
They are additional to the requirements applicable to the 2.2.2 Examination of bunker and vent piping systems.
remainder of the ship, given in Part A, Chapter 3, according 2.2.3 Suspect areas identified at previous surveys are to be
to the relevant surveys. examined. Thickness measurements are to be taken of the
areas of substantial corrosion and the extent of thickness
1.1.3 The requirements contain the minimum extent of measurements is to be increased to determine the extent of
examination, thickness measurements and tank testing. areas of substantial corrosion, as per the requirements of
When substantial corrosion, as defined in Ch 2, Sec 2, Tab 4.
[2.2.7], and/or structural defects are found, the survey is to
These extended thickness measurements are to be carried
be extended and is to include additional close-up surveys
out before the annual survey is credited as completed.
when necessary.
1.1.4 Thickness measurements of structures in areas where 2.3 Cargo handling rooms and piping
close-up surveys are required are to be carried out simulta-
2.3.1 The survey is to include:
neously with close-up surveys.
examination of cargo pump rooms, compressor rooms
and cargo control rooms and, as far as practicable, pipe
1.1.5 When, in any survey, thickness measurements are tunnels if fitted
required: examination of all pump room and compressor room
bulkheads for signs of leakage or fractures and, in par-
the procedure detailed in Ch 2, Sec 2, [2.3] is to be
ticular, the sealing arrangements of all penetrations of
applied
pump room and compressor room bulkheads
the thickness measurement operator is to attend the sur- examination of all accessible gas-tight bulkhead pene-
vey planning meeting held prior to commencing the trations including gas-tight shaft sealings
survey. examination of the sealing arrangements for tanks or
tank domes penetrating decks or tank covers
examination of the means for accomplishing gas tight- 2.6 Emergency towing arrangement
ness of the wheelhouse doors and windows. All win-
dows and sidescuttles within the area required to be of 2.6.1 The Owner or his representative is to declare to the
the fixed type (non-opening) are to be examined for gas attending Surveyor that no significant alterations have been
tightness. The closing devices for all air intakes and made, without prior approval from the Society, to the equip-
openings into accommodation spaces, service spaces, ment and arrangements fitted on board in accordance with
machinery spaces, control stations and approved open- the provisions given in Pt B, Ch 9, Sec 4, [4].
ings in superstructures and deckhouses facing the cargo
area or bow and stern loading/unloading arrangements,
2.6.2 The survey is to include:
are to be examined
examination of cargo and process piping, including the an examination, as far as practicable, of the emergency
expansion arrangements, insulation from the hull struc- towing arrangement
ture, pressure relief and drainage arrangements
confirmation that the aft towing arrangement is pre-
examination of venting systems, including vent masts rigged and forward chafing gear is secured to the strong-
and protective screens, for cargo tanks, interbarrier point
spaces, hold spaces, fuel tanks and ballast tanks
confirmation of the proper functioning of the light,
examination of cargo tank and interbarrier space relief
where it is provided, on the pick-up gear marker buoy.
valves and associated safety systems and alarms
confirmation that the certificate for the relief valve
opening/closing pressures is on board and that the cargo 3 Annual survey - Cargo machinery
tank relief valves are sealed items
examination of drip trays or insulation for deck protec-
tion against cargo leakage
confirmation of proper maintenance of arrangements for
3.1 Cargo area and cargo pump rooms
the airlocks
3.1.1 The survey is to include:
confirmation that all accessible cargo piping systems are
electrically bonded to the hull examination of mechanical ventilation fans in gas-dan-
visual examination of arrangements for burning meth- gerous spaces and zones
ane boil-off as far as practicable.
examination and confirmation of the satisfactory opera-
tion of mechanical ventilation of spaces normally
2.4 Other arrangements or devices entered during operation
2.5 Ballast tanks examination of cargo (if accessible), bilge, ballast and
stripping pumps for excessive gland seal leakage
2.5.1 Ballast tanks are to be internally examined when
confirmation that electrical equipment in gas-dangerous
required as a consequence of the results of the class
spaces and zones is in satisfactory condition and has
renewal survey or the intermediate survey; see [6.3.7] and
been properly maintained
footnote (3) of Tab 1, respectively.
examination, as far as possible, of arrangements for the
2.5.2 When considered necessary by the Surveyor, or use of cargo as fuel, and associated instrumentation and
where extensive corrosion exists, thickness measurement is safety devices.
to be carried out. If the results of these thickness measure-
ments indicate that substantial corrosion is found, then the confirmation that, if fitted, cargo reliquefaction or refrig-
extent of thickness measurements are to be increased to eration equipment is in satisfactory condition
determine the extent of areas of substantial corrosion in
accordance with the requirements given in Tab 4. These confirmation that relevant instruction and information
extended thickness measurements are to be carried out material such as cargo handling plans, filling limit infor-
before the annual survey is credited as completed. mation, cooling down procedures, etc., is available on
board.
3.2 Instrumentation and safety devices confirmation that any air drying system and any inter-
barrier and hold space purging inert gas system are sat-
3.2.1 The survey is to include: isfactory
confirmation that installed pressure gauges on cargo dis- for membrane containment systems normal operation of
charge lines are operational (see Note 1) the nitrogen control system for insulation and interbar-
rier spaces shall be confirmed to the Surveyor by the
confirmation that cargo tank liquid level gauges are Master.
operational and that high level alarms as well as auto-
matic shut-off systems are satisfactory (see Note 1)
confirmation that the temperature indicating equipment 4 Intermediate survey - Hull items
of the cargo containment system and associated alarms
are satisfactory (see Note 1)
4.1 General
examination of the logbooks for confirmation that the
emergency shutdown system has been tested 4.1.1 A survey planning meeting is to be held prior to the
confirmation that cargo tank, hold and insulation space commencement of the survey.
pressure gauging systems and associated alarms are sat-
isfactory (see Note 1)
4.2 Weather decks, cargo handling rooms
examination, and testing as appropriate, of fixed gas and piping
detection equipment
confirmation of the availability and suitability of the 4.2.1 The survey is to include:
portable gas detection equipment and instruments for examination, as far as applicable, of cargo and process,
measuring oxygen levels liquid nitrogen (if any), ballast, stripping and vent piping
systems as well as vent masts and headers. If upon
Note 1: Verification of these devices is to be done by one or more examination there is any doubt as to the condition of
of the following methods:
the piping, pressure testing, thickness measurement or
visual external examination both may be required
comparing of read outs from different indicators examination of vent line drainage arrangements
consideration of read outs with regard to the actual cargo and/ confirmation that cargo pipes and independent cargo
or actual conditions tanks, where applicable, are electrically bonded to the
examination of maintenance records with reference to cargo hull.
plant instrumentation maintenance manual
verification of calibration status of the measuring instruments. 4.3 Salt water ballast tanks
3.3 Fire-fighting systems in cargo area 4.3.1 The requirements for survey of salt water ballast tanks
given in Tab 1 are to be complied with.
3.3.1 The survey is to include the examination of fire-fight-
4.3.2 For ships having independent tanks of type C, with a
ing systems of any type fitted on board for the protection of
midship section similar to that of a general cargo ship, the
the cargo area, cargo pump room, cargo compressor room
extent of close-up surveys may be specially considered by
and other dangerous spaces, such as deck foam, water-
the Society.
spraying and dry powder systems, as applicable in accord-
ance with the relevant requirements given in Ch 3, Sec 1,
[3.4].
5 Intermediate survey - Cargo
machinery items
3.4 Environmental control for cargo
containment systems 5.1 General
3.4.1 The survey is to include: 5.1.1 The aim of the intermediate survey is to supplement
the examinations and tests as provided for the annual the annual survey by testing cargo handling installations
survey of inert gas systems of oil tankers, given in Ch 4, with related automatic control, alarm and safety systems for
Sec 3, [3.4] correct functioning.
Table 1 : Intermediate survey of salt water ballast tanks for liquefied gas carriers
5.2 Cargo area and cargo pump rooms 5.2.3 In addition to the requirements of [5.2.1] and [5.2.2],
the survey also consists of:
5.2.1 Electrical equipment and cables in dangerous zones confirmation that the cargo heating/cooling system is in
such as cargo pump rooms, cargo compressor rooms and satisfactory condition
spaces adjacent to and areas above cargo tanks are to be confirmation that spares are provided for cargo area
examined as far as practicable and tested with particular mechanical ventilation fans
regard to: confirmation that the heating system of the hull struc-
ture is in satisfactory working condition
protective earthing (spot check) general examination and test of leakage detection sys-
tems in interbarrier and hold spaces.
integrity of enclosures
examination, as far as practicable, of the piping of the 6 Class renewal survey - Hull items
gas detection system for corrosion and damage. The
integrity of the suction lines between suction points and
6.1 Preparation for survey
analysing units is to be verified as far as possible
calibration of gas detectors or verification thereof with 6.1.1 The Owner is to provide the necessary facilities for a
sample gases safe and practical execution of the surveys, including the
means of providing access to structures for close-up survey,
confirmation that two sets of portable gas detection
thickness measurements and tank testing. All other provi-
equipment suitable for the cargoes to be carried and a
sions described in Ch 2, Sec 2, [2.3], Ch 2, Sec 2, [2.5], Ch
suitable instrument for measuring oxygen levels are pro-
2, Sec 2, [2.6], Ch 2, Sec 2, [2.7] and Ch 2, Sec 2, [2.9]
vided
regarding procedures for thickness measurements, condi-
test of the manually operated emergency shutdown sys- tions for survey, access to structures, equipment for survey
tem (without flow in the pipelines) to verify that the sys- and survey at sea or at anchorage, respectively, are also to
tem will cause the cargo pumps and compressors to be complied with.
stop.
5.3.2 The arrangements for the use of cargo as fuel are to 6.2 Survey programme
be examined, when applicable. It is to be tested, as far as
6.2.1 A specific survey programme should be worked out
practicable, that the gas supply to the machinery space is
in advance of the class renewal survey by the Owner in
cut-off should the exhaust ventilation not be functioning
cooperation with the Society.
correctly and that master gas fuel valve may be remotely
closed from within the machinery space. 6.2.2 The survey programme is to include conditions for
The instrumentation and safety systems for burning cargo as survey, access to structures and equipment for surveys, tak-
fuel are to be examined in accordance with [5.3.1]. ing into account the minimum requirements of Tab 2 and
Tab 3 for close-up survey and thickness measurements, and
[6.6] for tank testing.
5.4 Inert gas system
6.3 Scope of survey
5.4.1 If an inert gas system such as that installed on board
oil tankers is fitted, the requirements given in Ch 4, Sec 3, 6.3.1 A survey planning meeting is to be held prior to the
[5.2] for intermediate survey of oil tankers are to be com- commencement of the survey.
plied with.
6.3.2 In addition to the requirements of annual surveys, the
5.4.2 In the case of low temperature liquid nitrogen stor- class renewal survey is to include examination, tests and
age, the plant and its associated arrangements for protecting checks of sufficient extent to ensure that the hull and related
the hull structure against liquid nitrogen leakage are to be piping, as required in [6.3.4], are in satisfactory condition
examined. and fit for the intended purpose for the new period of class
to be assigned, subject to proper maintenance and opera-
5.5 Personnel protection tion and to periodical surveys being carried out at the due
dates.
5.5.1 The survey is to include:
6.3.3 Ballast tanks, including double bottom tanks, pump
confirmation that two complete sets of safety equipment rooms, compressor rooms, pipe tunnels, cofferdams and
each permitting personnel to enter and work in a gas- void spaces bounding cargo tanks, decks and outer hull are
filled space are provided and properly stowed to be examined, and this examination is to be supple-
confirmation that the requisite supply of compressed air mented by thickness measurement and testing as required
is provided and examination, when applicable, of the in [6.5] and [6.6], to ensure that the structural integrity
arrangements for any special air compressor and low- remains effective. The aim of the examination is to discover
pressure air line system substantial corrosion, significant deformation, fractures,
confirmation that the medical first-aid equipment, damages or other structural deterioration that may be
including stretchers and oxygen resuscitation equip- present.
ment and antidotes, when available, for the products to
6.3.4 All piping systems within the above spaces, are to be
be carried are provided
examined and operationally tested to working pressure to
confirmation that respiratory and eye protection suitable attending Surveyor's satisfaction to ensure that tightness and
for emergency escape purposes are provided condition remain satisfactory.
confirmation that decontamination arrangements and
eyewashes are operational 6.3.5 The survey extent of ballast tanks converted to void
spaces is to be specially considered in relation to the
examination, when applicable, of the arrangements to
requirements for ballast tanks.
protect personnel against the effects of a major cargo
Note 1: For survey of automatic air pipe heads, refer to Ch 3, Sec 3,
release by a special suitably designed and equipped
Tab 1.
space within the accommodation spaces.
6.3.8 Where the hard protective coating in ballast tanks is 6.5 Thickness measurements
found to be in a good condition, the extent of close-up surveys
and thickness measurements may be specially considered. 6.5.1 The minimum requirements for thickness measure-
ments at class renewal survey are given in Tab 3.
6.4 Overall and close-up surveys 6.5.2 The Surveyor may extend the thickness measure-
ments as deemed necessary. When thickness measurements
6.4.1 An overall survey of all tanks and spaces, excluding indicate substantial corrosion, the extent of thickness meas-
fuel oil, lube oil and fresh water tanks, is to be carried out at urements is to be increased to determine the extent of areas
each class renewal survey. However, for fuel oil, lube oil of substantial corrosion in accordance with the require-
and fresh water tanks, the requirements given in Ch 3, Sec ments given in Tab 4.
3, Tab 2 are to be complied with.
Table 3 : Requirements for thickness measurements at class renewal survey of liquefied gas carriers
Table 4 : Requirements for extent of thickness measurements at those areas of substantial corrosion
Plating Suspect area and adjacent plates 5-point pattern over 1 m2 of plating
Stiffeners Suspect area 3 measurements each in line across web and flange
6.5.3 For areas in tanks where hard protective coatings are 6.7 Cargo tank structure
found to be in good condition as defined in Ch 2, Sec 2,
[2.2.14], the extent of thickness measurements according to
6.7.1 All cargo tanks are to be cleaned and examined inter-
Tab 3 may be specially considered by the Society.
nally.
6.5.4 For ships having independent tanks of type C, with a
midship section similar to that of a general cargo ship, the 6.7.2 When accessible, the outer surface of uninsulated
extent of thickness measurements may be increased to the cargo tanks or the outer surface of cargo tank insulation
tank top plating to the satisfaction of the Surveyor. together with any vapour or protective barrier is to be exam-
ined. Special attention is to be given to the tank and insula-
6.5.5 Transverse sections are to be chosen where the larg-
tion in way of chocks, supports and keys. Removal of
est reductions are suspected to occur or are revealed from
deck plating measurements. insulation, in part or entirely, may be required in order to
verify the condition of the tank or the insulation itself if
deemed necessary by the Surveyor.
6.6 Tank testing
Where the arrangement is such that the insulation cannot
6.6.1 All boundaries of water ballast tanks and deep tanks
used for water ballast within the cargo area are to be pres- be examined entirely, the surrounding structures of wing
sure tested. For fuel oil tanks, the representative tanks are to tanks, double bottom tanks and cofferdams are to be exam-
be pressure tested. ined for cold spots when the cargo tanks are in the cold
condition, unless voyage records together with the instru-
6.6.2 The Surveyor may extend the tank testing as deemed mentation give sufficient evidence of the integrity of the
necessary. insulation system.
6.6.3 Tank testing of fuel oil tanks is to be carried out with a
head of liquid to the highest point that liquid will rise under 6.7.3 Thickness measurements may be required if deemed
service conditions. Tank testing of fuel oil tanks may be spe- necessary by the Surveyor.
cially considered based on a satisfactory external examina-
tion of the tank boundaries, and a confirmation from the Close-up surveys are to be carried out in independent cargo
Master stating that the pressure testing has been carried out tanks of type B and C at those areas where corrosion may
according to the requirements with satisfactory results. develop.
6.7.4 Non-destructive testing is to supplement cargo tank 6.7.9 As far as accessible, hold spaces and hull insulation
inspection with special attention to be given to the integrity (if provided), secondary barriers and tank supporting struc-
of the main structural members, tank shell and highly tures are to be visually examined. The secondary barrier of
stressed parts, including welded connections as deemed tanks is to be checked for its effectiveness by means of a
necessary by the Surveyor. pressure/vacuum test, a visual examination or any other
However, for type C tanks, this does not mean that non- acceptable method.
destructive testing can be dispensed with totally.
6.7.10 For membrane, semi-membrane and internal insula-
The following items are, inter alia, considered highly tion tank systems, inspection and testing are to be carried
stressed areas: out in accordance with programmes specially prepared in
cargo tank supports and anti-rolling or anti-pitching accordance with an approved method for the actual tank
devices system.
web frames or stiffening rings For membrane containment systems, a tightness test of the
Y-connection of shell plates and longitudinal bulkhead primary and secondary barriers shall be carried out in
of bilobe tanks accordance with the system designers' procedures and
swash bulkhead boundaries acceptance criteria as approved by the Society. Low differ-
ential pressure tests may be used for monitoring the cargo
dome and stump connections to the shell plating
containment system performance, but they are not consid-
foundations for pumps, towers, ladders, etc. ered as an acceptable test for the tightness of the secondary
pipe connections. barrier.
For membrane containment systems with glued secondary
6.7.5 For independent tanks of type B, the extent of non- barriers, if the designer's threshold values are exceeded, an
destructive testing is to be as given in a program specially investigation is to be carried out and additional testing such
prepared for the cargo tank design. as thermographic or acoustic emission testing should be
carried out.
6.7.6 The tightness of all cargo tanks is to be verified by an
appropriate procedure. Provided that the effectiveness of
6.7.11 All gas-tight bulkheads are to be examined and the
the ship's gas detection equipment has been confirmed, it
effectiveness of gas-tight shaft sealing is to be verified.
will be acceptable to utilise this equipment for the tightness
test of independent tanks below deck. 6.7.12 It is to be verified that independent cargo tanks are
6.7.7 Where the results of the examinations dealt with in electrically bonded to the hull.
[6.7.1] to [6.7.6] or the examination of the voyage records
6.7.13 The pressure relief valves for the cargo tanks are to
raise doubts as to the structural integrity of a cargo tank, a
be opened for examination, adjusted, function tested and
hydraulic or hydropneumatic test is to be carried out.
sealed. If the cargo tanks are equipped with relief valves
For integral tanks and for independent tanks of type A and with non-metallic membranes in the main or pilot valves,
B, the test pressure is not to be less than the MARVS. these non-metallic membranes are to be replaced. Where a
For independent tanks of type C, the test pressure is not to proper record of continuous overhaul and re-testing of indi-
be less than 1,25 times the MARVS. vidually identifiable relief valves is maintained, considera-
tion may be given to acceptance on the basis of opening,
6.7.8 When the ship is 10 years old, at every alternate class internal examination and testing of a representative sample
renewal survey, independent cargo tanks of type C are to be of valves, including each size and type of liquefied gas or
either: vapour relief valves in use, provided there is evidence in the
hydraulically or hydro-pneumatically tested to log-book that the remaining valves have been overhauled
1,25 times the MARVS, and thereafter non-destructively and tested since crediting of the previous class renewal sur-
tested in accordance with [6.7.4], or vey.
subjected to thorough non-destructive testing in accord-
ance with a program specially prepared for the tank 6.8 Weather decks, cargo handling rooms
design submitted by the Owner to the Society for and piping
acceptance. If a special program of non-destructive test-
ing does not exist, special attention is to be given to the 6.8.1 Piping for cargo and process, liquid nitrogen (if any),
detection of surface cracks in welded connections in ballast, stripping and venting systems is to be examined to
highly stressed areas as listed in [6.7.4]. At least 10% of the Surveyor's satisfaction and opened as deemed neces-
the length of the welded connections in each of the sary. Insulation is to be removed as deemed necessary to
above-mentioned areas is to be tested. This testing is to ascertain the condition of the pipes. If the visual examina-
be carried out internally and externally, as applicable. tion raises doubts as to the integrity of the pipelines, a pres-
Insulation is to be removed as necessary for the required sure test at 1,25 times the MARVS for the pipeline is to be
non-destructive testing. carried out. After reassembly the complete piping systems
are to be tested for leaks.
Where hold space atmosphere control is permanently main-
tained, the scope of external examination of the tanks and It is to be verified that cargo piping systems are electrically
their supports may be reduced at the Surveyor's discretion. bonded to the hull.
6.8.2 The pressure relief valves on cargo piping are to be testing of systems for de-energising non-certified safe
function tested. A random selection of valves is to be electrical equipment located in spaces protected by air-
opened for examination and adjusted. locks, such as electric motor rooms, cargo control
rooms, etc.
6.8.3 All cargo pump room, compressor room and control
room boundaries are to be generally examined. Gas-tight 7.1.3 The electrical insulation resistance of the electrical
shaft sealing devices are to be examined. The bottom of equipment and circuits in dangerous zones is to be meas-
cargo pump rooms and cargo compressor rooms is to be ured. These measurements are only to be effected when the
presented clean for the examination of stripping devices ship is in a gas-free or inerted condition. Where a proper
and gutters. record of testing is maintained, consideration may be given
to accepting recent readings by the ships personnel.
6.8.4 Pressure/vacuum relief valves, rupture discs and other
pressure relief devices for interbarrier spaces and/or hold 7.1.4 When there is a reliquefaction or refrigeration plant,
spaces are to be examined and, if necessary, opened and and/or arrangements for the use of cargo as fuel, the corre-
tested in accordance with their design. sponding machinery and equipment, such as cargo pumps,
Vent line drainage arrangements are to be examined. compressors, heat exchangers, condensers and process
pressure vessels, are to be surveyed to the same extent as
required for similar equipment on board oil tankers at the
6.9 Emergency towing arrangement class renewal survey (refer to Ch 4, Sec 3).
6.9.1 The survey is to include: 7.1.5 In addition to the requirements of [7.1.1] to [7.1.4],
an examination of the emergency towing arrangement the survey also consists of:
confirmation that spares are provided for cargo area
confirmation that the arrangement is readily available
mechanical ventilation fans
with aft towing arrangement pre-rigged and forward
chafing gear secured to the strong-point confirmation that the installation for heating the hull
structure is in satisfactory working condition
an examination of the pick-up gear, towing pennant and
chafing gear over the full length for possible deteriora- general examination and testing of leakage detection
tion. Where the pennant line is stored in a watertight systems in interbarrier spaces and hold spaces
condition and can be confirmed as being maintained, examination of gas detection piping system for corro-
consideration may be given to waiving the requirement sion or damage; checking, as far as possible, of the
to examine the pennant line over the full length integrity of suction lines between suction points and
an examination of the strong-points, fairleads and ped- analysing units
estal roller together with their attachments to the hull examination and tests of systems for the removal of
structure. water from interbarrier spaces and hold spaces
examination of portable equipment, such as hoses and
7 Class renewal survey - Cargo spool pieces used for segregation of piping systems for
machinery items cargo, inert gas and bilge pumping.
7.3.2 In the case of low temperature liquid nitrogen stor- d) examination of cargo and process piping, including the
age, the plant and its associated arrangements for protecting expansion arrangements, insulation from the hull struc-
the hull structure against liquid nitrogen leakage are to be ture, pressure control valves, inlet/outlet valves, drain-
examined. age arrangements and high pressure manifolds
e) examination of the relief valves, their sealing and asso-
7.4 Personnel protection ciated safety systems and alarms
7.4.1 The requirements given in [5.5] are to be complied f) confirmation that the certificate for the relief valves
with. opening/closing pressures is on board
g) examination of high pressure pumps as far as practica-
8 First loaded voyage of ships carrying ble (including gland leakage and vibration indications)
liquefied natural gases (LNG) in bulk h) external examination of vaporisers and their fittings
i) external examination of heat exchangers
8.1
j) examination of drip trays or insulation for deck protec-
8.1.1 The survey requirements for the examination before tion and recesses against cargo leakage in revaporisa-
and after the first loaded voyage for ships assigned with the tion area
service notation liquefied gas carrier, carrying liquefied
k) confirmation that all accessible cargo piping systems
natural gases (LNG) in bulk are to be carried out in accord-
and components (cargo suction drum(s), vaporisers,
ance with Pt D, Ch 9, Sec 1, [4.2.4].
high pressure pumps) are electrically bonded to the
hull.
9 Revaporisation installation
9.2.3 Instrumentation and safety devices
9.1 Application The survey is to include examination of pressure gauges,
control valves, metering unit, temperature and vibration
9.1.1 The requirements of this Article are applicable to self- indicating equipments. Particular attention is to be given to
propelled ships which have been assigned the notations: high pressure pumps instrumentation and safety devices.
liquefied gas carrier RV, or Confirmation that the instrumentation fitted on revaporisa-
liquefied gas carrier RV STL-SPM tion equipment and in contact with gas and associated
alarms are satisfactory.
These requirements apply to the revaporisation installation
Examination and testing, as appropriate, of fixed gas detec-
and to the area in way of this installation.
tion equipment.
Reference is also made to other Articles of this Section for
items dedicated to the revaporisation installation such as Examination of the logbooks for confirmation that the auto-
cargo tanks or control stations. matic emergency shut-down system has been tested. Confir-
mation that the automatic shut-down system is satisfactory.
9.2 Annual survey 9.2.4 Other arrangements or devices
9.2.1 General The survey is to include confirmation that:
The annual survey of the revaporisation installation is pref- relevant shipboard instructions and procedures of the
erably carried out during unloading operations with this revaporisation installation are available
installation in operation.
the revaporisation control station is in satisfactory work-
Revaporisation installation operational record entries ing condition.
(Bridge and Cargo logbooks) since the last survey are to be
examined in order to check the past performance of the sys- Water spraying system against gas leakage is to be surveyed
tem and to establish whether certain parts have shown any in accordance with the relevant requirements given in Ch 3,
irregularities in operation. Sec 1, [3.4].
Water deluge system is to be examined, including piping
9.2.2 Equipment in contact with gas or in gas
dangerous areas nozzles if fitted, and distribution valves. The starting of the
pump is to be tested.
The survey is to include:
a) examination of the cargo suction drum(s) and their seal-
9.3 Intermediate survey
ing arrangements if applicable
b) examination of the areas dedicated to revaporisation 9.3.1 General
equipments The aim of the intermediate survey is to supplement the
c) examination of closing devices of air intakes and open- annual survey by testing the revaporisation installation with
ings into dedicated spaces for revaporisation if applica- related automatic control, alarm and safety systems for cor-
ble rect functioning.
9.3.2 Equipment in contact with gas or in gas b) When accessible, the outer surface of uninsulated cargo
dangerous areas suction drum(s) or the outer surface of unit insulation
The maintenance records of vaporisers are to be reviewed. together with any vapour or protective barrier is to be
If deemed necessary by the Surveyor, thickness measure- examined. Particular attention is to be given to the stock-
ments, pressure test and/or opening-up and internal exami- ing unit and insulation in way of supports. Removal of
nation as far as practicable may be required. Particular insulation, in part or entirely, may be required in order to
attention is to be given to rupture device if fitted. verify the condition of the unit or the insulation itself if
deemed necessary by the Surveyor.
The survey is also to include:
c) Thickness measurements or non-destructive testing may
a) examination, as far as applicable, of stripping and vent be required if deemed necessary by the Surveyor.
piping systems and high pressure manifolds of cargo
d) The tightness of cargo suction drums is to be verified by
and process. If upon examination there is any doubt as
an appropriate procedure.
to the condition of the piping, pressure testing, thickness
measurement or both may be required e) Where the results of the examinations in items a) to e) or
the examination of the operational records raise doubts
b) examination of vent line drainage arrangements
as to the structural integrity of the unit, a hydraulic or
c) confirmation that cargo pipes and revaporisation com- hydro pneumatic test is to be carried out. The test pres-
ponents are electrically bonded to the hull sure is not to be less than 1,25 times the MARVS.
d) random test of high pressure pumps lifting device f) When the ship is 10 years old, at every alternate class
renewal survey, cargo suction drum(s) is (are) to be
e) thickness measurements of cargo suction drum(s) if either: hydraulically tested and thereafter non-destruc-
deemed necessary by the Surveyor tively tested or subjected to thorough non-destructive
f) examination of electrical equipment according to [5.2]. testing as per [6.7.8].
g) As far as accessible, the cargo suction drum(s) support-
9.3.3 Instrumentation and safety devices ing structures are to be visually examined.
The survey is to include examination of pressure gauges, h) Their fittings, valves and safety devices are to be opened
control valves, metering unit, liquid level gauges, tempera- up, as deemed necessary by the Surveyor, for visual
ture and vibration indicating equipments, and associated examination and pressure tested as appropriate.
alarms. Particular attention is to be given to high pressure
pumps instrumentation and safety devices. 9.4.3 Equipment in contact with gas or in gas
The above mentioned instrumentation is to be tested by dangerous areas
changing pressure, level and temperature as far as practica- Piping for cargo and process, stripping, venting systems
ble and comparing with test instruments. Simulated tests high pressure manifolds are to be examined to the Sur-
may be accepted for sensors which are not accessible. The veyor's satisfaction. Insulation is to be removed as deemed
test is to include alarms and safety functions. necessary to ascertain the condition of the pipes. If the vis-
ual examination raises doubts as to the integrity of the pipe-
The manually operated emergency shut-down system is to
lines, a pressure test at 1,25 times the MARVS for the
be operationally tested to verify that the system will cause
pipeline is to be carried out. After reassembly the complete
the revaporisation installation to stop.
piping systems are to be tested for leaks.
9.3.4 Other arrangements or devices Maintenance records and log books of high pressure pumps
Water deluge system is to be tested as deemed necessary by including starting pumps are to be made available to the
the Surveyor. Surveyor. As deemed necessary by the Surveyor, the high
pressure pumps are to be opened up for visual examination
and their parts and components pressure tested. The lifting
9.4 Class renewal survey device is to be tested.
The bottom of the high pressure pump recess and vaporiser
9.4.1 General
spaces are to be presented clean for the examination of gut-
In addition to the requirements of annual surveys, the class ters and stripping devices.
renewal survey is to include examination, tests and checks
of sufficient extent to ensure that the revaporisation installa- The pressure relief valves are to be opened for examination,
tion is in satisfactory condition for the new period of class adjusted, function tested and sealed. The valves including
to be assigned, subject to proper maintenance and opera- inlet/outlet valves, pressure control valves and discharge
tion and to periodical surveys being carried out at the due valves are to be tested for proper operation.
dates. The maintenance records of vaporisers are to be reviewed.
The Surveyor may require as considered necessary:
9.4.2 Cargo suction drum
external and internal examination of vaporisers which
The following requirements apply: are to be presented clean
a) Cargo suction drum(s) is (are) to be presented clean and opening up of their fittings, valves and safety devices for
examined internally. visual examination and pressure tests
thickness measurements and/or pressure test 10.2.2 Piping and flexible riser
confirmation that cargo pipes and revaporisation com- The survey is to include:
ponents are electrically bonded to the hull. external examination of readily accessible parts includ-
Particular attention is to be taken in way of the vaporiser ing the outer sheath and the end fittings
rupture device if fitted. examination of pipes and their connections, of accesso-
As deemed necessary by the Surveyor, the vaporisers heat ries including gas vent systems, bending restrictors,
exchangers are to be opened up for visual examination and clamps and supports. Confirmation that there is no
their parts and components are to be pressure tested, as loose holding or connection
appropriate. A working test is also to be carried out, includ- examination of gas vent valves.
ing testing of alarms and safety devices.
The electrical equipment are to be surveyed according to 10.2.3 STL-SPM compartment, handling and
connecting systems
[7.1.2] and [7.1.3].
The annual survey is to include:
9.4.4 Instrumentation and safety devices a general examination of components of the installation
The survey is to include examination of pressure gauges, including winches, heave compensator and sheaves,
control valves, metering unit, liquid level gauges, tempera- rope guides, capstans, rope, hatch system, locking
ture and vibration indicating equipments, and associated mechanism, quick release unit, sealing devices, chain
alarms. Particular attention is to be given to high pressure stoppers, fairleads, pedestal roller and covers to verify
pumps instrumentation and safety devices. their satisfactory condition.
The above mentioned instrumentation is to be tested by an examination of the hull structures supporting and
changing pressure, level and temperature as applicable and adjacent to the installation, to verify that no deforma-
comparing with test instruments. Simulated tests may be tions or fractures have developed. Particular attention is
accepted for sensors which are not accessible. The test is to to be given to the lower part of the trunk, intermittently
include alarms and safety functions. in contact with sea water.
The emergency shut-down system is to be tested. confirmation that emergency escape route is practicable
and not blocked
9.4.5 Other arrangements or devices
a visual examination of the lower hatch covers, the seal-
Water spraying system against gas leakage, when fitted, are
ing arrangements as far as practicable, the supporting
to be surveyed in accordance with the relevant require-
and locking devices.
ments given in Ch 3, Sec 3, [3.8].
For water deluge system: 10.2.4 Swivel system
the associated pumps are to be opened up and exam- The survey is to include:
ined at the Surveyor's discretion
a) external examination of gas, electrical or/and hydraulic
a working test is to be carried out. swivels with instrumentation and safety devices
b) examination of piping systems including leak drainage
10 STL-SPM system
c) examination of connectors
10.1 Application d) examination of handling arm when fitted
10.1.1 The requirements of this Article apply to self-pro- e) tests of protective devices
pelled ships which have been assigned the notations lique- f) examination of support structure.
fied gas carrier RV STL-SPM. These requirements apply to
the installation for non permanent mooring or for connec- 10.2.5 Others
tion to single buoy and for cargo unloading and to the area The survey is to include:
in way of this installation.
a) examination of pressure gauges, control valves, temper-
Reference is also made to above Articles of this Section for
ature and vibration indicating equipments
items dedicated to the STL-SPM installation such as ventila-
tion or fire fighting. b) confirmation that the instrumentation dedicated to STL-
SPM and associated alarms are satisfactory
10.2 Annual survey c) examination and testing, as appropriate, of fixed gas
detection equipment
10.2.1 General
d) examination of the vent line drainage arrangements and
The Owner or his representative is to declare to the attend-
the trunk structure
ing Surveyor that no significant alterations have been made
without the prior approval of the Society. e) examination of blast relief panels and verification that
Operational record (log) entries since the last survey are to they are kept clear
be examined in order to check the past performance of the f) examination of the logbooks for confirmation that the
installation and to establish whether certain parts have emergency and automatic shutdown systems have been
shown any irregularities in operation. tested and confirmation that they are satisfactory
10.3.2 Instrumentation, safety device and others An examination of components is to be carried out with
opening as deemed necessary by the Surveyor to verify their
The survey is to include examination of pressure gauges, condition. Control and safety devices are to be tested.
control valves, liquid level gauges, temperature and vibra- Guides and sheaves are to be examined for wear.
tion indicating equipments, and associated alarms.
Satisfactory operation of the hatch covers is to be checked.
The above mentioned instrumentation is to be tested by
changing pressure, level and temperature as far as practica- Thickness measurements or other non-destructive tests may
ble and comparing with test instruments. Simulated tests be required by the Surveyor, where deemed necessary.
may be accepted for sensors which are not accessible. The
test is to include alarms and safety functions. 10.4.5 Swivel systems
Remote and/or automatic controls, alarms and safety The emergency shut-down system is to be tested according
to standard procedures.
devices are to be tested to demonstrate that they are in satis-
factory condition. A test of quick disconnection (without flow in the pipelines)
is to be carried out.
10.4.2 Cargo tanks requirements originated from
STL-SPM The drain pumps, including emergency pump are to be
operationally tested.
The surveys detailed in [6.7] are to be carried out taking
into account possible sloshing at intermediate filling levels
(i.e. for independent cargo tank, with particular attention to 10.5 Bottom survey
upper and lower parts of the pump tower and its supports).
10.5.1 The bottom survey is to include, as far as practica-
10.4.3 Piping and flexible riser ble:
The survey is to include: a visual examination of the shell plating in the sub-
merged buoy recess
a vacuum testing at vent holes in flexible pipe end fitting
a visual examination and an operational test of the
a pressure test if deemed necessary by the Surveyor lower hatch, including opening, closing and securing.
b) securing, supporting and locking devices are to be 2.3 Fire protection, detection and extinction
examined during a complete opening and closing oper-
ation; the following items are to be checked: 2.3.1 Within the scope of survey of fire protection, detec-
opening/closing system and securing/locking tion and extinction arrangements as required for the annual
devices are interlocked in such a way that they can survey of all ships in Ch 3, Sec 1, [3.4], attention is to be
only operate in proper sequence given to the particular arrangements related to ro-ro cargo
mechanical lock of the securing devices spaces, such as:
the securing devices remain locked in the event of
fire detection systems and alarms
loss of hydraulic fluid, if they are of hydraulic type
c) indicators of open/closed position of doors and of secur- fixed fire-extinguishing arrangements (gas, water-spray-
ing/locking devices at navigation bridge and other ing or foam systems)
remote control stations are to be checked; other safety
portable fire extinguishers in spaces and at entrances
devices such as isolation of securing/locking hydraulic
system from other hydraulic systems, access to operat- ventilation and related safety devices (including remote
ing panels, notice plates and warning indicator lights control on the bridge), and
are to be checked
d) a tightness hose test or equivalent of sealing arrange- electrical equipment of a safe type.
ments is to be carried out
e) a working test of the indicator system is to be carried 3 Ro-ro cargo ships - Class renewal
out, including checking of:
survey
visual indicators and audible alarms on the naviga-
tion bridge and operating panel
lamp test function, fail safe performance, power sup- 3.1 Shell and inner doors
ply for indicator system
proper condition of sensors and their protection 3.1.1 The class renewal survey is to include, in addition to
from water, ice formation and mechanical damage the requirements of the annual survey as required in [2],
confirmation that power supply for indicator system examination, tests and checks of sufficient extent to verify
is supplied by the emergency source or other secure that the bow, inner, side shell and stern doors are in satisfac-
power supply and is independent of the power sup- tory condition and considered able to remain in compli-
ply for operating the doors ance with the applicable requirements, subject to proper
maintenance and operation in accordance with the Opera-
f) a working test of the water leakage detection system for tion and Maintenance Manual (OMM) or the manufacturers
inner doors and for the area between the bow door and
recommendations and the periodical surveys being carried
the inner door (as applicable) is to be carried out and
out at the due dates for the five-year period until the next
the proper function of audible alarms on the navigation
class renewal survey.
bridge and the engine control room panel (as applica-
ble) is to be ascertained
3.1.2 The examinations of the doors are to be supple-
g) the television surveillance system is to be verified with
mented by thickness measurements and testing to verify
proper indication on the navigation bridge and engine
compliance with the applicable requirements so that the
control room monitors
structural and weathertight integrity remains effective. The
h) electrical equipment for opening, closing and securing aim of the examination is to identify corrosion, significant
the doors is to be examined. deformation, fractures, damages or other structural deterio-
ration that may be present.
2.1.9 Non-destructive tests and/or thickness measurements
may be required by the Surveyor after visual examination
and function test or in cases where cracks or deformations 3.1.3 A close visual inspection of structural arrangements is
have been found. to be carried out, supplemented by non-destructive tests
and/or thickness measurements, as deemed necessary by
the Surveyor.
2.2 Internal platforms and ramps
2.2.1 The annual survey of internal movable platforms and 3.1.4 A survey of the items listed in [2.1.4] and [2.1.5],
ramps (excluding those considered as inner doors and cov- including close-up survey of securing, supporting and lock-
ered in [2.1]) and related equipment consists of: ing devices, together with welding, is to be carried out.
a general examination of the installation, particular Non-destructive testing and thickness measurements are to
attention being paid to the condition of steel cables
be carried out on securing, supporting and locking devices,
confirmation of the proper operation of platforms/ramps including welding, to the extent considered necessary by
and of mechanical stops and locks the Surveyor. Whenever a crack is found, an examination
checking, as far as practicable, of the alarms and safety with NDT is to be carried out in the surrounding area and
devices. for similar items, as considered necessary by the Surveyor.
3.1.5 Clearances of hinges, bearings and thrust bearings confirmation of operation of watertight doors in the
are to be taken. Unless otherwise specified in the OMM or event of failure of main and emergency sources of
by the manufacturers recommendation, the measurement power
of clearances on ro-ro cargo ships may be limited to repre- confirmation that notices are affixed at appropriate loca-
sentative bearings where dismantling is needed in order to tions.
measure the clearances.
If dismantling is carried out, a visual examination of hinge 4.2 Openings in shell plating
pins and bearings together with NDT of the hinge pins are
to be carried out. 4.2.1 The survey consists of:
examination of the arrangements for closing sidescuttles
3.1.6 Non-return valves of drainage arrangements are to be and their deadlights, as well as scuppers, sanitary dis-
checked after dismantling. charges and similar openings and other inlets and dis-
charges in the shell plating below the margin line
3.1.7 The maximum thickness diminution of hinging arms,
securing, supporting and locking devices is to be treated confirmation that valves for closing the main and auxil-
according to the normal procedure for primary structures, iary sea inlets and discharges in the machinery spaces
but is not to be more than 15% of the as-built thickness or are readily accessible, and that indicators showing the
the maximum corrosion allowance of the Society, which- status of the valves are provided, as required or fitted
ever is less. Certain designs may be subject to the Societys confirmation that gangway access and cargo ports fitted
special consideration. below the margin line may be effectively closed and
that the inboard ends of any ash or rubbish chutes are
3.1.8 Checking the effectiveness of sealing arrangements fitted with an effective cover.
by hose testing or equivalent is to be carried out.
4.3 Miscellaneous
3.2 Internal platforms and ramps
4.3.1 It is to be verified that the emergency escape routes
3.2.1 The condition of pulleys, axles, cables and structure from passenger and crew spaces, including related stair-
of the platforms and ramps is to be checked. ways and ladders, are kept clear.
4 Passenger ships - Annual survey 5.1.2 The condition of the Low Location Lighting (LLL) sys-
tem, where fitted, and its power source(s) is to be verified.
4.1 Watertight bulkheads
6 Ro-ro passenger ships - Annual and
4.1.1 The survey of watertight bulkheads and arrangements class renewal surveys
consists of:
examination, as far as practicable, of collision and 6.1
watertight bulkheads, and confirmation that their water-
tight integrity has not been impaired 6.1.1 The scope of the annual survey and class renewal
checking the diagram provided on the navigation bridge survey of ro-ro passenger ship is to include the scope of sur-
showing the location of the watertight doors and related veys required for the service notations ro-ro cargo ship and
indicators for their open/closed position passenger ship, as detailed in [2] and [4] for annual survey
and in [3] and [5] for class renewal survey.
testing operation of local and remote control (from the
navigation bridge) of the watertight doors, and in partic- 6.1.2 In addition to [6.1.1], for both annual survey and
ular, operation from each side of the bulkhead of audi- class renewal survey, the condition of means of escape as
ble alarms or visual signals and control handles, as well as of fire protection, detection and extinction in special
required or fitted category spaces is to be checked.
1 General Note 1: This report does not apply to general dry cargo ships of
double side-skin construction, with double side-skin extending
over the entire length of the cargo area, and over the entire height
1.1 Application of the cargo hold to the upper deck.
1.1.1 The requirements of this Section apply to all self-pro- 2 Annual survey
pelled ships which have been assigned the service notation
general cargo ship or bulk carrier (without the ESP
additional service feature) of 500 GT and above carrying 2.1 General
solid cargoes other than dedicated wood chip carriers and
dedicated cement carriers. 2.1.1 Suspect areas identified at previous surveys are to be
examined. Thickness measurements are to be taken of the
The requirements of this Section do not apply to general dry
areas of substantial corrosion and the extent of thickness
cargo ships of double side-skin construction, with double
measurements is to be increased to determine the extent of
side-skin extending over the entire length of the cargo area,
areas of substantial corrosion, as per the requirements of
and over the entire height of the cargo hold to the upper
Tab 6. These extended thickness measurements are to be
deck.
carried out before the annual survey is credited as com-
pleted.
1.1.2 The requirements apply to surveys of hull structure
and piping systems in way of cargo holds, cofferdams, pipe
2.1.2 For survey of air pipes, flame screens on vents and
tunnels, void spaces and fuel oil tanks within the cargo area
ventilators, refer to Ch 3, Sec 1, [2.1.1].
and all ballast tanks. They are additional to the require-
ments applicable to the remainder of the ship, given in Part
A, Chapter 3 according to the relevant surveys. 2.2 Hatch covers and coamings
1.1.3 The requirements contain the minimum extent of 2.2.1 The annual survey of hatch covers is to be carried out
examination, thickness measurements and tank testing. according to the requirements of Ch 3, Sec 1, [2.2].
When substantial corrosion, as defined in Ch 2, Sec 2, In addition to these requirements, a close-up survey of
[2.2.7], and/or structural defects are found, the survey is to hatch cover and hatch coaming plating and its stiffeners is
be extended and is to include additional close-up surveys to be carried out.
when necessary.
Table 3 : Intermediate survey of salt water ballast spaces for general cargo ships
4 Class renewal survey 4.2.4 All piping systems within the above spaces are to be
examined and operationally tested to working pressure to
attending Surveyors satisfaction to ensure that tightness and
4.1 Preparation for survey condition remain satisfactory.
4.1.1 The Owner is to provide the necessary facilities for a 4.2.5 The survey extent of ballast tanks converted to void
safe and practical execution of the surveys, including the spaces is to be specially considered by the Society in rela-
means of providing access to structures for close-up survey, tion to the requirements for ballast tanks.
thickness measurements and tank testing. All other provi-
Note 1: For survey of automatic air pipe heads, refer to Ch 3, Sec 3,
sions described in Ch 2, Sec 2, [2.3], Ch 2, Sec 2, [2.5], Ch
Tab 1.
2, Sec 2, [2.6], Ch 2, Sec 2, [2.7] and Ch 2, Sec 2, [2.9]
regarding procedures for thickness measurements, condi- 4.2.6 As indicated in Ch 3, Sec 3, [2.1.1], a bottom survey
tions for survey, access to structures, equipment for survey in dry condition is to be a part of the class renewal survey.
and survey at sea or at anchorage, respectively, are also to The overall and close-up surveys and thickness measure-
be complied with. ments, as applicable, of the lower portions of the cargo
holds and water ballast tanks are to be carried out in
accordance with the applicable requirements for class
4.2 Scope of survey
renewal surveys, if not already performed.
4.2.1 A survey planning meeting is to be held prior to the Lower portions of the cargo holds and ballast tanks are con-
commencement of the survey. sidered to be the parts below light ballast water line.
4.2.2 In addition to the requirements of annual surveys, the 4.2.7 Where provided, the condition of the corrosion pre-
class renewal survey is to include examination, tests and vention system of ballast tanks is to be examined.
checks of sufficient extent to ensure that the hull and related
For tanks used for water ballast, excluding double bottom
piping, as required in [4.2.4]are in satisfactory condition and
tanks, where a hard protective coating is found in poor con-
fit for the intended purpose for the new period of class to be
dition and it is not renewed, where soft or semi-hard coat-
assigned, subject to proper maintenance and operation and
ing has been applied, or where a hard protective coating
to periodical surveys being carried out at the due dates.
was not applied from time of construction, the tanks in
question are to be examined at annual intervals. Thickness
4.2.3 All cargo holds, water ballast tanks, including double
measurements are to be carried out as found necessary by
bottom tanks, pipe tunnels, cofferdams and void spaces
the Surveyor.
bounding cargo holds, decks and outer hull are to be exam-
ined, and this examination is to be supplemented by thick- When such breakdown of hard protective coating is found
ness measurement and testing as required in [4.5] and [4.6] in water ballast double bottom tanks and it is not renewed,
to ensure that the structural integrity remains effective. The where a soft or semi-hard coating has been applied, or
aim of the examination is to discover substantial corrosion, where a hard protective coating was not applied from the
significant deformation, fractures, damages or other struc- time of construction, the tanks in question may be exam-
tural deformation, that may be present. ined at annual intervals. When considered necessary by the
Surveyor, or where extensive corrosion exists, thickness 4.4 Overall and close-up surveys
measurements are to be carried out.
4.4.1 An overall survey of all cargo holds, tanks and spaces
4.2.8 Where the hard protective coating in spaces is found is to be carried out at each class renewal survey. However,
to be in good condition, the extent of close-up surveys and for fuel oil, lube oil and fresh water tanks, the requirements
thickness measurements may be specially considered. given in Ch 3, Sec 3, Tab 2 are to be complied with.
Table 4 : Requirements for close-up survey at class renewal survey of general cargo ships
Figure 1 : Areas subject to close-up surveys and thickness measurements of general cargo ships
Single deck ship
Figure 2 : Areas subject to close-up surveys and thickness measurements of general cargo ships
Tweendeck ship
Figure 3 : Areas subject to close-up surveys and thickness measurements of general cargo ships
Single deck ship
!
!
"
#
$
%
&
Figure 4 : Areas subject to close-up surveys and thickness measurements of general cargo ships
Tweendeck ship
Table 5 : Requirements for thickness measurements at class renewal surveys of general cargo ships
For areas in spaces where hard protective coatings are 4.5.3 The thickness measurements may be dispensed with
found to be in a good condition, the extent of close-up sur- provided the Surveyor is satisfied, by the close-up examina-
veys according to Tab 4 may be specially considered. tion, that there is no structural diminution and that the hard
Note 1: For survey of automatic air pipe heads, reference is to be protective coating, where applied, remains efficient.
made to Ch 3, Sec 3, Tab 1.
4.5.4 The Surveyor may extend the thickness measure-
4.5 Thickness measurements ments as deemed necessary. When thickness measurements
indicate substantial corrosion, the extent of thickness meas-
4.5.1 The minimum requirements for thickness measure- urements is to be increased to determine the extent of areas
ments at class renewal survey are given in Tab 5. of substantial corrosion in accordance with the require-
ments given in Tab 6.
4.5.2 Representative thickness measurements to determine
both general and local levels of corrosion in the shell
frames and their end attachments in all cargo holds and 4.5.5 For areas in tanks where hard protective coatings are
water ballast tanks are to be carried out. Thickness measure- found to be in a good condition, the extent of thickness
ments are also to be carried out to determine the corrosion measurements according to Tab 5 may be specially consid-
levels on the transverse bulkhead plating. ered.
Table 6 : Requirements for extent of thickness measurements at those areas of substantial corrosion
Class renewal survey of general cargo ships
4.6 Tank testing 4.6.3 Tank testing of fuel oil tanks is to be carried out with
a head of liquid to the highest point that liquid will rise
4.6.1 All boundaries of water ballast tanks and deep tanks under service conditions. Tank testing of fuel oil tanks may
used for water ballast within the cargo length area are to be be specially considered based on a satisfactory external
pressure tested. For fuel oil tanks, the representative tanks
examination of the tank boundaries, and a confirmation
are to be pressure tested.
from the Master stating that the pressure testing has been
4.6.2 The Surveyor may extend the tank testing as deemed carried out according to the requirements with satisfactory
necessary. results.
1 General 2.2.2 For ships assigned with the service notation container
ship, examination of the torsion box girder or equivalent
structure at the top sides is carried out. Thickness measure-
1.1
ments additional to those related to the transverse sections
1.1.1 The requirements of this Section are applicable to may be required.
ships to be assigned one of the following service notations,
and given in the Articles specified below: 3 Livestock carrier
container ship, or ship equipped for the carriage of
containers, in Article [2] 3.1 Annual survey
livestock carrier, in Article [3]
FLS tanker, in Article [4] 3.1.1 The survey is to include a general examination of:
dredging units, i.e. ships with the service notations spaces for the livestock and related hatch covers (to be
dredger, hopper dredger, hopper unit, split hopper surveyed according to Ch 3, Sec 1, [2])
unit, split hopper dredger, in Article [5] ventilation means, including prime movers
tug, salvage tug, escort tug, in Article [6] main, emergency and portable lighting systems in live-
supply vessel, in Article [7] stock spaces, passageways and access routes
fire-fighting ship, in Article [8] the drainage system
oil recovery ship, in Article [9] fodder and fresh water systems
anchor handling vessel, in Article [10] fire-fighting appliances, with working test as far as nec-
cable laying ship, in Article [11] essary and practicable (according to Ch 3, Sec 1, [3.4])
lifting, in Article [12] means of escape, with confirmation they are kept clear.
diving support, i.e. diving support-integrated or diving
support-portable, in Article [13] 3.2 Class renewal survey
fishing vessel, in Article [14]
special service - standby rescue vessel, in Article [15] 3.2.1 The equipment related to ventilation, lighting and the
related power supply is to be submitted to a survey to the
yacht and charter yacht, in Article [16].
same extent as required for similar equipment at the class
renewal survey as indicated in Ch 3, Sec 3.
1.1.2 These requirements are additional to those given in
Part A, Chapter 3, according to the relevant surveys. 3.2.2 The drainage, fodder and fresh water systems, includ-
ing piping and pumps, are to be surveyed to the same extent
2 Container ship or ship equipped for as required for similar equipment at the class renewal sur-
vey as indicated in Ch 3, Sec 3.
the carriage of containers
The fresh water tanks are to be internally examined in
accordance with the periodicity given in Ch 3, Sec 3, Tab 2.
2.1 Annual survey
3.2.3 The fire-fighting systems are to be thoroughly exam-
2.1.1 The survey is to include: ined and tested.
confirmation of the availability of instructions and instru-
ments for stowage of containers, as required or fitted
4 FLS tanker
examination of container supports welded to the ships
structure or on to the hatch covers
4.1 Annual survey - Hull items
examination of cell guides, if fitted.
4.1.1 Weather decks
2.2 Class renewal survey The survey is to include:
2.2.1 The renewal is to include: examination of cargo tank openings, including gaskets,
examination of container supports welded to the ships covers, coamings and screens
structure or on to the hatch covers, checking for possi- examination of cargo tank pressure/vacuum valves and
ble cracks and deformations flame screens
examination of cell guides and associated elements, examination of flame screens on vents to all bunker, oily
checking for possible cracks, deformations or corrosion. ballast and oily slop tanks
examination of cargo, bunker, ballast and vent piping confirmation that any special arrangement made for
systems, including remote control valves, safety valves bow or stern loading/unloading is in satisfactory condi-
and various safety devices, as well as vent masts and tion.
headers
confirmation that wheelhouse doors and windows, side- 4.2.2 Instrumentation and safety devices
scuttles and windows in superstructure and deckhouse The survey is to include the following items, as far as
ends facing the cargo area are in satisfactory condition required or fitted:
confirmation that pumps, valves and pipelines are iden- examination of cargo tank gauging devices, high level
tified and distinctively marked. alarms and valves associated with overflow control
4.1.2 Cargo pump rooms and pipe tunnels confirmation that installed pressure gauges on cargo dis-
charge lines are properly operational
The survey is to include:
confirmation that the required gas detection instruments
examination of all pump room bulkheads and pipe tun-
are on board and satisfactory arrangements have been
nels (if any) for signs of chemical cargo leakage or frac-
made for the supply of any required vapour detection
tures and, in particular, the sealing arrangements of
tubes
penetrations in pump room bulkheads
examination of the condition of all piping systems, in confirmation that devices provided for measuring the
cargo pump rooms and pipe tunnels (if any) temperature of the cargo, if any, operate satisfactorily.
examination of the bilge and ballast arrangements and 4.2.3 Fire-fighting systems
confirmation that pumps and pipelines are identified.
The survey is to include:
4.2 Annual survey - Cargo machinery items external examination of piping and cut-out valves of
fixed fire-fighting systems related to cargo tanks and
4.2.1 Cargo area and cargo pump rooms cargo pump rooms
The Owner or his representative is to declare to the attend- confirmation, as far as practicable and when appropri-
ing Surveyor that no modifications or alterations which ate, that the remote means for closing the various open-
might impair safety have been made to the various installa- ings are operable
tions in dangerous zones without prior approval from the
Society. examination of the appropriate portable fire-extinguish-
ing equipment for the chemical cargoes to be carried in
The survey is to include: accordance with the relevant requirements given in Ch
3, Sec 1, [3.4.3]
confirmation that potential sources of ignition in or near
the cargo pump rooms, such as loose gear, excessive examination of fire-fighting systems of any type fitted on
product in bilge, excessive vapours, combustible mate- board such as deck foam, water-spraying, etc. as appli-
rials, are eliminated and that access ladders are in satis- cable in accordance with the relevant requirements
factory condition given in Ch 3, Sec 1, [3.4.2].
examination, as far as practicable, of cargo, bilge, bal-
last and stripping pumps for excessive gland seal leak- 4.2.4 Inert gas system
age, verification of proper operation of electrical and If an inert gas system such as that installed on board oil
mechanical remote operating and shutdown devices tankers is fitted, the requirements given in Ch 4, Sec 3, [3.4]
and operation of pump room bilge system, and check- are to be complied with.
ing that pump foundations are intact
confirmation that the ventilation system, including port-
4.3 Intermediate survey - Hull items
able equipment, if any, of all spaces in the cargo area
(including cargo pump room) is operational, ducting is
intact, dampers are operational and screens are clean 4.3.1 The survey is to include:
confirmation that electrical equipment in dangerous examination, as far as applicable, of cargo, stripping,
zones, cargo pump rooms and other spaces is in satis- cargo washing, bunker, ballast, steam and vent piping
factory condition and has been properly maintained systems as well as vent masts and headers. If upon
examination there is any doubt as to the condition of
confirmation that the remote operation of the cargo the piping, pressure testing, thickness measurement or
pump room bilge system is satisfactory both may be required
examination of the cargo heating system
confirmation, if applicable, that cargo pipes are electri-
examination of the cargo-transfer arrangement and con- cally bonded to the hull
firmation that the ship's cargo hoses are suitable for
their intended purpose and in satisfactory condition examination of vent line drainage arrangements.
for dredger, hopper dredger, split hopper dredger: 6.2.2 In addition to [6.2.1], for salvage tug, the survey is to
- visual examination, as far as practicable, of attach- include:
ments of suction piping and lifting systems to the a check and working test of specific equipment as
structure and external examination of piping in required in Pt D, Ch 14, Sec 2, [3]
dredging machinery spaces for absence of corrosion
checking by a specialist of the satisfactory condition of
and leakage
the towing line(s). A report is to be presented to the Sur-
- checking the condition of the dredging machinery veyor by the Owner and kept on board.
space and related equipment with regard to electri-
cal shocks, protection from rotating machinery, fire 6.2.3 For tug-barge combined, a visual examination of
and explosion hazards. components of the connection system is to be carried out,
completed by thickness measurements and non-destructive
5.2 Class renewal survey tests as deemed necessary by the Surveyor. A connec-
tion/disconnection test is to be carried out, including a
5.2.1 The survey is to include the following items, as far as check of related remote control, safety and alarm devices.
required or fitted, according to the service notation of the
ship:
for hopper dredger, hopper unit, visual examination of 7 Supply vessel-oil product or supply
hopper bottom doors or valves and accessories, such as vessel-chemical product
hinges, actuating rods, hydraulic systems, with disman-
tling as deemed necessary by the Surveyor 7.1 General
for split hopper unit, split hopper dredger, visual exam-
ination, as far as practicable, of superstructure hinges 7.1.1 The additional survey items for annual survey, inter-
and blocks, deck hinges, hydraulic jacks and associated mediate survey and class renewal survey are applicable
piping systems and alarms, with dismantling and/or fur- only to ships having the service notation supply vessel
ther checks as deemed necessary by the Surveyor assigned the additional service features oil product, LHNS
for dredger, hopper dredger, split hopper dredger: or WS.
- visual examination, as far as practicable, of attach-
ments of suction piping and lifting systems to the
7.2 Annual survey - Hull items
structure and external examination of piping in
dredging machinery spaces for absence of corrosion
7.2.1 Weather decks
and leakage
The survey is to include:
- checking the condition of the dredging machinery
space and related equipment with regard to electri- examination of cargo tank openings, including gaskets,
cal shocks, protection from rotating machinery, fire covers, coamings and screens
and explosion hazards. examination of cargo tank pressure/vacuum valves and
flame screens
6 Tug, salvage tug, escort tug examination of flame screens on vents to all bunker, oily
ballast and oily slop tanks
6.1 Annual survey
examination of cargo, bunker, ballast and vent piping
6.1.1 The survey is to include a general external examina- systems, including remote control valves, safety valves
tion of the towing hook or towing winch, as fitted, and and various safety devices, as well as vent masts and
unhooking device, as far as practicable. headers
confirmation that wheelhouse doors and windows, side-
6.1.2 In addition to [6.1.1], for salvage tug, the availability scuttles and windows in superstructure and deckhouse
and satisfactory condition of specific equipment as required ends facing the cargo area are in satisfactory condition
in Pt D, Ch 14, Sec 2, [3] is to be verified.
confirmation that pumps, valves and pipelines are iden-
6.1.3 For tug-barge combined, an examination of the tified and distinctively marked.
accessible parts of the connection system is to be carried
out. 7.2.2 Cargo pump rooms and pipe tunnels
The survey is to include:
6.2 Class renewal survey examination of all pump room bulkheads and pipe tun-
6.2.1 The survey is to include: nels (if any) for signs of oil or chemical product leakage
or fractures and, in particular, the sealing arrangements
checking the condition of the connection of the towing
of penetrations in pump room bulkheads
hook or towing winch to the structure, including related
reinforcements of the structure examination of the condition of all piping systems, in
checking the external condition of the towing hook or cargo pump rooms and pipe tunnels (if any)
towing winch; when applicable, a no-load test of the examination of the bilge and ballast arrangements and
unhooking device is to be carried out. confirmation that pumps and pipelines are identified.
7.3 Annual survey - Cargo machinery items examination of the appropriate portable fire-extinguish-
ing equipment for the cargoes to be carried in accord-
7.3.1 Cargo area and cargo pump rooms ance with the relevant requirements given in Ch 3, Sec
The Owner or his representative is to declare to the attend- 1, [3.4.3]
ing Surveyor that no modifications or alterations which examination of fire-fighting systems of any type fitted on
might impair safety have been made to the various installa- board such as deck foam, water-spraying etc. as applica-
tions in dangerous zones without prior approval from the ble in accordance with the relevant requirements given
Society. in Ch 3, Sec 1, [3.4.2].
The survey is to include:
confirmation that potential sources of ignition in or near 7.4 Intermediate survey - Hull items
the cargo pump rooms, such as loose gear, excessive
product in bilge, excessive vapours, combustible mate- 7.4.1 The survey is to include:
rials, etc., are eliminated and that access ladders are in
satisfactory condition examination, as far as applicable, of cargo, stripping,
bunker, ballast, steam and vent piping systems as well
examination, as far as practicable, of cargo, bilge, bal- as vent masts and headers. If upon examination there is
last and stripping pumps for excessive gland seal leak- any doubt as to the condition of the piping, pressure
age, verification of proper operation of electrical and testing, thickness measurement or both may be required
mechanical remote operating and shutdown devices
and operation of pump room bilge system, and check- confirmation that the pipelines are electrically bonded
ing that pump foundations are intact to the hull
confirmation that the ventilation system, including port- examination of vent line drainage arrangements.
able equipment, if any, of all spaces in the cargo area
(including cargo pump rooms) is operational, ducting is
intact, dampers are operational and screens are clean 7.5 Intermediate survey - Cargo machinery
items
confirmation that electrical equipment in dangerous
zones, cargo pump rooms and other spaces is in satis-
factory condition and has been properly maintained 7.5.1 Electrical equipment in dangerous zones
confirmation that the remote operation of the cargo A general examination of the electrical equipment and
pump room bilge system, if fitted, is satisfactory cables in dangerous zones such as cargo pump rooms and
areas adjacent to cargo tanks is to be carried out for defec-
examination of the cargo heating system tive and non-certified safe type electrical equipment, non-
examination of the cargo-transfer arrangement and con- approved lighting and fixtures, and improperly installed or
firmation that the ship's cargo hoses are suitable for defective or dead-end wiring.
their intended purpose and in satisfactory condition.
The electrical insulation resistance of the electrical equip-
7.3.2 Instrumentation and safety devices ment and circuits terminating in or passing through the dan-
gerous zones is to be tested; however, in cases where a
The survey is to include the following items, as far as proper record of testing is maintained, consideration may
required or fitted: be given to accepting recent test readings effected by the
examination of cargo tank gauging devices, high level ships personnel.
alarms and valves associated with overflow control
confirmation that installed pressure gauges on cargo dis- 7.5.2 Cargo heating system
charge lines are properly operational The satisfactory condition of the cargo heating system is to
confirmation that the required gas detection instruments be verified.
are on board and satisfactory arrangements have been
made for the supply of any required vapour detection 7.6 Class renewal survey - Hull items
tubes
confirmation that devices provided for measuring the 7.6.1 Piping
temperature of the cargo, if any, operate satisfactorily.
Piping for cargo, ballast, stripping and venting systems is to
7.3.3 Fire-fighting systems be examined to the Surveyor's satisfaction. Dismantling
and/or thickness measurements of these items may be
The survey is to include:
required. A hydraulic test is to be carried out in the event of
external examination of piping and cut-out valves of repair or dismantling of cargo or ballast piping, or where
fixed fire-fighting systems related to cargo tanks and doubts arise.
cargo pump rooms
Vent line drainage arrangements are to be examined.
confirmation, as far as practicable and when appropri-
ate, that the remote means for closing the various open- It is to be verified that cargo piping is electrically bonded to
ings are operable the hull.
visual examination of winch, including drum, end general examination of sheaves, drums and tensioners
flanges, reduction gears and brakes for damage, cracks or wastage; the connections of these
appliances to the structure are also to be checked
visual examination of wire stopper (i.e. shark jaw, karm general examination of fire fighting equipment, if fitted,
fork), stern roller, guide pins in way of cable storage spaces and working areas.
visual examination of the wire length (wire rope or
chain cable) 11.2 Class renewal survey
visual examination of equipment foundations, including
11.2.1 The equipment mentioned in [11.1.1] is to be dis-
related reinforcements of the structure
mantled, to the extent deemed necessary by the Surveyor, in
general examination of hydraulic and electric systems order to check its condition. Clearances of sheaves and
cable drum axles are to be ascertained.
winch functional test with no load in order to detect
vibration, leaks, shocks or sticking points and to check
11.2.2 Fire-fighting equipment is to be submitted to a sur-
emergency stop and alarms
vey to the same extent as required for similar equipment at
braking system functional test with no load the class renewal survey for all ships (see Ch 3, Sec 3).
general examination and test, as far as practicable, of
emergency quick-release system 12 Lifting
verification of manual or planning for anchor handling
operation 12.1 General
the review of the Owners service record books is to be
12.1.1 The requirements of this Article are additional to
carried out. The purpose is to verify that:
those laid down in NR526 Rules for the Certification of Lift-
- periodical testing of the equipment has been carried ing Appliances onboard Ships and Offshore Units or NR595
out in accordance with relevant standards, when Classification of Offshore Handling Systems, whichever is
applicable applicable.
- eventual repair, maintenance or replacement of
equipment or components are done in accordance 12.2 Annual survey
with applicable standards
12.2.1 The survey is to include verification and testing of
- on-board record showing the testing of the emer- the lifting equipment, as follows:
gency quick-release system was checked.
verification of the presence onboard of the following
documents:
10.2 Class renewal survey
- technical manual
10.2.1 In addition to the requirements of annual survey, the - planned maintenance system
class renewal survey is to include, as a minimum: general examination of the electrical cabling
verification of the equipment condition with disassem- functional testing of the main and alternative two-way
bly, as deemed necessary communication system at the lifting operating position
control of the safety devices with disassembly, as verification of the structural arrangement and founda-
deemed necessary tions of the lifting equipment
examination of the wire length (wire rope or chain testing of hydraulic installations
cable) and gauging load tests in accordance with the rules or requirements
winch static load test, as deemed necessary referred to in the lifting equipment certificate.
13 Diving support-integrated and diving k) Confirmation that the fire fighters' outfits including their
self-contained compressed air breathing apparatus, and
support-portable
two-way portable communication apparatus, and emer-
gency breathing masks are complete and in good condi-
13.1 Annual survey tion and that the cylinders, including the spare
cylinders, of any required self-contained breathing
13.1.1 The survey of the spaces containing the diving sys- apparatus are suitably charged
tem, is to include:
l) Confirmation that doors located in bulkheads forming
a) For non-permanent diving systems, verification that the boundaries with adjacent spaces are in a satisfactory
service notation diving support-capable or diving sup- condition
port-portable is specified on the Certificate of Classifi-
cation, in accordance with the configuration of the m) General examination of the visible parts of items form-
system ing the structural fire protection, such as bulkheads,
decks, doors and trunks, due attention being given to
b) Verification of the presence on-board of the following their integrity and to integrity of the insulating material.
system documentation:
diving equipment technical manual 13.2 Class renewal survey
planned maintenance system
13.2.1 In addition to the requirements of annual survey, the
type approval certificates for the oxygen-measuring
class renewal survey of the spaces containing the diving
equipment
system is to include:
c) Verification of the structural arrangement and scantling
of the foundations of pressure vessels and bell handling a) testing of the breathing gas installations, i.e. testing of
system the gas-tightness of all sealing devices of the enclosed
spaces for breathing gas storage
d) Verification of the fastening arrangement of the diving
equipment b) functional testing of self closing systems of door located
in bulkheads forming boundaries with adjacent spaces
e) Functional testing of the main source of electrical
power, emergency source of electrical power and c) verification of accuracy of oxygen-measuring equip-
switching from one to the other. Verification of the satis- ment by means of calibration gas, as far as practicable
factory operation of the alarms and indications
d) verification of the sea inlet protective structure, as rele-
f) General examination of the electrical cabling vant.
g) Functional testing of the main and alternative two-way
communication system at the dive location i.e. between
divers, chambers, control rooms, launch point and other
14 Fishing vessel
important locations
i) General examination of the automatic fire detection and 14.2.1 For fishing vessels 10 years age and over, the class
alarm system renewal survey is to include thickness measurements of
structural elements prone to rapid wastage, such as the stern
j) Verification of the suitable fixed fire-extinguishing sys- ramp, weather deck in way of the working area of the nets,
tem intended for interior spaces containing diving connections to hull structure of masts, gantries, winches
equipment and trawl gallows (for side trawlers).
15.2.1 A general external examination of the towing hook hull side openings with their securing appliances
or towing winch, as fitted, and unhooking device, as far as
freeing port shutters provided in bulwarks
practicable, is to be carried out.
anchors, chain cables and windlasses
15.3 Class renewal survey - Rescue
fastenings, including those through the ballast keel, as
arrangement, survivors accommodation
far as possible
and safety equipment
structural reinforcements in way of masts and chain
15.3.1 A general examination of rescue equipment and plates
facilities, survivors spaces, safety equipment, personal care
and medical provisions, in accordance with the require- hull condition in way of openings.
ments given in NR482, Section 4, is to be carried out.
Testing of rescue and safety equipment, as applicable, is to Testing of the above is to be carried out as appropriate.
be carried out.
The steering gear arrangement is to be examined and tested
including its associated equipment and control systems.
15.4 Class renewal survey - Towing
arrangements
15.4.1 The survey is to include: 16.2 Intermediate survey - Machinery and
checking the condition of the connection of the towing systems
hook or towing winch to the structure, including related
reinforcements of the structure 16.2.1 Ships assigned with the service notation yacht and
checking the external condition of the towing hook or having a length less than 24 m are submitted to a survey
towing winch; when applicable, a no-load test of the which scope is as indicated in Ch 3, Sec 1, [3].
unhooking device is to be carried out.
2.3.1 When calculating the transverse section modulus of 3.2.6 The thickness of each component should be deter-
the ship's hull girder, the requirements under Pt B, Ch 6, Sec mined by averaging all of the measurements in way of the
1, [2] should be applied. transverse section on each component.
3.3 Additional measurements ble diminution associated with each particular member).
Where differences in thickness at the butt joint exceed 15%
3.3.1 Where one or more of the transverse sections are of the lower thickness, a transition taper should be pro-
found to be deficient in respect of the longitudinal strength vided.
requirements given in this Appendix, the number of trans-
verse sections for thickness measurements should be 3.4.3 Alternative repair methods involving the fitting of
increased such that each tank within the 0,5L amidships straps or structural member modification should be subject
region has been sampled. Tank spaces that are partially to special consideration. In considering the fitting of straps,
within, but extend beyond, the 0,5 L region should be sam- it should be limited to the following conditions:
pled. to restore and/or increase longitudinal strength;
the thickness diminution of the deck or bottom plating
3.3.2 Additional thickness measurements should also be
to be reinforced should not be within the substantial
performed on one transverse section forward and one aft of
corrosion range (75% of the allowable diminution asso-
each repaired area to the extent necessary to ensure that the
ciated with the deck plating)
areas bordering the repaired section also comply with the
requirements of this Appendix. the alignment and arrangement, including the termina-
tion of the straps, is in accordance with a standard rec-
ognized by the Society
3.4 Repair methods
the straps are continuous over the entire 0,5 L amidships
3.4.1 The extent of renewal or reinforcement carried out to length; and
comply with this Appendix should be in accordance with continuous fillet welding and full penetration welds are
[3.4.2]. used at butt welding and, depending on the width of the
strap, slot welds. The welding procedures applied must
3.4.2 The minimum continuous length of a renewed or be acceptable to the Society.
reinforced structural member should be not less than twice
the spacing of the primary members in way. In addition, the 3.4.4 The existing structure adjacent to replacement areas
thickness diminution in way of the butt joint of each joining and in conjunction with the fitted straps should be capable
member forward and aft of the replaced member (plates, of withstanding the applied loads, taking into account the
stiffeners, girder webs and flanges, etc.) should not be buckling resistance and the condition of welds between the
within the substantial corrosion range (75% of the allowa- longitudinal members and hull envelope plating.
Chapter 5
SECTION 1 GENERAL
SECTION 1 GENERAL
Table 1 : Additional class notations for which specific survey requirements are applicable
Figure 1 : Actions to be taken in connection with the class renewal survey (VeriSTAR-HULL SIS)
(
(
!
"
#
$%& ''# $'
!
(
(
"
#
(
(
)
)
*
!$+' $%+'# $'"
3.2 Class renewal survey is either the immediate repair or the imposition of a rec-
ommendation for the STAR-HULL notation (without rec-
3.2.1 In addition to the scope of the class renewal survey as ommendation for class).
required for the ship concerned (see Fig 2), the following is The Inspection and Maintenance Plan is not complied
to be carried out: with (e.g. delays in performing the operations pro-
the assessment of the condition of coating and anodes grammed according to the plan or the scope of inspec-
additional thickness measurements and surveys may be tion and/or maintenance not completely fulfilled).
required by the Society The action to be taken is:
a specific survey for fatigue fracture detection as a result - either the immediate compliance with the require-
of the previous hot spot map. ments or the imposition of a recommendation if the
non-conformity is of a minor nature or is an excep-
3.2.2 On the basis of the results of the assessment, surveys,
tional occurrence
thickness measurements and fatigue fracture detection car-
ried out as indicated in [3.2.1], the as-inspected state of - or the suspension of the STAR-HULL notation if the
the ship is established. A structural reassessment of the as- non-conformity is of a major nature or a recurrence.
inspected state is performed according to the criteria in Ch A defect or a deficiency is found in applying the IMP.
2, App 3 or Pt E, Ch 1, App 2 for items as deemed appropri- The actions to be taken are the same as stated both for
ate by the Society. This state may be progressively updated repair of structure/coating/equipment (first two cases
based on the results of additional surveys and/or thickness above) and for the application of the IMP (third case
measurements required on the basis of the first run of the above).
analysis.
An unexpected defect or deficiency is found or an acci-
The Owner then defines a program of: dent occurs, i.e. not as a result of lack of maintenance
structural renewals and repairs or failure in the application of the IMP. The actions to be
renewals and repair of coating and anodes, taken are the same as stated for repair of structure/coat-
ing/equipment (first two cases above).
using the indications of the final as-inspected state.
In order to ensure that the ship continues to comply with 3.3.3 The withdrawal of the STAR-HULL notation may be
the acceptance criteria given in Pt E, Ch 1, Sec 2, [4]. In decided in different cases, such as:
addition, the IMP may be modified if needed. recurrent suspension of the STAR-HULL notation
suspension of the STAR-HULL notation for more than a
3.2.3 Once repairs and renewals are completed to the
given period (i.e. 3 months)
Society satisfaction, a new as-repaired state of the ship is
obtained, including an updated hot spot map expiry or withdrawal of class.
Figure 2 : Actions to be taken in connection with the class renewal survey (STAR-HULL)
(
(
$
!
"
#
$%& ''# $'
!
(
(
"
#
(
(
)
)
*
!$+' $%+'# $'"
*
% !
"
1.1 2.1
1.1.1 The requirements of this Section apply to ships which 2.1.1 At each annual survey the Owner or his representa-
have been assigned one of the following additional class tive is to declare to the attending Surveyor that no modifica-
notations related to availability of machinery, as described tions have been made to the systems affecting the notations
in Ch 1, Sec 2, [6.3]: without prior approval by the Society.
AVM-APS
AVM-DPS 3 Class renewal survey
AVM-IPS
AVM-FIRE 3.1
3.1.1 At each class renewal survey a test is to be conducted
in order to ascertain that the systems affecting the notations
operate satisfactorily. This test is usually to be carried out
during sea trials.
test of the steering gear to confirm the proper opera- the internal communication between the different
tion of the various remote controls from the wheel- workstations, checking at random the availability of
house data
test, as far as practicable, of the propulsion control, the external communication with the shore; consid-
including propeller pitch control, where fitted eration may be given to recent records of such exter-
check of the relevant indicators such as rudder nal communication from ship to shore and from
angle, ahead/astern position, propeller rpm or pitch shore to ship.
2.4.1 The annual survey is to include a check of the condi- 3.1 All notations
tion of the different workstations that belong to the IBS sys-
3.1.1 The requirements given in [2] for annual survey are to
tem, and a test, as far as practicable, of:
be complied with. An additional program of examinations,
the main functions of the IBS; in this respect, the exami- checks and tests is to be devised in agreement with the
nations and tests given in [2.2.1] are to be carried out, Owner and based on the operational data and experience of
previous surveys. This program is to include verification of the
where applicable
calibration of instruments and testing of control and safety
the transitional and emergency sources required for the functions of the installation. An additional program of random
system and recovery of systems after restoring power tests of the systems is to be performed during sea trials.
The Owner is to confirm that any modification to the hard-
the alarm and monitoring system in the wheelhouse, at ware and software is fully documented and properly
random. recorded.
2.1.2 Audit The following records for the preceding 12 months are to be
An on-board audit of the procedures, as required in Part E, reviewed as necessary:
Chapter 9, is done by the Surveyor in order to ascertain that oil record book (for CLEANSHIP, CLEANSHIP SUPER
the Master and crew are familiar with the ship's on-board and OWS-x ppm)
procedures for preventing pollution and in order to check
that the discharge records mentioned in Part E, Chapter 9 garbage record book (for CLEANSHIP, CLEANSHIP
are properly completed. SUPER and OWS-x ppm)
records of ballast exchanges after international voyages
2.2 Annual survey (for BWE and BWT)
ballast water record book (for BWE and BWT)
2.2.1 General
sewage and grey water discharge book (for CLEANSHIP,
The survey is to include, as far as practicable: CLEANSHIP SUPER, GWT and AWT)
confirmation of the installation being in accordance emissions record (for CLEANSHIP SUPER, NOX-x% and
with the plans. If modifications have been made, check- SOX-x%)
ing that these modifications are in accordance with results of the tests on effluents done by the Shipowner
approved documentation (for all additional class nota- according to Pt E, Ch 9, Sec 4, [2.3.1] for any pollution
tions related to pollution prevention systems) prevention system of [1.1.1] (for AWT).
2.3 Class renewal survey 3.1.2 NOx emission (CLEANSHIP SUPER, NOX-x%)
The procedures for demonstrating compliance with
2.3.1 The requirements given in [2.2] for annual surveys NOx emission limits on board are given in the NOx
are to be complied with. In addition, for all additional class Technical Code.
notations related to pollution prevention systems, the fol- During the annual survey, it is to be confirmed that the
lowing is to be carried out: NOx emission control procedure is available on-board
demonstration, under working conditions, of the correct NOx emission records.
functions of the most important components of the sew-
age treatment plant or AWT plant if fitted, the garbage 3.1.3 SOx emission (CLEANSHIP, CLEANSHIP
treatment plant, the oil filtering equipment, the incinera- SUPER, SOX-x%)
tors if fitted, the comminuters and grinders, the hazard- Procedures are to be established to detail the maximum sul-
ous waste recovery unit if fitted phur content in the fuel oil purchase orders, and to check
the actual content of sulphur at the delivery of bunker.
ascertainment of the correct function of the alarms.
In the case the actual sulphur content is checked by sam-
pling testing and analysis, procedures are to be carried out
3 Prevention of air pollution in accordance with a recognised standard acceptable to the
Society.
3.1 Annual survey The fuel management procedures are to be established and
followed as part of the certified ship management system of
3.1.1 Ozone depleting substances (CLEANSHIP, the ship.
CLEANSHIP SUPER)
Records on purchase orders and on type of checking carried
a) A procedure for annual verification of the system and out, including results, are to be kept on-board.
equipment condition by an authorised organisation is to The survey is to include the following items:
be settled. The interval of this verification may be
extended in case of predictive maintenance scheme verification that the above procedures for defining,
approved by the Society. ordering and checking fuel oils for control of SOx emis-
sion are available on-board
b) A procedure for weekly verification and maintenance is
confirmation that fuel oil sulphur content records are
to be settled enabling to:
available on-board
check the tightness of the circuits by satisfactory emission record (when exhaust gas cleaning is provided
means (such as weighing or vessel pressure monitor- (EGC)).
ing)
identify the location of possible leakage 3.1.4 Shipboard incineration (CLEANSHIP,
CLEANSHIP SUPER)
carry out necessary corrective actions.
Record books tracing all the operations carried out on The annual survey is to include the following items, when
board the ship according to the procedures mentioned fitted:
in the NOx Technical Code are to be kept on-board and external examination of the incinerators and confirma-
updated after each intervention. They are to include in tion that such equipment operates satisfactorily
particular the following records: test of the alarms, exhaust monitoring devices and
presence of leak and corrective action emergency stop located outside the compartment.
volume of substance recovered and indication of the 3.1.5 Exhaust Gas Cleaning System-Scrubber
storage location (EGCS-SCRUBBER)
volume of substance recharged The annual survey is to include the following items, when
fitted:
volume of substance consumed
examination of the logbooks with regard to correct
volume of substance disposed. functioning of the Exhaust Gas Cleaning Systems, emis-
The survey is to include the following items: sions monitoring and washwater monitoring systems
verification that the above procedures for annual confirmation that the approved Operating and Mainte-
and weekly checking of systems with ozone deplet- nance Instruction Manual is onboard
ing substances are available on-board confirmation that the Instrumentation, Control, Monitor-
confirmation that appropriate entries are being ing, and Safety equipment of each system unit are oper-
made in the record book for ozone depleting sub- ating satisfactorily
stances examination of emergency shutdown or bypass valves,
remote operating valves, and machinery and equipment
test of the proper operation of the leak detectors and
associated with processing or distribution of exhaust
related audible and visual alarms
gases and, as far as practicable, testing of the emergency
c) Review of ozone - depleting substance record book. shutdown of the system
examination and functional test of all tanks, piping, - visual inspection of all bypass, mixing, isolating,
hoses, pumps, strainers, separators, filtration units, dos- shut-down or control valves in the exhaust, water
ing systems, and equipment associated with processing treatment and dosing systems
of washwater, injection of reductant or collection of
- visual examination and test of all mechanical,
exhaust residues
hydraulic and pneumatic control actuators and their
examination of drip trays, overflow arrangements, power systems, as deemed necessary by the Sur-
shielding or insulation installed for the protection of veyor
personnel or of the ship
examination of electrical equipment associated with the - dock trials on control systems, in order to verify cor-
operation or monitoring of Exhaust Gas Cleaning Sys- rect operation of the automatic functions, monitor-
tems ing and alarms systems, safety systems, including
override of system functions if provided, manual
confirmation that Personal Protective Equipment (PPE)
control and automatic changeover of designated
and facilities are available onboard and maintained in
machinery associated with the Exhaust Gas Clean-
good conditions
ing Systems
external examination of all components including
scrubber units, of insulation, etc., including foundations external examination and operating tests of the equip-
and attachments ment and systems, as required in Pt E, Ch 9, Sec 2 and
confirmation of correct operation of all rotating and Pt E, Ch 9, Sec 3 (for all additional class notations
reciprocating components, such as exhaust gas fans, related to pollution prevention systems).
water treatment pumps, dry handling conveyors, venti-
lation fans
verification of the correct operation of all remotely oper- 4 Ship Energy Efficiency Management
ated or automatically controlled valves in the exhaust, Plan (SEEMP)
water treatment or dry handling systems
examination of the Exhaust Gas Cleaning System during 4.1 Intermediate and class renewal surveys
working condition. Multi-mode SOx scrubbers are to be
tested in all operational modes, as far as practicable.
4.1.1 Onboard verification
3.2 Class renewal survey The onboard survey is to include the following items:
3.2.1 The requirements given in [3.1] for annual surveys a) verification that the implementation of the energy meas-
are to be complied with. In addition, the following is to be ures is properly recorded
carried out: b) verification by sampling technique that the procedures
for CLEANSHIP SUPER, NOX-x% and SOX-x%, confir- to measure the data are properly implemented and that
mation of the operation and calibration of the emissions the measuring devices are properly maintained and/or
analysers, if fitted calibrated
for the Exhaust Gas Cleaning System (EGCS-SCRUB-
c) verification that EEOI and other EnPIs defined in the
BER), the associated systems and monitoring equip-
planning phase, if any, are properly calculated from the
ment, the following is also to be carried out:
collected data over the last 6 months of the ships opera-
- visual inspection of all washwater, water treatment tions, and recorded
pumps and reductant dosing pumps, including
openings, for examination, as deemed necessary by d) verification that the SEEMP is onboard and that the
the Surveyor record books are kept up to date.
2.5.2 The installation is to be visually examined and tested 3.2.3 Condensers and coolers are to be opened up for
to verify that the controlled atmosphere system remains sat- examination of tube plates, tubes and end covers.
isfactory. The survey is to include the following items: Condensers are to be pressure tested to 1,2 times the rated
examination of voyage logs, records of controlled atmos- working pressure.
phere zone air-tightness and calibration of instruments
3.2.4 Insulation of insulated parts (such as piping and pres-
confirmation that an operating and safety manual is
sure vessels) may need to be removed at random, to ascer-
available on board, complete and duly endorsed by the
tain the condition of such parts and of the insulation itself.
officers responsible
examination of controlled atmosphere zone sealing 3.2.5 The electrical installation of the plant is to be exam-
arrangements including cleats and hinges, pressure/vac- ined and insulation tests checked.
uum valves, door locks, ventilation of adjacent spaces,
warning notices 3.2.6 If independent from the electrical installation of the
test to design pressure of controlled atmosphere zones ship, the generators supplying electrical power to the refrig-
for air-tightness. Tests by ship's staff within one month erating installation are to be examined to the same extent as
prior to the survey may be accepted, based on a written described in Ch 3, Sec 3, [3.6].
report by the Master subject to visual inspection con- 3.2.7 Sea connections to condenser circulating pumps are
firming the air-tightness. to be opened up and piping examined.
operation and performance test of the gas supply equip-
ment, including controls, alarms, interlocks and safety 3.2.8 Other equipment, such as oil separators on refriger-
devices ant systems, filters and dehydrators, are to be examined to
examination and test of ventilation arrangements the satisfaction of the Surveyor.
including fans as deemed necessary
examination of electrical supply arrangements 3.3 Refrigerated spaces
check of gas analysers, analysing equipment and cali- 3.3.1 The lining and insulation in the refrigerated spaces
bration may need to be partly removed for examination of its condi-
check of relative humidity sensors and calibration tion. The condition of the hull part under the insulation is
check of permanent and portable gas monitoring, includ- then ascertained, as well as that of girders, meat rails, hooks
ing calibration, and of personnel safety equipment. and coil/cooler supports.
1 General 4 SPM
1.1.1 The requirements of this Section apply to ships which 4.1.1 The Owner or his representative is to declare to the
have been assigned one of the following additional class attending Surveyor that no significant alterations have been
notations described in Ch 1, Sec 2, [6.14]: made without the prior approval of the Society.
5 DYNAPOS
2 STRENGTHBOTTOM
5.1 Annual survey
2.1 Dry-docking survey
5.1.1 The program of the annual survey may be previously
2.1.1 The reinforced area of bottom plating and internal agreed with the Society.
associated structures are to be visually examined for possi- The Owner or his representative is to declare to the attend-
ble deformations, fractures or other damage. If deemed nec- ing Surveyor that no significant alterations have been made
essary, thickness measurements may be required. without the prior approval of the Society.
5.2.1 In general, the class renewal survey consists of the 6.1.2 The annual survey is to include:
checks detailed in [5.2.3] to [5.2.6]. However, a specific
an examination of the instruction manual to verify the
program of the class renewal survey prepared by the Owner
layout of the complete system and confirm the corre-
and taking into account the maintenance procedures of the
spondence to the actual system fitted on board
Manufacturers of the system is to be submitted to the Soci-
ety prior to the survey. a general examination of components of the system
such as vapour piping (including manifold and hoses),
5.2.2 The Owner is to confirm that any modification to the cargo tank gauging equipment, cargo tank level alarms,
software is fully documented and properly recorded. vapour pressure alarms and vapour balancing, if any, to
verify their satisfactory condition.
5.2.3 Prime movers of thrust units, electrical installations
and electric power generators are to be surveyed and tested
6.2 Class renewal survey
to the same extent as required in Ch 3, Sec 3, [3] for similar
equipment for the class renewal survey of machinery.
6.2.1 The requirements given in [6.1] for annual survey are
to be complied with. Additionally, the following is to be
5.2.4 During the bottom survey in dry condition which is to
carried out:
be carried out concurrently with the class renewal survey
(see Ch 3, Sec 3, [2.1]), the thrust units are to be generally a pressure test of the vapour piping, including manifold
examined. Other checks are to be carried out, such as tak- and hoses
ing clearances, examination of the orientation device or
variable pitch system, if any, verifying tightness devices, a check and test of the instrumentation (cargo tank
examination of results of lube oil analysis for detection of gauging equipment, cargo tank level alarms, vapour
possible deterioration of internal gears and pressure alarms)
bearings. Dismantling of internal parts may be required if an inspection and test of the vapour balancing equip-
the above examinations are not satisfactory. ment, if any
5.2.5 Sensors and position reference systems are to be a running test of the system.
tested to check their accuracy. Failure of sensors is to be
simulated in order to check the related alarm system and
switching logic. Switch over to the different reference sys-
7 COVENT
tems is to be checked.
7.1 Annual survey
5.2.6 An operational test of the installation is to be per-
formed, including: 7.1.1 The Owner or his representative is to declare to the
test of each thrust unit at different loads, pitches and attending Surveyor that no significant modifications have
speeds, and check of monitoring devices been made without the prior approval of the Society.
test of the thrust controls in the different available 7.1.2 The annual survey is to include a general examina-
modes (automatic, semi-automatic, manual), and the tion of components of the system such as ventilation piping
switch over between the different modes and fans.
test of the different alarms and safety systems, using sim-
ulated conditions as necessary 7.2 Class renewal survey
test of power supply failure and verification of intended
functioning in such cases 7.2.1 The requirements given in [7.1] for annual survey are
to be complied with. Additionally, the following is to be
final test to verify the capacity of the system to keep the carried out:
ship in the intended position and maintain the heading,
with related alarm and monitoring devices. The accu- an inspection of the components of the system to the
racy of the system is to be checked and compared with same extent as required in Ch 3, Sec 3, [3] for similar
previous results for evaluation of drift equipment for the class renewal survey of machinery
test of the power management system. a running test of the system.
a general examination of the items of equipment regard- general external examination of the socket outlets
ing remote control of operations and gauging/alarms provided close to each lifeboat to supply the heating
provided for all those parameters that are required to be system of lifeboat engine
kept under control to verify their satisfactory condition
test of the de-icing systems including indications
a running test which may be also performed by a spot and alarms, at random
check method.
test, as far as practicable, of the sequence of ventila-
tion in loop in the air inlet compartment on air
8.2 Class renewal survey intakes for HVAC, machinery room and emergency
generator room.
8.2.1 The requirements given in [8.1] for annual survey are
to be complied with. Additionally, the following is to be c) Machinery installations:
carried out:
general external examination and testing at random
a check and test of the instrumentation fitted to the com- of the ventilation system for the machinery compart-
ponents of the system ments (for COLD DI and COLD (H tDH, E tDE))
an overall running test of the system. general external examination of de-icing arrange-
ments for:
9 COLD DI, COLD (H tDH, E tDE) - sea inlets, overboard discharges (above the water
line and up to 1 m below the ballast water line),
air vent heads (for COLD (H tDH, E tDE))
9.1 General
- air pipes and their automatic closing devices
9.1.1 The requirements of this Article apply to ships which where fitted, sounding pipes and overflow pipes
have been assigned the following additional class notations (for cooling water recirculation tanks and water
defined in Ch 1, Sec 2, [6.14.12]: ballast tanks), piping systems in exposed areas
including ro-ro spaces, spray water lines, exposed
COLD DI
deck scuppers, washing lines and discharge lines
COLD (H tDH, E tDE) (for COLD DI and COLD (H tDH, E tDE))
when the additional class notation COLD (H tDH, general examination of the specific heating arrange-
ments provided for the cargo P/V valves (for COLD
E tDE) is assigned:
DI and COLD (H tDH, E tDE))
- manual for de-icing procedures
test of the de-icing systems including indications
- stability manual including loading conditions and alarms, at random (for COLD DI and COLD
with ice accretion. (H tDH, E tDE)).
10.1 General 11.3.1 The general wear of the ship can induce vibration
and noise increase. A survey, including noise and vibration
The requirements of this Article apply to ships which have measurements in harbour and sea conditions as well as
been assigned the additional class notation COLD CARGO, insulation and impact noise measurements, is to be carried
as defined in Ch 1, Sec 2, [6.14.13]. out.
Measurements can be limited to 30% of initial survey meas- a) The general examination of the physical characteristics
uring points. of the helideck is to include:
In case of additional class notation ACCOMMODATION, the dimensions as measured
noise measurements in harbour and sea conditions, insula- the declared D-value
tion and impact noise measurements are to be carried out the deck shape, and
only in case of significant modifications, as stated in the scale drawings of deck arrangement.
[11.2.1].
b) The general examination of the preservation of obstacle-
protected surfaces is to include:
12 Permanent means of access the minimum 210 Obstacle Free Sector (OFS) surface
the 150 Limited Obstacle Sector (LOS) surface, and
(ACCESS)
the minimum 180 falling 5:1 gradient surface with
respect to significant obstacles.
12.1 Annual survey, intermediate survey and Note 1: If one or more of these surfaces is/are infringed due, for
class renewal survey example, to the proximity of an adjacent installation or vessel,
an assessment is to be made to determine any possible negative
12.1.1 General conditions effect which may lead to operating restrictions.
Visual examination of following parts of permanent means c) The general examination of the marking and lighting is
of access is to be carried out in conjunction with surveys of to include:
spaces where the notation ACCESS is assigned: the adequate helideck perimeter lighting
visual examination for signs of corrosion the adequate helideck touchdown marking lighting
("H" and TD/PM Circle lighting) and/or floodlighting
examination for satisfactory condition of the marking the status lights (for day and night operations)
(e.g. strip, arrows, non-slip surfaces)
the helideck markings
examination of the location lighting where the perma- the dominant obstacle paint schemes and lighting,
nent mean of access is fitted and
examination for satisfactory condition of rails, stan- the general installation lighting levels including
chions, hand rails and other guard rails. floodlighting.
Note 2: Where inadequate helideck lighting exists, the Helideck
Limitation List (HLL) is to be annotated daylight only opera-
13 Offshore handling systems (OHS) tions.
d) The general examination of the deck surface is to
13.1 Application include:
the surface friction
13.1.1 The requirements of this Article apply to ships the helideck net (as applicable)
which have been assigned the additional class notation
the drainage system
OHS, as defined in Ch 1, Sec 2, [6.14.34].
the deck edge perimeter safety netting
the tie-down points, and
13.2 Periodical surveys
the cleaning of all contaminants (to maintain satis-
13.2.1 For survey requirements and for periodical surveys, factory recognition of helideck markings and preser-
refer to Section 4 of NR595 Classification of Offshore Han- vation of the helideck friction surface).
dling Systems. e) The verification of the environment effects is to include:
foreign object damage
14 Helideck (HEL) air quality degradation due to exhaust emissions, hot
and cold vented gas emissions and physical turbu-
lence generators
14.1 Application bird control
any adjacent helideck/installation having significant
14.1.1 The requirements of this Article apply to ships
environmental effects in any air quality assessment,
which have been assigned the additional class notation
and
HEL, as defined in Ch 1, Sec 2, [6.14.23].
flares.
f) The general examination of the rescue and fire fighting
14.2 Annual surveys
facilities is to include:
14.2.1 The Society considers that as a minimum these fol- the primary and complementary media types, quan-
lowing issues are to be examined during the periodic sur- tities, capacity and systems
veys to confirm that there has been no alteration or the Personal Protective Equipment (PPE), and
deterioration in the condition of the helicopter landing area: the crash box.
g) The general examination of the communications and i) The general examination of the additional operational
navigation system arrangements is to include: and handling equipment is to include:
the aeronautical radio(s) the windsock
the radio/telephone (R/T) call sign to match helideck
name and side identification which should be sim- the meteorological information (recorded by an
ple and unique automated means)
the Non-Directional Beacon (NDB) or equivalent (as the Helideck Motion System recording and reporting
appropriate), and (where applicable)
the radio log. the passenger briefing system
h) The general examination of the fuelling facilities is to the chocks
include:
the fuel system, ventilation, fire protection and the tie-downs, and
detection the weighing scales for passengers, baggage and
the pump and aircraft bonding safety systems. freight.
Chapter 6
RETROACTIVE REQUIREMENTS
FOR EXISTING SHIPS
SECTION 1 GENERAL
SECTION 2 BULK CARRIERS, ORE CARRIERS AND COMBINATION
CARRIERS
SECTION 3 RO-RO PASSENGER SHIPS
SECTION 1 GENERAL
Section in
Service notation Ships survey items or features concerned
Chapter 6
bulk carrier ESP Ch 6, Sec 2 - Scantlings of transverse bulkhead between the two foremost cargo holds
- Allowable hold loading of the foremost cargo hold
- Damage stability
- Intermediate survey in lieu of annual survey in the foremost cargo hold
- Detection of water ingress into cargo holds
- Cargo hatch cover securing arrangements
- Renewal criteria for side shell frames and brackets
- Restriction from sailing with any hold empty
bulk carrier ESP Ch 6, Sec 2 - Loading conditions, loading manuals and loading instruments
ore carrier ESP - Strength and securing of small hatches on the exposed fore deck
combination carrier/OBO ESP - Strength requirements for fore deck fittings and equipment
combination carrier/OOC ESP - Hold, ballast and dry space water level detectors
- Availability of pumping systems
ro-ro passenger ship Ch 6, Sec 3 - Increased stability and watertight integrity
general cargo ship Ch 6, Sec 4 - Strength and securing of small hatches on the exposed fore deck
bulk carrier (without ESP) - Strength requirements for fore deck fittings and equipment
refrigerated cargo ship
livestock carrier
deck ship
ships with Ice Classes Ch 6, Sec 5 - Maintenance of additional class notations ICE CLASS IA SUPER,
ICE CLASS IA, ICE CLASS IB, ICE CLASS IC
1 Foremost cargo hold requirements for ships which were 10 years of age or more, but less
than 15 years on 1st July 1998, by the due date of the next
intermediate survey or class renewal survey after the date
1.1 Application on which the ship reaches 15 years of age, but not later
than the date on which the ship reaches 17 years of age
1.1.1 These retroactive rule requirements apply to ships
with service notation bulk carrier ESP: for ships which were 5 years of age or more, but less
than 10 years on 1st July 1998, by the due date, after
of single side skin construction see Note 1 1st July 2003, of the next intermediate survey or class
of 150 metres in length and above renewal survey after the date on which the ship reaches
intended to carry solid bulk cargoes having a bulk den- 10 years of age, whichever occurs first
sity of 1,78 t/m3 or above for ships which were less than 5 years of age on 1st July
1998, by the date on which the ship reaches 10 years of
contracted for construction prior to 1st July 1998, and
age.
not constructed in compliance with the applicable
requirements for new buildings contracted after that 1.2.2 Completion, prior to 1st July 2003, of an intermediate
date, and given in Pt D, Ch 4, Sec 3. or class renewal survey with a due date after 1st July 2003,
cannot be used to postpone compliance.
Note 1: Single side skin bulk carriers means, as defined in SOLAS
conf. 4/25 Res.6, where one or more cargo holds are bound by the However, completion prior to 1st July 2003 of an intermedi-
side shell only or by two watertight boundaries, one of which is the ate survey the window for which straddles 1st July 2003 can
side shell, which are less than 760 mm apart in bulk carriers con- be accepted.
structed before 1st January 2000, and less than 1000 mm apart in
bulk carriers constructed on or after 1st January 2000. The distance 1.3 Scantlings of the vertically corrugated
between the watertight boundaries is to be measured perpendicular
to the side shell (ref.: IMO MSC Res.89(71)).
transverse watertight bulkhead between
the two foremost cargo holds
1.1.2 They are related to:
1.3.1 The net scantlings of the vertically corrugated trans-
scantlings of the transverse corrugated cargo hold bulk- verse watertight bulkhead between the two foremost cargo
head between the two foremost cargo holds, as detailed holds are to be assessed in accordance with the method
in [1.3] given in Ch 6, App 1, [2].
allowable hold loading of the foremost cargo hold with In these requirements, homogeneous loading condition
the same hold flooded, as detailed in [1.4] means a loading condition in which the ratio between the
damage stability with the foremost cargo hold flooded, highest and the lowest filling ratio, evaluated for the two
as detailed in [1.5]. foremost cargo holds, does not exceed 1,20, to be corrected
for different cargo densities.
1.1.3 In case where such ships cannot comply to the
requirements for damage stability due to their design, then 1.3.2 Thickness measurements are necessary to determine
the requirements of [1.6] are applicable, instead of those the general condition of the structure and to define the extent
laid down in [1.3], [1.4] and [1.5]. of possible repairs and/or reinforcements of the vertically cor-
rugated transverse watertight bulkhead for verification of the
1.2 Schedule for compliance compliance with the requirements given in Ch 6, App 1, [2].
Thickness measurements and assessment of the scantlings
1.2.1 These requirements are to be complied with by the are to be carried out for the initial evaluation at the limit
following limit dates: date as defined in [1.2.1], and thereafter at each subsequent
for ships which were 20 years of age or more on 1st July intermediate survey (for ships over 10 years of age) and
1998, by the due date of the first intermediate survey or each subsequent class renewal survey for purposes of veri-
the due date of the first class renewal survey, to be held fying continuing compliance with the above mentioned
after 1st July 1998, whichever comes first requirements.
for ships which were 15 years of age or more, but less 1.3.3 Taking into account the buckling criteria applied in
than 20 years on 1st July 1998, by the due date of the Ch 6, App 1, [2] in the evaluation of strength of the bulk-
first class renewal survey to be held after 1st July 1998, head, it is essential to determine the thickness diminution at
but not later than 1st July 2002 the critical levels shown in Fig 1 and Fig 2.
1.3.4 Thickness measurements are to be carried out at the 1.3.6 Where necessary, steel renewal and/or reinforce-
levels indicated in [1.3.5]. To adequately assess the scant- ments are to meet the requirements given in Ch 6, App 1,
lings of each individual vertical corrugation, each corruga- [2.6].
tion flange, web, shedder plate (see Ch 6, App 1, Fig 4 and
Ch 6, App 1, Fig 5) and gusset plate (see Ch 6, App 1, Fig 6,
Ch 6, App 1, Fig 7 and Ch 6, App 1, Fig 8) within each of
1.4 Allowable hold loading of the foremost
the levels indicated in [1.3.5] is to be measured. cargo hold with the same hold flooded
1.3.5 The locations at which thickness measurements are to 1.4.1 The loading in the foremost cargo hold is not to
be carried out are as follows for each of the prescribed lev- exceed the allowable hold loading in the flooded condition.
els a, b and c: The method of calculation is laid down in Ch 6, App 1, [4].
level a - bulkheads without lower stool (see Fig 1) In no case is the allowable hold loading in the flooding con-
- the mid-breadth of the corrugation flanges and webs dition to be taken greater than the design hold loading in
at approximately 200 mm above the line of shedder the intact condition.
plates
- the middle of gusset plates between corrugation 1.5 Damage stability
flanges, where fitted
- the middle of the shedder plates 1.5.1 Bulk carriers which are subject to compliance with
level b - bulkheads with lower stool (see Fig 2) the requirements laid down in [1.3.1] and [1.4.1] are, when
- the mid-breadth of the corrugation flanges and webs loaded to the summer loadline, to be able to withstand
at approximately 200 mm above the line of shedder flooding of the foremost cargo hold in all loading condi-
plates tions and remain afloat in a satisfactory condition of equi-
librium, as specified in [1.5.2].
- the middle of gusset plates between corrugation
flanges, where fitted
1.5.2 The condition of equilibrium after flooding is to sat-
- the middle of the shedder plates isfy the condition of equilibrium laid down in Pt B, Ch 3,
level c - bulkheads with or without lower stool (see Fig App 4. The assumed flooding need only take into account
1 and Fig 2) flooding of the cargo hold. The permeability of a loaded
- the mid-breadth of the corrugation flanges and webs hold is to be assumed as 0,90 and the permeability of an
at approximately the mid-height of the corrugation. empty hold is to be assumed as 0,95, unless a permeability
relevant to a particular cargo is assumed for the volume of a
Where the thickness changes within the horizontal levels, flooded hold occupied by cargo and a permeability of 0,95
the thinner plate is to be measured. is assumed for the remaining empty volume of the hold.
Figure 1 : Thickness measurement areas of cargo 1.5.3 Bulk carriers which have been assigned a reduced
hold transverse bulkhead without lower stool freeboard in compliance with the provisions of Pt B, Ch 3,
App 4 may be considered as complying with [1.5.1].
level c 1.6.1 Bulk carriers within the application limits of the pro-
visions in [1.5.2] which have been constructed with an
insufficient number of transverse watertight bulkheads to
level a satisfy this requirement may be exempted from the applica-
tion of the requirements given in [1.3], [1.4] and [1.5] pro-
vided that they fulfil those given in [1.6.2] and [1.6.3].
Figure 2 : Thickness measurement areas of 1.6.2 For the foremost cargo hold, the scope of the annual
cargo hold transverse bulkhead with lower stool survey given in Ch 4, Sec 2, [2] is also to include that of the
intermediate survey given in Ch 4, Sec 2, [3].
2 Loading instruments and loading 3.1.2 These retroactive rule requirements provide strength
requirements to resist green sea forces for the following
manuals items located within the forward quarter length: air pipes,
ventilator pipes and their closing devices.
2.1 Loading instruments
They are applicable only for air pipes, ventilator pipes and
their closing devices on the exposed deck serving spaces
2.1.1 Bulk carriers, ore carriers and combination carriers,
forward of the collision bulkhead, and to spaces which
which are assigned one of the following service notations:
extend over this line aft-wards.
bulk carrier ESP
The provisions for compliance with these strength require-
ore carrier ESP ments for fore deck fittings and equipment are given in Pt C,
combination carrier/OBO ESP Ch 1, Sec 10, [9.1.9].
combination carrier/OOC ESP These retroactive rule requirements are also applicable for
small hatches on the exposed deck giving access to spaces
of 150 m length and above, which were contracted for con- forward of the collision bulkhead, and to spaces which
struction before 1st July 1998, are to be provided with an extend over this line aft-wards.
approved loading instrument of a type to the satisfaction of
the Society not later than their entry into service or 1st Janu- They are related to the strength of, and securing for, such
ary 1999, whichever occurs later. small hatches fitted on the exposed fore deck.
3.1 Application and requirements for ships which will be 15 years of age or more on
1st January 2004, by the due date of the first intermedi-
3.1.1 These retroactive rule requirements apply to ships ate or class renewal survey after that date
which are assigned one of the following service notations: for ships which will be 10 years of age or more on
bulk carrier ESP 1st January 2004, by the due date of the first class
renewal survey after that date
bulk carrier BC-A ESP
for ships which will be less than 10 years of age on
bulk carrier BC-B ESP
1st January 2004, by the date on which the ship reaches
bulk carrier BC-C ESP 10 years of age.
ore carrier ESP
3.2.2 Completion, prior to 1st January 2004, of an interme-
combination carrier/OBO ESP diate or class renewal survey with a due date after 1st Janu-
combination carrier/OOC ESP, ary 2004 cannot be used to postpone compliance.
However, completion prior to 1st January 2004 of an inter-
of 100 m in length and above, that are contracted for con- mediate survey the window for which straddles 1st January
struction prior to 1st January 2004. 2004 can be accepted.
4 Cargo hatch cover securing the side shell frames and brackets of cargo holds
bounded by the single side shell of ships with service
arrangements for bulk carriers
notation combination carrier/OBO ESP as defined in
Ch 1, Sec 2, [4.3.4] but of single side skin construction,
4.1 Application and requirements
which were not built in accordance with the applicable
4.1.1 These retroactive rule requirements apply to ships requirements of Part II, Chapter 8, Section 8-03 of the
which are assigned one of the following service notations: 1st April 1998 edition of the Rules or subsequent editions.
bulk carrier ESP In the case a ship as defined above does not satisfy above
bulk carrier BC-A ESP definition in one or more holds, the retroactive rule require-
bulk carrier BC-B ESP ments do not apply to these individual holds.
bulk carrier BC-C ESP, 5.1.2 These requirements define steel renewal criteria or
and which were not built in accordance with Pt B, Ch 9, other measures (reinforcement or coating) to be taken for
Sec 7, [1] to Pt B, Ch 9, Sec 7, [7] of edition February 2003 the webs and flanges of side shell frames and brackets as
of the Rules as amended in accordance with November per the provisions of Ch 6, App 1, [5].
2003 amendments or subsequent editions. Reinforcing measures of side frames are also defined as per
Ch 6, App 1, [5.4.2].
4.1.2 They are related to steel hatch cover securing devices Finite element or other numerical analysis or direct calcula-
and stoppers for cargo hold hatchways No 1 and No 2 tion procedures cannot be used as an alternative to compli-
which are wholly or partially within 0,25 L of the fore per- ance with these requirements, except in cases of unusual
pendicular, except pontoon type hatch cover. side structure arrangements or framing to which these
The provisions for compliance with these requirements for requirements cannot be directly applied. In such cases, the
cargo hatch cover securing arrangements are given in Ch 6, analysis criteria and the strength check criteria are to be in
App 1, [6]. accordance with the Rules of the Society.
for ships which will be less than 10 years of age on Figure 3 : Zones of side shell frames and brackets
1st July 2005, by the date on which the ship reaches 10
years of age.
The minimum acceptable remaining thickness in any pit or 5.3.5 The gauging pattern for web plating for zones A, B and
groove is equal to: D are to be a five point pattern (see Fig 5). The 5 point pat-
tern is to be over the depth of the web and the same area ver-
75% of the as-built thickness, for pitting or grooving in
tically. The gauging report is to reflect the average reading.
the cargo hold side frame webs and flanges
70% of the as-built thickness, for pitting or grooving in Figure 5 : Typical 5 point pattern on the web plate
the side shell, hopper tank and topside tank plating
attached to the cargo hold side frame, over a width up Face Plate
to 30 mm from each side of it.
Side shell
5.3.4 Numbers of side frames to be measured are equiva- x x
lent to those of the class renewal survey or intermediate sur-
vey corresponding to the ships age. Representative
x W mm
thickness measurements are to be taken for each zone as
Web
specified below.
x x
Special consideration to the extent of the thickness meas-
urements may be given by the Society, if the structural
members show no thickness diminution with respect to the
as-built thicknesses and the coating is found in as-new W mm
condition (i.e without breakdown or rusting).
Where gauging readings close to the criteria are found, the
5.3.6 Depending upon the condition of the web in way of
number of hold frames to be measured is to be increased.
zone C, the web plating for zone C is to be measured by
If renewal or other measures according to the present Arti- taking 3 readings over the length of zone C and averaging
cle [5] are to be applied on individual frames in a hold, them. The average reading is to be compared with the
then all frames in that hold are to be gauged. allowable thickness. If the web plating has general corro-
sion then this pattern is to be expanded to a five point pat-
There is a variety of construction methods used for side tern as noted in [5.3.5].
shell frames in bulk carriers. Some have face plates (T sec-
tions) on the side shell frames, some have flanged plates 5.3.7 Where the lower bracket length or depth does not
and some have bulb plates. The use of face plates and meet the requirements in Pt D, Ch 4, Sec 3, [2.2.6], gaug-
flanged sections is considered similar for gauging purposes ings are to be taken at sections a) and b) to calculate the
in that both the web and face plate or web and flange plate actual section modulus required in Ch 6, App 1, [5.5.5] (see
are to be gauged. If bulb plate has been used, then web of Fig 6). At least 2 readings on the flange/face plate are to be
the bulb plate is to be gauged in the normal manner and the taken in way of each section. At least one reading of the
sectional modulus has to be specially considered if attached shell plating is to be taken on each side of the
required. frame (i.e. fore and aft) in way of section a) and section b).
6 Hold, ballast and dry space water 7.2 Schedule for compliance
level detectors
7.2.1 Ships referred to in [7.1.1] are to comply with the
provisions of Pt C, Ch 1, Sec 10, [6.6.3], item e) not later
6.1 Application and requirements
than the date of the first intermediate or class renewal sur-
6.1.1 These retroactive rule requirements apply to ships vey of the ship to be carried out after 1st July 2004, but in no
which are assigned one of the following service notations: case later than 1st July 2007.
bulk carrier ESP
bulk carrier BC-A ESP 8 Restriction from sailing with any
bulk carrier BC-B ESP hold empty
bulk carrier BC-C ESP
ore carrier ESP
combination carrier/OBO ESP
8.1 Application and requirements
combination carrier/OOC ESP,
8.1.1 These retroactive rule requirements apply to ships
of 500 GT and above constructed before 1 July 2004. which are assigned one of the service notations bulk carrier
ESP or combination carrier/OBO ESP:
6.1.2 They are related to the fitting of water level detectors.
The provisions for compliance with these requirements are of single side skin construction
given in Pt C, Ch 1, Sec 10, [6.12.1] and Pt C, Ch 1, Sec 10,
of 150 metres in length and above
[6.6.3], item d).
intended to carry solid bulk cargoes having a density of
6.2 Schedule for compliance 1,78 t/m3 in alternate hold loading conditions
6.2.1 Ships referred to in [6.1.1] are to comply with the contracted for construction prior to 1st July 1998 or con-
provisions of Pt C, Ch 1, Sec 10, [6.12.1] and Pt C, Ch 1, structed before 1st July 1999.
Sec 10, [6.6.3], item d) not later than the date of the annual,
intermediate or class renewal survey of the ship to be car- 8.1.2 Such ships, if not meeting the requirements for with-
ried out after 1st July 2004, whichever comes first. standing flooding of any one cargo hold, as specified in Part
II, Chapter 8, Section 8-03, 8-032-2, 8-037-3 and 8-033-4
7 Availability of pumping systems of the 1st April 1998 edition of the Rules or subsequent edi-
tions, and the retroactive requirements for side structure of
bulk carriers of single-side skin construction, as specified in
7.1 Application and requirements
[5], are not to sail with any hold loaded to less than 10% of
7.1.1 These retroactive rule requirements apply to ships the holds maximum allowable cargo weight when in the
which are assigned one of the following service notations: full load condition, after reaching 10 years of age.
bulk carrier ESP The applicable full load condition for this requirement is a
bulk carrier BC-A ESP load equal to, or greater than, 90% of the ships deadweight
bulk carrier BC-B ESP at the relevant assigned freeboard.
bulk carrier BC-C ESP
ore carrier ESP 8.1.3 Any restrictions imposed on the carriage of solid bulk
cargoes having a density of 1,78 t/m3 and above in accord-
combination carrier/OBO ESP
ance with these requirements are to be identified and
combination carrier/OOC ESP, recorded in the loading manual.
of 500 GT and above constructed before 1st July 2004.
8.1.4 A ship to which the requirements in [8.1.3] apply is
7.1.2 They are related to the availability of pumping sys- to be permanently marked on the side shell amidships, port
tems. and starboard, with a solid equilateral triangle having sides
The provisions for compliance with these requirements are of 500 mm and its apex 300 mm below the deck line, and
given in Pt C, Ch 1, Sec 10, [6.6.3], item e). painted a contrasting colour to that of the hull.
Table 1 : Date of compliance according to A/Amax 1000 N. < 1500 1st October 2006
600 N. < 1000 1st October 2008
Value of A/Amax Date of compliance 400 N. < 600 1st October 2010
A/Amax < 85% st
1 October 1998
a) when the age of the ship is equal to or greater than 20
85% A/Amax < 90% 1st October 2000
years, where the age of the ship means the time counted
90% A/Amax < 95% 1st October 2002 from the date on which the keel was laid, or the date on
95% A/Amax < 97,5% 1st October 2004 which it was at a similar stage of construction, or from
the date on which the ship was converted to a ro-ro pas-
A/Amax 97,5% 1st October 2005 senger ship.
Note 2: The scope of application for these type of ships is subject side of the cargo hold length extending vertically at least
to special consideration. from inner bottom to freeboard deck.
hf
D
df
h1
V
df
P
V = Volume of cargo
P = Calculation point
c : Bulk cargo density, in t/m3 hLS : Height of the lower stool, in m, from the
inner bottom.
lc : Length of the foremost cargo hold, in m
b) Case when df < d1
B : Ships breadth amidships, in m
At each point of the bulkhead located at a distance
vLS : Volume, in m3, of the bottom stool above the
between df and d1 from the base line, the pressure pc,f ,
inner bottom
in kN/m2, is given by:
hHT : Height of the hopper tanks amidships, in m,
from the base line pc,f = c g h1 tan2
pc,f = g hf where:
: Sea water density, in t/m3 The force Fc,f , in kN, acting on a corrugation is given by:
c : Bulk cargo density, in t/m3 2.2.4 Pressure in the flooded hold: empty hold
perm : Permeability of cargo, to be taken as 0,3 for At each point of the bulkhead, the hydrostatic pressure pf
ore (corresponding bulk cargo density for induced by the flooding head hf is to be considered.
iron ore may generally be taken as 3,0 t/m3)
The force Ff , in kN, acting on a corrugation is given by:
h1 : Vertical distance, in m, from the calculation
point to a level located at a distance d1 , as ( d f h DB h LS ) 2
defined above, from the base line (see Fig 1) F f = s 1 g --------------------------------------
-
2
: = 45 ( / 2) where:
: Angle of repose of the cargo, in degrees, s1 , , g, hLS : As given in [2.2.3], item a)
and may generally be taken as 35 for iron
ore. hDB : As given in [2.2.3]
The force Fc,f , in kN, acting on a corrugation is given by: df : As given in [2.2.2].
2.2.5 Pressure in the non-flooded bulk cargo loaded The resultant force F, in kN, acting on a corrugation is given by:
hold F = Fc,f
At each point of the bulkhead, the pressure pc , in kN/m2, is
Where the foremost cargo hold, in non-homogeneous load-
given by:
ing conditions, is not allowed to be loaded, the resultant
pc = c g h1 tan2 pressure p, in kN/m2, to be considered for the scantlings of
where: the bulkhead is given by:
c , g, h1 , : As given in [2.2.3], item a). p = pf
The force Fc , in kN, acting on a corrugation is given by: and the resultant force F, in kN, acting on a corrugation is
( d 1 h DB h LS ) 2 given by:
F c = s 1 c g ---------------------------------------
- tan2
2 F = Ff
where:
c , g, s1 , hLS , : As given in [2.2.3], item a) 2.3 Bending moment and shear force in the
d1 , hDB : As given in [2.2.3]. bulkhead corrugations
Shedder Plates
When f < 50
n
(*)
(): For the definition of , the internal end of the upper stool is not to be taken more than a distance from the deck at the centreline equal to:
- three times the depth of corrugations, in general
- twice the depth of corrugations, for rectangular stool.
the section modulus Zle , in cm3, is to be taken not larger tf : Net flange thickness, in mm
than the value Zle , in cm3, given by:
Fsh : Minimum upper yield stress, in N/mm2, of
Qh g 0, 5h s p g 2 the material used for the shedder plate
Z le = Z g + 10 3 ------------------------------------------
g 1
-
a
Ffl : Minimum upper yield stress, in N/mm2, of
where: the material used for the corrugation
flanges.
Zg : Section modulus of one half pitch corrugation,
in cm3, according to [2.4.4], in way of the upper
end of shedder or gusset plates, as applicable Figure 4 : Symmetrical shedder plates
a 2
: Allowable stress, in N/mm , as given in [2.4.5]. Lower
stool
Stresses are obtained by dividing the shear force Q by the
shear area. The shear area is to be reduced in order to
account for possible non-perpendicularity between the cor-
rugation webs and flanges. In general, the reduced shear
area may be obtained by multiplying the web sectional area
by (sin), being the angle between the web and the flange. Figure 5 : Asymmetrical shedder plates
tsh : Net shedder plate thickness, in mm sgu : Width of the gusset plates, in mm
tgu : Net gusset plate thickness, in mm, not to be Figure 8 : Asymmetrical gusset/shedder plates
taken greater than tf Sloping stool top plate
a
= 10 3 --- -----F
tf E
gusset
hg plate tf : Net flange thickness, in mm
a : As given in [2.4.2]
1
F : Minimum upper yield stress, in N/mm2, of the
Lower
stool material
E : Modulus of elasticity, in N/mm2, to be assumed
equal to 206000 N/mm2 for steel.
2.4.7 Shear buckling check The net thickness of the wider plating, in mm, is not to be
taken less than the maximum of the following values:
The buckling check is to be performed for the web plates at
the corrugation ends. p
t w = 14, 9s w -----
F
The shear stress is not to exceed the critical value C , in
N/mm2, obtained as follows: 440s w2 p 2
tw = ------------------- t np
F
C = E for E ----F where:
2
F
tnp : Thickness, in mm, less or equal to the actual net
C = F 1 -------
- for E > ----F thickness of the narrower plating and not to be
4 E 2
greater than:
F = ------F- p-
14, 9s w ----
3 F
where:
2.5 Local details
F : Minimum upper yield stress, in N/mm2, of the
material 2.5.1 General
2 As applicable, the design of local details is to comply with
E = 0, 9k t E ----------------
t
1000c the Societys requirements for the purpose of transferring the
corrugated bulkhead forces and moments to the boundary
kt = 6,34 structures, especially to the double bottom and cross-deck
structures.
E : Modulus of elasticity, in N/mm2, as given in
[2.4.6] In particular, the thickness and stiffness of gusset and shed-
der plates, as defined in [2.4.3], installed for strengthening
t : Net thickness, in mm, of corrugation web purposes, are to comply with the Societys requirements on
the basis of the load model in [2.2].
c : Width, in m, of corrugation web (see Fig 2).
Unless otherwise stated, weld connections and materials
2.4.8 Local net plate thickness are to be dimensioned and selected in accordance with the
Societys requirements.
The bulkhead local net plate thickness t, in mm, is given by:
p
2.6 Steel renewal
t = 14, 9s w -----
F
2.6.1 General
where: Renewal/reinforcement is to be carried out in accordance
with the following requirements and the guidelines con-
sw : Plate width, in m, to be taken equal to the width
tained in [3].
of the corrugation flange or web, whichever is
the greater (see Fig 2) 2.6.2 Steel renewal is required where the gauged thickness
p : Resultant pressure, in kN/m2, as defined in is less than (tnet + 0,5) mm, tnet being the thickness used for
[2.2.6] and [2.2.7], at the bottom of each strake the calculation of bending capacity and shear stresses as
of plating; in all cases, the net thickness of the given in [2.4.2] or the local net plate thickness as given in
lowest strake is to be determined using the [2.4.8]. Alternatively, reinforcing doubling strips may be
resultant pressure at the top of the lower stool or used providing the net thickness is not dictated by shear
at the inner bottom, if no lower stool is fitted, or strength requirements for web plates (see [2.4.5] and
at the top of shedders, if shedder or gusset/shed- [2.4.7]) or by local pressure requirements for web and
der plates are fitted flange plates (see [2.4.8]).
Where steel renewal is required, the bulkhead connections
F : Minimum upper yield stress, in N/mm2, of the
to the lower stool shelf plate (or inner bottom, if no stool is
material.
fitted) are to be made at least by deep penetration welds
For built-up corrugation bulkheads, when the thicknesses of (see Fig 9).
the flange and web are different, the net thickness of the Where the gauged thickness is within the range (tnet + 0,5)
narrower plating is to be not less than tn , in mm, given by: mm and (tnet + 1,0) mm, coating (applied in accordance
with the coating Manufacturers specifications) or annual
p
t n = 14, 9s n ----- gauging may be adopted as an alternative to steel renewal.
F
6 6
B
B
=
= =
2.6.4 Gussets with shedder plates, extending from the 3.1.2 In addition to Rule requirements, the assessment of
lower end of corrugations up to 0,1 , or reinforcing dou- the transverse corrugated bulkhead based on the criteria
bling strips (on bulkhead corrugations and stool side plat- given in [2] will take into account the following:
ing) are to be fitted when:
scantlings of individual vertical corrugations will be
Fs t st
-----------
- 0, 8 assessed for reinforcement/renewal based on thickness
Ffl t fl
measurements obtained in accordance with Ch 6, Sec
where: 2, [1.3] at their lower end, at mid-depth and in way of
Ffl : Minimum upper yield stress, in N/mm2, of the plate thickness changes in the lower 70%. These consid-
material used for the corrugation flanges erations will take into account the provision of gussets
Fs : Minimum upper yield stress, in N/mm2, of the and shedder plates and the benefits they offer, provided
material used for the lower stool side plating (or that they comply with [2.4.2] and [2.6].
floors, if no stool is fitted)
tfl : Flange thickness, in mm, which is found to be taking into account the scantlings and arrangements for
acceptable on the basis of the criteria specified each case, permissible levels of diminution will be
in [2.6.2] or, when steel renewal is required, the determined and appropriate measures taken in accord-
replenished thickness according to the criteria ance with [2.6].
specified in [2.6.3]. The above flange thickness
dictated by local pressure requirements (see 3.1.3 Where renewal is required, its extent is to be shown
[2.4.8]) need not be considered for this purpose clearly in plans. The vertical distance of each renewal zone
tst : As-built thickness, in mm, of the lower stool is to be determined by considering the criteria given in [2]
side plating (or floors, if no stool is fitted). and is generally to be not less than 15% of the vertical dis-
If gusset plates are fitted, their material is to be the same as tance between the upper and lower end of the corrugation
that of the corrugation flanges. The gusset plates are to be measured at the ships centreline.
connected to the lower stool shelf plate (or inner bottom, if
no lower stool is fitted) by deep penetration welds (see Fig 3.1.4 Where the reinforcement is accepted by adding
9). strips, the length of the reinforcing strips is to be sufficient to
Where gusset plates are to be fitted or renewed, their con- extend over the whole depth of the diminished plating. In
nections with the corrugations and the lower stool shelf general, the width and thickness of strips are to be sufficient
plate (or inner bottom, if no stool is fitted) are to be made at to comply with the criteria given in [2]. The material of the
least by deep penetration welds (see Fig 9). strips is to be the same as that of the corrugation plating.
The strips are to be attached to the existing bulkhead plating
3 Guidance on renewal/reinforcement by continuous fillet welds. The strips are to be suitably
of the transverse watertight vertically tapered or connected at ends in accordance with the usual
corrugated bulkhead between the welding practice to the Surveyors satisfaction.
3.1.6 Fig 10 gives a general arrangement of structural rein- contracted for construction prior to 1st July 1998, and
forcement. When such reinforcement is carried out, the fol- not constructed in compliance with the applicable
lowing applies: requirements for new buildings contracted after that
square or trapezoidal corrugations are to be reinforced date, and given in Pt D, Ch 4, Sec 3.
with plate strips fitted to each corrugation flange suffi-
4.1.2 The loading in the foremost cargo hold is not to
cient to meet the requirements given in [2]
exceed the allowable hold loading in the flooded condition,
the number of strips fitted to each corrugation flange is calculated as per [4.4], using the loads given in [4.2] and
to be sufficient to meet the requirements given in [2] the shear capacity of the double bottom given in [4.3].
the shedder plate may be fitted in one piece or prefabri- In no case is the allowable hold loading in flooding condi-
cated with a welded knuckle (gusset plate) tion to be taken greater than the design hold loading in
intact condition.
gusset plates, where fitted, are to be welded to the shelf
plate in line with the flange of the corrugation, to
reduce the stress concentrations at the corrugation cor- 4.2 Load model
ners. Good alignment is to be ensured between gusset
4.2.1 General
plates, corrugation flanges and lower stool sloping
plates. Deep penetration welding is to be used at all The loads to be considered as acting on the double bottom of
connections. Start and stop of welding are to be as far the foremost cargo hold are those given by the external sea
away as possible from corners of corrugations pressures and the combination of the cargo loads with those
induced by the flooding of the foremost cargo hold itself.
shedder plates are to be attached by one side full pene-
tration welds onto backing bars The most severe combinations of cargo induced loads and
flooding loads are to be used, depending on the loading
shedder and gusset plates are to have a thickness equal conditions included in the loading manual:
to or greater than the original bulkhead thickness. Gus-
homogeneous loading conditions
set plates are to have a minimum height (on the vertical
part) equal to half of the width of the corrugation flange. non-homogeneous loading conditions
Shedders and gussets are to be of the same material as packed cargo conditions, such as steel mill products.
that of the flange.
For each loading condition, the maximum bulk cargo den-
sity to be carried is to be considered in calculating the
4 Evaluation of allowable hold loading allowable hold limit.
of the foremost cargo hold with the
4.2.2 Inner bottom flooding head
same cargo hold flooded
The flooding head hf (see Fig 11) is the distance, in m, meas-
ured vertically with the ship in the upright position, from
4.1 Application and definitions the inner bottom to a level located at a distance df , in m,
from the base line equal to:
4.1.1 These requirements apply to bulk carriers:
- D in general
of single side skin construction - 0,95 D for ships less than 50,000 tonnes deadweight
of 150 metres in length and above with type B freeboard,
intended to carry solid bulk cargoes having a bulk den- D being the distance, in m, from the base line to the free-
sity of 1,78 t/m3 or above board deck at side amidships (see Fig 11).
Figure 11 : Calculation of pressure on the inner bottom in the flooded cargo hold
hf
D df
h1
V
V = Volume of cargo
4.3 Shear capacity of the double bottom of tC : Corrosion diminution, equal to 2 mm, in gen-
the foremost cargo hold eral; a lower value of tC may be adopted, pro-
vided that measures are taken, to the Societys
4.3.1 General satisfaction, to justify the assumption made.
The shear capacity C of the double bottom of the foremost 4.3.2 Floor shear strength
cargo hold is defined as the sum of the shear strength at
The floor shear strength in way of the floor panel adjacent to
each end of:
hoppers Sf1 , in kN, and the floor shear strength in way of
all floors adjacent to both hoppers, less one half of the the openings in the outermost bay (i.e. that bay which is
strength of the two floors adjacent to each stool, or closest to the hopper) Sf2 , in kN, are given by the following
transverse bulkhead if no stool is fitted (see Fig 12) expressions:
all double bottom girders adjacent to both stools, or
transverse bulkheads if no stool is fitted. S f1 = 10 3 A f -----a
1
The strength of girders or floors which run out and are not
S f2 = 10 3 A f, h -----a
directly attached to the boundary stool or hopper girder is 2
to be evaluated for the one end only. where:
Note 1: The floors and girders to be considered are those inside the Af : Sectional area, in mm2, of the floor panel adja-
hold boundaries formed by the hoppers and stools (or transverse cent to hoppers
bulkheads if no stool is fitted). The hopper side girders and the
Af,h : Net sectional area, in mm2, of the floor panels
floors directly below the connection of the bulkhead stools (or
transverse bulkheads if no stool is fitted) to the inner bottom are not in way of the openings in the outermost bay (i.e.
to be included. that bay which is closest to the hopper)
Note 2: When the geometry and/or the structural arrangement of a : Allowable shear stress, in N/mm2, to be taken
the double bottom is such as to make the above assumptions inad- equal to:
equate, at the Societys discretion, the shear capacity C of the dou-
ble bottom is to be calculated by means of direct calculations to be a = ------F-
carried out according to Pt B, Ch 7, App 1, as far as applicable.
3
F : Minimum upper yield stress, in N/mm2, of the
In calculating the shear strength, the net thicknesses of
floors and girders are to be used. The net thickness tnet , in material
mm, is given by: 1 : 1 = 1,10
tnet = t tC 2 : 2 = 1,20
2 may be reduced, at the Societys discretion,
where: down to 1,10 where appropriate reinforcements
t : As-built thickness, in mm, of floors and girders are fitted to the Societys satisfaction.
Lower stool
Transverse bulkhead
Girders
Floors
i=n
5 Renewal criteria for side shell frames 5.2.2 The renewal thicknesses for the additional structure
required to meet the ice strengthening notation are to be
and brackets in single side skin bulk
based on the Societys requirements.
carriers and single side skin OBO
carriers not built in accordance with 5.2.3 If the ice class notation is requested to be withdrawn,
Part II, Chapter 8, Section 8-03 of the the additional ice strengthening structure, with the excep-
tion of tripping brackets as required in [5.3.2], item b) and
1st April 1998 edition of the Rules or [5.4.2], is not to be considered to contribute to compliance
subsequent editions with the present Article.
Table 2 : tc values, in mm
2
t REN ,dt =
3
t REN, d t t REN, S
where tREN,S is obtained from [5.5.4].
5.3.3 Thickness criteria based on shear strength
check
Where tM in the lower part of side frames, as defined in Fig
15, is equal to or less than tCOAT , tREN,S is to be determined in
accordance with [5.5.4].
5.3.5 Criteria for other measures 5.3.6 Criteria for frames and brackets (bending
check)
When tREN < tM tCOAT, measures are to be taken, consisting
When lower end brackets were not fitted with flanges at the
of all the following items:
design stage, flanges are to be fitted so as to meet the bend-
a) sand blasting, or equivalent, and coating (refer to ing strength requirements in [5.5.5]. The full width of the
[5.4.1]) bracket flange is to extend up beyond the point at which the
frame flange reaches full width. Adequate back-up structure
b) Fitting tripping brackets (refer to [5.4.2]), when the in the hopper is to be ensured, and the bracket is to be
above condition occurs for any of the side frame zones aligned with the back-up structure.
A, B, C and D, as shown in Fig 15. Tripping brackets not
connected to flanges are to have soft toe, and the dis- Where the length or depth of the lower bracket does not
tance between the bracket toe and the frame flange is meet the requirements in Pt D, Ch 4, Sec 3, [2.2.6], a bend-
not to be greater than about 50 mm, see Fig 16, and ing strength check in accordance with [5.5.5] is to be car-
ried out and renewals or reinforcements of frames and/or
brackets effected as required therein.
c) Maintaining the coating in as-new condition (i.e.
The bending check needs not to be carried out in the case
without breakdown or rusting) at class renewal and
the bracket geometry is modified so as to comply with Pt D,
intermediate surveys.
Ch 4, Sec 3, [2.2.6] requirements.
The above measures may be waived if the structural mem-
bers show no thickness diminution with respect to the as 5.4 Other measures
built thicknesses and coating is in as-new condition (i.e.
without breakdown or rusting). 5.4.1 Thickness measurements, steel renewal, sand
blasting and coating
When the measured frame webs thickness tM is such that
tREN < tM tCOAT and the coating is in GOOD condition, sand
For the purpose of steel renewal, sand blasting and coating,
blasting and coating as required in a) above may be waived
four zones A, B, C and D are defined, as shown in Fig 15.
even if not found in as-new condition, as defined above,
When renewal is to be carried out, surface preparation and
provided that tripping brackets are fitted and the coating
coating are required for the renewed structures as given in
damaged in way of the tripping bracket welding is repaired.
Pt D, Ch 4, Sec 3, [7.1] for cargo holds of new buildings.
Representative thickness measurements are to be taken for
Figure 16 : Tripping brackets
each zone and are to be assessed against the criteria in [5.3].
When zone B is made up of different plate thicknesses, the
lesser thickness is to be used for the application of the
requirements in this Article [5].
Tripping brackets In case of integral brackets, when the criteria in [5.3] are
not satisfied for zone A or B, steel renewal, sand blasting
and coating, as applicable, are to be done for both zones A
and B.
In case of separate brackets, when the criteria in [5.3] are
x not satisfied for zone A or B, steel renewal, sand blasting
and coating is to be done for each one of these zones, as
applicable.
When steel renewal is required for zone C according to
[5.3], it is to be done for both zones B and C. When sand
blasting and coating is required for zone C according to
[5.3], it is to be done for zones B, C and D.
Where, according to the requirements in [5.3], a limited Double continuous welding is to be adopted for the con-
number of side frames and brackets are shown to require nections of tripping brackets to the side shell frames and
coating over part of their length, the following criteria shell plating.
apply:
Where side frames and side shell are made of Higher
a) The part to be coated includes: Strength Steel (HSS), Normal Strength Steel (NSS) tripping
the web and the face plate of the side frames and brackets may be accepted, provided the electrodes used for
brackets, welding are those required for the particular HSS grade, and
the thickness of the tripping brackets is equal to the frame
the hold surface of side shell, hopper tank and top-
web thickness, regardless of the frame web material.
side tank plating, as applicable, over a width not less
than 100 mm from the web of the side frame.
b) Epoxy coating or equivalent is to be applied. 5.4.3 Weld throat thickness
In all cases, all the surfaces to be coated are to be sand In case of steel renewal the welded connections are to com-
blasted prior to coating application. ply with Pt D, Ch 4, Sec 3, [8].
When flanges of frames or brackets are to be renewed
according to the retroactive rule requirements, the outstand- 5.4.4 Pitting and grooving
ing breadth to thickness ratio is to comply with Pt D, Ch 4, If pitting intensity is higher than 15% in area (see Fig 17),
Sec 3, [2.2.4] and Pt D, Ch 4, Sec 3, [2.2.5]. thickness measurement is to be taken to check pitting corro-
sion.
5.4.2 Reinforcing measures
The minimum acceptable remaining thickness in pits or
Reinforcing measures are constituted by tripping brackets,
grooves is equal to:
located at the lower part and at midspan of side frames (see
Fig 16). Tripping brackets may be located at every two 75% of the as built thickness, for pitting or grooving in
frames, but lower and midspan brackets are to be fitted in the frame and brackets webs and flanges
line between alternate pairs of frames.
70% of the as built thickness, for pitting or grooving in
The thickness of the tripping brackets is to be not less than the side shell, hopper tank and topside tank plating
the as-built thickness of the side frame webs to which they attached to the side frame, over a width up to 30 mm
are connected. from each side of it.
5.4.5 Renewal of all frames in one or more cargo Ps : Still water force, in kN.
holds When the upper end of the side frame span
When all frames in one or more holds are required to be h (see Fig 15) is below the load waterline:
renewed according to the retroactive rule requirements, the
p s, u + p s, L
compliance with the applicable requirements of Part II, P s = sh ----------------------
-
2
Chapter 8, Section 8-03 of the first April 1998 edition of the
Rules may be accepted in lieu of the compliance with the When the upper end of the side frame span
retroactive rule requirements, provided that: h (see Fig 15) is at or above the load water-
It is applied at least to all the frames of the hold(s) line:
The coating requirements for side frames of new ships p s, L
P s = sh -------
-
are complied with 2
The section modulus of side frames is calculated P1 : Wave force, in kN, in head sea, given by the
according to the relevant requirements of the Rules. following formula:
p 1, u + p 1, L
P 1 = sh -----------------------
5.4.6 Renewal of damaged frames -
2
In case of renewal of a damaged frame already complying P2 : Wave force, in kN, in beam sea, given by
with this Article [5], the following requirements apply:
the following formula:
The conditions accepted in compliance with this Article
p 2, u + p 2, L
are to be restored as a minimum. P 2 = sh -----------------------
-
2
For localised damages, the extension of the renewal is to
be carried out according to the standard practice of the h : Side frame span, in m, defined in Fig 15
Society. hB : Lower bracket length, in m, defined in Fig 18
h : Distance, in m, between the lower end of
5.5 Strength check criteria side frame span h (see Fig 15) and the load
waterline
5.5.1 In general, loads are to be calculated and strength
s : Frame spacing, in m
checks are to be carried out for the aft, middle and forward
frames of each hold. The scantlings required for frames in pS,U : Still water pressure, in kN/m2, at the upper
intermediate positions are to be obtained by linear interpo- end of the side frame span h (see Fig 15)
lation between the results obtained for the above frames. pS,L : Still water pressure, in kN/m2, at the lower
When scantlings of side frames vary within a hold, the end of the side frame span h (see Fig 15)
required scantlings are also to be calculated for the mid p1,U : Wave pressure, in kN/m2, as defined in item
frame of each group of frames having the same scantlings. b) below, for the upper end of the side frame
The scantlings required for frames in intermediate positions span h and corresponding to force P1
are to be obtained by linear interpolation between the
results obtained for the calculated frames. p1,L : Wave pressure, in kN/m2, as defined in item
b) below, for the lower end of the side frame
5.5.2 Load model span h and corresponding to force P1
p2,U : Wave pressure, in kN/m2, as defined in item
The following loading conditions are to be considered: b) below, for the upper end of the side frame
homogeneous heavy cargo (density > 1.78 t/m3) span h and corresponding to force P2
homogeneous light cargo (density < 1.78 t/m3) p2,L : Wave pressure, in kN/m2, as defined in item
b) below, for the lower end of the side frame
non homogeneous heavy cargo, if allowed.
span h and corresponding to force P2.
Multi port loading/unloading conditions need not be con- b) Wave pressures
sidered.
Wave pressure p1
a) Forces
The wave pressure p1, in kN/m2, at and below the
The forces Pfr,a and Pfr,b , in kN, to be considered for the waterline is given by:
strength checks at sections a) and b) of side frames
B
(shown in Fig 18, in the case of separate lower brackets, p 1 = 1, 50 p 11 + 135 ------------------------- ( 1, 2 ( T z ) )
section b) is at the top of the lower bracket), are given 2 ( B + 75 )
by: where:
Pfr,a = PS + max (P1, P2) P11 = 3 ks C + kf
h 2h The wave pressure p1, in kN/m2, above the waterline
P fr, b = P fr, a ------------------b
h is given by:
where: p1 = p1wl 7,50 (z T)
where ReH is the minimum yield stress, in N/mm2, of the 1000P fr, a h
Z a = --------------------------
-
material. ma a
Where tM in the lower part of side frames, as defined in Fig 1000P fr, a h
Z b = --------------------------
-
15, is equal to or less than tCOAT, shear strength check is to mb a
be carried out in accordance with the following.
where:
The thickness tREN,S, in mm, is the greater of the thicknesses
tREN,Sa and tREN,Sb obtained from the shear strength check at Pfr,a : Pressure force defined in [5.5.2], item a)
sections a) and b) (see Fig 18 and [5.5.2]) given by the fol-
lowing, but need not be taken greater than 0,75 tS12. h : Side frame span, in m, as defined in Fig 15
kS : Shear force distribution factor, to be taken equal tREN for the web thickness
to 0,6
the minimum thicknesses allowed by the Society
Pfr,a, Pfr,b : Pressure forces defined in [5.5.2], item a) renewal criteria for flange and attached plating.
da : Bracket web depth, in mm, at section a) (see Fig The attached plate breadth is equal to the frame spacing,
18) measured along the shell at midspan of h.
db : Frame web depth, in mm, at section b) (see Fig If the actual section moduli at sections a) and b) are less
18). In case of separate brackets, db is to be than the values Za and Zb , the frames and brackets are to be
taken as the minimum web depth deducing
renewed or reinforced in order to obtain actual section
possible scallops
moduli not less than 1,2 Za and 1,2 Zb , respectively.
: Angle between frame web and shell plate
In such a case, renewal or reinforcements of the flange are
a : Allowable shear stress, in N/mm2, defined in to be extended over the lower part of side frames, as
[5.5.3]. defined in Fig 15.
mb
ma
hB 0,08 h hB = 0,10 h hB 0,125 h
Empty holds of ships approved to operate in
10 17 19 22
non homogeneous loading conditions
Other cases 12 20 22 26
Note 1: Non homogeneous loading condition means a loading condition in which the ratio between the highest and the lowest fill-
ing ratio, evaluated for each hold, exceeds 1,20 corrected for different cargo densities.
Note 2: For intermediate values of the bracket length hB, the coefficient mb is obtained by linear interpolation between the Table values.
6 Cargo hatch cover securing c) Between cover and coaming and at cross-joints, a pack-
ing line pressure sufficient to obtain weathertightness is
arrangements for bulk carriers not to be maintained by the securing devices.
built in accordance with Pt B, Ch 9,
For packing line pressures exceeding 5 N/mm, the net
Sec 7
cross area A is to be increased in direct proportion. The
packing line pressure is to be specified.
6.1 Application
d) The hatch cover edge stiffness is to be sufficient to main-
6.1.1 These retroactive rule requirements apply to ships tain adequate sealing pressure between securing
which are assigned one of the following service notations: devices.
6.2.1 The strength of securing devices is to comply with the g) Where hydraulic cleating is adopted, a positive means is
following items: to be provided to ensure that it remains mechanically
locked in the closed position in the event of failure of
a) Panel hatch covers are to be secured by appropriate
the hydraulic system.
devices (bolts, wedges or similar) suitably spaced along-
side the coamings and between cover elements.
Arrangement and spacing are to be determined with 6.3 Stoppers
due attention to the effectiveness for weather-tightness,
depending upon the type and the size of the hatch 6.3.1 No.1 and No.2 hatch covers are to be effectively
cover, as well as on the stiffness of the cover edges secured, by means of stoppers, against the transverse forces
between the securing devices. arising from a pressure of 175 kN/m2.
Part B
Hull and Stability
Chapters 1 2 3 4 5 6 7 8 9 10 11
Chapter 1 GENERAL
Chapter 2 GENERAL ARRANGEMENT DESIGN
Chapter 3 STABILITY
Chapter 4 STRUCTURE DESIGN PRINCIPLES
Chapter 5 DESIGN LOADS
Chapter 6 HULL GIRDER STRENGTH
Chapter 7 HULL SCANTLINGS
Chapter 8 OTHER STRUCTURES
Chapter 9 HULL OUTFITTING
Chapter 10 CORROSION PROTECTION AND LOADING INFORMATION
Chapter 11 CONSTRUCTION AND TESTING
Section 1 Application
1 General 17
1.1 Structural requirements
1.2 Limits of application to lifting appliances
2 Rule application 17
2.1 Ship parts
2.2 Rules applicable to various ship parts
2.3 Rules applicable to other ship items
3 Rounding off of scantlings 18
3.1
Section 1 General
1 General 43
1.1 Application
1.2 Application to ships having additional service feature SPxxx
1.3 Application to ships performing lifting operations at sea
2 Examination procedure 43
2.1 Documents to be submitted
2.2 Inclining test/lightweight check
Section 1 Materials
1 General 77
1.1 Characteristics of materials
1.2 Testing of materials
1.3 Manufacturing processes
2 Steels for hull structure 77
2.1 Application
2.2 Information to be kept on board
2.3 Material factor k
2.4 Grades of steel
2.5 Grades of steel for structures exposed to low air temperatures
2.6 Grades of steel within refrigerated spaces
2.7 Through thickness properties
3 Steels for forging and casting 83
3.1 General
3.2 Steels for forging
3.3 Steels for casting
4 Aluminium alloy structures 83
4.1 General
4.2 Extruded plating
4.3 Mechanical properties of weld joints
4.4 Material factor k
5 Other materials and products 84
5.1 General
5.2 Iron cast parts
Chapter 1
GENERAL
SECTION 1 APPLICATION
SECTION 1 APPLICATION
1.1.1 Part B of the Rules contains the requirements for 1.2 Limits of application to lifting
determination of the minimum hull scantlings, applicable to
appliances
all types of seagoing monohull displacement ships of nor-
mal form, speed and proportions, made in welded steel
construction, excluding ships covered by NR600 Hull 1.2.1 The fixed parts of lifting appliances, considered as an
Structure and Arrangement for the Classification of Cargo integral part of the hull, are the structures permanently con-
Ships less than 65 m and Non Cargo Ships less than 90 m. nected by welding to the ships hull (for instance crane ped-
estals, masts, king posts, derrick heel seatings, etc.,
These requirements are to be integrated with those specified excluding cranes, derrick booms, ropes, rigging accessories,
in Part D, for any individual ship type, and in Part E, as and, generally, any dismountable parts). The shrouds of
applicable, depending on the additional class notations masts embedded in the ships structure are considered as
assigned to the ships. fixed parts.
fore part
1.1.2 The requirements of Part B, Part D and Part E apply
also to those steel ships in which parts of the hull, e.g. central part
superstructures or movable decks, are built in aluminium aft part.
alloys.
2.1.2 Fore part
1.1.3 Ships whose hull materials are different than those
given in [1.1.2] and ships with novel features or unusual The fore part includes the structures located forward of the
hull design are to be individually considered by the Society, collision bulkhead, i.e.:
on the basis of the principles and criteria adopted in the the fore peak structures
Rules.
the stems.
1.1.4 The strength of ships constructed and maintained
according to the Rules is sufficient for the draught corre- In addition, it includes:
sponding to the assigned freeboard. The scantling draught the reinforcements of the flat bottom forward area
considered when applying the Rules is to be not less than
that corresponding to the assigned freeboard. the reinforcements of the bow flare area.
2.1.3 Central part Table 2 : Part B Chapters and Sections applicable for
The central part includes the structures located between the the scantling of other items
collision bulkhead and the after peak bulkhead.
Applicable
Where the flat bottom forward area or the bow flare area Item
Chapters and Sections
extend aft of the collision bulkhead, they are considered as
Machinery space Ch 8, Sec 3
belonging to the fore part.
Superstructures and deckhouses Ch 8, Sec 4
2.1.4 Aft part Bow doors and inner doors Ch 8, Sec 5
The aft part includes the structures located aft of the after
Side shell doors and stern doors Ch 8, Sec 6
peak bulkhead.
Large hatch covers Ch 8, Sec 7
2.2 Rules applicable to various ship parts Small hatches Ch 8, Sec 8
Movable decks and inner ramp Ch 8, Sec 9
2.2.1 The various Chapters and Sections of Part B are to be
External ramps
applied for the scantling and arrangement of ship parts
according to Tab 1. Arrangement of hull and super- Ch 8, Sec 10
structures openings
Table 1 : Part B Chapters and Sections applicable for Helicopter decks Ch 8, Sec 11
the scantling of ship parts
Rudders Ch 9, Sec 1
Applicable Chapters and Other hull outfitting Ch 9, Sec 2
Part
Sections Ch 9, Sec 3
All parts Part B, Chapter 1 Ch 9, Sec 4
Part B, Chapter 2
Part B, Chapter 3 3 Rounding off of scantlings
Part B, Chapter 4
Part B, Chapter 5 3.1
Part B, Chapter 6
Part B, Chapter 8 (1), excluding: 3.1.1 Plate thicknesses
Ch 8, Sec 1 The rounding off of plate thicknesses is to be obtained from
Ch 8, Sec 2 the following procedure:
Part B, Chapter 10 a) the net thickness (see Ch 4, Sec 2) is calculated in
Part B, Chapter 11 accordance with the rule requirements.
Specific Fore part Ch 8, Sec 1 b) corrosion addition tC (see Ch 4, Sec 2) is added to the
parts
Central part Part B, Chapter 7
calculated net thickness, and this gross thickness is
rounded off to the nearest half-millimetre.
Aft part Ch 8, Sec 2
c) the rounded net thickness is taken equal to the rounded
(1) See also [2.3]. gross thickness, obtained in b), minus the corrosion
addition tC.
2.3 Rules applicable to other ship items
3.1.2 Stiffener section moduli
2.3.1 The various Chapters and Sections of Part B are to be Stiffener section moduli as calculated in accordance with
applied for the scantling and arrangement of other ship the rule requirements are to be rounded off to the nearest
items according to Tab 2. standard value; however, no reduction may exceed 3%.
1 Units 3 Definitions
2 Symbols
2.1
2.1.1
L : Rule length, in m, defined in [3.1]
L1 : L, but to be taken not greater than 200 m 3.2 Load line length
L2 : L, but to be taken not greater than 120 m
LLL : Load line length, in m, defined in [3.2] 3.2.1 The load line length LLL is the distance, in m, on the
waterline at 85% of the least moulded depth from the top
LS : Subdivision length, in m, defined in [3.3]
of the keel, measured from the forward side of the stem to
B : Moulded breadth, in m, defined in [3.4] the centre of the rudder stock. LLL is to be not less than 96%
D : Depth, in m, defined in [3.5] of the total length on the same waterline.
T : Moulded draught, in m, defined in [3.7]
: Moulded displacement, in tonnes, at draught T, 3.2.2 Where the stem contour is concave above the water-
in sea water (density = 1,025 t/m3) line at 85% of the least moulded depth, both the forward
CB : Total block coefficient: terminal of the total length and the fore-side of the stem
respectively is taken at the vertical projection to that water-
C B = -------------------------- line of the aftermost point of the stem contour (see Fig 2).
1 ,025 LBT
3.8 Lightweight
Dmin WL at 0,85 Dmin
3.8.1 The lightweight is the displacement, in t, without
cargo, fuel, lubricating oil, ballast water, fresh water and
LLL/2 LLL/2 F P feed water, consumable stores and passengers and crew
A P
and their effects, but including liquids in piping.
3.5 Depth 3.11.1 The bulkhead deck in a passenger ship means the
uppermost deck at any point in the subdivision length LS to
3.5.1 The depth D is the distance, in m, measured verti- which the main bulkheads and the ships shell are carried
cally on the midship transverse section, from the moulded watertight. In a cargo ship the freeboard deck may be taken
base line to the top of the deck beam at side on the upper- as the bulkhead deck.
most continuous deck.
In the case of a ship with a solid bar keel, the moulded base 3.12 Inner side
line is to be taken at the intersection between the upper
face of the bottom plating with the solid bar keel at the mid- 3.12.1 The inner side is the longitudinal bulkhead which
dle of length L. limits the inner hull for ships fitted with double hull.
3.22.2 Position 2
Position 2 includes: X
exposed superstructure decks situated aft of 0,25 L from
the perpendicular, at the forward side of the stem, to the
waterline at 85% of the least moulded depth measured
from the top of the keel and located at least one stand- Y
ard height of superstructure above the freeboard deck,
exposed superstructure decks situated forward of
0,25 LLL from the perpendicular, at the forward side of
the stem, to the waterline at 85% of the least moulded
depth measured from the top of the keel and located at
AE
least two standard heights of superstructure above the
freeboard deck.
Table 1 : Plans and documents to be submitted for approval for all ships
Chapter 2
1.1.2 Ships having additional service feature SPxxx with 145 L < 165 7 8
xxx less than 240 are to comply with the requirements of 165 L < 190 8 9
this Section, unless otherwise specified, considering the
L 190 to be defined on a case by case basis
special personnel as crew.
(1) After peak bulkhead and aft machinery bulkhead are
the same.
2 Number and arrangement of
transverse watertight bulkheads 3 Collision bulkhead
3.1
2.1 Number of watertight bulkheads
3.1.1 A collision bulkhead is to be fitted which is to be
2.1.1 General watertight up to the bulkhead deck. This bulkhead is to be
All ships, in addition to complying with the requirements of located at a distance from the forward perpendicular FPLL of
[2.1.2], are to have at least the following transverse water- not less than 5 per cent of the length LLL of the ship or 10 m,
tight bulkheads: whichever is the less, and, except as may be permitted by
the Society, not more than 8 per cent of LLL or 5 per cent of
one collision bulkhead the LLL + 3 m, whichever is the greater.
one after peak bulkhead for passenger ships and ro-ro For ships not covered by the SOLAS Convention, the length
passenger ships LLL need not be taken less than 50 m, unless required by the
National Authorities.
two bulkheads forming the boundaries of the machinery
space in ships with machinery amidships, and a bulk- 3.1.2 Where any part of the ship below the waterline
head forward of the machinery space in ships with extends forward of the forward perpendicular, e.g. a bul-
machinery aft. In the case of ships with an electrical pro- bous bow, the distances, in metres, stipulated in [3.1.1] are
pulsion plant, both the generator room and the engine to be measured from a point either:
room are to be enclosed by watertight bulkheads.
at the mid-length of such extension, or
at a distance 1,5 per cent of the length LLL of the ship
2.1.2 Additional bulkheads
forward of the forward perpendicular, or
For ships not required to comply with subdivision regula- at a distance 3 metres forward of the forward perpen-
tions, transverse bulkheads adequately spaced and in gen- dicular; whichever gives the smallest measurement.
eral not less in number than indicated in Tab 1 are to be
fitted. 3.1.3 The bulkhead may have steps or recesses provided
they are within the limits prescribed in [3.1.1] or [3.1.2].
Additional bulkheads may be required for ships having to
comply with subdivision or damage stability criteria (see No door, manhole, ventilation duct or any other opening is
Part D for the different types of ships). to be fitted in the collision bulkhead below the bulkhead
deck.
2.2 Water ingress detection 3.1.4 At Owner request and subject to the agreement of the
flag Administration, the Society may, on a case by case
2.2.1 A water ingress detection system is to be fitted basis, accept a distance from the collision bulkhead to the
according to Pt C, Ch 1, Sec 10, [6.12]. forward perpendicular FPLL greater than the maximum spe-
cified in [3.1.1] and [3.1.2], provided that subdivision and For ships less than 65 m, where the after peak bulkhead in
stability calculations show that, when the ship is in upright way of the sterntube stuffing box is not provided, sterntubes
condition on full load summer waterline, flooding of the are to be enclosed in watertight spaces of moderate volume.
space forward of the collision bulkhead will not result in
any part of the freeboard deck becoming submerged, or in 5 Height of transverse watertight
any unacceptable loss of stability.
bulkheads other than collision
In such a case, the attention of the Owner and the Shipyard
is drawn to the fact that the flag Administration may impose bulkhead and after peak bulkhead
additional requirements and that such an arrangement is, in
principle, officialized by the issuance of a certificate of 5.1
exemption under the SOLAS Convention provisions. More-
over, in case of change of flag, the taking Administration 5.1.1 Transverse watertight bulkheads are to extend water-
may not accept the exemption. tight up to the bulkhead deck. In exceptional cases at the
request of the Owner, the Society may allow transverse
3.1.5 Where a long forward superstructure is fitted, the col- watertight bulkheads to terminate at a deck below that from
lision bulkhead is to be extended weathertight to the next which freeboard is measured, provided that this deck is at
deck above the bulkhead deck. The extension need not be an adequate distance above the full load waterline.
fitted directly above the bulkhead below provided it is
located within the limits prescribed in [3.1.1] or [3.1.2] with 5.1.2 Where it is not practicable to arrange a watertight
the exemption permitted by [3.1.6] and the part of the deck bulkhead in one plane, a stepped bulkhead may be fitted. In
which forms the step is made effectively weathertight. this case, the part of the deck which forms the step is to be
watertight and equivalent in strength to the bulkhead.
3.1.6 Where bow doors are fitted and a sloping loading
ramp forms part of the extension of the collision bulkhead 6 Openings in watertight bulkheads
above the freeboard deck, the part of the ramp which is and decks for ships having a service
more than 2,3 m above the freeboard deck may extend for-
ward of the limit specified in [3.1.1] or [3.1.2] The ramp is to
notation other than passenger ship
be weathertight over its complete length. or ro-ro passenger ship
3.1.7 The number of openings in the extension of the colli- 6.1 Application
sion bulkhead above the freeboard deck is to be restricted
to the minimum compatible with the design and normal 6.1.1 The requirements in [6.2] and [6.3] apply to ships
operation of the ship. All such openings are to be capable of having a service notation other than passenger ship or ro-ro
being closed weathertight. passenger ship.
Openings in watertight bulkheads below the bulkhead deck
for ships with service notation passenger ship or ro-ro pas-
4 After peak, machinery space senger ship are to comply with Part D, Chapter 11 or Part
bulkheads and stern tubes D, Chapter 12, respectively.
4.1 6.1.2 The requirements in [6.2] and [6.3] are not applica-
ble to ships having additional service feature SPxxx with
4.1.1 General xxx less than 240.
Bulkheads are to be fitted separating the machinery space Openings in watertight bulkheads below the bulkhead deck
from the cargo and accommodation spaces forward and aft for ships with additional service feature SPxxx with xxx less
and made watertight up to the bulkhead deck. In passenger than 240 are to comply with Part D, Chapter 11.
ships, an after peak bulkhead is also to be fitted and made
watertight up to the bulkhead deck. The after peak bulk- 6.2 General
head may, however, be stepped below the bulkhead deck,
provided the degree of safety of the ship as regards subdivi- 6.2.1 The number of openings in watertight subdivisions is
sion is not thereby diminished. to be kept to a minimum compatible with the design and
proper working of the ship. Where penetrations of water-
4.1.2 Sterntubes tight bulkheads and internal decks are necessary for access,
In all cases, sterntubes are to be enclosed in watertight piping, ventilation, electrical cables, etc., arrangements are
spaces of moderate volume. In passenger ships, the stern to be made to maintain the watertight integrity. The Society
gland is to be situated in a watertight shaft tunnel or other may permit relaxation in the watertightness of openings
watertight space separate from the sterntube compartment above the freeboard deck, provided that it is demonstrated
and of such volume that, if flooded by leakage through the that any progressive flooding can be easily controlled and
stern gland, the bulkhead deck will not be immersed. In that the safety of the ship is not impaired.
cargo ships, other measures to minimise the danger of water
penetrating into the ship in case of damage to sterntube 6.2.2 No door, manhole ventilation duct or any other
arrangements may be taken at the discretion of the Society. opening is permitted in the collision bulkhead below the
subdivision deck.
6.2.3 Lead or other heat sensitive materials may not be 6.3.2 Openings normally closed at sea
used in systems which penetrate watertight subdivision Access doors and access hatch covers normally closed at
bulkheads, where deterioration of such systems in the event sea, intended to ensure the watertight integrity of internal
of fire would impair the watertight integrity of the bulk- openings, are to be provided with means of indication
heads. locally and on the bridge showing whether these doors or
hatch covers are open or closed. A notice is to be affixed to
6.2.4 Valves not forming part of a piping system are not each such door or hatch cover to the effect that it is not to
permitted in watertight subdivision bulkheads. be left open.
6.2.5 The requirements relevant to the degree of tightness, 6.3.3 Doors or ramps in large cargo spaces
as well as the operating systems, for doors or other closing
Watertight doors or ramps of satisfactory construction may
appliances complying with the provisions in [6.3] are spec-
be fitted to internally subdivide large cargo spaces, pro-
ified in Tab 2.
vided that the Society is satisfied that such doors or ramps
are essential. These doors or ramps may be hinged, rolling
6.3 Openings in the watertight bulkheads or sliding doors or ramps, but are not to be remotely con-
and internal decks trolled. Such doors are to be closed before the voyage com-
mences and are to be kept closed during navigation. Should
6.3.1 Openings used while at sea any of the doors or ramps be accessible during the voyage,
Doors provided to ensure the watertight integrity of internal they are to be fitted with a device which prevents unauthor-
openings which are used while at sea are to be sliding ised opening.
watertight doors capable of being remotely closed from the The word satisfactory means that scantlings and sealing
bridge and are also to be operable locally from each side of requirements for such doors or ramps are to be sufficient to
the bulkhead. Indicators are to be provided at the control withstand the maximum head of the water at the flooded
position showing whether the doors are open or closed, and waterline.
an audible alarm is to be provided at the door closure. The
power, control and indicators are to be operable in the 6.3.4 Openings permanently kept closed at sea
event of main power failure. Particular attention is to be Other closing appliances which are kept permanently
paid to minimise the effect of control system failure. Each closed at sea to ensure the watertight integrity of internal
power-operated sliding watertight door is to be provided openings are to be provided with a notice which is to be
with an individual hand-operated mechanism. The possibil- affixed to each such closing appliance to the effect that it is
ity of opening and closing the door by hand at the door to be kept closed. Manholes fitted with closely bolted cov-
itself from both sides is to be assured. ers need not be so marked.
Table 2 : Doors
protection equivalent to that afforded by a double bottom Cwf : Waterplane area coefficient forward of LLL/2:
complying with [3.1]. In no case, the vertical distance from
the bottom of such a well to a plane coinciding with the A wf
C wf = ----------
-
keel line is to be less than 500 mm. L LL
------- B
2
3.1.4 A double bottom need not be fitted in way of water- Awf : Waterplane area forward of LLL/2 at draught T1,
tight tanks, including dry tanks of moderate size, provided in m2.
the safety of the ship is not impaired in the event of bottom
or side damage as defined in Ch 3, Sec 3, [3.4]. For ships to which timber freeboards are assigned, the sum-
mer freeboard (and not the timber summer freeboard) is to
be assumed when applying the formula above.
3.1.5 Any part of a ship that is not fitted with a double bot-
tom in accordance with [3.1.1] or [3.1.4] is to be capable of
withstanding bottom damages, as specified in Ch 3, Sec 3, 5.1.2 Where the bow height required in [5.1.1] is obtained
[3.4], in that part of the ship. by sheer, the sheer is to extend for at least 15% of LLL of the
ship measured from the forward perpendicular. Where it is
obtained by fitting a superstructure, such superstructure is
3.1.6 In the case of unusual bottom arrangements, it is to to extend from the stem to a point at least 0,07LLL abaft the
be demonstrated that the ship is capable of withstanding forward perpendicular and is to be enclosed as defined in
bottom damages as specified in Ch 3, Sec 3, [3.4]. Ch 8, Sec 4.
3.1.7 Special requirements for passenger ships and tankers 5.1.3 Ships which, to suit exceptional operational require-
are specified in Part D. ments, cannot meet the requirements in [5.1.1] and [5.1.2]
will be considered by the Society on a case by case basis.
Figure 1 : Credited bow height where the freeboard deck has sheer extending from abaft 0,15 L
Figure 2 : Credited bow height where the freeboard deck has sheer extending for less than 0,15 L
5.1.6 All ships assigned a type B freeboard, other than oil F0 : Tabular freeboard, in mm, taken from the Inter-
tankers, chemical tankers and gas carriers, are to have addi- national Convention on Load Lines, as
tional reserve buoyancy in the fore end. Within the range of amended, Table 28.2, corrected for regulation
0,15LLL abaft of the forward perpendicular, the sum of the 27(9) or 27(10), as applicable
projected area between the summer load waterline and the
deck at side (A1 and A2 in Fig 3) and the projected area of f1 : Correction for block coefficient given in the
an enclosed superstructure, if fitted, is, in m2, to be not less International Convention on Load Lines, as
than: amended, regulation 30
A3 = (0,15 Fmin + 4 (LLL/3 + 10)) LLL/1000 f2 : Correction for depth, in mm, given in the Inter-
national Convention on Load Lines, as
where:
amended, regulation 31.
Fmin : Fmin = (F0 f1) + f2
6.1 General 8.1.3 Fuel oil tanks may not be located where spillage or
leakage therefrom can constitute a hazard by falling on
6.1.1 Shaft tunnels are to be watertight. heated surfaces.
See also Ch 8, Sec 2. Precautions are to be taken to prevent any oil that may
escape under pressure from any pump, filter or heater from
7 Watertight ventilators and trunks coming into contact with heated surfaces.
Fuel oil tanks in boiler spaces may not be located immedi-
7.1 General ately above the boilers or in areas subjected to high temper-
atures, unless special arrangements are provided in
7.1.1 Watertight ventilators and trunks are to be carried at agreement with the Society.
least up to the bulkhead deck in passenger ships and up to
the freeboard deck in ships other than passenger ships. 8.1.4 Where a compartment intended for goods or coal is
situated in proximity of a heated liquid container, suitable
8 Fuel oil tanks thermal insulation is to be provided.
8.1.1 The arrangements for the storage, distribution and 8.2.1 All ships with an aggregate oil fuel capacity of
utilisation of the fuel oil are to be such as to ensure the 600 m3 are to comply with the requirements of the Regula-
safety of the ship and persons on board. tion 12 A of Annex I to Marpol Convention, as amended.
1 General bulk carrier CSR BC-C ESP, ore carrier ESP, combination
carrier ESP, of 20,000 gross tonnage and over, and to ships
with service notation oil tanker ESP of 500 gross tonnage
1.1 and over. For such ships, refer to the applicable requirements
of Part D.
1.1.1 The number and size of small hatchways for trimming
and access openings to tanks or other enclosed spaces, are 3.1.2 The requirements in [3.2] to [3.4] are not applicable
to be kept to the minimum consistent with access and main- to spaces in double bottom and double side tanks.
tenance of the space.
2.2.1 Manholes are to be provided in floors and girders so 3.2.4 Tanks subdivided by wash bulkheads
as to provide convenient access to all parts of the double When a tank is subdivided by one or more wash bulkheads,
bottom. at least two hatchways are to be fitted, and these hatchways
are to be so located that the associated ladders effectively
2.2.2 The size of manholes and lightening holes in floors serve all subdivisions of the tank.
and girders is, in general, to be less than 50 per cent of the
local height of the double bottom.
3.3 Access within tanks
Where manholes of greater sizes are needed, edge rein-
forcement by means of flat bar rings or other suitable stiffen- 3.3.1 Wash bulkheads in tanks
ers may be required.
Where one or more wash bulkheads are fitted in a tank,
2.2.3 Manholes may not be cut into the continuous cen- they are to be provided with openings not less than 600 x
treline girder or floors and girders below pillars, except 800 mm and so arranged as to facilitate the access of per-
where allowed by the Society on a case by case basis. sons wearing breathing apparatus or carrying a stretcher
with a patient.
3.4.2 Construction
5.1.2 Suitable arrangements to ensure working access to
Ladders and handrails are to be constructed of steel of ade- steering gear machinery and controls are to be provided.
quate strength and stiffness and securely attached to the
tank structure by stays. The method of support and length These arrangements are to include handrails and gratings or
of stay are to be such that vibration is reduced to a practical other non-slip surfaces to ensure suitable working condi-
minimum. tions in the event of hydraulic fluid leakage.
Chapter 3
STABILITY
SECTION 1 GENERAL
SECTION 1 GENERAL
1.2.1 If used, permanent ballast is to be located in accord- 2.1.4 Angle of maximum righting lever
ance with a plan approved by the Society and in a manner The maximum righting arm is to occur at an angle of heel
that prevents shifting of position. Permanent ballast is not to preferably exceeding 30 but not less than 25.
be removed from the ship or relocated within the ship with-
When the righting lever curve has a shape with two maxi-
out the approval of the Society. Permanent ballast particu-
mums, the first is to be located at a heel angle not less than
lars are to be noted in the ships stability booklet.
25.
In cases of ships with a particular design and subject to the Figure 1 : Severe wind and rolling
prior agreement of the flag Administration, the Society may
accept an angle of heel max less than 25 but in no case less
than 15, provided that the area A below the righting lever
curve up to the angle of max is not less than the value
obtained, in m.rad, from the following formula:
A = 0,055 + 0,001 (30 max)
where max is the angle of heel in degrees at which the right-
ing lever curve reaches its maximum.
2.1.5 Initial metacentric height
The initial metacentric height GM0 is not to be less than
0,15 m.
the ship is subjected to a steady wind pressure acting P : 504 N/m2 for unrestricted navigation notation.
perpendicular to the ship's centreline which results in a The value of P used for ships with restricted nav-
steady wind heeling lever (w1) igation notation may be reduced subject to the
approval of the Society
from the resultant angle of equilibrium (0), the ship is
A : Projected lateral area in m2, of the portion of the
assumed to roll owing to wave action to an angle of roll
ship and deck cargo above the waterline
(1) to windward
Z : Vertical distance in m, from the centre of A to
the ship is then subjected to a gust wind pressure which
the centre of the underwater lateral area or
results in a gust wind heeling lever (w2)
approximately to a point at one half the draught
free surface effects, as described in [4], are to be
: Displacement in t
accounted for in the standard conditions of loading as
set out in Ch 3, App 2, [1.2]. g = 9,81 m/s2.
3.2.5 Tab 1 to Tab 4 and formulae described in [3.2.4] are tanks with variable filling level (e.g. consumable liquids
based on data from ships having: such as fuel oil, diesel oil, and fresh water, and also liq-
uid cargo and water ballast during liquid transfer opera-
B/T1 smaller than 3,5 tions). Except as permitted in [4.5.1] and [4.6.1], the free
(KG/T11) between 0,3 and 0,5 surface correction is to be the maximum value attaina-
ble among the filling limits envisaged for each tank, con-
TR smaller than 20 s.
sistent with any operating instructions.
For ships with parameters outside of the above limits the
angle of roll (1) may be determined with model experi- 4.4 Consumable liquids
ments of a subject ship with the procedure described in
IMO MSC.1/Circ. 1200 as the alternative. In addition, the 4.4.1 In calculating the free surfaces effect in tanks contain-
Society may accept such alternative determinations for any ing consumable liquids, it is to be assumed that for each
ship, if deemed appropriate. type of liquid at least one transverse pair or a single cen-
treline tank has a free surface and the tank or combination
3.2.6 Alternative means for determining the wind heeling of tanks taken into account are to be those where the effect
lever (W1) may be accepted, to the satisfaction of the Soci- of free surface is the greatest.
ety as an equivalent to the calculation in [3.2.3]. When such
alternative tests are carried out, reference shall be made
based on the Interim Guidelines for alternative assessment
4.5 Water ballast tanks
of the weather criterion (IMO MSC.1/Circ.1200). the wind
4.5.1 Where water ballast tanks, including anti-rolling tanks
velocity used in the tests shall be 26 m/s in full scale with
and anti-heeling tanks, are to be filled or discharged during
uniform velocity profile. the value of wind velocity used for
the course of a voyage, the free surfaces effect is to be cal-
ships in restricted services may be reduced to the satisfac-
culated to take account of the most onerous transitory stage
tion of the Society.
relating to such operations.
4.8.1 Small tanks which satisfy the following condition 5.3.1 For ships loaded with timber deck cargoes and pro-
using the values of k corresponding to an angle of inclina- vided that the cargo extends longitudinally between super-
tion of 30 need not be included in the correction: structures (where there is no limiting superstructure at the
after end, the timber deck cargo is to extend at least to the
M fs min < 0 ,01 m
after end of the aftermost hatchway) and transversely for
where: the full beam of ship after due allowance for a rounded gun-
wale not exceeding 4% of the breadth of the ship and/or
min : Minimum ship displacement, in t, calculated at securing the supporting uprights and which remains
dmin securely fixed at large angles of heel, the Society may apply
dmin : Minimum mean service draught, in m, of ship the criteria given in [5.3.2] to [5.3.5], which substitute
without cargo, with 10% stores and minimum those given in [2.1.2], [2.1.3], [2.1.4] and [2.1.5] and in
water ballast, if required. [3.2].
5.3.2 The area under the righting lever curve (GZ curve) is
4.9 Remainder of liquid
to be not less than 0,08 m.rad up to = 40 or the angle of
flooding if this angle is less than 40.
4.9.1 The usual remainder of liquids in the empty tanks
need not be taken into account in calculating the correc-
tions, providing the total of such residual liquids does not 5.3.3 The maximum value of the righting lever (GZ) is to be
constitute a significant free surface effect. at least 0,25 m.
5.7.3 Excessive initial stability is to be avoided as it will 6.4 Guidance relating to ice accretion
result in rapid and violent motion in heavy seas which will
6.4.1 The following icing areas are to be considered:
impose large sliding and racking forces on the cargo causing
high stresses on the lashings. Unless otherwise stated in the a) the area north of latitude 6530'N, between longitude
stability booklet, the metacentric height is generally not to 28W and the west coast of Iceland; north of the north
exceed 3% of the breadth in order to prevent excessive coast of Iceland; north of the rhumb line running from
acceleration in rolling provided that the relevant stability cri- latitude 66N, longitude 15W to latitude 7330'N, lon-
teria given in [5.3] are satisfied. gitude 15E, north of latitude 7330'N between longi-
tude 15E and 35E, and east of longitude 35E, as well
as north of latitude 56N in the Baltic Sea
5.8 Stowage of timber deck cargoes
b) the area north of latitude 43N bounded in the west by
5.8.1 The stowage of timber deck cargoes is to comply with the North American coast and the east by the rhumb
the provisions of chapter 3 of the Code of Safe Practice for line running from latitude 43N, longitude 48W to lati-
Ships Carrying Timber Deck Cargoes, 1991 (resolution tude 63N, longitude 28W and thence along longitude
A.715(17)). 28W
c) all sea areas north of the North American Continent, within the areas defined in a), c), d) and e) of [6.4.1]
west of the areas defined in a) and b) known to having icing conditions significantly different
from those described in [6.3], ice accretion require-
d) the Bering and Okhotsk Seas and the Tartary Strait dur- ments of one half to twice the required allowance may
ing the icing season, and be applied
e) south of latitude 60S. within the area defined in b), where ice accretion in
excess of twice the allowance required by [6.3] may be
expected, more severe requirements than those given in
6.4.2 For ships operating where ice accretion may be
[6.3] may be applied.
expected:
1.1.1 Damage stability calculation is required for ships The consequence of such standard of damage is the crea-
which have been requested to receive SDS additional class tion of a group of damage cases, the number of which, as
notation. well as the number of compartments involved in each case,
depend on the ships dimensions and internal subdivision.
1.2 Ships having additional class notation For each loading condition, each damage case is to be con-
sidered, and the applicable criteria are to be complied with.
SDS and additional service feature
SPxxx Different deterministic methods in damage stability have
been developed depending on ship type, on freeboard
1.2.1 Ships having additional class notation SDS and addi- reduction, and on the kind of cargo carried.
tional service feature SPxxx are to comply, in addition to the The deterministic methods to be applied for passenger ships,
applicable requirements of this Section, with the require- oil tankers, chemical tankers, gas carriers and special pur-
ments of Pt D, Ch 11, Sec 3, [1.3], considering the special pose ships are reported in the relevant chapters of Part D.
personnel as passengers, where the attained subdivision
index A (defined in Pt D, Ch 11, Sec 3, [1.3.3]) is not to be The deterministic methods to be applied in the case of free-
less than: board reduction are specified in Ch 3, App 4.
R, where the ship is carrying 240 persons or more, 2.1.3 Probabilistic approach
0.8 R, where the ship is carrying not more than 60 per- The probabilistic concept takes the probability of survival
sons, after collision as a measure of ship safety in the damaged
condition, referred to as the attained subdivision index A.
R value to be calculated by linear interpolation between
0.8 R and R, where the ship is carrying more than 60 The damage stability calculations are performed for a lim-
(but not more than 240) persons. ited number of draughts and relevant GM values in order to
draw a minimum GM curve where the attained subdivision
1.2.2 However, for ships having additional class notation index A achieves the minimum required level of safety R.
SDS and additional service feature SPxxx with xxx less than For cargo ships, each case of damage is not required to
240 persons, Pt D, Ch 11, Sec 3, [1.3.12] is not applicable. comply with the applicable criteria, but the attained index
A, which is the sum of the contribution of all damage cases,
is to be equal to or greater than R.
2 General
The probabilistic method developed on the basis of the
above-mentioned concepts is detailed in Ch 3, App 3.
2.1 Approaches to be followed for damage
As a general rule, the probabilistic method applies to cargo
stability investigation
ships of a length not less than 80 m, and for which no deter-
ministic methods apply; the application of the probabilistic
2.1.1 General damage stability investigation is specified in the relevant
Damage stability calculations are required in order to assess chapters of Part D.
the attitude and stability of the ship after flooding.
In order to assess the behaviour of the ship after damage, 3 Documents to be submitted
two approaches have been developed: the deterministic
and the probabilistic, which are to be applied depending on 3.1 Damage stability calculations
the ship type as specified in Part D.
The metacentric heights (GM), stability levers (GZ) and cen- 3.1.1 Damage stability documentation
tre of gravity positions for judging the final conditions are to For all ships to which damage stability requirements apply,
be calculated by the constant displacement (lost buoyancy) documents including damage stability calculations are to
method. be submitted.
watertight and weathertight door plan with pressure cal- The openings may be listed in the following categories,
culation depending on their means of closure:
pipes and damaged area when the destruction of these Unprotected openings may lead to progressive flooding
pipes results in progressive flooding. if they are situated within the range of the positive right-
ing lever curve or if they are located below the water-
3.1.2 Additional information for the probabilistic line after damage (at any stage of flooding). Unprotected
approach openings are openings which are not fitted with at least
weathertight means of closure.
In addition to the information listed in [3.1.1], the following
is to be provided: Weathertight
subdivision length LS Openings fitted with weathertight means of closure are
initial draughts and the corresponding GM-values not able to sustain a constant head of water, but they
can be intermittently immersed within the positive
required subdivision index R
range of stability.
attained subdivision index A with a summary table for
Weathertight openings may lead to progressive flooding
all contributions for all damaged zones.
if they are located below the waterline after damage (at
draught, trim, GM in damaged condition any stage of flooding).
damage extension and definition of damage cases with Semi-watertight
probabilistic values p, v and r
Internal openings fitted with semi-watertight means of
righting lever curve (including GZmax and range) with closure are able to sustain a constant head of water cor-
factor of survivability s responding to the immersion relevant to the highest
critical weathertight and unprotected openings with waterline after damage at the equilibrium of the inter-
their angle of immersion mediate stages of flooding.
details of sub-compartments with amount of in-flooded Semi-watertight openings may lead to progressive flood-
water/lost buoyancy with their centres of gravity. ing if they are located below the final equilibrium
waterline after damage.
The use of a loading instrument performing damage stability Figure 1 : Major progressive flooding
calculations may be accepted as a supplement to the dam-
age control documentation. This instrument is to be
approved by the Society according to the requirements of righting arms
Ch 10, Sec 2, [4.8].
0.04m
The damage control plan is required for the following ships:
ships carrying passengers
cargo ships of 500 GT and over.
5 Specific interpretations
5.2.2 In the case where the progressive flooding is of lim-
ited nature that does not continue unabated and causes an
5.1 Assumed damage penetration in way of acceptably slow reduction in righting lever of less than 0,04
sponsons m, the remainder of the curve is to be partially truncated by
assuming that the progressively flooded space is so flooded
5.1.1 If sponsons are fitted, it is necessary to establish the
from the beginning, as shown in Fig 2.
maximum assumed damage penetration (B/5) to be used
when deciding on the various damage cases. For this pur-
pose, the breadth B in the way of such sponsons is to be Figure 2 : Progressive flooding of limited nature
measured to the outside of the sponsons.
Clear of any suck sponsons, the breadth B is to be the mid- righting arms
ship breadth measured to the outside of the original shell. In
< 0.04 m
other words, the assumed penetration of B/5 is the same as
that which applied before the fitting of sponsons.
1 Inclining test and lightweight check the ship is to be as complete as possible at the time of
the test. The number of weights to be removed, added
or shifted is to be limited to a minimum. Temporary
1.1 General material, tool boxes, staging, sand, debris, etc., on
board is to be reduced to an absolute minimum
1.1.1 General conditions of the ship
The following conditions are to be met, as far as practicable: decks should be free of water. Water trapped on deck
may shift and pocket in a fashion similar to liquids in a
the weather conditions are to be favourable tank. Any rain, snow or ice accumulated on the ship
the ship should be moored in a quiet, sheltered area free should be removed prior to the test.
from extraneous forces such as propeller wash from
passing vessels, or sudden discharges from shore side
pumps. The tide conditions and the trim of the ship dur- 1.1.2 Inclining weights
ing the test should be considered. Prior to the test, the
depth of water should be measured and recorded in as
The total weight used is preferably to be sufficient to pro-
many locations as are necessary to ensure that the ship
vide a minimum inclination of one degree and a maximum
will not contact the bottom. The specific gravity of water
of four degrees of heel to each side. The Society may, how-
should be accurately recorded. The ship should be
ever, accept a smaller inclination angle for large ships pro-
moored in a manner to allow unrestricted heeling. The
access ramps should be removed. Power lines, hoses, vided that the requirement on pendulum deflection or U-
etc., connected to shore should be at a minimum, and tube difference in height specified in [1.1.4] is complied
kept slack at all times with. Test weights are to be compact and of such a configu-
ration that the VCG (vertical centre of gravity) of the
the ship should be as upright as possible; with inclining weights can be accurately determined. Each weight is to be
weights in the initial position, up to one-half degree of
marked with an identification number and its weight. Re-
list is acceptable. The actual trim and deflection of keel,
certification of the test weights is to be carried out prior to
if practical, should be considered in the hydrostatic
the incline. A crane of sufficient capacity and reach, or
data. In order to avoid excessive errors caused by signif-
icant changes in the water plane area during heeling, some other means, is to be available during the inclining test
hydrostatic data for the actual trim and the maximum to shift weights on the deck in an expeditious and safe man-
anticipated heeling angles should be checked before- ner. Water ballast transfer may be carried out, when it is
hand impractical to incline using solid weights and subject to
requirement of [1.1.3].
cranes, derrick, lifeboats and liferafts capable of induc-
ing oscillations are to be secured Weights, such as porous concrete, that can absorb signifi-
main and auxiliary boilers, pipes and any other system cant amounts of moisture should only be used if they are
containing liquids are to be filled weighed just prior to the inclining test or if recent weight
certificates are presented. Each weight should be marked
the bilge and the decks are to be thoroughly dried with an identification number and its weight. For small
the anticipated liquid loading for the test should be ships, drums completely filled with water may be used.
included in the planning for the test. Preferably, all tanks Drums should normally be full and capped to allow accu-
should be empty and clean, or completely full. The rate weight control. In such cases, the weight of the drums
number of slack tanks should be kept to an absolute should be verified in the presence of a surveyor of the Soci-
minimum. The viscosity of the fluid, the depth of the ety using a recently calibrated scale.
fluid and the shape of the tank should be such that the
free surface effect can be accurately determined Precautions should be taken to ensure that the decks are
not overloaded during weight movements. If deck strength
the weights necessary for the inclination are to be
is questionable then a structural analysis should be per-
already on board, located in the correct place. Their
formed to determine if existing framing can support the
certificates are to be presented to the Surveyor witness-
ing the inclining test and are also to be included into the weight.
inclining test report. Generally, the test weights should be positioned as far out-
all work on board is to be suspended and crew or per- board as possible on the upper deck. The test weights
sonnel not directly involved in the incline test are to should be on board and in place prior to the scheduled time
leave the ship of the inclining test.
1.1.3 Water ballast as inclining weight 1.1.5 Free surface and slack tanks
The number of slack tanks should normally be limited to
Where the use of solid weights to produce the inclining one port/starboard pair or one centreline tank of the follow-
moment is deemed to be impracticable, the movement of ing:
ballast water may be permitted as an alternative method.
This acceptance would be granted for a specific test only, fresh water reserve feed tanks
and approval of the test procedure by the Society is fuel/diesel oil storage tanks
required. As a minimal prerequisite for acceptability, the
following conditions are to be required: fuel/diesel oil day tanks
inclining tanks are to be wall-sided and free of large lube oil tanks
stringers or other internal members that create air pockets sanitary tanks
tanks are to be directly opposite to maintain ships trim potable water tanks.
specific gravity of ballast water is to be measured and To avoid pocketing, slack tanks are normally to be of regular
recorded (i.e. rectangular, trapezoidal, etc.) cross section and be
pipelines to inclining tanks are to be full. If the ships 20% to 80% full if they are deep tanks and 40% to 60%
piping layout is unsuitable for internal transfer, portable full if they are double-bottom tanks. These levels ensure that
pumps and pipes/hoses may be used the rate of shifting of liquid remains constant throughout the
heel angles of the inclining test. If the trim changes as the
blanks must be inserted in transverse manifolds to pre- ship is inclined, then consideration are also to be given to
vent the possibility of liquids being leaked during longitudinal pocketing. Slack tanks containing liquids of suf-
transfer. Continuous valve control must be maintained ficient viscosity to prevent free movement of the liquids, as
during the test the ship is inclined (such as bunker at low temperature), are
to be avoided since the free surface cannot be calculated
all inclining tanks must be manually sounded before accurately. A free surface correction for such tanks is not to
and after each shift be used unless the tanks are heated to reduce viscosity.
vertical, longitudinal and transverse centres are to be Communication between tanks are never to be allowed.
calculated for each movement Cross-connections, including those via manifolds, are to be
closed. Equal liquid levels in slack tank pairs can be a warn-
accurate sounding/ullage tables are to be provided. The ing sign of open cross connections. A bilge, ballast, and fuel
ships initial heel angle is to be established prior to the oil piping plan can be referred to, when checking for cross
incline in order to produce accurate values for volumes connection closures.
and transverse and vertical centres of gravity for the
inclining tanks at every angle of heel. The draught marks 1.1.6 Means of communications
amidships (port and starboard) are to be used when
establishing the initial heel angle Efficient two-way communications are to be provided
between central control and the weight handlers and
verification of the quantity shifted may be achieved by a between central control and each pendulum station. One
flowmeter or similar device person at a central control station is to have complete con-
trol over all personnel involved in the test.
the time to conduct the inclining is to be evaluated. If
time requirements for transfer of liquids are considered
1.1.7 Documentation
too long, water may be unacceptable because of the
possibility of wind shifts over long periods of time. The person in charge of the inclining test is to have available
a copy of the following plans at the time of the test:
1.1.4 Pendulums
lines plan
The use of three pendulums is recommended but a mini- hydrostatic curves or hydrostatic data
mum of two are to be used to allow identification of bad
readings at any one pendulum station. However, for ships of general arrangement plan of decks, holds, inner bot-
a length equal to or less than 30 m, only one pendulum can toms, etc.
be accepted. They are each to be located in an area pro- capacity plan showing capacities and vertical and longi-
tected from the wind. The pendulums are to be long tudinal centres of gravity of cargo spaces, tanks, etc.
enough to give a measured deflection, to each side of When water ballast is used as inclining weights, the
upright, of at least 15 cm. To ensure recordings from indi- transverse and vertical centres of gravity for the applica-
vidual instruments are kept separate, it is suggested that the ble tanks, for each angle of inclination, must be available
pendulums be physically located as far apart as practical.
tank sounding tables
The use of an inclinometer or U-tube is to be considered in
draught mark locations, and
each separate case. It is recommended that inclinometers or
other measuring devices only be used in conjunction with at docking drawing with keel profile and draught mark cor-
least one pendulum. rections (if available).
it is to be checked that the bilge is dry, and an evalua- 1 shift 2 shift 3 shift 4 shift
tion of the liquids which cannot be pumped, remaining
in the pipes, boilers, condenser, etc., is to be carried out 1 1 1 1
the entire ship is to be surveyed in order to identify all 2 2 2 2
items which need to be added, removed or relocated to
bring the ship to the lightship condition. Each item is to 3 3 3 3
be clearly identified by weight and location of the cen-
4 4 4 4
tre of gravity
the possible solid permanent ballast is to be clearly 5 shift 6 shift 7 shift 8 shift
identified and listed in the report.
1 1 1 1
normally, the total value of missing weights is not to
exceed 2% and surplus weights, excluding liquid bal- 2 2 2 2
last, not exceed 4% of the lightship displacement. For 3 3
3 3
smaller vessels, higher percentages may be allowed.
4 4 4 4
1 Trim and stability booklet lightship data from the inclining test, as indicated in Ch
3, Sec 1, [2.2], including lightship displacement, centre
of gravity co-ordinates, place and date of the inclining
1.1 Information to be included in the trim
test, as well as the Society approval details specified in
and stability booklet the inclining test report. It is suggested that a copy of the
1.1.1 General approved test report be included
A trim and stability booklet is a stability manual, to be Where the above-mentioned information is derived
approved by the Society, which is to contain information to from a sister ship, the reference to this sister ship is to be
enable the Master to operate the ship in compliance with indicated, and a copy of the approved inclining test
the applicable requirements contained in the Rules. report relevant to this sister ship is to be included
The format of the stability booklet and the information standard loading conditions as indicated in [1.2] and
included vary depending on the ship type and operation. examples for developing other acceptable loading con-
ditions using the information contained in the booklet
1.1.2 List of information intact stability results (total displacement and its centre
The following information is to be included in the trim and of gravity co-ordinates, draughts at perpendiculars, GM,
stability booklet: GM corrected for free surfaces effect, GZ values and
a general description of the ship, including: curve, criteria as indicated in Ch 3, Sec 2, [2] and Ch 3,
- the ships name and the Society classification Sec 2, [3] as well as possible additional criteria speci-
number fied in Part D when applicable, reporting a comparison
between the actual and the required values) are to be
- the ship type and service notation
available for each of the above-mentioned operating
- the class notations conditions. The method and assumptions to be followed
- the yard, the hull number and the year of delivery in the stability curve calculation are specified in [1.3]
- the Flag, the port of registry, the international call information on loading restrictions (maximum allowa-
sign and the IMO number ble load on double bottom, maximum specific gravity
- the moulded dimensions allowed in liquid cargo tanks, maximum filling level or
- the draught corresponding to the assigned summer percentage in liquid cargo tanks, maximum KG or mini-
load line, the draught corresponding to the assigned mum GM curve or table which can be used to deter-
summer timber load line and the draught corre- mine compliance with the applicable intact and
sponding to the tropical load line, if applicable damage stability criteria) when applicable
- the displacement corresponding to the above-men- information about openings (location, tightness, means
tioned draughts of closure), pipes or other progressive flooding sources
instructions on the use of the booklet information concerning the use of any special cross-
general arrangement and capacity plans indicating the flooding fittings with descriptions of damage conditions
assigned use of compartments and spaces (cargo, pas- which may require cross-flooding, when applicable
senger, stores, accommodation, etc.) any other guidance deemed appropriate for the opera-
a sketch indicating the position of the draught marks tion of the ship
referred to the ships perpendiculars a table of contents and index for each booklet.
hydrostatic curves or tables corresponding to the design
trim, and, if significant trim angles are foreseen during 1.2 Loading conditions
the normal operation of the ship, curves or tables corre-
sponding to such range of trim are to be introduced. A 1.2.1 General
reference relevant to the sea density, in t/m3, is to be The standard loading conditions to be included in the trim
included as well as the draught measure (from keel or and stability booklet are:
underkeel) lightship condition
cross curves (or tables) of stability calculated on a free ship in ballast in the departure condition, without cargo
trimming basis, for the ranges of displacement and trim but with full stores and fuel
anticipated in normal operating conditions, with indica-
ship in ballast in the arrival condition, without cargo
tion of the volumes which have been considered in the
and with 10% stores and fuel remaining.
computation of these curves
tank sounding tables or curves showing capacities, cen- Further loading cases may be included when deemed nec-
tres of gravity, and free surface data for each tank essary or useful.
When a tropical freeboard is to be assigned to the ship, the same loading condition as above, but with 10% stores
corresponding loading conditions are also to be included. and consumables
lightship condition with full stores and consumables
The heel at the equilibrium of any sailing condition is not to
be greater than 1. lightship condition with 10% stores and consumables.
The vertical location of the centre of gravity for each con-
1.2.2 Ships carrying cargo on deck tainer is generally to be taken at one half of the container
In addition to the loading conditions indicated in [1.2.1] to height. Different locations of the vertical centre of gravity
[1.2.13], in the case of cargo carried on deck the following may be accepted in specific cases, if documented.
cases are to be considered:
1.2.5 Bulk carriers, ore carriers and combination
ship in the fully loaded departure condition having carriers
cargo homogeneously distributed in the holds and a Dry cargo is intended to mean grain, as well as any other
cargo specified in extension and weight on deck, with type of solid bulk cargo.
full stores and fuel
The term grain covers wheat, maize (corn), oats, rye, barley,
ship in the fully loaded arrival condition having cargo rice, pulses, seeds and processed forms thereof, whose
homogeneously distributed in holds and a cargo speci- behaviour is similar to that of grain in its natural state.
fied in extension and weight on deck, with 10% stores The term solid bulk cargo covers any material, other than
and fuel. liquid or gas, consisting of a combination of particles, gran-
ules or any larger pieces of material, generally uniform in
1.2.3 General cargo ships composition, which is loaded directly into the cargo spaces
of a ship without any intermediate form of containment.
In addition to the standard loading conditions reported in
[1.2.1], the following loading cases are to be included in In addition to the standard loading conditions defined in
the trim and stability booklet: [1.2.1], for ships with the service notation bulk carrier, bulk
carrier ESP, ore carrier ESP and combination carrier ESP
ship in the fully loaded departure condition, with cargo the following loading cases are to be included in the trim
homogeneously distributed throughout all cargo spaces and stability booklet:
and with full stores and fuel
ship in the fully loaded departure conditions at the sum-
ship in the fully loaded arrival condition with cargo mer load waterline, with cargo homogeneously distrib-
homogeneously distributed throughout all cargo spaces uted throughout all cargo holds and with full stores and
and with 10% stores and fuel remaining. consumables, for at least three specific gravities, one of
which is relevant to the complete filling of all cargo
For ships with service notation general cargo ship completed holds
by the additional feature nonhomload, the following loading same conditions as above, but with 10% stores and con-
cases are also to be included in the trim and stability booklet: sumables
ship in the departure condition, with cargo in alternate ship in the departure condition, with cargo holds not
holds, for at least three stowage factors, one of which is entirely filled, for at least three stowage factors, one of
relevant to the summer load waterline and with full which is relevant to the summer load waterline and with
stores and consumables full stores and consumables
same conditions as above, but with 10% stores and con-
Where the condition with cargo in alternate holds rele-
sumables.
vant to the summer load waterline leads to local loads
on the double bottom greater than those allowed by the For ships with one of the service notations ore carrier ESP
Society, it is to be replaced by the one in which each and combination carrier ESP and for ships with the service
hold is filled in order to reach the maximum load notation bulk carrier or bulk carrier ESP completed by the
allowed on the double bottom; in no loading case is additional feature nonhomload, the following loading cases
such value to be exceeded are also to be included in the trim and stability booklet:
same conditions as above, but with 10% stores and con- ship in the departure conditions, with cargo in alternate
sumables. holds, for at least three stowage factors, one of which is
relevant to the summer load waterline, and with full
1.2.4 Container ships stores and consumables.
Where the condition with cargo in alternate holds rele-
In addition to the standard loading conditions specified in vant to the summer load waterline leads to local loads
[1.2.1], for ships with the service notation container ship on the double bottom greater than those allowed by the
the following loading cases are to be included in the trim Society, it is to be replaced by the one in which each
and stability booklet: hold is filled in order to reach the maximum load
ship with a number of containers having a weight corre- allowed on the double bottom; in no loading case is
sponding to the maximum permissible weight for each such value to be exceeded.
container at the summer load waterline when loaded same conditions as above, but with 10% stores and con-
with full stores and consumables sumables.
1.2.6 Oil tankers and FLS tankers In addition to the standard loading conditions defined in
[1.2.1], for ships with the service notation chemical tanker
All the intended cargo loading conditions are to be
ESP the following loading cases are to be included in the
included in the trim and stability booklet for examination
within the scope of Pt D, Ch 7, Sec 3, [1]. trim and stability booklet:
Further cases are subject to prior examination by the Soci- ship in the fully loaded departure condition, with cargo
ety before the loading; alternatively, an approved loading homogeneously distributed throughout all cargo tanks
instrument capable of performing damage stability calcula- and with full stores and consumables
tions in accordance with the requirements in Pt D, Ch 7,
same loading condition as above, but with 10% stores
Sec 3, [1] may be used.
and consumables
In addition to the standard loading conditions specified in
three loading conditions corresponding to different spe-
[1.2.1], for ships with the service notation oil tanker ESP or
FLS tanker the following loading cases are to be included in cific gravities with cargo homogeneously distributed
the trim and stability booklet: throughout all cargo tanks and with full stores and con-
sumables
ship in the fully loaded departure condition at the sum-
mer load waterline, with cargo homogeneously distrib- same loading conditions as above, but with 10% stores
uted throughout all cargo tanks and with full stores and and consumables
consumables
four loading conditions corresponding to different cargo
same condition as above, but with 10% stores and con- segregations in order to have slack tanks with full stores
sumables and consumables. Cargo segregation is intended to
mean loading conditions with liquids of different spe-
ship in the departure condition loaded with a cargo hav-
ing a density in order to fill all cargo tanks, with full cific gravities
stores and consumables, but immersed at a draught less When it is impossible to have segregations, these condi-
than the summer load waterline
tions are to be replaced by loading conditions corre-
same condition as above, but with 10% stores and con- sponding to different specific gravities with slack cargo
sumables tanks
ship in the fully loaded departure condition at the sum- same loading conditions as above, but with 10% stores
mer load waterline, with cargo tanks not entirely filled and consumables.
and with full stores and consumables
When it is impossible to have segregations, these condi-
same condition as above, but with 10% stores and con- tions may be replaced by cases corresponding to differ-
sumables ent specific gravities with slack cargo tanks.
two loading conditions corresponding to different cargo
segregations in order to have slack tanks with full stores 1.2.8 Liquefied gas carriers
and consumables
All the intended cargo loading conditions are to be
When it is impossible to have segregations, these condi- included in the trim and stability booklet for examination
tions are to be replaced by loading conditions with the within the scope of Pt D, Ch 9, Sec 2, [6].
same specific gravity and with slack cargo tanks
Further cases are subject to prior examination by the Soci-
same loading condition as above, but with 10% stores ety before the loading; alternatively, an approved loading
and consumables instrument capable of performing damage stability calcula-
for oil tankers having segregated ballast tanks as defined tions in accordance with Pt D, Ch 9, Sec 2, [6] may be
in Pt D, Ch 7, Sec 2, [2], the lightship condition with used.
segregated ballast only is also to be included in the trim
In addition to the standard loading conditions defined in
and stability booklet for examination.
[1.2.1], for ships with the service notation liquefied gas car-
rier the following loading cases are to be included in the
1.2.7 Chemical tankers
trim and stability booklet:
All the intended cargo loading conditions are to be
included in the trim and stability booklet for examination ship in the fully loaded departure condition, with cargo
within the scope of Pt D, Ch 8, Sec 2, [6]. homogeneously distributed throughout all cargo spaces
and with full stores and fuel
Further cases are subject to prior examination by the Society
before the loading; alternatively, an approved loading instru- ship in the fully loaded arrival condition with cargo
ment capable of performing damage stability calculations in homogeneously distributed throughout all cargo spaces
accordance with Pt D, Ch 8, Sec 2, [6] may be used. and with 10% stores and fuel remaining.
ship without cargo, but with full stores and fuel and the 1.2.11 Tugs and fire-fighting ships
full number of passengers and their luggage
In addition to the standard loading conditions defined in
ship in the same condition as above, but with only 10% [1.2.1], for ships with one of the service notations tug and
stores and fuel remaining. fire fighting ship the following loading cases are to be
included in the trim and stability booklet:
1.2.10 Dredgers
ship in the departure condition at the waterline corre-
For ships with one of the service notations dredger, hopper sponding to the maximum assigned immersion, with full
dredger, hopper unit, split hopper dredger and split hop- stores, provisions and consumables
per unit, the loading conditions described in a) and b) are
to replace the standard loading conditions defined in same conditions as above, but with 10% stores and con-
[1.2.1]. sumables.
a) State of cargo: liquid
1.2.12 Supply vessels
ship loaded to the dredging draught with cargo con-
sidered as a liquid In addition to the standard loading conditions specified in
[1.2.1], for ships with the service notation supply vessel the
hopper(s) fully loaded with a homogeneous cargo following loading cases are to be included in the trim and
having density m, up to the spill out edge of the stability booklet:
hopper coaming:
ship in the fully loaded departure condition having
m = M1 / V1 under deck cargo, if any, and cargo specified by posi-
M1 : Mass of cargo, in t, in the hopper when tion and weight on deck, with full stores and fuel, corre-
loaded at the dredging draught sponding to the worst service condition in which all the
relevant stability criteria are met
V1 : Volume, in m3, of the hopper at the spill
out edge of the hopper coaming. ship in the fully loaded arrival condition with cargo as
specified above, but with 10 per cent stores and fuel
The conditions of stores and fuel are to be equal to
100% and 10%, and an intermediate condition is to ship in the worst anticipated operating condition.
be considered if it is more critical than both 100%
and 10%. 1.2.13 Fishing vessels
hopper(s) filled or partly filled with a homogeneous In addition to the standard loading conditions defined in
cargo having densities equal to 1000, 1200, 1400, [1.2.1], for ships with the service notation fishing vessel the
1600, 1800 and 2000 kg/m3
following loading cases are to be included in the trim and
When the dredging draught cannot be reached due stability booklet:
to the density of the cargo, the hopper is to be con-
departure conditions for the fishing grounds with full
sidered filled up to the spill out edge of the hopper
coaming. fuel stores, ice, fishing gear, etc.
The conditions of stores and fuel are to be the most departure from the fishing grounds with full catch
conservative obtained from the stability calculations
arrival at home port with 10% stores, fuel, etc. remain-
with the density m.
ing and full catch
b) State of the cargo: solid
arrival at home port with 10% stores, fuel, etc. and a
ship loaded to the dredging draught with cargo con- minimum catch, which is normally to be 20% of the full
sidered as a solid catch but may be up to 40% if documented.
1.2.14 Ships having the additional service feature Where deckhouses comply with the above conditions,
SPxxx except that no additional exit is provided to a deck above,
In addition to the standard loading conditions specified in such deckhouses are not to be taken into account; however,
[1.2.1], for ships with the additional service feature SPxxx any deck openings inside such deckhouses are to be consid-
the following loading cases are to be included in the trim ered as closed even where no means of closure are pro-
and stability booklet: vided.
ship in the fully loaded departure condition, having Deckhouses, the doors of which do not comply with the
cargo specified by position and weight, with full stores requirements of Ch 8, Sec 4, [1.5.4], are not to be taken into
and fuel, and with the total number of persons on board, account; however, any deck openings inside the deckhouse
including crew, special personnel and passengers are regarded as closed where their means of closure comply
with the requirements of Ch 8, Sec 7, [9] or Ch 8, Sec 8, as
ship in the fully loaded arrival condition, with cargo and relevant.
total number of persons as specified above, but with 10
Deckhouses on decks above the freeboard deck are not to
per cent stores and fuel
be taken into account, but openings within them may be
ship in the worst anticipated operating condition. regarded as closed.
Superstructures and deckhouses not regarded as enclosed
may, however, be taken into account in stability calculations
1.3 Stability curve calculation
up to the angle at which their openings are flooded (at this
1.3.1 General angle, the static stability curve is to show one or more steps,
and in subsequent computations the flooded space are to
Hydrostatic and stability curves are normally prepared on a be considered non-existent).
designed trim basis. However, where the operating trim or Trunks may be taken into account. Hatchways may also be
the form and arrangement of the ship are such that change taken into account having regard to the effectiveness of
in trim has an appreciable effect on righting arms, such their closures.
change in trim is to be taken into account.
The calculations are to take into account the volume to the 1.3.3 Angle of flooding
upper surface of the deck sheathing. In cases where the ship would sink due to flooding through
any openings, the stability curve is to be cut short at the cor-
1.3.2 Superstructures, deckhouses, etc. which may responding angle of flooding and the ship is to be consid-
be taken into account ered to have entirely lost its stability.
Enclosed superstructures complying with Ch 1, Sec 2, [3.13] Small openings such as those for passing wires or chains,
may be taken into account. tackle and anchors, and also holes of scuppers, discharge
and sanitary pipes are not to be considered as open if they
The second tier of similarly enclosed superstructures may submerge at an angle of inclination more than 30. If they
also be taken into account. submerge at an angle of 30 or less, these openings are to
Deckhouses on the freeboard deck may be taken into be assumed open if the Society considers this to be a source
account, provided that they comply with the conditions for of significant progressive flooding; therefore such openings
enclosed superstructures laid down in Ch 1, Sec 2, [3.16]. are to be considered on a case by case basis.
1.5.2 The factor p(x1, x2) is to be calculated according to 1.5.3 Where neither limit of the compartment or group of
the formulae given in [1.5.3] to [1.5.5], compartments under consideration coincides with the aft or
with: forward terminals:
1.6 Calculation of factor si immersion of any part of piping or ventilation ducts car-
ried through a watertight boundary that is located
1.6.1 The factor si is to be determined for each case of within any compartment included in damage cases con-
assumed flooding involving a compartment or group of tributing to the attained index A, if not fitted with water-
compartments according to the requirement indicated in tight means of closure at each boundary.
[1.6.2] to [1.6.9].
1.6.4 Unsymmetrical flooding is to be kept to a minimum
1.6.2 The factor si is to be obtained from the following for- consistent with the efficient arrangements. Where it is nec-
essary to correct large angles of heel, the means adopted
mula:
are, where practicable, to be self-acting, but in any case
1
--- where controls to equalization devices are provided they
GZ max Range 4
s i = K ---------------
- ----------------- are to be operable from above the bulkhead deck. These fit-
0, 12 16
tings, together with their controls, are to be acceptable to
where: the Society. Suitable information concerning the use of
equalization devices are to be supplied to the master of the
GZmax : Maximum positive righting lever, in metres, up
ship.
to the angle v . GZmax is not to be taken as more
than 0,12 m
Range : Range of positive righting levers, in degrees, 1.6.5 Tanks and compartments taking part in such equal-
measured from the angle e . The positive range ization are to be fitted with air pipes or equivalent means of
is to be taken up to the angle v . Range is not to sufficient cross-section to ensure that the flow of water into
be taken as more than 16 the equalization compartments is not delayed.
v : Angle where the righting lever becomes nega-
tive, or angle at which an opening incapable of 1.6.6 Where horizontal watertight boundaries are fitted
being closed weathertight becomes submerged above the waterline under consideration, the s-value calcu-
e : Final equilibrium heel angle, in degrees lated for the lower compartment or group of compartments
is to be obtained by multiplying the value as determined in
if e min : K = 1
[1.6.2] by the reduction factor m according to [1.6.7],
if e max : K = 0 which represents the probability that the spaces above the
horizontal subdivision will not be flooded.
otherwise:
max e
K = -------------------------
- 1.6.7 The factor m is to be obtained from the following for-
max min
mula:
with min = 25 and max = 30
m = ( H j, n, m, d ) ( H j, n, m 1, d )
1.6.8 The factors (Hj, n, m , d) and (Hj, n, m1 , d) are to be Table 2 : Permeability of cargo compartments
obtained from the following formulae:
Permeability at draught
Spaces
if (Hm d) 7,8 m: dS dP dL
Dry cargo spaces 0,70 0,80 0,95
(H d)
( H, d ) = 0, 8 ------------------ Container spaces 0,70 0,80 0,95
7, 8
Ro-ro spaces 0,90 0,90 0,95
in all other cases: Cargo liquids 0,70 0,80 0,95
2.1.1 The initial condition of loading before flooding is to Lubricating oil 0,900
be determined according to [2.1.2] and [2.1.3].
3 Damage assumptions
2.1.2 The ship is loaded to its summer load waterline on an
imaginary even keel. 3.1 Damage dimension
2.1.3 When calculating the vertical centre of gravity, the 3.1.1 The principles indicated in [3.1.2] to [3.1.5] regard-
following principles apply: ing the character of the assumed damage apply.
a) Homogeneous cargo is carried. 3.1.2 The vertical extent of damage in all cases is assumed
b) All cargo compartments, except those referred to under to be from the base line upwards without limit.
c), but including compartments intended to be partially
filled, are to be considered fully loaded except that in 3.1.3 The transverse extent of damage is equal to B/5 or
the case of fluid cargoes each compartment is to be 11,5 metres, whichever is the lesser, measured inboard from
treated as 98 per cent full. the side of the ship perpendicularly to the centre line at the
level of the summer load waterline.
c) If the ship is intended to operate at its summer load
waterline with empty compartments, such compart-
3.1.4 If damage of a lesser extent than specified in [3.1.2]
ments are to be considered empty provided the height
and [3.1.3] results in a more severe condition, such lesser
of the centre of gravity so calculated is not less than as
extent is to be assumed.
calculated under b).
d) Fifty per cent of the individual total capacity of all tanks 3.1.5 Except where otherwise required in [3.4.3], the flood-
and spaces fitted to contain consumable liquids and ing is to be confined to a single compartment between adja-
stores is allowed for. It is to be assumed that for each cent transverse bulkheads provided the inner longitudinal
type of liquid, at least one transverse pair or a single boundary of the compartment is not in a position within the
centre line tank has maximum free surface, and the tank transverse extent of assumed damage. Transverse boundary
or combination of tanks to be taken into account are to bulkheads of wing tanks, which do not extend over the full
be those where the effect of free surfaces is the greatest; breadth of the ship are to be assumed not to be damaged,
in each tank the centre of gravity of the contents is to be provided they extend beyond the transverse extent of
taken at the centre of volume of the tank. The remaining assumed damage prescribed in [3.1.3].
tanks are to be assumed either completely empty or
completely filled, and the distribution of consumable
liquids between these tanks is to be effected so as to
3.2 Steps and recesses
obtain the greatest possible height above the keel for the 3.2.1 If in a transverse bulkhead there are steps or recesses
centre of gravity. of not more than 3,05 metres in length located within the
e) At an angle of heel of not more than 5 degrees in each transverse extent of assumed damage as defined in [3.1.3],
compartment containing liquids, as prescribed in b) such transverse bulkhead may be considered intact and the
adjacent compartment may be floodable singly. If, however, 3.2.4 Where, otherwise, the transverse and longitudinal
within the transverse extent of assumed damage there is a bulkheads bounding a main inboard compartment are
step or recess of more than 3,05 metres in length in a trans- entirely inboard of the assumed damage position, damage is
verse bulkhead, the two compartments adjacent to this bulk- assumed to occur between the transverse bulkheads and the
head are to be considered as flooded. The step formed by adjacent wing compartment. Any step or recess in such
the after peak bulkhead and the after peak tank top is not to wing tank is to be treated as indicated above.
be regarded as a step for the purpose of this regulation.
Examples are shown in Fig 1 to Fig 4:
3.2.2 Where a main transverse bulkhead is located within
the transverse extent of assumed damage and is stepped in Fig 1and Fig 2 refer to [3.2.2]
way of a double bottom or side tank by more than 3,05
metres, the double bottom or side tanks adjacent to the Fig 3 and Fig 4 refer to [3.2.1] and [3.2.2].
stepped portion of the main transverse bulkhead are to be
considered as flooded simultaneously. If this side tank has
openings into one or several holds, such as grain feeding 3.3 Transverse bulkhead spacing
holes, such hold or holds are to be considered as flooded
simultaneously. Similarly, in a ship designed for the carriage 3.3.1 Where the flooding of any two adjacent fore and aft
of fluid cargoes, if a side tank has openings into adjacent compartments is envisaged, main transverse watertight
compartments, such adjacent compartments are to be con- bulkheads are to be spaced at least 1/3(L)2/3 or 14,5 metres,
sidered as empty and flooded simultaneously. This provision whichever is the lesser, in order to be considered effective.
is applicable even where such openings are fitted with clos- Where transverse bulkheads are spaced at a lesser distance,
ing appliances, except in the case of sluice valves fitted in one or more of these bulkheads are to be assumed as non-
bulkheads between tanks and where the valves are con- existent in order to achieve the minimum spacing between
trolled from the deck. Manhole covers with closely spaced
bulkheads.
bolts are considered equivalent to the unpierced bulkhead
except in the case of openings in topside tanks making the
topside tanks common to the holds.
3.4 Damage assumption
3.2.3 Where a transverse bulkhead forming the forward or
aft limit of a wing tank or double bottom tank is not in line 3.4.1 A Type A ship, if over 150 metres in length to which a
with the main transverse bulkhead of the adjacent inboard freeboard less than Type B has been assigned, when loaded
compartment, it is considered to form a step or recess in the as considered in [2.1], is to be able to withstand the flood-
main transverse bulkhead. ing of any compartment or compartments, with an assumed
Such a step or recess may be assumed not to be damaged permeability of 0,95, consequent upon the damage
provided that, either: assumptions specified in [3.1], and is to remain afloat in a
the longitudinal extent of the step or recess, measured satisfactory condition of equilibrium as specified in [3.5]
from the plan of the main transverse bulkhead, is not and [3.6]. In such a ship, the machinery space is to be
more than 3,05 metres, or treated as a floodable compartment, but with a permeability
any longitudinal surface forming the step or recess is of 0,85. See Tab 2.
located inboard of the assumed damage.
Figure 2 : Step and recesses - Example 2
Figure 1 : Step and recesses - Example 1
#
Figure 3 : Step and recesses - Example 3 Figure 4 : Step and recesses - Example 4
!
#
3.6.3 When any part of the deck outside the compartment sageway which is as strongly constructed as the casing and
assumed flooded in a particular case of damage is is separated from the stairway to the engine room by a sec-
immersed, or in any case where the margin of stability in the ond weathertight door of steel or other equivalent material.
flooded condition may be considered doubtful, the residual
stability is to be investigated. It may be regarded as suffi- 4.2.3 Gangway and access
cient if the righting lever curve has a minimum range of 20 An efficiently constructed fore and aft permanent gangway
degrees beyond the position of equilibrium with a maxi- of sufficient strength is to be fitted on Type A ships at the
mum righting lever of at least 0,1 metre within this range. level of the superstructure deck between the poop and the
The area under the righting lever curve within this range is midship bridge or deckhouse where fitted, or equivalent
to be not less than 0,0175 metre-radians. The Society is to means of access is to be provided to carry out the purpose
give consideration to the potential hazard presented by pro- of the gangway, such as passages below deck. Elsewhere,
tected or unprotected openings which may become tempo- and on Type A ships without a midship bridge, arrange-
rarily immersed within the range of residual stability. ments to the satisfaction of the Society are to be provided to
safeguard the crew in reaching all parts used in the neces-
3.6.4 The Society is satisfied that the stability is sufficient sary work of the ship.
during intermediate stages of flooding. In this regard, the Safe and satisfactory access from the gangway level is to be
Society will apply the same criteria relevant to the final available between separate crew accommodation spaces
stage, also during the intermediate stages of flooding. and also between crew accommodation spaces and the
machinery space.
4 Requirements for Type B-60 and B-
4.2.4 Freeing arrangements
100 ships
Type A ships with bulwarks are to be provided with open
rails fitted for at least half the length of the exposed parts of
4.1 Requirements for Type B-60 ships the weather deck or other effective freeing arrangements.
The upper edge of the sheer strake is to be kept as low as
4.1.1 Any Type B ships of over 100 metres, having hatch-
practicable.
ways closed by weathertight covers as specified in [4.3],
may be assigned freeboards less than those required for Where superstructures are connected by trunks, open rails
Type B, provided that, in relation to the amount of reduc- are to be fitted for the whole length of the exposed parts of
tion granted, the requirements in [4.1.2] to [4.1.4] are con- the freeboard deck.
sidered satisfactory by the Society.
In addition, the requirements stated in [3.4.2] are to be 4.3 Hatchways closed by weathertight cov-
complied with. ers of steel or other equivalent material
fitted with gaskets and clamping devices
4.1.2 The measures provided for the protection of the crew
are to be adequate. 4.3.1 At positions 1 and 2 the height above the deck of
hatchway coamings fitted with weathertight hatch covers of
4.1.3 The freeing arrangements are to comply with the pro- steel or other equivalent material fitted with gaskets and
visions of Ch 8, Sec 10. clamping devices is to be:
600 millimetres if in position 1
4.1.4 The covers in positions 1 and 2 comply with the pro-
450 millimetres if in position 2.
visions of [4.3] and have strength complying with Ch 8, Sec
7, special care being given to their sealing and securing The height of these coamings may be reduced, or the coam-
arrangements. ings omitted entirely, upon proper justification. Where
coamings are provided they are to be of substantial con-
4.2 Requirements for Type B-100 ships struction.
4.2.1 In addition to the requirements specified in [4.1], not 4.3.2 Where weathertight covers are of mild steel the
taking into account the prescription stated in [3.4.2], the strength is to be calculated with assumed loads not less than
requirements in [4.2.2] to [4.2.4] are to be complied with. those specified in Ch 8, Sec 7.
In addition, the provisions of [3.4.3] are to be complied
4.3.3 The strength and stiffness of covers made of materials
with.
other than mild steel are to be equivalent to those of mild
steel to the satisfaction of the Society.
4.2.2 Machinery casings
Machinery casings on Type A ships are to be protected by
4.3.4 The means for securing and maintaining weather-
an enclosed poop or bridge of at least standard height, or
tightness are to be to the satisfaction of the Society. The
by a deckhouse of equal height and equivalent strength,
arrangements are to ensure that the tightness can be main-
provided that machinery casings may be exposed if there
tained in any sea conditions, and for this purpose tests for
are no openings giving direct access from the freeboard
tightness are required at the initial survey, and may be
deck to the machinery space. A door complying with the
required at periodical surveys and at annual inspections or
requirements of [4.4] may, however, be permitted in the
at more frequent intervals.
machinery casing, provided that it leads to a space or pas-
4.4 Doors and clamping devices or other equivalent means and are to
be permanently attached to the bulkhead or to the doors
4.4.1 All access openings in bulkheads at ends of enclosed themselves, and the doors are to be so arranged that they
superstructures are to be fitted with doors of steel or other can be operated from both sides of the bulkhead.
equivalent material, permanently and strongly attached to
the bulkhead, and framed, stiffened and fitted so that the 4.4.2 Except as otherwise provided, the height of the sills of
whole structure is of equivalent strength to the unpierced access openings in bulkheads at ends of enclosed super-
bulkhead and weathertight when closed. The means for structures is to be at least 380 millimetres above the deck.
securing these doors weathertight are to consist of gaskets
Chapter 4
SECTION 1 MATERIALS
SECTION 1 MATERIALS
2.3 Material factor k General requirements are given in Tab 3. Additional mini-
mum requirements are given in:
2.3.1 Unless otherwise specified, the material factor k has Tab 4 for ships, excluding membrane-type liquefied gas
the values defined in Tab 2, as a function of the minimum carriers, greater than 150 m in length and having a sin-
specified yield stress ReH. gle strength deck
For intermediate values of ReH , k may be obtained by linear Tab 5 for membrane type liquefied gas carriers greater
interpolation. than 150 m in length and having a deck arrangement as
shown in Fig 1
2.3.2 Steels with a yield stress lower than 235 N/mm2 or
greater than 390 N/mm2 are considered by the Society on a Tab 5 may apply to similar ships with a double deck
case by case basis. arrangement above the strength deck.
In particular, where higher strength steel having a minimum Tab 6 for ships greater than 250 m in length
specified yield stress ReH equal to 460 N/mm2 are used Tab 7 for single-side bulk carrier, bulk carrier ESP and
according to [2.1.2], the material factor k is to be taken combination carrier / OBO ESP
equal to 0,62. Tab 8 for ships with ice strengthening.
Table 2 : Material factor k
2.4.2 Materials are to be of a grade not lower than that
indicated in Tab 9 depending on the material class and
ReH , in N/mm2 k
structural member gross thickness (see [2.4.5]).
235 1,00
315 0,78 2.4.3 For strength members not mentionned in Tab 3, Tab 4,
355 0,72 Tab 5, Tab 6, Tab 7 and Tab 8, grade A/AH may generally be
used.
390 0,68 (1)
(1) The material factor k may be taken equal to 0,66 for 2.4.4 Plating materials for sternframes supporting the rud-
steels with yield stress equal to 390 N/mm2, provided der and propeller boss, rudders, rudder horns and shaft bra-
that the hull structure is additionally verified for com- chets are generally to be of grades not lower than those
pliance with finite element analysis and spectral fatigue corresponding to Class II.
assessment according to NI539, Spectral Fatigue Analy-
sis Methodology for Ships and Offshore Units. For rudder and rudder body plates subjected to stress con-
centrations (e.g. in way of lower support of semi-spade rud-
Figure 1 : Typical deck arrangement for membrane ders or at upper part of spade rudders), Class III is to be
type liquefied natural gas carriers applied.
Trunk deck 2.4.5 The steel grade is to correspond to the as fitted gross
thickness when this is greater than the gross thickness
obtained from the net thickness required by the Rules,
Inner deck according to Ch 4, Sec 2, [1].
primary category
Deck plating exposed to weather, other than that belonging to I A / AH
the primary or special category
Side plating
Bottom plating, including keel plate
Strength deck plating, excluding that belonging to the special
category
PRIMARY
Table 4 : Application of material classes and grades for ships, excluding membrane-type liquefied gas carriers,
greater than 150 m in length and having a single strength deck
Table 5 : Application of material classes and grades for membrane-type liquefied gas carriers,
greater than 150 m in length
Table 6 : Application of material classes and grades for ships greater than 250 m in length
Table 7 : Application of material classes and grades for single-side bulk carrier, bulk carrier ESP
and combination carrier / OBO ESP
Table 8 : Application of material classes and grades 2.4.12 For ships having the service notation container ship,
for ships with ice strengthening where higher strength steel having a minimum specified
yield stress ReH of 460 N/mm2 is used for longitudinal struc-
Structural member category Material grade tural members in the upper deck region (such as hatch side
Shell strakes in way of ice coaming, hatch coaming top and attached longitudinal stiff-
B/AH eners), the steel grade is to be EH47CAS.
strengthening area for plates
Table 9 : Material grade requirements 2.5 Grades of steel for structures exposed
for classes I, II and III to low air temperatures
2.5.1 For ships intended to operate in areas with low air
Class I II III temperatures (20C or below), e.g. regular service during
Gross thickness, winter seasons to Arctic or Antarctic waters, the materials in
NSS HSS NSS HSS NSS HSS exposed structures are to be selected based on the design
in mm
temperature tD, to be taken as defined in [2.5.2].
t 15 A AH A AH A AH
15 < t 20 A AH A AH B AH 2.5.2 The design temperature tD is to be taken as the lowest
20 < t 25 A AH B AH D DH mean daily average air temperature in the area of operation,
where:
25 < t 30 A AH D DH D DH
Mean : Statistical mean over observation period (at least
30 < t 35 B AH D DH E EH
20 years)
35 < t 40 B AH D DH E EH
Average : Average during one day and night
40 < t 50 D DH E EH E EH
Lowest : Lowest during one year
Note 1: NSS and HSS mean, respectively:
Fig 2 illustrates the temperature definition for Arctic waters.
Normal Strength Steel and Higher Strength Steel.
For seasonally restricted service, the lowest value within the
period of operation applies.
2.4.10 In the case of full penetration welded joints located
in positions where high local stresses may occur perpendic- 2.5.3 For the purpose of the selection of steel grades to be
ular to the continuous plating, the Society may, on a case by used for the structural members above the lowest ballast
case basis, require the use of rolled products having ade- waterline and exposed to air, the latter are divided into cat-
quate ductility properties in the through thickness direction, egories (SECONDARY, PRIMARY and SPECIAL), as indi-
such as to minimize the risk of lamellar tearing (Z type steel, cated in Tab 10.
see NR216 Materials and Welding).
Tab 10 also specifies the classes (I, II and III) of the materials
2.4.11 In highly stressed areas, the Society may require that to be used for the various categories of structural members.
plates of gross thickness greater than 20 mm are of grade For non-exposed structures and structures below the lowest
D/DH or E/EH. ballast waterline, see [2.4].
Table 10 : Application of material classes and grades - Structures exposed to low air temperatures
Material class
Structural member category
Within 0,4L amidships Outside 0,4L amidships
SECONDARY: I I
Deck plating exposed to weather (in general)
Side plating above TB (1)
Transverse bulkheads above TB (1)
PRIMARY: II I
Strength deck plating (2)
Continuous longitudinal members above strength deck (excluding longitudinal
hatch coamings of ships equal to or greater than 90 m in length)
Longitudinal bulkhead above TB (1)
Topside tank bulkhead above TB (1)
SPECIAL: III II
Sheer strake at strength deck (3)
Stringer plate in strength deck (3)
Deck strake at longitudinal bulkhead (4)
Continuous longitudinal hatch coamings of ships equal to or greater than 90 m in
length (5)
(1) TB is the draught in light ballast condition, defined in Ch 5, Sec 1, [2.4.3].
(2) Plating at corners of large hatch openings to be considered on a case by case basis.
Class III or grade E/EH to be applied in positions where high local stresses may occur.
(3) To be not less than grade E/EH within 0,4 L amidships in ships with length exceeding 250 m.
(4) In ships with breadth exceeding 70 metres at least three deck strakes to be class III.
(5) To be not less than grade D/DH.
Note 1: Plating materials for sternframes, rudder horns, rudders and shaft brackets are to be of grades not lower than those corre-
sponding to the material classes in [2.4].
Figure 2 : Commonly used definitions of temperatures 2.5.4 Materials may not be of a lower grade than that indi-
cated in Tab 11 to Tab 13 depending on the material class,
structural member gross thickness and design temperature tD.
For design temperatures tD < 55C, materials will be spe-
cially considered by the Society on a case by case basis.
mean value of temperatures in the adjacent spaces, for 2.6.3 Situations other than those mentioned in [2.6.1] and
plating insulated on both sides, with insulated stiffening [2.6.2] or special arrangements will be considered by the
members, when the temperature difference between the Society on a case by case basis.
adjacent spaces is generally not greater than 10 C
(when the temperature difference between the adjacent
2.6.4 Irrespective of the provisions of [2.6.1], [2.6.2] and
spaces is greater than 10C, the temperature value is
established by the Society on a case by case basis) Tab 14, steel having grades lower than those required in
in the case of non-refrigerated spaces adjacent to refrig- [2.4], Tab 3 and Tab 9, in relation to the class and gross
erated spaces, the temperature in the non-refrigerated thickness of the structural member considered, may not be
spaces is to be conventionally taken equal to 0C. used.
Gross thickness, 20C / 25C 26C / 35C 36C / 45C 46C / 55C
in mm NSS HSS NSS HSS NSS HSS NSS HSS
t 10 A AH B AH D DH D DH
10 < t 15 B AH D DH D DH D DH
15 < t 20 B AH D DH D DH E EH
20 < t 25 D DH D DH D DH E EH
25 < t 30 D DH D DH E EH E EH
30 < t 35 D DH D DH E EH E EH
35 < t 45 D DH E EH E EH N.A. FH
45 < t 50 E EH E EH N.A. FH N.A. FH
Note 1: NSS and HSS mean, respectively, Normal Strength Steel and Higher Strength Steel.
Note 2: N.A. = not applicable.
Gross thickness, 20C / 25C 26C / 35C 36C / 45C 46C / 55C
in mm NSS HSS NSS HSS NSS HSS NSS HSS
t 10 B AH D DH D DH E EH
10 < t 20 D DH D DH E EH E EH
20 < t 30 D DH E EH E EH N.A. FH
30 < t 40 E EH E EH N.A. FH N.A. FH
40 < t 45 E EH N.A. FH N.A. FH N.A. N.A.
45 < t 50 E EH N.A. FH N.A. FH N.A. N.A.
Note 1: NSS and HSS mean, respectively, Normal Strength Steel and Higher Strength Steel.
Note 2: N.A. = not applicable.
Gross thickness, 20C / 25C 26C / 35C 36C / 45C 46C / 55C
in mm NSS HSS NSS HSS NSS HSS NSS HSS
t 10 D DH D DH E EH E EH
10 < t 20 D DH E EH E EH N.A. FH
20 < t 25 E EH E EH E FH N.A. FH
25 < t 30 E EH E EH N.A. FH N.A. FH
30 < t 35 E EH N.A. FH N.A. FH N.A. N.A.
35 < t 40 E EH N.A. FH N.A. FH N.A. N.A.
40 < t 50 N.A. FH N.A. FH N.A. N.A. N.A. N.A.
Note 1: NSS and HSS mean, respectively, Normal Strength Steel and Higher Strength Steel.
Note 2: N.A. = not applicable.
Table 14 : Material grade requirements for members In such case, compliance with the requirements of NR216
within or adjacent to refrigerated spaces Materials and Welding, Ch 2, Sec 1, relevant to the quality
and testing of rolled parts accepted in lieu of forged parts,
Design Gross Structural member category may be required.
temperature, thickness, Primary or
in mm Secondary
in C Special 3.3 Steels for casting
t 20 B / AH B / AH
10 tD < 0 20 < t 25 B / AH D / DH 3.3.1 Cast parts intended for stems, sternframes, rudders,
parts of steering gear and deck machinery in general may be
t > 25 D / DH E / EH made of C and C-Mn weldable steels of quality 1, having
t 15 B / AH D / DH specified minimum tensile strength Rm = 400 N/mm2 or
25 tD < 10 15 < t 25 D / DH E / EH 440 N/mm2, in accordance with the applicable require-
t > 25 E / EH E / EH ments of NR216 Materials and Welding, Ch 2, Sec 4.
40 tD < 25 t 25 D / DH E / EH Items which may be subjected to high stresses may be
required to be of quality 2 steels of the above types.
t > 25 E / EH E / EH
3.3.2 For the purpose of testing, which is to be carried out
2.7 Through thickness properties in accordance with NR216 Materials and Welding, Ch 2,
Sec 4, the above steels for casting are assigned to class 1
2.7.1 Where normal tensile loads induce out-of-plane
irrespective of their quality.
stress greater than 0,5 Ry in steel plates:
for plates with t < 15 mm: 3.3.3 The welding of cast parts to main plating contributing
ultrasonic testing is to be performed to hull strength members is considered by the Society on a
for plates with t 15 mm: case by case basis.
Z-quality steel is to be used or ultrasonic testing is to be The Society may require additional properties and tests for
performed such casting, in particular impact properties which are
appropriate to those of the steel plating on which the cast
in order to prevent laminar tearing. parts are to be welded and non-destructive examinations.
The above mentioned ultrasonic testing is to be performed,
3.3.4 Heavily stressed cast parts of steering gear, particu-
before and after welding, on the area of the plate located
larly those intended to form a welded assembly and tillers
within 50 mm or t, whichever is the greater, around the
or rotors mounted without key, are to be subjected to sur-
weld, in accordance with NR216 Materials and Welding,
face and volumetric non-destructive examination to check
Ch 2, Sec 1, [9.10].
their internal structure.
3.2.2 Rolled bars may be accepted in lieu of forged prod- 4.2.2 In general, the application is limited to decks, bulk-
ucts, after consideration by the Society on a case by case heads, superstructures and deckhouses. Other uses may be
basis. permitted by the Society on a case by case basis.
4.3.3 The as welded properties of aluminium alloys of 4.4.2 In the case of welding of two different aluminium
series 6000 are to be agreed by the Society. alloys, the material factor k to be considered for the scant-
lings is the greater material factor of the aluminium alloys of
4.4 Material factor k the assembly.
Symbols
tC : Rule corrosion addition, in mm, see [3] 2.1.2 Plating
wN : Net section modulus, in cm3, of ordinary stiffeners The net thickness is to be obtained by deducting tc from the
wG : Gross section modulus, in cm3, of ordinary stiff- gross thickness.
eners.
2.1.3 Ordinary stiffeners
1 Application criteria The net transverse section is to be obtained by deducting tC
from the gross thickness of the elements which constitute
the stiffener profile. For bulb profiles, an equivalent angle
1.1 General profile, as specified in Ch 4, Sec 3, [3.1.2], may be consid-
1.1.1 The scantlings obtained by applying the criteria spec- ered.
ified in Part B are net scantlings, i.e. those which provide The net strength characteristics are to be calculated for the
the strength characteristics required to sustain the loads, net transverse section. As an alternative, the net section
excluding any addition for corrosion. Exceptions are the modulus may be obtained from the following formula:
scantlings:
wN = wG (1 tC) tC
obtained from the yielding checks of the hull girder in
Ch 6, Sec 2 where and are the coefficients defined in Tab 1.
of bow doors and inner doors in Ch 8, Sec 5 Table 1 : Coefficients and
of side doors and stern doors in Ch 8, Sec 6
of rudder structures and hull appendages in Part B, Type of ordinary stiffeners
Chapter 9 Flat bars 0,035 2,8
of massive pieces made of steel forgings, steel castings
Flanged profiles 0,060 14,0
or iron castings,
Bulb profiles:
which are gross scantlings, i.e. they include additions for wG 200 cm3 0,070 0,4
corrosion. 0,035 7,4
wG > 200 cm3
1.1.2 The required strength characteristics are:
thickness, for plating including that which constitutes 2.1.4 Primary supporting members analysed
through an isolated beam structural model
primary supporting members
The net transverse section is to be obtained by deducting tC
section modulus, shear area, moments of inertia and
local thickness, for ordinary stiffeners and, as the case from the gross thickness of the elements which constitute
may be, primary supporting members the primary supporting members.
section modulus, moments of inertia and first moment The net strength characteristics are to be calculated for the
for the hull girder. net transverse section.
1.1.3 The ship is to be built at least with the gross scant- 2.1.5 Primary supporting members analysed
lings obtained by adding the corrosion additions, specified through a three dimensional model or a
in Tab 2, to the net scantlings. complete ship model
The net thickness of plating which constitutes primary sup-
2 Net strength characteristic porting members is to be obtained by deducting 0,5tc from
the gross thickness.
calculation
2.1.6 Hull girder net strength characteristics to be
2.1 Designers proposal based on gross used for the check of plating, ordinary
scantlings stiffeners and primary supporting members
For the hull girder, the net hull transverse sections are to be
2.1.1 General criteria considered as being constituted by plating and stiffeners
If the Designer provides the gross scantlings of each struc- having net scantlings calculated on the basis of the corro-
tural element without providing their corrosion additions, sion additions tC , according to [2.1.2] to [2.1.4].
the structural checks are to be carried out on the basis of the
It is to be checked whether:
net strength characteristics derived as specified in [2.1.2] to
[2.1.6]. ZNA 0,9 ZGD
When, according to Tab 2, a structural element is affected 3.1.4 Corrosion additions for non-alloyed steel clad
by more than one value of corrosion additions (e.g. a side with stainless steel
frame in a dry bulk cargo hold extending above the lower For plates made of non-alloyed steel clad with stainless
zone), the scantling criteria are generally to be applied con- steel, the corrosion addition tc is to be taken equal to 0 only
sidering the value of corrosion addition applicable at the
for the plate side clad with stainless steel.
lowest point of the element.
3.1.3 Corrosion additions for stainless steel 3.1.5 Corrosion additions for aluminium alloys
For structural members made of stainless steel, the corro- For structural members made of aluminium alloys, the cor-
sion addition tc is to be taken equal to 0. rosion addition tc is to be taken equal to 0.
Symbols
1.2.1 The vertical extent of higher strength steel is to com- 3.1 General
ply with the requirements of Ch 6, Sec 2, [4.5].
3.1.1 Stiffener not perpendicular to the attached
1.2.2 When a higher strength steel is adopted at deck, plating
members not contributing to the longitudinal strength and
Where the stiffener is not perpendicular to the attached
welded on the strength deck (e.g. hatch coamings, strength-
plating, the actual net section modulus may be obtained, in
ening of deck openings) are also generally to be made of the
cm3, from the following formula:
same higher strength steel.
w = w0 sin
1.3.2 Any heterogeneous jointing system is considered by A bulb section may be taken as equivalent to an angle pro-
the Society on a case by case basis. file.
The dimensions of the equivalent angle profile are to be
1.3.3 The use of transition joints made of aluminium/steel- obtained, in mm, from the following formulae:
clad plates or profiles is considered by the Society on a case
h w
by case basis (see NR216 Materials, Ch 3, Sec 2, [4]). h w = h w -------
-+2
9 ,2
t w = t w
2 Plating h w
b f = t w + -------
-2
6 ,7
JM
are to be fitted with slot welds, to be effected according to
Ch 11, Sec 1, [2.6].
DM
3.2 Span of ordinary stiffeners where the plating extends on both sides of the ordinary
stiffener:
3.2.1 General bP = s
The span of ordinary stiffeners is to be measured as shown where the plating extends on one side of the ordinary
in Fig 2 to Fig 5. stiffener (i.e. ordinary stiffeners bounding openings):
bP = 0,5s.
3.2.2 Ordinary stiffeners connected by struts
The span of ordinary stiffeners connected by one or two 3.3.2 Buckling check and ultimate strength check
struts, dividing the span in equal lengths, may be taken The attached plating to be considered for the buckling and
equal to 0,7. ultimate strength check of ordinary stiffeners is defined in
Ch 7, Sec 2, [4.1] and Ch 7, Sec 2, [5.2], respectively.
Figure 2 : Ordinary stiffener without brackets
l 3.4 Geometric properties
3.4.1 Built section
The geometric properties of built sections as shown in Fig 6
may be calculated as indicated in the following formulae.
tw
hw
tf
bf
Figure 4 : Ordinary stiffener with end bracket
These formulae are applicable provided that:
l
Aa tf bf
IB h
-----w- 10
tp
I h
-----w- 10
tf
where:
lb Aa : Net sectional area, in mm2, of the attached plating.
The net section modulus of a built section with attached plat-
ing is to be obtained, in cm3, from the following formula:
Figure 5 : Ordinary stiffener with a bracket
and a stiffener at one end
h w t f b f t W h 2W Aa tf bf
l - + ------------- 1 + ------------------------
w = ------------- -
1000 6000 t W h W
A a + ------------
2
IB
The distance from face plate to neutral axis is to be
I obtained, in cm, from the following formula:
h W ( A a + 0, 5t W h W )
v = --------------------------------------------------
-
10 ( A a + t f b f + t W h W )
lb
The net moment of inertia of a built section with attached
plating is to be obtained, in cm4, from the following formula:
3.3 Width of attached plating I=wv
3.3.1 Yielding check The net shear sectional area of a built section with attached
plating is to be obtained, in cm2, from the following formula:
The width of the attached plating to be considered for the
yielding check of ordinary stiffeners is to be obtained, in m, hw t
A Sh = ----------w-
from the following formulae: 100
Table 2 : Characteristic data for JIS bulb profiles Figure 9 : End connection of ordinary stiffener
Without collar plate
hw dw bf-gr tf-gr bf-ctr hf-ctr
(mm) (mm) (mm) (mm) (mm) (mm)
180 156 34 11,9 9,0 170
200 172 39 13,7 10,4 188
230 198 45 15,2 11,7 217
250 215 49 17,1 12,9 235
Note 1: Note 1 and Note 2 of Tab 1 are applicable.
Figure 10 : End connection of ordinary stiffener
Collar plate
Figure 8 : Characteristic data for bulb profiles
bf-ctr
0,5 tw-gr
Figure 11 : End connection of ordinary stiffener
One large collar plate
hw
dw hf-ctr
tw-gr
4.2 Width of attached plating I1, I2 : Net moments of inertia, in cm4, of deep webs
(1) and (2), respectively, with attached plating
4.2.1 General around their neutral axes parallel to the plating
The width of the attached plating to be considered for the ASh1, ASh2 : Net shear sectional areas, in cm2, of deep webs
yielding check of primary supporting members analysed (1) and (2), respectively, to be calculated
through beam structural models is to be obtained, in m, according to [4.3.2]
from the following formulae:
: Span, in cm, of deep webs (1) and (2).
where the plating extends on both sides of the primary
supporting member: Figure 14 : Large openings in the web
bP = min (s; 0,2) of primary supporting members
where the plating extends on one side of the primary
supporting member (i.e. primary supporting members
bounding openings): (1) I , ASh1
1
bP = 0,5 min (s; 0,2)
tb : Minimum net bracket web thickness, in mm: soft-toed. Where primary supporting members are con-
structed of steel having a strength higher than the strength of
R eH, S the bracket steel, particular attention is to be paid to the
t b ( 2 + 0, 2 w ) -----------
-
R eH, B design of the end bracket toes in order to minimise stress
concentrations.
with:
Where a face plate is welded onto, or adjacent to, the edge
w : Net required section modulus of the
of the end bracket (see Fig 16), the face plate is to be sniped
primary supporting member, in cm3. and tapered at an angle not greater than 30.
ReH,S : Minimum yield stress, in N/mm2, of
the stiffener material. Figure 16 : Bracket face plate adjacent to the edge
ReH,B : Minimum yield stress, in N/mm2, of
the bracket material. Bracket toe area
Face plate area
Moreover, the net thickness of the bracket face plate is not
to be less than the net thickness of the bracket web.
b
Arm length
(bracket height)
Note: The details shown in this Figure are only used to illustrate
items described in the text and are not intended to represent a
design guidance or recommendations.
Arm length Where face plates of end connecting brackets are symmetri-
cal, the following requirements are in general to be com-
plied with:
4.4.3 Arrangement of end brackets
face plates are to be tapered at ends with a total angle
Where length b of the bracket free edge is greater than
not greater than 30
1,5 m, the web of the bracket is to be stiffened as follows:
the breath of face plates at ends is not to be greater than
the net sectional area, in cm2, of stiffener webs is not to
25 mm
be less than 16,5 , where is the span, in m, of the
stiffener face plates of 20 mm thick and above are to be tapered
in thickness at their ends down to their mid-thickness
tripping flat bars are to be fitted. Where the width of the
symmetrical face plate is greater than 400 mm, addi- bracket toes are to be of increased thickness
tional backing brackets are to be provided.
an additional tripping bracket is to be fitted
For a ring system, where the end bracket is integral with the
web of the members and the face plate is welded continu- the radius R of the face plate is to be as large as possible
ously onto the edge of the members and the bracket, the full collar plates welded to the plating are to be fitted in way
area of the larger face plate is to be maintained close to the of the bracket toes
mid-point of the bracket and gradually tapered to the
smaller face plate. Butts in face plates are to be kept well throat thickness of fillet welds is not to be less than t/2,
clear of the bracket toes. with t being the thickness of the bracket toe.
Figure 17 : Bracket with symmetrical face plate 4.5.2 In the case of bracketless crossing between three pri-
mary supporting members (see Fig 19), when the flange of
member 2 and member 3 is continuous, the net thickness,
in mm, of the common part of the webs is not to be less
than the greater of:
R m Sf 1 1
t b = ------------------------
-
0, 5h 2 R y
tb = max (t1 , t2)
to be defined as [4.5.1].
Member 3
R m Sf 2 2 h2
t b = ------------------------
-
0, 5h 1 R y
tb = max (t1 , t2)
where:
4.5.3 The common part of the webs is to be generally stiff-
R, m : Partial safety factors as defined in Ch 7, Sec 3,
ened where the minimum height of the member 1 and
[1.4]
member 2 is greater than 100tb.
Sf1, Sf2 : Net flange section, in mm2,of member 1 and
member 2 respectively 4.5.4 When lamellar tearing of flanges may occur, the
1, 2 : Normal stresses, in N/mm2 , in member 1 and flange in way of the connection may be requested to be of Z
member 2 respectively quality or a 100% ultrasonic testing of the flange in way of
t1, t2 : Net web thicknesses, in mm, of member 1 and the weld may be required prior to and after welding.
member 2 respectively
4.6 Cut-outs and holes
Figure 18 : Bracketless end connections
between two primary supporting members
4.6.1 Cut-outs for the passage of ordinary stiffeners are to
be as small as possible and well rounded with smooth
edges.
h1 In general, the depth of cut-outs is to be not greater than
tb Member 1 50% of the depth of the primary supporting member.
4.6.4 Over half of the span of primary supporting members, MA, MB : Bending moments, in kN.m, in sections A and B
the length of openings is to be not greater than the distance of the primary supporting member
between adjacent openings. m1, m2 : Bending moments, in kN.m, in (1) and (2)
At the ends of the span, the length of openings is to be not d : Distance, in m, between the neutral axes of (1)
greater than 25% of the distance between adjacent open- and (2)
ings. F1, F2 : Axial stresses, in N/mm2, in (1) and (2)
4.6.5 In the case of large openings as shown in Fig 20, the m1, m2 : Bending stresses, in N/mm2, in (1) and (2)
secondary stresses in primary supporting members are to be QT : Shear force, in kN, equal to QA or QB, which-
considered for the reinforcement of the openings. ever is greater
The secondary stresses may be calculated in accordance 1 , 2 : Shear stresses, in N/mm2, in (1) and (2)
with the following procedure. w1, w2 : Net section moduli, in cm3, of (1) and (2)
S1, S2 : Net sectional areas, in cm2, of (1) and (2)
Figure 20 : Large openings in primary supporting
Sw1, Sw2 : Net sectional areas, in cm2, of webs in (1) and
members - Secondary stresses
(2)
MA I1, I2 : Net moments of inertia, in cm4, of (1) and (2)
M with attached plating
MB I1
QA K 1 = -------------
-
Q QB I1 + I2
I2
R/2 K 2 = -------------
-
I1 + I2
The combined stress C calculated at the ends of members
1 (1) and (2) is to be obtained from the following formula:
2 2
c = ( F + m ) + 3
A 2 B
The combined stress C is to comply with the checking cri-
R teria in Ch 7, Sec 3, [3.6] or Ch 7, Sec 3, [4.4], as applica-
ble. Where these checking criteria are not complied with,
the cut-out is to be reinforced according to one of the solu-
2 F
m2 tions shown in Fig 21 to Fig 23:
K2 QT
d continuous face plate (solution 1): see Fig 21
-F
m1
straight face plate (solution 2): see Fig 22
1
K1 QT compensation of the opening (solution 3): see Fig 23
combination of the above solutions.
Members (1) and (2) are subjected to the following forces,
moments and stresses: Figure 21 : Stiffening of large openings in primary
supporting members - Solution 1
MA + MB
F = ---------------------
-
2d
MA MB K
m 1 = --------------------
- 1
2
MA MB K
m 2 = --------------------
- 2
2
F
F1 = 10 -----
S1 Figure 22 : Stiffening of large openings in primary
supporting members - Solution 2
F
F2 = 10 -----
S2
m H
m1 = -------1 10
3
w1
m
m2 = -------2 10
3
w2
K1 QT
1 = 10 ------------
-
S w1
K2 QT
2 = 10 ------------
-
S w2 0,5 H
1,5 H
where:
1.2.1 In ships greater than 120 m in length, the bottom is, 2.1.2 In general, girders are to be fitted spaced not more
in general, to be longitudinally framed. than 2,5 m apart and formed by a vertical intercostal web
plate and a horizontal face plate continuous over the floors.
1.2.2 The bottom structure is to be checked by the
Intercostal web plates are to be aligned and welded to
Designer to make sure that it withstands the loads resulting
floors.
from the dry-docking of the ship.
2.1.3 Centre and side girders are to be extended as far aft
1.2.3 The bottom is to be locally stiffened where concen-
and forward as practicable.
trated loads are envisaged.
2.1.4 Where side girders are fitted in lieu of the centre
1.2.4 Girders or floors are to be fitted under each line of
girder, the scarfing is to be adequately extended and addi-
pillars, when deemed necessary by the Society on the basis
tional stiffening of the centre bottom may be required.
of the loads carried by the pillars.
2.1.5 Longitudinal girders are to be fitted in way of each
1.2.5 Adequate tapering is to be provided between double
line of pillars.
bottom and adjacent single bottom structures. Similarly,
adequate continuity is to be provided in the case of height 2.1.6 Floors are to be made with a welded face plate
variation in the double bottom. Where such a height varia- between the collision bulkhead and 0,25L from the fore
tion occurs within 0,6 L amidships, the inner bottom is gen- end.
erally to be maintained continuous by means of inclined
plating.
2.2 Floors
1.2.6 Provision is to be made for the free passage of water
2.2.1 In general, the floor spacing is to be not greater than
from all parts of the bottom to the suctions, taking into
5 frame spacings.
account the pumping rate required.
1.2.7 When solid ballast is fitted, it is to be securely posi- 2.3 Longitudinal ordinary stiffeners
tioned. If necessary, intermediate floors may be required for
this purpose. 2.3.1 Longitudinal ordinary stiffeners are generally to be
continuous when crossing primary members.
1.3 Keel
3 Transversely framed single bottom
1.3.1 The width of the keel is to be not less than the value
obtained, in m, from the following formula:
3.1 General
L
b = 0 ,8 + 0 ,5 ----------
100 3.1.1 The requirements in [2.1] apply also to transversely
framed single bottoms.
1.4 Drainage and openings for air passage
3.2 Floors
1.4.1 Holes are to be cut into floors and girders to ensure
the free passage of air and liquids from all parts of the dou- 3.2.1 Floors are to be fitted at every frame.
ble bottom.
3.2.2 The height, in m, of floors at the centreline is to be
1.4.2 Air holes are to be cut as near to the inner bottom not less than /16. In the case of ships with considerable
and draining holes as near to the bottom shell as practica- rise of floor, this height may be required to be increased so
ble. as to assure a satisfactory connection to the frames.
6.1.4 Welding
Welding of bilge keel and intermediate plate connections is
to be in accordance with Ch 11, Sec 1, [3.2].
6 Bilge keel
6.1.1 Arrangement
Bilge keels may not be welded directly on the shell plating. Figure 3 : Bilge keel alternative arrangement
An intermediate flat, or doubler, is required on the shell
plating.
The ends of the bilge keel are to be sniped at an angle of
15 or rounded with large radius. They are to be located in
way of a transverse bilge stiffener. The ends of the interme-
diate flat are to be sniped at an angle of 15.
In general, scallops and cut-outs are not to be used. Crack
arresting holes are to be drilled in the bilge keel butt welds
as close as practicable to the ground bar. The diameter of
the hole is to be greater than the width W of the butt weld
and is to be a minimum of 25 mm (see Fig 2). Where the
butt weld has been subject to non-destructive examination,
the crack arresting hole may be omitted.
The arrangement shown in Fig 2 is recommended.
The arrangement shown in Fig 3 may also be accepted.
1.1.2 The transversely framed side structures are built with 2.2 Primary supporting members
transverse frames possibly supported by side girders (see
2.2.1 In general, the side vertical primary supporting mem-
[5.3.1]).
ber spacing may not exceed 5 frame spacings.
1.1.3 The longitudinally framed side structures are built
2.2.2 In general, the side vertical primary supporting mem-
with longitudinal ordinary stiffeners supported by side verti-
bers are to be bracketed to the double bottom transverse
cal primary supporting members.
floors.
where:
4.2 Primary supporting members
: Coefficient equal to:
4.2.1 The height of side vertical primary supporting mem-
for unflanged brackets:
bers may be gradually tapered from bottom to deck. The
maximum acceptable taper, however, is 8 cm per metre. = 48
4.2.2 Side vertical primary supporting members supported for flanged brackets:
by a strut and two diagonals converging on the former are = 43,5
to be considered by the Society on a case by case basis.
w : Required net section modulus of the stiffener, in
cm3, given in [6.2.2] and [6.2.3] and depending
5 Transversely framed double side on the type of connection
t : Bracket net thickness, in mm.
5.1 General
6.2.2 For connections of perpendicular stiffeners located in
5.1.1 The requirements in [4.1] also apply to transversely
the same plane (see Fig 1) or connections of stiffeners
framed double side.
located in perpendicular planes (see Fig 2), the required net
5.1.2 Transverse frames may be connected to the vertical section modulus is to be taken equal to:
ordinary stiffeners of the inner side by means of struts. w = w2 if w2 w1
Struts are generally to be connected to transverse frames w = w1 if w2 > w1
and vertical ordinary stiffeners of the inner side by means of
vertical brackets. where w1 and w2 are the required net section moduli of
stiffeners, as shown in Fig 1 and Fig 2.
5.2 Frames
Figure 1 : Connections of perpendicular stiffeners
5.2.1 Transverse frames are to be fitted at every frame. in the same plane
6 Frame connections d
w1
6.1 General
6.1.1 End connections of frames are to be bracketed. Figure 2 : Connections of stiffeners located
in perpendicular planes
6.1.2 'Tweendeck frames are to be bracketed at the top and
welded or bracketed at the bottom to the deck. d
6.2.3 For connections of frames to deck beams (see Fig 3), Figure 4 : Lower brackets of main frames
the required net section modulus is to be taken equal to:
for bracket A: h
wA = w1 if w2 w1
d2
wA = w2 if w2 > w1
for bracket B:
wB = w1 need not be greater than w1 ,
where w1 , w1 and w2 are the required net section moduli
h
1,5
of stiffeners, as shown in Fig 3.
w2
7.1 Position of openings
2.2 Longitudinal ordinary stiffeners 4.2.7 Where side pillars are not fitted in way of hatch ends,
vertical stiffeners of bulkheads supporting hatch side girders
2.2.1 In ships equal to or greater than 120 m in length, or hatch end beams are to be bracketed at their ends.
strength deck longitudinal ordinary stiffeners are to be con-
tinuous through the watertight bulkheads and/or deck trans-
5 Hatch supporting structures
verses.
6.1.3 If the openings arrangements do not comply with the 6.2.2 For hatchways located in the positions specified in
requirements of the present Sub-Article, the hull girder lon- [6.2.1], insert plates are, in general, not required in way of
gitudinal strength assessment is to be carried out by sub- corners where the plating cut-out has an elliptical or para-
tracting such opening areas. bolic profile and the half axes of elliptical openings, or the
half lengths of the parabolic arch, are not less than:
6.2 Corners of hatchways 1/20 of the hatchway width or 600 mm, whichever is
the lesser, in the transverse direction
6.2.1 For hatchways located within the cargo area, insert twice the transverse dimension, in the fore and aft direc-
plates, whose thickness is to be determined according to tion.
[6.2.3], are generally to be fitted in way of corners where
the plating cut-out has a circular profile. 6.2.3 Where insert plates are required, their thickness is
obtained, in mm, from the following formula:
The radius of circular corners is to be not less than:
t INS = 0 ,8 + 0 ,4 --- t
5% of the hatch width, where a continuous longitudinal b
deck girder is fitted below the hatch coaming
without being taken less than t or greater than 1,6t
8% of the hatch width, where no continuous longitudi-
where:
nal deck girder is fitted below the hatch coaming.
: Width, in m, in way of the corner considered, of
Corner radiusing, in the case of the arrangement of two or the cross deck strip between two consecutive
more hatchways athwartship, is considered by the Society hatchways, measured in the longitudinal direc-
on a case by case basis. tion (see Fig 1)
b : Width, in m, of the hatchway considered, meas- way of corners may be considered by the Society on a case
ured in the transverse direction (see Fig 1) by case basis.
t : Actual thickness, in mm, of the deck at the side
of the hatchways. 7 Openings in decks other than the
For the extreme corners of end hatchways, the thickness of strength deck
insert plates is to be 60% greater than the actual thickness
of the adjacent deck plating. A lower thickness may be
accepted by the Society on the basis of calculations show- 7.1 General
ing that stresses at hatch corners are lower than permissible
values. 7.1.1 The requirements for such openings are similar to
those in [6.1] for the strength deck. However, circular open-
6.2.4 Where insert plates are required, the arrangement ings need not to be compensated.
shown in Ch 11, App 2, Tab 68 is to be complied with.
7.1.2 Corners of hatchway openings are to be rounded, as
6.2.5 For hatchways located in positions other than those in specified in [6.2] for the strength deck; insert plates may be
[6.2.1], a reduction in the thickness of the insert plates in omitted, however, when deemed acceptable by the Society.
1.1 Application
1.3 Watertight bulkheads of trunks, tunnels,
1.1.1 The requirements of this Section apply to longitudinal etc.
or transverse bulkhead structures which may be plane or
1.3.1 Watertight trunks, tunnels, duct keels and ventilators
corrugated.
are to be of the same strength as watertight bulkheads at
corresponding levels. The means used for making them
1.1.2 Bulkheads may be horizontally or vertically stiffened.
watertight, and the arrangements adopted for closing open-
Horizontally framed bulkheads consist of horizontal ordi- ings in them, are to be to the satisfaction of the Society.
nary stiffeners supported by vertical primary supporting
members.
1.4 Openings in watertight bulkheads
Vertically framed bulkheads consist of vertical ordinary stiff-
eners which may be supported by horizontal girders. 1.4.1 Openings may not be cut in the collision bulkhead
below the freeboard deck.
1.2 General arrangement The number of openings in the collision bulkhead above
the freeboard deck is to be kept to the minimum compatible
1.2.1 The number and location of watertight bulkheads are with the design and proper working of the ship.
to be in accordance with the relevant requirements given in All such openings are to be fitted with means of closing to
Ch 2, Sec 1. weathertight standards.
1.2.2 For ships greater than 170 m in length, longitudinal 1.4.2 Certain openings below the freeboard deck are per-
corrugated bulkheads are to have horizontal corrugations mitted in the other bulkheads, but these are to be kept to a
and the upper and lower strakes of longitudinal corrugated minimum compatible with the design and proper working
bulkheads are to be plane up to a distance of at least 0,1D of the ship and to be provided with watertight doors having
from deck and bottom. strength such as to withstand the head of water to which
Transverse corrugated bulkheads having horizontal corruga- they may be subjected.
tions are to be fitted with vertical primary supporting mem-
bers of number and size sufficient to ensure the required 1.5 Watertight doors
vertical stiffness of the bulkhead.
1.5.1 The net scantlings of watertight doors is to be not less
1.2.3 Where an inner bottom terminates on a bulkhead, the than that required in Ch 8, Sec 12.
lowest strake of the bulkhead forming the watertight floor of
the double bottom is to extend at least 300 mm above the 1.5.2 Where vertical stiffeners are cut in way of watertight
inner bottom. doors, reinforced stiffeners are to be fitted on each side of
the door and suitably overlapped; cross-bars are to be pro-
1.2.4 Longitudinal bulkheads are to terminate at transverse vided to support the interrupted stiffeners.
bulkheads and are to be effectively tapered to the adjoining
1.5.3 Watertight doors required to be open at sea are to be
structure at the ends and adequately extended in the
of the sliding type and capable of being operated both at
machinery space, where applicable.
the door itself, on both sides, and from an accessible posi-
tion above the bulkhead deck.
1.2.5 Where the longitudinal watertight bulkheads contrib-
ute to longitudinal strength, the plating thickness is to be Means are to be provided at the latter position to indicate
uniform for a distance of at least 0,1D from the deck and whether the door is open or closed, as well as arrows indi-
bottom. cating the direction in which the operating gear is to be
operated.
1.2.6 The structural continuity of the bulkhead vertical and
horizontal primary supporting members with the surround- 1.5.4 Watertight doors may be of the hinged type if they are
ing supporting structures is to be carefully ensured. always intended to be closed during navigation.
Such doors are to be framed and capable of being secured
1.2.7 The height of vertical primary supporting members of watertight by handle-operated wedges which are suitably
longitudinal bulkheads may be gradually tapered from bot- spaced and operable at both sides.
b = 80 w + 20-
----------------
2.1 General t
ps
b = ---------
2.1.1 Where a bulkhead does not extend up to the upper- t
most continuous deck (such as the after peak bulkhead),
suitable strengthening is to be provided in the extension of where:
the bulkhead. : Span, in m, of the stiffener measured between
supports
2.1.2 Bulkheads are to be stiffened in way of deck girders. w : Net section modulus, in cm3, of the stiffener
2.1.3 The webs of vertical stiffeners on hopper and topside t : Net thickness, in mm, of the bracket
tank watertight transverse bulkheads are generally to be p : Design pressure, in kN/m2, calculated at mid-
aligned with the webs of longitudinal stiffeners on sloping span
plates of inner hull. : Coefficient equal to:
= 4,9 for tank bulkheads
2.1.4 A primary supporting member is to be provided in
way of any vertical knuckle in longitudinal bulkheads. The = 3,6 for watertight bulkheads.
distance between the knuckle and the primary supporting
member is to be taken not greater than 70 mm. 2.3.2 The connection between the stiffener and the bracket
is to be such that the net section modulus of the connection
2.1.5 Plate floors are to be fitted in the double bottom in is not less than that of the stiffener.
way of plane transverse bulkheads.
Figure 1 : Bracket at upper end of ordinary stiffener
2.1.6 A doubling plate of the same net thickness as the on plane bulkhead
bulkhead plating is to be fitted on the after peak bulkhead
in way of the sterntube, unless the net thickness of the bulk- b
head plating is increased by at least 60%.
ues, in mm:
for arm length a:
a
- brackets of horizontal stiffeners and bottom bracket
of vertical stiffeners:
a = 100 b
- upper bracket of vertical stiffeners:
a = 80
for normal strength steel: 3.3.3 The continuity of the corrugated bulkhead with the
stool plating is to be adequately ensured. In particular, the
Ri = 2,5 t
upper strake of the lower stool is to be of the same net thick-
for high tensile steel: ness and yield stress as those of the lower strake of the bulk-
head.
Ri = 3,0 t
where t is the net thickness, in mm, of the corrugated plate. 4 Non-tight bulkheads
3.1.4 When welds in a direction parallel to the bend axis 4.1 Non-tight bulkheads not acting as pillars
are provided in the zone of the bend, the welding proce-
dures are to be submitted to the Society for approval, as a 4.1.1 Non-tight bulkheads not acting as pillars are to be
function of the importance of the structural element. provided with vertical stiffeners with a maximum spacing
Moreover, when the gross thickness of the bulkhead plating equal to:
is greater than 20 mm, the Society may require the use of 0,9 m, for transverse bulkheads
steel grade E or EH. two frame spacings, with a maximum of 1,5 m, for lon-
gitudinal bulkheads.
3.1.5 In general, where girders or vertical primary support-
ing members are fitted on corrugated bulkheads, they are to
4.2 Non-tight bulkheads acting as pillars
be arranged symmetrically.
4.2.1 Non-tight bulkheads acting as pillars are to be pro-
3.2 Structural arrangement vided with vertical stiffeners with a maximum spacing equal
to:
3.2.1 The strength continuity of corrugated bulkheads is to two frame spacings, when the frame spacing does not
be ensured at ends of corrugations. exceed 0,75 m,
one frame spacing, when the frame spacing is greater
3.2.2 Where corrugated bulkheads are cut in way of primary than 0,75 m.
members, attention is to be paid to ensure correct alignment
of corrugations on each side of the primary member. 4.2.2 Each vertical stiffener, in association with a width of
plating equal to 35 times the plating net thickness, is to
3.2.3 The connection of the corrugated bulkhead with the comply with the applicable requirements for pillars in Ch 7,
deck and the bottom is to be carefully designed and spe- Sec 3, the load supported being determined in accordance
cially considered by the Society. with the same requirements.
4.2.3 In the case of non-tight bulkheads supporting longitu- height), the areas of openings, expressed as percentages of
dinally framed decks, vertical girders are to be provided in the corresponding areas of these portions, are to be within
way of deck transverses. the limits given in Tab 1.
5 Wash bulkheads 5.2.2 In any case, the distribution of openings is to fulfil the
strength requirements specified in [4.2].
5.1 General
5.2.3 In general, openings may not be cut within 0,15D
5.1.1 The requirements in [5.2] apply to transverse and lon- from bottom and from deck.
gitudinal wash bulkheads whose main purpose is to reduce
the liquid motions in partly filled tanks.
Table 1 : Areas of openings in transverse
wash bulkheads
5.2 Openings
5.2.1 The total area of openings in a transverse wash bulk- Bulkhead portion Lower limit Upper limit
head is generally to be between 10% and 30% of the total Upper 10 % 15 %
bulkhead area.
Central 10 % 50 %
In the upper, central and lower portions of the bulkhead
(the depth of each portion being 1/3 of the bulkhead Lower 2% 10 %
Part B
Hull and Stability
Chapters 1 2 3 4 5 6 7 8 9 10 11
Chapter 1 GENERAL
Chapter 2 GENERAL ARRANGEMENT DESIGN
Chapter 3 STABILITY
Chapter 4 STRUCTURE DESIGN PRINCIPLES
Chapter 5 DESIGN LOADS
Chapter 6 HULL GIRDER STRENGTH
Chapter 7 HULL SCANTLINGS
Chapter 8 OTHER STRUCTURES
Chapter 9 HULL OUTFITTING
Chapter 10 CORROSION PROTECTION AND LOADING INFORMATION
Chapter 11 CONSTRUCTION AND TESTING
Section 1 General
1 Definitions 15
1.1 Still water loads
1.2 Wave loads
1.3 Dynamic loads
1.4 Local loads
1.5 Hull girder loads
1.6 Loading condition
1.7 Load case
2 Application criteria 15
2.1 Fields of application
2.2 Hull girder loads
2.3 Local loads
2.4 Load definition criteria to be adopted in structural analyses based on plate or
isolated beam structural models
2.5 Load definition criteria to be adopted in structural analyses based on three
dimensional structural models
2.6 Navigation coefficients
Section 1 Plating
1 General 67
1.1 Net thicknesses
1.2 Partial safety factors
1.3 Elementary plate panel
1.4 Load point
2 General requirements 68
2.1 General
2.2 Minimum net thicknesses
2.3 Bilge plating
2.4 Inner bottom of cargo holds intended to carry dry cargo
2.5 Sheerstrake
2.6 Stringer plate
2.7 Deck plating protected by wood sheathing or deck composition
2.8 Corrugated bulkhead
3 Strength check of plating subjected to lateral pressure 69
3.1 General
3.2 Load model
3.3 Longitudinally framed plating contributing to the hull girder longitudinal
strength
3.4 Transversely framed plating contributing to the hull girder longitudinal strength
3.5 Plating not contributing to the hull girder longitudinal strength
3.6 Plating subject to impact loads
4 Strength check of plating subjected to wheeled loads 72
4.1 General
4.2 Load model
4.3 Plating
5 Buckling check 73
5.1 General
5.2 Load model
5.3 Critical stresses
5.4 Checking criteria
Chapter 5
DESIGN LOADS
SECTION 1 GENERAL
SECTION 1 GENERAL
1.1.1 Still water loads are those acting on the ship at rest in
1.7 Load case
calm water.
1.7.1 A load case is a state of the ship structures subjected
1.2 Wave loads to a combination of hull girder and local loads.
1.2.1 Wave loads are those due to wave pressures and ship 2 Application criteria
motions, which can be assumed to have the same wave
encounter period. 2.1 Fields of application
1.4.2 For the structures which constitute the boundary of 2.2.1 The still water, wave and dynamic hull girder loads to
spaces not intended to carry liquids and which do not be used for the determination of:
belong to the outer shell, the still water and wave pressures the hull girder strength, according to the requirements
in flooding conditions are also to be considered. of Part B, Chapter 6, and
the structural scantling of plating, ordinary stiffeners and
1.5 Hull girder loads primary supporting members contributing to the hull
girder strength, in combination with the local loads
given in Ch 5, Sec 5 and Ch 5, Sec 6, according to the
1.5.1 Hull girder loads are (still water, wave and dynamic)
requirements in Part B, Chapter 7,
forces and moments which result as effects of local loads
acting on the ship as a whole and considered as a beam. are specified in Ch 5, Sec 2.
2.3 Local loads 2.4.3 Draught associated with each cargo and
ballast distribution
2.3.1 Load cases
Local loads are to be calculated on the basis of the ships
The local loads defined in [1.4] are to be calculated in each draught T1 corresponding to the cargo or ballast distribution
of the mutually exclusive load cases described in Ch 5, Sec 4. considered according to the criteria in [2.4.2]. The ship
Dynamic loads are to be taken into account and calculated draught is to be taken as the distance measured vertically
according to the criteria specified in Ch 5, Sec 5 and Ch 5, on the hull transverse section at the middle of the length L,
Sec 6. from the moulded base line to the waterline in:
2.4.2 Cargo and ballast distributions For all ship types for which analyses based on three dimen-
sional models are required according to Ch 7, Sec 3, [4],
When calculating the local loads for the structural scantling
the most severe loading conditions for the structural ele-
of an element which separates two adjacent compartments,
ments under investigation are to be considered. These load-
the latter may not be considered simultaneously loaded.
ing conditions are to be selected among those envisaged in
The local loads to be used are those obtained considering
the ship loading manual.
the two compartments individually loaded.
For elements of the outer shell, the local loads are to be cal- For ships with the service notation general cargo ship, bulk
culated considering separately: carrier or bulk carrier ESP completed by the additional
service feature nonhomload, the loading conditions to be
the still water and wave external sea pressures, consid-
considered are to include the cases where the selected
ered as acting alone without any counteraction from the
holds are empty at draught T, according to the indications
ship interior
specified in the ship notation.
the still water and wave differential pressures (internal
pressure minus external sea pressure) considering the Further criteria applicable to specific ship types are speci-
compartment adjacent to the outer shell as being loaded. fied in Part D.
Symbols
For symbols not defined in this Section, refer to the list at the vertical bending moment M is positive when it
the beginning of this Chapter. induces tensile stresses in the strength deck (hogging
C : Wave parameter: bending moment); it is negative in the opposite case
(sagging bending moment)
L the vertical shear force Q is positive in the case of
C = ( 118 0 ,36L ) ------------- for 65m L < 90m
1000 downward resulting forces preceding and upward
300 L 1 ,5
C = 10 ,75 ------------------- for 90m L < 300m resulting forces following the ship transverse section
100 under consideration; it is negative in the opposite case.
C = 10 ,75 for 300m L 350m
1 ,5
L 350
C = 10 ,75 ------------------- for L > 350m 2 Still water loads
150
Q: (+)
Aft Fore
M: (+)
In Fig 2, MSW is the design still water bending moment 3.2 Horizontal wave bending moment
amidships, in hogging or sagging conditions, whose abso-
lute values are to be taken not less than those obtained, in 3.2.1 The horizontal wave bending moment at any hull
kN.m, from the following formulae: transverse section is obtained, in kN.m, from the following
hogging conditions: formula:
2 3
M SWM ,H = 175n 1 CL B ( C B + 0 ,7 )10 M WV ,H MWH = 0,42 FM n H L2 T CB
sagging conditions:
where FM is the distribution factor defined in [3.1.1].
2 3
M SWM ,S = 175n 1 CL B ( C B + 0 ,7 )10 + M WV ,S
where MWV,H, MWV,S are the vertical wave bending moments, 3.3 Wave torque
in kN.m, defined in [3.1].
3.3.1 The wave torque at any hull transverse section is to
2.3 Still water shear force be calculated considering the ship in two different condi-
tions:
2.3.1 The design still water shear force QSW at any hull
transverse section is the maximum positive or negative condition 1: ship direction forming an angle of 60o with
shear force calculated, at that hull transverse section, for the the prevailing sea direction
loading conditions specified in [2.1.2].
condition 2: ship direction forming an angle of 120o
3 Wave loads with the prevailing sea direction.
sagging conditions: FTM, FTQ : Distribution factors defined in Tab 2 for ship
MWV,S = 110 FM n C L B (CB + 0,7) 10
2 3 conditions 1 and 2 (see also Fig 4 and Fig 5)
x CW = 0,165 + 0,95 CB
0 x < 0,4 L 2 ,5 ---
L
where CB is to be assumed not less than 0,6. In
0,4 L x 0,65 L 1 the absence of more precise determination, CW
may be taken equal to the value provided by the
2 ,86 1 ---
x
065 L < x L above formula.
L
d : Vertical distance, in m, from the centre of tor-
Figure 3 : Distribution factor FM sion to a point located 0,6 T above the baseline.
FM
Table 2 : Distribution factors FTM and FTQ
1,0
Ship Distribution factor Distribution factor
condition FTM FTQ
2x 2x
1 1 cos ---------- sin ----------
L L
x
0,0 0,4 0,65 1,0 FE L 2 ( L x ) 2 ( L x )
2 1 cos ------------------------ sin ------------------------
AE L L
Distribution factor FQ
Hull transverse section location
Positive wave shear force Negative wave shear force
x x
0 x < 0,2 L 4 ,6A --- 4 ,6 ---
L L
0,2 L x 0,3 L 0,92 A 0,92
0,7 L x 0,85 L 1 A
For multideck ships, the upper deck shown in Fig 7 is to be 4.2 Increase in sagging wave bending
taken as the deck (including superstructures) which extends moment
up to the extreme forward end of the ship and has the larg-
est breadth forward of 0,2L from the fore end. 4.2.1 General
The sagging wave bending moment at any hull transverse
section, defined in [3.1], is to be multiplied by the coeffi-
Figure 7 : Area AS
cient FD obtained from the formulae in Tab 4, which takes
AS/2 into account the dynamic effects of bow flare impact.
Upper deck (including Where at least one of the conditions in [4.1.1] does not
a2 superstructures, if any)
a1 occur, the coefficient FD may be taken equal to 1.
Table 4 : Coefficient FD
Waterline at the
calculation draught
a0 Hull transverse section location Coefficient FD
0 x < 0,4 L 1
b
0,2L 0,1L
1 + 10 ( C D 1 ) --- 0, 4
x
FE 0,4 L x < 0,5 L L
0,5 L x L CD
4.1.2 When the effects of bow flare impact are to be con- Note 1:
sidered, according to [4.1.1], the sagging wave bending
AS
moment is to be increased as specified in [4.2.1] and C D = 262, 5 --------------------------------------
- 0, 6 with 1 ,0 C D 1 ,2
CLB ( C B + 0, 7 )
[4.2.2].
AS : Area, in m2, defined in [4.1.1].
4.1.3 The Society may require the effects of bow flare
impact to be considered also when one of the conditions in 4.2.2 Direct calculations
[4.1.1] does not occur, if deemed necessary on the basis of As an alternative to the formulae in [4.2.1], the Society may
the ships characteristics. accept the evaluation of the effects of bow flare impact from
direct calculations, when justified on the basis of the ships
In such cases, the increase in sagging wave bending characteristics and intended service. The calculations are to
moment is defined on a case by case basis. be submitted to the Society for approval.
Symbols
For the symbols not defined in this Section, refer to the list 2 Ship absolute motions and
at the beginning of this Chapter.
accelerations
aB : Motion and acceleration parameter:
h W 2.1 Surge
a B = n 0 ,76F + 1 ,875 ------
-
L
h W 0 ,6 0 ,75 2 2
A p -------
Reference value of the relative motion h1
0 ,328 a B 1 ,32 ------
- -------- 0 ,575 L Tp Location
L CB in the upright ship condition, in m
4 ,35
0 ,7 ----------- 3 ,25 h 1 ,M if C B < 0, 875
2.5 Pitch x=0 C
B
h 1 ,M if C B 0, 875
2.5.1 The pitch amplitude, period and acceleration are
obtained from the formulae in Tab 4. h 1 ,AE h 1 ,M x
x < 0,3 L h 1 ,AE --------------------------
- ---
0 ,3 L
Note 1:
3 Ship relative motions and accelerations
C : Wave parameter defined in Ch 5, Sec 2
h1,AE : Reference value h1 calculated for x = 0
3.1 Definitions h1,M : Reference value h1 calculated for x = 0,5 L
h1,FE : Reference value h1 calculated for x = L
3.1.1 Ship relative motions
3.3.2 The reference value, in m, of the relative motion in
The ship relative motions are the vertical oscillating transla- the inclined ship condition is obtained, at any hull trans-
tions of the sea waterline on the ship side. They are meas- verse section, from the following formula:
ured, with their sign, from the waterline at draught T1.
BW
h 2 = 0 ,5h 1 + A R ------
-
2
3.1.2 Accelerations
where:
At any point, the accelerations in X, Y and Z direction are
the acceleration components which result from the ship h1 : Reference value, in m, of the relative motion in
motions defined in [2.1] to [2.6]. the upright ship, calculated according to [3.3.1]
Symbols
h1 : Reference value of the ship relative motion in the Load cases c and d refer to the ship in inclined condi-
upright ship condition, defined in Ch 5, Sec 3, tions (see Ch 5, Sec 3, [3.2]), i.e. having sway, roll and yaw
[3.3] motions.
Figure 1 : Wave loads in load case a Figure 3 : Wave loads in load case c
Z Z
Positive h1
h1 h2
0,7a Y 0,25M WV
h2
0,25Q WV
0,625Q wv 0,625Mwv T1
T1
0,625MWT
Y Y
0,625M WH
Z
Negative h1
Figure 4 : Wave loads in load case d
h1
0,625Q wv 0,625Mwv
T1
0,5 h 2 0,25Q WV
1,0a Y
0,25M WV
0,5 h 2
Y T1
0,625M WH
Figure 2 : Wave loads in load case b
Y
Z
The internal loads are the still water loads induced by the
weights carried, including those carried on decks, and the
Y wave loads induced by the accelerations.
and induces: 2.3.1 The wave local and hull girder loads to be considered
in each load case are summarised in Tab 1 and Tab 2,
vertical wave bending moment and shear force in the
respectively.
hull girder
These loads are obtained by multiplying, for each load case,
horizontal wave bending moment in the hull girder
the reference value of each wave load by the relevant com-
in load case c, torque in the hull girder. bination factor.
Symbols
For the symbols not defined in this Section, refer to the list Table 2 : Coefficient for pressure on exposed decks
at the beginning of this Chapter.
Exposed deck location 1
: Sea water density, taken equal to 1,025 t/m3
h1 : Reference values of the ship relative motions in Freeboard deck and below 1,00
the upright ship condition, defined in Ch 5, Sec Top of lowest tier 0,75
3, [3.3] Top of second tier 0,56
h2 : Reference values of the ship relative motions in
Top of third tier 0,42
the inclined ship conditions, defined in Ch 5,
Sec 3, [3.3]. Top of fourth tier 0,32
Top of fifth tier 0,25
1 Still water pressure Top of sixth tier 0,20
Top of seventh tier 0,15
1.1 Pressure on sides and bottom
Top of eighth tier and above 0,10
1.1.1 The still water pressure at any point of the hull is
obtained from the formulae in Tab 1 (see also Fig 1). 2 Wave pressure
Table 1 : Still water pressure 2.1 Upright ship conditions (load cases a
Still water pressure pS,
and b)
Location
in kN/m2 2.1.1 Pressure on sides and bottom
Points at and below the waterline The wave pressure at any point of the sides and bottom is
g (T1 z)
(z T1) obtained from the formulae in Tab 3 (see also Fig 2 for load
Points above the waterline case a and Fig 3 for load case b).
0
(z > T1)
Figure 2 : Wave pressure in load case a
Figure 1 : Still water pressure Positive h1
h1
T1
T1
T1
Negative h1
1.2 Pressure on exposed decks
1.2.1 On exposed decks, the pressure due to the load carried
is to be considered. This pressure is to be defined by the
Designer and, in general, it may not be taken less than
1012 kN/m2, where 1 is defined in Tab 2, and 2 in Tab 4.
T1
The Society may accept pressure values lower than
1012 kN/m2, when considered appropriate on the basis
of the intended use of the deck.
Table 3 : Wave pressure on sides and bottom in upright ship conditions (load cases a and b)
Table 4 : Wave pressure on exposed decks in upright ship conditions (load cases a and b)
19, 6 H F 17 ,5 x
0,5 L < x < 0,75 L - --- 0, 5 n 1 2
17 ,5 + ----------------------------------------- 0
0 ,25 L
0,75 L x L 19 ,6n 1 2 H 0
Note 1:
2
H = C F1 2 ,66 --- 0 ,7 + 0 ,14
x VL
------- ( z T 1 ) without being taken less than 0,8
L CB
Figure 4 : Wave pressure in load case c Figure 5 : Wave pressure in load case d
Z Z
h2 0,5h2
T1 T1
Y Y
Table 5 : Wave pressure on sides, bottom and exposed decks in inclined ship conditions (load cases c and d)
g T 1 + C F2 ------- h 1 + A R y z
y
Sides above the waterline BW
0
(z > T1)
without being taken, for case c only, less than 0,15 1 2 L
0 ,4 g T 1 + C F2 ------- h 1 + A R y z
y
BW
Exposed decks 0
without being taken, for case c only, less than 0,15 1 2 L
(1) In the formulae giving the wave pressure pW, the ratio (y / BW) is not to be taken greater than 0,5.
Note 1:
1 : Coefficient defined in Tab 2
2 : Coefficient defined in Tab 4
CF2 : Combination factor, to be taken equal to:
CF2 = 1,0 for load case c
CF2 = 0,5 for load case d
BW : Moulded breadth, in m, measured at the waterline at draught T1 , at the hull transverse section considered
AR : Roll amplitude, defined in Ch 5, Sec 3, [2.4.1].
Symbols
For the symbols not defined in this Section, refer to the list C : Longitudinal distance, in m, between transverse
at the beginning of this Chapter. watertight bulkheads or transverse wash bulk-
heads, if any, or between a transverse watertight
L : Density, in t/m3, of the liquid carried
bulkhead and the adjacent transverse wash
B : Density, in t/m3, of the dry bulk cargo carried; in bulkhead; to this end, wash bulkheads are those
certain cases, such as spoils, the water held by satisfying the requirements in Ch 4, Sec 7, [5]
capillarity is to be taken into account bC : Transverse distance, in m, between longitudinal
zTOP : Z co-ordinate, in m, of the highest point of the watertight bulkheads or longitudinal wash bulk-
tank in the z direction heads, if any, or between a longitudinal water-
tight bulkhead and the adjacent longitudinal
zL : Z co-ordinate, in m, of the highest point of the wash bulkhead; to this end, wash bulkheads are
liquid: those satisfying the requirements in Ch 4, Sec 7,
[5]
zL = zTOP + 0,5 (zAP zTOP)
dTB : Vertical distance, in m, from the baseline to the
zAP : Z co-ordinate, in m, of the top of air pipe, to be tank bottom
taken not less than zTOP
dAP : Distance from the top of air pipe to the top of
pPV : Setting pressure, in bar, of safety valves compartment, in m
M : Mass, in t, of a dry unit cargo carried d0 : Distance, in m, to be taken equal to:
aX1,aY1,aZ1: Reference values of the accelerations in the d0 = 0,02 L for 65 m L < 120 m
upright ship condition, defined in Ch 5, Sec 3,
d0 = 2,4 for L 120 m.
[3.4], calculated in way of:
aX2,aY2,aZ2: Reference values of the accelerations in the 1.1.1 Still water pressure
inclined ship condition, defined in Ch 5, Sec 3,
The still water pressure to be used in combination with the
[3.4], calculated in way of:
inertial pressure in [1.1.2] is the greater of the values
the centre of gravity of the compartment, in obtained, in kN/m2, from the following formulae:
general
pS = L g (zL z)
the centre of gravity of any dry unit cargo, in
pS = L g (zTOP z) + 100 pPV
the case of this type of cargo
CFA : Combination factor, to be taken equal to: In no case is it to be taken, in kN/m2, less than:
0, 8L 1
CFA = 0,7 for load case c p S = L g --------------------
-
420 L 1
CFA = 1,0 for load case d
b L [ 0, 5a X1 B + a Z1 ( z TOP z ) ]
Inclined c
(negative roll angle) L [ a TY ( y y H ) + a TZ ( z z H ) + g ( z z TOP ) ]
d
Note 1:
B : Longitudinal distance, in m, between the transverse tank boundaries, without taking into account small recesses in the
lower part of the tank (see Fig 1)
aTY, aTZ : Y and Z components, in m/s2, of the total acceleration vector defined in [1.1.3] for load case c and load case d
yH, zH : Y and Z co-ordinates, in m, of the highest point of the tank in the direction of the total acceleration vector, defined in
[1.1.4] for load case c and load case d.
Figure 1 : Upright ship conditions - Distance B greatest distance from the tanks centre of gravity. It is to be
Z
determined for the inclined ship condition, as indicated in
Fig 2, where A and G are the vectors defined in [1.1.3] and
C is the tanks centre of gravity.
B
Components (negative roll angle)
Angle , in rad
aTY , in m/s2 aTZ , in m/s2
a TY
0,7 CFA aY2 0,7 CFA aZ2 g atan -------
a TZ
X
1.2 Swash bulkheads
1.1.3 Total acceleration vector
1.2.1 Still water and inertial pressures
The total acceleration vector is the vector obtained from the
The still water and inertial pressures transmitted to the
following formula:
swash bulkhead structures are obtained, in kN/m2, as speci-
fied in Tab 3.
AT = A + G
the ship roll motion and the transverse motion of the liq-
uid inside the tank, for inclined ship condition
Ship Resonance
Risk of resonance if: dF
condition due to:
T d watertight or wash transverse
Upright 0 ,6 < -----X < 1 ,3 and -----F > 0 ,1 Pitch bulkheads
TP C
T d
Inclined 0 ,8 < -----Y < 1 ,2 and -----F- > 0 ,1 Roll
TR bC
Figure 4 : Breadth bS of the free surface of the liquid, Figure 5 : Breadth bS of the free surface of the liquid,
for ships without longitudinal bulkheads for ships with longitudinal bulkheads
bS/2
bS/2
bS/2
bS bS/2
dF dF
dF
dF
bS/2 bS/2 bS
dF
dF
bS/2 bS bS/2
dF
dF
pS = L g (dF + dTB z) + 100 pPV for z < dF + dTB 2.4.2 Inclined ship condition
Where there is a risk of resonance in inclined ship condi-
pS = 100 pPV for z dF + dTB tion for a filling level dF, the dynamic sloshing pressure pSL
calculated according to [2.4.3] is to be considered as acting
2.3.2 Still water pressure to be used in combination on longitudinal bulkheads, inner sides or sides which, as
with the dynamic impact pressure the case may be, form tank boundaries, in the area
extended vertically 0,2 dF above and below dF (see Fig 6).
The still water pressure to be used in combination with the
However, the dynamic sloshing pressure may not be con-
dynamic impact pressure defined in [2.5] is to be obtained,
sidered where there is a risk of resonance for filling levels dF
in kN/m2, from the following formulae: lower than 0,5 H.
pS = L g (0,7 H + dTB z) + 100 pPV for z < 0,7 H + dTB If sloped longitudinal topsides are fitted, they are to be con-
sidered as subjected to the sloshing pressure if their height
pS = 100 pPV for z 0,7 H + dTB is less than 0,3 H.
where:
p0 : Reference pressure defined in Tab 5 for upright
and inclined ship conditions
: Coefficient taken equal to (see Fig 7):
0,2dF dF
= ------------- for d F < 0 ,6H
0 ,6H
H 0,2dF
=1 for 0 ,6H d F 0 ,7H
p0 H dF
= ---------------- for d F > 0 ,7H
dF 0 ,3H
Figure 7 : Coefficient
0,7H
0,2dF 0,6H
H 0,2dF
p0
dF
2.4.5 Alternative methods the tank top in the area extended transversely 0,3bC
from the above longitudinal bulkheads, inner sides or
The Society may accept that the dynamic sloshing pressure
sides.
is evaluated on the basis of dynamic calculation proce-
dures, where deemed necessary in relation to the tanks
However, the dynamic impact pressure may not be consid-
dimensions and the ships characteristics. The calculations
ered for filling levels dF lower than 0,5H.
are to be submitted to the Society for verification.
Where the upper part of a longitudinal bulkhead, inner side
2.5 Dynamic impact pressure or side is sloped, the impact pressure is to be considered as
acting on this sloped part and the tank top (as the case may
2.5.1 Upright ship condition be) in the area extended transversely 0,3 bC from the longi-
Where there is a risk of resonance in upright ship condition, tudinal bulkhead, inner side or side.
for tanks having arrangements such that S is greater than
The impact pressure is obtained, in kN/m2, from the follow-
0,13 L at any filling level dF from 0,05 H to 0,95 H, the ing formula:
dynamic impact pressure due to liquid motions is to be con-
sidered as acting on: p I ,I = 0 ,61 I L g ( 0 ,75B 8 )b C A R
transverse bulkheads which form tank boundaries, in
where:
the area extended vertically 0,15 H from the tank top
the tank top in the area extended longitudinally 0,3 C I : Coefficient defined in Tab 5.
from the above transverse bulkheads. Where the upper part of a longitudinal bulkhead, inner side
However, the dynamic impact pressure may not be consid- or side is sloped, the pressure pI,I may be multiplied by the
ered for filling levels dF lower than 0,5 H. coefficient obtained from the following formula:
Ship condition Load case Still water pressure pS and inertial pressure pW, in kN/m2
Still water
2
2
p S = B g ( z B z ) ( sin ) tan 45 ---
2 o
+ ( cos )
2
2
2
p W = B a Z1 ( z B z ) ( sin ) tan 45 ---
2 o
b + ( cos )
2
Inclined c The inertial pressure transmitted to the hull structures in inclined condition may gen-
erally be disregarded. Specific cases in which this simplification is not deemed per-
d missible by the Society are considered individually.
Note 1:
zB : Z co-ordinate, in m, of the rated upper surface of the bulk cargo (horizontal ideal plane of the volume filled by the
cargo); see [3.1.2]
: Angle, in degrees, between the horizontal plane and the surface of the hull structure to which the calculation point belongs
: Angle of repose, in degrees, of the bulk cargo (considered drained and removed); in the absence of more precise evalu-
ation, the following values may be taken:
= 30 in general
= 35 for iron ore
= 25 for cement.
3.1.2 Rated upper surface of the bulk cargo yHT : Half breadth, in m, of the hold, measured at the
middle of H and at a vertical level correspond-
The Z co-ordinate of the rated upper surface of the bulk
ing to the top of the hopper tank.
cargo is obtained, in m, from the following formula (see
Fig 8):
Figure 8 : Rated upper surface of the bulk cargo
M C V LS
----------- + -------- + ( h HT h DB )b HT
B H H
z B = ---------------------------------------------------------------------- + h DB
2y HT
where:
4.1 Still water and inertial pressures 6.1 Still water and inertial forces
4.1.1 General 6.1.1 General
The still water and inertial pressures are obtained, in kN/m2, Caterpillar trucks and unusual vehicles are considered by
as specified in Tab 7. the Society on a case by case basis.
The load supported by the crutches of semi-trailers, han-
Table 7 : Dry uniform cargoes
dling machines and platforms is considered by the Society
Still water and inertial pressures
on a case by case basis.
Ship Load Still water pressure pS 6.1.2 Tyred vehicles
condition case and inertial pressure pW, in kN/m2
The forces transmitted through the tyres are comparable to
Still The value of pS is generally specified by pressure uniformly distributed on the tyre print, whose
water the Designer; in any case, it may not be dimensions are to be indicated by the Designer together
taken less than 10 kN/m2. with information concerning the arrangement of wheels on
When the value of pS is not specified by
axles, the load per axles and the tyre pressures.
the Designer, it may be taken, in kN/m2,
equal to 6,9 hTD , where hTD is the com- With the exception of dimensioning of plating, such forces
partment tweendeck height at side, in m. may be considered as concentrated in the tyre print centre.
Upright a No inertial pressure The still water and inertial forces transmitted to the hull
(positive structures are to be determined on the basis of the forces
heave a Z1
b p W ,Z = p S ------- in z direction obtained, in kN, as specified in Tab 9.
motion) g
4.1.2 General cargo ships with the service notation Still water (1) (2) FS = M g
completed with the additional service feature Upright (positive a No inertial force
heavycargo heave motion) (1)
b FW,Z = M aZ1 in z direction
For ships with the service notation general cargo ship com-
pleted by the additional service feature heavycargo Inclined (negative c FW,Y = M CFA aY2 in y direction
[AREA1, X1 kN/m2 -AREA2, X2 kN/m2 - ....] (see Pt A, Ch 1, roll angle) (2)
d FW,Z = M CFA aZ2 in z direction
Sec 2, [4.2.2]), the values of pS, in kN/m2, are to be speci-
Loading/ FW,X = 0,035 M g in x direction
fied by the Designer for each AREAi, according to [4.1.1],
unloading (3) FW,Y = 0,087 M g in y direction
and introduced as Xi values in the above service feature.
FW,Z = 0,100 M g in z direction
5 Dry unit cargoes (1) This condition defines the force, applied by one wheel,
to be considered for the determination of scantlings of
plating, ordinary stiffeners and primary supporting
5.1 Still water and inertial forces
members, as defined in Part B, Chapter 7, where:
5.1.1 The still water and inertial forces transmitted to the : Coefficient taken equal to:
hull structures are to be determined on the basis of the 0,5 in general
forces obtained, in kN, as specified in Tab 8, taking into 1,0 for landing gears of trailers
account the elastic characteristics of the lashing arrange- M : Mass, in t, taken equal to
ment and/or the structure which contains the cargo. Q
M = ------A-
nW
Table 8 : Dry unit cargoes
Still water and inertial forces QA : Axle load, in t. For fork-lift trucks, the
value of QA is to be taken equal to the total
Ship Load Still water force FS mass of the vehicle, including that of the
condition case and inertial force FW, in kN cargo handled, applied to one axle only.
Still water FS = M g nW : Number of wheels for the axle considered.
(2) This condition is to be considered for the racking analy-
Upright (positive a No inertial force sis of ships with the service notation ro-ro cargo ship or
heave motion) ro-ro passenger ship, as defined in Ch 7, App 1, with M
b FW,X = M aX1 in x direction
FW,Z = M aZ1 in z direction taken equal to the mass, in t, of wheeled loads located
on the structural member under consideration.
Inclined (negative c FW,Y = M CFA aY2 in y direction
(3) Loading/unloading condition is to be considered only
roll angle) FW,Z = M CFA aZ2 in z direction
d for fork-lift trucks.
For vehicles on rails, all the forces transmitted are to be con- Still water pS = 10
sidered as concentrated at the contact area centre. Upright a No inertial pressure
(positive
heave b a Z1
p W = p S -------
7 Accommodation motion) g
Inclined c The inertial pressure transmitted to the pSF = g dF without being taken less than 0,4 g d0
deck structures in inclined condition
may generally be disregarded. Specific pWF = 0,6 aZ1 dF without being taken less than 0,4 g d0
d cases in which this simplification is not
deemed permissible by the Society are where:
considered individually.
dF : Distance, in m, from the calculation point to the
deepest equilibrium waterline.
Table 11 : Still water deck pressure
The deepest equilibrium waterlines are to be
in accommodation compartments
provided by the Designer under his own
responsibility.
Type of accommodation compartment pS , in kN/m2
Large public spaces, such as: 5,0 Table 13 : Flooding - Still water and inertial pressures
restaurants, halls, cinemas, lounges for ships for which damage stability calculations
are not required
Large rooms, such as: 3,0
rooms with fixed furniture
Still water pressure pSF , Inertial pressure pWF ,
games and hobbies rooms, hospitals
in kN/m2 in kN/m2
Cabins 3,0
Compartment located Compartment located
Other compartments 2,5 below bulkhead deck: below bulkhead deck:
g (zF z) 0,6 aZ1 (zF z)
without being taken less without being taken less
8 Machinery than 0,4 g d0 than 0,4 g d0
Compartment located Compartment located
8.1 Still water and inertial pressures immediately above the immediately above the
bulkhead deck: bulkhead deck:
8.1.1 The still water and inertial pressures transmitted to 0,32 g d0 0,32 g d0
the deck structures are obtained, in kN/m2, as specified in Note 1:
Tab 12. zF : Z co-ordinate, in m, of the bulkhead deck.
1 Liquid cargoes and ballast - Inertial identified and the relevant formulae written using the tank
geometric characteristics.
pressure
1.1.2 This Appendix provides the formulae for calculating
1.1 Introduction the inertial pressure pW in the case of typical tank arrange-
ments.
1.1.1 Ch 5, Sec 6, [1] defines the criteria to calculate the
inertial pressure pW induced by liquid cargoes and ballast in 1.2 Formulae for the inertial pressure
any type of tank. The relevant formulae are specified in Ch calculation
5, Sec 6, Tab 1 and entail the definition of the highest point
of the tank in the direction of the total acceleration vector. 1.2.1 For typical tank arrangements, the inertial pressure
As specified in Ch 5, Sec 6, [1.2], this point depends on the transmitted to the hull structures at the calculation point P
geometry of the tank and the values of the acceleration. For in inclined ship condition may be obtained from the formu-
typical tank arrangements, the highest point of the tank in lae in Tab 1, obtained by applying to those tanks the general
the direction of the total acceleration vector can easily be formula in Ch 5, Sec 6, Tab 1.
Table 1 : Liquid cargoes and ballast - Inertial pressure for typical tank arrangements
Inclined c
(negative roll angle) 0, 7C FA L ( a Y2 b L + a Z2 d H )
d
Note 1:
CFA : Combination factor, to be taken equal to:
CFA = 0,7 for load case c
CFA = 1,0 for load case d
L : Density, in t/m3, of the liquid cargo carried
aY2, aZ2 : Reference values of the acceleration in the inclined ship condition, defined in Ch 5, Sec 3, [3.4], calculated in way of
the centre of gravity of the tank
bL, dH : Transverse and vertical distances, in m, to be taken as indicated in Fig 1 to Fig 6 for various types of tanks; for the cases
in Fig 1 to Fig 4, where the central cargo area is divided into two or more tanks by longitudinal bulkheads, bL and dH for
calculation points inside each tank are to be taken as indicated in Fig 5 for the double side. The angle which appears
in Fig 3 and Fig 4 is defined in Ch 5, Sec 6, Tab 2.
bT At calculation point P
dH bL = 0,5bT+dCT
At calculation point P
P bL = 0,5bT+dCT
dCT
dCT
dH
bT
bT
dH
At calculation point P
bL = 0,5bT+dCT
P
dCT
: bL = bT
At calculation point P1 in
bT At calculation point P2 in : bL = dT
dH dH
dT
P1
bL = bT P2
bL = dT
Chapter 6
Symbols
For symbols not defined in this Section, refer to the list at 2.1.4 Longitudinal girders between hatchways
the beginning of this Chapter. Where longitudinal girders are fitted between hatchways,
the sectional area that can be included in the hull girder
1 Application transverse sections is obtained, in m2, from the following
formula:
1.1 AEFF = ALG a
1.1.1 This Section specifies the criteria for calculating the where:
hull girder strength characteristics to be used for the checks
in Ch 6, Sec 2 and Ch 6, Sec 3, in association with the hull ALG : Sectional area, in m2, of longitudinal girders
girder loads specified in Ch 5, Sec 2. a : Coefficient:
for longitudinal girders effectively supported
2 Calculation of the strength by longitudinal bulkheads or primary sup-
characteristics of hull girder porting members:
transverse sections a=1
for longitudinal girders not effectively sup-
2.1 Hull girder transverse sections ported by longitudinal bulkheads or primary
supporting members and having dimensions
2.1.1 General
and scantlings such that 0 / r 60:
Hull girder transverse sections are to be considered as being
constituted by the members contributing to the hull girder 0 ,5
a = 0 ,6 ----- + 0 ,15
s
longitudinal strength, i.e. all continuous longitudinal mem- b1
bers below the strength deck defined in [2.2], taking into
account the requirements in [2.1.2] to [2.1.9]. for longitudinal girders not effectively sup-
ported by longitudinal bulkheads or primary
These members are to be considered as having (see also Ch 4,
supporting members and having dimensions
Sec 2):
and scantlings such that 0 / r > 60:
gross scantlings, when the hull girder strength character-
istics to be calculated are used for the yielding checks in a=0
Ch 6, Sec 2
0 : Span, in m, of longitudinal girders, to be taken
net scantlings, when the hull girder strength characteris- as shown in Fig 1
tics to be calculated are used for the ultimate strength
checks in Ch 6, Sec 3 and for calculating the hull girder r : Minimum radius of gyration, in m, of the longi-
stresses for the strength checks of plating, ordinary stiffen- tudinal girder transverse section
ers and primary supporting members in Part B, Chapter s, b1 : Dimensions, in m, defined in Fig 1.
7.
2.1.2 Continuous trunks and continuous Figure 1 : Longitudinal girders between hatchways
longitudinal hatch coamings
Continuous trunks and continuous longitudinal hatch com-
0
mons may be included in the hull girder transverse sections,
provided they are effectively supported by longitudinal
bulkheads or primary supporting members. b1
2.1.8 Small openings 2.2.1 The strength deck is, in general, the uppermost con-
Smaller openings than those in [2.1.7] in one transverse tinuous deck.
section in the strength deck or bottom area need not be In the case of a superstructure or deckhouses contributing
deducted from the sectional areas included in the hull to the longitudinal strength, the strength deck is the deck of
girder transverse sections, provided that: the superstructure or the deck of the uppermost deckhouse.
bS 0,06 (B b) 2.2.2 A superstructure extending at least 0,15 L within 0,4
where: L amidships may generally be considered as contributing to
the longitudinal strength. For other superstructures and for
bS : Total breadth of small openings, in m, in the
deckhouses, their contribution to the longitudinal strength
strength deck or bottom area at the transverse
is to be assessed on a case by case basis, through a finite
section considered, determined as indicated in
element analysis of the whole ship, which takes into
Fig 2
account the general arrangement of the longitudinal ele-
b : Total breadth of large openings, in m, at the ments (side, decks, bulkheads).
transverse section considered, determined as
The presence of openings in the side shell and longitudinal
indicated in Fig 2
bulkheads is to be taken into account in the analysis. This
Where the total breadth of small openings bS does not ful- may be done in two ways:
fil the above criteria, only the excess of breadth is to be by including these openings in the finite element model
deducted from the sectional areas included in the hull
girder transverse sections. by assigning to the plate panel between the side frames
beside each opening an equivalent thickness, in mm,
Additionally, individual small openings which do not com- obtained from the following formula:
ply with the arrangement requirements given in Ch 4, Sec 6, 2 1
t EQ = 10 P ------------- + -----
[6.1], are to be deducted from the sectional areas included 3 Gh 1
in the hull girder transverse sections. 12EI J A J
y
Figure 3 : Side openings V D = ( z T N ) 0 ,9 + 0 ,2 -----T z D N
B
Side frames
where:
y yT , z T : Y and Z co-ordinates, in m, of
the top of continuous trunk or
h x x hatch coaming with respect to
the reference co-ordinate system
y defined in Ch 1, Sec 2, [4]; yT
p Cross section of and zT are to be measured for
the opening jamb the point which maximises the
value of VD
2.3 Section modulus if longitudinal ordinary stiffeners or girders
welded above the strength deck are taken
2.3.1 The section modulus at any point of a hull transverse into account in the calculation of IY , as
section is obtained, in m3, from the following formula: specified in [2.1.3], VD is to be obtained
IY from the formula given above for continu-
Z A = ---------------
- ous trunks and hatch coamings. In this case,
zN
yT and zT are the Y and Z co-ordinates, in m,
where: of the top of the longitudinal stiffeners or
IY : Moment of inertia, in m4, of the hull transverse girders with respect to the reference co-ordi-
section defined in [2.1], about its horizontal nate system defined in Ch 1, Sec 2, [4].
neutral axis
z : Z co-ordinate, in m, of the calculation point 2.4 Moments of inertia
with respect to the reference co-ordinate system
defined in Ch 1, Sec 2, [4] 2.4.1 The moments of inertia IY and IZ , in m4, are those,
N : Z co-ordinate, in m, of the centre of gravity of calculated about the horizontal and vertical neutral axes,
the hull transverse section defined in [2.1], with respectively, of the hull transverse sections defined in [2.1].
respect to the reference co-ordinate system
defined in Ch 1, Sec 2, [4]. 2.5 First moment
2.3.2 The section moduli at bottom and at deck are
2.5.1 The first moment S, in m3, at a level z above the base-
obtained, in m3, from the following formulae: line is that, calculated with respect to the horizontal neutral
at bottom: axis, of the portion of the hull transverse sections defined in
[2.1] located above the z level.
I
Z AB = ---Y-
N
2.6 Structural models for the calculation of
at deck:
normal warping stresses and shear
IY
Z AD = ------
stresses
VD
2.6.1 The structural models that can be used for the calcu-
where: lation of normal warping stresses, induced by torque, and
IY, N : Defined in [2.3.1] shear stresses, induced by shear forces or torque, are:
Symbols
For symbols not defined in this Section, refer to the list at 1 Application
the beginning of this Chapter.
2.2 Normal stresses induced by torque and The shear force corrections QC and Q are to be taken
bending moments into account, in accordance with [2.4.1] and [2.4.2],
respectively.
2.2.1 Ships having large openings in the strength
deck 2.3.2 The vertical shear forces to be considered in these
The normal stresses induced by torque and bending analyses are:
moments are to be considered for ships having large open-
ings in the strength decks, i.e. ships for which at least one of for all ships, the vertical shear forces QSW and QWV, tak-
the three following conditions occur: ing into account the combination factors defined in Ch 5,
Sec 4, Tab 2
b / B0 > 0,7
in addition, for ships having large openings in the
A / 0 > 0,89
strength deck, the shear forces due to the torques MWT
b / B0 > 0,6 and A / 0 > 0,7 and MSW,T as specified in [2.2].
where b, B0 , A and 0 are the dimensions defined in Fig 1. When deemed necessary by the Society on the basis of the
In the case of two or more openings in the same hull trans- ships characteristics and intended service, the horizontal
verse section, b is to be taken as the sum of the breadth b1 shear force is also to be calculated, using direct calcula-
of each opening. tions, and taken into account in the calculation of shear
stresses.
2.2.2 Normal stresses
The normal stresses are to be calculated for the load case 2.3.3 As an alternative to the above procedure, the shear
constituted by the hull girder loads specified in Tab 1 stresses induced by the vertical shear forces QSW and QWV
together with their combination factors. They are to be may be obtained through the simplified procedure in [2.4].
obtained, in N/mm2, from the following formula:
Figure 1 : Ships with large openings
M SW 0.4M WV M WH 3
1 = ----------
- + -------------------- + ------------ y 10 +
ZA ZA IZ A
where:
: Warping stress, in N/mm2, induced by the
torque MWT and obtained through direct calcu-
B0
b1
2.4 Simplified calculation of shear stresses QC : Shear force correction (see Fig 2), which takes
induced by vertical shear forces into account, when applicable, the portion of
loads transmitted by the double bottom girders
2.4.1 Ships without effective longitudinal bulkheads to the transverse bulkheads:
or with one effective longitudinal bulkhead
for ships with double bottom in alternate
In this context, effective longitudinal bulkhead means a loading conditions:
bulkhead extending from the bottom to the strength deck.
P
The shear stresses induced by the vertical shear forces in the Q C = ------------ T 1
BH C
calculation point are obtained, in N/mm2, from the follow-
ing formula: for other ships:
S
1 = ( Q SW + Q WV Q C ) ------ QC = 0
IY t
with:
where:
t : Minimum thickness, in mm, of side, inner side 0 b0
= g ------------------
-
and longitudinal bulkhead plating, as applica-
2 + ----0-
ble according to Tab 2 b0
: Shear distribution coefficient defined in Tab 2 = 1 ,38 + 1 ,55 ----0- 3 ,7
b0
= sgn(QSW)
0 , b0 : Length and breadth, respectively, in
Figure 2 : Shear force correction QC m, of the flat portion of the double
bottom in way of the hold consid-
ered; b0 is to be measured on the
Qc
Note 1:
tS, tIS, tB : Minimum thicknesses, in mm, of side, inner side and longitudinal bulkhead plating, respectively
tSM, tISM, tBM : Mean thicknesses, in mm, over all the strakes of side, inner side and longitudinal bulkhead plating, respectively. They
are calculated as (i ti) / i, where i and ti are the length, in m, and the thickness, in mm, of the ith strake of side, inner
side and longitudinal bulkhead.
where:
4.2.2 For ships with CB less than or equal to 0,8, the gross
1,ALL : Allowable normal stress, in N/mm2, taken equal section moduli ZAB and ZAD at the midship section are to be
to: not less than the value obtained, in m3, from the following
formula:
175
1, ALL = ----------
k ZR,MIN = n1 C L2 B (CB + 0,7) k 106
In addition, the gross section moduli ZAB and ZAD within where:
0,4L amidships are to be not less than the value obtained, in 1B, 1D : Normal stresses, in N/mm2, at bottom and deck,
m3, from the following formula: respectively, calculated according to [2.1.1]
M SW + M WV 3 zD : Z co-ordinate, in m, of the strength deck,
Z R = ----------------------------
- 10
1, ALL defined in Ch 6, Sec 1, [2.2], with respect to the
reference co-ordinate system defined in Ch 1,
4.2.3 Where the total breadth bS of small openings, as Sec 2, [4]
defined in Ch 6, Sec 1, [2.1.8], is deducted from the sec- N : Z co-ordinate, in m, of the centre of gravity of
tional areas included in the hull girder transverse sections, the hull transverse section defined in Ch 6, Sec
the values ZR and ZR,MIN defined in [4.2.1] or [4.2.2] may be 1, [2.3.1], with respect to the reference co-ordi-
reduced by 3%. nate system defined in Ch 1, Sec 2, [4]
4.2.4 Scantlings of members contributing to the longitudi- VD : Vertical distance, in m, defined in Ch 6, Sec 1,
nal strength (see Ch 6, Sec 1, [2]) are to be maintained [2.3.2].
within 0,4 L amidships.
4.5.2 The higher strength steel is to extend in length at least
throughout 0,4 L amidships where it is required for strength
4.3 Section modulus outside 0,4L amidships purposes according to the provisions of Part B.
4.3.1 The gross section moduli ZAB and ZAD outside 0,4 L
amidships are to be not less than the value obtained, in m3, 5 Permissible still water bending moment
from the following formula: and shear force during navigation
M SW + M WV 3
Z R = ----------------------------
- 10
1, ALL 5.1 Permissible still water bending moment
4.3.2 Scantlings of members contributing to the hull girder 5.1.1 The permissible still water bending moment at any
longitudinal strength (see Ch 6, Sec 1, [2]) may be gradually hull transverse section during navigation, in hogging or sag-
reduced, outside 0,4L amidships, to the minimum required ging conditions, is the value MSW considered in the hull
for local strength purposes at fore and aft parts, as specified girder section modulus calculation according to [4.2] and
in Part B, Chapter 8. [4.3].
In the case of structural discontinuities in the hull transverse
4.4 Midship section moment of inertia sections, the distribution of permissible still water bending
moments is considered on a case by case basis.
4.4.1 The gross midship section moment of inertia about its
horizontal neutral axis is to be not less than the value 5.2 Permissible still water shear force
obtained, in m4, from the following formula:
n 2
5.2.1 Direct calculations
I YR = 3 ----- Z R, MIN L 10
n1 Where the shear stresses are obtained through calculation
where ZR,MIN is the required midship section modulus analyses according to [2.3], the permissible positive or neg-
ative still water shear force at any hull transverse section is
ZR,MIN, in m3, calculated as specified in [4.2.1] or [4.2.2],
obtained, in kN, from the following formula:
but assuming k = 1.
QP = |QT| QWV
4.5 Extent of higher strength steel where:
= sgn(QSW)
4.5.1 When a material factor for higher strength steel is
used in calculating the required section modulus at bottom QT : Shear force, in kN, which produces a shear
or deck according to [4.2] or [4.3], the relevant higher stress = 110/k N/mm2 in the most stressed
strength steel is to be adopted for all members contributing point of the hull transverse section, taking into
to the longitudinal strength (see Ch 6, Sec 1, [2]), at least up account the shear force correction QC and Q
to a vertical distance, in m, obtained from the following for- in accordance with [2.4.1] and [2.4.2], respec-
mulae: tively.
above the baseline (for section modulus at bottom):
5.2.2 Ships without effective longitudinal bulkheads
1B k 1, ALL or with one effective longitudinal bulkhead
V HB = ------------------------------
-z
1B + 1D D Where the shear stresses are obtained through the simpli-
below a horizontal line located at a distance VD (see Ch fied procedure in [2.4.1], the permissible positive or nega-
6, Sec 1, [2.3.2]) above the neutral axis of the hull trans- tive still water shear force at any hull transverse section is
verse section (for section modulus at deck): obtained, in kN, from the following formula:
1D k 1, ALL 110 I Y t
V HD = -------------------------------
- ( N + VD ) Q P = ---------- -----
- + Q C Q WV
1B + 1D k S
Symbols
For symbols not defined in this Section, refer to the list at MH = S1 MP,H + 0,1 W1 MWV
the beginning of this Chapter.
where MP,H is the permissible still water bending moment in
harbour conditions, defined in Ch 6, Sec 2, [6.1.1].
1 Application
3.2 Hull girder ultimate bending moment
1.1
capacities
1.1.1 The requirements of this Section apply to ships equal
to or greater than 170 m in length. 3.2.1 Curve M-
The ultimate bending moment capacities of a hull girder
2 General transverse section, in hogging and sagging conditions, are
defined as the maximum values of the curve of bending
moment capacity M versus the curvature of the transverse
2.1 Net scantlings section considered (see Fig 1).
2.1.1 As specified in Ch 4, Sec 2, [1], the ultimate strength The curvature is positive for hogging condition and nega-
of the hull girder is to be checked on the basis of the net tive for sagging condition.
strength characteristics of the transverse section which is to
be calculated according to Ch 4, Sec 2, [2]. The curve M- is to be obtained through an incremental-iter-
ative procedure according to the criteria specified in Ch 6,
App 1.
2.2 Partial safety factors
2.2.1 The partial safety factors to be considered for check- Figure 1 : Curve bending moment capacity M
ing the ultimate strength of the hull girder are specified in versus curvature
Tab 1. M
Table 1 : Partial safety factors Hogging condition
MUH
Partial safety factor covering
Symbol Value
uncertainties on:
- F
Still water hull girder loads S1 1,00
F
Wave induced hull girder loads W1 1,10
Material m 1,02 Sagging condition MUS
Resistance R 1,03
3 Hull girder ultimate strength check 3.2.2 Hull girder transverse sections
The hull girder transverse sections are constituted by the
3.1 Hull girder loads elements contributing to the hull girder longitudinal
strength, considered with their net scantlings, according to
3.1.1 Bending moments in navigation Ch 6, Sec 1, [2].
The bending moment in navigation, in sagging and hogging
conditions, to be considered in the ultimate strength check 3.3 Checking criteria
of the hull girder, is to be obtained, in kN.m, from the fol-
lowing formula: 3.3.1 It is to be checked that the hull girder ultimate bend-
M = S1 MSW + W1 MWV ing capacity at any hull transverse section is in compliance
with the following formulae:
3.1.2 Bending moments in harbour conditions
MU
The bending moment in harbour conditions, in sagging and ---------- M
R m
hogging conditions, to be considered in the ultimate
strength check of the hull girder, is to be obtained, in kN.m, MU
---------- MH
from the following formula: R m
Symbols
For symbols not defined in this Appendix, refer to the list at Figure 1 : Curve bending moment capacity M
the beginning of this Chapter. versus curvature
ReH : Minimum upper yield stress, in N/mm2, of the M
material
MUH
IY : Moment of inertia, in m4, of the hull transverse Hogging condition
section around its horizontal neutral axis, to be
calculated according to Ch 6, Sec 1, [2.4]
ZAB ,ZAD : Section moduli, in cm3, at bottom and deck,
respectively, defined in Ch 6, Sec 1, [2.3.2] - F
s : Spacing, in m, of ordinary stiffeners F
: Span, in m, of ordinary stiffeners, measured
between the supporting members (see Ch 4, Sec Sagging condition MUS
3, Fig 2 to Ch 4, Sec 3, Fig 5)
hw : Web height, in mm, of an ordinary stiffener
tw : Web net thickness, in mm, of an ordinary stiff- Each step of the incremental procedure is represented by
ener the calculation of the bending moment Mi which acts on
the hull transverse section as the effect of an imposed cur-
bf : Face plate width, in mm, of an ordinary stiffener
vature i.
tf : Face plate net thickness, in mm, of an ordinary
stiffener For each step, the value i is to be obtained by summing an
increment of curvature to the value relevant to the previ-
AS : Net sectional area, in cm2, of an ordinary stiff- ous step i-1.This increment of curvature corresponds to an
ener increment of the rotation angle of the hull girder transverse
tp : Net thickness, in mm, of the plating attached to section around its horizontal neutral axis.
an ordinary stiffener. This rotation increment induces axial strains in each hull
structural element, whose value depends on the position of
1 Hull girder ultimate strength check the element. In hogging condition, the structural elements
above the neutral axis are lengthened, while the elements
below the neutral axis are shortened. Vice-versa in sagging
1.1 Introduction condition.
1.1.1 Ch 6, Sec 3, [2] defines the criteria for calculating The stress induced in each structural element by the strain
the ultimate bending moment capacities in hogging condi- is to be obtained from the load-end shortening curve -
tion MUH and sagging condition MUS of a hull girder trans- of the element, which takes into account the behaviour of
verse section. the element in the non-linear elasto-plastic domain.
As specified in Ch 6, Sec 3, [2], the ultimate bending The distribution of the stresses induced in all the elements
moment capacities are defined as the maximum values of composing the hull transverse section determines, for each
the curve of bending moment capacity M versus the curva- step, a variation of the neutral axis position, since the rela-
ture of the transverse section considered (see Fig 1). tionship - is non-linear. The new position of the neutral
axis relevant to the step considered is to be obtained by
1.1.2 This Appendix provides the criteria for obtaining the means of an iterative process, imposing the equilibrium
curve M-. among the stresses acting in all the hull elements.
Once the position of the neutral axis is known and the rele-
1.2 Criteria for the calculation of the curve vant stress distribution in the section structural elements is
M- obtained, the bending moment of the section Mi around the
new position of the neutral axis, which corresponds to the
1.2.1 Procedure curvature i imposed in the step considered, is to be
The curve M- is to be obtained by means of an incremen- obtained by summing the contribution given by each ele-
tal-iterative approach, summarised in the flow chart in Fig 2. ment stress.
Figure 2 : Flow chart of the procedure for the evaluation of the curve M-
Start
First step
i-1= 0
i-1 = i NO F = 1
1 2 = specified tolerance on zero value
YES
YES
NO > F
YES
End
1.3 Load-end shortening curves -
ReH
1.3.1 Plating panels and ordinary stiffeners
Plating panels and ordinary stiffeners composing the hull
girder transverse sections may collapse following one of the
modes of failure specified in Tab 1.
2 ,25 1 ,25
b E = ----------- ----------- s for E > 1 ,25
E E2
bE = s for E 1 ,25
s R eH
E = 10 3 --- -----------
tp E
1.3.6 Web local buckling of flanged ordinary
stiffeners
Figure 4 : Load-end shortening curve CR1-
for beam column buckling The equation describing the load-end shortening curve
CR3- for the web local buckling of flanged ordinary stiffen-
ers composing the hull girder transverse section is to be
CR1 obtained from the following formula:
C1 10 3 b E t P + h WE t W + b F t F
CR3 = R eH -------------------------------------------------------
-
10 3 st P + h W t W + b F t F
where:
: Edge function defined in [1.3.3]
bE : Width, in m, of the attached shell plating,
defined in [1.3.4]
hWE : Effective height, in mm, of the web:
1.3.5 Torsional buckling
2 ,25 1 ,25
h WE = ----------- ----------- h for W > 1 ,25
The equation describing the load-end shortening curve W W 2 W
1.3.7 Web local buckling of flat bar ordinary 1.3.8 Plate buckling
stiffeners
The equation describing the load-end shortening curve
The equation describing the load-end shortening curve CR5- for the buckling of transversely stiffened panels com-
CR4- for the web local buckling of flat bar ordinary stiffen- posing the hull girder transverse section is to be obtained
ers composing the hull girder transverse section is to be from the following formula:
obtained from the following formula (see Fig 6):
10st P CP + A S C4 R eH
CR4 = -------------------------------------------
A S + 10st P CR5 = min s 2 ,25 1 ,25 1 2
R eH - ----------- ----------- + 0 ,1 1 -- 1 + -----2
s
2
where: E E E
12 ( 1 ) b
2 4
K 3 = 2 1 + 1 + -------------------------
4
- -------
2 2
- 10 6
r t
r : Radius of curvature, in m.
Chapter 7
HULL SCANTLINGS
SECTION 1 PLATING
SECTION 1 PLATING
Symbols
For symbols not defined in this Section, refer to the list at ca : Aspect ratio of the plate panel, equal to:
the beginning of this Chapter.
s 2
c a = 1 ,21 1 + 0 ,33 -- 0 ,69 -
s
pS : Still water pressure, in kN/m2, see [3.2.2]
pW : Wave pressure and, if necessary, dynamic pres- to be taken not greater than 1,0
sures, in kN/m2 (see [3.2.2]) cr : Coefficient of curvature of the panel, equal to:
pSF, pWF : Still water and wave pressure, in kN/m2, in cr = 1 0,5 s / r
flooding conditions, defined in Ch 5, Sec 6, [9] to be taken not less than 0,5
(see [3.2.3])
r : Radius of curvature, in m
FS : Still water wheeled force, in kN, see [4.2.2]
t : Net thickness, in mm, of a plate panel.
FW,Z : Inertial wheeled force, in kN, see [4.2.2]
X1 : In-plane hull girder normal stress, in N/mm2, 1 General
defined in:
[3.2.5] for the strength check of plating sub- 1.1 Net thicknesses
jected to lateral pressure
1.1.1 As specified in Ch 4, Sec 2, [1], all thicknesses
[5.2.2] for the buckling check of plating referred to in this Section are net, i.e. they do not include
1 : In-plane hull girder shear stress, in N/mm2, any margin for corrosion.
defined in [3.2.6] The gross thicknesses are obtained as specified in Ch 4, Sec 2.
: Length, in m, of the longer side of the plate 1.2.1 The partial safety factors to be considered for the
panel checking of the plating are specified in Tab 1.
1.4 Load point Table 2 : Minimum net thickness of plating (in mm)
The net thickness of a rounded sheerstrake is to be not less 2.7.1 The net thickness of deck plating protected by wood
than the actual net thickness of the adjacent deck plating. sheathing, deck composition or other arrangements deemed
suitable by the Society may be reduced on a case by case
basis. In any case this net thickness is to be not less than the
2.5.3 Net thickness of the sheerstrake in way of
minimum value given in Tab 2.
breaks of long superstructures
The net thickness of the sheerstrake is to be increased in 2.7.2 The sheathing is to be secured to the deck to the satis-
way of breaks of long superstructures occurring within 0,5L faction of the Society.
amidships, over a length of about one sixth of the ships
breadth on each side of the superstructure end.
2.8 Corrugated bulkhead
This increase in net thickness is to be equal to 40%, but
need not exceed 4,5 mm. 2.8.1 Unless otherwise specified, the net plating thickness
of a corrugated bulkhead is to be not less than that obtained
Where the breaks of superstructures occur outside 0,5L from [3] and [5] with s equal to the greater of b and c,
amidships, the increase in net thickness may be reduced to where b and c are defined in Ch 4, Sec 7, Fig 3.
30%, but need not exceed 2,5 mm.
S1 M SW ,S + 0 ,625 W1 C FV F D M WV ,S M SW ,S 0 ,625F D M WV ,S
------------------------------------------------------------------------------------
-1 -------------- ( z N ) 10 3 ------------------------------------- ( z N ) 10 3
S1 M SW ,H + 0 ,625 W1 C FV M WV ,H IY IY
0 ,625M WH
--------------------------- y 10 3
S1 M SW ,S + 0 ,625 W1 C FV F D M WV ,S M SW ,H 0 ,625M WV ,H IZ
------------------------------------------------------------------------------------
-<1 --------------- ( z N ) 10 3 -------------------------------- ( z N ) 10 3
S1 M SW ,H + 0 ,625 W1 C FV M WV ,H IY IY
(1) When the ship in still water is always in hogging condition, MSW,S is to be taken equal to 0.
Note 1:
FD : Coefficient defined in Ch 5, Sec 2, [4].
3.2.6 In-plane hull girder shear stresses for bilge, side, inner side and longitudinal bulkheads
The in-plane hull girder shear stresses to be considered for (including possible longitudinal sloping plates):
the strength check of plating, subjected to lateral loads,
2 x1 2 x1
which contributes to the longitudinal strength are obtained, L = 1 3 m ----1- 0 ,95 m ------- 0 ,225 m -------
R y Ry Ry
in N/mm2, from the following formula:
1 = S1 S1 + 0 ,625C FV W1 W1 3.3.2 Flooding conditions
where: The plating which constitute vertical watertight boundary
between two compartments not intended to carry liquid
CFV : Combination factor defined in Tab 4
(excluding side shell platings) is to be checked in flooding
S1 : Absolute value of the hull girder shear stresses, conditions. To this end, its net thickness is to be not less
in N/mm2, induced by the maximum still water than the value obtained, in mm, from the following formula:
hull girder vertical shear force in the section
considered S2 p SF + W2 p WF
t = 14 ,9 c a c r s R m --------------------------------------
L Ry
W1 : Absolute value of the hull girder shear stresses,
in N/mm2, induced by the maximum wave hull where L is defined in [3.3.1].
girder vertical shear force in the section consid-
ered. 3.3.3 Testing conditions
S1 and W1 are to be taken not less than the values indicated The plating of compartments or structures as defined in Ch
in Tab 5. 5, Sec 6, Tab 14 is to be checked in testing conditions. To
this end, its net thickness is to be not less than the value
Table 5 : Hull girder shear stresses obtained, in mm, from the following formula:
S2 p SF + W2 p WF
4.2 Load model
t = 14 ,9 c a c r s R m --------------------------------------
Ry
4.2.1 General
The still water and inertial forces induced by the sea and the
3.5.3 Testing conditions
various types of wheeled vehicles are to be considered,
The plating of compartments or structures as defined in Ch 5, depending on the location of the plating.
Sec 6, Tab 14 is to be checked in testing conditions. To this
end, its net thickness is to be not less than the value The inertial forces induced by the sea are to be calculated
obtained, in mm, from the following formula: in load case b, as defined in Ch 5, Sec 4.
3.6 Plating subject to impact loads Still water force is the vertical force (FS) defined in Ch 5, Sec
6, [6.1].
3.6.1 General Inertial force is the vertical force (FW,Z) defined in Ch 5, Sec
Unless otherwise specified, the net thickness of plate panels 6, [6.1], for load case b.
subject to impact generated by fluids is to be not less than
the value obtained, in mm, from the following formula:
4.3 Plating
15, 8s P
t = -------------------- -------I- 4.3.1 The net thickness of plate panels subjected to
Cd R eH
wheeled loads is to be not less than the value obtained, in
where: mm, from the following formula:
: Coefficient defined as follows: nP 0 k
t = 0,9 C WL ------------
s
= 1, 2 ------------
2, 1 where:
without being taken greater than 1,0 CWL : Coefficient to be taken equal to:
Cd : Plate capacity correction coefficient: 0 ,5
C WL = 2, 15 0, 05 - + 0 ,02 4 - 1 ,75
0 ,25
AT : Tyre print area, in m2. In the case of double or t2 : Net thickness obtained, in mm, from [4.3.1] for
triple wheels, AT is the print area of the group of n = 1, considering one wheel located on the
wheels. AT is not to be taken greater than the plate panel
value given in [4.3.2]
2, 3, 4: Coefficients obtained from the following for-
,s : Lengths, in m, of, respectively, the longer and mula, by replacing i by 2, 3 and 4, respectively
the shorter sides of the plate panel (see Fig 1):
n : Number of wheels on the plate panel, taken
for xi / b < 2:
equal to:
1 in the case of a single wheel i = 0,8 (1,2 2,02 i + 1,17 i2 0,23 i3)
the number of wheels in a group of wheels for xi / b 2:
in the case of double or triple wheels
P0 : Wheeled force, in kN, taken equal to: i = 0
P 0 = S2 F S + W2 F W ,Z
Figure 1 : Four wheel axle located on a plate panel
: Coefficient taken equal to:
for longitudinally framed plating:
= L as defined in [3.3.1] X4
X2 X3
for transversely framed plating:
= T as defined in [3.4.1].
b
4.3.2 When the tyre print area is not known, it may be
taken equal to: 3
2 1 4
nQ A
A T = 9, 81 ------------
- a
nW pT
where:
n : Number of wheels on the plate panel, defined xi : Distance, in m, from the wheel considered to
in [4.3.1] the reference wheel (see Fig 1)
QA : Axle load, in t b : Dimension, in m, of the plate panel side per-
nW : Number of wheels for the axle considered pendicular to the axle
pT : Tyre pressure, in kN/m2. When the tyre pressure
x
is not indicated by the designer, it may be taken i = ----i
b
as defined in Tab 6.
4.3.3 For vehicles with the four wheels of the axle located Rectangular plate panels are considered as being simply
on a plate panel as shown in Fig 1, the net thickness of deck supported. For specific designs, other boundary conditions
plating is to be not less than the greater of the values may be considered, at the Societys discretion, provided that
obtained, in mm, from the following formulae: the necessary information is submitted for review.
t = t1
5.1.2 Compression and bending with or without shear
t = t2 (1 + 2 + 3 + 4)0,5
For plate panels subjected to compression and bending
where: along one side, with or without shear, as shown in Fig 2,
t1 : Net thickness obtained, in mm, from [4.3.1] for side b is to be taken as the loaded side. In such case, the
n = 2, considering one group of two wheels compression stress varies linearly from 1 to 2 = 1
located on the plate panel ( 1) along edge b.
Figure 2 : Buckling of a simply supported rectangular plate panel subjected to compression and bending,
with and without shear
a a
1 1 1 1
b b
2 2 2 2
following formula:
X1 = S1 S1 + W1 ( C FV WV1 + C FH WH1 + C F )
where:
S1, WV1, WH1 : Hull girder normal stresses, in N/mm2,
a or b defined in Tab 7
: Compression warping stress, in N/mm2,
induced by the torque 0,625 MWT and obtained
5.1.4 Bi-axial compression and shear
through direct calculation analyses based on a
For plate panels subjected to bi-axial compression along structural model in accordance with Ch 6, Sec
sides a and b, and to shear, as shown in Fig 4, side a 1, [2.6]
is to be taken as the side in the direction of the primary sup- CFV, CFH, CF : Combination factors defined in Tab 4.
porting members.
X1 is to be taken as the maximum compression stress on
the plate panel considered.
Figure 4 : Buckling of a simply supported
rectangular plate panel subjected to When the ship in still water is always in hogging condition,
bi-axial compression and shear X1 may be evaluated by means of direct calculations when
justified on the basis of the ships characteristics and
b intended service. The calculations are to be submitted to
the Society for approval.
Where deemed necessary, the buckling check is to be car-
Primary
supporting
ried out in harbour conditions by considering a reduced
members wave bending moment equal to 0,1 MWV given in Ch 5, Sec
Ordinary
a
2, [3.1].
a
stiffeners
M SW ,S 0 ,625F D M WV ,S
zN -------------- ( z N )10 3 ------------------------------------- ( z N )10 3
IY IY 0 ,625M WH 3
--------------------------- y 10
M SW ,H 0 ,625M WV ,H IZ
z<N --------------- ( z N )10 3 -------------------------------- ( z N )10 3
IY IY
(1) When the ship in still water is always in hogging condition, S1 for z N is to be obtained, in N/mm2, from the following for-
mula, unless X1 is evaluated by means of direct calculations (see [5.2.2]):
M SW ,Hmin
- ( z N )10 3
S1 = ---------------------
IY
Note 1:
FD : Coefficient defined in Ch 5, Sec 2, [4].
5.2.4 Combined in-plane hull girder and local 1 : Shear stress, in N/mm2, induced by the hull
compression normal stresses girder still water and wave loads, defined in
The combined in-plane compression normal stresses to be [5.2.3]
considered for the buckling check of plating are to take into 2,S : Shear stress, in N/mm2, induced by the local
account the hull girder stresses and the local stresses resulting bending of the primary supporting members
from the bending of the primary supporting members. These and obtained from a direct structural analysis
local stresses are to be obtained from a direct structural analy- using the still water design loads given in Part B,
sis using the design loads given in Part B, Chapter 5. Chapter 5
With respect to the reference co-ordinate system defined in 2,W : Shear stress, in N/mm2, induced by the local
Ch 1, Sec 2, [4.1], the combined stresses in x and y direc- bending of the primary supporting members and
tion are obtained, in N/mm2, from the following formulae: obtained from a direct structural analysis using
X = X1 + S2 X2 ,S + W2 X2 ,W the wave design loads given in Part B, Chapter 5.
Y = S2 Y2 ,S + W2 Y2 ,W
where: 5.3 Critical stresses
X1 : Compression normal stress, in N/mm2, induced 5.3.1 Compression and bending for plane panel
by the hull girder still water and wave loads,
The critical buckling stress is to be obtained, in N/mm2,
defined in [5.2.2]
from the following formulae:
X2,S,Y2,S: Compression normal stress in x and y direction,
respectively, in N/mm2, induced by the local R eH
bending of the primary supporting members c = E for E -------
-
2
and obtained from a direct structural analysis R eH R eH
using the still water design loads given in Part B, c = R eH 1 --------
- for E > -------
-
4 E 2
Chapter 5
X2,W,Y2,W: Compression normal stress in x and y direction, where:
respectively, in N/mm2, induced by the local E : Euler buckling stress, to be obtained, in N/mm2,
bending of the primary supporting members from the following formula:
and obtained from a direct structural analysis
2 E t 2
using the wave design loads given in Part B, - --- K 10 6
E = -------------------------
12 ( 1 2 ) b 1
Chapter 5.
K1 : Buckling factor defined in Tab 8
5.2.5 Combined in-plane hull girder and local shear
: Coefficient to be taken equal to:
stresses
The combined in-plane shear stresses to be considered for = 1,00 for 1
the buckling check of plating are to take into account the = 1,05 for < 1 and side b stiffened by
hull girder stresses and the local stresses resulting from the flat bar
bending of the primary supporting members. These local = 1,10 for < 1 and side b stiffened by
stresses are to be obtained from a direct structural analysis bulb section
using the design loads given in Part B, Chapter 5.
= 1,21 for < 1 and side b stiffened by
The combined stresses are obtained, in N/mm2, from the angle or T-section
following formula:
= 1,30 for < 1 and side b stiffened by
= 1 + S2 2 ,S + W2 2 ,W primary supporting members
where: with = a / b.
1 2 1 2
------------- --- 23 ,9 -------------
2 3 2
1
1 ,87 1 2 1 2
1 2
------------- < --- 15 ,87 + -------------------------2 + 8 ,6 ------------- -------------
1 2 2
2 3
-------------
2
Note 1:
= -----2
1
5.3.2 Shear for plane panel : Slenderness of the panel, to be taken equal to:
The critical shear buckling stress is to be obtained, in 3 a R eH
= 10 --- -------
-
N/mm2, from the following formulae: t E
without being taken less than 1,25.
R eH
c = E for E ----------
- The critical buckling stress c,b for compression on side b
2 3
of the panel is to be obtained, in N/mm2, from the formulae
R eH R eH R eH in [5.3.1].
- 1 ---------------
c = ------- - for E > ---------- -
3 4 3 E 2 3
The critical shear buckling stress is to be obtained, in
where: N/mm2, from the formulae in [5.3.2].
E : Euler shear buckling stress, to be obtained, in 5.3.4 Compression and shear for curved panels
N/mm2, from the following formula: The critical buckling stress of curved panels subjected to
compression perpendicular to curved edges is to be
2 E t 2
- --- K 10 6
E = ------------------------- obtained, in N/mm2, from the following formulae:
12 ( 1 2 ) b 2
R eH
K2 : Buckling factor to be taken equal to: c = E for E -------
-
2
R eH R eH
4 c = R eH 1 --------
- for E > -------
-
K 2 = 5 ,34 + -----2- for > 1 4 E 2
5 ,34 where:
K 2 = -----------
2
+ 4 for 1
E : Euler buckling stress, to be obtained, in N/mm2,
from the following formula:
: Coefficient defined in [5.3.1].
2 E t 2
- --- K 3 10 6
E = -------------------------
2
5.3.3 Bi-axial compression and shear for plane panel 12 ( 1 ) b
The critical buckling stress c,a for compression on side a b : Width of curved panel, in m, measured on arc
of the panel is to be obtained, in N/mm2, from the following between two adjacent supports
formula: K3 : Buckling factor to be taken equal to:
2 ,25 1 ,25
c ,a = ----------- ----------- 12 ( 1 2 ) b 4
R eH K 3 = 2 1 + 1 + -------------------------
- -------- 10 6
2
4
r 2 2
t
where: r : Radius of curvature, in m.
2
b 12 R m b ( 1- ) 3 R eH
- 10 for E ----------
t = --- ------------------------------------------ -
tw tf EK i 2 3
2 2
b R eH ( 1- ) R eH
t = --- --------------------------------------------
- 10 for E > ----------
3
V' -
R
EK i -------- - R m b
eH 2 3
3
Ki = K4 , defined in [5.3.4] for a curved panel. For plate panels subjected to bi-axial compression and
shear, the critical buckling stresses are to comply with the
5.4.4 Compression, bending and shear following formula:
For plate panels subjected to compression, bending and
shear, the combined critical stress is to comply with the fol- R m a 1, 9
+ ----------------
R m b
1.9
+ -------------
R m
1.9
1
----------------- - -
lowing formulae: c ,a c ,b c
where:
comb R eH
F1 - -------------
for ------------ -
F 2 R m c,a : Critical buckling stress for compression on side
4 comb comb comb R eH a, in N/mm2, defined in [5.3.3]
F ----------------------
- 1 ---------------------- - > -------------
- for ------------ -
R eH R m R eH R m F 2 R m
c,b : Critical buckling stress for compression on side
where: b, in N/mm2, defined in [5.3.3]
comb = 12 + 3 2 a : Compression stress acting on side a, in
N/mm2, to be calculated as specified in [5.2.2]
1+ 3 2 2 2
F = R m ------------- -------1- + ------------- -----1 + ---- or [5.2.4], as the case may be
4 E 4 E E
b : Compression stress acting on side b, in
E : Euler buckling stress, in N/mm2, defined in N/mm2, to be calculated as specified in [5.2.2]
[5.3.1], [5.3.4] or [5.3.5] as the case may be or [5.2.4], as the case may be
E : Euler shear buckling stress, in N/mm2, defined
in [5.3.2] or [5.3.4], as the case may be =a/b
Symbols
For symbols not defined in this Section, refer to the list at AS : Net sectional area, in cm2, of the stiffener with
the beginning of this Chapter. attached plating of width s
pS : Still water pressure, in kN/m2, see [3.3.2] and Ae : Net sectional area, in cm2, of the stiffener with
[5.3.2] attached plating of width be
pW : Wave pressure and, if necessary, dynamic pres- AU : Net sectional area, in cm2, of the stiffener with
sures, according to the criteria in Ch 5, Sec 5, attached plating of width bU
[2] and Ch 5, Sec 6, [2], in kN/m2 (see [3.3.2]
and [5.3.2]) ASh : Net shear sectional area, in cm2, of the stiffener,
to be calculated as specified in Ch 4, Sec 3,
pSF, pWF : Still water and wave pressures, in kN/m2, in
[3.4]
flooding conditions, defined in Ch 5, Sec 6, [9]
I : Net moment of inertia, in cm4, of the stiffener
FS : Still water wheeled force, in kN, see [3.3.5]
without attached plating, about its neutral axis
FW,Z : Inertial wheeled force, in kN, see [3.3.5] parallel to the plating (see Ch 4, Sec 3, Fig 4 and
X1 : Hull girder normal stress, in N/mm2, defined in: Ch 4, Sec 3, Fig 5)
[3.3.6] for the yielding check of ordinary IS : Net moment of inertia, in cm4, of the stiffener
stiffeners with attached shell plating of width s, about its
[4.2.2] for the buckling check of ordinary neutral axis parallel to the plating
stiffeners Ie : Net moment of inertia, in cm4, of the stiffener
[5.3.3] for the ultimate strength check of with attached shell plating of width be , about its
ordinary stiffeners neutral axis parallel to the plating
ReH,P : Minimum yield stress, in N/mm2, of the plating IU : Net moment of inertia, in cm4, of the stiffener
material, defined in Ch 4, Sec 1, [2] with attached shell plating of width bU , about
ReH,S : Minimum yield stress, in N/mm2, of the stiffener its neutral axis parallel to the plating
material, defined in Ch 4, Sec 1, [2] S : Radius of gyration, in cm, of the stiffener with
s : Spacing, in m, of ordinary stiffeners attached plating of width s
: Span, in m, of ordinary stiffeners, measured U : Radius of gyration, in cm, of the stiffener with
between the supporting members, see Ch 4, Sec 3, attached plating of width bU .
[3.2]
hw : Web height, in mm 1 General
tw : Net web thickness, in mm
bf : Face plate width, in mm 1.1 Net scantlings
tf : Net face plate thickness, in mm
1.1.1 As specified in Ch 4, Sec 2, [1], all scantlings referred
bp : Width, in m, of the plating attached to the stiff- to in this Section are net, i.e. they do not include any mar-
ener, for the yielding check, defined in Ch 4, gin for corrosion.
Sec 3, [3.3.1]
The gross scantlings are obtained as specified in Ch 4, Sec 2.
be : Width, in m, of the plating attached to the stiff-
ener, for the buckling check, defined in [4.1]
1.2 Partial safety factors
bU : Width, in m, of the plating attached to the stiff-
ener, for the ultimate strength check, defined in 1.2.1 The partial safety factors to be considered for the
[5.2] checking of ordinary stiffeners are specified in Tab 1.
tp : Net thickness, in mm, of the attached plating
w : Net section modulus, in cm3, of the stiffener, 1.3 Load point
with an attached plating of width bp , to be cal-
culated as specified in Ch 4, Sec 3, [3.4] 1.3.1 Lateral pressure
A : Net sectional area, in cm2, of the stiffener with- Unless otherwise specified, lateral pressure is to be calcu-
out attached plating lated at mid-span of the ordinary stiffener considered.
tw
hw
1.4 Net dimensions of ordinary stiffeners
1.4.3 T-section
The net dimensions of a T-section ordinary stiffener (see Fig 2)
are to comply with the following requirements: tf
hw
------ 55 k
tw
bf bf
---- 33 k
tf
hw tw Figure 3 : Net dimensions of an angle
b f t f ----------
-
6
1.4.4 Angle
The net dimensions of an angle ordinary stiffener (see Fig 3)
are to comply with the following requirements:
hw
hw tw
------ 55 k
tw tf
b
----f 16 ,5 k
tf
hw tw bf
b f t f ----------
-
6
2.1.1 The requirements in [2.2] and [2.3] are to be applied 2.5.1 The scantlings of deck ordinary stiffeners are to be
to ordinary stiffeners in addition of those in [3] to [5]. determined by direct calculations.
2.2 Minimum net thicknesses 2.5.2 The loads exerted by launching appliance are to cor-
respond to the SWL of the launching appliance.
2.2.1 The net thickness of the web of ordinary stiffeners is
to be not less than the lesser of: 2.5.3 The combined stress, in N/mm2, is not to exceed the
the value obtained, in mm, from the following formulae: smaller of ReH/2,2 and Rm/4,5 where Rm is the ultimate mini-
mum tensile strength of the ordinary stiffener material, in
tMIN = 0,8 + 0,004 L k1/2 + 4,5 s for L < 120 m
N/mm2.
tMIN = 1,6 + 2,2 k 1/2
+s for L 120 m
the net as built thickness of the attached plating.
3 Yielding check
2.3 Struts connecting ordinary stiffeners
3.1 General
2.3.1 The sectional area ASR, in cm2, and the moment of
inertia ISR about the main axes, in cm4, of struts connecting 3.1.1 The requirements of this Article apply for the yielding
ordinary stiffeners are to be not less than the values check of ordinary stiffeners subjected to lateral pressure or
obtained from the following formulae: to wheeled loads and, for ordinary stiffeners contributing to
the hull girder longitudinal strength, to hull girder normal
p SR s
A SR = ------------
- stresses.
20
2
0 ,75s ( p SR1 + p SR2 )A ASR SR 3.1.2 When tanks are partly filled and if a risk of resonance
I SR = -------------------------------------------------------------------
-
47 ,2A ASR s ( p SR1 + p SR2 ) exists, the yielding check of vertical ordinary stiffeners of
where: tank structures subjected to sloshing and impact pressures is
to be carried out by direct calculation.
pSR : Pressure to be taken equal to the greater of the
values obtained, in kN/m2, from the following 3.1.3 The yielding check is also to be carried out for ordi-
formulae: nary stiffeners subjected to specific loads, such as concen-
pSR = 0,5 (pSR1 + pSR2) trated loads.
pSR = pSR3
pSR1 : External pressure in way of the strut, in kN/m2, 3.2 Structural model
acting on one side, outside the compartment in
which the strut is located, equal to: 3.2.1 Boundary conditions
pSR1 = S2 pS + W2 pW The requirements in [3.4], [3.7.3], [3.7.4] and [3.8] apply to
pSR2 : External pressure in way of the strut, in kN/m2, stiffeners considered as clamped at both ends, whose end
acting on the opposite side, outside the com- connections comply with the requirements in [3.2.2].
partment in which the strut is located, equal to: The requirements in [3.5] and [3.7.5] apply to stiffeners
pSR2 = S2 pS + W2 pW considered as simply supported at both ends. Other bound-
pSR3 : Internal pressure at mid-span of the strut, in ary conditions may be considered by the Society on a case
kN/m2, in the compartment in which the strut is by case basis, depending on the distribution of wheeled
located, equal to: loads.
pSR3 = S2 pS + W2 pW For other boundary conditions, the yielding check is to be
considered on a case by case basis.
: Span, in m, of ordinary stiffeners connected by
the strut (see Ch 4, Sec 3, [3.2.2])
3.2.2 Bracket arrangement
SR : Length, in m, of the strut
The requirements of this Article apply to ordinary stiffeners
AASR : Actual net sectional area, in cm2, of the strut. without end brackets, with a bracket at one end or with two
end brackets, where the bracket length is not greater than
2.4 Corrugated bulkhead 0,2 .
2.4.1 Unless otherwise specified, the net section modulus In the case of ordinary stiffeners with end brackets of length
and the net shear sectional area of a corrugation are to be not greater than 0,2 , the determination of normal and shear
less than those obtained from [3] to [5] with s equal to the stresses due to design loads and the required section modu-
greater of (a + b), where a and b are defined in Ch 4, Sec 7, lus and shear sectional area are considered by the Society
Fig 3. on a case by case basis.
Table 2 : Hull girder normal stresses - Ordinary stiffeners subjected to lateral pressure
M SW ,H 0 ,625M WV ,H
z<N --------------- ( z N ) 10 3 -------------------------------- ( z N ) 10 3
IY IY 0 ,625M WH
--------------------------- y 10 3
IZ
Lateral pressure applied on the same side
as the ordinary stiffener:
M SW ,H 0 ,625M WV ,H
zN --------------- ( z N ) 10 3 -------------------------------- ( z N ) 10 3
IY IY
M SW ,S 0 ,625F D M WV ,S
z<N -------------- ( z N ) 10 3 ------------------------------------- ( z N ) 10 3
IY IY
(1) When the ship in still water is always in hogging condition, MSW,S is to be taken equal to 0.
Note 1:
FD : Coefficient defined in Ch 5, Sec 2, [4].
Table 3 : Hull girder normal stresses - Ordinary stiffeners subjected to wheeled loads
M SW ,H 0 ,625M WV ,H 0 ,625M WH
Hogging - ( z N )10 3 + W1 C FV -------------------------------
X1H = S1 -------------- - y10 3 + C F
- ( z N )10 3 + C FH ---------------------------
IY IY IZ
M SW ,S 0 ,625F D M WV ,S 0 ,625M WH
Sagging (1) - ( z N )10 3 + W1 C FV ------------------------------------
X1S = S1 ------------- - y10 3 + C F
- ( z N )10 3 + C FH ---------------------------
IY IY IZ
(1) When the ship in still water is always in hogging condition, MSW,S is to be taken equal to 0.
Note 1:
FD : Coefficient defined in Ch 5, Sec 2, [4].
Table 4 : Combination factors CFV , CFH and CF 3.4.2 Single span longitudinal and transverse
ordinary stiffeners
Load case CFV CFH CF The maximum normal stress and shear stress are to be
obtained, in N/mm2, from the following formulae:
a 1,0 0 0
S2 p S + W2 p W
1 ------ s 10 + X1
s
= b ----------------------------------
2 3
b 1,0 0 0 12w 2
c 0,4 1,0 1,0
S2 p S + W2 p W
1 ------ s
s
= 5 s ----------------------------------
d 0,4 1,0 0 A Sh 2
where:
b , s : Coefficients defined in Tab 5.
Table 5 : Coefficients b and s
3.4.3 Single span vertical ordinary stiffeners
The maximum normal stress and shear stress are to be
Brackets at Bracket
b s obtained, in N/mm2, from the following formulae:
ends lengths
S2 p S + W2 p W
1 ------ s 10
s
= b b ----------------------------------
2 3
0 1 1
12w 2
1 b b 2
1 -----
- 1 -----b- S2 p S + W2 p W
1 ------ s
s
2 2 = 5 s s ----------------------------------
A Sh 2
2 b1 ; b2 1 ------
b1 b2
2
b1 b2 where:
- ------- 1 ------
- -------
2 2 2 2 b , s : Coefficients defined in [3.4.2]
b : Coefficient taken equal to the greater of the fol- w : Coefficient taking account of the number of
lowing values: wheels per axle considered as acting on the
S2 ( p Sd p Su ) + W2 ( p Wd p Wu ) stiffener, defined in Tab 6
b = 1 + 0 ,2 -----------------------------------------------------------------------------
-
KS , KT : Coefficients taking account of the number of
S2 ( p Sd + p Su ) + W2 ( p Wd + p Wu )
S2 ( p Sd p Su ) + W2 ( p Wd p Wu ) axles considered as acting on the stiffener,
b = 1 0, 2 -----------------------------------------------------------------------------
- defined in Tab 7.
S2 ( p Sd + p Su ) + W2 ( p Wd + p Wu )
s : Coefficient taken equal to the greater of the fol- Table 6 : Wheeled loads - Coefficient W
lowing values:
Configuration W
S2 ( p Sd p Su ) + W2 ( p Wd p Wu )
s = 1 + 0 ,4 -----------------------------------------------------------------------------
-
S2 ( p Sd + p Su ) + W2 ( p Wd + p Wu ) Single wheel
S2 ( p Sd p Su ) + W2 ( p Wd p Wu )
s = 1 0, 4 -----------------------------------------------------------------------------
-
S2 ( p Sd + p Su ) + W2 ( p Wd + p Wu )
1
pSd : Still water pressure, in kN/m2, at the lower end
of the ordinary stiffener considered
pSu : Still water pressure, in kN/m2, at the upper end
of the ordinary stiffener considered
Double wheels
pWd : Wave pressure, in kN/m2, at the lower end of
the ordinary stiffener considered
pWu : Wave pressure, in kN/m2, at the upper end of y
2 1 ---
y
the ordinary stiffener considered. s
3.4.4 Multispan ordinary stiffeners
The maximum normal stress and shear stress in a multi- s
span ordinary stiffener are to be determined by a direct cal-
culation taking into account: Triple wheels
the distribution of still water and wave pressure and
forces, to be determined on the basis of the criteria
specified in Ch 5, Sec 5 and Ch 5, Sec 6 y
y
the number and position of intermediate supports 3 2 ---
s
(decks, girders, etc.)
the condition of fixity at the ends of the stiffener and at
intermediate supports s
the geometrical characteristics of the stiffener on the
intermediate spans. Note 1:
y : Distance, in m, from the external wheel of a
group of wheels to the stiffener under considera-
3.5 Normal and shear stresses due to
tion, to be taken equal to the distance from the
wheeled loads external wheel to the centre of the group of
wheels.
3.5.1 General
Normal and shear stresses, induced by the wheeled loads, in Table 7 : Wheeled loads - Coefficients KS and KT
ordinary stiffeners are to be obtained from the formulae in:
[3.5.2] in the case of single span longitudinal and trans- Configuration
Coefficient
verse stiffeners Single axle Double axles
[3.5.3]in the case of multispan stiffeners. if d 3
3.5.2 Single span longitudinal and transverse 2 4
172 4d d d
ordinary stiffeners subjected to wheeled loads ---------- ------- ----2- + ----4-
81 3
The maximum normal stress and shear stress are to be KS 1
obtained, in N/mm2, from the following formulae: if d > 3
P0 3
= W K S -------
- 10 + X1, Wh
4 4d 3d 8d
2 3
6w --- ------- + --------
- --------3-
3 3 2
10P 3
= W K T ------------0
A Sh 2 3
d 3d d
KT 1 2 ------ --------2- + ----3-
where: 2 2
P0 : Wheeled force, in kN, taken equal to: Note 1:
P0 = S2 FS + W2 FW,Z d : Distance, in m, between two axles (see Fig 4).
Figure 4 : Wheeled load on stiffeners - Double axles 3.7.2 Groups of equal ordinary stiffeners
Where a group of equal ordinary stiffeners is fitted, it is
acceptable that the minimum net section modulus in [3.7.1]
is calculated as the average of the values required for all the
d stiffeners of the same group, but this average is to be taken
not less than 90% of the maximum required value.
The same applies for the minimum net shear sectional area.
3.8 Net section modulus and net shear s : Coefficient taken equal to the greater of the fol-
sectional area of ordinary stiffeners lowing values:
subjected to lateral pressure in flooding S2 ( p SFd p SFu ) + W2 ( p WFd p WFu )
s = 1 + 0 ,4 --------------------------------------------------------------------------------------
conditions S2 ( p SFd + p SFu ) + W2 ( p WFd + p WFu )
S2 ( p SFd p SFu ) + W2 ( p WFd p WFu )
s = 1 0, 4 --------------------------------------------------------------------------------------
3.8.1 General S2 ( p SFd + p SFu ) + W2 ( p WFd + p WFu )
The requirements in [3.8.3] to [3.8.5] provide the minimum pSFd : Still water pressure, in kN/m2, in flooding con-
net section modulus and net shear sectional area of ordi- ditions, at the lower end of the ordinary stiffener
nary stiffeners located on platings which constitute vertical considered
watertight boundary between two compartments not
pSFu : Still water pressure, in kN/m2, in flooding con-
intended to carry liquids (excluding stiffeners on side shell
ditions, at the upper end of the ordinary stiffener
platings) in flooding conditions.
considered
3.8.2 Groups of equal ordinary stiffeners pWFd : Wave pressure, in kN/m2, in flooding condi-
tions, at the lower end of the ordinary stiffener
Where a group of equal ordinary stiffeners is fitted, it is considered
acceptable that the minimum net section modulus in [3.8.1]
pWFu : Wave pressure, in kN/m2, in flooding condi-
is calculated as the average of the values required for all the
stiffeners of the same group, but this average is to be taken tions, at the upper end of the ordinary stiffener
not less than 90% of the maximum required value. considered.
The same applies for the minimum net shear sectional area. 3.8.5 Multispan ordinary stiffeners
The minimum net section modulus and the net shear sec-
3.8.3 Single span longitudinal and transverse tional area of multispan ordinary stiffeners are to be
ordinary stiffeners obtained from [3.4.4], considering the still water pressure
pSF and the wave pressure pWF in flooding conditions, and
The net section modulus w, in cm3, and the net shear sec-
taking account of the checking criteria indicated in [3.6].
tional area ASh , in cm2, of longitudinal or transverse ordi-
nary stiffeners are to be not less than the values obtained
from the following formulae: 3.9 Net section modulus and net shear
sectional area of ordinary stiffeners
S2 p SF + W2 p WF subjected to lateral pressure in testing
- 1 ------ s 2 10 3
s
w = R m b ------------------------------------------
12 ( R y R m X1 ) 2 conditions
S2 p SF + W2 p WF
1 ------ s
s
A Sh = 10 R m s --------------------------------------
Ry 2 3.9.1 General
The requirements in [3.9.3] to [3.9.5] provide the minimum
where: net section modulus and net shear sectional area of ordinary
stiffeners of compartments subject to testing conditions.
b , s : Coefficients defined in [3.4.2].
3.9.2 Groups of equal ordinary stiffeners
3.8.4 Single span vertical ordinary stiffeners
Where a group of equal ordinary stiffeners is fitted, it is
The net section modulus w, in cm3, and the net shear sec- acceptable that the minimum net section modulus in [3.9.1]
tional area ASh , in cm2, of vertical ordinary stiffeners are to is calculated as the average of the values required for all the
be not less than the values obtained from the following for- stiffeners of the same group, but this average is to be taken
mulae: not less than 90% of the maximum required value.
The same applies for the minimum net shear sectional area.
S2 p SF + W2 p WF
1 ------ s 10
s
w = R m b b --------------------------------------
2 3
12R y 2 3.9.3 Single span longitudinal and transverse
S2 p SF + W2 p WF ordinary stiffeners
1 ------ s
s
A Sh = 10 R m s s --------------------------------------
Ry 2 The net section modulus w, in cm3, and the net shear sec-
tional area ASh , in cm2, of longitudinal or transverse ordi-
where: nary stiffeners are to be not less than the values obtained
b , s : Coefficients defined in [3.4.2] from the following formulae:
b S2 p T
1 ------ s 10
: Coefficient taken equal to the greater of the fol- s
w = R m b ------------
2 3
3.10 Net section modulus and net shear to be taken not greater than s
sectional area of ordinary stiffeners where:
subject to impact loads
s b 3
e = --- -----10
3.10.1 Single span longitudinal, transverse and tp E
vertical ordinary stiffeners
b : Compression stress X or Y, in N/mm2, acting on
Unless otherwise specified, the net plastic section modulus the plate panel, defined in Ch 7, Sec 1, [5.2.4],
Zpl , in cm3, as defined in Ch 4, Sec 3, [3.4.3] and the net according to the direction x or y considered.
web thickness tw , in mm, of stiffeners subject to impact gen-
erated by fluids are to be not less than the values obtained
4.2 Load model
from the following formulae:
3 PI tension: positive
t w = ------- -----------------------------
- s10 3
2 ( h w + t p )R eH compression: negative.
(1) When the ship in still water is always in hogging condition, S1 for z N is to be obtained, in N/mm2, from the following for-
mula, unless X1 is evaluated by means of direct calculations (see [4.2.2]):
M SW ,Hmin
- ( z N )10 3
S1 = ---------------------
IY
Note 1:
FD : Coefficient defined in Ch 5, Sec 2, [4].
4.2.2 Hull girder compression normal stresses E2 : Euler torsional buckling stress, in N/mm2, given
The hull girder compression normal stresses to be consid- in [4.3.3]
ered for the buckling check of ordinary stiffeners contribut- E3 : Euler web buckling stress, in N/mm2, given in
ing to the hull girder longitudinal strength are obtained, in [4.3.4].
N/mm2, from the following formula:
4.3.2 Column buckling of axially loaded stiffeners
X1 = S1 S1 + W1 (CFV WV1 + CFH WH1 + CF )
The Euler column buckling stress is obtained, in N/mm2,
where: from the following formula:
S1, WV1, WH1 : Hull girder normal stresses, in N/mm2,
Ie
defined in Tab 8 -2 10 4
E = 2 E ----------
Ae
: Compression warping stress, in N/mm2, induced
by the torque 0,625MWT and obtained through 4.3.3 Torsional buckling of axially loaded stiffeners
direct calculation analyses based on a structural The Euler torsional buckling stresses is obtained, in N/mm2,
model in accordance with Ch 6, Sec 1, [2.6] from the following formula:
CFV, CFH, CF : Combination factors defined in Tab 4.
2 EI w K C I
For longitudinal stiffeners, X1 is to be taken as the maxi- -2 -------2 + m 2 + 0 ,385 E ---t
E = -----------------
10 I p m Ip
4
mum compression stress on the stiffener considered.
where:
When the ship in still water is always in hogging condition,
X1 may be evaluated by means of direct calculations when Iw : Net sectorial moment of inertia, in cm6, of the
justified on the basis of the ships characteristics and stiffener about its connection to the attached
intended service. The calculations are to be submitted to plating:
the Society for approval. for flat bars:
Where deemed necessary, the buckling check is to be carried h w3 t w3 6
I w = -----------
- 10
out in harbour conditions by considering a reduced wave 36
bending moment equal to 0,1 MWV given in Ch 5, Sec 2, for T-sections:
[3.1].
t f b f3 h w2 6
I w = ---------------
- 10
12
4.3 Critical stress
for angles and bulb sections:
4.3.1 General b f3 h w2
I w = ------------------------------
- [t ( b 2 + 2b f h w + 4h w2 )
The critical buckling stress is to be obtained, in N/mm2, 12 ( b f + h w ) 2 f f
from the following formulae: 6
+ 3t w b f h w ] 10
It : St. Venants net moment of inertia, in cm4, of the Figure 5 : Buckling of stiffeners parallel to
stiffener without attached plating: the direction of compression
t
I t = --- h w t w3 + b f t f3 1 0 ,63 ----f 10
1 4 b
3 b f
tW 2 4 where:
E = 16 ------
- 10
h W /s : Ratio to be taken not less than 1,41
E,0 : Euler buckling stress, in N/mm2, of the unstiff-
for stiffeners with face plate:
ened plate taken equal to:
2
tW
E = 78 ------
2
E t 2
h W
- 10 4 - ---p K 1 ,0 10 6
E ,0 = -------------------------
2
12 ( 1 )
K1,0 : Coefficient defined in Ch 7, Sec 1, Tab 8 for:
4.4 Checking criteria 0 1 and = a /
: Coefficient defined in Ch 7, Sec 1, [5.3.1]
4.4.1 Stiffeners parallel to the direction of
compression Figure 6 : Buckling of stiffeners perpendicular
The critical buckling stress of the ordinary stiffener parallel to the direction of compression
to the direction of compression, as shown in Fig 5, is to
a
comply with the following formula:
c
---------- b
R m
s
where:
ous types of cargoes and for ballast, and for each load
case a, b, c and d.
s
5.3.3 Hull girder compression normal stresses
The hull girder compression normal stresses X1 to be con-
sidered for the ultimate strength check of stiffeners contrib-
5 Ultimate strength check of ordinary
uting to the longitudinal strength are those given in [4.2.2],
stiffeners contributing to the hull where the partial safety factors are those specified in Tab 1
girder longitudinal strength for the ultimate strength check.
5.1.1 The requirements of this Article apply to ships equal 5.4.1 The ultimate strength stress U is to be obtained, in
to or greater than 170 m in length. For such ships, the ulti- N/mm2, from the formulae in Tab 10, for resultant lateral
mate strength of stiffeners subjected to lateral pressure and pressure acting either on the side opposite to the ordinary
to hull girder normal stresses is to be checked. stiffener, with respect to the plating, or on the same side as
the ordinary stiffener.
5.2 Width of attached plating
5.5 Checking criteria
5.2.1 The width of the attached plating to be considered for
the ultimate strength check of ordinary stiffeners is to be 5.5.1 The ultimate strength stress of the ordinary stiffener is
obtained, in m, from the following formulae: to comply with the following formula:
if U 1,25: U
---------- X1
bU = s R m
Resultant load pressure acting on the side opposite to the Resultant load pressure acting on the same side as
Symbol
ordinary stiffener, with respect to the plating, in N/mm2 the ordinary stiffener, in N/mm2
A
f ------U 1 ------------- R eH ,P
s
U ReH,S f
AS 10b U
2 1
f --- ----- --------------------------2-
2 4 ( 1 + P ) U
1 1 + P +
--------------- + --------------------------
-
1 + P ( 1 + P ) U2
125ps 2 d P ,U
--------------------------------------------- 41, 7ps 2 d F ,S
---------------------------------
R eH ,P I U 1 -------------
s
R eH ,S I S
10b U
+ 13ps d P ,U , 5ps 4 d F ,S
------------------ 10 4 -------- 0, 577 + 1
--------------------- 10 4 -------
4
- -
0 ET IS U2 0
ET IS S2
1 d P ,U
d P A ------ ----- --------
1
P - 0
A U A S 2
U
31 ,8 R eH ,P ,4- R eH ,S
--------------- ----------- 1 -------------
s 18
U -------------- -----------
U ET 10b U S ET
Note 1:
dP,U : Distance, in cm, between the neutral axis of the cross-section of the stiffener with attached plating of width bU and the
fibre at half-thickness of the plating
dF,S : Distance, in cm, between the neutral axis of the cross-section of the stiffener with attached plating of width s and the
fibre at half-thickness of the face plate of the stiffener
dP : Distance, in cm, between the neutral axis of the ordinary stiffener without attached plating and the fibre at half-thickness
of the attached plating
p : Lateral pressure acting on the stiffener, equal to: p = S2 pS + W2U pW
0 : Pre-deformation, in cm, of the ordinary stiffener, to be assumed, in the absence of more accurate evaluation: 0 = 0,2
ET : Structural tangent modulus, equal to:
X1E X1E
E T = 4E ----------
- 1 ----------- for X1E > 0 ,5R eH ,P
R eH ,P R eH ,P
ET = E for X1E 0 ,5R eH ,P
s
= 1000 -----------
tP E
Symbols
For symbols not defined in this Section, refer to the list at 1.1.2 Structural models
the beginning of this Chapter.
Depending on the service notation and structural arrange-
pS 2
: Still water pressure, in kN/m , see [3.4.2] and ment, primary structural models are to be modelled as spec-
[3.4.4] ified in Tab 1.
pW : Wave pressure, in kN/m2, see [3.4.2] and Table 1 : Selection of structural models
[3.4.4]
pSF, pWF : Still water and wave pressures, in kN/m2, in Ship length,
Service notation Calculation model
in m
flooding conditions, defined in Ch 5, Sec 6, [9]
Ro-ro cargo ship L 120 Isolated beam model,
X1 : Hull girder normal stress, in N/mm2, defined in Ro-ro passenger or three dimensional
[3.4.5] ship beam model for gril-
Passenger ship lage or complex
s : Spacing, in m, of primary supporting members arrangement
Container ship
: Span, in m, of primary supporting members, General cargo ship 120 < L 170 Three dimensional
with large deck beam model
measured between the supporting elements, see
openings
Ch 4, Sec 3, [4.1] L > 170 Complete ship model
bp : Width, in m, of the plating attached to the pri- Other ships L 120 Isolated beam model,
or three dimensional
mary supporting member, for the yielding
beam model for gril-
check, defined in Ch 4, Sec 3, [4.2] lage or complex
arrangement
w : Net section modulus, in cm3, of the primary
supporting member, with an attached plating of 120 < L 170 Three dimensional
width bp , to be calculated as specified in Ch 4, beam model
Sec 3, [4.3] L > 170 Three dimensional
finite element model
ASh : Net shear sectional area, in cm2, of the primary
supporting member, to be calculated as speci-
1.1.3 Yielding check
fied in Ch 4, Sec 3, [4.3]
The yielding check is to be carried out according to:
m : Boundary coefficient, to be taken equal to:
[3] for primary supporting members analysed through
m = 10 in general isolated beam models
m = 12 for bottom and side primary sup- [4] for primary supporting members analysed through
porting members three dimensional beam or finite element models
I : Net moment of inertia, in cm4, of the primary [5] for primary supporting members analysed through
supporting member without attached plating, complete ship models.
about its neutral axis parallel to the plating.
1.1.4 Buckling check
1 General The buckling check is to be carried out according to [7], on
the basis of the stresses in primary supporting members cal-
culated according to [3], [4] or [5], depending on the struc-
1.1 Application tural model adopted.
1.2 Analysis documentation identification of the critical areas, where the results of
the checkings exceed 97,5% of the permissible rule cri-
1.2.1 The following documents are to be submitted to the teria in [4.4] or [5.3] and [7].
Society for review of the three dimensional beam or finite
element structural analyses: 1.2.2 According to the results of the submitted calcula-
tions, the Society may request additional runs of the model
reference to the calculation program used with identifi- with structural modifications or local mesh refinements in
cation of the version number and results of the valida- highly stressed areas.
tion text, if the results of the program have not been
already submitted to the Society approval
1.3 Net scantlings
extent of the model, element types and properties,
material properties and boundary conditions 1.3.1 As specified in Ch 4, Sec 2, [1], all scantlings referred
to in this Section are net, i.e. they do not include any mar-
loads given in print-out or suitable electronic format. In
gin for corrosion.
particular, the method used to take into account the
interaction between the overall, primary and local load- The gross scantlings are obtained as specified in Ch 4, Sec 2.
ings is to be described. The direction and intensity of
pressure loads, concentrated loads, inertia and weight 1.4 Partial safety factors
loads are to be provided
1.4.1 The partial safety factors to be considered for check-
stresses given in print-out or suitable electronic format ing primary supporting members are specified in:
buckling checks as required in [7] Tab 2 for analyses based on isolated beam models
fatigue checks of structural details, as required in Ch 7, Tab 3 for analyses based on three dimensional models
Sec 4 Tab 4 for analyses based on complete ship models.
Table 2 : Primary supporting members analysed through isolated beam models - Partial safety factors
Table 3 : Primary supporting members analysed through three dimensional models - Partial safety factors
Table 4 : Primary supporting members analysed through complete ship models - Partial safety factors
Table 5 : Primary supporting members analysed Table 6 : Minimum net thicknesses of webs
through three dimensional or complete ship models of double bottom primary supporting members
Resistance partial safety factor
Minimum net thickness, in mm
Resistance partial safety factor R Primary supporting
Type of three member Area within Area outside
(see [4.4] and [5.3]) 0,4L amidships 0,4L amidships
dimensional model
(see Ch 7, App 1) Flooding Testing Centre girder 2,0 L1/3 k1/6 1,7 L1/3 k1/6
General
pressure check
Side girders 1,4 L 1/3 k 1/6 1,4 L1/3 k1/6
Beam model 1,20 1,02 1,20
Floors 1,5 L1/3 k1/6 1,5 L1/3 k1/6
Coarse mesh finite
1,20 1,02 1,20 Girder bounding a
element model 1,5 + 0,8 L1/2 k1/4 1,5 + 0,8 L1/2 k1/4
duct keel (1)
Fine mesh finite ele-
1,05 1,02 1,05 Margin plate
ment model L1/2 k1/4 0,9 L1/2 k1/4
Very fine mesh finite (1) The minimum net thickness is to be taken not less than
1,05 1,02 1,05
element model that required for the centre girder.
3.1.2 The yielding check is also to be carried out for pri- 3.4.3 Lateral pressure in flooding conditions
mary supporting members subjected to specific loads, such The lateral pressure in flooding conditions is constituted by
as concentrated loads. the still water pressure pSF and the wave pressure pWF
defined in Ch 5, Sec 6, [9].
3.2 Bracket arrangement
3.4.4 Wheeled loads
3.2.1 The requirements of this Article apply to primary sup- For primary supporting members subjected to wheeled
porting members with brackets at both ends of length not loads, the yielding check may be carried out according to
greater than 0,2 . [3.5] to [3.7] considering uniform pressures equivalent to
In the case of a significantly different bracket arrangement, the distribution of vertical concentrated forces, when such
the determination of normal and shear stresses due to forces are closely located.
design loads and the required section modulus and shear For the determination of the equivalent uniform pressures,
sectional area are considered by the Society on a case by the most unfavourable case, i.e. where the maximum
case basis. number of axles is located on the same primary supporting
member according to Fig 1 to Fig 3, is to be considered.
3.3 Load point
The equivalent still water pressure and inertial pressure are
3.3.1 Lateral pressure indicated in Tab 8.
Unless otherwise specified, lateral pressure is to be calcu-
Table 8 : Wheeled loads
lated at mid-span of the primary supporting member con-
Equivalent uniform still water and inertial pressures
sidered.
Figure 1 : Wheeled loads - Distribution of vehicles For arrangements different from those shown in Fig 1 to Fig 3,
on a primary supporting member the yielding check of primary supporting members is to be
carried out by a direct calculation, taking into account the
distribution of concentrated loads induced by vehicle wheels.
where:
S1, WV1, WH1 : Hull girder normal stresses, in N/mm2,
defined in:
Tab 9 for primary supporting members sub-
jected to lateral pressure
Tab 10 for primary supporting members sub-
jected to wheeled loads
: absolute value of the warping stress, in N/mm2,
induced by the torque 0,625 MWT and obtained
s X1
in accordance with Ch 6, Sec 1, [2.6]
CFV, CFH, CF : Combination factors defined in Tab 11.
Figure 3 : Wheeled loads
Distance between axles of two consecutive vehicles
3.5 Normal and shear stresses due to lateral
pressure in intact conditions
3.5.1 General
Normal and shear stresses, induced by lateral pressures, in
primary supporting members are to be determined from the
formulae given in:
[3.5.2] in the case of longitudinal and transverse stiffen-
X1
ers
X2
[3.5.3] in the case of vertical stiffeners.
Table 9 : Hull girder normal stresses - Primary supporting members subjected to lateral pressure
(1) When the ship in still water is always in hogging condition, MSW,S is to be taken equal to 0.
Note 1:
FD : Coefficient defined in Ch 5, Sec 2, [4].
Table 10 : Hull girder normal stresses - Primary supporting members subjected to wheeled loads
(1) When the ship in still water is always in hogging condition, MSW,S is to be taken equal to 0.
Note 1:
FD : Coefficient defined in Ch 5, Sec 2, [4].
Table 11 : Combination factors CFV, CFH and CF s : Coefficient taken equal to the greater of the fol-
lowing values:
Load case CFV CFH CF
S2 ( p Sd p Su ) + W2 ( p Wd p Wu )
a 1,0 0 0 s = 1 + 0 ,4 -----------------------------------------------------------------------------
-
S2 ( p Sd + p Su ) + W2 ( p Wd + p Wu )
b 1,0 0 0 S2 ( p Sd p Su ) + W2 ( p Wd p Wu )
s = 1 0, 4 -----------------------------------------------------------------------------
-
c 0,4 1,0 1,0 S2 ( p Sd + p Su ) + W2 ( p Wd + p Wu )
d 0,4 1,0 0
pSd : Still water pressure, in kN/m2, at the lower end
of the primary supporting member considered
3.5.2 Longitudinal and transverse primary
supporting members pSu : Still water pressure, in kN/m2, at the upper end
The maximum normal stress and shear stress are to be of the primary supporting member considered
obtained, in N/mm2, from the following formulae:
pWd : Wave pressure, in kN/m2, at the lower end of
S2 p S + W2 p W 2 3 the primary supporting member considered
= b ---------------------------------- s 10 + X1
mw
pWu : Wave pressure, in kN/m2, at the upper end of
S2 p S + W2 p W
= 5 s ---------------------------------- s the primary supporting member considered
A Sh
S2 ( p Sd p Su ) + W2 ( p Wd p Wu ) Ry
b = 1 + 0 ,2 -----------------------------------------------------------------------------
- ----------
S2 ( p Sd + p Su ) + W2 ( p Wd + p Wu ) R m
S2 ( p Sd p Su ) + W2 ( p Wd p Wu ) Ry
b = 1 0, 2 -----------------------------------------------------------------------------
- 0 ,5 ----------
S2 ( p Sd + p Su ) + W2 ( p Wd + p Wu ) R m
3.7 Net section modulus and net sectional 3.8.2 Longitudinal and transverse primary
supporting members
shear area complying with the checking
criteria The net section modulus w, in cm3, and the net shear sec-
tional area ASh , in cm2, of longitudinal or transverse primary
3.7.1 General supporting members are to be not less than the values
obtained from the following formulae:
The requirements in [3.7.2] and [3.7.3] provide the mini-
mum net section modulus and net shear sectional area of S2 p SF + W2 p WF 2 3
w = R m b -------------------------------------- s 10
primary supporting members subjected to lateral pressure in m ( R y m X1 )
intact conditions, complying with the checking criteria indi- S2 p SF + W2 p WF
A Sh = 10 R m s -------------------------------------- s
cated in [3.6]. Ry
where:
3.7.2 Longitudinal and transverse primary
supporting members b, s : Coefficients defined in [3.5.2].
The net section modulus w, in cm3, and the net shear sec-
3.8.3 Vertical primary supporting members
tional area ASh , in cm2, of longitudinal or transverse primary
supporting members are to be not less than the values The net section modulus w, in cm3, and the net shear sec-
obtained from the following formulae: tional area ASh , in cm2, of vertical primary supporting mem-
bers are to be not less than the values obtained from the
S2 p S + W2 p W following formulae:
w = R m b ----------------------------------------
- s 2 10 3
m ( R y R m X1 )
S2 p S + W2 p W S2 p SF + W2 p WF 2 3
A Sh = 10 R m s ---------------------------------- s w = R m b b -------------------------------------- s 10
Ry mR y
S2 p SF + W2 p WF
A Sh = 10 R m s s -------------------------------------- s
where b and s are the coefficients defined in [3.5.2]. Ry
where:
3.7.3 Vertical primary supporting members
The net section modulus w, in cm3, and the net shear sec- b, s : Coefficients defined in [3.5.2]
tional area ASh , in cm2, of vertical primary supporting mem- b : Coefficient taken equal to the greater of the fol-
bers are to be not less than the values obtained from the lowing values:
following formulae:
S2 ( p SFd p SFu ) + W2 ( p WFd p WFu )
b = 1 + 0 ,2 --------------------------------------------------------------------------------------
S2 p S + W2 p W 2 3 S2 ( p SFd + p SFu ) + W2 ( p WFd + p WFu )
w = R m b b --------------------------------------
- s 10
m ( R y R m A ) S2 ( p SFd p SFu ) + W2 ( p WFd p WFu )
b = 1 0, 2 --------------------------------------------------------------------------------------
S2 p S + W2 p W S2 ( p SFd + p SFu ) + W2 ( p WFd + p WFu )
A Sh = 10 R m s s ---------------------------------- s
Ry
s : Coefficient taken equal to the greater of the fol-
where: lowing values:
3.9 Net section modulus and net shear sec- 4 Yielding check of primary supporting
tional area of primary supporting mem- members analysed through a three
bers subjected to lateral pressure in dimensional structural model
testing conditions
4.4.4 Stress averaging on fine mesh Figure 5 : Example of stress averaging area
The average Von Mises equivalent stress VM-av , in N/mm2, at rounded bracket edge
is to be obtained from the following formula:
A i VM i
VM av = --------------------------
1
n
-
A i
1
where:
VM-i : Von Mises stress at the centre of the i-th element
within the considered area, in N/mm2
Ai : Area of the i-th element within the considered
area, in mm2
n : Number of elements within the considered area.
Stress averaging is to be performed over an area defined as
follows:
4.4.5 Particular requirements
the area considered for stress averaging is to have a size
not above the relevant spacing of ordinary stiffeners For fine mesh regions located on bracket webs in the vicin-
(s x s) ity of bracket toes, where an equivalent (s x s) area cannot
be defined, the yielding check is to be based only on the
for fine mesh along rounded edges (openings, rounded
criteria given in [4.4.3], item b).
brackets) the area considered for stress averaging is to
be limited only to the first ring of border elements, over Other structural details having shapes not allowing the
a length not greater than the relevant spacing of ordi- stress averaging as required in [4.4.4] are to be specially
nary stiffeners (see Fig 4 and Fig 5) considered by the Society, on a case by case basis.
5 Yielding check of primary supporting For all the elements modelled with fine meshes, it is to be
checked that the normal stresses 1 and 2 and the shear
members analysed through a
stress 12 , calculated according to Ch 7, App 3, [4], are in
complete ship structural model compliance with the following formulae:
Ry
5.1 General ---------- max( 1 , 2)
R m
Ry
5.1.1 The requirements of this Article apply for the yielding 0 ,5 ---------- 12
R m
check of primary supporting members which are to be ana-
lysed through a complete ship structural model.
6 Primary members subject to impact
5.1.2 A complete ship structural model is to be carried out, loads
when deemed necessary by the Society, to analyse primary
supporting members of ships with one or more of the fol-
lowing characteristics:
6.1 General
ships having large deck openings 6.1.1 The net section modulus w, in cm3, of primary sup-
ships having large space arrangements porting members and their net shear area Ash , in cm2, at any
position along their span are not to be less than the values
multideck ships having series of openings in side or lon- obtained from the following formulae:
gitudinal bulkheads, when the stresses due to the differ- 2
ent contribution of each deck to the hull girder strength f cb P I f p s 3
w = ----------------------
- 10
are to be taken into account. mR eH
3Q I
5.1.3 Based on the criteria in [5.1.2], analyses based on A sh = 10 ------------------
0, 9R eH
complete ship models may be required, in general, for the
following ship types: where:
ships with the service notation general cargo ship, hav- fcb : Correction factor for the bending moment at the
ing large deck openings ends and considering the patch load, taken as:
3 2
ships with the service notation container ship f cb = 3f p 8f p + 6f p
ships with the service notation ro-ro cargo ship PI : Any impact pressure defined in the Rules,
including:
ships with the service notation passenger ship
bottom impact pressure, as defined in Ch 8,
ships with the service notation ro-ro passenger ship. Sec 1, [3.2]
bow impact pressure, as defined in Ch 8,
5.2 Analysis criteria Sec 1, [4.2]
dynamic impact pressure, as defined in Ch 5,
5.2.1 The analysis of primary supporting members based Sec 6, [2.5]
on complete ship models is to be carried out according to stern impact pressure, as defined in Ch 8,
Ch 7, App 3. Sec 2, [4.2]
These requirements apply for: fp : Patch load modification factor, taken as:
the structural modelling
f p = ---I
the load modelling
QI : Shear force, in kN, taken as:
the stress calculation.
QI = fcs fdist PI I bI
R eH
cB = E1 for E1 -------
-
2
7 Buckling check
R eH R eH
cB = R eH 1 ----------
- for E1 > -------
-
4 E1 2
7.1 Local buckling of plate panels
where:
E1 : Euler column buckling stress, to be obtained, in
7.1.1 A local buckling check is to be carried out, for plate
N/mm2, from the following formula:
panels which constitute primary supporting members
and/or corrugated bulkheads, according to: I
E1 = 2 E ----------------2 10 4
A ( f )
Ch 7, App 1, [6] in case of buckling check based on a I : Minimum net moment of inertia, in cm4, of the
standard mesh element model pillar
Ch 7, Sec 1, [5] in other cases, calculating the stresses A : Net cross-sectional area, in cm2, of the pillar
in the plate panels according to [3] or [5], depending on : Span, in m, of the pillar
the structural model. f : Coefficient, to be obtained from Tab 13.
Table 13 : Coefficient f IXX : Net moment of inertia about the XX axis of the
pillar section (see Fig 7)
Boundary conditions of the pillar f
IYY : Net moment of inertia about the YY axis of the
Both ends fixed pillar section (see Fig 7)
Y
2
-------
2
X X
R eH
cL = E3 for E3 -------
-
2
7.2.3 Critical torsional buckling stress of built-up
R eH R eH
pillars cL = R eH 1 ----------
- for E3 > -------
-
4 E3 2
The critical torsional buckling stress of built-up pillars is to
be obtained, in N/mm2, from the following formulae:
where:
R eH
cT = E2 for E2 -------
- E3 : Euler local buckling stress, to be taken equal to
2
the lesser of the values obtained, in N/mm2,
R eH R eH
cT = R eH 1 ----------
- for E2 > -------
- from the following formulae:
4 E2 2
tW 2 4
where: E3 = 78 ------
- 10
h W
E2 : Euler torsional buckling stress, to be obtained,
in N/mm2, from the following formula: t 2 4
E3 = 32 ----F- 10
2 EI w I b F
E2 = -----------------
-2 + 0 ,41 E ---t
10 I p
4 I p
tW, hW, tF, bF : Dimensions, in mm, of the built-up section,
Iw : Net sectorial moment of inertia of the pillar, to
defined in [7.2.3].
be obtained, in cm6, from the following formula:
t f b f3 h w2 6 7.2.5 Critical local buckling stress of pillars having
I w = ---------------
- 10
24 hollow rectangular section
hW : Web height of built-up section, in mm The critical local buckling stress of pillars having hollow
tW : Net web thickness of built-up section, in mm rectangular section is to be obtained, in N/mm2, from the
bF : Face plate width of built-up section, in mm following formulae:
tF : Net face plate thickness of built-up section, in
mm R eH
cL = E4 for E4 -------
-
Ip : Net polar moment of inertia of the pillar, to be 2
R eH R eH
obtained, in cm4, from the following formula: cL = R eH 1 ----------
- for E4 > -------
-
4 E4 2
Ip = IXX + IYY
bF
cB F cT F cL F bF
tF ---------- 10 ----A- ---------- 10 ----A- ---------- 10 ----A- ----- 40
R m A R m A R m A tF
hW
tW
Hollow tubular
t d
cB F --- 55
---------- 10 ----A- Not required Not required t
d R m A
t 5,5 mm
Hollow rectangular
b b
--- 55
t2
t2
t1 cB F cL F h
---------- 10 ----A- Not required ---------- 10 ----A- --- 55
h R m A R m A t1
t1 5,5 mm
t2 5,5 mm
Note 1:
cB : Critical column buckling stress, in N/mm2, defined in [7.2.2]
cT : Critical torsional buckling stress, in N/mm2, defined in [7.2.3]
cL : Critical local buckling stress, in N/mm2, defined in [7.2.4] for built-up section or in [7.2.5] for hollow rectangular section
R : Resistance partial safety factor, equal to:
1,15 for column buckling
1,05 for torsional and local buckling
FA : Compression axial load in the pillar, in kN, defined in [7.2.1]
A : Net sectional area, in cm2, of the pillar.
1 provided that:
= ---------------------
10F M2 M1
1 ------------ tan2 u --------------------
- tan2 u
E1 A M2 + M1
Symbols
For symbols not defined in this Section, refer to the list at 1.1.4 Details where the stresses are to be calculated
the beginning of this Chapter. through a three dimensional structural model
pS : Still water pressure, in kN/m2, see [2.2] The requirements of Ch 7, App 1, [7] apply, in addition of
pW : Wave pressure, in kN/m2, see [2.2] those of [1] to [5] of this Section.
i : Index which denotes the load case a, b, c 1.1.5 Details located at ends of ordinary stiffeners
or d
The requirements of [1] to [6] of this Section apply.
j : Index which denotes the loading condition
Full load or Ballast 1.1.6 Other details
Kh, K : Stress concentration factors, defined in Ch 11, In general, for details other than those in [1.1.3], the stresses
Sec 2 for the special structural details there are to be calculated through a method agreed by the Soci-
specified ety on a case by case basis, using the load model defined in
KF : Fatigue notch factor, defined in [4.3.1] [2].
Km : Stress concentration factor, taking account of The checking criteria in [5] is generally to be applied.
misalignment, defined in [4.3.1]
KS : Coefficient taking account of the stiffener sec- 1.2 Net scantlings
tion geometry, defined in [6.2.2]
1.2.1 As specified in Ch 4, Sec 2, [1], all scantlings referred
T1 : Draught, in m, corresponding to the loading
to in this Section are net, i.e. they do not include any mar-
condition considered. gin for corrosion.
The gross scantlings are obtained as specified in Ch 4, Sec 2.
1 General
1.3 Sign conventions
1.1 Application
1.3.1 Bending moments
1.1.1 General
The sign conventions of bending moments at any ship trans-
The requirements of this Section apply to ships equal to or
verse section are the following ones:
greater than 170 m in length.
the vertical bending moment is positive when it induces
1.1.2 Structural details to be checked tensile stresses in the strength deck (hogging bending
The requirements of this Section apply for the fatigue check moment); it is negative in the opposite case (sagging
of special structural details defined in Ch 11, Sec 2, bending moment)
depending on the ship type and on the hull area where the the horizontal bending moment is positive.
detail are located.
1.3.2 Stresses
The Society may require other details to be checked, when
deemed necessary on the basis of the detail geometry and The sign conventions of stresses are the following ones:
stress level. tensile stresses are positive
In case of a hot spot located in a plate edge without any compressive stresses are negative.
welded joint, the SN curve to be used is to be considered
on a case by case basis by the Society. 1.4 Definitions
1.1.3 Categorisation of details 1.4.1 Hot spots
With respect to the method to be adopted to calculate the
Hot spots are the locations where fatigue cracking may
stresses acting on structural members, the details for which
occur. They are indicated in the relevant figures of special
the fatigue check is to be carried out may be grouped as fol-
structural details in Ch 11, Sec 2 (see [1.1.2]).
lows:
details where the stresses are to be calculated through a 1.4.2 Nominal stress
three dimensional structural model (e.g. connections Nominal stress is the stress in a structural component taking
between primary supporting members) into account macro-geometric effects but disregarding the
details located at ends of ordinary stiffeners, for which stress concentration due to structural discontinuities and to
an isolated structural model can be adopted. the presence of welds (see Fig 1).
t
2.1.2 Local and hull girder loads
hot spot
The fatigue check is based on the stress range induced at the
0,5 t
hot spot by the time variation of the local pressures and hull
1,5 t
girder loads in each load case a, b, c and d defined
in [2.2] for the loading conditions defined in [2.1.4] and
[2.1.3] (see Fig 2).
1.4.3 Hot spot stress For the purpose of fatigue check, each load case a, b,
Hot spot stress is a local stress at the hot spot taking into c and d is divided in two cases -max and -min for
which the local pressures and corresponding hull girder
account the influence of structural discontinuities due to the
loads are defined in [2.2] and [2.3] respectively.
geometry of the detail, but excluding the effects of welds
(see Fig 1).
Figure 2 : Stress range
1.4.4 Notch stress
Notch stress is a peak stress in a notch such as the root of a
weld or the edge of a cut-out. This peak stress takes into max
account the stress concentrations due to the presence of
notches (see Fig 1).
1.5 Partial safety factors The most severe full load and ballast conditions for the
detail concerned are to be considered in accordance with
Ch 5, Sec 1, [2.5].
1.5.1 The partial safety factors to be considered for the
fatigue check of structural details are specified in Tab 1.
2.1.4 Loading conditions for details located at ends
of ordinary stiffeners
Table 1 : Fatigue check - Partial safety factors
The cargo and ballast distribution is to be considered in
accordance with Ch 5, Sec 1, [2.4].
Value
Partial safety factors
covering uncertainties Symbol Details at 2.1.5 Spectral fatigue analysis
regarding: General ends of ordi-
nary stiffeners For ships with non-conventional shapes or with restricted
navigation, the Society may require a spectral fatigue analy-
Still water hull girder S1 1,00 1,00
sis to be carried out.
loads
Wave hull girder loads W1 1,05 1,15 In this analysis, the loads and stresses are to be evaluated
through long-term stochastic analysis taking into account
Still water pressure S2 1,00 1,00
the characteristics of the ship and the navigation notation.
Wave pressure W2 1,10 1,20
The load calculations and fatigue analysis are to be submit-
Resistance R 1,02 1,02 ted to the Society for approval.
14 gh T 1 + z
Bottom and sides below the ------------1 --------------
-
14 gh T 1 + z 2 T1
waterline ------------1 --------------
-
2 T1
(z T1) without being taken less than -----S- g ( z T 1 )
W
Note 1:
= T1 / T
14 y T1 + z
C F2 gh 2 ------- --------------
14 y T1 + z BW T1
y0 C F2 gh 2 ------- --------------
BW T1
without being taken less than -----S- g ( z T 1 )
Bottom and sides W
below the waterline
(z T1) 14 y T1 + z
C F2 gh 2 ------- --------------
BW T1 14 y T1 + z
y<0 C F2 gh 2 ------- --------------
BW T1
without being taken less than -----S- g ( z T 1 )
W
14 y
y0 g T 1 + 2C F2 ------- h z 0,0
Sides BW 2
above the waterline
(z > T1) 14 y
y<0 0,0 g T 1 + 2C F2 ------- h z
BW 2
(1) In the formulae giving the wave pressure pW, the ratio |y| / BW is not to be taken greater than 0,5.
Note 1:
= T1 / T
CF2 : Combination factor, to be taken equal to:
CF2 = 1,0 for load case c
CF2 = 0,5 for load case d
BW : Moulded breadth, in m, measured at the waterline at draught T1 , at the hull transverse section considered
h2 : Reference value, in m, of the relative motion in the inclined ship condition, defined in Ch 5, Sec 3, [3.3.2] and not to be
taken greater than the minimum of T1 and (D 0,9 T1).
b-min p W = L [ 0, 5a X1 B + a Z1 ( z TOP z ) ]
c-max
p W = L [ 0, 7C FA a Y2 ( y y H ) + ( 0, 7C FA a Z2 g ) ( z z H ) + g ( z z TOP ) ]
d-max
c-min
p W = L [ 0, 7C FA a Y2 ( y y H ) + ( 0, 7C FA a Z2 g ) ( z z H ) + g ( z z TOP ) ]
d-min
Dry bulk cargoes
2
2
p W = B a Z1 ( z B z ) ( sin ) tan 45 ---
2 o
b-max + ( cos )
2
2
2
p W = B a Z1 ( z B z ) ( sin ) tan 45 ---
2 o
b-min + ( cos )
2
The inertial pressure transmitted to the hull structures in inclined condition may gen-
c-max and c-min
erally be disregarded. Specific cases in which this simplification is not deemed per-
d-max and d-min
missible by the Society are considered individually.
(1) The symbols used in the formulae of inertial pressures are defined in Ch 5, Sec 6.
Note 1:
CFA : Combination factor, to be taken equal to:
CFA = 0,7 for load case c
CFA = 1,0 for load case d.
2.2.4 Load cases c-max and c-min, in inclined for members not contributing to the hull girder longitu-
ship condition dinal strength:
Still water pressure (pS) includes: h = 0
the still water sea pressure defined in Ch 5, Sec 5, [1]
where:
the still water internal pressure, defined in Ch 5, Sec 6
for the various types of cargoes and for ballast. SW : Still water hull girder normal stresses, in
N/mm2, taken equal to:
Wave pressure (pW) includes:
M SW
the wave pressure obtained from Tab 3 - ( z N )10 3
SW = ----------
IY
the inertial pressure obtained from Tab 4 for the various
types of cargoes and ballast. MSW : Still water bending moment for the loading con-
dition considered
2.2.5 Load cases d-max and d-min, in inclined
ship condition WV, WV, WH: Hull girder normal stresses, in N/mm2,
defined in Tab 5
Still water pressure (pS) includes:
the still water sea pressure defined in Ch 5, Sec 5, [1] Table 5 : Nominal hull girder normal stresses
the still water internal pressure, defined in Ch 5, Sec 6
for the various types of cargoes and for ballast. Load
WV, in N/mm2 WH, in N/mm2
case
Wave pressure (pW) includes:
0 ,625M WV ,H
the wave pressure obtained from Tab 3 a-max ------------------------------- ( z N )10 3 0
IY
the inertial pressure obtained from Tab 4 for the various
types of cargoes and ballast. 0 ,625F D M WV ,S
a-min ------------------------------------ ( z N )10 3 0
IY
2.3 Nominal hull girder normal stresses b-max
0 0
b-min
2.3.1 The nominal hull girder normal stresses are obtained,
in N/mm2, from the following formulae: c-max 0 ,625M WH 3
0 --------------------------- y10
d-max IZ
for members contributing to the hull girder longitudinal
strength: c-min 0 ,625M WH
0 --------------------------- y10 3
h = S1 SW + W1 ( C FV WV + C FH WH + C F ) d-min IZ
: Warping stresses, in N/mm2, induced by the TA : Average period, in seconds, to be taken equal
torque 0,625MWT and obtained through direct to:
calculation analyses based on a structural
TA = 4 log L
model in accordance with Ch 6, Sec 1, [2.6]
TFL : Design fatigue life, in years, taken equal to:
CFV, CFH, CF: Combination factors defined in Tab 6.
TFL = 20, when the additional class notation
Table 6 : Combination factors CFV, CFH and CF VeriSTAR-HULL DFL xx years is not
assigned
Load case CFV CFH CF TFL = xx, when the additional class notation
a 1,0 0 0 VeriSTAR-HULL DFL xx years is assigned,
xx having a value between 25 and 40
b 1,0 0 0
c 0,4 1,0 1,0 pR = 105
X t
N [ X + 1 , ij ] = t e dt
0
X t
D ij = -----t -------------------------
- --- + 1 C [ X + 1 ] = t e dt
K p ( ln p R ) 3 ij C 0
Value of ij
X
1,5 2,0 2,5 3,0 3,5 4,0 4,5 5,0 5,5 6,0 6,5 7,0 7,5 8,0
2,5 0,38 0,73 1,13 1,53 1,90 2,22 2,48 2,70 2,86 2,99 3,08 3,15 3,20 3,24
2,6 0,38 0,75 1,19 1,63 2,04 2,41 2,71 2,96 3,16 3,31 3,42 3,51 3,57 3,61
2,7 0,39 0,78 1,25 1,73 2,20 2,62 2,97 3,26 3,49 3,67 3,81 3,91 3,99 4,04
2,8 0,39 0,80 1,31 1,85 2,38 2,85 3,26 3,60 3,87 4,09 4,25 4,37 4,46 4,53
2,9 0,39 0,83 1,38 1,98 2,57 3,11 3,58 3,98 4,30 4,56 4,75 4,90 5,01 5,10
3,0 0,39 0,86 1,45 2,12 2,78 3,40 3,95 4,41 4,79 5,09 5,33 5,51 5,65 5,75
3,1 0,40 0,89 1,54 2,27 3,01 3,72 4,35 4,89 5,34 5,70 5,99 6,21 6,37 6,49
3,2 0,40 0,92 1,62 2,43 3,27 4,08 4,81 5,44 5,97 6,40 6,74 7,01 7,21 7,36
3,3 0,41 0,95 1,72 2,61 3,56 4,48 5,32 6,06 6,68 7,20 7,61 7,93 8,17 8,36
3,4 0,41 0,99 1,82 2,81 3,87 4,92 5,90 6,76 7,50 8,11 8,60 8,99 9,29 9,51
3,5 0,42 1,03 1,93 3,03 4,22 5,42 6,55 7,55 8,42 9,15 9,74 10,21 10,57 10,85
3,6 0,42 1,07 2,04 3,26 4,60 5,97 7,27 8,45 9,48 10,34 11,05 11,62 12,06 12,41
3,7 0,43 1,12 2,17 3,52 5,03 6,59 8,09 9,47 10,68 11,71 12,56 13,25 13,79 14,21
3,8 0,43 1,16 2,31 3,80 5,50 7,28 9,02 10,63 12,06 13,28 14,30 15,13 15,80 16,31
3,9 0,44 1,21 2,45 4,10 6,02 8,05 10,06 11,94 13,63 15,09 16,31 17,32 18,12 18,76
4,0 0,45 1,26 2,61 4,43 6,59 8,91 11,23 13,43 15,42 17,16 18,63 19,85 20,83 21,61
4,1 0,45 1,32 2,78 4,80 7,22 9,87 12,55 15,12 17,47 19,54 21,31 22,78 22,98 24,94
4,2 0,46 1,38 2,96 5,20 7,93 10,95 14,05 17,05 19,82 22,29 24,41 26,19 27,65 28,83
4,3 0,47 1,44 3,16 5,63 8,70 12,15 15,73 19,24 22,51 25,45 28,00 30,16 31,93 33,38
4,4 0,48 1,51 3,37 6,11 9,56 13,50 17,64 21,74 25,60 29,10 32,16 34,77 36,94 38,71
4,5 0,49 1,57 3,60 6,63 10,52 15,01 19,79 24,58 29,14 33,31 36,99 40,15 42,79 44,96
4,6 0,49 1,65 3,85 7,20 11,57 16,70 22,23 27,82 33,20 38,17 42,59 46,41 49,63 52,29
4,7 0,50 1,73 4,12 7,82 12,75 18,59 24,98 31,53 37,88 43,79 49,10 53,72 57,65 60,91
4,8 0,52 1,81 4,40 8,50 14,04 20,72 28,11 35,75 43,25 50,29 56,66 62,26 67,05 71,05
4,9 0,52 1,90 4,71 9,25 15,49 23,11 31,64 40,57 49,42 57,81 65,47 72,24 78,08 82,98
5,0 0,53 1,99 5,04 10,07 17,09 25,78 35,65 46,08 56,53 66,52 75,72 83,92 91,03 97,05
5,1 0,55 2,09 5,40 10,97 18,86 28,79 40,19 52,39 64,71 76,61 87,66 97,58 106,3 113,6
5,2 0,56 2,19 5,79 11,95 20,84 32,17 45,34 59,60 74,15 88,32 101,6 113,6 124,2 133,2
5,3 0,57 2,30 6,21 13,03 23,03 35,96 51,19 67,85 85,02 101,9 117,8 132,4 145,3 156,4
5,4 0,58 2,41 6,66 14,21 25,46 40,23 57,83 77,29 97,56 117,7 136,8 154,4 170,1 183,8
5,5 0,59 2,54 7,14 15,50 28,17 45,03 65,37 88,11 112,0 136,0 159,0 180,3 199,4 216,2
5,6 0,61 2,67 7,67 16,92 31,18 50,42 73,93 100,5 128,8 157,3 184,9 210,7 234,0 254,6
5,7 0,62 2,80 8,23 18,48 34,53 56,49 83,66 114,7 148,1 182,0 215,2 246,4 274,8 300,1
5,8 0,64 2,95 8,84 20,19 38,25 63,33 94,73 131,0 170,4 210,9 250,7 288,4 323,1 354,1
5,9 0,65 3,10 9,50 22,07 42,39 71,02 107,3 149,8 196,2 244,4 292,2 337,9 380,2 418,2
6,0 0,67 3,26 10,21 24,13 47,00 79,69 121,6 171,2 226,1 283,5 340,9 396,2 447,7 494,4
6,1 0,68 3,44 10,98 26,39 52,14 89,45 138,0 195,9 260,6 329,0 398,0 464,9 527,7 585,0
6,2 0,70 3,62 11,82 28,87 57,86 100,5 156,5 224,2 300,6 382,1 464,9 546,0 622,5 692,8
6,3 0,72 3,81 12,71 31,60 64,24 112,9 177,7 256,8 347,0 444,0 543,5 641,6 734,9 821,1
6,4 0,73 4,02 13,68 34,60 71,34 126,9 201,7 294,3 400,7 516,3 635,8 754,5 868,3 974,0
6,5 0,75 4,23 14,73 37,90 79,25 142,6 229,2 337,3 463,0 600,6 744,2 887,9 1026,6 1156,3
6,6 0,77 4,46 15,87 41,52 88,07 160,4 260,5 386,9 535,2 699,2 871,6 1045,5 1214,6 1373,8
2,5 3,323 3,3 8,855 the fatigue life improvement factor for grinding IF may,
generally, be taken equal to 2,2 provided that a perma-
2,6 3,717 3,4 10,136
nent protective coating is applied on the ground weld.
2,7 4,171 3,5 11,632 Otherwise, the value of IF may be considered by the
2,8 4,694 3,6 13,381 Society on a case by case basis.
2,9 5,299 3,7 15,431
3.1.4 Improvement techniques other than grinding
3,0 6,000 3,8 17,838 of welds
3,1 6,813 3,9 20,667 Improving fatigue life by using improvement techniques
3,2 7,757 4,0 24,000 other than grinding is to be regarded as an exceptional
measure. Such improvement techniques may be considered
by the Society on a case by case basis. In such a case, the
Table 9 : Part of the ships life in full load condition fatigue life improvement factor IF is to be duly justified by
the designer.
Service notation Coefficient
Oil tanker ESP 4 Stress range
Chemical tanker ESP
Liquefied gas carrier
Tanker 0,60
4.1 General
Bulk carrier
Ore carrier ESP
4.1.1 Calculation point
Combination carrier ESP Unless otherwise specified, stresses are to be determined at
the hot spots indicated, for each detail, in the relevant fig-
Others 0,75
ures in Ch 11, Sec 2.
DaF, DbF, DcF, DdF: Elementary damage ratios for load cases 4.1.2 Stress components
a, b, c and d, respectively, in Full
For the details in [1.1.3], the stresses to be used in the
load condition, defined in [3.1.1]
fatigue check are the normal stresses in the directions indi-
DaB, DbB, DcB: Elementary damage ratios for load cases a, cated, for each detail, in the relevant figures in Ch 11, Sec 2.
b, and c, respectively, in Ballast condi- Where the fatigue check is required for details other than
tion, defined in [3.1.1] those in [1.1.3], the stresses to be used are the principal
Kcor : Corrosion factor, taken equal to: stresses at the hot spots which form the smallest angle with
the crack rising surface.
Kcor = 1,5 for cargo oil tanks
Kcor = 1,1 for ballast tanks having an effec- 4.2 Hot spot stress range
tive coating protection.
4.2.1 Elementary hot spot stress range
3.1.3 Grinding of welds The elementary hot spot stress range G,ij is to be obtained,
in N/mm2, in accordance with:
In principle, grinding technique for improving fatigue life is
applicable only to full penetration welds; applicability is Ch 7, App 1, [7] for details where the stresses are to be
indicated in Tab 11 depending on the weld configuration. calculated through a three dimensional structural mod-
For welds other than full penetration welds, grinding may els
be considered on a case by case basis. [6.2] for details located at ends of ordinary stiffeners.
When applicable, grinding of welds is to be regarded as an
exceptional measure considered case by case, and only 4.3 Notch stress range
when the design fatigue life cannot be achieved by the
design (such as improvement of the shape of cut-outs, sof- 4.3.1 Elementary notch stress range
tening of bracket toes and local increase in thickness) and
The elementary notch stress range is to be obtained, in
geometry of the structural detail.
N/mm2, from the following formula:
In such a case:
N,ij = KC,ij N0,ij
the information "grinding of welds", with indication of with:
the toe to be ground, is to be specified by the designer
on drawings N0,ij = 0,7 KF Km G,ij
Geometry Km (1)
Axial misalignment between flat plates
t m
3 ( m m0 )
1 + --------------------------
t
32
6 ( m m0 ) t1
1 + -------------------------- ----------------------
32 32
-
t1 t1 + t2
t2 m t1
mm
1 + -----------------0-
t+h
m
t
(1) When the actual misalignment m is lower than the permissible misalignment m0, Km is to be taken equal to 1.
Note 1:
m : Actual misalignment between two abutting members
m0 : Permissible misalignment for the detail considered, given in Ch 11, Sec 2.
Butt weld
Perpendicular to
2,40 yes
the weld
Continuous
Perpendicular to
2,15 yes
the weld (1)
Axial loading
Lap weld out of plane and
4,50 no
(root cracking) perpendicular to
the weld
Perpendicular to
Full penetration 2,10 yes
the weld
Cruciform
joint
Toe cracking:
yes
2,10
Perpendicular to
Partial penetration
the weld
Root cracking:
no
4,50
(1) This case includes the hot spots indicated in the sheets of special structural details in Ch 11, Sec 2 relevant to the connections
of longitudinal ordinary stiffeners with transverse primary supporting members.
S2 p S + W2 p W
1 ------ s 10
s
= ----------------------------------
2 3
12w 2
where:
w : Net section modulus, in cm3, of the stiffener,
with an attached plating of width bp , to be cal-
culated as specified in Ch 4, Sec 3, [3.4] tf : Face plate net thickness, in mm
s : Spacing, in m, of ordinary stiffeners bf : Face plate width, in mm
: Span, in m, of ordinary stiffeners, measured wA, wB : Net section moduli of the stiffener without
between the supporting members, see Ch 4, Sec attached plating, in cm3, respectively in A and B
3, [3.2]. (see Fig 3), about its neutral axis parallel to the
stiffener web
6.2.2 Elementary hot spot stress range
: Local range of deflection, in mm, of the ordi-
For each load case a, b, c and d, the elementary hot nary stiffener
spot stress range G,ij is to be obtained, in N/mm2, from the
I : Net moment of inertia, in cm4, of the ordinary
following formula:
stiffener with an attached plating of width bp , to
G, ij = | G (i-max) G (i-min) | + KDEF, ij be calculated as specified in Ch 4, Sec 3, [3.4].
Symbols
For symbols not defined in this Appendix, refer to the list at analysed through three dimensional structural models,
the beginning of this Chapter. according to Ch 7, Sec 3.
: Sea water density, taken equal to 1,025 t/m3 The analysis application procedure is shown graphically in
g : Gravity acceleration, in m/s2: Fig 1.
g = 9,81 m/s2 1.1.2 This Appendix deals with that part of the structural
h1 : Reference values of the ship relative motions in analysis which aims at:
the upright ship condition, defined in Ch 5, Sec calculating the stresses in the primary supporting mem-
3, [3.3] bers in the midship area and, when necessary, in other
h2 : Reference values of the ship relative motions in areas, which are to be used in the yielding and buckling
the inclined ship conditions, defined in Ch 5, checks
Sec 3, [3.3] calculating the hot spot stress ranges in the structural
T details which are to be used in the fatigue check.
= -----1
T
Figure 1 : Application procedure of the analyses
T1 : Draught, in m, corresponding to the loading
based on three dimensional models
condition considered
MSW : Still water bending moment, in kN.m, at the Capability of the
Demand
hull transverse section considered hull strucuture
2 = 1 for L 120 m
2 = L/120 for L < 120 m Fatigue analysis
1 General
Adjustment of Yes
local details
1.1 Application
1.1.1 The requirements of this Appendix apply for the anal- END
of
ysis criteria, structural modelling, load modelling and stress analysis
calculation of primary supporting members which are to be
1.1.3 The yielding and buckling checks of primary support- 3.1.2 Net scantlings
ing members are to be carried out according to Ch 7, Sec 3. All the elements in [3.1.1] are to be modelled with their net
The fatigue check of structural details is to be carried out scantlings according to Ch 4, Sec 2. Therefore, also the hull
according to Ch 7, Sec 4. girder stiffness and inertia to be reproduced by the model
are those obtained by considering the net scantlings of the
2 Analysis criteria hull structures.
2.1.1 All primary supporting members in the midship 3.2.1 The longitudinal extension of the structural model is
regions are normally to be included in the three dimen- to be such that:
sional model, with the purpose of calculating their stress the hull girder stresses in the area to be analysed are
level and verifying their scantlings. properly taken into account in the structural analysis
When the primary supporting member arrangement is such the results in the areas to be analysed are not influenced
that the Society can accept that the results obtained for the by the unavoidable inaccuracy in the modelling of the
midship region are extrapolated to other regions, no addi- boundary conditions.
tional analyses are required. Otherwise, analyses of the
other regions are to be carried out. 3.2.2 In general, for multitank/hold ships more than 170 m
in length, the conditions in [3.2.1] are considered as being
2.2 Finite element model analyses satisfied when the model is extended over at least three
cargo tank/hold lengths.
2.2.1 The analysis of primary supporting members is to be For the analysis of the midship area, this model is to be such
carried out on standard mesh models, as defined in [3.4.3]. that its aft end corresponds to the first transverse bulkhead
aft of the midship, as shown in Fig 2. The structure of the
2.2.2 Areas which appear, from the primary supporting
fore and aft transverse bulkheads located within the model,
member analysis, to be highly stressed may be required to
including the bulkhead plating, is to be modelled.
be further analysed through appropriately meshed structural
models, as defined in [3.4.4].
Figure 2 : Model longitudinal extension
Ships more than 170 m in length
2.3 Beam model analyses
2.3.1 Beam models may be adopted in cases specified in
Ch 7, Sec 3, [1.1.2], provided that:
primary supporting members are not so stout that the CL
beam theory is deemed inapplicable by the Society
their behaviour is not substantially influenced by the
transmission of shear stresses through the shell plating. Length of the model
In any case, finite element models are to be adopted when
deemed necessary by the Society on the basis of the ships
3.2.3 For ships less than 170 m in length, the model may
structural arrangement.
be limited to one cargo tank/hold length (one half cargo
tank/hold length on either side of the transverse bulkhead;
2.4 Structural detail analysis see Fig 3).
2.4.1 Structural details in Ch 7, Sec 4, [1.1.4], for which a However, larger models may need to be adopted when
fatigue analysis is to be carried out, are to be modelled as deemed necessary by the Society on the basis of the ships
specified in [7]. structural arrangement.
3.3 Finite element modelling criteria 3.3.2 Modelling of the most highly stressed areas
The areas which appear from the analyses based on stand-
3.3.1 Modelling of primary supporting members ard mesh models to be highly stressed may be required to
The analysis of primary supporting members based on be further analysed, using the mesh accuracy specified in
standard mesh models, as defined in [3.4.3], is to be carried [3.4.4].
out by applying one of the following procedures (see Fig 4),
depending on the computer resources: 3.4 Finite element models
an analysis of the whole three dimensional model based
on a standard mesh 3.4.1 General
an analysis of the whole three dimensional model based Finite element models are generally to be based on linear
on a coarse mesh, as defined in [3.4.2], from which the assumptions. The mesh is to be executed using membrane
nodal displacements or forces are obtained to be used or shell elements, with or without mid-side nodes.
as boundary conditions for analyses based on fine mesh Meshing is to be carried out following uniformity criteria
models of primary supporting members, e.g.: among the different elements.
- transverse rings Most of quadrilateral elements are to be such that the ratio
- double bottom girders between the longer side length and the shorter side length
- side girders does not exceed 2. Some of them may have a ratio not
exceeding 4. Their angles are to be greater than 60 and less
- deck girders than 120. The triangular element angles are to be greater
- primary supporting members of transverse bulk- than 30 and less than 120.
heads Further modelling criteria depend on the accuracy level of
- primary supporting members which appear from the the mesh, as specified in [3.4.2] to [3.4.4].
analysis of the whole model to be highly stressed.
3.4.2 Coarse mesh
Figure 4 : Finite element modelling criteria The number of nodes and elements is to be such that the
stiffness and inertia of the model properly represent those of
the actual hull girder structure, and the distribution of loads
Whole three dimensional model Whole three dimensional model among the various load carrying members is correctly taken
STANDARD MESH COARSE MESH
into account.
To this end, the structural model is to be built on the basis of
Models of primary supporting the following criteria:
members
STANDARD MESH
ordinary stiffeners contributing to the hull girder longitu-
dinal strength and which are not individually repre-
sented in the model are to be modelled by rod elements
and grouped at regular intervals
Application of boundary
conditions derived from coarse webs of primary supporting members may be modelled
mesh model analysis with only one element on their height
face plates may be simulated with bars having the same
cross-section
Strength criteria : the plating between two primary supporting members
- yielding check, may be modelled with one element stripe
- buckling check
of primary supporting members holes for the passage of ordinary stiffeners or small pipes
may be disregarded
(When necessary)
manholes (and similar discontinuities) in the webs of
primary supporting members may be disregarded, but
Mesh for the analysis of the element thickness is to be reduced in proportion to
highly stressed areas the hole height and the web height ratio.
The structural model is to be built on the basis of the follow- for open section beams (see Fig 5):
ing criteria:
1
( t )10
4
I T = ---
3
i i
webs of primary members are to be modelled with at 3
i
least three elements on their height
for box-type section beams, e.g. those with which hop-
the plating between two primary supporting members is
per tanks and lower stools are modelled (see Fig 6):
to be modelled with at least two element stripes
2
the ratio between the longer side and the shorter side of 4 4
I T = ----------- 10
i
elements is to be less than 3 in the areas expected to be
highly stressed
---
ti
i
holes for the passage of ordinary stiffeners may be disre- for beams of double skin structures (see Fig 7):
garded.
2
t 1 t 2 ( b 1 + b 2 )H D 4
I T = --------------------------------------
- 10
In some specific cases, some of the above simplifications 2 ( t1 + t2 )
may not be deemed acceptable by the Society in relation to
the type of structural model and the analysis performed. where:
i : Sum of all the profile segments that constitute
3.4.4 Fine mesh for the analysis of structural details
the beam section
In order to obtain an accurate representation of stresses in
ti , i : Net thickness and length, respectively, in mm,
the area of interest, the structural model is to be built on the
of the i-th profile segment of the beam section
basis of the following criteria:
(see Fig 5 and Fig 6)
the mesh dimensions are to be such as to enable a faith-
: Area, in mm2, of the section enclosed by the
ful representation of the stress gradients
beam box profile (see Fig 6)
the size of elements in the area of interest is not to be
t1 , t2 : Net thickness, in mm, of the inner and outer
greater than 50 mm x 50 mm
plating, respectively, (see Fig 7)
the extent of the refined area is to be at least of 10 ele- b1 , b2 : Distances, in mm, from the beam considered to
ments in any direction around its centre
the two adjacent beams (see Fig 7)
the use of membrane elements is only allowed when HD : Height, in mm, of the double skin (see Fig 7).
significant bending effects are not present; in the other
cases, elements with general behaviour are to be used
Figure 5 : Open section beams
the use of linear triangular elements is to be avoided as
much as possible in high stress area; quadrilateral ele-
ments are to have 90 angles as much as possible, or
angles between 60 and 120; the aspect ratio is to be
close to 1; when the use of a linear triangular element
cannot be avoided, its edges are to have the same length
the local fine mesh can either be included directly into
the global model or belong to a separate sub-model; the Ji
gradient of mesh size must be reasonably low.
i
3.5 Beam models
Figure 7 : Beams of double skin structures Table 1 : Symmetry and anti-symmetry conditions
b1 b2 in way of the ships centreline longitudinal plane
t1
Boundary DISPLACEMENTS in directions (1)
conditions X Y Z
HD Symmetry free fixed free
Anti-symmetry fixed free fixed
t2
Boundary ROTATION around axes (1)
conditions X Y Z
3.5.3 Variable cross-section primary supporting
members Symmetry fixed free fixed
In the case of variable cross-section primary supporting
Anti-symmetry free fixed free
members, the inertia characteristics of the modelling beams
may be assumed as a constant and equal to their average (1) X, Y and Z directions and axes are defined with respect
value along the length of the elements themselves. to the reference co-ordinate system in Ch 1, Sec 2, [4].
3.5.4 Modelling of primary supporting members ends 3.6.2 Structural models extended over one cargo
The presence of end brackets may be disregarded; in such tank/hold length
case their presence is also to be neglected for the evaluation
of the beam inertia characteristics. Symmetry conditions are to be applied at the fore and aft
ends of the model, as specified in Tab 2.
Rigid end beams are generally to be used to connect ends
of the various primary supporting members, such as:
Table 2 : Symmetry conditions
floors and side vertical primary supporting members at the model fore and aft ends
bottom girders and vertical primary supporting members
of transverse bulkheads DISPLACEMENTS ROTATION
cross ties and side/longitudinal bulkhead primary sup- in directions (1): around axes (1):
porting members. X Y Z X Y Z
fixed free free free fixed fixed
3.5.5 Beams representing hull girder characteristics
(1) X, Y and Z directions and axes are defined with respect
The stiffness and inertia of the hull girder are to be taken
to the reference co-ordinate system in Ch 1, Sec 2, [4].
into account by longitudinal beams positioned as follows:
on deck and bottom in way of side shell and longitudi-
nal bulkheads, if any, for modelling the hull girder bend- When the hull structure is modelled over half the ship's
ing strength breadth (see [3.2.4]), in way of the ships centreline longitu-
dinal plane, symmetry or anti-symmetry boundary condi-
on deck, side shell, longitudinal bulkheads, if any, and
tions as specified in Tab 1 are to be applied, depending on
bottom for modelling the hull girder shear strength.
the loads applied to the model (symmetrical or anti-sym-
metrical, respectively).
3.6 Boundary conditions of the whole three
dimensional model Vertical supports are to be fitted at the nodes positioned in
way of the connection of the transverse bulkheads with lon-
3.6.1 Structural model extended over at least three gitudinal bulkheads, if any, or with sides.
cargo tank/hold lengths
The whole three dimensional model is assumed to be fixed
at one end, while shear forces and bending moments are 4 Primary supporting members load
applied at the other end to ensure equilibrium (see [4]). model
At the free end section, rigid constraint conditions are to be
applied to all nodes located on longitudinal members, in 4.1 General
such a way that the transverse section remains plane after
deformation.
4.1.1 Loading conditions and load cases in intact
When the hull structure is modelled over half the ship's conditions
breadth (see [3.2.4]), in way of the ships centreline longitu-
dinal plane, symmetry or anti-symmetry boundary condi- The still water and wave loads are to be calculated for the
tions as specified in Tab 1 are to be applied, depending on most severe loading conditions as given in the loading man-
the loads applied to the model (symmetrical or anti-sym- ual, with a view to maximising the stresses in the longitudi-
metrical, respectively). nal structure and primary supporting members.
The following loading conditions are generally to be con- Wave loads include:
sidered: the wave pressure, defined in [4.2.2] for each load case
homogeneous loading conditions at draught T a, b, c and d
non-homogeneous loading conditions at draught T, the inertial loads, defined in Ch 5, Sec 6 for the various
when applicable types of cargoes and for ballast, and for each load case
a, b, c and d.
partial loading conditions at the relevant draught
ballast conditions at the relevant draught. 4.2.2 Wave loads
The wave pressure at any point of the model is obtained
The wave local and hull girder loads are to be calculated in from the formulae in Tab 3 for upright ship conditions (load
the mutually exclusive load cases a, b, c and d in cases a and b) and in Tab 4 for inclined ship conditions
Ch 5, Sec 4. (load cases c and d).
4.1.2 Loading conditions and load cases in flooding 4.2.3 Distributed loads
conditions
Distributed loads are to be applied to the plating panels.
When applicable, the pressures in flooding conditions are
In the analyses carried out on the basis of membrane finite
to be calculated according to Ch 5, Sec 6, [9].
element models or beam models, the loads distributed per-
pendicularly to the plating panels are to be applied on the
4.1.3 Lightweight
ordinary stiffeners proportionally to their areas of influence.
The structure weight of the modelled portion of the hull is to When ordinary stiffeners are not modelled or are modelled
be included in the static loads. In order to obtain the actual with rod elements (see [3.4]), the distributed loads are to be
longitudinal distribution of the still water bending moment, applied to the primary supporting members actually sup-
the lightweight is to be uniformly distributed over the length porting the ordinary stiffeners.
of the model.
4.2.4 Concentrated loads
4.1.4 Models extended over half ships breadth When the elements directly supporting the concentrated
When the ship is symmetrical with respect to her centreline loads are not represented in the structural model, the loads
longitudinal plane and the hull structure is modelled over are to be distributed on the adjacent structures according to
half the ship's breadth, non-symmetrical loads are to be the actual stiffness of the structures which transmit them.
broken down into symmetrical and anti-symmetrical loads
In the analyses carried out on the basis of coarse mesh finite
and applied separately to the model with symmetry and
element models or beam models, concentrated loads applied
anti-symmetry boundary conditions in way of the ships
in five or more points almost equally spaced inside the same
centreline longitudinal plane (see [3.6]).
span may be applied as equivalent linearly distributed loads.
4.2 Local loads 4.2.5 Cargo in sacks, bales and similar packages
The vertical loads are comparable to distributed loads. The
4.2.1 General loads on vertical walls may be disregarded.
Still water loads include:
4.2.6 Other cargoes
the still water sea pressure, defined in Ch 5, Sec 5, [1]
The modelling of cargoes other than those mentioned under
the still water internal loads, defined in Ch 5, Sec 6 for [4.2.3] to [4.2.5] will be considered by the Society on a
the various types of cargoes and for ballast. case by case basis.
g T 1 + C F2
14 ------
y
- h + A R y z
Sides above the waterline BW 1
0,0
(z > T1)
without being taken, for case c only, less than 0,15 1 2 L
(1) In the formulae giving the wave pressure pW, the ratio (y / BW) is not to be taken greater than 0,5.
Note 1:
CF2 : Combination factor, to be taken equal to:
CF2 = 1,0 for load case c
CF2 = 0,5 for load case d
BW : Moulded breadth, in m, measured at the waterline at draught T1 , at the hull transverse section considered
AR : Roll amplitude, defined in Ch 5, Sec 3, [2.4.1].
Table 5 : Coefficient 1 These loads are to be applied for the following two conditions:
maximal bending moments at the middle of the central
Exposed deck location 1 tank/hold within 0,4 L amidships: the hull girder loads
Freeboard deck and below 1,00 applied at the free end section are to be such that the
Top of lowest tier 0,75 values of the hull girder loads in Tab 6 are obtained
Top of second tier 0,56 maximal shear forces in way of the aft transverse bulk-
Top of third tier 0,42 head of the central tank/hold: the hull girder loads
applied at the free end section are to be such that the
Top of fourth tier 0,32
values of the hull girder loads in Tab 7 are obtained.
Top of fifth tier 0,25
Top of sixth tier 0,20 4.3.2 Structural model extended over one cargo
tank/hold length
Top of seventh tier 0,15
The normal and shear stresses induced by the hull girder
Top of eighth tier and above 0,10 loads in Tab 8 are to be added to the stresses induced in the
primary supporting members by local loads.
4.3 Hull girder loads
4.3.1 Structural model extended over at least three 4.4 Additional requirements for the load
cargo tank/hold lengths assignment to beam models
The hull girder loads are constituted by:
the still water and wave vertical bending moments 4.4.1 Vertical and transverse concentrated loads are to be
applied to the model, as shown in Fig 8, to compensate the
the horizontal wave bending moment
portion of distributed loads which, due to the positioning of
the still water and wave vertical shear forces, beams on their neutral axes, are not modelled.
and are to be applied at the model free end section. The In this figure, FY and FZ represent concentrated loads equiv-
shear forces are to be distributed on the plating according to alent to the dashed portion of the distributed loads which is
the theory of bidimensional flow of shear stresses. not directly modelled.
Table 6 : Hull girder loads - Maximal bending moments at the middle of the central tank/hold
Vertical bending moments at the Horizontal wave bending Vertical shear forces at the
Ship
Load case middle of the central tank/hold moment at the middle middle of the central tank/hold
condition
Still water Wave of the central tank/hold Still water Wave
Upright a crest S1 MSW 0,625 W1 MWV,H 0 0 0
a trough S1 MSW 0,625 W1 FD MWV,S 0 0 0
b S1 MSW 0,625 W1 FD MWV,S 0 0 0
Inclined c S1 MSW 0,250 W1 MWV 0,625 W1 MWH 0 0
d S1 MSW 0,250 W1 MWV 0,625 W1 MWH 0 0
Note 1: Hull girder loads are to be calculated at the middle of the central tank/hold.
Table 7 : Hull girder loads - Maximal shear forces in way of the aft bulkhead of the central tank/hold
Note 1: Hull girder loads are to be calculated in way of the aft bulkhead of the central tank/hold.
Table 8 : Hull girder loads for a structural model extended over one cargo tank/hold length
Vertical bending moments at the Horizontal wave bending Vertical shear forces at the
Ship middle of the model middle of the model
Load case moment at the middle
condition
Still water Wave of the model Still water Wave
Upright a crest S1 MSW 0,625 W1 MWV,H 0 S1 QSW 0,625 W1 QWV
Note 1: Hull girder loads are to be calculated at the middle of the model.
Figure 8 : Concentrated loads case, the stresses calculated by the finite element program
equivalent to non-modelled distributed loads include the contribution of both local and hull girder loads.
When finite element models extend over one cargo
tank/hold length, only local loads are directly applied to the
structural model, as specified in [4.3.2]. In this case, the
stresses calculated by the finite element program include
the contribution of local loads only. Hull girder stresses are
to be calculated separately and added to the stresses
induced by local loads.
6.1.2 Thickness
In order to carry out the critical stresses according to Ch 7,
Sec 1, [5.3], the net thickness of the buckling panel is to be
obtained by deducting tC from the gross thickness.
1 Where the thickness is not constant across a buckling panel
X, Y, Z : defined by a number of finite plate elements, an equivalent
Y reference co-ordinate system average thickness is calculated according to the following
formula:
n
A t i i
VM =
2
1 + 3 12
2 Ai A i
i i
The values of the stresses are to be used for carrying out the 6.2.2 The edge stress ratio for the stresses (x , y) is equal
checks required. to 1.
Stiffeners
Primary
x
x
supporting
S
members
Co-ordinate system of
the buckling panel
Finite
element
Primary Primary
supporting supporting
members members
Ordinary Ordinary
x
x
a) stiffeners stiffeners
Primary
supporting
members
Ordinary
b) stiffeners
Type a) : Compression according to Ch 7, Sec 1, [5.4.2]
Type b) : Shear according to Ch 7, Sec 1, [5.4.3]
Primary Primary
supporting supporting
members members
Ordinary Ordinary
x
c) stiffeners stiffeners
y
y
Primary
supporting
members
Ordinary
x
d) stiffeners
7.2.2 Finite element modelling criteria 7.2.4 Calculation of the elementary hot spot stress
The finite element model is to be built according to the fol- range
lowing requirements: The elementary hot spot stress range is to be obtained, in
the detail may be considered as being realised with no N/mm2, from the following formula:
misalignment S ,ij = S ,ij ,max S ,ij ,min
the size of finite elements located in the vicinity of the where:
hot spot is to be about once to twice the thickness of the
S,ij,max , S,ij,min: Maximum and minimum values of the hot
structural member. Where the details is the connection
between two or more members of different thickness, spot stress, induced by the maximum and mini-
the thickness to be considered is that of the thinnest mum loads, defined in Ch 7, Sec 4, [2.2] and
member Ch 7, Sec 4, [2.3]
the centre of the first element adjacent to a weld toe is i : Denotes the load case
to be located between the weld toe and 0,4 times the j : Denotes the loading condition.
thickness of the thinnest structural member connected
by the weld 7.3 Hot spot stresses obtained through the
plating, webs and face plates of primary and secondary calculation of nominal stresses
members are to be modelled by 4-node thin shell or 8-
node solid elements. In the case of a steep stress gradi- 7.3.1 Finite element model
ent, 8-node thin shell elements or 20-node solid ele- A finite element is to be adopted, to be built according to
ments are recommended the requirements in [3.3] and [3.4]. The areas in the vicinity
when thin shell elements are used, the structure is to be of the structural details are to be modelled with standard
modelled at mid-face of the plates mesh models, as defined in [3.4.3].
the aspect ratio of elements is to be not greater than 2. 7.3.2 Calculation of the elementary nominal stress
range
7.2.3 Calculation of hot spot stresses
The elementary nominal stress range is to be obtained, in
When the detail is located at a structural discontinuity N/mm2, from the following formula:
where a large stress gradient is expected the hot spot
stresses are normally obtained by linear extrapolation. The n ,ij = n ,ij ,max n ,ij ,min
stress components must be evaluated at a distance of 0,5 where:
and 1,5 times the thickness of the plating from the weld toe n,ij,max, n,ij,min: Maximum and minimum values of the nom-
and linearly extrapolated to the weld toe. The two evalua-
inal stress, induced by the maximum and mini-
tion points must be located in two different finite elements.
mum loads, defined in Ch 7, Sec 4, [2.2] and
In other cases or when extrapolation can not be used the Ch 7, Sec 4, [2.3]
hot spot stresses are to be calculated at the centroid of the i : Denotes the load case
first element adjacent to the hot spot. The size of this ele-
j : Denotes the loading condition.
ment has to be determined according to the requirements in
[7.2.2]. 7.3.3 Calculation of the elementary hot spot stress
Where the detail is the free edge of an opening (e.g. a cut- range
out for the passage of an ordinary stiffener through a pri- The elementary hot spot stress range is to be obtained, in
mary supporting member), the hot spot stresses have to be N/mm2, from the following formula:
calculated at the free edge. The stresses can be obtained by S,ij = KS n,ij
linear extrapolation or using fictitious truss elements with
minimal stiffness fitted along the edge. where:
The stress components to be considered are those specified KS : Stress concentration factor, defined in Ch 11,
in Ch 7, Sec 4, [4.1.2]. They are to be calculated at the sur- Sec 2, [2], for the relevant detail configuration
face of the plate in order to take into account the plate n,ij : Elementary nominal stress range, defined in
bending moment, where relevant. [7.3.2].
2.2 Beam model analyses 3.3.2 Boundary conditions at the fore and aft ends
of the model
2.2.1 For ships less than 200 m in length, beam models, Symmetry conditions are to be applied at the fore and aft
built according to Ch 7, App 1, [3.5], may be adopted in ends of the model, as specified in Tab 1.
lieu of the finite element models in [2.1], provided that:
primary supporting members are not so stout that the Table 1 : Symmetry conditions
beam theory is deemed inapplicable by the Society at the model fore and aft ends
their behaviour is not substantially influenced by the DISPLACEMENTS ROTATION
transmission of shear stresses through the shell plating. in directions (1): around axes (1):
2.2.2 In any case, finite element models may need to be X Y Z X Y Z
adopted when deemed necessary by the Society on the fixed free free free fixed fixed
basis of the ships structural arrangement.
(1) X, Y and Z directions and axes are defined with respect
to the reference co-ordinate system in Ch 1, Sec 2, [4].
3 Primary supporting members
structural modelling 3.3.3 Additional boundary conditions at the fore and
aft ends of models subjected to transverse
loads
3.1 Model construction
When the model is subjected to transverse loads, i.e. when
3.1.1 Elements the loads in inclined ship conditions (as defined in Ch 5,
Sec 4) are applied to the model, the transverse displace-
The structural model is to represent the primary supporting
ments of the deck beams are to be obtained by means of a
members with the plating to which they are connected. In
racking analysis and applied at the fore and aft ends of the
particular, the following primary supporting members are to
model, in way of each deck beam.
be included in the model:
deck beams For ships with a traditional arrangement of fore and aft
parts, a simplified approximation may be adopted, when
side primary supporting members deemed acceptable by the Society, defining the boundary
primary supporting members of longitudinal and trans- conditions without taking into account the racking calcula-
verse bulkheads, if any tion and introducing springs, acting in the transverse direc-
pillars tion, at the fore and aft ends of the model, in way of each
deck beam (see Fig 1). Each spring, which simulates the
deck beams, deck girders and pillars supporting ramps
effects of the deck in way of which it is modelled, has a stiff-
and deck openings, if any.
ness obtained, in kN/m, from the following formula:
3.1.2 Net scantlings 24EJ D s a 10
3
All the elements in [3.1.1] are to be modelled with their net R D = -----------------------------------------------------------------------------------------------
JD
2x 4L D x + L D x + 15 ,6 ------
4 3 2 2 3
scantlings according to Ch 4, Sec 2, [1]. + LD x
A D
where:
3.2 Model extension
JD : Net moment of inertia, in m4, of the average
3.2.1 The structural model is to represent a hull portion cross-section of the deck, with the attached side
which includes the zone under examination and which is shell plating
repeated along the hull. The non-modelled hull parts are to
be considered through boundary conditions as specified in Figure 1 : Springs at the fore and aft ends
[3.3]. of models subjected to transverse loads
In addition, the longitudinal extension of the structural
model is to be such that the results in the areas to be ana- RDN
lysed are not influenced by the unavoidable inaccuracy in
the modelling of the boundary conditions.
AD : Net area, in m2, of the average cross-section of Wave induced loads include:
deck plating the wave pressure, defined in Ch 5, Sec 5, [2] for load
sa : Spacing of side vertical primary supporting cases b and d
members, in m the inertial forces defined in Ch 5, Sec 6, Tab 9 for load
x : Longitudinal distance, in m, measured from the cases b and d.
transverse section at mid-length of the model to
any deck end When the ships decks are also designed to carry dry uni-
LD : Length of the deck, in m, to be taken equal to form cargoes, local loads also include the still water and
inertial pressures defined in Ch 5, Sec 6, [4]. Inertial pres-
the ships length. Special cases in which such
sures are to be calculated for load cases b and d.
value may be reduced will be considered by the
Society on a case by case basis. 4.2.2 Tyred vehicles
For the purpose of primary supporting members analyses,
4 Load model the forces transmitted through the tyres may be considered
as concentrated loads in the tyre print centre.
4.1 General The forces acting on primary supporting members are to be
4.1.1 Hull girder and local loads determined taking into account the area of influence of
each member and the way ordinary stiffeners transfer the
Only local loads are to be directly applied to the structural
forces transmitted through the tyres.
model.
The stresses induced by hull girder loads are to be calcu- 4.2.3 Non-tyred vehicles
lated separately and added to the stresses induced by local The requirements in [4.2.2] also apply to tracked vehicles.
loads. In this case, the print to be considered is that below each
4.1.2 Loading conditions and load cases: wheeled wheel or wheelwork.
cargoes For vehicles on rails, the loads transmitted are to be applied
The still water and wave loads are to be calculated for the as concentrated loads.
most severe loading conditions as given in the loading man-
ual, with a view to maximising the stresses in primary sup- 4.2.4 Distributed loads
porting members. In the analyses carried out on the basis of beam models or
The loads transmitted by vehicles are to be applied taking membrane finite element models, the loads distributed per-
into account the most severe axle positions for the ship pendicularly to the plating panels are to be applied on the
structures. primary supporting members proportionally to their areas of
influence.
The wave local loads and hull girder loads are to be calcu-
lated in the mutually exclusive load cases b and d in
Ch 5, Sec 4. Load cases a and c may be disregarded for 4.3 Hull girder loads
the purposes of the structural analyses dealt with in this
Appendix. 4.3.1 The normal stresses induced by the hull girder loads
in Tab 2 are to be added to the stresses induced in the pri-
4.1.3 Loading conditions and load cases: dry mary supporting members by local loads.
uniform cargoes
When the ships decks are also designed to carry dry uni- Table 2 : Hull girder loads
form cargoes, the loading conditions which envisage the
transportation of such cargoes are also to be considered. Vertical bending Horizontal
The still water and wave loads induced by these cargoes are moments at the middle wave bending
Ship Load of the model
to be calculated for the most severe loading conditions, moment at the
condition case
with a view to maximising the stresses in primary support- Still middle of the
Wave model
ing members. water
The wave local loads and hull girder loads are to be calcu- Upright b MSW 0,625 FD MWV,S 0
lated in the mutually exclusive load cases b and d in Ch
Inclined d MSW 0,25 MWV 0,625 MWH
5, Sec 4. Load cases a and c may be disregarded for the
purposes of the structural analyses dealt with in this Appen- Note 1:
dix. MSW : Still water bending moment at the middle of the
model, for the loading condition considered
4.2 Local loads MWV,S : Sagging wave bending moments at the middle
of the model, defined in Ch 5, Sec 2
4.2.1 General MWV : Wave bending moment at the middle of the
Still water loads include: model, defined in Ch 5, Sec 2, having the same
the still water sea pressure, defined in Ch 5, Sec 5, [1] sign as MSW
the still water forces induced by wheeled cargoes, MWH : Horizontal wave bending moment at the middle
defined in Ch 5, Sec 6, Tab 9. of the model, defined in Ch 5, Sec 2.
5 Stress calculation the normal stress 1 in the direction of the beam axis
the shear stress 12 in the direction of the local loads
5.1 Stresses induced by local and hull applied to the beam
girder loads the Von Mises equivalent stress, obtained from the fol-
lowing formula:
5.1.1 Only local loads are directly applied to the structural
2 2
model, as specified in [4.1.1]. Therefore, the stresses calcu- VM = 1 + 3 12
lated by the program include the contribution of local loads
only. Hull girder stresses are to be calculated separately and 5.3.2 Stress calculation points
added to the stresses induced by local loads. Stresses are to be calculated at least in the following points
of each primary supporting member:
5.2 Analyses based on finite element models in the primary supporting member span where the max-
imum bending moment occurs
5.2.1 Stress components
at the connection of the primary supporting member
Stress components are generally identified with respect to with other structures, assuming as resistant section that
the element co-ordinate system, as shown, by way of exam- formed by the member, the bracket (if any and if repre-
ple, in Fig 2. The orientation of the element co-ordinate sys- sented in the model) and the attached plating
tem may or may not coincide with that of the reference co-
ordinate system in Ch 1, Sec 2, [4]. at the toe of the bracket (if any and if represented in the
model) assuming as resistant section that formed by the
member and the attached plating.
Figure 2 : Reference and element co-ordinate systems
The values of the stresses calculated in the above points are
Z to be used for carrying out the checks required.
2
X
the Von Mises equivalent stress, obtained from the fol- The structural model used to represent the deck primary
lowing formula: supporting members is a beam grillage model.
VM =
2 2
1 + 2 1 2 + 3 12
2 6.2.2 Model extension
The structural model is to represent a hull portion which
5.2.2 Stress calculation points includes the zone under examination and which is repeated
along the hull. The non-modelled hull parts are to be con-
Stresses are generally calculated by the computer programs sidered through boundary conditions as specified in [3.3].
for each element. The values of these stresses are to be used
for carrying out the checks required.
6.3 Boundary conditions
5.3 Analyses based on beam models 6.3.1 Boundary conditions at the fore and aft ends
of the model
5.3.1 Stress components
Symmetry conditions are to be applied at the fore and aft
The following stress components are to be calculated: ends of the model, as specified in Tab 1.
The contribution of flexural stiffness supplied by the side 6.5 Stress calculation
primary supporting members to the deck beams is to be
simulated by springs, applied at their connections, having 6.5.1 Stress components are to be calculated according to
rotational stiffness, in the plane of the deck beam webs, [5.1] and [5.3].
obtained, in kN.m/rad, from the following formulae:
Figure 3 : Heights of tweendecks for grillage analysis
for intermediate decks: of deck primary supporting members
3E ( J 1 + J 2 ) ( 1 + 2 ) 5
R F = ----------------------------------------------
2 2
- 10
1 + 2 1 2
6EJ 5
R F = -----------1 10
1 2
deck under examination
where:
Symbols
: Moulded displacement in seawater, in t All the elements in [2.1.1] are to be modelled with their net
scantlings according to Ch 4, Sec 2. Therefore, also the hull
B : Moulded breadth, in m girder stiffness and inertia to be reproduced by the model
are those obtained by considering the net scantlings of the
L : Rule length, in m hull structures.
TR : Roll period, in s, defined in Ch 5, Sec 3, [2.4.1]
1.1.2 This Appendix deals with that part of the structural 2.3 Finite element modelling criteria
analysis which aims at calculating the stresses in the pri-
mary supporting members and also in the hull plating, to be 2.3.1 Modelling of primary supporting members
used for yielding and buckling checks. The analyses of primary supporting members are to be
based on standard mesh models, as defined in Ch 7, App 1,
1.1.3 The yielding and buckling checks of primary support- [3.4.3].
ing members are to be carried out according to Ch 7, Sec 3.
Such analyses may be carried out deriving the nodal dis-
placements or forces, to be used as boundary conditions,
2 Structural modelling from analyses of the complete ship based on coarse
meshes, as defined in Ch 7, App 1, [3.4.2].
2.1 Model construction The areas for which analyses based on standard mesh mod-
els are to be carried out are listed in Tab 1 for various types
of ships.
2.1.1 Elements
Other areas may be required to be analysed through stand-
The structural model is to represent the primary supporting
ard mesh models, where deemed necessary by the Society,
members with the plating to which they are connected. depending on the ships structural arrangement and loading
conditions as well as the results of the coarse mesh analysis.
Ordinary stiffeners are also to be represented in the model
in order to reproduce the stiffness and the inertia of the For ship with service notation container ship, Pt D, Ch 2,
actual hull girder structure. Sec 2, [8] is to be applied.
2.3.2 Modelling of the most highly stressed areas To this end, the structural model is to be built on the basis of
the following criteria:
The areas which appear from the analyses based on stand-
ard mesh models to be highly stressed may be required to ordinary stiffeners contributing to the hull girder longitu-
be further analysed, using the mesh accuracy specified in dinal strength and which are not individually repre-
Ch 7, App 1, [3.4.4]. sented in the model are to be modelled by rod elements
and grouped at regular intervals
Table 1 : Areas to be analysed
through standard mesh models webs of primary supporting members may be modelled
with only one element on their height
2.5.1 In order to prevent rigid body motions of the overall 3.1 General
model, the constraints specified in Tab 2 are to be applied.
3.1.1 Design wave method
2.5.2 When the hull structure is modelled over half the The various load components which occur simultaneously
may be combined by setting the characteristics of regular
ship's breadth (see [2.2.2]), in way of the ships centreline
waves that maximise the dominant load parameters given in
longitudinal plane, symmetry or anti-symmetry boundary Part B, Chapter 5.
conditions as specified in Tab 3 are to be applied, depend- Any other method may be used provided that relevant doc-
ing on the loads applied to the model (respectively symmet- umentation is submitted to the Society for review.
rical or anti-symmetrical). A recommended procedure to compute the characteristics
of the design wave is provided in [3.2].
Table 2 : Boundary conditions
to prevent rigid body motion of the model 3.1.2 Loads
Still water loads include:
Boundary conditions DISPLACEMENTS the still water sea pressure, defined in Ch 5, Sec 5, [1]
in directions (1) the still water internal loads, defined in Ch 5, Sec 6 for
X Y Z the various types of cargoes and for ballast.
One node on the fore end of the ship free fixed fixed Wave loads, determined by mean of hydrodynamic calcula-
tions according to [3.2], include:
One node on the port side shell at fixed free fixed
aft end of the ship (2) the wave pressure
One node on the starboard side shell free fixed fixed the inertial loads.
at aft end of the ship (2)
3.1.3 Lightweight
The lightweight of the ship is to be distributed over the
Boundary conditions ROTATION model length, in order to obtain the actual longitudinal dis-
around axes (1) tribution of the still water bending moment.
X Y Z 3.1.4 Models extended over half ships breadth
One node on the fore end of the ship free free free When the ship is symmetrical with respect to her centreline
One node on the port side shell at free free free longitudinal plane and the hull structure is modelled over
aft end of the ship (2) half the ship's breadth, non-symmetrical loads are to be
broken down into symmetrical and anti-symmetrical loads
One node on the starboard side shell free free free
and applied separately to the model with symmetry and
at aft end of the ship (2)
anti-symmetry boundary conditions in way of the ships
(1) X, Y and Z directions and axes are defined with respect centreline longitudinal plane (see [2.5.2]).
to the reference co-ordinate system in Ch 1, Sec 2, [4].
(2) The nodes on the port side shell and that on the star- 3.2 Procedure for the selection of design
board side shell are to be symmetrical with respect to
the ships longitudinal plane of symmetry.
waves
3.2.1 Summary of the loading procedure
Table 3 : Symmetry and anti-symmetry conditions Applicable cargo loading conditions given in Part D are
in way of the ships centreline longitudinal plane analysed through:
the computation of the characteristics of the finite ele-
Boundary DISPLACEMENTS in directions (1) ment model under still water loads (see [3.3.1])
conditions the selection of the load cases critical for the strength of
X Y Z
the resistant structural members (see [3.3.2]).
Symmetry free fixed free
The determination of the design wave characteristics for
Anti-symmetry fixed free fixed
each load case includes the following steps:
computation of the response operators (amplitude and
Boundary ROTATION around axes (1) phase) of the dominant load effect
conditions X Y Z selection of the wave length and heading according to
the guidelines in [3.3]
Symmetry fixed free fixed
determination of the wave phase such that the dominant
Anti-symmetry free fixed free load effect reaches its maximum
(1) X, Y and Z directions and axes are defined with respect computation of the wave amplitude corresponding to
to the reference co-ordinate system in Ch 1, Sec 2, [4]. the design value of the dominant load effect.
3.2.2 Dominant load effects The response amplitude operators are to be calculated for
wave headings ranging from following seas (0 degree) to
Each critical load case maximises the value of one of the
head seas (180 degrees) by increment of 15 degrees, using a
nine following load effects having a dominant influence on
ship speed of 60% of the maximum service speed.
the strength of some parts of the structure:
The amplitude and phase of other dominant load effects
vertical wave bending moment in hogging condition at
may be computed at relevant wave period, using the RAOs
midship section
listed above.
vertical wave bending moment in sagging condition at
midship section 3.2.4 Design waves
For each load case, the ship is considered to encounter a
vertical wave shear force on transverse bulkheads
regular wave, defined by its parameters:
horizontal wave bending moment at midship section wave length or period T
wave torque within cargo area of ships with large deck heading angle (see Fig 1)
openings
wave height (double amplitude)
vertical acceleration in midship and fore body sections
wave phase (see Fig 1).
transverse acceleration at deck at sides at midship sec-
tion The wave length and the wave period T are linked by the
following relation:
wave pressure at bottom at centreline in upright ship
condition, at midship section = g T2/ 2
The range of variation of design wave period is between T1
wave pressure at bottom at side in inclined ship condi-
and 22 seconds, where T1 is equal to:
tion, at midship section.
B
3.2.3 Response Amplitude Operators T1 = 2 -------
g
The Response Amplitude Operators (RAOs) and associated The possible wave height H, in m, is limited by the maxi-
phase characteristics are to be computed for wave periods mum wave steepness according to the relation (see Fig 2):
between 4 and 22 seconds, using a seakeeping program, for
the following motions and load effects: H = 0,02 g T2
heave, sway, pitch, roll and yaw motions Figure 2 : Allowable range of design waves
vertical wave bending moment at 0,50L or at the longi-
tudinal position where the bending moment RAO is
Wave height (m)
maximum
vertical wave shear force at 0,25L and 0,50L
40
horizontal wave bending moment at 0,50L
gT 2
= 0 = 180
F X 3.2.5 Design wave amplitude
CR
ES
T
The amplitude of the design wave is obtained by dividing
the design value of the dominant load effect by the value of
Phase angle (degrees) = c . 360 the response amplitude operator of this effect computed for
F : center of rotation the relevant heading and wave length.
The design values of load effect, heading and wave length
are given for each load case in [3.3.2].
When positioning the finite element model of the ship on deformed wave profile and varies linearly between the
the design wave, the amplitude of the wave is to be cor- mean waterline and the wave crest levels.
rected to obtain the design value of the dominant load
b) The fluid pressure in tanks is affected by the change of
effect in order to take into account the non linear effects
direction of the total acceleration vector defined in Ch
due to the hull shape and to the pressure distribution above
5, Sec 6, [1.1.3].
the mean water line given in [3.2.7].
c) For dry unit cargoes, the inertial forces are computed at
The design wave phase is the phase of the dominant load
the centre of mass, taking into account the mass
effect.
moment of inertia.
3.2.6 Combined load cases d) Inertial loads for structure weight and dry uniform cargo
are computed using local accelerations calculated at
For the wave characteristics and crest position selected their location.
according to [3.2.5], the value of the wave-induced
motions, accelerations and other load effects is obtained by 3.2.8 Equilibrium check
the following formula:
The finite element model is to be in equilibrium condition
Ei = RAOi a cos(d i) with all the still water and wave loads applied.
where: The unbalanced forces in the three axes are not to exceed
Ei : Value of amplitude of the load component i 2% of the displacement.
RAOi : Response amplitude operator of the load com- The unbalanced moments are not to exceed 2% of .B
ponent i computed for the design heading and around y and z axes and 0,2% of .B around x axis.
wave length
As a rule, the amplitude of the load components computed For each cargo loading condition given in the relevant
chapter of Part E, the longitudinal distribution of still water
above are not to exceed their rule reference value by a fac-
shear force and bending moment is to be computed and
tor Cmax given in Tab 4.
checked by reference to the approved loading manual (see
Ch 10, Sec 2).
Table 4 : Values of factor Cmax
The convergence of the displacement, trim and vertical
Load component Cmax bending moment is deemed satisfactory if within the follow-
ing tolerances:
Wave bending moments and wave torque
1,10
(see Ch 5, Sec 2, [3]) 2% of the displacement
Wave shear forces 0,1 degrees of the trim angle
1,40
(see Ch 5, Sec 2, [3])
10% of the still water bending moment.
Roll angle, vertical and horizontal accelerations
1,10
(see Ch 5, Sec 3, [2])
3.3.2 Value of load effects
Wave pressure
1,20
(see Ch 7, App 1, [4.2.2])
The wave length and heading which maximise each domi-
nant load effect are specified in Tab 5. Where two values of
3.2.7 Finite element model loading heading angle are indicated in the table, the angle which
corresponds to the highest peak value of the load effects
The loads are applied to the finite element model according RAO is to be considered. The wave length and heading may
to the following indications: have to be adjusted in order to fulfil the requirements given
in [3.3.2].
a) For fatigue analysis of structural members located in the
vicinity of the mean waterline, the sum of the wave and The design value of dominant load effects is specified in Tab
hydrostatic parts of the pressure is zero above the 6.
where:
C = 1,0 for 90 heading
1,15 for 105 heading
CW : Waterplane coefficient at
load waterline
9 Vertical acceleration in = 1,6 L (0,575 + 0,8 F)2 180 From forward end
upright ship condition of cargo area to F.P.
10 Transverse acceleration = 1,35 g TR2 / (2) 90 Midship section
without being taken greater than
756 m
11 Wave pressure at bot- 0,7 L 180 or Midship section may have to be increased
tom at centreline in 0 to keep the wave steepness
upright ship condition below wave breaking limit
12 Wave pressure at bot- = 0,35 g TR2 / (2) 90 Midship section
tom at side in inclined without being taken less than
ship condition 2,0B
(1) The forward ship speed is to be taken equal to 0,6 V.
Combined load
Dominant load effect Design value References
components
Vertical wave bending moment in hog-
0,625 W1 MWV ,H MWV,H defined in Ch 5, Sec 2, [3.1.1]
ging condition
Vertical wave bending moment in sag- MWV,S defined in Ch 5, Sec 2, [3.1.1]
0,625 W1 FD MWV ,S
ging condition FD defined in Ch 5, Sec 2, [4.2.1]
Vertical wave shear force 0,625 W1 QWV QWV defined in Ch 5, Sec 2, [3.4]
Horizontal wave bending moment 0,625 W1 MWH MWH defined in Ch 5, Sec 2, [3.2.1]
Horizontal wave bending
Wave torque (1) 0,625 W1 MWT MT defined in Ch 5, Sec 2, [3.3]
moment
Vertical acceleration at centreline in Vertical relative motion at
W2 aZ1 aZ1 defined in Ch 5, Sec 3, [3.4.1]
upright ship condition sides at F.E.
Vertical acceleration at deck at sides in
W2 aZ2 aZ2 defined in Ch 5, Sec 3, [3.4.1]
inclined ship condition
Transverse acceleration at deck at sides W2 aY2 Roll angle aY2 defined in Ch 5, Sec 3, [3.4.1]
Wave pressure at bottom at centreline Vertical wave bending pW defined in Ch 7, App 1, Tab 3 for
W2 pW
in upright ship condition moment at midship case a
Wave pressure at bottom at side in pW defined in Ch 7, App 1, Tab 4 for
W2 pW
inclined ship condition case c
(1) This load effect is to be considered for ships with large deck openings only.
4 Stress calculation
Figure 3 : Reference and element co-ordinate systems
4.1 Stress components
Z 2
4.1.1 Stress components are generally identified with X
respect to the element co-ordinate system, as shown, by
way of example, in Fig 3. The orientation of the element co-
ordinate system may or may not coincide with that of the
reference co-ordinate system in Ch 1, Sec 2, [4].
Element
The following stress components are to be calculated at the
centroid of each element:
the normal stresses 1 and 2 in the directions of ele-
ment co-ordinate system axes
the shear stress 12 with respect to the element co-ordi-
nate system axes 1
X, Y, Z :
the Von Mises equivalent stress, obtained from the fol- reference co-ordinate system
Y
lowing formula:
2 2 2
VM = 1 + 2 1 2 + 3 12
Part B
Hull and Stability
Chapters 1 2 3 4 5 6 7 8 9 10 11
Chapter 1 GENERAL
Chapter 2 GENERAL ARRANGEMENT DESIGN
Chapter 3 STABILITY
Chapter 4 STRUCTURE DESIGN PRINCIPLES
Chapter 5 DESIGN LOADS
Chapter 6 HULL GIRDER STRENGTH
Chapter 7 HULL SCANTLINGS
Chapter 8 OTHER STRUCTURES
Chapter 9 HULL OUTFITTING
Chapter 10 CORROSION PROTECTION AND LOADING INFORMATION
Chapter 11 CONSTRUCTION AND TESTING
1 General 79
1.1 Definition
1.2 Application
1.3 Materials
2 Small hatches fitted on exposed decks 79
2.1 General
2.2 Gaskets
1 General 85
1.1 Application
1.2 Definitions
2 External openings 85
2.1 General
3 Sidescuttles, windows and skylights 85
3.1 General
3.2 Opening arrangement
3.3 Glasses
3.4 Deadlight arrangement
4 Discharges 88
4.1 Arrangement of discharges
4.2 Arrangement of garbage chutes
4.3 Scantlings of garbage chutes
5 Transducers 89
5.1 General
5.2 Protection of transducers in ballast and main compartment
5.3 Fitting of hull boss and transducer receiver
5.4 Fitting of transducer in heavily stressed areas
Section 1 Rudders
1 General 103
1.1 Application
1.2 Gross scantlings
1.3 Arrangements
1.4 Materials
2 Force and torque acting on the rudder 104
2.1 Rudder blade without cut-outs
2.2 Rudder blade with cut-outs (semi-spade rudders
3 Rudder types and relevant loads acting on the rudder structure 106
3.1 General
4 Rudder stock scantlings 106
4.1 Rudder stock diameter
4.2 Deformation criterion
4.3 Service notations - Navigation in ice
5 Rudder stock couplings 109
5.1 Horizontal flange couplings
5.2 Couplings between rudder stocks and tillers
5.3 Cone couplings between rudder stocks and rudder blades
5.4 Vertical flange couplings
5.5 Couplings by continuous rudder stock welded to the rudder blade
5.6 Rudder trunks
6 Rudder stock and pintle bearings 114
6.1 Forces on rudder stock and pintle bearings
6.2 Rudder stock bearing
6.3 Pintle bearings
6.4 Pintles
7 Rudder blade scantlings 115
7.1 General
7.2 Strength checks
7.3 Rudder blade plating
7.4 Connections of rudder blade structure with solid parts in forged or cast steel
7.5 Connection of the rudder blade with the rudder stock by means of horizontal
flanges
7.6 Single plate rudders
8 Rudder horn and solepiece scantlings 119
8.1 General
8.2 Rudder horn
8.3 Solepieces
9 Simplex rudder shaft 120
9.1 Scantlings
9.2 Connections
Section 4 Equipment
1 General 130
1.1 General
2 Equipment number 130
2.1 Equipment number
3 Anchoring equipment 133
3.1 Anchors
3.2 Chain cables for bower anchors
3.3 Attachment pieces
3.4 Hawse pipes
3.5 Windlass
Section 3 Testing
1 Testing procedures of watertight compartments 195
1.1 Application
1.2 General
1.3 Definitions
1.4 Structural test procedures
1.5 Leak test procedures
1.6 Test methods
1.7 Application of coating
1.8 Safe access to joints
1.9 Hydrostatic or hydropneumatic tightness test
2 Miscellaneous 200
2.1 Watertight decks, trunks, etc.
2.2 Steering nozzles
Chapter 8
OTHER STRUCTURES
Symbols
pS, pW : Still water pressure and wave pressure defined In addition, it includes:
in [2.3] reinforcements of the flat bottom forward area
pBI : Bottom impact pressure, defined in [3.2] reinforcements of the bow flare area.
pFI : Bow impact pressure, defined in [4.2]
1.1.2 Fore peak structures which form vertical watertight
s : Spacing, in m, of ordinary stiffeners or primary boundary between two compartments not intended to carry
supporting members, as applicable liquids, and which do not belong to the outer shell, are to
: Span, in m, of ordinary stiffeners or primary be subjected to lateral pressure in flooding conditions. Their
supporting members, as applicable scantlings are to be determined according to the relevant
criteria in Part B, Chapter 7.
ca : Aspect ratio of the plate panel, equal to:
2.1.2 The partial safety factors to be considered for testing If the compartment adjacent to the outer shell is not
of fore peak structures are specified in Tab 2. intended to carry liquids, only the external sea pressures are
to be considered.
Table 2 : Fore peak structures
Partial safety factors for testing 2.3.3 Lateral pressures for elements other than
those of the outer shell
Partial safety factors Partial safety factors
The still water and wave lateral pressures to be considered
covering uncertainties Ordinary
Symbols Plating as acting on an element which separates two adjacent com-
regarding: stiffeners partments are those obtained considering the two compart-
Still water pressure S2 1,00 1,00 ments individually loaded.
Wave induced pressure W2 N.A. N.A.
Table 3 : Still water and wave pressures
Material m 1,02 1,02
Resistance R 1,05 1,20
Still water sea
Wave pressure pW,
Location pressure pS,
in kN/m2
2.2 Load point in kN/m2
Bottom and side 2 ( T z )
---------------------------
2.2.1 Unless otherwise specified, lateral pressure is to be below the g (T z) gh 1 e
L
the lower edge of the elementary plate panel consid- Side above the g (T + h1 z)
ered, for plating waterline: 0 without being taken
z>T less than 0,15 L
mid-span, for stiffeners.
Exposed deck Pressure due to the
19 ,6n 1 2 H
load carried (1)
2.3 Load model (1) The pressure due to the load carried is to be defined by
the Designer and, in any case, it may not be taken less
2.3.1 General than 10 1 2 kN/m2, where 1 and 2 are defined here-
after.
The still water and wave lateral pressures in intact condi-
The Society may accept pressure values lower than
tions are to be considered. They are to be calculated as
10 1 2 kN/m2 when considered appropriate on the
specified in [2.3.2] for the elements of the outer shell and in
basis of the intended use of the deck.
[2.3.3] for the other elements.
Note 1:
Still water pressure (pS) includes: 1 : Coefficient defined in Tab 4
2 : Coefficient taken equal to:
the still water sea pressure, defined in Tab 3 2 = 1 if L 120 m
the still water internal pressure due to liquids or ballast, 2 = L/120 if L < 120 m
defined in Tab 5 2
H = 2 ,66 --- 0 ,7 + 0 ,14
x VL
------- ( z T )
L CB
the still water internal pressure due to dry uniform car-
goes on deck, defined in Tab 6. without being taken less than 0,8
V : Maximum ahead service speed, in knots, to be
Wave pressure (pW) includes: taken not less than 13 knots.
the wave pressure, defined in Tab 3
Table 4 : Coefficient for pressure on exposed decks
the inertial internal pressure due to liquids or ballast,
defined in Tab 5
Exposed deck location 1
the inertial internal pressure due to dry uniform cargoes
on deck, defined in Tab 6. Freeboard deck 1,00
Top of lowest tier 0,75
2.3.2 Lateral pressures for the elements of the outer Top of second tier 0,56
shell
Top of third tier 0,42
The still water and wave lateral pressures are to be calcu-
Top of fourth tier 0,32
lated considering separately:
Top of fifth tier 0,25
the still water and wave external sea pressures
Top of sixth tier 0,20
the still water and wave internal pressures, considering
Top of seventh tier 0,15
the compartment adjacent to the outer shell as being
loaded. Top of eighth tier and above 0,10
Table 5 : Still water and inertial internal pressures pS : Still water sea pressure defined in Tab 3 and cal-
due to liquids culated for the draught T1 at which the testing is
carried out.
Still water pressure pS Inertial pressure pW
If the draught T1 is not defined by the Designer,
in kN/m2 in kN/m2
it may be taken equal to the light ballast draught
L g (zL z) L aZ1 (zTOP z) TB defined in Ch 5, Sec 1, [2.4.3].
Note 1:
zTOP : Z co-ordinate, in m, of the highest point of the tank 2.4 Longitudinally framed bottom
zL : Z co-ordinate, in m, of the highest point of the
liquid: 2.4.1 Plating and ordinary stiffeners
zL = zTOP + 0,5 (zAP zTOP) The net scantlings of plating and ordinary stiffeners are to
zAP : Z co-ordinate, in m, of the moulded deck line of be not less than the values obtained from the formulae in
the deck to which the air pipes extend, to be Tab 7 and the minimum values in the same Table.
taken not less than zTOP.
2.4.2 Floors
Table 6 : Still water and inertial internal pressures Floors are to be fitted at every four frame spacing and gener-
due to dry uniform cargoes ally spaced no more than 2,5 m apart.
Inertial pressure The floor dimensions and scantlings are to be not less than
Still water pressure pS, in kN/m2 those specified in Tab 8.
pW, in kN/m2
The value of pS is, in general, defined by a Z1 In no case may the above scantlings be lower than those of
the Designer; in any case it may not be p S ------
- the corresponding side transverses, as defined in [2.6.2].
g
taken less than 10 kN/m2.
When the value of pS is not defined by 2.4.3 Centre girder
the Designer, it may be taken, in kN/m, Where no centreline bulkhead is fitted (see [2.10]), a centre
equal to 6,9 hTD, where hTD is the com- bottom girder having the same dimensions and scantlings
partment tweendeck height at side, in m. required in [2.4.2] for floors is to be provided.
The centre bottom girder is to be connected to the collision
2.3.4 Lateral pressure in testing conditions
bulkhead by means of a large end bracket.
The lateral pressure in testing conditions, pT , in kN/m2, is
taken equal to: 2.4.4 Side girders
pST pS for bottom shell plating and side shell plating Side girders, having the same dimensions and scantlings
pST otherwise required in [2.4.2] for floors, are generally to be fitted every
two longitudinals, in line with bottom longitudinals located
where: aft of the collision bulkhead. Their extension is to be com-
pST : Still water pressure defined in Ch 5, Sec 6, Tab 14 patible in each case with the shape of the bottom.
Net shear sectional area, in cm2: the net thickness of the attached plating.
S2 p S + W2 p W
1 ------ s
s
A Sh = 10 R m s -----------------------------------
Ry 2
Their net section modulus w, in cm3, and net shear sec- 2.7.8 Non-tight platforms
tional area ASh, in cm2, are to be not less than the values Non-tight platforms may be fitted in lieu of side girders and
obtained from the following formulae: panting beams. Their openings and scantlings are to be in
S2 p S + W2 p W 2 3 accordance with [2.9.1].
w = R m b ---------------------------------- s 10
8R y Their spacing is to be not greater than 2,5 m.
S2 p S + W2 p W If the peak exceeds 10 m in depth, a non-tight platform is to
A Sh = 10 R m s ---------------------------------- s
Ry be arranged at approximately mid-depth.
Moreover, the depth bA, in mm, and the net thickness tA, in
2.7.9 Additional transverse bulkheads
mm, of the side girder web are generally to be not less than
the values obtained from the following formulae: Where the peak exceeds 10 m in length and the frames are
supported by panting beams or non-tight platforms, additional
bA = 2,5 (180 + L) transverse wash bulkheads or side transverses are to be fitted.
tA = (6 + 0,018 L) k1/2
2.8 Decks
2.7.3 Panting structures
2.8.1 Plating and ordinary stiffeners
In order to withstand the panting loads, horizontal structures
are to be provided. These structures are to be fitted at a spac- The net scantlings of plating and ordinary stiffeners are to
ing generally not exceeding 2 m and consist of side girders be not less than the values obtained from the formulae in
supported by panting beams or side transverses whose ends Tab 11 and the minimum values in the same Table.
are connected to deck transverses, located under the tank
2.8.2 Primary supporting members
top, so as to form a strengthened ring structure.
Scantlings of primary supporting members are to be in
Panting beams, which generally consist of sections having accordance with Ch 7, Sec 3, considering the loads in [2.3].
the greater side vertically arranged, are to be fitted every
two frames.
2.9 Platforms
2.7.4 Connection between panting beams, side
2.9.1 Non-tight platforms
frames and side girders
Non-tight platforms located inside the peak are to be pro-
Each panting beam is to be connected to the side frames by
vided with openings having a total area not less than 10%
means of brackets whose arms are generally to be not less
of that of the platforms. Moreover, the thickness of the plat-
than twice the panting beam depth.
ing and the section modulus of ordinary stiffeners are to be
not less than those required in [2.10] for the non-tight cen-
2.7.5 Connection between side frames and side
tral longitudinal bulkhead.
girders
Side frames not supporting panting beams are to be con- The number and depth of non-tight platforms within the
nected to side girders by means of brackets having the same peak is considered by the Society on a case by case basis.
thickness as that of the side girder and arms which are to be The platforms may be replaced by equivalent horizontal
not less than one half of the depth of the side girder. structures whose scantlings are to be supported by direct
calculations.
2.7.6 Panting beam scantlings
2.9.2 Platform transverses
The net area AB , in cm2, and the net inertia JB , in cm4, of the
panting beam section are to be not less than the values The net sectional area of platform transverses, calculated
obtained from the following formulae: considering a width of attached plating whose net sectional
area is equal to that of the transverse flange, is to be not less
AB = 0,5 L 18 than the value obtained, in cm2, from the following formula:
JB = 0,34 (0,5 L 18) bB2 S2 p S + W2 p W
A = 10 R m ---------------------------------- dS hS
where: CP Ry
hS : Half of the vertical distance, in m, between the 2.10 Central longitudinal bulkhead
two transverses vertically adjacent to that under
consideration 2.10.1 General
Except for dry peaks, a centreline longitudinal wash bulk-
CP : Coefficient, to be taken equal to: head may be required in liquid compartments for which
there is a risk of resonance in the transverse direction.
dP
CP = 1 for ----- 70
rP 2.10.2 Extension
d d In the case of a bulbous bow, such bulkhead is generally to
C P = 1 ,7 0 ,01 -----P for 70 < -----P 140 extend for the whole length and depth of the fore peak.
rP rP
Where hull structures are flared, such as those situated
When dP / rP > 140, the scantlings of the struts are above the bulb and in the fore part of the peak, the bulk-
considered by the Society on a case by case basis head may be locally omitted.
dP : Distance, in cm, from the face plate of the side Similarly, the extension of the bulkhead may be limited for
bows without a bulb, depending on the shape of the hull.
transverse and that of the bulkhead vertical
However, the bulkhead is to be fitted in the higher part of
web, connected by the strut, measured at the
the peak.
level of the platform transverse
2.10.3 Plating thickness
rP : Radius of gyration of the strut, to be obtained, in
The net plating thickness of the lower part of the longitudi-
cm, from the following formula: nal bulkhead over a height at least equal to hM defined in
[2.4.2] is to be not less than that required for the centre
J
rP = ----- girder in [2.4.3].
AE
Elsewhere, the net thickness of the longitudinal bulkhead
J : Minimum net moment of inertia, in cm , of the 4 plating is to be not less than the value obtained, in mm,
strut considered from the following formula:
t = 6,5 + 0,013 L1
AE : Actual net sectional area, in cm2, of the trans-
verse section of the strut considered. 2.10.4 Ordinary stiffeners
The net section modulus of ordinary stiffeners is to be not less
2.9.3 Breasthooks than the value obtained, in cm3, from the following formula:
w = 3,5 s 2 k (zTOP zM)
Breasthooks are to have the same thickness of that required
for platforms. They are to be arranged on the stem, in way where:
of every side longitudinal, or at equivalent spacing in the zTOP : Z co-ordinate, in m, of the highest point of the
case of transverse framing, extending aft for a length equal tank
to approximately twice the breasthook spacing. zM : Z co-ordinate, in m, of the stiffener mid-span.
2.11.2 Shell plating without being taken less than 0,2 or greater than 0,25
transversely, over the whole flat bottom and the adja-
The thickness of the shell plating of the fore end of the bulb
cent zones up to a height, from the base line, not less
and the first strake above the keel is generally to be not less
than 2L, in mm. In any case, it is not necessary that such
than that required in [5.2.1] for plate stems. This thickness is
height is greater than 300 mm.
to be extended to the bulbous zone, which, depending on
its shape, may be damaged by anchors and chains during Note 1: The requirements of this article [3] are not applicable to
handling. ships having the navigation notation sheltered area.
Note 2: For ships having the navigation notation coastal area, a
2.11.3 Connection with the fore peak reduction of 20% may be applied on the bottom impact pressure
on a case by case basis.
Fore peak structures are to be extended inside the bulb as
far as permitted by the size and shape of the latter. 3.1.2 The bottom dynamic impact pressure is to be consid-
ered if:
2.11.4 Horizontal diaphragms
TF < min (0,04L; 8,6 m)
At the fore end of the bulb, the structure is generally to be
supported by means of horizontal diaphragms, spaced not where TF is the minimum forward draught, in m, among
more than 1 m apart, and a centreline vertical diaphragm. those foreseen in operation in ballast conditions or condi-
tions of partial loading.
2.11.5 Longitudinal stiffeners
3.1.3 The value of the minimum forward draught TF
Bottom and side longitudinals are to extend inside the bulb, adopted for the calculations is to be specified in the loading
forward of the fore end by at least 30% of the bulb length manual.
measured from the perpendicular to the fore end of the
bulb. 3.1.4 An alternative arrangement and extension of strength-
ening with respect to the above may also be required where
The fore end of longitudinals is to be located in way of a
the minimum forward draught exceeds 0,04 L, depending
reinforced transverse ring; forward of such ring, longitudi-
on the shape of the forward hull body and the ships length
nals are to be replaced by ordinary transverse rings.
and service speed.
2.11.6 Floors
3.2 Bottom impact pressure
Solid floors are to be part of reinforced transverse rings gen-
erally arranged not more than 3 frame spaces apart. 3.2.1 The bottom impact pressure pBI is to be obtained, in
kN/m2, from the following formula:
2.11.7 Breasthooks
pBI = 62 C1 CSL L0,6 if L 135
Breasthooks, to be placed in line with longitudinals, are to
be extended on sides aft of the stem, so as to form longitudi- pBI = (1510 2,5 L) C1 CSL if L > 135
nal side girders. where:
C1 : Coefficient defined as follows: 3.4.2 Bottom longitudinals and side girders, if any, are to
general case: extend as far forward as practicable, and their spacing may
not exceed that adopted aft of the collision bulkhead.
T
119 2300 -----F
L 3.4.3 The spacing of solid floors in a single or double bot-
C 1 = -----------------------------------
TF tom is to be not greater than either that required for the mid-
78 + 1800 -----
L ship section in Ch 4, Sec 4 or (1,35 + 0,007 L) m, whichever
without being taken greater than 1,0 is the lesser.
for non-propelled units: However, where the minimum forward draught TF is less
than 0,02 L, the spacing of floors forward of 0,2 L from the
T
119 2300 -----F stem is to be not greater than (0,9 + 0,0045 L) m.
L
C 1 = ----------------------------------- + 0, 09
TF 3.4.4 The Society may require adequately spaced side gird-
156 + 3600 -----
L ers having a depth equal to that of the floors. As an alterna-
without being taken greater than 0,59 tive to the above, girders with increased scantlings may be
TF : Draught defined in [3.1.2] fitted.
CSL : Longitudinal distribution factor, taken equal to:
3.5 Arrangement of primary supporting
C SL = 0 for x x 1 members and ordinary stiffeners:
x x1 transversely framed double bottom
C SL = ---------------- for x 1 < x < x 2
x2 x1
C SL = 1 for x x 2
3.5.1 The requirements in [3.5.2] to [3.5.3] apply to the
structures of the flat bottom forward area, defined in [3.1],
in addition to the requirements of [2.5].
x 1 = 0 ,55 + ------------- L
L
2000
3.5.2 Solid floors are to be fitted:
at every second frame between 0,75L and 0,8L from the
x 2 = 0 ,35 + 0 ,5C B + ------------- L with 0 ,6 C B 0 ,85
L
3000 aft end
at every frame space forward of 0,8L from the aft end.
3.3 Scantlings 3.5.3 Side girders with a depth equal to that of the floors
are to be fitted at a spacing generally not exceeding 2,4 m.
3.3.1 Plating
In addition, the Society may require intermediate half
The net thickness t, in mm, of the hull envelope plating is to height girders, half the depth of the side girders, or other
be not less than the value obtained from the formula given equivalent stiffeners.
in Ch 7, Sec 1, [3.6.1].
B where:
L3 : Ships length L, in m, but to be taken not greater
Section A A than 300.
Above the load waterline this thickness may be gradually
tapered towards the stem head, where it is to be not less
4.3 Scantlings than that required for side plating at ends.
4.3.1 Plating 5.2.2 The expanded width of the stem is not to be less than
the rule breadth of the plate keel, defined in Ch 4, Sec 4,
The net thickness t, in mm, of the hull envelope plating is to
[1.3.1].
be not less than the value obtained from the formula given
in Ch 7, Sec 1, [3.6.1].
5.2.3 The plating forming the stems is to be supported by
horizontal diaphragms spaced not more than 1200 mm
4.3.2 Ordinary stiffeners
apart and connected, as far as practicable, to the adjacent
The net plastic section modulus Zpl , in cm3, as defined in frames and side stringers.
Ch 4, Sec 3, [3.4.3] and the net web thickness tw , in mm, of
longitudinal or transverse ordinary stiffeners are not to be 5.2.4 If considered necessary, and particularly where the
less than the values obtained from the formulae given in Ch stem radius is large, a centreline stiffener or web of suitable
7, Sec 2, [3.10.1]. scantlings is to be fitted.
5.3 Bar stems 5.3.4 The lower part of the stem may be constructed of cast
steel subject to the examination by the Society; where nec-
5.3.1 The gross area of bar stems constructed of forged or essary, a vertical web is to be fitted for welding of the centre
rolled steel is to be not less than the value obtained, in cm2, keelson.
from the following formulae:
5.3.5 Welding of the bar stem with the bar keel and the
A P = 0 ,40 + ---------- ( 0 ,009L 2 + 20 ) k for L 90
10T
L shell plating is to be in accordance with Ch 11, Sec 1, [3.5].
Symbols
pS, pW : Still water pressure and wave pressure defined 1.2 Connections of the aft part with structures
in [2.3] located fore of the after peak bulkhead
s : Spacing, in m, of ordinary stiffeners or primary
supporting members, as applicable 1.2.1 Tapering
: Span, in m, of ordinary stiffeners or primary Adequate tapering is to be ensured between the scantlings
supporting members, as applicable in the aft part and those fore of the after peak bulkhead. The
tapering is to be such that the scantling requirements for
ca : Aspect ratio of the plate panel, equal to:
both areas are fulfilled.
s 2
c a = 1 ,21 1 + 0 ,33 - 0 ,69 -
s
1.3 Net scantlings
to be taken not greater than 1,0
1.3.1 As specified in Ch 4, Sec 2, [1], all scantlings referred
cr : Coefficient of curvature of the panel, equal to:
to in this Section are net, i.e. they do not include any mar-
cr = 1 0,5 s / r gin for corrosion.
to be taken not less than 0,5 Gross scantlings are obtained as specified in Ch 4, Sec 2.
r : Radius of curvature, in m
b , s : Coefficients defined in Ch 7, Sec 2, [3.4.2] 2 Aft peak
b , s : Coefficients defined in Ch 7, Sec 2, [3.4.3]
cE : Coefficient to be taken equal to: 2.1 Partial safety factors
cE = 1 for L 65 m
2.1.1 The partial safety factors to be considered for check-
cE = 3 L/30 for 65 m < L < 90 m
ing aft peak structures are specified in Tab 1.
cE = 0 for L 90 m
cF : Coefficient: Table 1 : Aft peak structures - Partial safety factors
cF = 0,8 for poop sides
Partial safety Partial safety factors
cF = 1,0 in other cases factors covering Primary
uncertainties Ordinary
m : Boundary coefficient, to be taken equal to: Symbol Plating supporting
regarding: stiffeners
m = 12 in general, for stiffeners considered members
as clamped Still water S2 1,00 1,00 1,00
m = 8 for stiffeners considered as simply pressure
supported Wave pressure W2 1,20 1,20 1,20
other values of m may be considered, on a case Material m 1,02 1,02 1,02
by case basis, for other boundary conditions. Resistance R 1,20 1,40 1,60
the still water sea pressure, defined in Tab 3 Still water pressure pS, Inertial pressure pW,
the still water internal pressure due to liquids or ballast, in kN/m2 in kN/m2
defined in Tab 5 g (zL z) aZ1 (zTOP z)
the still water internal pressure due to dry uniform car- Note 1:
goes on deck, defined in Tab 6. zTOP : Z co-ordinate, in m, of the highest point of the
tank
Wave pressure (pW) includes: zL : Z co-ordinate, in m, of the highest point of the
liquid:
the wave pressure, defined in Tab 3 zL = zTOP + 0,5 (zAP zTOP)
the inertial internal pressure due to liquids or ballast, zAP : Z co-ordinate, in m, of the moulded deck line of
defined in Tab 5 the deck to which the air pipes extend, to be
taken not less than zTOP.
the inertial internal pressure due to dry uniform cargoes
on deck, defined in Tab 6.
Table 6 : Still water and inertial internal pressures
due to dry uniform cargoes
Table 3 : Still water and wave pressures
2.3.3 Lateral pressures for elements other than Floors are to be fitted with stiffeners having spacing not
those of the outer shell greater than 800 mm.
The still water and wave lateral pressures to be considered
as acting on an element which separates two adjacent com- 3.1.3 Side frames
partments are those obtained considering the two compart- Side frames are to be extended up to a deck located above
ments individually loaded. the full load waterline.
Side frames are to be supported by one of the following
2.3.4 Lateral pressure in testing conditions types of structure:
The lateral pressure in testing conditions, pT , in kN/m2, is non-tight platforms, to be fitted with openings having a
taken equal to: total area not less than 10% of the area of the platforms
pST pS for bottom shell plating and side shell plating side girders supported by side primary supporting mem-
pST otherwise bers connected to deck transverses.
The net section modulus w, in cm3, and the net shear sec- P SI = ------------ ---------------------------------
-
tan L
tional area ASh , in cm2, of side girders are to be not less than
the values obtained from the following formulae: where:
S2 p S + W2 p W 2 3 hSI = h1
w = R m b ---------------------------------- s 10
8R y h1 : Reference value of the relative motion in the
S2 p S + W2 p W upright ship condition, in m, defined in Ch 5,
A Sh = 10 R m s ---------------------------------- s
Ry Sec 3, Tab 5, and calculated with the reference
value, for x = 0,5 L, taken equal to:
3.2.5 Deck primary supporting members
h1,M = 0,67 n C (CB + 0,7), without being taken
Scantlings of deck primary supporting members are to be in
accordance with Ch 7, Sec 3, considering the loads in [2.3]. greater than the minimum of T1 and D 0,9 T
: Longitudinal or transverse deadrise angle at the
4 Reinforcements of the flat area of the calculation point, whichever is the greater, but
bottom aft not to be taken less than 10
T1 : Draugtht as defined in Part B, Chapter 5, Sym-
4.1 General bols.
4.1.1 Application
Requirements of this Article apply to ships with the service 4.3 Scantling
notations Container ship, Passenger ship or Liquefied gas
carrier, and having a length L at least equal to 170m. How- 4.3.1 Plating
ever, for ships with other service notations and shorter The net thickness t, in mm, of the hull envelope plating is to
length, the Society may require reinforcements of the flat aft be not less than the value obtained from the formula given
on a case by case basis. in Ch 7, Sec 1, [3.6.1].
4.3.2 Ordinary stiffeners The side transverses are to be fitted with end brackets and
The net plastic section modulus Zpl , in cm3, as defined in located within the poop. Where there is no poop, the scant-
Ch 4, Sec 3, [3.4.3] and the net web thickness tw , in mm, of lings of side transverses below the weather deck are to be
longitudinal or transverse ordinary stiffeners are not to be adequately increased with respect to those obtained from
less than the values obtained from the formulae given in Ch the formulae in [3.2.3].
7, Sec 2, [3.10.1]
5.2.2 Side girders
4.3.3 Primary supporting members Where the depth from the peak tank top to the weather
The net shear area Ash , in cm2, of primary supporting mem- deck is greater than 2,6 m and the side is transversely
bers at any position along their span is not to be less than framed, one or more side girders are to be fitted, preferably
the value obtained from the formula given in Ch 7, Sec 3, in line with similar structures existing forward.
[6.1.1].
6 Sternframes
5 Connection of hull structures with
the rudder horn 6.1 General
5.1 Connection of after peak structures with 6.1.1 Sternframes may be made of cast or forged steel, with
the rudder horn a hollow section, or fabricated from plate.
5.2 Structural arrangement above the after 6.2.3 Connection with transom floors
peak Rudder posts and, in the case of ships greater than 90 m in
length, propeller posts are to be connected with transom
5.2.1 Side transverses
floors having height not less than that of the double bottom
Where a rudder horn is fitted, side transverses, connected to and net thickness not less than that obtained, in mm, from
deck beams, are to be arranged between the platform form- the following formula:
ing the peak tank top and the weather deck.
t = 9 + 0,023 L1 k1/2
The side transverse spacing is to be not greater than:
2-frame spacing in way of the horn 6.2.4 Connection with centre keelson
4-frame spacing for and aft of the rudder horn Where the sternframe is made of cast steel, the lower part of
6-frame spacing in the area close to the after peak bulk- the sternframe is to be fitted, as far as practicable, with a
head. longitudinal web for connection with the centre keelson.
Fabricated propeller post Cast propeller post Bar propeller post, cast or forged,
having rectangular section
Gross
diaphragm of
thickness t d
diaphragm of
scantlings of
thickness t d
t t1
propeller b R b
posts,
b
in mm
a t2
a
a
Fabricated propeller post Cast propeller post Bar propeller post, cast or forged,
having rectangular section
Gross
diaphragm of
scantlings of
diaphragm of
thickness t d
thickness t d
propeller
t1 t2 t1
t2 b t3 b
posts, b
in mm
a a
a
Fabricated propeller post Cast propeller post Bar propeller post, cast or forged,
having rectangular section
Gross
diaphragm of
scantlings of
diaphragm of
thickness t d
thickness t d
propeller
t1 t2 t1
t2 b t3 b
posts, b
in mm
a a
a
6.3.3 Section modulus below the propeller shaft Figure 1 : Integral rudder post
bossing
In the case of a propeller post without a sole piece, the sec-
tion modulus of the propeller post may be gradually
reduced below the propeller shaft bossing down to 85% of
the value calculated with the scantlings in Tab 9 or Tab 10,
as applicable.
y
6.4.1 Net section modulus of integral rudder post Section X - X
Symbols
2.1.5 Side bottom girders in way of machinery The depth of manholes is generally to be not greater than
seatings 40% of the floor local depth, and in no case greater than
Additional side bottom girders are to be fitted in way of 750 mm, and their width is to be equal to approximately
machinery seatings. 400 mm.
Side bottom girders arranged in way of main machinery In general, manhole edges are to be stiffened with flanges;
seatings are to extend for the full length of the machinery failing this, the floor plate is to be adequately stiffened with
space. flat bars at manhole sides.
Where the machinery space is situated amidships, the bot- Manholes with perforated portable plates are to be fitted in
tom girders are to extend aft of the after bulkhead of such the inner bottom in the vicinity of wells arranged close to
space for at least three frame spaces, and beyond to be con- the aft bulkhead of the engine room.
nected to the hull structure by tapering.
Drainage of the tunnel is to be arranged through a well
Where the machinery space is situated aft, the bottom gird- located at the aft end of the tunnel.
ers are to extend as far aft as practicable in relation to the
shape of the bottom and to be supported by floors and side
2.2 Minimum thicknesses
primary supporting members at the ends.
Forward of the machinery space forward bulkhead, the bot- 2.2.1 The net thicknesses of inner bottom, floor and girder
tom girders are to be tapered for at least three frame spaces webs are to be not less than the values given in Tab 1.
and are to be effectively connected to the hull structure.
2.2.2 Lower net thickness values for floor and web girder
2.1.6 Floors in longitudinally framed double bottom web can be accepted, if based on direct calculations.
Where the double bottom is longitudinally framed, the floor
spacing is to be not greater than: 3 Single bottom
1-frame spacing in way of the main engine and thrust
bearing
3.1 Arrangement
2-frame spacing in other areas of the machinery space.
3.1.1 Bottom girder
Additional floors are to be fitted in way of other important
machinery. For single bottom girder arrangement, the requirements of
Ch 4, Sec 4, [4.1] and Ch 4, Sec 4, [4.4] for double bottom
2.1.7 Floors in transversely framed double bottom apply.
Where the double bottom in the machinery space is trans-
versely framed, floors are to be arranged at every frame. 3.1.2 Floors in longitudinally framed single bottom
Where the single bottom is longitudinally framed, the floor
Furthermore, additional floors are to be fitted in way of
spacing is to be not greater than:
boiler foundations or other important machinery.
1-frame spacing in way of the main engine and thrust
2.1.8 Floors stiffeners bearing
In addition to the requirements in Ch 4, Sec 3, [4.7], floors 2-frame spacing in other areas of the machinery spaces.
are to have web stiffeners sniped at the ends and spaced not
more than approximately 1 m apart. Additional floors are to be fitted in way of other important
machinery.
The section modulus of web stiffeners is to be not less than
1,2 times that required in Ch 4, Sec 3, [4.7]. 3.1.3 Floors in transversely framed single bottom
2.1.9 Manholes and wells Where the single bottom is transversely framed, the floors
The number and size of manholes in floors located in way are to be arranged at every frame.
of seatings and adjacent areas are to be kept to the mini- Furthermore, additional floors are to be fitted in way of
mum necessary for double bottom access and maintenance. boiler foundations or other important machinery.
Table 1 : Double bottom - Minimum net thicknesses of inner bottom, floor and girder webs
3.1.4 Floor height For a longitudinally framed side, the side transverse spacing
The height of floors in way of machinery spaces located is to be not greater than 4-frame spacing.
amidships is to be not less than B/14,5. Where the top of the For a transversely framed side, the side transverse spacing is
floors is recessed in way of main machinery, the height of to be not greater than 5 frame spaces. The web height is to
the floors in way of this recess is generally to be not less be not less than twice that of adjacent frames and the sec-
than B/16. Lower values will be considered by the Society tion modulus is to be not less than four times that of adja-
on a case by case basis. cent frames.
Where the machinery space is situated aft or where there is Side transverse spacing greater than that above may be
considerable rise of floor, the depth of the floors will be accepted provided that the scantlings of ordinary frames are
considered by the Society on a case by case basis. increased, according to the Societys requirements to be
defined on a case by case basis.
3.1.5 Floor flanging
Floors are to be fitted with welded face plates in way of:
5 Platforms
engine bed plates
thrust blocks 5.1 Arrangement
auxiliary seatings.
5.1.1 General
3.2 Minimum thicknesses The location and extension of platforms in machinery
spaces are to be arranged so as to be a continuation of the
3.2.1 The net thicknesses of floor and girder webs are to be structure of side longitudinals, as well as of platforms and
not less than the values given in Tab 2. side girders located in the adjacent hull areas.
4.1.1 General
6.1 Arrangement
The type of side framing in machinery spaces is generally to 6.1.1 General
be the same as that adopted in the adjacent areas.
The pillaring arrangement in machinery spaces is to
4.1.2 Extension of the hull longitudinal structure account both for the concentrated loads transmitted by
within the machinery space machinery and superstructures and for the position of main
machinery and auxiliary engines.
In ships where the machinery space is located aft and where
the side is longitudinally framed, the longitudinal structure 6.1.2 Pillars
is preferably to extend for the full length of the machinery
space. Pillars are generally to be arranged in the following posi-
tions:
In any event, the longitudinal structure is to be maintained
for at least 0,3 times the length of the machinery space, cal- in way of machinery casing corners and corners of large
culated from the forward bulkhead of the latter, and abrupt openings on platforms; alternatively, two pillars may be
structural discontinuities between longitudinally and trans- fitted on the centreline (one at each end of the opening)
versely framed structures are to be avoided. in way of the intersection of platform transverses and
girders
4.1.3 Side transverses
in way of transverse and longitudinal bulkheads of the
Side transverses are to be aligned with floors. One is prefer- superstructure.
ably to be located in way of the forward end and another in
way of the after end of the machinery casing. In general, pillars are to be fitted with brackets at their ends.
The ordinary stiffener spacing in portions of casings which 8.1.3 Supporting structure included in the double
are particularly exposed to wave action is considered by the bottom structure
Society on a case by case basis. Where large internal combustion engines or turbines plants
are fitted, supporting members are to be integral with the
double bottom structure. Longitudinal members supporting
7.2 Openings
the bedplates in way of seatings are to be aligned with dou-
ble bottom girders and are to be extended aft in order to
7.2.1 General
form girders for thrust blocks.
All machinery space openings, which are to comply with
The longitudinal members in way of seatings are to be con-
the requirements in Ch 8, Sec 10, [7], are to be enclosed in
tinuous from the bedplates to the bottom shell.
a steel casing leading to the highest open deck. Casings are
to be reinforced at the ends by deck beams and girders 8.1.4 Supporting structure above the double
associated to pillars. bottom plating
In the case of large openings, the arrangement of cross-ties Where the supporting structure is situated above the double
as a continuation of deck beams may be required. bottom plating, the girders in way of seatings are to be fitted
with flanged brackets, generally located at each frame and
Skylights, where fitted with openings for light and air, are to extending towards both the centre of the ship and the sides.
have coamings of a height not less than:
The extension of the seatings above the double bottom plat-
900 mm, if in position 1 ing is to be limited as far as practicable while ensuring ade-
quate spaces for the fitting of bedplate bolts. Bolt holes are
760 mm, if in position 2.
to be located such that they do not interfere with supporting
structures.
7.2.2 Access doors
Access doors to casings are to comply with Ch 8, Sec 10, 8.1.5 Seatings in a single bottom structure
[7.2]. For ships having a single bottom structure within the
machinery space, seatings are to be located above the floors
7.3 Scantlings and to be adequately connected to the latter and to the gird-
ers located below.
7.3.1 Plating and ordinary stiffeners 8.1.6 Number of longitudinal members in way of
The net scantlings of plating and ordinary stiffeners are to seatings of engines
be not less than those obtained according to the applicable In general, at least two longitudinal members are to be fitted
requirements in Ch 8, Sec 4. in way of seatings of main engines.
One longitudinal member may be fitted only where the fol-
7.3.2 Minimum thicknesses lowing three formulae are complied with:
The net thickness of bulkheads is to be not less than: L < 150 m
5,5 mm for bulkheads in way of cargo holds P < 7100 kW
4 mm for bulkheads in way of accommodation spaces. P < 2,3 nR LE
Symbols
1.1.1 The requirements of this Section apply for the scant- Where hatchways are fitted close to the ends of superstruc-
ling of plating and associated structures of front, side and aft tures, additional strengthening may be required.
bulkheads and decks of superstructures and deckhouses,
which may or may not contribute to the longitudinal 1.4.2 Connection to the deck of corners of superstructures
and deckhouses is considered by the Society on a case by
strength.
case basis. Where necessary, doublers or reinforced weld-
ing may be required.
1.1.2 The requirements of this Section comply with the
applicable regulations of the 1966 International Convention 1.4.3 As a rule, the frames of sides of superstructures and
on Load Lines, as amended, with regard to the strength of deckhouses are to have the same spacing as the beams of
enclosed superstructures. the supporting deck.
1.2.1 As specified in Ch 4, Sec 2, [1], all scantlings referred 1.4.4 The side plating at ends of superstructures is to be
to in this Section are net, i.e. they do not include any mar- tapered into the bulwark or sheerstrake of the strength deck.
gin for corrosion. Where a raised deck is fitted, this arrangement is to extend
over at least a 3-frame spacing.
The gross scantlings are obtained as specified in Ch 4, Sec 2.
Where the freeboard exceeds one standard superstructure Web frames are also to be arranged in way of large open-
height, defined in Ch 1, Sec 2, Tab 2 for all other super- ings, boats davits and other areas subjected to point loads.
structures, the lowest tier may be considered as an upper Web frames, pillars, partial bulkheads and similar strength-
tier when calculating the scantlings of superstructures and ening are to be arranged, in conjunction with deck trans-
deckhouses. verses, at ends of superstructures and deckhouses.
When a superstructure is located above a raised quarter 2.1 Sides contributing to the longitudinal
deck, the thickness of the raised quarter deck stringer plate strength
is to be increased by 30% and is to be extended within the
superstructure. 2.1.1 Load point
Lateral pressure is to be calculated at:
The increase above may be reduced when the raised quar-
the lower edge of the elementary plate panel, for plating
ter deck terminates outside 0,5 L amidships.
mid-span, for stiffeners.
1.5.3 Openings 2.1.2 Lateral pressure
Openings are to be in accordance with Ch 6, Sec 1. The lateral pressure is constituted by the still water sea
pressure (pS) and the wave pressure (pW), defined in Ch 5,
Continuous coamings are to be fitted above and below Sec 5.
doors or similar openings.
Moreover, when the side is a tank boundary, the
lateral pressure constituted by the still water internal pres-
1.5.4 Access and doors sure (pS) and the inertial pressure (pW), defined in Ch 5, Sec
Access openings cut in sides of enclosed superstructures are 6, [1], is also to be considered.
to be fitted with doors made of steel or other equivalent
material, and permanently attached. 2.2 Front, side and aft bulkheads not
contributing to the longitudinal strength
Special consideration is to be given to the connection of
doors to the surrounding structure. 2.2.1 Load point
Lateral pressure is to be calculated at:
Securing devices which ensure watertightness are to
include tight gaskets, clamping dogs or other similar appli- mid-height of the bulkhead, for plating
ances, and are to be permanently attached to the bulkheads mid-span, for stiffeners.
and doors. These doors are to be operable from both sides.
2.2.2 Lateral pressure
Unless otherwise permitted by the Society, doors open out- The lateral pressure to be used for the determination of
wards to provide additional security against the impact of scantlings of the structure of front, side and aft bulkheads of
the sea. superstructures and deckhouses is to be obtained, in kN/m2,
from the following formula:
1.5.5 Strengthening of deckhouses in way of p = 10 n a c [b f (z T)]
lifeboats and rescue boats
without being less than pmin
Sides of deckhouses are to be strengthened in way of life-
where:
boats and rescue boats and the top plating is to be rein-
n : Navigation coefficient, defined in Ch 5, Sec 1,
forced in way of their lifting appliances.
[2.6]
Aluminium alloys may be adopted for front bulkheads of f : Coefficient defined in Tab 3
superstructures or deckhouses above the first tier. pmin : Minimum lateral pressure defined in Tab 4.
Table 1 : Lateral pressure for superstructures and Table 3 : Lateral pressure for superstructures and
deckhouses - Coefficient a deckhouses - Coefficient f
Table 2 : Lateral pressure for superstructures and 3.1 Front, side and aft bulkheads
deckhouses - Coefficient b
3.1.1 Plating contributing to the longitudinal
strength
Location of bulkhead (1) b
The net thickness of side plate panels contributing to the
x 2
longitudinal strength is to be determined in accordance
x --- 0 ,45
--- 0 ,45 L
1 + --------------------- with the applicable requirements of Ch 7, Sec 1, consider-
L C B + 0 ,2 ing the lateral pressure defined in [2.1.2].
For plating which forms tank boundaries, the net thickness : Coefficient depending on the stiffener end con-
is to be determined in accordance with [3.1.1], considering nections, and taken equal to:
the hull girder stress equal to 0. 1 for lower tier stiffeners
This net thickness is to be not less than: value defined in Tab 6 for stiffeners of upper
tiers
the values given in Tab 5 for steel superstructures,
, : Parameters defined in Ch 4, Sec 2, Tab 1.
the following values for aluminium superstructures:
The section modulus of side ordinary stiffeners need not be
- 4 mm for rolled products greater than that of the side ordinary stiffeners of the tier sit-
- 2,5 mm for extruded products. uated directly below taking account of spacing and span.
For ordinary stiffeners of plating forming tank boundaries,
Table 5 : Minimum thicknesses of the net scantlings are to be determined in accordance with
superstructures and deckhouses [4.1.1], considering the hull girder stress equal to 0.
Sniped lower
3.2.1 The net thickness of plate panels of decks which may 1,15 1,00 1,15
end
or may not contribute to the longitudinal strength is to be
determined in accordance with the applicable requirements
of Ch 7, Sec 1. 4.2 Decks
3.2.2 For decks sheathed with wood, the net thickness 4.2.1 The net scantlings of ordinary stiffeners of decks
obtained from [3.2.1] may be reduced by 10 percent. which may or may not contribute to the longitudinal
strength are to be determined in accordance with the appli-
cable requirements of Ch 7, Sec 2.
4 Ordinary stiffeners
5 Primary supporting members
4.1 Front, side and aft bulkheads
5.1 Front, side and aft bulkheads
4.1.1 General
The net scantlings of ordinary stiffeners are to be deter- 5.1.1 Primary supporting members of plating
contributing to the longitudinal strength
mined according to:
The net scantlings of side primary supporting members of
[4.1.2] for single span vertical ordinary stiffeners of plating contributing to the longitudinal strength are to be
plating not contributing to the longitudinal strength determined in accordance with the applicable requirements
Ch 7, Sec 2 for all the other cases. of Ch 7, Sec 3.
6 Additional requirements applicable still water and inertial forces, determined according to
Ch 5, Sec 6, [5]
to movable wheelhouses
wind forces, corresponding to a lateral pressure of
1,2kN/m2.
6.1 General
6.2.2 Checking criteria
6.1.1 The requirements of this Article apply in addition of
those in [1] to [5]. It is to be checked that the equivalent stress VM , calculated
according to Ch 7, App 1, [5.1.2] or Ch 7, App 1, [5.2.2], as
6.1.2 The structures of movable wheelhouses are to be applicable, is in compliance with the following formula:
checked in low and in high position.
Ry
---------- VM
6.1.3 Mechanical locking devices are to be fitted in addi- R m
tion to hydraulic systems. where:
Ry : Minimum yield stress, in N/mm2, of the mate-
6.2 Supports and guides, connections with rial, to be taken equal to 235/k, unless other-
the deck, under deck reinforcements, wise specified
locking devices R : Partial safety factor covering uncertainties
regarding resistance, to be taken equal to:
6.2.1 Still water and inertial forces
1,10 in general
The supports or guides of movable wheelhouses, connec-
tions with the deck, under deck reinforcements and locking 1,40 for checking locking devices
devices are to be checked considering the sum of the fol- m : Partial safety factor covering uncertainties
lowing forces: regarding material, to be taken equal to 1,02.
Other types of bow door are considered by the Society on a 1.4.2 Supporting device
case by case basis in association with the applicable A supporting device is a device used to transmit external or
requirements of this Section. internal loads from the door to a securing device and from
the securing device to the ships structure, or a device other
1.2 Gross scantlings than a securing device, such as a hinge, stopper or other
fixed device, which transmits loads from the door to the
1.2.1 With reference to Ch 4, Sec 2, [1], all scantlings and ships structure.
dimensions referred to in this Section are gross, i.e. they
1.4.3 Locking device
include the margins for corrosion.
A locking device is a device that locks a securing device in
the closed position.
1.3 Arrangement
1.3.1 Bow doors are to be situated above the freeboard 2 Design loads
deck. A watertight recess in the freeboard deck located for-
ward of the collision bulkhead and above the deepest 2.1 Bow doors
waterline fitted for arrangement of ramps or other related
mechanical devices may be regarded as a part of the free- 2.1.1 Design external pressure
board deck for the purpose of this requirement. The design external pressure to be considered for the scant-
lings of primary supporting members and securing and sup-
1.3.2 An inner door is to be fitted as part of the collision porting devices of bow doors is to be not less than that
bulkhead. The inner door need not be fitted directly above obtained, in kN/m2, from the following formula:
the bulkhead below, provided it is located within the limits 2
p E = 0, 5n D C L C Z ( 0 ,22 + 0 ,15 tan ) ( 0 ,4 V sin + 0 ,6 L 1 )
specified for the position of the collision bulkhead, as per
Ch 2, Sec 1, [3.1]. where:
A vehicle ramp may be arranged for this purpose, provided nD : Navigation coefficient, defined in Tab 1
its position complies with Ch 2, Sec 1, [3.1]. V : Maximum ahead service speed, in knots
: Flare angle at the calculation point, defined as h : Height, in m, to be taken as the lesser of h1 and
the angle between a vertical line and the tan- h2
gent to the side plating, measured in a vertical
plane normal to the horizontal tangent to the h1 : Height, in m, of the door between the levels of
shell plating (see Fig 1) its bottom and the upper deck
: Entry angle at the calculation point, defined as h2 : Height, in m, of the door between its bottom
the angle between a longitudinal line parallel to and top
the centreline and the tangent to the shell plat-
ing in a horizontal plane (see Fig 1). : Length, in m, of the door at a height h/2 above
the bottom of the door
Table 1 : Navigation coefficient AX : Area, in m2, of the transverse vertical projection
of the door between the levels of the bottom of
Navigation notation Navigation coefficient nD the door and the top of the upper deck bulwark
Unrestricted navigation 1,00 or between the bottom of the door and the top
Summer zone 1,00 of the door, including the bulwark, where it is
part of the door, whichever is lesser. Where the
Tropical zone 0,80
flare angle of the bulwark is at least 15 degrees
Coastal area 0,80 less than the flare angle of the adjacent shell
Sheltered area 0,50 plating, the height from the bottom of the door
may be measured to the upper deck or to the
Figure 1 : Definition of angles and top of the door, whichever is lesser. In determin-
ing the height from the bottom of the door to the
/2 /2 upper deck or to the top of the door, the bul-
wark is to be excluded
4.1.2 Where inner doors also serve as vehicle ramps, their Figure 3 : Thrust bearing
scantlings are to be not less than those obtained according
to Ch 8, Sec 9.
5.1 General
5.1.1 Bow doors are to be fitted with adequate means of
securing and supporting so as to be commensurate with the
strength and stiffness of the surrounding structure.
The hull supporting structure in way of the bow doors is to
be suitable for the same design loads and design stresses as
the securing and supporting devices. 5.2 Scantlings
Where packing is required, the packing material is to be of 5.2.1 Securing and supporting devices are to be adequately
a comparatively soft type, and the supporting forces are to designed so that they can withstand the reaction forces
be carried by the steel structure only. Other types of packing within the allowable stresses defined in [6.1.1].
may be considered by the Society on a case by case basis.
The maximum design clearance between securing and sup- 5.2.2 For visor doors, the reaction forces applied on the
porting devices is generally not to exceed 3 mm. effective securing and supporting devices assuming the
door as a rigid body are determined for the following com-
A means is to be provided for mechanically fixing the door bination of external loads acting simultaneously together
in the open position. with the self weight of the door:
5.1.2 Only the active supporting and securing devices having Case 1: FX and FZ
an effective stiffness in the relevant direction are to be included Case 2: 0,7FY acting on each side separately together
and considered to calculate the reaction forces acting on the with 0,7FX and 0,7FZ ,
devices. Small and/or flexible devices such as cleats intended
to provide local compression of the packing material may gen- where FX, FY and FZ are to be calculated as indicated in
erally not be included in the calculation in [5.2.5]. [2.1.2] and applied at the centroid of projected areas.
The number of securing and supporting devices is generally
5.2.3 For side-opening doors, the reaction forces applied
to be the minimum practical while taking into account the
on the effective securing and supporting devices assuming
requirements for redundant provision given in [5.2.6] and
the door as a rigid body are determined for the following
[5.2.7] and the available space for adequate support in the
combination of external loads acting simultaneously
hull structure.
together with the self weight of the door:
5.1.3 For visor doors which open outwards, the pivot Case 1: FX , FY and FZ acting on both doors
arrangement is generally to be such that the visor is self- Case 2: 0,7FX and 0,7FZ acting on both doors and 0,7FY
closing under external loads, i.e. it is to be checked that the acting on each door separately,
closing moment MY, defined in [2.1.3], is in compliance
with the following formula: where FX, FY and FZ are to be calculated as indicated in
MY > 0 [2.1.2] and applied at the centroid of projected areas.
Moreover, the closing moment MY is to be not less than the 5.2.4 The support forces as calculated according to Case 1
value MY0 , in kN.m, obtained from the following formula: in [5.2.2] and Case 1 in [5.2.3] are to generally give rise to a
zero moment about the transverse axis through the centroid
M Y0 = 10Wc + 0 ,1 a 2 + b 2 F X2 + F Z2
of the area AX.
5.1.4 For side-opening doors, a thrust bearing is to be pro- For visor doors, longitudinal reaction forces of pin and/or
vided in way of girder ends at the closing of the two leaves wedge supports at the door base contributing to this
to prevent one leaf from shifting towards the other under the moment are not to be in the forward direction.
effect of unsymmetrical pressure (see example in Fig 3).
5.2.5 The distribution of the reaction forces acting on the
The parts of the thrust bearing are to be kept secured to securing and supporting devices may need to be supported
each other by means of securing devices. by direct calculations taking into account the flexibility of
The Society may consider any other arrangement serving the hull structure and the actual position and stiffness of the
the same purpose. supports.
5.2.6 The arrangement of securing and supporting devices 6.1.2 Buckling check
in way of these securing devices is to be designed with The buckling check of primary supporting members is to be
redundancy so that, in the event of failure of any single carried out according to Ch 7, Sec 3, [7].
securing or supporting device, the remaining devices are
capable of withstanding the reaction forces without exceed- 6.1.3 Bearings
ing by more than 20% the allowable stresses defined in For steel to steel bearings in securing and supporting
[6.1.1]. devices, it is to be checked that the nominal bearing pres-
5.2.7 For visor doors, two securing devices are to be pro- sure B, in N/mm2, is in compliance with the following for-
vided at the lower part of the door, each capable of provid- mula:
ing the full reaction force required to prevent opening of the B 0,8 Re,HB
door within the allowable stresses defined in [6.1.1].
where:
The opening moment M0 to be balanced by this reaction
force is to be taken not less than that obtained, in kN.m, F
B = 10 ------
from the following formula: AB
M0 = 10 W d + 5 AX a F : Design force, in kN, defined in [2.1.2]
where: AB : Projected bearing area, in cm2
d : Vertical distance, in m, from the hinge axis to Re,HB : Yield stress, in N/mm2, of the bearing material.
the centre of gravity of the door, as shown in Fig For other bearing materials, the allowable bearing pressure
2 is to be determined according to the manufacturers specifi-
a : Vertical distance, in m, defined in [2.1.3]. cation.
5.2.8 For visor doors, the securing and supporting devices 6.1.4 Bolts
excluding the hinges are to be capable of resisting the verti-
The arrangement of securing and supporting devices is to be
cal design force (FZ 10 W), in kN, within the allowable
such that threaded bolts do not carry support forces.
stresses defined in [6.1.1].
It is to be checked that the tension T in way of threads of
5.2.9 All load transmitting elements in the design load bolts not carrying support forces is in compliance with the
path, from the door through securing and supporting following formula:
devices into the ships structure, including welded connec-
T T,ALL
tions, are to be of the same strength standard as required for
the securing and supporting devices. These elements where:
include pins, supporting brackets and back-up brackets. T,ALL : Allowable tension in way of threads of bolts, in
N/mm2, equal to:
6 Strength criteria T,ALL = 125/k
k : Material coefficient defined in [6.1.1].
6.1 Primary supporting members and
securing and supporting devices
7 Securing and locking arrangement
6.1.1 Yielding check
It is to be checked that the normal stresses , the shear 7.1 Systems for operation
stress and the equivalent stress VM, induced in the pri-
mary supporting members and in the securing and support- 7.1.1 Securing devices are to be simple to operate and eas-
ing devices of bow doors by the design load defined in [2], ily accessible.
are in compliance with the following formulae:
Securing devices are to be equipped with mechanical lock-
ALL ing arrangement (self-locking or separate arrangement), or
ALL to be of the gravity type.
VM = (2 + 3 2) 0,5 VM,ALL The opening and closing systems as well as securing and
locking devices are to be interlocked in such a way that
where:
they can only operate in the proper sequence.
ALL : Allowable normal stress, in N/mm2, equal to:
ALL = 120/k 7.1.2 Bow doors and inner doors giving access to vehicle
ALL 2
: Allowable shear stress, in N/mm , equal to: decks are to be provided with an arrangement for remote
control, from a position above the freeboard deck, of:
ALL = 80/k
the closing and opening of the doors, and
VM,ALL : Allowable equivalent stress, in N/mm2, equal to:
associated securing and locking devices for every door.
VM,ALL = 150/k
k : Material factor, defined in Ch 4, Sec 1, [2.3], Indication of the open/closed position of every door and
but to be taken not less than 0,72 unless a every securing and locking device is to be provided at the
fatigue analysis is carried out. remote control stations.
The operating panels for operation of doors are to be inac- 7.2.3 The indication panel on the navigation bridge is to be
cessible to unauthorised persons. equipped with a mode selection function harbour/sea voy-
age, so arranged that an audible alarm is given on the nav-
A notice plate, giving instructions to the effect that all secur-
igation bridge if the ship leaves harbour with the bow door
ing devices are to be closed and locked before leaving har-
or the inner door not closed or with any of the securing
bour, is to be placed at each operating panel and is to be
devices not in the correct position.
supplemented by warning indicator lights.
7.2.4 A water leakage detection system with an audible
7.1.3 Where hydraulic securing devices are applied, the
alarm and television surveillance is to be arranged to pro-
system is to be mechanically lockable in closed position.
vide an indication to the navigation bridge and to the
This means that, in the event of loss of hydraulic fluid, the
engine control room of leakage through the inner door.
securing devices remain locked.
Note 1: The indicator system is considered designed on the fail-safe
The hydraulic system for securing and locking devices is to principal when:
be isolated from other hydraulic circuits, when in closed
The indication panel is provided with:
position.
- a power failure alarm
- an earth failure alarm
7.2 Systems for indication/monitoring
- a lamp test
7.2.1 Separate indicator lights and audible alarms are to - separate indication for door closed, door locked, door not
be provided on the navigation bridge and on the operating closed and door not locked
panel to show that the bow door and inner door are closed Limit switches electrically closed when the door is closed
and that their securing and locking devices are properly (when more limit switches are provided they may be con-
positioned. nected in series)
The indication panel is to be provided with a lamp test Limit switches electrically closed when securing arrangements
function. It is not to be possible to turn off the indicator are in place (when more limit switches are provided they may
light. be connected in series)
Two electrical circuits (also in one multicore cable), one for the
7.2.2 The indicator system is to be designed on the fail safe indication of door closed/not closed and the other for door
principle and is to show by visual alarms if the door is not locked/not locked
fully closed and not fully locked and by audible alarms if In case of dislocation of limit switches, indication to show: not
securing devices become open or locking devices become closed/not locked/securing arrangement not in place - as
unsecured. appropriate.
The power supply for the indicator system for operating and 7.2.5 Between the bow door and the inner door a televi-
closing doors is to be independent of the power supply for sion surveillance system is to be fitted with a monitor on the
operating and closing the doors and is to be provided with a navigation bridge and in the engine control room.
back-up power supply from the emergency source of power
or other secure power supply, e.g. UPS. The system is to monitor the position of the doors and a suf-
ficient number of their securing devices.
The sensors of the indicator system are to be protected from
water, ice formation and mechanical damage. Special consideration is to be given for the lighting and con-
trasting colour of the objects under surveillance.
Note 1: The indicator system is considered designed on the fail-safe
principal when: Note 1: The indicator system is considered designed on the fail-safe
principal when:
The indication panel is provided with:
The indication panel is provided with:
- a power failure alarm
- a power failure alarm
- an earth failure alarm
- an earth failure alarm
- a lamp test - a lamp test
- separate indication for door closed, door locked, door not - separate indication for door closed, door locked, door not
closed and door not locked closed and door not locked
Limit switches electrically closed when the door is closed Limit switches electrically closed when the door is closed
(when more limit switches are provided they may be con- (when more limit switches are provided they may be con-
nected in series) nected in series)
Limit switches electrically closed when securing arrangements Limit switches electrically closed when securing arrangements
are in place (when more limit switches are provided they may are in place (when more limit switches are provided they may
be connected in series) be connected in series)
Two electrical circuits (also in one multicore cable), one for the Two electrical circuits (also in one multicore cable), one for the
indication of door closed/not closed and the other for door indication of door closed/not closed and the other for door
locked/not locked locked/not locked
In case of dislocation of limit switches, indication to show: not In case of dislocation of limit switches, indication to show: not
closed/not locked/securing arrangement not in place - as closed/not locked/securing arrangement not in place - as
appropriate. appropriate.
7.2.6 The indicator system for the closure of the doors and 8 Operating and Maintenance Manual
the television surveillance systems for the doors and water
leakage detection, and for special category and ro-ro spaces 8.1 General
are to be suitable to operate correctly in the ambient condi-
tions on board and to be type approved on the basis of the 8.1.1 An Operating and Maintenance Manual for the bow
applicable tests required in Part D, Chapter 1 and/or Part D, door and inner door is to be provided on board and is to
Chapter 12. contain the necessary information on:
a) main particulars and design drawings:
7.2.7 A drainage system is to be arranged in the area special safety precautions
between bow door and ramp or, where no ramp is fitted, details of ship
between the bow door and the inner door. equipment and design loading (for ramps)
The system is to be equipped with an audible alarm func- key plan of equipment (doors and ramps)
tion to the navigation bridge being set off when the water manufacturers recommended testing for equipment
levels in these areas exceed 0,5 m or the high water level description of equipment:
alarm, whichever is lesser. - bow doors
Note 1: The indicator system is considered designed on the fail-safe
- inner bow doors
principal when: - bow ramp/doors
- central power pack
The indication panel is provided with:
- bridge panel
- a power failure alarm - engine control room panel
- an earth failure alarm b) service conditions:
limiting heel and trim of ship for loading/unloading
- a lamp test
limiting heel and trim for door operations
- separate indication for door closed, door locked, door not doors/ramps operating instructions
closed and door not locked doors/ramps emergency operating instructions
Limit switches electrically closed when the door is closed c) maintenance:
(when more limit switches are provided they may be con- schedule and extent of maintenance
nected in series) trouble shooting and acceptable clearances
Limit switches electrically closed when securing arrangements manufacturers maintenance procedures
are in place (when more limit switches are provided they may d) register of inspections, including inspection of locking,
be connected in series) securing and supporting devices, repairs and renewals.
Two electrical circuits (also in one multicore cable), one for the This manual is to be submitted in duplicate to the Society
indication of door closed/not closed and the other for door for approval that the above mentioned items are contained
locked/not locked in the OMM and that the maintenance part includes the
necessary information with regard to inspections, trouble-
In case of dislocation of limit switches, indication to show: not shooting and acceptance/rejection criteria.
closed/not locked/securing arrangement not in place - as Note 1: It is recommended that inspections of the doors and sup-
appropriate. porting and securing devices be carried out by ships personnel at
monthly intervals or following any incidents which could result in
7.2.8 For ro-ro passenger ships on international voyages, the damage, including heavy weather or contact in the region of the
special category spaces and ro-ro spaces are to be continu- shell doors. A record is to be kept and any damage found during
such inspections is to be reported to the Society.
ously patrolled or monitored by effective means, such as tel-
evision surveillance, so that any movement of vehicles in 8.1.2 Documented operating procedures for closing and
adverse weather conditions or unauthorized access by pas- securing the bow door and inner door are to be kept on
sengers thereto, can be detected whilst the ship is underway. board and posted at an appropriate place.
1.1.1 The requirements of this Section apply to the arrange- 2 Design loads
ment, strength and securing of side doors located abaft the
collision bulkhead, and of stern doors leading to enclosed 2.1 Side and stern doors
spaces and dedicated to loading/unloading of cargo and
vehicles.
2.1.1 Design forces
The requirements apply to ships engaged on international The design external forces FE and the design internal forces
voyages and also to ships engaged only in domestic (non- FI to be considered for the scantlings of primary supporting
international) voyages, except where specifically indicated members and securing and supporting devices of side doors
otherwise in this section. and stern doors are to be obtained, in kN, from the formu-
Small shell doors not covered by this Section are dealt with lae in Tab 1.
in Ch 8, Sec 12.
3 Scantlings of side doors and stern
1.2 Gross scantlings doors
1.2.1 With reference to Ch 4, Sec 2, [1], all scantlings and 3.1 General
dimensions referred to in this Section are gross, i.e. they
include the margins for corrosion. 3.1.1 The strength of side doors and stern doors is to be
commensurate with that of the surrounding structure.
1.3 Arrangement
3.1.2 Side doors and stern doors are to be adequately stiff-
ened and means are to be provided to prevent any lateral or
1.3.1 Side doors and stern doors are to be so fitted as to
vertical movement of the doors when closed.
ensure tightness and structural integrity commensurate with
their location and the surrounding structure. Adequate strength is to be provided in the connections of
the lifting/manoeuvring arms and hinges to the door struc-
1.3.2 Where the sill of any side door is below the upper- ture and to the ships structure.
most load line, the arrangement is considered by the Soci-
ety on a case by case basis. 3.1.3 Where doors also serve as vehicle ramps, the design
of the hinges is to take into account the ship angle of trim
and heel which may result in uneven loading on the hinges.
1.3.3 Doors are preferably to open outwards.
3.1.4 Shell door openings are to have well rounded corners
1.4 Definitions and adequate compensation is to be arranged with web
frames at sides and stringers or equivalent above and below.
1.4.1 Securing device
A securing device is a device used to keep the door closed 3.2 Plating and ordinary stiffeners
by preventing it from rotating about its hinges or about piv-
oted attachments to the ship. 3.2.1 Plating
The thickness of the door plating is to be not less than that
1.4.2 Supporting device obtained according to the requirements in Ch 7, Sec 1, for
side plating, using the door stiffener spacing. In no case
A supporting device is a device used to transmit external or
may it be less than the minimum required thickness of side
internal loads from the door to a securing device and from
plating.
the securing device to the ships structure, or a device other
than a securing device, such as a hinge, stopper or other Where doors also serve as vehicle ramps, the thickness of
fixed device, which transmits loads from the door to the the door plating is to be not less than that obtained accord-
ships structure. ing to Ch 8, Sec 9.
Table 2 : Navigation coefficient 3.3.2 The primary supporting members and the hull struc-
ture in way are to have sufficient stiffness to ensure struc-
tural integrity of the boundary of the door.
Navigation notation Navigation coefficient nD
Unrestricted navigation 1,00 3.3.3 Scantlings of primary supporting members are gener-
ally to be verified through direct strength calculations on
Summer zone 1,00
the basis of the design forces in [2.1.1] and the strength cri-
Tropical zone 0,80 teria in Ch 8, Sec 5, [6.1.1] and Ch 8, Sec 5, [6.1.2].
Coastal area 0,80 In general, isolated beam models may be used to calculate
the loads and stresses in primary supporting members.
Sheltered area 0,50
Members are to be considered to have simply supported
3.2.2 Ordinary stiffeners end connections.
The scantling of door ordinary stiffeners is to be not less
than that obtained according to the requirements in Ch 7, 4 Securing and supporting of doors
Sec 2, for the side, using the door stiffener spacing.
Consideration is to be given, where necessary, to differ-
4.1 General
ences in conditions of fixity between the ends of ordinary 4.1.1 Side doors and stern doors are to be fitted with ade-
stiffeners of doors and those of the side. quate means of securing and supporting so as to be com-
Where doors also serve as vehicle ramps, the scantling of mensurate with the strength and stiffness of the surrounding
ordinary stiffeners is to be not less than that obtained structure.
according to Ch 8, Sec 9. The hull supporting structure in way of the doors is to be
suitable for the same design loads and design stresses as the
3.3 Primary supporting members securing and supporting devices.
Where packing is required, the packing material is to be of
3.3.1 The door ordinary stiffeners are to be supported by a comparatively soft type, and the supporting forces are to
primary supporting members constituting the main stiffen- be carried by the steel structure only. Other types of packing
ing of the door. may be considered by the Society on a case by case basis.
where:
4.2.3 The arrangement of securing and supporting devices
in way of these securing devices is to be designed with F
B = 10 ------
redundancy so that, in the event of failure of any single AB
securing or supporting device, the remaining devices are with:
capable of withstanding the reaction forces without exceed-
ing by more than 20% the allowable stresses defined in Ch F : Design force, in KN, defined in [2.1.1]
8, Sec 5, [6.1.1]. AB : Projected bearing area, in cm2
ReH,B : Yield stress, in N/mm2, of the bearing material.
4.2.4 All load transmitting elements in the design load
path, from the door through securing and supporting For other bearing materials, the allowable bearing pressure
devices into the ships structure, including welded connec- is to be determined according to the manufacturers specifi-
tions, are to be of the same strength standard as required for cation.
the securing and supporting devices. These elements
include pins, support brackets and back-up brackets. 5.1.4 Bolts
The arrangement of securing and supporting devices is to be
such that threaded bolts do not carry support forces.
5 Strength criteria
It is to be checked that the tension T in way of threads of
bolts not carrying support forces is in compliance with the
5.1 Primary supporting members and following formula:
securing and supporting devices
T T,ALL
5.1.1 Yielding check where:
It is to be checked that the normal stress , the shear stress T,ALL : Allowable tension in way of threads of bolts, in
and the equivalent stress VM, induced in the primary sup- N/mm2:
porting members and in the securing and supporting
T,ALL = 125 / k
devices of doors by the design load defined in [2], are in
compliance with the following formulae: k : Material factor, defined in Ch 8, Sec 5, [6.1.1].
6 Securing and locking arrangement 6.2.3 The indicator system is to be designed on the fail safe
principle and is to show by visual alarms if the door is not
fully closed and not fully locked and by audible alarms if
6.1 Systems for operation securing devices become open or locking devices become
unsecured. The power supply for the indicator system is to
6.1.1 Securing devices are to be simple to operate and eas- be independent of the power supply for operating and clos-
ily accessible. ing the doors and is to be provided with a backup power
Securing devices are to be equipped with mechanical lock- supply from the emergency source of power or secure
ing arrangement (self-locking or separate arrangement), or power supply, e.g. UPS.
to be of the gravity type. The sensors of the indicator system are to be protected from
The opening and closing systems as well as securing and water, ice formation and mechanical damages.
locking devices are to be interlocked in such a way that Note 1: See Ch 8, Sec 5, [7.2.2] for fail safe principal design.
they can only operate in the proper sequence.
6.2.4 The indication panel on the navigation bridge is to be
6.1.2 Doors which are located partly or totally below the equipped with a mode selection function "harbour/sea voy-
freeboard deck with a clear opening area greater than 6 m2 age", so arranged that audible alarm is given on the naviga-
are to be provided with an arrangement for remote control, tion bridge if the ship leaves harbour with any side shell or
from a position above the freeboard deck, of: stern door not closed or with any of the securing devices
not in the correct position.
the closing and opening of the doors
associated securing and locking devices. 6.2.5 For passenger ships, a water leakage detection system
with audible alarm and television surveillance is to be
For doors which are required to be equipped with a remote arranged to provide an indication to the navigation bridge
control arrangement, indication of the open/closed position and to the engine control room of any leakage through the
of the door and the securing and locking device is to be doors.
provided at the remote control stations. For cargo ships, a water leakage detection system with audi-
The operating panels for operation of doors are to be inac- ble alarm is to be arranged to provide an indication to the
cessible to unauthorised persons. navigation bridge.
A notice plate, giving instructions to the effect that all secur- 6.2.6 For ro-ro passenger ships, on international voyages,
ing devices are to be closed and locked before leaving har- the special category spaces and ro-ro spaces are to be con-
bour, is to be placed at each operating panel and is to be tinuously patrolled or monitored by effective means, such
supplemented by warning indicator lights. as television surveillance, so that any movement of vehicles
in adverse weather conditions and unauthorized access by
6.1.3 Where hydraulic securing devices are applied, the passengers thereto, can be detected whilst the ship is under-
system is to be mechanically lockable in closed position. way.
This means that, in the event of loss of hydraulic fluid, the
securing devices remain locked.
7 Operating and Maintenance Manual
The hydraulic system for securing and locking devices is to
be isolated from other hydraulic circuits, when in closed
position. 7.1 General
Symbols
For symbols not defined in this Section, refer to the list at 1.2.5 Pontoon type cover
the beginning of this Chapter.
A special type of portable cover, secured weathertight by
LLL : Load line length LLL , in m, as defined in Ch 1, tarpaulins and battening devices.
Sec 2, [3.2]
L3 : L, but to be taken not greater than 300 m 1.3 Materials
hs : Standard height of superstructure, as defined in
Ch 1, Sec 2, [3.19] 1.3.1 Steel
tC : Corrosion additions, in mm, as defined in [1.4] The materials used for construction of the steel large hatch
covers are to comply with the applicable requirements of
s : Stiffener spacing, in m NR216 Materials and Welding, Chapter 2.
pW : Wave pressure, in kN/m2, as defined in [3.1.1]
ASh : Net shear sectional area, in cm2, of the ordinary 1.3.2 Other materials
stiffener or primary supporting member The use of materials other than steel is considered by the
w : Net section modulus, in cm3, of the ordinary Society on a case-by-case basis, by checking that criteria
stiffener or primary supporting member. adopted for scantlings are such as to ensure strength and
stiffness equivalent to those of steel hatch covers.
1 General
1.4 Net scantling approach
1.1 Application
1.4.1 Corrosion additions for steel other than
stainless steel
1.1.1 The requirements of this Section apply to large cargo
hatch covers and coamings on exposed decks of all ships Unless otherwise specified, the thicknesses t in this Section
except those having the service notation bulk carrier, ore are net thicknesses.
carrier or combination carrier, for which Pt D, Ch 4, Sec 4
applies. The net thicknesses are the member thicknesses necessary
to obtain the minimum net scantlings required in [4] and
[8].
1.2 Definitions
The required gross thicknesses are obtained by adding cor-
1.2.1 Large hatches rosion additions tC given in Tab 1.
Large hatches are hatches with openings greater than Strength calculations using beam theory, grillage analysis or
2,5 m2. finite element (FE) analysis are to be performed with net
scantlings.
1.2.2 ICLL
Where ICLL is referred to in the text, this is to be taken as 1.4.2 Corrosion additions for aluminium alloys
the International Convention on Load Lines, 1966 as For structural members made of aluminium alloys, the cor-
amended by the 1988 protocol, as amended in 2003. rosion addition tC is to be taken equal to 0.
Application Structure tC , in mm
2.1.2 The height of hatch coamings in positions 1 and 2 2.2.4 Flange breadth of the primary supporting members is
closed by steel covers provided with gaskets and securing to be not less than 40% of their depth for laterally unsup-
devices may be reduced with respect to the values given in ported spans greater than 3 m. Tripping brackets attached to
[2.1.1] or the coamings may be omitted entirely, on condi- the flange may be considered as a lateral support for the pri-
tion that the Society is satisfied that the safety of the ship is mary supporting members.
not thereby impaired in any sea conditions.
2.2.5 The covers used in 'tweendecks are to be fitted with
In such cases, the scantlings of the covers, their gasketing, an appropriate system ensuring an efficient stowing when
their securing arrangements and the drainage of recesses in the ship is sailing with open 'tweendecks.
the deck are considered by the Society on a case-by-case
basis. 2.2.6 Efficient retaining arrangements are to be provided to
prevent translation of the hatch covers under the action of
2.1.3 Regardless of the type of closing arrangement the longitudinal and transverse forces exerted by the stacks
adopted, the coamings may have reduced height or be of containers on the covers. These retaining arrangements
omitted in way of openings in closed superstructures or are to be located in way of the hatch coaming side brackets.
decks below the freeboard deck.
Solid fittings are to be welded on the hatch covers where
the corners of the containers are resting. These parts are
2.2 Hatch covers intended to transmit the loads of the container stacks onto
the hatch covers on which they are resting as well as to pre-
2.2.1 Hatch covers on exposed decks are to be weather- vent horizontal translation of the stacks by means of special
tight. However, non-weathertight hatch covers may be fitted intermediate parts arranged between the corner supports
for cargo holds solely dedicated to the transport of contain- and the container corners.
ers, provided they comply with [6.2.2].
Longitudinal stiffeners are to stiffen the hatch cover plates in
Hatch covers in closed superstructures need not be weath- way of these supports and connect the nearest transverse
ertight. stiffeners. Extension is to be calculated to ensure a satisfac-
tory strength.
However, hatch covers fitted in way of ballast tanks, fuel oil
tanks or other tanks are to be watertight.
2.2.7 The width of each bearing surface for hatch covers is
to be at least 65 mm.
2.2.2 Primary supporting members and ordinary stiffeners
of hatch covers are to be continuous over the breadth and
length of hatch covers, as far as practical. When this is 2.3 Hatch coamings
impractical, sniped end connections are not to be used and
appropriate arrangements are to be adopted to ensure suffi- 2.3.1 Coamings, stiffeners and brackets are to be capable
cient load carrying capacity. of withstanding the local forces in way of the clamping
devices and handling facilities necessary to secure and to
2.2.3 The spacing of primary supporting members parallel move the hatch covers, as well as the forces due to the car-
to the direction of ordinary stiffeners is to be not greater goes stowed on the latter.
than 1/3 of the span of primary supporting members. When
strength calculation is carried out by finite element analysis 2.3.2 Special attention is to be paid to the strength of the fore
using plane strain or shell elements, this requirement can be transverse coaming of the foremost hatch and to the scant-
waived. lings of the hatch cover closing devices on this coaming.
2.3.3 The longitudinal coamings are to extend at least to 3 Hatch cover and coaming load model
the lower edge of the deck beams.
Where they are not part of the continuous deck girders, the 3.1 Weather loads
longitudinal coamings are to extend over at least two-frame
spaces beyond the ends of the openings. 3.1.1 Vertical weather design load
The pressure pW, in kN/m, on the hatch cover panels is
Where the longitudinal coamings are part of the continuous given in Tab 2. The vertical weather design load need not
deck girders, their scantlings are to be as required in Ch 7, be combined with the cargo loads defined in [3.2].
Sec 3.
The positions 1 and 2, as specified in Ch 1, Sec 2, [3.22],
are illustrated in Fig 1 for an example ship.
2.3.4 The transverse coamings are to extend below the
deck at least to the lower edge of the longitudinals. When an increased freeboard is assigned, the design load for
hatch covers, as defined in Tab 2, on the actual freeboard
The transverse coamings not in line with the ordinary deck deck may be as required for a superstructure deck, provided
beams are to extend below the deck over at least three lon- the summer freeboard is such that the resulting draught is not
gitudinal frame spaces beyond the side coamings. greater than that corresponding to the minimum freeboard
calculated from an assumed freeboard deck situated at a dis-
2.3.5 Ordinary stiffeners of hatch coamings are to be con- tance at least equal to the standard superstructure height hS
tinuous over the breadth and the length of hatch coamings. below the actual freeboard deck. See Fig 2.
2**
2**
2** 2
2 1* 1*
Freeboard Deck 1 1 1
Tfb
0,25 LLL
Length LLL
* : Reduced load upon exposed superstructure decks located at least one superstructure standard height above the freeboard deck
** : Reduced load upon exposed superstructure decks of ships with LLL > 100 m located at least one superstructure standard height
above the lowest position 2 deck.
2**
2**
2** 2**
2** 2 2 > hN
Actual Freeboard Deck 2 2 1*
Assumed Freeboard Deck
Tfb
0,25 LLL
Length LLL
* : Reduced load upon exposed superstructure decks located at least one superstructure standard height above the freeboard deck
** : Reduced load upon exposed superstructure decks of ships with LLL > 100 m located at least one superstructure standard height
above the lowest position 2 deck.
(1) Upon exposed superstructure decks located at least one superstructure standard height hs above the freeboard deck, the design
load pW may be taken equal to:
14,9 + 0,195 LLL if LLL < 100
34,3 if LLL 100
(2) Upon exposed superstructure decks located at least one superstructure standard height hs above the lowest position 2 deck, the
design load pW may be taken equal to 20,6 kN/m2.
Note 1:
pWP : Pressure, in kN/m2, at the forward perpendicular, to be taken equal to:
49,1 + 0,0726 (LLL 100) for type B ships
49,1 + 0,3560 (LLL 100) for type B-60 or type B-100 ships
x : Longitudinal coordinate, in m, of the assessed structural member mid-point, measured from the aft end of length L or
LLL , as applicable.
Table 3 : Minimum design load pAmin for side and protected front coamings and
hatch cover skirt plates:
PAmin , in kN/m L
L a = 5 + -----3-
For unprotected fronts Elsewhere 15
L 50 30 15 for aft ends of coamings and aft hatch cover
skirt plates abaft amidships:
50 < L < 250 25 + L/10 12,5 + L/20
L3 x
L 250 50 25 - 8 ----
a = 7 + ---------
100 L
for aft ends of coamings and aft hatch cover
3.1.2 Horizontal weather design load
skirt plates forward of amidships:
The horizontal weather design load pA , in kN/m2, for deter-
L3 x
mining the scantlings of outer edge girders (skirt plates) of - 4 ----
a = 5 + ---------
100 L
weather deck hatch covers and of hatch coamings is not to
be taken less than the greater of: c : Coefficient taken equal to 0,3 + 0,7 b/B
with b/B to be taken not less than 0,25
the minimum values pAmin given in Tab 3
b : Breadth of coaming, in m, at the position con-
pA = a c (b cL f z) sidered
where: B : Actual maximum breadth of ship, in m, on the
exposed weather deck at the position considered
a : Coefficient taken equal to:
b : Coefficient taken equal to:
for unprotected front coamings and hatch for x/L < 0,45:
cover skirt plates: 2
x
---- 0, 45
L
b = 1, 0 + ------------------------
L
a = 20 + -----3-
12 C B + 0, 2
for unprotected front coamings and hatch
for x/L 0,45:
cover skirt plates, where the distance from
2
the actual freeboard deck to the summer x
---- 0, 45
b = 1, 0 + 1, 5 ------------------------
load line exceeds the minimum non-cor- L
C B + 0, 2
rected tabular freeboard according to ICLL
by at least one standard superstructure
with 0,6 CB 0,8. When determining scant-
height hs :
lings of aft ends of coamings and aft hatch cover
L skirt plates forward of amidships, CB need not
a = 10 + -----3-
12 be taken less than 0,8
x : Distance, in m, between the transverse coaming V0 : Maximum speed, in knots, at summer load line
or the hatch cover skirt plate considered and aft draught, to be taken not less than L1/2.
end of the length L. When determining side
coamings or side hatch cover skirt plates, the 3.2.2 Concentrated loads
side is to be subdivided into parts of approxi- The loads P, in kN, due to single forces and resulting from
mately equal length, not exceeding 0,15 L each, heave and pitch (e.g. in case of containers), are to be deter-
and x is to be taken as the distance between aft mined as follows:
end of the length L and the centre of each part
P = PS (1 + V)
considered
where:
cL : Coefficient taken equal to:
PS : Single force, in kN
for L< 90 m:
V : Acceleration addition, as defined in [3.2.1].
L
cL = ------
90 3.2.3 Container loads
for L 90 m: Where containers are stowed on hatch covers, the following
loads AZ , BZ and By , in kN, due to heave, pitch and rolling
cL = 1
motion are to be considered (see Fig 3):
f : Wave parameter, taken equal to:
Figure 3 : Forces due to container loads
L
f = ------ + 4, 1 for L < 90m
25
1 ,5
300 L
f = 10 ,75 ------------------- for 90m L < 300m
100
f = 10 ,75 for 300m L 350m
L 350 1 ,5 hm M
f = 10 ,75 ------------------- for L > 350m
150
Note 1: It is recommended to apply, for M and hm , those values 4.2 Permissible stresses and deflections
which are used for the calculations of cargo securing (container
lashing). If different assumptions are made for M and hm , the 4.2.1 Stresses
designer has to verify that, in the calculation model, the hatch cover
structure is not loaded with values less than those recommended. The equivalent stress V in steel hatch cover structures
In case of container stacks secured to lashing bridges or car- related to the net thickness is not to exceed 0,8 ReH , where
ried in cell guides, the forces acting on the hatch cover may ReH is the minimum yield stress of the material, in N/mm2.
be specially considered.
For design loads defined in [3.1.2], [3.2] and [3.3], the
Alternatively, container loads may be applied based on equivalent stress V related to the net thickness is not to
accelerations calculated by an individual acceleration anal- exceed 0,9 ReH when the stresses are assessed by means of
ysis for the lashing system used. finite element analysis using plane stress or shell elements.
3.2.4 Load cases with partial loading For beam element calculations and grillage analysis, the
equivalent stress V, in N/mm2, may be taken as follows:
The loads defined in [3.2.1], [3.2.2] and [3.2.3] are also to
be considered for partial non homogeneous loading which 2 2
V = + 3
may occur in practice, e.g. where specified container stack
places are empty. where:
The load case partial loading of container hatch covers can : Normal stress, in N/mm2
be evaluated using a simplified approach, where the hatch
cover is loaded without the outermost stacks (see Fig 4). : Shear stress, in N/mm2.
where:
x : Normal stress, in N/mm2, in x-direction
y : Normal stress, in N/mm2, in y-direction
: Shear stress, in N/mm2, in the x-y plane.
Indices x and y are coordinates of a two-dimensional
Cartesian system in the plane of the considered struc-
tural element.
In case of finite element analysis using shell or plane
strain elements, the stresses are to be read from the cen-
3.3 Global loads tre of the individual element. Where shell elements are
used, the stresses are to be evaluated at the mid plane of
3.3.1 Loads due to elastic deformations of the hull the element.
Hatch covers which are, in addition to the loads defined in
[3.1] and [3.2], loaded in the ship's transverse direction by 4.2.2 Deflection
forces due to elastic deformations of the hull, are to be The vertical deflection of primary supporting members due
designed such that the sum of stresses does not exceed the to the vertical weather design load defined in [3.1.1] is to
permissible values given in [4.2.1].
be not more than g ,
4.1.1 Hatch covers supporting wheeled loads for weathertight hatch covers:
The scantlings of hatch covers supporting wheeled loads are = 0,0056
to be obtained in accordance with the applicable require-
for pontoon hatch covers and portable beams:
ments of:
Ch 7, Sec 1, for plating = 0,0044
Ch 7, Sec 2, or by direct calculations under considera- Note 1: Where hatch covers are arranged for carrying containers
and mixed stowage is allowed, i.e. a 40'-container stowed on top
tion of the permissible stresses given in [4.2.1], for ordi-
of two 20'-containers, particular attention is to be paid to the
nary stiffeners deflections of hatch covers. Further the possible contact of
Ch 7, Sec 3, for primary supporting members. deflected hatch covers with in hold cargo is to be observed.
4.3 Plating 4.3.2 Lower plating of double skin hatch covers and
box girders
4.3.1 Local net plate thickness The thickness to fulfill the strength requirements is to be
The local net plate thickness t, in mm, of the hatch cover obtained from the calculations according to [4.5] under
top plating is not to be less than the greater of: consideration of the permissible stresses defined in [4.2.1].
hw 235
------ 15 ---------
-
tw R eH
where:
Stiffeners parallel to primary supporting members and 4.4.4 Ordinary stiffeners and primary supporting
arranged within the effective breadth according to [4.5.2] members of variable cross-section
are to be continuous at crossing primary supporting mem- The net section modulus of ordinary stiffeners and primary
bers and may be regarded for calculating the cross-sectional supporting members with a variable cross-section is to be
properties of primary supporting members. It is to be veri- not less than the greater of the values obtained, in cm3, from
fied that the combined stress of those stiffeners induced by the following formulae:
the bending of primary supporting members and lateral
pressures does not exceed the permissible stresses defined w = w CS
in [4.2.1]. 3 ,2 0 ,8
w = 1 + ------------------------------------- w CS
7 + 0 ,4
For hatch cover stiffeners under compression, sufficient
safety against lateral and torsional buckling according to where:
[5.3.5] and [5.3.6] is to be verified. wCS : Net section modulus, in cm3, for a constant
cross-section, obtained according to [4.4.1]
4.4.2 Net scantlings of primary supporting
members = ----1
0
Scantlings of primary supporting members are obtained w
= ------1
from the calculations according to [4.5] under considera- w0
tion of the permissible stresses defined in [4.2.1].
1 : Length of the variable section part, in m (see Fig 6)
For all components of primary supporting members, suffi- 0 : Span measured, in m, between end supports
cient safety against buckling is to be verified according to (see Fig 6)
[5]. For biaxial compressed flange plates, this is to be veri-
fied within the effective widths according to [5.3.3]. w1 : Net section modulus at end, in cm3 (see Fig 6)
w0 : Net section modulus at mid-span, in cm3 (see
The net thickness, in mm, of webs of primary supporting Fig 6).
members is not to be less than the greater of:
Moreover, the net moment of inertia of ordinary stiffeners
t = 6,5 s and primary supporting members with a variable cross-sec-
tion is to be not less than the greater of the values obtained,
tmin = 5 mm. in cm4, from the following formulae:
I = ICS
4.4.3 Edge girders (skirt plates)
1
I = 1 + 8 -------------------------- I CS
3
Scantlings of edge girders are obtained from the calcula- 0 ,2 + 3
tions according to [4.5] under consideration of the permissi-
ble stresses defined in [4.2.1]. where:
The net thickness, in mm, of the outer edge girders exposed ICS : Net moment of inertia with a constant cross-
to wash of sea is not to be less than the greatest of: section, in cm4, calculated with wave pressure,
as given in [3.1.1] or distributed load as given in
pA [3.2.1]. It is to be such that the deflection does
t = 15, 8 s ---------------------
- not exceed ( ), with as defined in [4.2.2]
0, 95R eH
I
t = 8,5 s = ---1
I0
tmin = 5 mm, I1 : Net moment of inertia at end, in cm4 (see Fig 6)
I0 : Net moment of inertia at mid-span, in cm4 (see
where:
Fig 6).
pA : Horizontal pressure, in kN/m2, as defined in The use of these formulae are limited to the determination
[3.1.2]. of the strength of ordinary stiffeners and primary supporting
members in which abrupt changes in the cross-section do
The stiffness of edge girders is to be sufficient to maintain
not occur along their length.
adequate sealing pressure between securing devices. The
moment of inertia I, in cm4, of edge girders is not to be less
Figure 6 : Variable cross-section stiffener
than:
I = 6 q sSD4
w1
where:
11 w0
q : Packing line pressure, in N/mm, to be taken not
less than 5 N/mm
1 10
0
sSD : Spacing, in m, of securing devices.
/e 0 1 2 3 4 5 6 7 8
em1 0 0,36 e 0,64 e 0,82 e 0,91 e 0,96 e 0,98 e 1,00 e 1,00 e
em2 0 0,20 e 0,37 e 0,52 e 0,65 e 0,75 e 0,84 e 0,89 e 0,90 e
Note 1:
: Length of zero-points of bending moment curve:
= 0 for simply supported primary supporting members
= 0,6 0 for primary supporting members with both ends constraint,
0 :
Unsupported length of the primary supporting member
e :
Width of plating supported, measured from centre to centre of the adjacent unsupported fields
em1 :
To be applied where primary supporting members are loaded by uniformly distributed loads or else by not less than
6 equally spaced single loads
em2 : To be applied where primary supporting members are loaded by 3 or less single loads.
Note 2: Intermediate values may be obtained by direct interpolation.
e : Reference stress, in N/mm2, taken equal to: x = (x* 0,3 y*) / 0,91
e = 0,9 E (t/b) 2
y = (y* 0,3 x*) / 0,91
: Edge stress ratio taken equal to 1 / 2 with:
1 : Maximum compressive stress, in N/mm2 x*, y* : Stresses containing the Poisson-effect.
2 : Minimum compressive stress or tension stress, Where the compressive stress fulfils the condition:
in N/mm2
y* < 0,3 x*, then:
S : Safety factor (based on net scantling approach),
taken equal to: y = 0 and x = x*
S = 1,25 for hatch covers when subjected to x* < 0,3 y*, then:
the vertical weather design load according x = 0 and y = y*
to [3.1.1]
S = 1,10 for hatch covers when subjected to 5.2.3 Webs and flanges of primary supporting
loads according to [3.1.2], [3.2] and [3.3] members
: Reference degree of slenderness, taken equal to: For non-stiffened webs and flanges of primary supporting
members, sufficient buckling strength as for the hatch cover
R eH top and lower plating is to be demonstrated according to
= --------
-
K e [5.2.1].
x S e1 y S e2 x y S2 S 3
e3 The effective width of attached plating of ordinary stiffeners,
-------------
- + -------------- B ----------------
- + ----------------- 1, 0
x R eH y R eH R 2 R eH to be considered for buckling assessment, may be deter-
eH
mined by the following formulae (see also Fig 7):
where: for longitudinal stiffeners: bm = x b
e1 = 1 + x 4
for transverse stiffeners: am = y a
e2 = 1 + y 4
The effective width of attached plating is not to be taken
e3 = 1 + x y 2 greater than the value obtained from [4.5.2].
B : Factor taken equal to:
Figure 7 : General arrangement of panel
for x and y positive (compression stress):
Longitudinal
B = (x y)5 stiffener Single field Partial field
Table 6 : Buckling factor K and reduction factor for plane elementary plate panels
t >
.N .N
0 > > 1 1 K = 7, 63 ( 6, 26 10 ) where:
c = ( 1, 25 0, 12 ) 1, 25
0, 88
c = --- 1 + 1 -------------
1 K = 5, 975 ( 1 )
2 c
2 c
2 1 R + F (H R)
2
y = c --- ------------------------------------
-
2
2, 1
K = F 1 1 + -----2 -------------------------
1
2
10 1
O
.O ( + 1, 1 )
where:
J >
c = ( 1, 25 0, 12 ) 1, 25
2, 1 ( 1 + )
2
K = F 1 1 + -----2 ---------------------------- -----2 ( 13, 9 10 )
1 R = ( 1 c ) for < c
1 1, 5
O .O 1, 1
.>
R = 0, 22 for c
0 > > 1
2, 1 ( 1 + )
2
K = F 1 1 + -----2 ----------------------------
1
0, 88
c = --- 1 + 1 -------------
c
1, 1
> 1, 5 2 c
8, 6
-----2 5, 87 + 1, 87 + --------
- 10
2
2
F = c 1 1 ------------- 1 p 0
K 2
0, 91
3(1 ) 1 2
1 ---------------------- K = 5, 975 F 1 ------------- 2 2
p = 0, 5 for 1 p 3
2
4
c1 = (1 F1/) 0
1
2
H = --------------------------------------- R
2
3(1 ) 1 2
1 4 c (T + T 4)
> ---------------------- K = F 1 3, 9675 ------------- + 0, 5375 ------------- + 1, 87
4
14 1
T = + ---------- + ---
15 3
3
K = 4 0, 425 + -----2 ( 3 + 1 )
1
10
.>
N N
>0
t >
K = 4 0, 425 + -----2- ( 1 + ) 5 ( 1 3, 42 )
1
0 > 1 x = 1 for 0, 7
.N .N
4 1
x = ------------------------
2
for > 0.7
+ 0, 51
1 3
K = 0, 425 + -----2 -------------
t b 1 1 >0 2
x x
5 K = K 3
= 1 for 0, 84
4
1 K = 5, 34 + -----2
J >
0, 84
5, 34 = ------------- for > 0, 84
0<<1 K = 4 + ------------
-
.>
2
b < em
em = n bm am
n = int (em / b) a
am and bm for flange plates are in general to be determined The stress distribution between two primary supporting
for = 1. members can be obtained by the following formula:
y y
Figure 8 : Stiffening parallel x ( y ) = x1 1 --- 3 + c 1 4c 2 2 --- ( 1 + c 1 2c 2 )
e e
to web of primary supporting members
where:
e
em x2
c 1 = ------- with 0 c 1 1
x1
em
1, 5
c 2 = --------- ( e m1 + e m2 ) 0, 5
e
appropriate
x,e m(y)
5.3.5 Lateral buckling of ordinary stiffeners Ix, Iy : Net moments of inertia, in cm4, of the longitudi-
The longitudinal and transverse ordinary stiffeners are to nal or transverse stiffener including effective
comply with the following criteria: width of attached plating according to [5.3.2].
Ix and Iy are to comply with the following crite-
a + b
------------------- S1 ria:
R eH
3
bt
where: I x -------------------4-
12 10
a : Uniformly distributed compressive stress, in
3
N/mm2, in the direction of the stiffener axis: at
I y -------------------4-
for longitudinal stiffeners: a = x 12 10
b 2
p zx = --- xl -------- + 2c y y + 2 1
M0 + M1 t
b = --------------------
3
-
b a
w st 10
m m
M1 : Bending moment, in Nmm, due to the lateral 1 = t R eH E ------2-1 + ------2-2 0
load p, taken equal to: a b
for longitudinal stiffeners: m1 , m2 : Coefficients taken equal to:
pba
2 for longitudinal stiffeners:
M 1 = --------------------3
24 10 if a/b 2,0: m1 = 1,47 and m2 = 0,49
for transverse stiffeners: if a/b < 2,0: m1 = 1,96 and m2 = 0,37
pa ( nb )
2
for transverse stiffeners:
M 1 = --------------------
3
-
8c s 10 if a/(nb) 0,5: m1 = 0,37 and m2 = 1,96/n2
with n to be taken equal to 1 for ordinary if a/(nb) < 0,5: m1 = 0,49 and m2 = 1,47/n2
transverse stiffeners
= 0 + 1
p : Lateral load, in kN/m2
0 : Assumed imperfection, in mm
FKi : Ideal buckling force, in N, of the stiffener, taken
equal to: for longitudinal stiffeners:
3 10 3
3 3 3
hw tw tw h w tw tw bf tf t
IT ---------------
-4 1 0, 63 -----
- ---------------
-4 1 0, 63 ----- - 1 0, 63 ----f
- + ---------------
3 10 hw 3 10 h w 3 10 4 bf
3 3 2 2 3 2
hw tw A f e f b f A f + 2, 6A w bf tf e f
I -------------------
- --------------------6- ---------------------------- -------------------
-
12 10 A f + A w
6 6
36 10 12 10
Note 1: bf bf bf tf
hw : Web height, in mm
tw : Net web thickness, in mm
tw tw tw tw
bf : Flange breadth, in mm
tf : Net flange thickness, in mm ef b1 b1 b2
hw
Aw : Net web area, in mm2, equal to: Aw = hw tw
Af : Net flange area, in mm2, equal to: Af = bf tf ta
C C C C
ef : Distance, in mm, equal to: ef = hw + tf / 2
Ip : Net polar moment of inertia of the stiffener, in The packings are to be compressed so as to give the neces-
cm4, defined in Tab 7 and related to the point C sary tightness effect for all expected operating conditions.
IT : Net St. Venant's moment of inertia of the stiff- Special consideration is to be given to the packing arrange-
ment in ships with large relative movements between hatch
ener, in cm4, defined in Tab 7
covers and coamings or between hatch cover sections.
I : Net sectorial moment of inertia of the stiffener, in
cm6, defined in Tab 7 and related to the point C If necessary, suitable devices are to be fitted to limit such
movements.
: Degree of fixation, taken equal to:
Coamings and steel parts of hatch covers in contact with
4
a 3 gaskets are to have no sharp edges.
= 1 + ----------------------------------------- 10
3 4 b 4h w
--- I ---3 + --------- - Metallic contact is required for an earthing connection
4 t 3t
3
w
between the hatch cover and the hull structures. If neces-
h w , tw : As defined in Tab 7. sary, this is to be achieved by means of a special connection
for the purpose.
5.3.7 Torsional buckling of transverse ordinary
stiffeners 6.2.2 Dispensation of weathertight gaskets
For transverse ordinary stiffeners loaded by compressive For hatch covers of cargo holds solely for the transport of
stresses and which are not supported by longitudinal stiffen- containers, upon request by the Owner and subject to com-
ers, sufficient torsional buckling strength is to be demon- pliance with the following conditions, the fitting of weather-
strated analogously in accordance with [5.3.6]. tight gaskets according to [6.2.1] may be dispensed:
The hatchway coamings are to be not less than 600 mm
6 Weathertightness in height.
The exposed deck on which the hatch covers are located
6.1 Weathertightness is situated above a depth H(x). H(x), in m, is to be shown
to comply with the following criterion:
6.1.1 Where the hatchway is exposed, the weathertightness
is to be ensured by gaskets and clamping devices sufficient H(x) T + fb + h
in number and quality.
where:
Weathertightness may also be ensured by means of tarpau-
fb : Minimum required freeboard, in m, deter-
lins.
mined according to ICLL Reg.28, as amended
6.1.2 In general, a minimum of two securing devices or h : Distance, in m, taken equal to:
equivalent is to be provided on each side of the hatch cover.
- for x / LLL 0,75: h = 2 hs
10sp
A Sh = ------------------A
R eH
where:
: Ordinary stiffener span, in m, to be taken as the
spacing of coaming stays.
For sniped stiffeners at coaming corners, the section modu- 9 Closing arrangements
lus and shear area at the fixed support are to be increased
by 35%. The gross thickness of the coaming plate, in mm, at
the sniped stiffener end is to be not less than: 9.1 Securing devices
p A s ( 0, 5 s ) 9.1.1 General
t = 19, 6 ----------------------------------
-
R eH Securing devices between cover and coaming and at cross-
joints are to be installed to provide weathertightness. Suffi-
Horizontal stiffeners on hatch coamings, which are part of cient packing line pressure is to be maintained.
the longitudinal hull structure, are to be designed according
to the applicable requirements in Ch 7, Sec 2. Securing devices are to be appropriate to bridge displace-
ments between cover and coaming due to hull deforma-
tions.
8.3.3 Coaming stays
Securing devices are to be of reliable construction and
Coaming stays are to be designed for the loads transmitted
effectively attached to the hatchway coamings, decks or
through them and permissible stresses according to [4.2.1].
covers. Individual securing devices on each cover are to
have approximately the same stiffness characteristics.
8.3.4 Coaming stay section modulus
Sufficient number of securing devices is to be provided at
For coamings having a height hs less than 1,6 m and each side of the hatch cover considering the requirements
designed for the load pA , the net section modulus w of of [4.4.3]. This applies also to hatch covers consisting of
coaming stays, in cm3, is to be not less than: several parts.
9.1.5 Materials
The materials of stoppers, securing devices and their weld-
ings are to comply with the applicable requirements of Ch 4,
Sec 1 and Part B, Chapter 11 respectively. Specifications of
the materials are to be shown in the drawings of the hatch AZ AZ AZ AZ B AZ B
covers. BZ BZ BZ Z Z
9.1.6 Cleats
Lifting force
Where rod cleats are fitted, resilient washers or cushions
are to be incorporated.
Where hydraulic cleating is adopted, a positive means is to 9.2 Hatch cover supports, stoppers and
be provided so that it remains mechanically locked in the supporting structures
closed position in the event of failure of the hydraulic sys-
tem. 9.2.1 Horizontal forces
For the design of the securing devices against shifting, the
9.1.7 Cross-sectional area of the securing devices horizontal force Fh , in kN, to be considered is given by the
following formula:
The gross cross-sectional area, in cm2, of the securing
devices is not to be less than: Fh = m
where:
A = 0, 28 qs SD k
: Acceleration taken equal to:
where: in longitudinal direction: X = 0,2 g
in transverse direction: Y = 0,5 g
q : Packing line pressure, in N/mm, to be taken not
less than 5 N/mm m : Sum of mass of cargo lashed on the hatch cover
and mass of hatch cover, in t.
sSD : Spacing between securing devices, in m, to be
taken not less than 2 m 9.2.2 Hatch cover supports
For the transmission of the support forces resulting from the
e
k = ( 235 R eH ) load cases specified in [3] and of the horizontal mass forces
specified in [9.2.1], supports are to be provided which are
ReH : Minimum yield strength of the material, in to be designed such that the nominal surface pressures, in
N/mm2, without being taken greater than 0,7 Rm N/mm2, do not exceed in general the following values:
Rm : Tensile strength of the material, in N/mm2 pn max = d pn
The permissible stress in stoppers and their substructures, in 10.1.5 If a continuous outer steel contact between cover
the cover, and of the coamings is to be determined accord- and ship structure is arranged, drainage from the space
ing to [4.2.1]. In addition, the provisions in [9.2.2] are to be between the steel contact and the gasket is also to be pro-
observed. vided for.
1.3.1 Steel 2.2.2 Coamings and steel parts of hatch covers in contact
Materials used for the construction of steel small hatch cov- with gaskets are to have no sharp edges.
ers are to comply with the applicable requirements of
NR216 Materials and Welding, Chapter 2. 2.2.3 For non-bolted hatch covers, metal-to-metal contacts
are to be provided in order to prevent over compression of
1.3.2 Other materials the gasket. They are to be designed in order to withstand the
The use of materials other than steel is considered by the bearing force induced by any relevant lateral load on the
Society on a case-by-case basis, by checking that criteria hatch cover.
adopted for scantlings are such as to ensure strength and
stiffness equivalent to those of steel hatch covers. 3 Small hatches fitted on the exposed
fore deck
2 Small hatches fitted on exposed
decks 3.1 Application
2.1 General 3.1.1 Small hatches designed for emergency escape need
not comply with the requirements in [3.4.1], items a) and
2.1.1 Hatch covers on exposed decks are to be weather- b), [3.4.3] and [3.5.1].
tight.
Securing devices of hatches designed for emergency escape
2.1.2 The height of small hatch coamings is to be not less are to be of a quick-acting type (e.g. one action wheel han-
than 600 mm if located in position 1, and 450 mm if dles are provided as central locking devices for latch-
located in position 2. ing/unlatching of hatch cover) operable from both sides of
the hatch cover.
Where the closing appliances are secured weathertight by
gaskets and swing bolts, the height of the coamings may be
reduced or the coamings may be omitted altogether. 3.2 Strength
2.1.3 In any case the gross thickness of covers is to be not 3.2.1 The gross thickness of covers is to be not less than
less than that of the adjacent plating, based on the same that of the adjacent plating based on the same spacing and
spacing and the same steel. the same steel.
3.2.2 For small rectangular steel hatch covers, the gross plate 3.4.2 The primary securing method is to be designed and
thickness, stiffener arrangement and scantlings are to be not manufactured such that the designed compression pressure
less than those obtained, in mm, from Tab 1 and Fig 1. is achieved by one person without the need of any tools.
Ordinary stiffeners, where fitted, are to be aligned with the
metal-to-metal contact points, required in [3.3.1] (see also 3.4.3 For a primary securing method using butterfly nuts,
Fig 1). the forks (clamps) are to be of robust design. They are to be
Primary stiffeners are to be continuous. designed to minimize the risk of butterfly nuts being dis-
All stiffeners are to be welded to the inner edge stiffener lodged while in use by means of curving the forks upwards,
(see Fig 2). a raised surface on the free end, or a similar method. The
plate thickness of unstiffened steel forks is to be not less
Table 1 : Gross scantlings for than 16 mm. An example arrangement is shown in Fig 2.
small steel hatch covers on the fore deck
Primary Ordinary
3.4.4 For small hatch covers located on the exposed deck
Cover plate
Nominal size stiffeners stiffeners forward of the foremost cargo hatch, the hinges are to be fit-
thickness
(mm x mm) ted such that the predominant direction of green seas is to
(mm) Flat bar (mm x mm) ; number
cause the cover to close, which means that the hinges are
630 x 630 8 normally to be located on the fore edge.
630 x 830 8 100 x 8 ; 1
830 x 630 8 100 x 8 ; 1 3.4.5 On small hatches located between the main hatches,
for example between Nos. 1 and 2, the hinges are to be
830 x 830 8 100 x 10 ; 1
placed on the fore edge or outboard edge, whichever is
1030 x 1030 8 120 x 12 ; 1 80 x 8 ; 2 practicable for protection from green water in beam sea and
1330 x 1330 8 150 x 12 ; 2 100 x 10 ; 2 bow quartering conditions.
1 : Butterfly nut
2 : Bolt
3 : Pin
4 : Centre of pin
5 : Fork (clamp) plate
6 : Hatch cover
7 : Gasket
8 : Hatch coaming
9 : Bearing pad welded on the bracket of a toggle bolt for metal to metal contact
10 : Stiffener
11 : Inner edge stiffener.
The gross scantlings are obtained as specified in Ch 4, Sec 2. PP : Mass of the movable deck, in kN
PV : Mass of a vehicle, in kN
nV : Maximum number of vehicles loaded on the
1.4 Plating movable deck
AP : Effective area of the movable deck, in m2.
1.4.1 The net thickness of plate panels subjected to
wheeled loads is to be not less than the value obtained from 1.6.3 Lateral pressure
Ch 7, Sec 1, [4.3], where nP0 is not to be taken less than The lateral pressure is constituted by still water pressure and
inertial pressure. The lateral pressure is to be obtained, in
5 kN.
kN/m2, from the following formula:
p = S2 pS + W2 pW
1.5 Ordinary stiffeners where:
S2, W2 : Partial safety factors defined in Ch 7, Sec 3,
1.5.1 The net section modulus and the net shear sectional [1.4]
area of ordinary stiffeners subjected to wheeled loads is to pS, pW : Still water and inertial pressures transmitted to
be not less than the value obtained from Ch 7, Sec 2, the movable deck or inner ramp structures,
[3.7.5]. obtained, in kN/m2, from Tab 1.
Table 1 : Movable decks and inner ramps 1.7.2 It is to be checked that the combined stress VM in
Still water and inertial pressures rigid supports and locking devices is in accordance with the
criteria defined in Ch 7, Sec 3, [4.4.2].
Ship Load Still water pressure pS and
condition case inertial pressure pW, in kN/m2
1.8 Tests and trials
Still water pS = p0 in harbour condition during lifting
condition pS = p0 + p1 in other cases 1.8.1 Tests and trials defined in [1.8.2] to [1.8.4] are to be
Upright a No inertial pressure carried out in the presence of the Surveyor. Upon special
sea request, these conditions of tests and trials may be modified
b a X1
condition p W ,X = ------- ( p0 + p1 ) in x direction to comply with any relevant national regulations in use.
g
a Z1
p W ,Z = ------- ( p 0 + p 1 ) in z direction 1.8.2 The wire ropes are to be submitted to a tensile test on
g
test-piece.
Inclined c C FA a Y2
sea p W ,Y = ----------------
- ( p0 + p1 ) in y direction 1.8.3 The loose gears used for the platform and ramp han-
g
condition dling (chain, shackles, removable blocks, etc.) are to have a
d C FA a Z2
(negative p W ,Z = ----------------
- ( p 0 + p 1 ) in z direction maximum safe working load (SWL) and are to be submitted
roll angle) g
to an individual test before fitting on board.
Harbour during pW,X = 0,035 p0 in x direction The test of these loose gears are to be in accordance with
condition lifting pW,Y = 0,087 p0 in y direction the applicable requirements of Rule Note NR 184: Rules for
(1) pW,Z = 0,200 p0 in z direction the construction and certification of lifting appliances.
at rest pW,X = 0,035 (p0 + p1) in x direction
pW,Y = 0,087 (p0 + p1) in y direction 1.8.4 A trial to verify the correct operation of lowering and
pW,Z = 0,100 (p0 + p1) in z direction lifting devices of the platform is to be carried out before
going into service.
(1) For harbour conditions, a heel angle of 5 and a trim
angle of 2 are taken into account. This trial is made without overload unless special require-
Note 1: ment of National Authorities.
p 0, p 1 : Pressures, in kN/m2, to be calculated according
to [1.6.2] for the condition considered. 2 External ramps
: Coefficient taken equal to 0,5
CFA : Combination factor, to be taken equal to:
CFA = 0,7 for load case c 2.1 General
CFA = 1,0 for load case d
2.1.1 The external ramps are to be able to operate with a
1.6.4 Checking criteria heel angle of 5 and a trim angle of 2.
It is to be checked that the combined stress VM is in accord-
ance with the criteria defined in Ch 7, Sec 3, [4.4.2]. 2.1.2 The net thicknesses of plating and the net scantlings
of ordinary stiffeners and primary supporting members are
1.6.5 Allowable deflection to be determined under vehicle loads in harbour condition,
The scantlings of main stiffeners and the distribution of sup- at rest, as defined in Tab 1.
ports are to be such that the deflection of the loaded mova-
ble deck or loaded inner ramp does not exceed 5 mm/m. 2.1.3 The external ramps are to be examined for their
watertightness, if applicable.
1.7 Supports, suspensions and locking
devices 2.1.4 The locking of external ramps in stowage position at
sea is examined by the Society on a case by case basis.
1.7.1 Scantlings of wire suspensions are to be determined
by direct calculation on the basis of the loads in [1.6.2] and 2.1.5 The ships structure under the reactions due to the
[1.6.3], taking account of a safety factor at least equal to 5. ramp is examined by the Society on a case by case basis.
2.1.3 No openings, be they permanent openings, recessed 3.1.6 Means of closing and opening
promenades or temporary openings such as shell doors, The arrangement and efficiency of the means for closing
windows or ports, are allowed on the side shell between the any opening in the shell plating are to be consistent with its
embarkation station of the marine evacuation system and intended purpose and the position in which it is fitted is to
the waterline in the lightest seagoing condition. Windows be generally to the satisfaction of the Society.
and sidescuttles of the non-opening type are allowed if
complying with Pt C, Ch 4, Sec 5, [3.2.3], item c). 3.1.7 Opening of sidescuttles
2.1.4 Other closing appliances which are kept permanently All sidescuttles, the sills of which are below the bulkhead
closed at sea to ensure the watertight integrity of external deck for passenger ships or the freeboard deck for cargo
openings are to be provided with a notice affixed to each ships, are to be of such construction as to prevent effec-
appliance to the effect that it is to be kept closed. Manholes tively any person opening them without the consent of the
fitted with closely bolted covers need not be so marked. Master of the ship.
3.3.4 Thickness of monolithic window 3.3.7 Thickness of glasses forming screen bulkheads
The thicknesses, in mm, of monolithic windows and side- or internal boundaries of deckhouses
scuttles are to be obtained from the following formula: The thickness of glasses forming screen bulkheads on the
rectangular window or sidescuttle: side of enclosed promenade spaces and that for rectangular
windows in the internal boundaries of deckhouses which
pS
t = 27, 4s -----------f are protected by such screen bulkheads are considered by
Rm
the Society on a case by case basis.
circular window or sidescuttle:
The Society may require both limitations on the size of rec-
pS tangular windows and the use of glasses of increased thick-
t = 17, 4d --------f
Rm ness in way of front bulkheads which are particularly
exposed to heavy sea.
where:
s : Shorter side, in m, of rectangular window or
sidescuttle 3.4 Deadlight arrangement
: Longer side, in m, of rectangular window or
side scuttle 3.4.1 General
d : Diameter, in m, of circular window or sidescuttle Sidescuttles to the following spaces are to be fitted with effi-
Rm : Guaranteed minimum flexural strength, in cient, hinged inside deadlights:
N/mm2, of material used. For guidance only, the spaces below the freeboard deck
guaranteed minimum flexural strength Rm for
spaces within the first tier of enclosed superstructures
glass window is:
for glass thermally tempering (toughened): first tier deckhouses on the freeboard deck protecting
openings leading below or considered buoyant in stabil-
Rm = 150 N/mm2
ity calculations.
for glass chemically toughened:
Deadlights are to be capable of being closed and secured
Rm = 200 N/mm2
watertight if fitted below the freeboard deck and weather-
Sf : Safety factor taken equal to 5,0 tight if fitted above.
: Aspect ratio coefficient of the rectangular win-
dow or sidescuttle, obtained in Tab 1.
3.4.2 Watertight deadlights
The thickness of semi-circular windows may be obtained,
considering an equivalent rectangular shape with: Efficient hinged inside deadlights, so arranged that they can
be easily and effectively closed and secured watertight, are
s = d/2
to be fitted to all sidescuttles except that, abaft one eighth of
/s = 2. the ship's length from the forward perpendicular and above
a line drawn parallel to the bulkhead deck at side and hav-
Table 1 : Coefficient
ing its lowest point at a height of (3,7+0,025B) m above the
deepest subdivision summer load line, the deadlights may
/s be portable in passenger accommodation other than that
1,0 0,284 for steerage passengers, unless the deadlights are required
1,5 0,475 by the International Convention on Load Lines in force to be
permanently attached in their proper positions. Such porta-
2,0 0,608
ble deadlights are to be stowed adjacent to the sidescuttles
2,5 0,684 they serve.
3,0 0,716
3,5 0,734 3.4.3 Openings at the side shell in the second tier
4,0 0,750
Sidescuttles and windows at the side shell in the second
3.3.5 Thickness of laminated window tier, protecting direct access below or considered buoyant
in the stability calculations, are to be provided with effi-
Laminated windows are glass windows realized by placing
cient, hinged inside deadlights capable of being effectively
a layer of resin (polyvinyl butyral as a general rule) between
closed and secured weathertight.
two sheets of glass.
The thickness of laminated window is to be calculated as
defined in [3.3.4], considering the total thickness of the 3.4.4 Openings set inboard in the second tier
laminated window as a monolithic window. Sidescuttles and windows set inboard from the side shell in
the second tier, protecting direct access below to spaces
3.3.6 Thickness of double windows listed in [3.4.1], are to be provided with either efficient,
Double windows are glass windows realized by two sheets hinged inside deadlights or, where they are accessible, per-
of glass, separated by a spacebar hermetically sealed. manently attached external storm covers of approved
The thickness of the outside glass exposed to loads is to be design and substantial construction capable of being effec-
calculated as defined in [3.3.4]. tively closed and secured weathertight.
Cabin bulkheads and doors in the second tier separating 4.2.2 Inboard end below the waterline
sidescuttles and windows from a direct access leading Where the inboard end of a garbage chute is below the free-
below may be accepted in place of fitted deadlights or board deck of a passenger ship, or the waterline corre-
storm covers. sponding to the deepest draught after damage in a cargo
Note 1: Deadlights in accordance with recognised standards are ship of more than 100 m in length, then:
fitted to the inside of windows and sidescuttles, while storm covers
of comparable specifications to deadlights are fitted to the outside the inboard end hinged cover/valve is to be watertight
of windows, where accessible, and may be hinged or portable. the valve is to be a screw-down non-return valve fitted
in an easily accessible position above the deepest subdi-
3.4.5 Deckhouses on superstructures of less than vision load line
standard height
the screw-down non-return valve is to be controlled
Deckhouses situated on a raised quarterdeck or on a super- from a position above the bulkhead deck and provided
structure of less than standard height may be treated as with open/shut indicators. The valve control is to be
being on the second tier as far as the provision of deadlights clearly marked: Keep closed when not in use.
is concerned, provided the height of the raised quarterdeck
or superstructure is not less than the standard quarterdeck
height. 4.2.3 Gate valves
For garbage chutes, two gate valves controlled from the work-
3.4.6 Openings protected by a deckhouse ing deck of the chute may be accepted instead of a non-
Where an opening in a superstructure deck or in the top of return valve with a positive means of closing it from a position
a deckhouse on the freeboard deck which gives access to a above the freeboard deck. In addition, the lower gate valve is
space below the freeboard deck or to a space within an to be controlled from a position above the freeboard deck. An
enclosed superstructure is protected by a deckhouse, then it interlock system between the two valves is to be arranged.
is considered that only those sidescuttles fitted in spaces The distance between the two gate valves is to be adequate
which give direct access to an open stairway need to be fit- to allow the smooth operation of the interlock system.
ted with deadlights.
4.2.4 Hinged cover and discharge flap
4 Discharges The upper gate valve, as required in [4.2.3], may be
replaced by a hinged weathertight cover at the inboard end
of the chute together with a discharge flap which replaces
4.1 Arrangement of discharges
the lower gate valve.
4.1.1 Inlets and discharges The cover and discharge flap are to be arranged with an
All inlets and discharges in the shell plating are to be fitted interlock so that the flap cannot be operated until the hop-
with efficient and accessible arrangements for preventing per cover is closed.
the accidental admission of water into the ship.
4.2.5 Marking of valve and hinged cover
4.1.2 Inboard opening of ash-chute, rubbish-chute,
etc. The gate valve controls and/or hinged cover are to be
clearly marked: Keep closed when not in use.
The inboard opening of each ash-chute, rubbish-chute, etc.
is to be fitted with an efficient cover.
If the inboard opening is situated below the bulkhead deck 4.3 Scantlings of garbage chutes
for passenger ships or the freeboard deck for cargo ships,
the cover is to be watertight, and in addition an automatic 4.3.1 Material
non-return valve is to be fitted in the chute in an easily
The chute is to be constructed of steel. Other equivalent
accessible position above the deepest subdivision summer
materials are considered by the Society on a case by case
load line. When the chute is not in use, both the cover and
basis.
the valve are to be kept closed and secured.
4.3.2 Wall thickness
4.2 Arrangement of garbage chutes The wall thickness of the chute up to and including the
cover is to be not less than that obtained, in mm, from Tab 2.
4.2.1 Inboard end above the waterline
The inboard end is to be located above the waterline Table 2 : Wall thickness of garbage chutes
formed by an 8,5 heel, to port or starboard, at a draught
corresponding to the assigned summer freeboard, but not External diameter d, in mm Thickness, in mm
less than 1000 mm above the summer load waterline.
d 80 7,0
Where the inboard end of the garbage chute exceeds 0,01L
above the summer load waterline, valve control from the 80 < d< 180 7,0 + 0,03 (d 80)
freeboard deck is not required, provided the inboard gate 180 d 220 10,0 + 0,063 (d 180)
valve is always accessible under service conditions.
d > 220 12,5
However, bulwarks may not have substantial openings or 6.2.2 Minimum freeing port area for a deckhouse
accesses near the breaks of superstructures, unless they are having breadth not less than 0,8 B
effectively detached from the superstructure sides.
Where a flush deck ship is fitted amidships with a deck-
6.1.4 Freeing port positioning house having breadth not less than 0,8 B and the width of
the passageways along the side of the ship less than 1,5 m,
The lower edge of freeing ports is to be as near the deck as
practicable. the freeing port area is to be calculated for two separate
wells, before and abaft the deckhouse. For each of these
All the openings in the bulwark are to be protected by rails wells, the freeing port area is to be obtained from Tab 4,
or bars spaced approximately 230 mm apart.
where B is to be taken equal to the actual length of the well
considered.
6.1.5 Freeing port closures
If shutters or closures are fitted to freeing ports, ample clear-
ance is to be provided to prevent jamming. Hinges are to 6.2.3 Minimum freeing port area for screen bulkhead
have pins or bearings of non-corrodible material. If shutters
are fitted with securing appliances, these appliances are to Where a screen bulkhead is fitted across the full breadth of
be of approved construction. the ship at the fore end of a midship deckhouse, the
weather deck is to be considered as divided into two wells,
6.1.6 Gutter bars irrespective of the width of the deckhouse, and the freeing
Gutter bars greater than 300 mm in height fitted around the port area is to be obtained in accordance with [6.1.2].
weather decks of tankers, in way of cargo manifolds and
cargo piping, are to be treated as bulwarks. The freeing port
area is to be calculated in accordance with the applicable 6.3 Freeing port area in a well contiguous to
requirements of this Section. a trunk or hatchways
6.2 Freeing port area in a well not adjacent 6.3.1 Freeing port area for continuous trunk or
to a trunk or hatchways continuous hatchway coaming
Superstructure
0,35 + 0,0175 B + 0,5 AC 0,035 B + 0,5 AC B hS
decks 0,4 B < BH < 0,75 B 0,2 0,286 ------H 0,4 B h B ----------
-
B 2h W
Note 1:
hS
B : Length, in m, of bulwark in the well, to be taken BH 0,75 B 0,1 B h B ----------
-
not greater than 0,7 LLL 2h W
AC : Area, in m2, to be taken, with its sign, equal to: Note 1:
B : Length, in m, of bulwark in a well at one side of
A C = -----B- ( h B 1 ,2 ) for h B > 1,2 the ship
25
AC = 0 for 0,9 h B 1 ,2 hB : Mean height, in m, of bulwark in a well of
B length B
A C = ------ ( h B 0 ,9 ) for h B < 0 ,9 hS : Standard superstructure height, in m, defined in
25
[1.2.1]
hB : Mean height, in m, of the bulwark in a well of hW : Distance, in m, of the well deck above the free-
length B. board deck, to be taken not less than 0,5 hS .
6.3.2 Freeing area for non-continuous trunk or cSH : Coefficient which accounts for the absence of
hatchway coaming sheer, if applicable, to be taken equal to:
Where the free flow of water across the deck of the ship is cSH = 1,0 in the case of standard sheer or sheer
impeded due to the presence of a non-continuous trunk, greater than standard sheer
hatchway coaming or deckhouse in the whole length of the
cSH = 1,5 in the case of no sheer
well considered, the freeing port area in the bulwark of this
well is to be not less than that obtained, in m2, from Tab 6. b0 : Breadth, in m, of the openings in the end bulk-
head of enclosed superstructures
hS, hW : As defined in Tab 5.
Table 6 : Freeing port area in a well
contiguous to a non-continuous trunk or hatchway
6.4.3 Freeing port area for open well
Free flow area fP , in m 2
Freeing port area A3 , in m 2 The freeing port area on each side of the ship for the open
well is to be not less than that obtained, in m2, from the fol-
fp A1 A2
lowing formula:
A1 < fP < A2 A1 + A2 fP
hS
fP A2 A1 A W = A 1 c SH ----------
2h W
Note 1:
A1 : Freeing port area, in m2, required for an open
fP : Free flow area on deck, equal to the net area of
gaps between hatchways, and between hatch- well of length W, in accordance with Tab 4
ways and superstructures and deckhouses up to
W : Defined in [6.4.2].
the actual height of the bulwark
A1 : Area of freeing ports, in m2, to be obtained from The resulting freeing port areas for the open superstructure
Tab 4 AS and for the open well AW are to be provided along each
A2 : Area of freeing ports, in m2, to be obtained from side of the open space covered by the open superstructure
Tab 5. and each side of the open well, respectively.
6.4 Freeing port area in an open space 6.5 Freeing port area in bulwarks of the
within superstructures freeboard deck for ships of types A, B-100
and B-60
6.4.1 General
In ships having superstructures on the freeboard or super- 6.5.1 Freeing arrangement for type B-60
structure decks, which are open at either or both ends to For type B-60 ships, the freeing port area in the lower part of
wells formed by bulwarks on the open decks, adequate pro- the bulwarks of the freeboard deck is to be not less than
vision for freeing the open spaces within the superstructures 25% of the total area of the bulwarks in the well considered.
is to be provided.
The upper edge of the sheer strake is to be kept as low as
possible.
6.4.2 Freeing port area for open superstructures
6.5.2 Freeing arrangement for type A and type B-
The freeing port area on each side of the ship for the open 100 ships with trunks
superstructure is to be not less than that obtained, in m2, For type A and type B-100 ships, open rails are to be fitted
from the following formula: on the weather parts of the freeboard deck in way of the
2
trunk for at least half the length of these exposed parts.
W b0 hS
A S = A 1 c SH 1 -----
- ---------------
-
T 2 T h W Alternatively, if a continuous bulwark is fitted, the freeing
port area in the lower part of the bulwarks of the freeboard
where: deck is to be not less than 33% of the total area of the bul-
warks in the well considered.
T : Total well length, in m, to be taken equal to:
S : Length, in m, of the common space within the 7.1.1 Engine room skylights in positions 1 or 2 are to be
open superstructures properly framed, securely attached to the deck and effi-
ciently enclosed by steel casings of suitable strength. Where
A1 : Freeing port area, in m2, required for an open the casings are not protected by other structures, their
well of length T , in accordance with Tab 4, strength will be considered by the Society on a case by case
where AC is to be taken equal to zero basis.
7.2 Closing devices Where, due to the ships size and arrangement, this is not
practicable, lesser heights for machinery space and emer-
7.2.1 Machinery casings gency generator room ventilator coamings, fitted with
Openings in machinery space casings in positions 1 or 2 are weathertight closing appliances in accordance with [9.1.2],
to be fitted with doors of steel or other equivalent materials, may be permitted by the Society in combination with other
permanently and strongly attached to the bulkhead, and suitable arrangements to ensure an uninterrupted, adequate
framed, stiffened and fitted so that the whole structure is of supply of ventilation to these spaces.
equivalent strength to the unpierced bulkhead and weather-
tight when closed. The doors are to be capable of being 8 Companionway
operated from both sides and generally to open outwards to
give additional protection against wave impact.
8.1 General
Other openings in such casings are to be fitted with equiva-
lent covers, permanently attached in their proper position. 8.1.1 Openings in freeboard deck
Openings in freeboard deck other than hatchways, machinery
7.2.2 Machinery casings on Type A ships space openings, manholes and flush scuttles are to be pro-
Machinery casings on Type A ships are to be protected by tected by an enclosed superstructure or by a deckhouse or
an enclosed poop or bridge of at least standard height, or companionway of equivalent strength and weathertightness.
by a deckhouse of equal height and equivalent strength.
8.1.2 Openings in superstructures
Machinery casings may, however, be exposed if there are no
openings giving direct access from the freeboard deck to Openings in an exposed superstructure deck or in the top of
the machinery spaces. a deckhouse on the freeboard deck which give access to a
space below the freeboard deck or a space within an
However, a weathertight door is permitted in the machinery enclosed superstructure are to be protected by an efficient
casing, provided that it leads to a space or passageway deckhouse or companionway.
which is as strongly constructed as the casing and is sepa-
rated from the stairway to the engine room by a second
8.1.3 Openings in superstructures having height
weathertight door of steel or other equivalent material. less than standard height
Openings in the top of a deckhouse on a raised quarterdeck
7.2.3 Height of the sill of the door or superstructure of less than standard height, having a
The height of the sill of the door is to be not less than: height equal to or greater than the standard quarterdeck
600 mm above the deck if in position 1 height are to be provided with an acceptable means of clos-
ing but need not be protected by an efficient deckhouse or
380 mm above the deck if in position 2 companionway provided the height of the deckhouse is at
230 mm in all other cases. least the standard height of a superstructure.
8.3.2 Height of sills room ventilator coamings fitted with weathertight closing
The height above the deck of sills to the doorways in com- appliances in accordance with [9.1.1], [9.1.3] and [9.1.4]
panionways is to be not less than: in combination with other suitable arrangements, such as
600 mm in position 1 separators fitted with drains, to ensure an uninterrupted,
adequate supply of ventilation to these spaces.
380 mm in position 2.
Where access is not provided from above, the height of the 9.1.7 Closing arrangements of ventilators led
sills to doorways in a poop bridge or deckhouse on the free- overboard or through enclosed superstructures
board deck is to be 600 mm.
Closing arrangements of ventilators led overboard to the
Where access is provided to spaces inside a bridge or poop ship side or through enclosed superstructures are consid-
from the deck as an alternative to access from the freeboard ered by the Society on a case by case basis. If such ventila-
deck, the height of the sills into the bridge or poop is to be tors are led overboard more than 4,5 m above the freeboard
380 mm. This also applies to deckhouses on the freeboard deck, closing appliances may be omitted provided that sat-
deck. isfactory baffles and drainage arrangements are fitted.
Symbols
Note 1: The following items may exceed the height of the landing
area, but not more than 100 mm:
5 Design loads
guttering or slightly raised kerb
5.1 Emergency landing load
lightning equipment
outboard edge of the safety net 5.1.1 The emergency landing force FEL transmitted through
foam monitors
one landing gear or one skid to the helicopter deck or plat-
form is to be obtained, in kN, from the following formulae:
those handrails and other items associated with the landing
area which are incapable of complete retraction or lowering for
helicopter with landing gears:
helicopter operations. FEL = 1,25 g WH
Ship condition Load case Still water force FS and inertial force FW , in kN
Still water condition FS = (WH + WP) g
Upright condition a No inertial force
FW,X = (WH + WP) aX1 + 1,2 AHX in x direction
b
FW,Z = (WH + WP) aZ1 in z direction
Inclined condition (negative roll angle) (1) c FW,Y = CFA (WH + WP) aY2 + 1,2 AHY in y direction
d FW,Z = CFA (WH + WP) aZ2 in z direction
(1) Inclined condition is not applicable for ships less than 65 m in length.
Note 1:
Wp : Structural weight of the helicopter platform, in t, to be evenly distributed, and to be taken not less than the value
obtained from the following formula:
Wp = 0,2 AH
AH : Area, in m2, of the entire landing area
aX1, aZ1 : Accelerations, in m/s2, determined at the helicopter centre of gravity for the upright ship condition, and defined in Ch 5,
Sec 3, [3.4]
aY2, aZ2 : Accelerations, in m/s2, determined at the helicopter centre of gravity for the inclined ship condition, and defined in Ch 5,
Sec 3, [3.4]
AHX, AHY : Vertical areas, in m2, of the helicopter platform in x and y directions respectively. Unless otherwise specified, AHX and
AHY may be taken equal to AH/3
CFA : Combination factor, to be taken equal to:
CFA = 0,7 for load case c
CFA = 1,0 for load case d.
helicopter with landing skids: 5.3 Specific loads for helicopter platforms
FEL = 2,5 g WH 5.3.1 The still water and inertial forces applied to an heli-
copter platform are to be determined, in kN, as specified in
The point of application of the force FEL is to be taken so as to Tab 2.
produce the most severe stresses on the supporting structure.
6 Scantlings
5.2 Garage load
6.1 General
5.2.1 Where a garage zone is fitted in addition to the land-
6.1.1 The scantlings of the structure of an helicopter deck
ing area, the still water and inertial forces transmitted trough
or platform are to be obtained according to [6.2], [6.3]and
each landing gear or each landing skid to the helicopter
[6.4]. They are to be considered in addition to scantlings
deck or platform are to be obtained, in kN, as specified in
obtained from other applicable loads, in particular from sea
Ch 5, Sec 6, [6.1.2], where M is to be taken equal to:
pressures.
for helicopter with landing gears:
6.1.2 As specified in Ch 4, Sec 2, [1], all scantlings referred
M is the landing gear load, in t, to be specified by the to in this section are net, i.e. they do not include any margin
Designer. If the landing gear load is not known, M is to for corrosion.
be taken equal to: The gross scantlings are obtained as specified in Ch 4, Sec 2,
[1].
1, 25
M = ------------- W H
n
6.2 Plating
where n is the total number of landing gears
6.2.1 Load model
for helicopter with landing skids: The following forces P0 are to be considered independently:
P0 = FEL
M = 0,5 WH
where FEL is the force corresponding to the emergency
landing load, as defined in [5.1]
5.2.2 When helicopters are parked in an unprotected area,
sea pressures on deck, as per Ch 5, Sec 5, [1.2], are to be P0 = s2 Fs + w2 Fw,z
considered simultaneously with the loads defined in where Fs and Fw,z are the forces corresponding to the
[5.2.1]. garage load, as defined in [5.2], if applicable.
For helicopters with wheels, in the particular case where 6.3.2 Normal and shear stresses
u > s, the tyre print outside of the plate panel is to be disre- The normal stress and the shear stress induced by forces
garded. In such a case, the load is to be considered as being defined in [6.3.1] in an ordinary stiffener of an helicopter
fully distributed on the spacing s only (see Fig 1). deck or platform are to be obtained, in N/mm2, according
to:
6.2.4 Helicopter with skids
P0 3
For helicopters with skids, in the particular case where = ----------
- 10 + X1, Wh
mW
v > , the skid print outside of the plate panel is to be disre-
garded. In such a case, the load is to be considered as being 10P
= ------------0
fully distributed on the span only (see Fig 2). A Sh
where:
Figure 1 : Tyre print with u > s m : Coefficient to be taken equal to:
m = 6, in the case of an helicopter with
wheels
m = 10, in the case of an helicopter with
landing skids.
In addition, in both cases of helicopter with wheels and hel-
icopter with landing skids, the hull girder stresses X1,Wh are
u s to be taken equal to 0 in the particular case of an helicopter
platform.
In addition, the hull girder stresses are to be taken equal to R = 1,02 for garage load
0 in the particular case of an helicopter platform. R = 1,00 for emergency landing load.
2.1.1 Doors are to be designed to offer equivalent strength 4.1.1 Doors are to be fitted with adequate means of secur-
compared to the adjacent bulkhead in which they are fitted. ing and supporting so as to be commensurate with the
Therefore, they are to be assessed considering the same strength and stiffness of the surrounding structure.
design loads, as per the examples given in the following
requirements. The hull supporting structure in way of the doors is to be
suitable for the same design loads and design stresses as the
2.2 Side shell doors securing and supporting devices.
2.2.1 Doors fitted in side shell are to be checked with the Where packing is required, the packing material is to be of
outside sea pressures defined in Ch 5, Sec 5, and whenever a comparatively soft type, and the supporting forces are to
relevant, with the internal flooding pressure defined in Ch 5, be carried by the steel structure only. Other types of packing
Sec 6, [9]. may be considered by the Society on a case by case basis.
4.1.2 Only the active supporting and securing devices having 5.2 Hydrostatic pressure testing
an effective stiffness in the relevant direction are to be included
and considered to calculate the reaction forces acting on the 5.2.1 The head of water used for the pressure test shall cor-
devices. Small and/or flexible devices such as cleats intended respond at least to the head measured from the lower edge
to provide local compression of the packing material may gen- of the door opening, at the location in which the door is to
erally not be included in the calculation in [4.2]. be fitted in the vessel, to the bulkhead deck or freeboard
deck, as applicable, or to the most unfavourable damage
The number and distribution of securing and supporting
waterplane, if that be greater. Testing may be carried out at
devices is to be set to achieve the scantling criteria in [4.2]
the factory or other shore based testing facility prior to
and the required degree of watertightness.
installation in the ship. The duration of the test is to be at
least 30 min.
4.2 Scantlings
5.2.2 Leakage criteria for watertight doors
4.2.1 Securing and supporting devices are to be adequately The following acceptable leakage criteria should apply:
designed so that they can comply with the checking criteria doors with gaskets: no leakage
defined in Ch 7, Sec 3, [3.6.1] for primary members, using
doors with metallic sealing: max leakage 1 litre/min.
general or flooding partial safety factors as relevant.
Limited leakage may be accepted for pressure tests on large
4.2.2 In addition to the requirements in [4.2.1], every ele- doors located in cargo spaces employing gasket seals or
ment transmitting loads by means of direct contact must be guillotine doors located in conveyor tunnels, in accordance
checked against bearing. In that respect, the maximum nor- with the following value, in litre/min:
mal compressive stress c distributed over the contact area 2
between the two elements is not to be higher than ReH. (----------------------------------------
P + 4.572 ) h -
6568
4.2.3 The distribution of the reaction forces acting on the where:
securing and supporting devices is generally to be sup- P : Perimeter of door opening (m)
ported by direct calculations taking into account the flexi-
h : Test head of water (m).
bility of the hull structure, the actual position of the
supports and the design load pattern. In case of homogene- However, in the case of doors where the water head taken
ously distributed supports and uniform design pressure, the for the determination of the scantling does not exceed
total force acting on the door may be considered as evenly 6,10 m, the leakage rate may be taken equal to
divided amongst the supports. 0,375 litre/min if this value is greater than that calculated by
the above-mentioned formula.
4.2.4 All load transmitting elements in the design load
5.2.3 Leakage criteria for semi-watertight doors
path, from the door through securing and supporting
devices into the ship's structure, including welded connec- A leakage quantity of approximately 100 l/hour is to be
tions, are to be of the same strength standard as required for considered as being acceptable for a 1,35 m2 opening.
the securing and supporting devices. These elements
5.2.4 For doors on passenger ships which are normally
include pins, support brackets and back-up brackets.
open and used at sea or which become submerged by the
equilibrium or intermediate waterplane, a prototype test
5 Inspection and testing shall be conducted, on each side of the door, to check the
satisfactory closing of the door against a force equivalent to
a water height of at least 1m above the sill on the centre line
5.1 General
of the door.
5.1.1 Watertight and semi-watertight doors which become
immersed by an equilibrium or intermediate waterplane are 5.3 Hose testing
to be subjected to a hydrostatic pressure test.
5.3.1 All watertight, semi-watertight and weathertight
5.1.2 For large doors of more than 6 m2 intended for use in doors shall be subject to a hose test after installation in a
the watertight subdivision boundaries of cargo spaces, ship. Hose testing is to be carried out:
structural analysis may be accepted in lieu of pressure test- from both sides of a watertight or semi-watertight door
ing. Where such doors utilize gasket seals, a prototype pres- unless, for a specific application, exposure to floodwa-
sure test to confirm that the compression of the gasket ter is anticipated only from one side
material is capable of accommodating any deflection, from both sides of internal bulkheads weathertight doors
revealed by the structural analysis, is to be carried out. (fitted above bulkhead deck)
from the exposed side of external weathertight doors
5.1.3 Watertight doors which are not immersed by an equi-
(superstructures).
librium or intermediate waterplane but become intermit-
tently immersed at angles of heel in the required range of Where a hose test is not practicable because of possible
positive stability beyond the equilibrium position may be damage to machinery, electrical equipment insulation or
only hose tested (required only to be weathertight accord- outfitting items, it may be replaced by means such as an
ing to Ch 3, Sec 3, [3.3.2]. ultrasonic leak test or an equivalent test.
Chapter 9
HULL OUTFITTING
SECTION 1 RUDDERS
SECTION 4 EQUIPMENT
APPENDIX 1 CRITERIA FOR DIRECT CALCULATION OF RUDDER LOADS
SECTION 1 RUDDERS
Symbols
VAV : Maximum ahead service speed, in knots, with 1.1.3 Steering nozzles
the ship on summer load waterline; if VAV is less The requirements for steering nozzles are given in [10].
than 10 knots, the maximum service speed is to
be taken not less than the value obtained from 1.1.4 Special rudder types
the following formula:
Rudders others than those in [1.1.1], [1.1.2] and [1.1.3] are
V AV + 20 to be considered by the Society on a case-by-case basis.
V MIN = ---------------------
-
3
VAD : Maximum astern speed, in knots, to be taken 1.2 Gross scantlings
not less than 0,5 VAV
A : Total area of the rudder blade, in m2, bounded 1.2.1 With reference to Ch 4, Sec 2, [1], all scantlings and
by the blade external contour, including the dimensions referred to in this Section are gross, i.e. they
mainpiece and the part forward of the cen- include the margins for corrosion.
treline of the rudder pintles, if any
k1 : Material factor, defined in [1.4.3] 1.3 Arrangements
k : Material factor, defined in Ch 4, Sec 1, [2.3]
(see also [1.4.5]) 1.3.1 Effective means are to be provided for supporting the
CR : Rudder force, in N, acting on the rudder blade, weight of the rudder without excessive bearing pressure,
defined in [2.1.2] e.g. by means of a rudder carrier attached to the upper part
of the rudder stock. The hull structure in way of the rudder
MTR : Rudder torque, in N.m, acting on the rudder
carrier is to be suitably strengthened.
blade, defined in [2.1.3] and [2.2.3]
MB : Bending moment, in N.m, in the rudder stock, 1.3.2 Suitable arrangements are to be provided to prevent
to be calculated according to Ch 9, App 1, the rudder from lifting.
[1.4], for each type of rudder listed in Tab 4.
In addition, structural rudder stops of suitable strength are
to be provided, except where the steering gear is provided
1 General with its own rudder stopping devices, as detailed in Pt C,
Ch 1, Sec 11.
1.1 Application
1.3.3 In rudder trunks which are open to the sea, a seal or
1.1.1 Ordinary profile rudders stuffing box is to be fitted above the deepest load waterline,
The requirements of this Section apply to ordinary profile to prevent water from entering the steering gear compart-
rudders, without any special arrangement for increasing the ment and the lubricant from being washed away from the
rudder force, whose maximum orientation at maximum rudder carrier. If the top of the rudder trunk is below the
ship speed is limited to 35 on each side. deepest waterline two separate stuffing boxes are to be pro-
In general, an orientation greater than 35 is accepted for vided.
manoeuvres or navigation at very low speed.
1.4 Materials
1.1.2 High efficiency rudders
The requirements of this Section also apply to rudders fitted 1.4.1 Rudder stocks, pintles, coupling bolts, keys and cast
with flaps to increase rudder efficiency. For these rudder parts of rudders are to be made of rolled steel, steel forgings
types, an orientation at maximum speed different from 35 or steel castings according to the applicable requirements in
may be accepted. In these cases, the rudder forces are to be NR216 Materials and Welding, Chapter 2.
calculated by the Designer for the most severe combina-
tions between orientation angle and ship speed. These cal- 1.4.2 The material used for rudder stocks, pintles, keys and
culations are to be considered by the Society on a case-by- bolts is to have a minimum yield stress not less than
case basis. 200 N/mm2.
The rudder scantlings are to be designed so as to be able to
sustain possible failures of the orientation control system, 1.4.3 The requirements relevant to the determination of
or, alternatively, redundancy of the system itself may be scantlings contained in this Section apply to steels having a
required. minimum yield stress equal to 235 N/mm2.
Where the material used for rudder stocks, pintles, coupling AT : Area, in m2, to be calculated by adding the rud-
bolts, keys and cast parts of rudders has a yield stress differ- der blade area A to the area of the rudder post
ent from 235 N/mm2, the scantlings calculated with the for- or rudder horn, if any, up to the height h
mulae contained in the requirements of this Section are to r2 : Coefficient to be obtained from Tab 2
be modified, as indicated, depending on the material factor
r3 : Coefficient to be taken equal to:
k1, to be obtained from the following formula:
r3 = 0,8 for rudders outside the propeller jet
n
k 1 = ----------
235 (centre rudders on twin screw ships, or simi-
R eH
lar cases)
where: r3 = 1,15 for rudders behind a fixed propel-
ReH : Minimum yield stress, in N/mm2, of the speci- ler nozzle
fied steel, and not exceeding the lower of r3 = 1,0 in other cases.
0,7 Rm and 450 N/mm2
Rm : Minimum ultimate tensile strength, in N/mm2, Table 1 : Navigation coefficient
of the steel used
Navigation notation Navigation coefficient nR
n : Coefficient to be taken equal to:
Unrestricted navigation 1,00
n = 0,75 for ReH > 235 N/mm2
Summer zone 0,95
n = 1,00 for ReH 235 N/mm2.
Tropical zone 0,85
1.4.4 Significant reductions in rudder stock diameter due to Coastal area 0,85
the application of steels with yield stresses greater than
Sheltered area 0,75
235 N/mm2 may be accepted by the Society subject to the
results of a check calculation of the rudder stock deforma- Table 2 : Values of coefficient r2
tions (refer to [4.2.1]).
r2 for ahead r2 for astern
1.4.5 Welded parts of rudders are to be made of approved Rudder profile type
condition condition
rolled hull materials. For these members, the material factor
k defined in Ch 4, Sec 1, [2.3] is to be used. NACA 00 - Goettingen
rudder
Figure 1 : Geometry of rudder blade without cut-outs Figure 2 : Rudder blades with cut-outs
z
4
b
A1
A1
3
A2
A2
AF
h
Trapezoidal rudder blade Trapezoidal rudder blade
Semi-spade rudder with Semi-spade rudder with
rudder horn - 2 bearings rudder horn - 3 bearings
2 x The rudder forces CR1 and CR2 , acting on each part A1 and
1 A2 of the rudder blade, respectively, are to be obtained, in
N, from the following formulae:
2.1.3 Rudder torque A
C R1 = C R ------1
The rudder torque MTR , for both ahead and astern condi- A
tions, is to be obtained, in N.m, from the following formula: A
C R2 = C R ------2
MTR = CR r A
where: The levers r1 and r2 of the forces CR1 and CR2 , respectively,
are to be obtained, in m, from the following formulae:
r : Lever of the force CR , in m, equal to:
A 1F
r 1 = b 1 -------
-
A
r = b -----F A1
A
A 2F
r 2 = b 2 -------
-
and to be taken not less than 0,1 b for the ahead A2
condition
where:
b : Mean breadth, in m, of rudder area to be taken
b1, b2 : Mean breadths of the rudder blade parts having
equal to (see Fig 1):
areas A1 and A2, respectively, to be determined
x2 + x3 x1 according to [2.1.3]
b = ---------------------------
2 A1F, A2F : Areas, in m2, of the rudder blade parts, defined
: Coefficient to be taken equal to: in Fig 3
= 0,33 for ahead condition : Coefficient to be taken equal to:
= 0,66 for astern condition = 0,33 for ahead condition
AF : Area, in m2, of the rudder blade portion afore = 0,66 for astern condition
the centreline of rudder stock (see Fig 1). For rudder parts located behind a fixed structure
such as a rudder horn, is to be taken equal to:
2.2 Rudder blade with cut-outs (semi-spade = 0,25 for ahead condition
rudders = 0,55 for astern condition.
2.2.1 Rudder blade description Figure 3 : Geometry of rudder blade with cut-outs
A rudder blade with cut-outs may have trapezoidal or rec-
tangular contour, as indicated in Fig 2.
The torques MTR1 and MTR2 , relevant to the rudder blade moment, MB , acting on the rudder stock. The Von Mises
parts A1 and A2 respectively, are to be obtained, in N.m, equivalent stress, E , calculated for this state of stress, has to
from the following formulae: be in compliance with the following formula:
MTR1 = CR1 r1 E E,ALL
dS : Stock diameter, in mm
3.1 General
E,ALL : Allowable equivalent stress, in N/mm2, equal to:
3.1.1 Loads per rudder category - basic E,ALL = 118 / k1
assumptions
For this purpose, the rudder stock diameter is to be not less
Depending on the shape of the rudder blade and arrange- than the value obtained, in mm, from the following formula:
ment of the rudder, twelve types of rudders are considered.
Tab 4 summarizes these rudder types. 4 M Bi 2 1/6
1 + --- ---------
13
d TFi = 4, 2 ( M TR k 1 )
3 M TR
The force and torque acting on the rudder, defined in [2],
may induce in the rudder structure the following loads: where MBi is to be obtained according to Ch 9, App 1,
bending moment and torque in the rudder stock [1.1.1], for each type of rudder listed in Tab 4.
Type 2
Type 1
FA3
UpSB=LoSB
FA2
PR
FA1
PiB
General description: 3-bearing rudder, including 2 pintle bear-
General description: 4-bearing rudder, including 3 pintle bear-
ings and 1 rudder-stock bearing (the lower pintle bearing is repre-
ings and 1 rudder-stock bearing.
sented by 1-elastic support).
See Ch 9, App 1, [1.4.1].
See Ch 9, App 1, [1.4.2].
Type 3 Type 4
General description: 3-bearing semi-spade rudder, including
General description: 3-bearing rudder, including 2 bearings asso- 2 pintle bearings and 1 rudder-stock bearing (the lower pintle
ciated to the simplex rudder shaft and 1 rudder-stock bearing. bearing is represented by 1-elastic support).
See Ch 9, App 1, [1.4.3]. See Ch 9, App 1, [1.4.4].
Type 5 Type 6a
PR PR
FA1
PiB
General description: 3-bearing rudder, including 1-elastic pintle General description: 2-bearing spade rudder, including 2 rudder-
bearing and 2 rudder-stock bearings. stock bearings, both of them located out of the rudder blade area.
See Ch 9, App 1, [1.4.5]. See Ch 9, App 1, [1.4.6].
Type 6b Type 6c
LoSB LoSB
FA2
MCR1 FA2
CR1
PR
PR
General description: 2-bearing spade rudder, including 2 rudder- General description: 2-bearing spade rudder, including 2 rudder-
stock bearings, the lowest one located inside of the rudder blade stock bearings, the lowest one located inside of the rudder blade
area and close to its upper edge. See Ch 9, App 1, [1.4.7]. area. See Ch 9, App 1, [1.4.8].
Type 8
Type 7
UpSB FA3
UpSB FA3
LoSB
LoSB FA2
FA2
PR20 FA1
PR20 FA1
PiB
PR10 PR10
PiB
UpSB FA3
UpSB FA3
LoSB LoSB
FA2
FA2
PR20 PR20 FA1
FA1
PR10
PR10 PiB
PiB
Rudder type 0 1
Types 1, 2, 3 and 4 (see Tab 4) M TR 2 + 5 d 0 R eH
- 10 3
6, 2 ----------------------- ----------------- ----------------
-
cd M t S A 1, 8 10 6 c
Types 5, 6, 7, 8, 9 and 10 (see Tab 4) The greater of:
M TR
- 10 3
6, 2 -----------------------
cd M t S A 2 + 5 d 0 R eH
----------------- --------------------------------
1, 8 10 6 c ( 1 + 1 )
M TR d 1L 6
d 1S 6
3
16 ---------------- --------------------- 10
ct S2 d 1S6
High lift profile and special rudder types The greater of: The smaller of:
M TR 2 + 5 d 0 R eH
- 10 3
6, 2 ----------------------- ----------------- --------------------------------
cd M t S A 1, 8 10 6 c ( 1 + 1 )
M TR d 1L 6
d 1S 6 2 + 5 d 0 R eH
16 ---------------- --------------------- 10
3
----------------- --------------------------------
ct S
2
d 1S6 1, 8 10 6 c ( 1 + 2 )
M T
- 10 3
6, 2 -----------------------
cd M t S A
M F
- 10 3
18, 4 -------------
ct S2
Note 1:
80 d 1L 6
d 1S 6
1 = ------------------------------------------------
-
d 2
R eH d M t S2 1 -----0
d E
3
7, 4M F 10
2 = ------------------------------------------------
-
d 2
R eH d M t S2 1 -----0
d E
ReH :
Defined in [1.4.3]
MF, MT :
Bending moment and torsional moment, respectively, in N.m, provided by the manufacturer
d1L :
Rudder stock diameter dTF , in mm, calculated in way of the lower part of the rudder stock (between the top of the rudder
plate and the lower bearing of the rudder stock) in compliance with the requirement [4.1.2], considering k1 = 1
d1S : Rudder stock diameter dT, in mm, calculated in way of the upper part of the rudder stock (at tiller level) in compliance
with the requirement [4.1.3], considering k1 = 1
, c, , dM, dE, , , : Defined in [5.2.3]
tS, dU, d0 : Defined in Fig 4.
5.3.3 Lower rudder stock end d1 : Rudder stock diameter defined in [4.1.2]
The lower rudder stock end is to be fitted with a threaded dE : External diameter, in mm, of the massive part of
part having a core diameter, dG, in mm, not less than: Fig 4, having the thickness tS
dG = 0,65d1
dM : Mean diameter, in mm, of the conical bore, as
where: defined in [5.2.3]
d1 : Rudder stock diameter defined in [4.1.2]. tS, dG, tN, dN, d0 : Geometrical parameters of the coupling,
This threaded part is to be fitted with an adequate slogging defined in Fig 4.
nut efficiently locked in rotation.
The above minimum dimensions, dN and tN, of the locking
The dimensions of the massive part and slogging nut are to nut, are only given for guidance. The determination of ade-
be in accordance with the following formulae: quate scantlings is left to the Designer.
tS 1,5 d1
dE dM + 0,6 d1 5.3.4 Washer
The washer is not needed if the seat-surface of the nut is flat 5.5 Couplings by continuous rudder stock
and, at least, identical to the contact surface calculated for a welded to the rudder blade
washer with the required diameter.
5.5.1 When the rudder stock extends through the upper
5.3.5 Couplings with key plate of the rudder blade and is welded to it, the thickness
For cone couplings without hydraulic arrangements for of this plate in the vicinity of the rudder stock is to be not
assembling and disassembling the coupling, a key is to be less than 0,20 d1, where d1 is defined in [4.1.2].
fitted having a section of (0,25dT x 0,10dT) mm2 and key-
5.5.2 The welding of the upper plate of the rudder blade
ways in both the tapered part and the rudder gudgeon.
with the rudder stock is to be made with a full penetration
The key is to be machined and located on the fore or aft weld and is to be subjected to non-destructive inspection
part of the rudder. The key is to be inserted at half-thickness through dye penetrant or magnetic particle test and ultra-
into stock and into the solid part of the rudder. sonic test.
The throat weld at the top of the rudder upper plate is to be
5.3.6 Keyless couplings concave shaped to give a fillet shoulder radius as large as
For cone couplings with hydraulic arrangements for assem- practicable. This radius:
bling and disassembling the coupling, the key may be omit- is to be not less than 0,15 d1 , where d1 is defined in
ted. In this case the designer is to submit to the Society [4.1.2]
shrinkage calculations supplying all data necessary for the
may be obtained by grinding. If disk grinding is carried
push-up length check, according to [5.3.2].
out, score marks are to be avoided in the direction of the
weld
5.3.7 Instructions
is to be checked with a template for accuracy. Four pro-
All necessary instructions for hydraulic assembly and disas-
files, at least, are to be checked. A report is to be sub-
sembly of the nut, including indication of the values of all
mitted to the Surveyor.
relevant parameters, are to be available on board.
5.6.4 Before welding is started, a detailed welding proce- Table 6 : Allowable bearing pressure
dure specification is to be submitted to the Society covering
the weld preparation, welding positions, welding parame- Bearing material pF,ALL , in N/mm2
ters, welding consumables, preheating, post weld heat Lignum vitae 2,5
treatment and inspection procedures. This welding proce- White metal, oil lubricated 4,5
dure is to be supported by approval tests in accordance with
Synthetic material with hardness 5,5
the applicable requirements of NR216 Materials and Weld-
between 60 and 70 Shore D (1)
ing, Ch 5, Sec 4.
Steel, bronze and hot-pressed bronze- 7,0
The manufacturer is to maintain records of welding, subse- graphite materials (2)
quent heat treatment and inspections traceable to the (1) Indentation hardness test at 23C and with 50% mois-
welds. These records are to be submitted to the Surveyor. ture to be performed according to a recognised stand-
ard. Type of synthetic bearing materials is to be
Non destructive tests are to be conducted at least 24 hours
approved by the Society.
after completion of the welding. The welds are to be 100%
(2) Stainless and wear-resistant steel in combination with
magnetic particle tested and 100% ultrasonic tested. The
stock liner approved by the Society.
welds are to be free from cracks, lack of fusion and incom-
plete penetration. The non destructive tests reports are to be 6.2.2 An adequate lubrication of the bearing surface is to
handed over to the Surveyor. be ensured.
5.6.5 Rudder trunks in materials other than steel are to be 6.2.3 The length/diameter ratio of the bearing surface is not
specially considered by the Society. to be greater than 1,2.
pF,ALL : Allowable bearing pressure, in N/mm2, defined 6.3.2 An adequate lubrication of the bearing surface is to
in Tab 6. be ensured.
Values greater than those given in Tab 6 may be accepted 6.3.3 The length/diameter ratio of the bearing surface is not
by the Society on the basis of specific tests. to be less than 1 and not to be greater than 1,2.
6.3.4 The manufacturing clearance t0 on the diameter of The above minimum dimensions of the locking nut are only
metallic supports is to be not less than the value obtained, given for guidance, the determination of adequate scant-
in mm, from the following formula: lings being left to the Designer.
d AC
t 0 = ------------
-+1 6.4.4 The length of the pintle housing in the gudgeon,
1000
which corresponds to tS in Fig 4, is to be not less than values
In the case of non-metallic supports, the clearances are to obtained, in mm, from the following formulae:
be carefully evaluated on the basis of the thermal and dis-
tortion properties of the materials employed. In any case, h L = 0 ,35 F Ai k 1
for non-metallic supports, the clearance on support diame-
hL = da
ter is to be not less than 1,5 mm.
where:
6.4 Pintles FAi : Force, in N, acting on the pintle, as specified in
Tab 4.
6.4.1 Rudder pintles are to have a diameter not less than
the value obtained, in mm, from the following formula: The thickness of pintle housing in the gudgeon, in mm, is to
be not less than 0,25 dA, where dA is defined in [6.4.1].
0 ,38V AV
d A = --------------------
- F Ai k 1 + f C
V AV + 3
7 Rudder blade scantlings
where:
dA : corresponds to du value shown in Fig 4 7.1 General
FAi : Force, in N, acting on the pintle, as specified in
Tab 4 7.1.1 Application
fC : Coefficient depending on corrosion, whose The requirements in [7.1] to [7.6] apply to streamlined rud-
value may generally be obtained from the fol- ders and, when applicable, to rudder blades of single plate
lowing formula: rudders.
Table 8 : Thickness of the vertical webs and rudder side plating welded to solid part or to rudder flange
HE : Vertical distance, in m, between the lower edge 7.4.4 Thickness of horizontal web plates
of the rudder blade and the upper edge of the In the vicinity of the solid parts, the thickness of the hori-
solid part zontal web plates, as well as that of the rudder blade plating
HX : Vertical distance, in m, between the considered between these webs, is to be not less than the greater of the
cross-section and the upper edge of the solid values obtained, in mm, from the following formulae:
part tH = 1,2 tF
k, k1 : Material factors, defined in [1.4], for the rudder 2
d
blade plating and the rudder stock, respectively. t H = 0 ,045 -----S
sH
7.4.3 Calculation of the actual section modulus of where:
the connection with the rudder stock housing
tF : Defined in [7.3.1]
The actual section modulus of the cross-section of the struc-
dS : Diameter, in mm, to be taken equal to:
ture of the rudder blade which is connected with the solid
part where the rudder stock is housed is to be calculated d1 for the solid part connected to the rudder
with respect to the symmetrical axis of the rudder. stock
The breadth of the rudder plating to be considered for the dA for the solid part connected to the pintle
calculation of this actual section modulus is to be not d1 : Rudder stock diameter, in mm, defined in
greater than that obtained, in m, from the following for- [4.1.2]
mula:
dA : Pintle diameter, in mm, defined in [6.4.1]
H sH : Spacing, in mm, between the two horizontal
b = s V + 2 ------X-
m web plates.
where: Different thickness may be accepted when justified on the
sV : Spacing, in m, between the two vertical webs basis of direct calculations submitted to the Society for
(see Fig 6) approval.
HX : Distance defined in [7.4.2] 7.4.5 Thickness of side plating and vertical web
m : Coefficient to be taken, in general, equal to 3. plates welded to the solid part
The thickness of the vertical web plates welded to the solid
Where openings for access to the rudder stock nut are not
part where the rudder stock is housed as well as the thick-
closed by a full penetration welded plate according to
ness of the rudder side plating under this solid part is to be
[7.1.3], they are to be deducted (see Fig 6).
not less than the values obtained, in mm, from Tab 8.
Figure 6 : Cross-section of the connection between 7.4.6 Solid part protrusions
rudder blade structure and rudder stock housing
The solid parts are to be provided with protrusions. Vertical
and horizontal web plates of the rudder are to be butt
welded to these protrusions.
These protrusions are not required when the web plate
thickness is less than:
10 mm for web plates welded to the solid part on which
the lower pintle of a semi-spade rudder is housed and
for vertical web plates welded to the solid part of the
rudder stock coupling of spade rudders
x x
20 mm for the other web plates.
Access to the
rudder stock
nut, if any 7.5 Connection of the rudder blade with the
rudder stock by means of horizontal
HX /3 HX /3 flanges
7.5.1 Minimum section modulus of the connection
The section modulus of the cross-section of the structure of
the rudder blade which is directly connected with the
x x flange, which is made by vertical web plates and rudder
blade plating, is to be not less than the value obtained, in
cm3, from the following formula:
sV wS = 1,3 d13 10-4
where d1 is the rudder stock diameter dTF , in mm, to be cal-
Section x-x culated in compliance with [4.1.2], taking k1 equal to 1.
7.5.2 Actual section modulus of the connection The section modulus of the generic section is to be not less
The section modulus of the cross-section of the structure of than the value obtained, in cm3, from the following formula:
the rudder blade which is directly connected with the
ZA = 0,5 s CH2 VAV2 k
flange is to be calculated with respect to the symmetrical
axis of the rudder. where:
For the calculation of this actual section modulus, the CH : Horizontal distance, in m, from the aft edge of
length of the rudder cross-section equal to the length of the the rudder to the centreline of the rudder stock
rudder flange is to be considered. (see Fig 7)
Where the rudder plating is provided with an opening
s : Defined in [7.6.2].
under the rudder flange, the actual section modulus of the
rudder blade is to be calculated in compliance with [7.4.3].
Figure 7 : Single plate rudder
7.5.3 Welding of the rudder blade structure to the
rudder blade flange
The welds between the rudder blade structure and the rud-
der blade flange are to be full penetrated (or of equivalent
strength) and are to be 100% inspected by means of non-
destructive tests.
Where the full penetration welds of the rudder blade are
accessible only from outside of the rudder, a backing flat
S
bar is to be provided to support the weld root.
The external fillet welds between the rudder blade plating
and the rudder flange are to be of concave shape and their
throat thickness is to be at least equal to 0,5 times the rud- CH
der blade thickness.
Moreover, the rudder flange is to be checked before weld-
ing by non-destructive inspection for lamination and inclu-
sion detection in order to reduce the risk of lamellar tearing.
Bending moment, shear forces and torque are to be calcu- ALL : Allowable shear stress, in N/mm2, equal to:
lated according to Ch 9, App 1, [1.6], or Ch 9, App 1, [1.7], ALL = 48 / k1
depending on the relevant type of rudder.
8.3.2 Minimum section modulus around the
8.2.3 Shear stress check horizontal axis
For the generic section of the rudder horn, it is to be The section modulus around the horizontal axis Y (see Ch
checked that: 9, App 1, Fig 11) is to be not less than the value obtained, in
S ALL cm3, from the following formula:
where: WY = 0,5 WZ
A ( V AV + 2 ) 2 1 / 3
where: d = 17 ,9 ----------------------------------
E : Equivalent stress to be obtained, in N/mm2,
from the following formula: where:
8.3 Solepieces
However, the thickness of the ring web, in way of the head- 10.4 Pintles
box and pintle support structure, is to be not less than tF.
10.4.1 The diameter of the pintles is to be not less than the
The Society may consider reduced thicknesses where an value obtained, in mm, from the following formula:
approved stainless steel is used, in relation to its type.
0, 35V AV
d A = ---------------------
- S AV + 30 k 1
V AV + 3
10.3 Nozzle stock
where:
10.3.1 The diameter of the nozzle stock is to be not less SAV : Defined in [10.3.1].
than the value obtained, in mm, from the following formula:
10.4.2 The length/diameter ratio of the pintle is not to be
dNTF = 6,42 (MT k1)1/3
less than 1 and not to be greater than 1,2.
where: Smaller values of hA may be accepted provided that the
MT : Torque, to be taken as the greater of those pressure on the gudgeon bearing pF is in compliance with
obtained, in N.m, from the following formulae: the following formula:
MTAV = 0,3 SAV a pF pF,ALL
A2N = L1 H1
10.5 Nozzle coupling
a, b, LM , dM , L1 , H1 : Geometrical parameters of the noz-
zle, in m, defined in Fig 9. 10.5.1 Diameter of coupling bolts
The diameter of the coupling bolts is to be not less than the
The diameter of the nozzle stock may be gradually tapered
value obtained, in mm, from the following formula:
above the upper stock bearing so as to reach, in way of the
tiller or quadrant, the value obtained, in mm, from the fol- 3
d NTF k 1B
lowing formula: d B = 0 ,62 -------------------
-
n B e M k 1S
dNT = 0,75 dNTF where:
dNTF : Diameter of the nozzle stock, in mm, defined in
Figure 9 : Geometrical parameters of the nozzle [10.3.1]
k1S : Material factor k1 for the steel used for the stock
k1B : Material factor k1 for the steel used for the bolts
eM : Mean distance, in mm, from the bolt axes to the
longitudinal axis through the coupling centre
L1 (i.e. the centre of the bolt system)
nB : Total number of bolts, which is to be not less
than:
H1 b a
4 if dNTF 75 mm
dM
6 if dNTF > 75 mm.
LM
Non-fitted bolts may be used provided that, in way of the
mating plane of the coupling flanges, a key is fitted having a
section of (0,25dNT x 0,10dNT) mm2, where dNT is defined in
[10.3.1], and keyways in both the coupling flanges, and
provided that at least two of the coupling bolts are fitted
bolts.
The distance from the bolt axes to the external edge of the
coupling flange is to be not less than 1,2 dB.
M TR d NTF
6
d NT 6 11.1.3 Operating conditions
16 ---------------- ------------------------
- The maximum angle at which the azimuth propulsion system
ct S2 d NT6
The total force which acts on the azimuth propulsion system maximum loads calculated for an orientation of the sys-
is to be obtained by integrating the lateral pressure on the tem equal to the maximum angle at which the azimuth
external surface of the system. propulsion system can be oriented on each side when
The calculations of lateral pressure and total force are to be the ship navigates at its maximum speed
submitted to the Society for information. maximum loads calculated for the possible orientations
of the system greater than the maximum angle at the rel-
11.4 Plating evant speed (see [11.1.3])
maximum loads calculated for the crash stop of the ship
11.4.1 Plating of the rudder part of the azimuth obtained through inversion of the propeller rotation
propulsion system
maximum loads calculated for the crash stop of the ship
The thickness of plating of the rudder part of the azimuth
obtained through a 180 rotation of the pod.
propulsion system is to be not less than that obtained, in
mm, from the formulae in [7.3.1], in which the term CR /A is 11.6.3 Strength check
to be replaced by the lateral pressure calculated according
to [11.3]. It is to be checked that the Von Mises equivalent stress E in
primary supporting members, calculated, in N/mm2, for the
11.4.2 Plating of the pod load cases defined in [11.6.2], is in compliance with the
The thickness of plating of the pod is to be not less than that following formula:
obtained, in mm, from the formulae in Ch 7, Sec 1, where E ALL
the lateral pressure is to be calculated according to [11.3].
where:
11.4.3 Webs ALL : Allowable stress, in N/mm2, to be taken equal to
The thickness of webs of the rudder part of the azimuth pro- 0,55 ReH
pulsion system is to be determined according to [7.3.4],
ReH : Minimum yield stress, in N/mm2, of the speci-
where the lateral pressure is to be calculated according to
fied steel. ReH is not to exceed the lower of
[11.3].
0,7 Rm and 450 N/mm2
11.5 Ordinary stiffeners Rm : Minimum ultimate tensile strength, in N/mm2,
of the steel used.
11.5.1 Ordinary stiffeners of the pod When the loads are calculated for crash stop of the ship, the
The scantlings of ordinary stiffeners of the pod are to be not criteria given in [11.6.4] are to be complied with.
less than those obtained from the formulae in Ch 7, Sec 2,
where the lateral pressure is to be calculated according to When fine mesh finite element analysis (typically 50x50 mm)
[11.3]. is used for the calculation of stresses, then the following crite-
ria may be applied:
11.6 Primary supporting members for elements not adjacent to the weld:
E 1,53 ALL
11.6.1 Analysis criteria
for elements adjacent to the weld:
The scantlings of primary supporting members of the azi-
muth propulsion system are to be obtained by the Designer E 1,34 ALL
through direct calculations, to be carried out according to
the following requirements: 11.6.4 Strength check for crash stop of the ship
the structural model is to include the pod, the rudder When the loads are calculated for crash stop of the ship, the
part of the azimuth propulsion system, the bearing and Von Mises equivalent stress E in primary supporting mem-
the hull supports bers, calculated, in N/mm2, is to be checked with the fol-
the boundary conditions are to represent the connec- lowing formula:
tions of the azimuth propulsion system to the hull struc- E CRASH
tures
where:
the loads to be applied are those defined in [11.6.2].
CRASH = 1,25 ALL
The direct calculation analyses (structural model, load and
stress calculation, strength checks) carried out by the ALL : Allowable stress as defined in [11.6.3].
Designer are to be submitted to the Society for information. When fine mesh finite element analysis (typically 50 by 50
mm) is used for the calculation of stresses, then the follow-
11.6.2 Loads ing criteria may be applied:
The following loads are to be considered by the Designer in for elements not adjacent to the weld:
the direct calculation of the primary supporting members of
the azimuth propulsion system: E 1,53CRASH
gravity loads for elements adjacent to the weld:
buoyancy E 1,34CRASH
11.7 Hull supports of the azimuth propulsion for elements not adjacent to the weld:
system E 1,53ALL
11.7.1 Analysis criteria for elements adjacent to the weld:
The scantlings of hull supports of the azimuth propulsion E 1,34ALL
system are to be obtained by the Designer through direct
calculations, to be carried out in accordance with the Values of E greater than ALL may be accepted by the Soci-
requirements in [11.6.1]. ety on a case-by-case basis, depending on the localisation
of E and on the type of direct calculation analysis.
11.7.2 Loads
The loads to be considered in the direct calculation of the 11.7.4 Strength check for crash stop of the ship
hull supports of the azimuth propulsion system are those
When the loads are calculated for crash stop of the ship, the
specified in [11.6.2].
Von Mises equivalent stress E in primary supporting mem-
11.7.3 Strength check bers, calculated, in N/mm2, is to be checked with the fol-
It is to be checked that the Von Mises equivalent stress E in lowing formula:
hull supports, in N/mm2, calculated for the load cases E CRASH
defined in [11.6.2], is in compliance with the following for-
mula: where:
E ALL CRASH = 1,25 ALL
where: ALL : Allowable stress as defined in [11.7.3].
ALL : Allowable stress, in N/mm2, equal to: When fine mesh finite element analysis (typically 50 by 50
ALL = 65 / k mm) is used for the calculation of stresses, then the follow-
k : Material factor, defined in Ch 4, Sec 1, [2.3]. ing criteria may be applied:
When the loads are calculated for crash stop of the ship, the for elements not adjacent to the weld:
criteria given in [11.7.4] is to be complied with. E 1,53CRASH
When fine mesh finite element analysis (typically 50 by 50
for elements adjacent to the weld:
mm) is used for the calculation of stresses, then the follow-
ing criteria may be applied: E 1,34CRASH
1 General 2 Bulwarks
2.1 General
1.1 Introduction
2.1.1 As a rule, plate bulwarks are to be stiffened at the
1.1.1 The requirements of this Section apply to the arrange- upper edge by a suitable bar and supported either by stays
ment of bulwarks and guard rails provided at boundaries of or plate brackets spaced not more than 2,0 m apart.
the freeboard deck, superstructure decks and tops of the first Bulwarks are to be aligned with the beams located below or
tier of deckhouses located on the freeboard deck. are to be connected to them by means of local transverse
stiffeners.
As an alternative, the lower end of the stay may be sup-
1.2 General ported by a longitudinal stiffener.
1.2.1 Efficient bulwarks or guard rails are to be fitted on all 2.1.2 In type A, B-60 and B-100 ships, the spacing forward
exposed parts of the freeboard deck and superstructure of 0,07 L from the fore end of brackets and stays is to be not
decks directly attached to the freeboard deck, as well as the greater than 1,2 m.
first tier of deckhouses fitted on the freeboard deck and the
2.1.3 Where bulwarks are cut completely, the scantlings of
superstructure ends. stays or brackets are to be increased with respect to those
given in [2.2].
1.2.2 The height of the bulwarks or guard rails is to be at
least 1 m from the deck. However, where their height would 2.1.4 As a rule, bulwarks are not to be connected either to
interfere with the normal operation of the ship, a lesser the upper edge of the sheerstrake plate or to the stringer
height may be accepted, if adequate protection is provided plate.
and subject to any applicable statutory requirement. Failing this, the detail of the connection will be examined
by the Society on a case-by-case basis.
1.2.3 Where superstructures are connected by trunks, open
rails are to be fitted for the whole length of the exposed
2.2 Scantlings
parts of the freeboard deck. 2.2.1 The thickness of bulwarks on the freeboard deck not
exceeding 1100 mm in height is to be not less than:
1.2.4 In type A and B-100 ships, open rails on the weather 5,5 mm for L 30 m
parts of the freeboard deck for at least half the length of the 6,0 mm for 30 m < L 120 m
exposed parts are to be fitted.
6,5 mm for 120 m < L 150 m
Alternatively, freeing ports complying with Ch 8, Sec 10, 7,0 mm for L > 150 m.
[6.5.2] are to be fitted. Where the height of the bulwark is equal to or greater than
1800 mm, its thickness is to be equal to that calculated for
1.2.5 In ships with bulwarks and trunks of breadth not less the side of a superstructure situated in the same location as
than 0,6 B, which are included in the calculation of free- the bulwark.
board, open rails on the weather parts of the freeboard deck For bulwarks between 1100 mm and 1800 mm in height,
in way of the trunk for at least half the length of the exposed their thickness is to be calculated by linear interpolation.
parts are to be fitted.
2.2.2 Bulwark plating and stays are to be adequately
Alternatively, freeing ports complying with Ch 8, Sec 10, strengthened in way of eyeplates used for shrouds or other
[6.3.1] are to be fitted. tackles in use for cargo gear operation, as well as in way of
hawserholes or fairleads provided for mooring or towing.
1.2.6 In ships having superstructures which are open at
2.2.3 At the ends of partial superstructures and for the dis-
either or both ends, adequate provision for freeing the
tance over which their side plating is tapered into the bul-
space within such superstructures is to be provided. wark, the latter is to have the same thickness as the side
plating; where openings are cut in the bulwark at these
1.2.7 The freeing port area in the lower part of the bulwarks positions, adequate compensation is to be provided either
is to be in compliance with the applicable requirements of by increasing the thickness of the plating or by other suita-
Ch 8, Sec 10, [6]. ble means.
2.2.4 The section modulus of stays in way of the lower part 3.1.4 Fixed, removable or hinged stanchions are to be fitted
of the bulwark is to be not less than the value obtained, in about 1,5 m apart. At least every third stanchion is to be
cm3, from the following formula: supported by a bracket or stay.
hB : Height of bulwark, in m, measured between its every stanchion is of increased breadth: k bs = 1,9 bs
upper edge and the deck.
where:
The actual section of the connection between stays and
deck structures is to be taken into account when calculating bs : breadth of normal stanchion according to the
the above section modulus. design standard
To this end, the bulb or face plate of the stay may be taken Flat steel stanchions of increased breadth (see Fig 1) are to
into account only where welded to the deck; in this case the be aligned with member below deck. A minimum flat bar
beam located below is to be connected by double continu- 100 x 12 is to be welded to deck by double continuous fillet
ous welding. welds with leg size of minimum 7 mm or as specified by the
design standard.
For stays with strengthening members not connected to the
deck, the calculation of the required minimum section The stanchions with increased breadth need not be aligned
modulus is considered by the Society on a case-by-case with under deck structure for deck plating exceeding
basis. 20 mm.
At the ends of the ship, where the bulwark is connected to Removable or hinged stanchions are to be capable of being
the sheerstrake, an attached plating having width not locked in the upright position.
exceeding 600 mm may also be included in the calculation
of the actual section modulus of stays. 3.1.5 Wire ropes may only be accepted in lieu of guard
rails in special circumstances and then only in limited
2.2.5 Openings in bulwarks are to be arranged so that the lengths. Wires are to be made taut by means of turnbuckles.
protection of the crew is to be at least equivalent to that
provided by the horizontal courses in [3.1.2]. 3.1.6 Chains may only be accepted in short lengths in lieu
of guard rails if they are fitted between two fixed stanchions
For this purpose, vertical rails or bars spaced approximately
and/or bulwarks.
230 mm apart may be accepted in lieu of rails or bars
arranged horizontally.
Figure 1 : Guardrail stanchion of increased breadth
2.2.6 In the case of ships intended for the carriage of timber
deck cargoes, the specific provisions of the freeboard regu-
lations are to be complied with.
3 Guard rails
3.1
Symbols
1.1 General
1.1.1 Propeller shafting is either enclosed in bossing or
independent of the main hull and supported by shaft brack- l
ets.
L
1.2 Double arm propeller shaft brackets
1.2.1 General It is to be checked that the bending stress F, the compres-
This type of propeller shaft bracket consists of two arms sive stress N and the shear stress are in compliance with
arranged, as far as practicable, at right angles and converg- the following formula:
ing in the propeller shaft bossing. 2 2
( F + N ) + 3 ALL
Exceptions to this will be considered by the Society on a
case by case basis. where:
M 3
1.2.2 Scantlings of arms F = ------- 10
wA
The moment in the arm, in kN.m, is to be obtained from the
L sin
following formula: N = 10F C -------------------
A sin
FC L
- --- d cos + L
M = ----------- L cos
= 10F C ---------------------
sin 1 A S sin
1.2.3 Scantlings of propeller shaft bossing 1.3.3 Scantlings of propeller shaft bossing
The length of the propeller shaft bossing is to be not less The length of the propeller shaft bossing is to be not less
than the length of the aft sterntube bearing bushes (see Pt C, than the length of the aft sterntube bearing bushes (see Pt C,
Ch 1, Sec 7, [2.4]). Ch 1, Sec 7, [2.4]).
The thickness of the propeller shaft bossing is to be not less The thickness of the propeller shaft bossing is to be not less
than 0,33 dP. than 0,33 dP.
SECTION 4 EQUIPMENT
Symbols
EN : Equipment Number defined in [2.1] For ships having the navigation notation coastal area or
sheltered area, the equipment in anchors and chain cables
ALL 2
: Allowable stress, in N/mm , used for the yield-
may be reduced. The reduction consists of entering in Tab 1
ing check in [4.9.7], [4.10.7], [4.11.2] and
one line higher for ships having the navigation notation
[4.11.3], to be taken as the lesser of:
coastal area and two lines higher for ships having the navi-
ALL = 0,67 ReH gation notation sheltered area, based on their Equipment
Number EN.
ALL = 0,40 Rm
For ships of special design or ships engaged in special serv-
ReH : Minimum yield stress, in N/mm2, of the mate- ices or on special voyages, the Society may consider equip-
rial, defined in Ch 4, Sec 1, [2] ment other than that in Tab 1.
Rm : Tensile strength, in N/mm2, of the material, 2.1.2 Equipment Number for ships with perpendicular
defined in Ch 4, Sec 1, [2]. superstructure front bulkhead
The Equipment Number EN is to be obtained from the fol-
1 General lowing formula:
EN = 2/3 + 2 h B + 0,1 A
1.1 General where:
: Moulded displacement of the ship, in t, to the
1.1.1 The requirements in [2] and [3] apply to temporary summer load waterline
mooring of a ship within or near harbour, or in a sheltered h : Effective height, in m, from the summer load
area, when the ship is awaiting a berth, the tide, etc. waterline to the top of the uppermost house, to
be obtained in accordance with the following
Therefore, the equipment complying with the requirements formula:
in [2] and [3] is not intended for holding a ship off fully h = a + hn
exposed coasts in rough weather or for stopping a ship
which is moving or drifting. When calculating h, sheer and trim are to be
disregarded
1.1.2 The equipment complying with the requirements in a : Freeboard amidships from the summer load
[2] to [4] is intended for holding a ship in good holding waterline to the upper deck, in m
ground, where the conditions are such as to avoid dragging hn : Height, in m, at the centreline of tier n of
of the anchor. In poor holding ground the holding power of superstructures or deckhouses having a breadth
the anchors is to be significantly reduced. greater than B/4. Where a house having a
breadth greater than B/4 is above a house with a
1.1.3 It is assumed that under normal circumstances a ship breadth of B/4 or less, the upper house is to be
will use one bow anchor only. included and the lower ignored
A : Area, in m2, in profile view, of the parts of the
hull, superstructures and houses above the sum-
2 Equipment number mer load waterline which are within the length
LE and also have a breadth greater than B/4
2.1 Equipment number LE : Equipment length, in m, equal to L without
being taken neither less than 96% nor greater
than 97% of the total length of the summer load
2.1.1 General
waterline.
All ships are to be provided with equipment in anchors and Fixed screens, fixed picture windows or bulwarks 1,5 m or
chain cables (or ropes according to [3.2.5]), to be obtained more in height are to be regarded as parts of houses when
from Tab 1, based on their Equipment Number EN. determining h and A. In particular, the hatched area shown
in Fig 1 is to be included. In case of non butt-jointed picture
In general, stockless anchors are to be adopted.
windows, only the efficient closed areas are to be included.
For ships with EN greater than 16000, the determination of The height of hatch coamings and that of any deck cargo,
the equipment will be considered by the Society on a case such as containers, may be disregarded when determining h
by case basis. and A.
1,5 m 1,5 m
Bulwark
a
Summer load waterline
Fore end
Table 1 : Equipment
Equipment number EN Stockless bower anchors Stud link chain cables for bower anchors
A < EN B Diameter, in mm
Mass per anchor, Total length
N (1)
A B in kg in m Q1 Q2 Q3
50 70 2 180 220,0 14,0 12,5
70 90 2 240 220,0 16,0 14,0
90 110 2 300 247,5 17,5 16,0
110 130 2 360 247,5 19,0 17,5
130 150 2 420 275,0 20,5 17,5
150 175 2 480 275,0 22,0 19,0
175 205 2 570 302,5 24,0 20,5
205 240 3 660 302,5 26,0 22,0 20,5
240 280 3 780 330,0 28,0 24,0 22,0
280 320 3 900 357,5 30,0 26,0 24,0
320 360 3 1020 357,5 32,0 28,0 24,0
360 400 3 1140 385,0 34,0 30,0 26,0
400 450 3 1290 385,0 36,0 32,0 28,0
450 500 3 1440 412,5 38,0 34,0 30,0
500 550 3 1590 412,5 40,0 34,0 30,0
550 600 3 1740 440,0 42,0 36,0 32,0
600 660 3 1920 440,0 44,0 38,0 34,0
660 720 3 2100 440,0 46,0 40,0 36,0
720 780 3 2280 467,5 48,0 42,0 36,0
780 840 3 2460 467,5 50,0 44,0 38,0
840 910 3 2640 467,5 52,0 46,0 40,0
910 980 3 2850 495,0 54,0 48,0 42,0
980 1060 3 3060 495,0 56,0 50,0 44,0
1060 1140 3 3300 495,0 58,0 50,0 46,0
1140 1220 3 3540 522,5 60,0 52,0 46,0
1220 1300 3 3780 522,5 62,0 54,0 48,0
1300 1390 3 4050 522,5 64,0 56,0 50,0
1390 1480 3 4320 550,0 66,0 58,0 50,0
1480 1570 3 4590 550,0 68,0 60,0 52,0
(1) See [3.1.4].
Equipment number EN Stockless bower anchors Stud link chain cables for bower anchors
A < EN B Diameter, in mm
Mass per anchor, Total length
N (1)
A B in kg in m Q1 Q2 Q3
1570 1670 3 4890 550,0 70,0 62,0 54,0
1670 1790 3 5250 577,5 73,0 64,0 56,0
1790 1930 3 5610 577,5 76,0 66,0 58,0
1930 2080 3 6000 577,5 78,0 68,0 60,0
2080 2230 3 6450 605,0 81,0 70,0 62,0
2230 2380 3 6900 605,0 84,0 73,0 64,0
2380 2530 3 7350 605,0 87,0 76,0 66,0
2530 2700 3 7800 632,5 90,0 78,0 68,0
2700 2870 3 8300 632,5 92,0 81,0 70,0
2870 3040 3 8700 632,5 95,0 84,0 73,0
3040 3210 3 9300 660,0 97,0 84,0 76,0
3210 3400 3 9900 660,0 100,0 87,0 78,0
3400 3600 3 10500 660,0 102,0 90,0 78,0
3600 3800 3 11100 687,5 105,0 92,0 81,0
3800 4000 3 11700 687,5 107,0 95,0 84,0
4000 4200 3 12300 687,5 111,0 97,0 87,0
4200 4400 3 12900 715,0 114,0 100,0 87,0
4400 4600 3 13500 715,0 117,0 102,0 90,0
4600 4800 3 14100 715,0 120,0 105,0 92,0
4800 5000 3 14700 742,5 122,0 107,0 95,0
5000 5200 3 15400 742,5 124,0 111,0 97,0
5200 5500 3 16100 742,5 127,0 111,0 97,0
5500 5800 3 16900 742,5 130,0 114,0 100,0
5800 6100 3 17800 742,5 132,0 117,0 102,0
6100 6500 3 18800 742,5 120,0 107,0
6500 6900 3 20000 770,0 124,0 111,0
6900 7400 3 21500 770,0 127,0 114,0
7400 7900 3 23000 770,0 132,0 117,0
7900 8400 3 24500 770,0 137,0 122,0
8400 8900 3 26000 770,0 142,0 127,0
8900 9400 3 27500 770,0 147,0 132,0
9400 10000 3 29000 770,0 152,0 132,0
10000 10700 3 31000 770,0 137,0
10700 11500 3 33000 770,0 142,0
11500 12400 3 35500 770,0 147,0
12400 13400 3 38500 770,0 152,0
13400 14600 3 42000 770,0 157,0
14600 16000 3 46000 770,0 162,0
(1) See [3.1.4].
2.1.3 Anchoring equipment for EN below 50 The mass of VHHP anchors is to be, in general, less than or
The Society may accept ships with low equipment number equal to 1500 kg.
(30< EN 50), on a case-by-case basis. Anchors and stud link
chain cables are to be fitted according to the values in Tab 2. 3.1.4 Third anchor
At the discretion of the Society, reductions of the anchoring Where three bower anchors are provided, two are to be
equipment may be permitted for ships having special serv- connected to their own chain cables and positioned on
ice and/or navigation notation on a case-by-case basis. board always ready for use.
However, the design of such equipment is to comply with The third bower anchor is intended as a spare and is not
the present section and the requirements in NR216 Materi- required for the purpose of classification.
als and Welding, Ch 4, Sec 1.
3.1.5 Test for high holding power anchors approval
Table 2 : Equipment for 30 < EN 50 For approval of a HHP anchor, comparative tests are to be
performed on various types of sea bottom. Such tests are to
Stockless bower Stud link chain cables for bower show that the holding power of the HHP anchor is at least
anchors anchors
twice the holding power of an ordinary stockless anchor of
Mass per Diameter, the same mass.
Total length, in mm
N anchor,
in m For approval as HHP anchors of a whole range of mass,
in kg Q1 Q2
such tests are to be carried out on anchors whose sizes are,
2 120 192,5 12,5 11 as far as possible, representative of the full range of masses
proposed. In this case, at least two anchors of different sizes
3 Anchoring equipment are to be tested. The mass of the maximum size to be
approved is to be not greater than 10 times the maximum
3.1 Anchors size tested. The mass of the smallest is to be not less than
0,1 times the minimum size tested.
3.1.1 General
The anchors are to be of an approved type and satisfy the test- 3.1.6 Test for very high holding power anchors
ing conditions laid down in NR216 Materials and Welding. approval
The scantlings of anchors are to be in compliance with For approval of a VHHP anchor, comparative tests are to be
[3.1.2] to [3.1.7]. performed at least on three types of sea bottom: soft mud or
silt, sand or gravel and hard clay or similar compounded
Anchors are to be constructed and tested in compliance material. Such tests are to show that the holding power of
with approved plans. the VHHP anchor is to be at least four times the holding
power of an ordinary stockless anchor of the same mass or
3.1.2 Ordinary anchors
at least twice the holding power of a previously approved
The required mass for each bower anchor is to be obtained HHP anchor of the same mass.
from Tab 1.
The holding power test load is to be less than or equal to the
The individual mass of a main anchor may differ by 7%
proof load of the anchor, specified in NR216 Materials and
from the mass required for each anchor, provided that the
Welding, Ch 4, Sec 1, [1.5.2].
total mass of anchors is not less than the total mass required
in Tab 1. For approval as VHHP anchors of a whole range of mass,
The mass of the head of an ordinary stockless anchor, such tests are to be carried out on anchors whose sizes are,
including pins and accessories, is to be not less than 60% of as far as possible, representative of the full range of masses
the total mass of the anchor. proposed. In this case, at least three anchors of different
sizes are to be tested. relevant to the bottom, middle and
Where a stock anchor is provided, the mass of the anchor, top of the mass range.
excluding the stock, is to be not less than 80% of the mass
required in Tab 1 for a stockless anchor. The mass of the 3.1.7 Specification for test on high holding power
stock is to be not less than 25% of the mass of the anchor and very high holding power anchors
without the stock but including the connecting shackle. Tests are generally to be carried out from a tug. Shore based
tests may be accepted by the Society on a case-by-case
3.1.3 High and very high holding power anchors
basis.
High holding power (HHP) and very high holding power
(VHHP) anchors, i.e. anchors for which a holding power Alternatively, sea trials by comparison with a previous
higher than that of ordinary anchors has been proved approved anchor of the same type (HHP or VHHP) of the
according to NR216 Materials and Welding, Ch 4, Sec 1, one to be tested may be accepted by the Society on a case-
[1], do not require prior adjustment or special placement on by-case basis.
the sea bottom. For each series of sizes, the two anchors selected for testing
Where HHP or VHHP anchors are used as bower anchors, (ordinary stockless and HHP anchors for testing HHP anchors,
the mass of each anchor is to be not less than 75% or 50%, ordinary stockless and VHHP anchors or, when ordinary
respectively, of that required for ordinary stockless bower stockless anchors are not available, HHP and VHHP anchors
anchors in Tab 1. for testing VHHP anchors) are to have the same mass.
The length of chain cable connected to each anchor, having 3.2.5 Wire ropes
a diameter appropriate to its mass, is to be such that the pull As an alternative to the stud link or short link chain cables
on the shank remains practically horizontal. For this pur- mentioned, wire ropes may be used in the following cases:
pose a value of the ratio between the length of the chain
wire ropes for both the anchors, for ship length less than
cable paid out and the water depth equal to 10 is consid-
30 m
ered normal. A lower value of this ratio may be accepted by
the Society on a case-by-case basis. wire rope for one of the two anchors, for ship length
between 30 m and 40 m.
Three tests are to be carried out for each anchor and type of
sea bottom. The wire ropes above are to have a total length equal to 1,5
The pull is to be measured by dynamometer; measurements times the corresponding required length of stud link chain
based on the RPM/bollard pull curve of tug may, however, cables, obtained from Tab 1, and a minimum breaking load
be accepted instead of dynamometer readings. equal to that given for the corresponding stud link chain
cable (see [3.2.2]).
Note is to be taken where possible of the stability of the
anchor and its ease of breaking out. A short length of chain cable is to be fitted between the wire
rope and the anchor, having a length equal to 12,5m or the
distance from the anchor in the stowed position to the
3.2 Chain cables for bower anchors winch, whichever is the lesser.
3.2.1 Material
The chain cables are classified as grade Q1, Q2 or Q3 3.3 Attachment pieces
depending on the type of steel used and its manufacture.
3.3.1 General
The characteristics of the steel used and the method of man- Where the lengths of chain cable are joined to each other
ufacture of chain cables are to be approved by the Society by means of shackles of the ordinary Dee type, the anchor
for each manufacturer. The material from which chain may be attached directly to the end link of the first length of
cables are manufactured and the completed chain cables chain cable by a Dee type end shackle.
themselves are to be tested in accordance with the applica-
ble requirements of NR216 Materials and Welding, Ch 4, A detachable open link in two parts riveted together may be
Sec 1. used in lieu of the ordinary Dee type end shackle; in such
case the open end link with increased diameter, defined in
Chain cables made of grade Q1 may not be used with high [3.3.2], is to be omitted.
holding power and very high holding power anchors.
Where the various lengths of chain cable are joined by
3.2.2 Scantlings of stud link chain cables means of lugless shackles and therefore no special end and
The mass and geometry of stud link chain cables, including increased diameter links are provided, the anchor may be
the links, are to be in compliance with the requirements in attached to the first length of chain cable by a special pear-
NR216 Materials and Welding, Ch 4, Sec 1. shaped lugless end shackle or by fitting an attachment
piece.
The diameter of stud link chain cables is to be not less than
the value in Tab 1. 3.3.2 Scantlings
The diameters of the attachment pieces, in mm, are to be
3.2.3 Studless link chain cables
not less than the values indicated in Tab 3.
For ships with EN less than 90, studless short link chain
cables may be accepted by the Society as an alternative to Attachment pieces may incorporate the following items
stud link chain cables, provided that the equivalence in between the increased diameter stud link and the open end
strength is based on proof load, defined in NR216 Materials link:
and Welding, Ch 4, Sec 1, [3], and that the steel grade of swivel, having diameter = 1,2 d
the studless chain is equivalent to the steel grade of the stud increased stud link, having diameter = 1,1 d
chains it replaces, as defined in [3.2.1].
Where different compositions are provided, they will be
3.2.4 Chain cable arrangement considered by the Society on a case-by-case basis.
Chain cables are to be made by lengths of 27,5 m each,
joined together by Dee or lugless shackles. Table 3 : Diameters of attachment pieces
The total length of chain cable, required in Tab 1, is to be Attachment piece Diameter, in mm
divided in approximately equal parts between the two
End shackle 1,4 d
anchors ready for use.
Open end link 1,2 d
Where different arrangements are provided, they are con-
Increased stud link 1,1 d
sidered by the Society on a case-by-case basis.
Common stud link d
Where the ship may anchor in areas with current speed
greater than 2,5 m/s, the Society may require a length of Lugless shackle d
heavier chain cable to be fitted between the anchor and the Note 1:
rest of the chain in order to enhance anchor bedding. d : Diameter, in mm, of the common link.
*
Note that Py is to be examined from both inboard and outboard directions separately - see [3.6.2]
The sign convention for yi is reversed when Py is from the opposite direction as shown.
3.6.3 Strength requirements 3.8.4 Where the chain locker is arranged aft of the collision
Tensile axial stresses in the individual bolts in each bolt bulkhead, its boundary bulkheads are to be watertight and a
group i are to be calculated. The horizontal forces Fxi and Fyi drainage system is to be provided.
are normally to be reacted by shear chocks. Where "fitted"
3.8.5 Spurling pipes and chain lockers are to be watertight
bolts are designed to support these shear forces in one or
up to the weather deck.
both directions, the von Mises equivalent stresses in the
individual bolts are to be calculated, and compared to the Bulkheads between separate chain lockers (see Fig 4,
stress under proof load. Where pour-able resins are incor- Arrangement 1) or which form a common boundary of
porated in the holding down arrangements, due account is chain lockers (see Fig 4, Arrangement 2), need not however
to be taken in the calculations. be watertight.
The safety factor against bolt proof strength is to be not less 3.8.6 Where means of access is provided, it is to be closed
than 2,0. by a substantial cover and secured by closely spaced bolts.
3.7 Chain stoppers 3.8.7 Where a means of access to spurling pipes or cable
lockers is located below the weather deck, the access cover
3.7.1 A chain stopper is generally to be fitted between the and its securing arrangements are to be in accordance with
windlass and the hawse pipe in order to relieve the wind- recognized standards or equivalent for watertight manhole
lass of the pull of the chain cable when the ship is at covers. Butterfly nuts and/or hinged bolts are prohibited as
anchor. A chain stopper is to be capable of withstanding a the securing mechanism for the access cover.
pull of 80% of the breaking load of the chain cable. The
deck at the chain stopper is to be suitably reinforced. 3.8.8 Spurling pipes through which anchor cables are led
are to be provided with permanently attached closing appli-
For the same purpose, a piece of chain cable may be used
ances, to minimize water ingress.
with a rigging screw capable of supporting the weight of the
anchor when housed in the hawse pipe or a chain ten- Examples of arrangements for permanently attached closing
sioner. Such arrangements are not to be considered as chain appliances are such as steel plates with cut-outs to accom-
stoppers. modate chain links or canvas hoods with a lashing arrange-
ment that maintains the cover in the secured position.
3.7.2 Where the windlass is at a distance from the hawse
pipes and no chain stoppers are fitted, suitable arrangements
are to be provided to lead the chain cables to the windlass.
4 Emergency towing arrangements
4.1.1 Deadweight
3.8.1 The capacity of the chain locker is to be adequate to
stow all chain cable equipment and provide an easy direct Deadweight is the difference, in t, between the displace-
lead to the windlass. ment of a ship in water of a specific gravity of 1,025 t/m3 at
the summer load line corresponding to the assigned sum-
3.8.2 Where two chains are used, the chain lockers are to mer freeboard and the lightweight of the ship.
be divided into two compartments, each capable of housing
the full length of one line.
4.2 Application
3.8.3 The inboard ends of chain cables are to be secured to
suitably reinforced attachments in the structure by means of 4.2.1 The requirements of this Article apply to equipment
end shackles, whether or not associated with attachment arrangement for towing ships out of danger in emergencies
pieces. such as complete mechanical breakdowns, loss of power or
loss of steering capability.
Generally, such attachments are to be able to withstand a
force not less than 15% of the breaking load of the chain The concerned ships are:
cable. - the ships as defined in [4.2.2]
In an emergency, the attachments are to be easily released - all ships when the additional class notation ETA is
from outside the chain locker. assigned (see Pt A, Ch 1, Sec 2, [6.15.3]).
Towing pennant
Fairleads
Marker buoy
4.5.2 Alternative to testing the rapid deployment for Table 5 : Safe working load
each ship
Ship deadweight DWT, in t Safe working load, in kN
At the request of the Owner, the testing of the rapid deploy-
ment for each ship according to [4.5.1] may be waived pro- 20000 DWT < 50000 1000
vided that: DWT 50000 2000
the design of emergency towing arrangements of the
considered ship is identical to the type approved
arrangements and this is confirmed by the on board 4.7 Towing pennant
inspection required in [4.5.1]
4.7.1 Material
the strongpoints (chain stoppers, towing brackets or The towing pennant may be made of steel wire rope or syn-
equivalent fittings) are type approved (prototype tested). thetic fibre rope, which is to comply with the applicable
requirements in NR216 Materials and Welding, Ch 4, Sec 1.
In this case, an exemption certificate is to be issued.
4.7.2 Length of towing pennant
In general, such dispensation may be granted to subsequent
The length P of the towing pennant is to be not less than
ships of a series of identical new buildings fitted with identi-
that obtained, in m, from the following formula:
cal arrangements.
P = 2 H + 50
where:
4.6 Safe working load (SWL) of towing
pennants, chafing gears, fairleads and H : Lightest seagoing ballast freeboard measured, in
m, at the fairlead.
strongpoints
4.7.3 Minimum breaking strength of towing
4.6.1 Safe working load pennants when separate chafing gear is used
The safe working load (defined as one half of the ultimate Where a separate chafing gear is used, the minimum break-
strength) of towing pennants, chafing gear, fairleads and ing strength MBSp of towing pennants, including their termi-
strongpoints is to be not less than that obtained, in kN, from nations, is to be not less than that obtained from the
Tab 5. following formula:
The strength of towing pennants, chafing gear, fairleads and MBSP = 2 SWL
strongpoints is to be sufficient for all pulling angles of the where:
towline, i.e. up to 90 from the ships centreline to port and : Coefficient that accounts for the possible loss in
starboard and 30 vertical downwards. strength at eye terminations, to be taken not less
The safe working load of other components is to be suffi- than 1,1
cient to withstand the load to which such components may SWL : Safe working load of the towing pennants,
be subjected during the towing operation. defined in [4.6.1].
4.7.4 Minimum breaking strength of towing pennants 4.8.6 Diameter of the common links
when no separate chafing gear is used The diameter of the common links of stud link chain cables
Where no separate chafing gear is used (i.e. where the tow- is to be not less than:
ing pennant may chafe against the fairlead during towing
operation), the minimum breaking strength of the towing 52 mm for a safe working load, defined in [4.6.1], equal
pennants MBSPC is to be not less than that obtained, in kN, to 1000 kN
from the following formula: 76 mm for a safe working load, defined in [4.6.1], equal
MBSPC = MBSP to 2000 kN.
2d
Towards
2,
4.8.2 Type
Chafing chains are to be stud link chains. 4.8.8 Storing
The chafing chain is to be stored and stowed in such a way
4.8.3 Material
that it can be rapidly connected to the strongpoint.
In general, grade Q3 chain cables and associated accesso-
ries complying with the applicable requirements in NR216
Materials and Welding, Ch 4, Sec 1 are to be used. 4.9 Fairleads
4.8.4 Chafing chain length 4.9.1 General
The chafing chain is to be long enough to ensure that the
Fairleads are normally to be of a closed type (such as Pan-
towing pennant, or the towline, remains outside the fairlead
ama chocks).
during the towing operation. A chain extending from the
strongpoint to a point at least 3 m beyond the fairlead com- Fairleads are to have an opening large enough to pass the
plies with this requirement. largest portion of the chafing gear, towing pennant or tow-
line. The corners of the opening are to be suitably rounded.
4.8.5 Minimum breaking strength Where the fairleads are designed to pass chafing chains, the
The minimum breaking strength of the stud link chafing openings are to be not less than 600mm in width and
chain and the associated links is to be not less than twice 450mm in height.
the safe working load defined in [4.6.1].
Stopping device
(tongue)
Securing pin
in open position
Securing pin Grade Q3 chafing chain
in closed position Sliding track common link diameter = d
2,2 d
Towards
fairlead
Thrust chock
Horizontal part of
sliding track 14 d
Sliding track
3,5 d (approx.)
2,2 d
Towards
fairlead
Horizontal part of
sliding track 14 d
Towing bracket
(*) : See [4.10.6]
Studless end link
Enlarged link
5,3 d
Common links
(diameter = d)
Connecting pin (*) 1,8 d(*)
(steel grade Q3)
approx.
14 d
3,5 d
(approx.)
The materials used for the reinforcement of the hull structure in 4.12.4 Forward
way of the fairleads or the strongpoints are to comply with the
The forward emergency towing arrangement is to be capa-
applicable requirements of NR216 Materials and Welding.
ble of being deployed in harbour conditions in not more
Main welds of the strongpoints with the hull structure are to than 1 hour.
be 100% inspected by adequate non-destructive tests. The forward emergency towing arrangement is to be
designed at least with a means of securing a towline to the
4.11.2 Yielding check of bulwark and stays chafing gear using a suitably positioned pedestal roller to
The equivalent Von Mises stress E , in N/mm2, induced in facilitate connection of the towing pennant.
the bulwark plating and stays in way of the fairleads by a Forward emergency towing arrangements which comply
load equal to the safe working load defined in [4.6.1], for with the requirements for aft emergency towing arrange-
the operating condition of the fairleads defined in [4.9.3], is ments may be accepted.
to comply with the following formula:
Material Equipment
Component Reference of applicable Reference of applicable
Certificate Certificate
requirements requirements
Towing pennant Not applicable [4.7.1] COI (1) [4.7]
Chafing chain and associated COI (2) [4.8.3] COI (1) [4.8]
accessories
Fairleads CW [4.9.2] COI [4.9]
Strongpoint: COI (3) [4.10]
main framing COI (2) [4.10.2]
stopping device COI (2) [4.10.2]
Pick-up gear: No requirement
rope Not applicable CW
buoy Not applicable Not required (4)
line-throwing appliance Not applicable Not required (4)
Pedestal roller fairlead CW Not required (4) No requirement
(1) according to NR216 Materials and Welding, Ch 4, Sec 1.
(2) according to NR216 Materials and Welding, Chapter 1.
(3) to be type approved.
(4) may be type approved.
Note 1:
COI : Certificate of inspection,
CW : Works certificate 3.1.B according to EN 10204.
Equipment number EN
Towline (1) Mooring lines (1)
A < EN B
Minimum length, Breaking load, Length of each line, Breaking load,
A B N (2)
in m in kN in m in kN (3)
50 70 180 98,1 3 80 34
70 90 180 98,1 3 100 37
90 110 180 98,1 3 110 39
110 130 180 98,1 3 110 44
130 150 180 98,1 3 120 49
150 175 180 98,1 3 120 54
175 205 180 112 3 120 59
205 240 180 129 4 120 64
240 280 180 150 4 120 69
280 320 180 174 4 140 74
(1) The towline and the mooring lines are given as a guidance, but are not required as a condition of classification.
(2) See [5.2.7].
(3) For mooring lines with breaking load above 490 kN, see [5.2.4].
Equipment number EN
Towline (1) Mooring lines (1)
A < EN B
Minimum length, Breaking load, Length of each line, Breaking load,
A B N (2)
in m in kN in m in kN (3)
320 360 180 207 4 140 78
360 400 180 224 4 140 88
400 450 180 250 4 140 98
450 500 180 277 4 140 108
500 550 190 306 4 160 123
550 600 190 338 4 160 132
600 660 190 371 4 160 147
660 720 190 406 4 160 157
720 780 190 441 4 170 172
780 840 190 480 4 170 186
840 910 190 518 4 170 201
910 980 190 550 4 170 216
980 1060 200 603 4 180 230
1060 1140 200 647 4 180 250
1140 1220 200 692 4 180 270
1220 1300 200 739 4 180 284
1300 1390 200 786 4 180 309
1390 1480 200 836 4 180 324
1480 1570 220 889 5 190 324
1570 1670 220 942 5 190 333
1670 1790 220 1024 5 190 353
1790 1930 220 1109 5 190 378
1930 2080 220 1168 5 190 402
2080 2230 240 1259 5 200 422
2230 2380 240 1356 5 200 451
2380 2530 240 1453 5 200 481
2530 2700 260 1471 6 200 481
2700 2870 260 1471 6 200 490
2870 3040 260 1471 6 200 500
3040 3210 280 1471 6 200 520
3210 3400 280 1471 6 200 554
3400 3600 280 1471 6 200 588
3600 3800 300 1471 6 200 612
3800 4000 300 1471 6 200 647
4000 4200 300 1471 7 200 647
4200 4400 300 1471 7 200 657
4400 4600 300 1471 7 200 667
4600 4800 300 1471 7 200 677
4800 5000 300 1471 7 200 686
5000 5200 300 1471 8 200 686
5200 5500 300 1471 8 200 696
(1) The towline and the mooring lines are given as a guidance, but are not required as a condition of classification.
(2) See [5.2.7].
(3) For mooring lines with breaking load above 490 kN, see [5.2.4].
Equipment number EN
Towline (1) Mooring lines (1)
A < EN B
Minimum length, Breaking load, Length of each line, Breaking load,
A B N (2)
in m in kN in m in kN (3)
5500 5800 300 1471 8 200 706
5800 6100 300 1471 9 200 706
6100 6500 300 1471 9 200 716
6500 6900 300 1471 9 200 726
6900 7400 300 1471 10 200 726
7400 7900 300 1471 11 200 726
7900 8400 300 1471 11 200 735
8400 8900 300 1471 12 200 735
8900 9400 300 1471 13 200 735
9400 10000 300 1471 14 200 735
10000 10700 300 1471 15 200 735
10700 11500 300 1471 16 200 735
11500 12400 300 1471 17 200 735
12400 13400 300 1471 18 200 735
13400 14600 300 1471 19 200 735
14600 16000 300 1471 21 200 735
(1) The towline and the mooring lines are given as a guidance, but are not required as a condition of classification.
(2) See [5.2.7].
(3) For mooring lines with breaking load above 490 kN, see [5.2.4].
The breaking load of synthetic fibre ropes BLS is to be not Note 2: Shipboard fittings are limited to the following components:
less than that obtained, in kN, from the following formula: bollards and bitts, fairleads, stand rollers, chocks used for the
mooring and similar components used for the normal towing of the
BLS = K BL0 ship. Other components such as capstans, winches, etc. are not
covered by the present sub-article.
where:
Any weld or bolt or equivalent device connecting the ship-
BL0 : Breaking load, in kN, for the mooring line, board fitting to the supporting structure is part of the ship-
defined in Tab 7 board fitting and subject to recognised standard applicable
K : Coefficient to be taken equal to: to the shipboard fitting.
K = 1,3 for polypropylene mooring lines The strength of shipboard fittings, designed for mooring and
normal towing operations, and which are located at bow,
K = 1,2 for mooring lines made in other syn- sides and stern, and their supporting structures, are to com-
thetic material. ply with the present sub-article.
Fibre rope diameters are to be not less than 20 mm.
The supporting hull structure of capstans, winches, etc.
used for the mooring and normal towing operations is also
5.2.7 Number of mooring lines for ro-ro cargo ships,
ro-ro passenger ships and passenger ships subject to the present requirement.
For ships with one of the service notations ro-ro cargo ship, Note 3: The term supporting hull structure refers to that part of the
ship structure on/in which the shipboard fitting is placed and which
passenger ship or ro-ro passenger ship, additional mooring
is directly submitted to the forces exerted on the shipboard fitting.
lines are defined in Tab 9, in addition to the number of
mooring lines defined in Tab 7. For chain stoppers, refer also to [3.7].
Table 9 : Additional mooring lines For shipboard fittings used also for emergency towing, the
requirements of [4] are also applicable.
Number of additional
A / EN 5.3.2 Shipboard fittings
mooring lines
0,9 < A / EN 1,1 1 The selection of shipboard fittings is to be made by the ship-
yard in accordance with a recognised standard accepted by
1,1 < A / EN 1,2 2 the Society (ISO standard for example).
1,2 < A / EN 3
Whatever is the selection method of the shipboard fitting,
Note 1: A and EN are defined in [2.1.2]. the design load used to assess its strength and its attachment
to the ship is to be in accordance with [5.3.4].
5.2.8 Length of mooring lines for supply vessels
For ships with the service notation supply vessel, the length 5.3.3 Supporting hull structure
of mooring lines may be reduced. The reduced length is to The arrangement and strength of supporting hull structure of
be not less than that obtained, in m, from the following for- equipment used for towing and mooring (shipboard fittings,
mula: winches and capstans, etc.) are to comply with:
= L + 20 a) Arrangement
Equipment for normal towing and mooring are to be
5.3 Shipboard fittings and supporting hull located on longitudinals, beams and/or girders, which
structures associated with towing and are part of the deck construction so as to facilitate effi-
mooring cient distribution of the towing and mooring loads.
Other equivalent arrangements may be accepted (for
5.3.1 Application example, Panama chocks, etc.).
Note 1: Normal towing operations means harbour operations or However, the total resultant force calculated as above
manoeuvring. Escort towing operations means towing operation and applied to the fitting and to the hull supporting
other than normal towing operations and emergency towing opera- structures needs not to be more than twice the design
tion. load.
Symbols
10, 20, 30, 40 : Lengths, in m, of the individual girders of They are to be used for the stress analysis required in:
the rudder system Ch 9, Sec 1, [4], for the rudder stock
50 : Length, in m, of the solepiece Ch 9, Sec 1, [6], for the rudder stock and the pintle
bearings
TRU : Length, in m, of the trunk
Ch 9, Sec 1, [7] for the rudder blade
J10, J20, J30, J40 : Moments of inertia about the x axis, in cm4,
of the individual girders of the rudder system Ch 9, Sec 1, [8] for the rudder horn and the solepiece.
having lengths 10, 20, 30, 40 . For rudders sup-
ported by a solepiece only, J20 indicates the 1.2 Required data
moment of inertia of the pintle in the sole piece
1.2.1 Forces per unit length
J50 : Moment of inertia about the z axis, in cm4, of
The forces per unit length are to be calculated, in N/m, for
the solepiece
each type of rudder, according to requirements given under
JTRU : Moment of inertia about the x axis, in cm4, of [1.4].
the trunk
1.2.2 Support stiffness properties
CR : Rudder force, in N, acting on the rudder blade,
defined in Ch 9, Sec 1, [2.1.1] Three general cases are considered:
CR1, CR2 : Rudder forces, in N, defined in Ch 9, Sec 1, a) All supports are completely rigid. This is assumed for the
[2.2.3] rudder types 1 and 3.
E : Youngs modulus, in N/m2: b) Combination of one elastic support with several rigid
supports.
E = 2,06 1011 N/m2
The elastic support is represented by a spring, with its
G : Shear elasticity modulus, in N/m2: constant calculated in N/m, according to [1.3.1] and
G = 7,85 1010 N/m2. [1.3.2]:
ZC for rudders with solepiece (rudder type 2 as in
Fig 1, and rudder type 5 as in Fig 3)
1 Criteria for direct calculation of the
ZP for semi-spade rudders with one elastic support pro-
loads acting on the rudder structure
vided by a rudder horn (rudder type 4 as in Fig 2, rud-
der type 7 as in Fig 7, and rudder type 8 as in Fig 8)
1.1 General ZTRU for spade rudders with rudder trunk (rudder
type 6c, as shown in Fig 6).
1.1.1 Application
c) Combination of 2-conjugate elastic supports and one
The requirements of this Appendix apply to all types of rud-
rigid support (rudder type 9 as in Fig 9, and rudder type
ders listed under Ch 9, Sec 1, Tab 4.
10 as in Fig 10).
The requirements of this Appendix provide the criteria for The 2-conjugate elastic supports are defined by using
calculating the following forces and moments: two additional equations, according to [1.3.3].
bending moment MBi in the rudder stock (defined as the
maximum of absolute values of bending moment MBi 1.3 Calculation of support stiffness
over the rudder stock length) properties
support forces FAi
1.3.1 Sole piece
bending moment MR and shear force QR in the rudder
The spring constant ZC for the support in the solepiece (see
body.
Fig 11) is to be obtained, in N/m, from the following for-
1.1.2 Calculation of forces and moments mula:
1.3.2 Rudder horn with 1-elastic support K11, K22, K12: Rudder horn compliance constants obtained,
The spring constant ZP for the support in the rudder horn in m/N, from the following formulae:
(see Fig 12 and Fig 13) is to be obtained, in N/m, from the 3 2
e
following formula: K 11 = 1, 3 ------------- + ------------
3EJ 1h GJ th
3 2 2
1
Z P = -------------- (d ) e
fB + fT K 12 = 1, 3 ------------- + --------------------------- + ------------
3EJ 1h 2EJ 1h GJ th
3 2 2 3 2
where: (d ) (d ) (d ) e d
K 22 = 1, 3 ------------- + --------------------------- + --------------------------- + ------------------- + -------------
3EJ 1h EJ 1h EJ 1h 3EJ 2h GJ th
fB : Unit displacement of rudder horn due to a unit
force of 1 N acting in the centroid of the rudder where:
horn, to be obtained, in m/N, from the follow-
ing formula: d : Height of the rudder horn, in m, defined in Fig
14 and Fig 15. This value is measured down-
d3 wards from the upper rudder horn end, at the
f B = 1 ,3 ----------- 10
8
3EJ N point of curvature transition, till the mid-line of
fT : Unit displacement due to torsion, in m/N, to be the lower rudder horn pintle
obtained, in case of a rudder horn with a hol- : Length, in m, as defined in Fig 14 and Fig 15.
low cross section, from the following formula: This length is measured downwards from the
de 2 ui upper rudder horn end, at the point of curvature
f T = --------------2
4GF T ---t-
i
transition, till the mid-line of the upper rudder
i
horn bearing. For = 0, the above formulae
with: converge to those given in [1.3.2], in case of a
rudder horn with a hollow cross-section
d : Height, in m, of the rudder horn as defined in
Fig 12 and Fig 13. This value is measured down- e : Rudder-horn torsion lever, in m, as defined in
wards from the upper rudder horn end, at the Fig 14 and Fig 15 (value taken at z = d/2)
point of curvature transition, till the mid-line of
the lower rudder horn pintle J1h : Moment of inertia of rudder horn about the
x axis, in m4, for the region above the upper
JN : Moment of inertia of rudder horn about the x rudder horn bearing. Note that J1h is an average
axis, in cm4 value over the length (see Fig 15)
e : Rudder-horn torsion lever, in m, as defined in
J2h : Moment of inertia of rudder horn about the x
Fig 12 and Fig 13(value taken at z = d/2)
axis, in m4, for the region between the upper
FT : Mean of areas enclosed by outer and inner and lower rudder horn bearings. Note that J2h is
boundaries of the thin walled section of rudder an average value over the length d (see Fig
horn, in m2 15)
ui : Length, in mm, of the individual plates forming Jth : Torsional stiffness factor of the rudder horn, in
the mean horn sectional area
m4 .
ti : Thickness of the individual plates mentioned
For any thin wall closed section:
above, in mm.
2
1.3.3 Rudder horn with 2-conjugate elastic supports 4F T
J th = ------------
ui
The 2-conjugate elastic supports are defined by the follow- ----
ti
ing equations: i
FA1, FA2 : Horizontal support forces, in N, at the lower Note that the Jth value is taken as an average
and upper rudder horn bearings, respectively value, valid over the rudder horn height.
FA1 = FA2 = FA3 = CR / 3 maximum bending moment in the rudder stock, in Nm:
FA4 = 0 MB = 0
MR1
MR2 FA2
MB FA3
l40 J40
l30 J30
PR
J10
l10
FA1
l20 J20
J50 Load Zc M Q
l50
MR1
MR2 FA2
MB FA3
l40 J40
FA1
l20 J20 d
d/ 2
e Zp
l10 J10
PR10
Load M Q
MR
MB1
FA2
MB2 FA3
l40 J40
l30 J30
PR
l10 J10
FA1
l20
J20
J50 Load Zc M Q
l50
l30 J30
l20 J20
C2
J10 PR
l10
C1
Load M Q
1.4.6 Rudder type 6a The force per unit length pR acting on the lower part of the
The rudder structure is to be calculated according to load, rudder body is to be obtained, in N/m, from the following
shear force and bending moment diagrams shown in Fig 4. formula:
The force per unit length pR acting on the rudder body is to p R20 p R10
p Rz = p R10 + ------------------------- z
be obtained, in N/m, from the following formula: 10
l20
A1
Z=l10
A2
l10
PR
Z=0
Load M Q
1.4.8 Rudder type 6c A2 : Rudder blade area, in m2, located below the
This type of rudder provides a more general solution for the lower rudder stock bearing
scantling of spade rudders with rudder trunks continued CG2 : Vertical position, in m, of the centre of gravity of
into the rudder blade. There is no limitation on the location the rudder blade area A2 , to be taken from the
of the centre of gravity of the total rudder blade area, which bottom of the rudder blade.
may be located either below the lower rudder stock bearing
or slightly above it. The rudder structure is to be calculated The bending moment MR, in Nm, for the scantling of the
according to load, shear force and bending moment dia- rudder blade, shall be taken as the greatest of the following
grams shown in Fig 6. values:
M_CR2 = CR2 (10 CG2)
The force per unit length pR acting on the lower part of the
rudder body is to be obtained, in N/m, from the following M_CR1 = CR1 (CG1 10)
formula:
where:
p R20 p R10
p Rz = p R10 + ------------------------- z M_CR2 : Bending moment, in Nm, induced by the rud-
10
der force CR2 (M_CR2 is assumed to be of a nega-
where: tive sign)
z : Position of rudder blade section, in m, taken M_CR1 : Bending moment, in Nm, induced by the rud-
over 10 length der force CR1 (M_CR1 is assumed to be of a posi-
tive sign)
pRz : Force per unit length, in N/m, obtained at the z
CR1 : Force, in N, acting on the rudder blade area A1,
position
to be calculated in accordance with Ch 9, Sec
pR10 : Force per unit length, in N/m, obtained for z 1, [2.2.3]
equal to zero
A1 : Rudder blade area, in m2, located above the
pR20 : Force per unit length, in N/m, obtained for z lower rudder stock bearing
equal to 10. CG1 : Vertical position, in m, of the centre of gravity of
The values of pR10 and pR20 are obtained from the following the rudder blade area A1 , to be taken from the
two equations: bottom of the rudder blade.
The bending moment MB, in Nm, for the scantling of the
2C R2 ( 2 10 3 CG2 )
p R10 = -----------------------------------------------
2
- lower rudder stock diameter, is given by the algebraic sum
10 of M_CR2 and M_CR1, as follows:
2C R2 ( 3 CG2 10 )
p R20 = -------------------------------------------
2
- MB = M_CR2 + M_CR1
10
The reaction forces FA2 and FA3, in N, may be determined as
where: follows:
CR2 : Force, in N, acting on the rudder blade area A2,
FA3 = MB / (20 + 30)
to be calculated in accordance with Ch 9, Sec
1, [2.2.3] FA2 = (CR1 + CR2 + FA3)
MR FA3
30
A1
20 MCR1
Z=10
CR1
ZTRU
A2
10
PR
Z=0
Load M Q
The forces per unit length pR10 and pR20 acting on the rudder The forces per unit length pR10 and pR20 acting on the rudder
body are to be obtained, in N/m, from the following formu- body are to be obtained, in N/m, from the following formu-
lae: lae:
C R2 C R2
p R10 = -------
- p R10 = -------
-
10 10
C R1 C R1
p R20 = -------
- p R20 = -------
-
where: with:
MB FA3
40 J40
30 J30
e Zp
10
J10 PR10
Load M Q
MR FA2
MB FA3
J40
l40
Zp
e
PR10
l10 J10
Load M Q
C R2 C R2
p R10 = -------
- p R10 = -------
-
10 10
C R1 C R1
p R20 = -------
- p R20 = -------
-
with: with:
= 20 = 20 + 30
The stiffness properties of the 2-conjugate elastic supports The stiffness properties of the 2-conjugate elastic supports
are to be calculated according to [1.3.3]. are to be calculated according to [1.3.3].
MR FA2
MB FA3
l40 J40
J1h
l30 J30
Jth
PR20
d k11, k12
l20 J20 k12, k22
J2h d/2 FA1
e
l10 J10
PR10
Load M Q
MR FA2
MB FA3
J40
40
J1h
30 J30 PR20
d
20 J20 Jth
k11, k12
k12, k22
FA1
d/2
J2h
e
10 J10
PR10
Load M Q
FA1 : Supporting force, in N, in the pintle bearing, to MS : Bending moment, in Nm, at the section consid-
be determined according to [1.4], for the rele- ered, as defined in [1.5.1]
vant type of rudder
FA1 : Force, in N, defined in [1.5.1]
x : Distance, in m, defined in Fig 11. WZ : Section modulus, in cm3, around the vertical
axis Z (see Fig 11)
Figure 11 : Solepiece geometry
AS : Shear sectional area, in mm2, in a plane perpen-
Z dicular to the X axis of the solepiece.
F A1
S = ------- e
AH
l10 J10
FA1 : Force, in N, defined in [1.6.1]
AH : Effective shear sectional area of the rudder horn,
in mm2, in y-direction
FA1 : Support force at the rudder horn lower-support, 1.7.4 Shear stress calculation
in N, to be obtained according to [1.4], for the a) For a generic section of the rudder horn, located
relevant type of rudder between its lower and upper bearings, the following
FA2 : Support force at the rudder horn upper-support, stresses are to be calculated:
in N, to be obtained according to [1.4], for the S : Shear stress, in N/mm2, to be obtained from
relevant type of rudder the following formula:
z : Distance, in m, defined in Fig 15, to be taken F A1
S = -------
less than the distance d, in m, defined in the AH
same figure
T : Torsional stress, in N/mm2, to be obtained
dlu : Distance, in m, between the rudder-horn lower for hollow rudder horn from the following
and upper bearings (according to Fig 14, formula:
dlu = d ).
M T 10 3
T = ----------------
2F T t H
Figure 14 : Rudder and rudder horn geometries
(2-conjugate elastic supports) For solid rudder horn, T is to be considered
by the Society on a case-by-case basis
b) For a generic section of the rudder horn, located in the
region above its upper bearing, the following stresses
are to be calculated:
l40 J40 S : Shear stress, in N/mm2, to be obtained from
the following formula:
l30 J30 F A1 + F A2
S = ---------------------
-
AH
d T : Torsional stress, in N/mm2, to be obtained
for hollow rudder horn from the following
l20 J20 d/2 formula:
M T 10 3
T = ----------------
2F T t H
e For solid rudder horn, T is to be considered
l10 by the Society on a case-by-case basis
J10 where:
FA1, FA2 : Support forces, in N, defined in [1.7.1]
AH : Effective shear sectional area of the rudder horn,
1.7.2 Shear force in mm2, in y-direction
The shear force QH acting on the generic section of the rud- MT : Torque, in Nm, defined in [1.7.3]
der horn is to be obtained, in N, from the following formu- FT : Mean of areas enclosed by outer and inner
lae: boundaries of the thin walled section of rudder
between the lower and upper rudder horn bearings: horn, in m2
tH : Plate thickness of rudder horn, in mm. For a
QH = FA1
given cross section of the rudder horn, the max-
above the rudder horn upper-bearing: imum value of T, is obtained at the minimum
QH = FA1 + FA2 value of tH .
FA2 TRU FA2
TRU
X
MBH QH
Mid-line of
the lower rudder dITRU
stock bearing
section
dOTRU
Chapter 10
1.2.1 All salt water ballast spaces with boundaries formed 3.2.3 Where the double bottom is intended to carry water,
by the hull envelope are to have a corrosion protective coat- ceiling on the inner bottom may lie next to the plating, pro-
ing, epoxy or equivalent, applied in accordance with the vided a suitable protective composition is applied before-
manufacturer's requirements. hand.
For ships assigned with the additional service feature or the 3.2.4 The Shipyard is to take care that the attachment of
additional class notation CPS (WBT) according to Pt A, Ch ceiling does not affect the tightness of the inner bottom.
1, Sec 2, [4.3.2], Pt A, Ch 1, Sec 2, [4.4.2] and Pt A, Ch 1,
Sec 2, [6.15.4], reference is to be made to NR 530 Coating 3.2.5 In single bottom ships, ceiling is to be fastened to the
Performance Standard. reversed frames by galvanised steel bolts or any other equiv-
alent detachable connection.
1.2.2 Corrosion protective coating is not required for inter-
A similar connection is to be adopted for ceiling over the
nal surfaces of spaces intended for the carriage of cargo oil
lateral bilges in double bottom ships.
or fuel oil.
2 Protection against galvanic Where the floor spacing is large, the thicknesses may be
considered by the Society on a case by case basis.
corrosion in tanks
4 Protection of decks by wood
2.1 General
sheathing
2.1.1 Non-stainless steel is to be electrically insulated from
stainless steel or from aluminium alloys. 4.1 General
2.1.2 Where stainless steel or aluminium alloys are fitted in 4.1.1 Where decks are intended to carry specific loads,
the same tank as non-stainless steel, a protective coating is such as caterpillar trucks and unusual vehicles, the Society
to cover both materials. may require such decks wood sheathed.
4.4.2 Data verification approval - Endorsed test An installation test is also to be carried out on the second
conditions nominated computer, when applicable as indicated in Pt C,
The Society is to verify the results and actual ship data used Ch 3, Sec 6, [2.4.1], which would be used in the event of
by the calculation program for the particular ship on which failure of the first computer. Where the installation test is
the program will be installed. carried out on a type approved computer, a second nomi-
nated computer and test are not required.
Upon application for data verification, the Society is to
advise the applicant of a minimum of four loading condi- Subject to the satisfactory completion of installation tests, the
tions, taken from the ships approved loading manual, Societys Surveyor endorses the test conditions, adding details
which are to be used as the test conditions. Within the of the place and the date of the installation test survey, as well
range of these test conditions, each compartment is to be as the Society stamp and the Surveyors signature.
loaded at least once. The test conditions normally cover the
4.4.5 Operational manual
range of load draughts from the deepest envisaged loaded
condition to the light ballast condition. In addition, the A uniquely identified ship specific operational manual is to
lightship test condition is to be submitted. be submitted to the Society for documentation.
When the loading instrument also performs stability calcu- The operational manual is to be written in a concise and
lations, it is to cover all the stability requirements applicable unambiguous manner. The use of illustrations and flow-
to the ship. The test conditions are to be taken from the charts is recommended.
ships approved trim and stability booklet. The operational manual is to contain:
The data indicated in [4.4.3] and contained in the loading a general description of the program denoting identifi-
program are to be consistent with the data specified in the cation of the program and its stated version number
approved loading manual. Particular attention is drawn to details of the hardware specification needed to run the
the final lightship weight and centres of gravity derived from loading program
the inclining experiment or lightweight check. a description of error messages and warnings likely to
The approval of the computer application software is based be encountered, and unambiguous instructions for sub-
on the acceptance of the results of the test conditions sequent actions to be taken by the user in each case
according to [4.5], [4.6], [4.7], and [4.8], as applicable. where applicable, the shear force correction factors
When the requested information has been submitted and where applicable, the local permissible limits for single
the results of the test conditions are considered satisfactory, and two adjacent hold loadings as a function of the
the Society endorses the test conditions, a copy of which is appropriate draught and the maximum weight for each
to be available on board. hold
where applicable, the Societys restrictions (maximum
4.4.3 Data to be submitted allowable load on double bottom, maximum specific
The following data, submitted by the applicant, are to be gravity allowed in liquid cargo tanks, maximum filling
consistent with the as-built ship: level or percentage in liquid cargo tanks)
identification of the calculation program including the example of a calculation procedure supported by illus-
version number trations and sample computer output
main dimensions, hydrostatic particulars and, if applica- example computer output of each screen display, com-
ble, ship profile plete with explanatory text.
position of the forward and after perpendiculars and, if
4.4.6 Calculation program specifications
appropriate, the calculation method to derive the for-
The software is to be written so as to ensure that the user
ward and after draughts at the actual position of the
cannot alter the critical ship data files containing the fol-
ships draught marks
lowing information:
ship lightweight and lightweight distribution along the
lightship weight and lightship weight distribution and
ships length
associated centres of gravity
lines plans and/or offset tables the Societys structural limitations or restrictions
compartment definitions, including frame spacing and geometric hull form data
centre of volumes, together with capacity tables (sound-
hydrostatic data and cross curves, where applicable
ing/ullage tables), if appropriate
compartment definitions, including frame spacing and
deadweight definitions for each loading condition.
centre of volumes, together with capacity tables (sound-
4.4.4 Installation testing ing/ullage tables), if appropriate.
During the installation test, one of the ships senior officers Any changes in the software are to be made by the manu-
is to operate the loading instrument and calculate the test facturer or his appointed representative and the Society is to
conditions. This operation is to be witnessed by a Surveyor be informed immediately of such changes. Failure to advise
of the Society. The results obtained from the loading instru- of any modifications to the calculation program may invali-
ment are to be identical to those stated in the endorsed test date the approval issued. In cases where the approval is
conditions. If the numerical output from the loading instru- considered invalid by the Society, the modified calculation
ment is different from the endorsed test conditions, no program is to be re-assessed in accordance with the
approval will be confirmed. approval procedure.
4.4.7 Functional specification Additional read-out points may be required between bulk-
The calculation program is to be user-friendly and designed heads of long holds or tanks, or between container stacks.
such that it limits possible input errors by the user. Where the still water torsion moments are required to be
The forward, midship and after draughts, at the respective calculated, one test condition is to demonstrate such a cal-
perpendiculars, are to be calculated and presented to the culation.
user on screen and hardcopy output in a clear and unam- The calculated forces and moments are to be displayed in
biguous manner. both graphical and tabular formats, including the percent-
age of permissible values. The screen and hardcopy output
It is recommended that the forward, midship and after
is to display the calculated forces or moments, and the cor-
draughts, at the actual position of the ships draught marks
responding permissible limits, at each specified read-out
are calculated and presented to the user on screen and hard
point. Alternative limits may be considered by the Society
copy output in a clear and unambiguous manner.
on a case by case basis.
The displacement is to be calculated for the specified load-
ing condition and corresponding draught readings and pre- 4.5.2 Acceptable tolerances
sented to the user on screen and hardcopy output. The accuracy of the calculation program is to be within the
acceptable tolerance band, specified in Tab 2, of the results
The loading instrument is to be capable of producing print-
at each read-out point obtained by the Society, using an
outs of the results in both numerical and graphical forms.
independent program or the approved loading manual with
The numerical values are to be given in both forms, as abso-
identical input.
lute values and as the percentage of the permissible values.
This print-out is to include a description of the correspond- Table 2 : Tolerance band for the comparison
ing loading condition. of computational accuracy
All screen and hardcopy output data is to be presented in a
clear and unambiguous manner with an identification of the Tolerance (percentage of the
Computation
calculation program (the version number is to be stated). permissible values)
Still Water Shear Force 5%
4.5 Hull girder forces and moments Still Water Bending Moment 5%
Still Water Torsion Moment, 5%
4.5.1 General where applicable
The loading program is to be capable of calculating the fol-
4.5.3 Permissible limits and restrictions
lowing hull girder forces and moments in accordance with
Ch 5, Sec 2, [2]: The user is to be able to view the following Society struc-
tural limitations in a clear and unambiguous manner:
Still Water Shear Force (SWSF) including the shear force
all permissible still water shear forces and still water
correction, where applicable
bending moments
Still Water Bending Moment (SWBM) where applicable, the permissible still water torsion
Still Water Torsion Moment (SWTM), where applicable moments
For ships with relatively large deck openings, additional where applicable, all local loading limits both for one
considerations such as torsional loads are to be consid- hold and for adjacent hold loadings
ered. cargo hold weight
The data which are to be provided to, or accepted by, the ballast tank/hold capacities
Society are specified in Tab 1. filling restrictions.
Read-out points are usually to be selected at the position of It is to be readily apparent to the user when any of the struc-
the transverse bulkheads or other obvious boundaries. tural limits has been exceeded.
4.6 Intact stability In such case, the loading instrument is also to perform intact
stability calculations, and therefore the approval is to be
4.6.1 Application based on the requirements specified in [4.6].
The loading instrument approval for stability purposes is Additional requirements relevant to grain stability are pro-
required when a loading instrument to be installed on vided in [4.7.2] and [4.7.3].
board a ship performs stability calculations, as stated in
[4.3.6]. 4.7.2 Data verification approval - Endorsed test
conditions
4.6.2 Data verification approval - Endorsed test The requirements stated in [4.6.2] apply. In addition, when
conditions
the ship is allowed to carry grain in slack hold, at least one
The requirements in [4.4.2] apply. In addition, at least one of the four loading conditions required is to include par-
of the four loading conditions required is to show the com- tially filled holds.
partments, intended for liquid loads in which the free sur-
face effect is considerable, filled in order to have the The additional data necessary for the approval of the load-
maximum free surface moment. ing instrument for grain stability purposes are specified in
[4.7.3].
The additional data necessary for the approval of the load-
ing instrument for stability purposes are specified in [4.6.3]. In order to obtain the approval of the loading instrument, all
the grain stability requirements and relevant criteria speci-
In order to obtain the approval of the loading instrument, all fied in Pt D, Ch 4, Sec 3, [1.2] are to be available in the
the intact stability requirements (and relevant criteria) appli- computer output.
cable to the ship, reported in Ch 3, Sec 2 as well as in Part
D, are to be available in the computer output; the lack of In addition, the outputs are to include:
any one of them is sufficient to prevent the endorsement of the reference to the type of calculation (trimmed or
the test conditions. untrimmed ends)
the value of the actual grain heeling moment for each
4.6.3 Additional data to be submitted hold
In addition to the data required in [4.4.3], the following are
the value of the maximum permissible grain heeling
to be submitted:
moment for each hold
cross curves of stability calculated on a free trimming
the total value of the actual grain heeling moment
basis, for the ranges of displacement and trim antici-
pated in normal operating conditions, with indication of the total value of the maximum permissible grain heel-
the volumes which have been considered in the compu- ing moment.
tation of these curves The lack of any of the above is sufficient to prevent the
capacity tables indicating, for each compartment or endorsement of the test conditions.
space, the values of the co-ordinates XG, YG and ZG of
the centre of gravity, as well as the inertia, correspond- 4.7.3 Additional data to be submitted
ing to an adequate number of filling percentages In addition to the data required in [4.6.3], the following are
list of all the openings (location, tightness, means of clo- to be submitted:
sure), pipes or other sources which may lead to progres- calculation of the total grain heeling moment
sive flooding calculation of the maximum permissible total grain
deadweight definitions for each loading condition in heeling moment as a function of the draught (or dis-
which, for any load taken into account, the following placement) and maximum KG
information is to be specified: curves or tables of volume, centre of volume and volu-
- weight and centre of gravity co-ordinates metric heeling moment for partially filled compartments
- percentage of filling (if liquid load) (if applicable)
- free surface moment (if liquid load) for filled holds: volumetric heeling moment for trimmed
and/or untrimmed ends, as applicable, including tem-
information on loading restrictions (maximum filling
porary bulkheads, if any.
level or percentage in liquid cargo tanks, maximum KG
or minimum GM curve or table which can be used to
determine compliance with the applicable intact and 4.8 Damage stability
damage stability criteria), when applicable
4.8.1 Application
all the intact stability criteria applicable to the ship con-
The loading instrument approval for stability purposes is
cerned.
required when a loading instrument to be installed on
board a ship performs damage stability calculations, as
4.7 Grain loading stated in [4.3.6].
4.7.1 Application In such case, the loading instrument is also to perform intact
The loading instrument approval for stability purposes is stability calculations, and therefore the approval is to be
required when a loading instrument to be installed on based on the requirements specified in [4.6].
board a ship performs grain loading stability calculations, as Additional requirements relevant to damage stability are
stated in [4.3.6]. given in [4.8.2] and [4.8.3].
4.8.2 Data verification approval - Endorsed test This information is to be taken from the approved dam-
conditions age stability documentation, and the source details are
The requirements specified in [4.6.2] apply. to be clearly indicated; in the case of unavailability of
The additional data necessary for the approval of the load- such documentation, the above-mentioned information
ing instrument for stability purposes are specified in [4.8.3]. may be requested from the Society.
The approval of damage stability calculations performed by all the damage stability criteria applicable to the ship
a loading instrument is limited to those relevant to deter-
concerned.
ministic damage stability rules specified in Part D applica-
ble to ships with one of the service notations passenger
ship, oil tanker ESP, chemical tanker ESP or liquefied gas 4.9 Acceptable tolerances
carrier. In order to obtain the approval of the loading instru-
ment, all the damage stability requirements (and relevant
4.9.1 General
criteria) applicable to the ship are to be available in the
computer output. The lack of any one of them is sufficient to The acceptable tolerances for the stability particulars are to
prevent the endorsement of the test conditions. be in agreement with the requirements of IACS Unified
Requirements UR L5 as amended.
4.8.3 Additional data to be submitted
In addition to the data required in [4.6.3], the following are
to be submitted: 4.10 Operation manual
list of all the damage cases which are to be considered
in accordance with the relevant deterministic damage 4.10.1 General
stability rules. Each damage case is to clearly indicate
all the compartments or spaces taken into account, as A simple and straightforward operation manual is to be pro-
well as the permeability associated with each compart- vided, containing the information as mentioned in IACS
ment or space. Unified Requirements UR L5 as amended
Symbols
T : Scantling draught, in m Figure 1 : Bulk cargo hold
Geometrical characteristics
B : Density, in t/m3, of the dry bulk cargo carried
( b m3 + 2y HT 2b HT )b m3
2.2.1 Maximum mass P max = B H ----------------------------------------------------------
- ( h HT h DB ) V LS M DB
b HT
For any particular seagoing condition, the maximum mass
of cargo in each hold in terms of the draught at mid-length where:
of hold is given by:
b HT
- h 1 ,025-
b m3 = ---------------------- -------------- ( T 0 ,5h 1 T 1 )
1 ,025 h HT h DB m B
if h m --------------- ( T T 1 ) h HT h DB :
B
3.2 Maximum and minimum masses of 3.3 Maximum and minimum masses of
cargo in two adjacent holds in seagoing cargo in two adjacent holds in harbour
condition condition
Chapter 11
SECTION 3 TESTING
1.5.1 The structural plans to be submitted for approval, 2.2 Butt welding
according to Ch 1, Sec 3, are to contain the necessary data
relevant to the fabrication by welding of the structures and 2.2.1 General
items represented as far as class is concerned. In general, butt connections of plating are to be full penetra-
For important structures, the main sequences of prefabrica- tion, welded on both sides except where special procedures
tion, assembly and welding and non-destructive examina- or specific techniques, considered equivalent by the Soci-
tion planned are also to be represented in the plans. ety, are adopted.
Connections different from the above may be accepted by
1.5.2 A plan showing the location of the various steel types the Society on a case by case basis; in such cases, the rele-
is to be submitted at least for outer shell, deck and bulkhead vant detail and workmanship specifications are to be
structures. approved.
2.2.2 Welding of plates with different thicknesses 2.3.2 Fillet welding types
In the case of welding of plates with a difference in gross Fillet welding may be of the following types:
thickness equal to or greater than: continuous fillet welding, where the weld is constituted
3 mm, if the thinner plate has a gross thickness equal to by a continuous fillet on each side of the abutting plate
or less than 10 mm (see [2.3.3])
4 mm, if the thinner plate has a gross thickness greater intermittent fillet welding, which may be subdivided
than 10 mm, (see [2.3.4]) into:
a taper having a length of not less than 4 times the differ- - chain welding
ence in gross thickness is to be adopted for connections of - scallop welding
plating perpendicular to the direction of main stresses. For - staggered welding.
connections of plating parallel to the direction of main
stresses, the taper length may be reduced to 3 times the dif- 2.3.3 Continuous fillet welding
ference in gross thickness. Continuous fillet welding is to be adopted:
When the difference in thickness is less than the above val- for watertight connections
ues, it may be accommodated in the weld transition
between plates. for connections of brackets, lugs and scallops
at the ends of connections for a length of at least 75mm
2.2.3 Edge preparation, root gap where intermittent welding is not allowed, according to
Typical edge preparations and gaps are indicated in Ch 11, [2.3.4].
App 1, [1.2].
Continuous fillet welding may also be adopted in lieu of
The acceptable root gap is to be in accordance with the
intermittent welding wherever deemed suitable, and it is
adopted welding procedure and relevant bevel preparation.
recommended where the spacing p, calculated according
2.2.4 Butt welding on permanent backing to [2.3.4], is low.
Butt welding on permanent backing, i.e. butt welding 2.3.4 Intermittent welding
assembly of two plates backed by the flange or the face
The spacing p and the length d, in mm, of an intermittent
plate of a stiffener, may be accepted where back welding is
weld, shown in:
not feasible or in specific cases deemed acceptable by the
Society. Fig 1, for chain welding
The type of bevel and the gap between the members to be Fig 2, for scallop welding
assembled are to be such as to ensure a proper penetration Fig 3, for staggered welding
of the weld on its backing and an adequate connection to
the stiffener as required. are to be such that:
p
2.2.5 Section, bulbs and flat bars ---
d
When lengths of longitudinals of the shell plating and
strength deck within 0,6 L amidships, or elements in general where the coefficient is defined in Tab 2 and Tab 3 for the
subject to high stresses, are to be connected together by different types of intermittent welding, depending on the
butt joints, these are to be full penetration. Other solutions type and location of the connection.
may be adopted if deemed acceptable by the Society on a In general, staggered welding is not allowed for connec-
case by case basis. tions subjected to high alternate stresses.
The work is to be done in accordance with an approved One side continuous welding may be accepted instead of
procedure; in particular, this requirement applies to work chain and staggered intermittent welding for connections of
done on board or in conditions of difficult access to the stiffeners in the dry spaces of deckhouses and superstruc-
welded connection. Special measures may be required by tures, where not affected by sea pressure, tank pressure or
the Society. concentrated loads.
Welding of bulbs without a doubler is to be performed by In addition, the following limitations are to be complied
welders specifically certified by the Society for such type of with:
welding. chain welding (see Fig 1):
d 75 mm
2.3 Fillet welding
p d 200 mm
2.3.1 General
Figure 1 : Intermittent chain welding
Ordinary fillet welding may be adopted for T connections of
the various simple and composite structural elements,
where they are subjected to low tensile stress or where they
are not critical for fatigue.
Where this is not the case, partial or full T penetration weld- p d
ing according to [2.4] is to be adopted.
scallop welding (see Fig 2): staggered welding (see Fig 3):
d 75 mm d 75 mm
p d 150 mm p 2d 300 mm
v 0,25 b without being greater than 75 mm
p 2d for connections subjected to high alternate
stresses.
Figure 2 : Intermittent scallop welding
Figure 3 : Intermittent staggered welding
v b
p d
p d
Table 2 : Welding factors wF and coefficient for the various hull structural connections
Table 3 : Welding factors wF and coefficient for connections of primary supporting members
Figure 5 : Intermittent scallop fillet welding pS, pW : Still water and wave pressure, respectively, in
between cut-outs kN/m2, acting on the ordinary stiffener, defined
in Ch 7, Sec 2, [3.3.2]
S2, W2 : Partial safety factors defined in Ch 7, Sec 2,
[1.2.1]
k1 : Coefficient depending on the connection of the
Throat thickness a primary supporting member web with the ordi-
nary stiffener, taken equal to:
k1 = 0, when there is no primary supporting
member web stiffener in way of the ordinary
stiffener
the value defined in Ch 4, Sec 3, [4.7.2],
when there is a primary supporting member
1 2 3
=(i) web stiffener in way of the ordinary stiffener
b,c,d,u,v: Main dimensions, in mm, of the cut-out shown
in Fig 6.
2.3.8 Throat thickness of welds connecting
ordinary stiffeners with primary supporting Figure 6 : End connection of ordinary stiffener
members Dimensions of the cut-out
The throat thickness tT of fillet welds connecting ordinary
stiffeners and collar plates, if any, to the web of primary c
supporting members is to be not less than the value
obtained, in mm, from the following formula:
tT = 0,27 fyd tw + 0,7 g
where:
fyd : Correction factor taking into account the yield u d
v
strength of the weld deposit:
0, 5 0, 75
f yd = --- -----------
1 235
-
k weld
for full penetration welds: Fig 9 and Fig 10, in which f, 2.4.2 Lamellar tearing
in mm, is to be taken between 0 and 3 mm, and Precautions are to be taken in order to avoid lamellar tears,
between 45 and 60 which may be associated with:
Back gouging is generally required for full penetration cold cracking when performing T connections between
welds. plates of considerable thickness or high restraint
large fillet welding and full penetration welding on
Figure 7 : Partial penetration weld higher strength steels.
T
2.5 Lap-joint welding
f 2.5.1 General
Lap-joint welding may be adopted for:
= = peripheral connection of doublers
internal structural elements subjected to very low
stresses.
2.6.2 Dimensions
Figure 10 : Full penetration weld Slot welds are to be of appropriate shape (in general oval)
and dimensions, depending on the plate thickness, and may
6 not be completely filled by the weld.
Typical dimensions of the slot weld and the throat thickness
B of the fillet weld are given in Ch 11, App 1, [1.3].
=
The distance between two consecutive slot welds is to be
not greater than a value which is defined on a case by case
basis taking into account:
- the transverse spacing between adjacent slot weld lines
- the stresses acting in the connected plates
- the structural arrangement below the connected plates.
2.7.1 Plug welding may be adopted only when accepted by 3.5.1 The bar stem is to be welded to the bar keel generally
the Society on a case by case basis, according to specifi- with butt welding.
cally defined criteria. Typical details are given in Ch 11, The shell plating is also to be welded directly to the bar
App 1, [1.3]. stem with butt welding.
3.1.1 Corner joint welding, as adopted in some cases at the 3.7 Pillars connection
corners of tanks, performed with ordinary fillet welds, is
permitted provided the welds are continuous and of the 3.7.1 For pillars in tension, continuous fillet welding may
required size for the whole length on both sides of the joint. be accepted provided that the tensile stress in welds does
not exceed 50/k N/mm2, where k is the greatest material
3.1.2 Alternative solutions to corner joint welding may be factor of the welded elements and the filler metal.
considered by the Society on a case by case basis.
For pillars subjected to higher tensile stress, full penetration
welding is to be adopted.
3.2 Bilge keel connection
4 Workmanship
3.2.1 The intermediate flat, through which the bilge keel is
connected to the shell according to Ch 4, Sec 4, [6], is to be
welded as a shell doubler by continuous fillet welds. 4.1 Welding procedures and consumables
The butt welds of the doubler and bilge keel are to be full 4.1.1 The various welding procedures and consumables
penetration and shifted from the shell butts. are to be used within the limits of their approval and in
accordance with the conditions of use specified in the
The butt welds of the bilge plating and those of the doublers
respective approval documents.
are to be flush in way of crossing, respectively, with the
doubler and with the bilge keel.
4.2 Welding operations
Butt welds of the intermediate flat are to be made to avoid
direct connection with the shell plating, in order that they 4.2.1 Weather protection
do not alter the shell plating, by using, for example, a cop- Adequate protection from the weather is to be provided to
per or a ceramic backing. parts being welded; in any event, such parts are to be dry.
In welding procedures using bare, cored or coated wires
3.3 Struts connecting ordinary stiffeners with gas shielding, the welding is to be carried out in
weather protected conditions, so as to ensure that the gas
3.3.1 In case of a strut connected by lap joint to the ordi- outflow from the nozzle is not disturbed by winds and
nary stiffener, the throat thickness of the weld is to be draughts.
obtained, in mm, from the following formula:
4.2.2 Butt connection edge preparation
F
t T = ------------- 10
3
The edge preparation is to be of the required geometry and
n W
correctly performed. In particular, if edge preparation is car-
where: ried out by flame, it is to be free from cracks or other detri-
mental notches.
F : Maximum force transmitted by the strut, in kN
: Safety factor, to be taken equal to 2 4.2.3 Surface condition
n : Number of welds in way of the strut axis The surfaces to be welded are to be free from rust, moisture
and other substances, such as mill scale, slag caused by
W : Length of the weld in way of the strut axis, in oxygen cutting, grease or paint, which may produce defects
mm in the welds.
: Permissible shear stress, to be taken equal to Effective means of cleaning are to be adopted particularly in
100 N/mm2. connections with special welding procedures; flame or
mechanical cleaning may be required.
3.4 Connection between propeller post and The presence of a shop primer may be accepted, provided it
propeller shaft bossing has been approved by the Society.
Shop primers are to be approved by the Society for a spe-
3.4.1 Fabricated propeller posts are to be welded with full cific type and thickness according to NR216 Materials and
penetration welding to the propeller shaft bossing. Welding, Ch 5, Sec 3.
t g
Moreover, during the welding operation afloat, loading con- When any serious or systematic defect is detected either in
ditions are to be adjusted in order to have an acceptable the welded connections or in the base material, the manu-
level of longitudinal stress. facturer is required to promptly inform the Surveyor and
Note 1: As a general guidance, the level of longitudinal stress dur- submit the repair proposal.
ing the welding operation is to be below 50 MPa in the concerned The Surveyor may require destructive or non-destructive
area; however, lower limits may be requested by the surveyor examinations to be carried out for initial identification of
depending on the specificities of the ship and/or welding.
the defects found and, in the event that repairs are under-
taken, for verification of their satisfactory completion.
4.2.11 Interpass cleaning
After each run, the slag is to be removed by means of a
chipping hammer and a metal brush; the same precaution is 5.4 Repairs on structures already welded
to be taken when an interrupted weld is resumed or two
5.4.1 In the case of repairs involving the replacement of
welds are to be connected.
material already welded on the hull, the procedures to be
4.2.12 Stress relieving adopted are to be agreed with the Society on a case by case
basis.
It is recommended and in some cases it may be required that
special structures subject to high stresses, having complex
shapes and involving welding of elements of considerable 6 Inspections and checks
thickness (such as rudder spades and stern frames), are pre-
fabricated in parts of adequate size and stress-relieved in the 6.1 General
furnace, before final assembly, at a temperature within the
range 550C 620C, as appropriate for the type of steel. 6.1.1 Materials, workmanship, structures and welded con-
nections are to be subjected, at the beginning of the work,
4.3 Crossing of structural elements during construction and after completion, to inspections by
the Shipbuilder suitable to check compliance with the
4.3.1 In the case of T crossing of structural elements (one applicable requirements, approved plans and standards.
element continuous, the other physically interrupted at the
crossing) when it is essential to achieve structural continuity 6.1.2 The Shipbuilder is to make available to the Surveyor a
through the continuous element (continuity obtained by list of the manual welders and welding operators and their
means of the welded connections at the crossing), particular respective qualifications.
care is to be devoted to obtaining the correspondence of the The Shipbuilder's internal organisation is responsible for
interrupted elements on both sides of the continuous ele- ensuring that welders and operators are not employed
ment. Suitable systems for checking such correspondence under improper conditions or beyond the limits of their
are to be adopted. respective valid qualifications and that welding procedures
are adopted within the approved limits and under the
5 Modifications and repairs during appropriate operating conditions.
construction 6.1.3 The Shipbuilder is responsible for ensuring that the
operating conditions, welding procedures and work sched-
5.1 General ule are in accordance with the applicable requirements,
approved plans and recognised good welding practice.
5.1.1 Deviations in the joint preparation and other speci-
fied requirements, in excess of the permitted tolerances and 6.1.4 The Shipbuilder is responsible for ensuring that non-
found during construction, are to be repaired as agreed with destructive examination (NDE) procedures and plans are
the Society on a case by case basis. adhered to during the construction and that NDE reports are
made available to the Society.
5.2 Gap and weld deformations
6.2 Non-destructive examination
5.2.1 Welding by building up of gaps exceeding the
required values and repairs of weld deformations may be 6.2.1 Non-destructive examination techniques refer to the
accepted by the Society upon special examination. testing methods applicable to the detection of surface
imperfections (Visual Testing, Magnetic particle Testing, Liq-
uid penetrant Testing) or sub-surface imperfections (Ultra-
5.3 Defects sonic Testing, Radiographic Testing).
5.3.1 Defects and imperfections on the materials and 6.2.2 NDE of hull welds are to be performed in accordance
welded connections found during construction are to be with written procedures accepted by the Society. Such pro-
evaluated for possible acceptance on the basis of the appli- cedures are to contain appropriate details about the applied
cable requirements of the Society. codes or standards, testing method, equipment, calibration,
Where the limits of acceptance are exceeded, the defective testing conditions and personnel qualification. For each
material and welds are to be discarded or repaired, as NDE technique, appropriate details means typically the
deemed appropriate by the Surveyor on a case by case basis. details described in IACS Recommendation 20.
6.2.3 The NDE acceptance criteria defined by the Ship- 6.3.2 As far as automatic welding of the panels butt welds
builder are to be submitted to the Society and should com- during the premanufacturing stage is concerned, the Ship-
ply with the IACS Recommendation 20 or with a recognized builder is to carry out random non-destructive testing of the
standard which has been accepted by the Society. welds (radiographic or ultrasonic testing) in order to ascertain
Where applicable, specific criteria defined in Ch 11, Sec 2, the regularity and the constancy of the welding inspection.
for special structural details are to be refered to.
6.3.2 In the midship area, radiographies are to be taken at
6.2.4 All finished welds are to be subjected to visual testing the joinings of panels.
by the Shipbuilder's qualified personnel. Each radiography is situated in a butt joint at a cross-shaped
welding.
6.2.5 After completion of the welding operation and work-
shop inspection, the structure is to be presented to the Sur- In a given ship cross-section bounded by the panels, a radi-
veyor for general visual examination at a suitable stage of ography is to be made of each butt of sheerstrake, stringer,
fabrication. bilge and keel plate; in addition, the following radiogra-
phies are to be taken:
As far as possible, the results on non-destructive examina-
tions are to be submitted. bottom plating: two
deck plating: two
6.2.6 Radiographic testing is to be carried out on the
welded connections of the hull in accordance with [6.3]. side shell plating: two each side.
The results are to be made available to the Society. The sur-
For ships where B + D 15 m, only one radiography for
veyor may require to witness some testing preparations.
each of the above items is required.
6.2.7 The Society may accept radiographic testing to be This requirement remains applicable where panel butts are
replaced by ultrasonic testing. shifted or where some strakes are built independently from
the panels. It is recommended to take most of these radiog-
6.2.8 The Shipbuilder's NDE plan describing the extent, raphies at the intersections of butt and panel seams.
type and location of NDE is to be submitted to the Society
for acceptance. Still in the midship area, radiographic testing is to be carried
out, at random, of the following main members of the struc-
6.2.9 When the non-destructive examinations reveal the ture:
presence of unacceptable indications, the relevant connec- butts of continuous longitudinal bulkheads
tion is to be repaired to an extent and according to a proce-
dure agreed with the Surveyor. butts of longitudinal stiffeners, deck and bottom girders
contributing to the overall strength
The repaired zone is then to be submitted to non-destruc-
tive examination, using a method deemed suitable by the assembly joints of insert plates at the corners of the
Surveyor to verify that the repair is satisfactory. openings.
Additional examinations may be required by the Surveyor Moreover, radiographic testing is to be carried out, at ran-
on a case by case basis. dom, of the weldings of the bilge keel and of intermediate
flat.
6.2.10 Ultrasonic and magnetic particle testing may also be
required by the Surveyor in specific cases to check the base 6.3.4 Outwards the midship area, a programme of radio-
material. graphic testing at random is to be set up by the Shipbuilder
in agreement with the Surveyor for the major points. It is
further recommended:
6.3 Radiographic testing
to take a number of radiographies of the very thick parts
6.3.1 Radiographic testing is to be carried out on the and those comprising restrained joint, such as stern-
welded butts of shell plating, strength deck plating as well frames, shaft brackets, stabiliser recesses, masts
as of members contributing to the longitudinal strength. to take a complete set of radiographies or to increase the
Radiographic Testing may also be required for the joints of number of radiographies for the first joint of a series of
members subject to heavy stresses. identical joints. This recommendation is applicable not
only to the assembly joints of prefabricated members
The requirements [6.3.2] to [6.3.5] constitute general rules:
completed on the slip, but also to joints completed in
the number of radiographs may be increased where
the workshop to prepare such prefabricated members.
requested by the Surveyor, mainly where visual inspection
or radiographic soundings have revealed major defects, spe- 6.3.3 Where a radiography is rejected and where it is
cially for butts of sheerstrake, stringer plate, bilge strake or decided to carry out a repair, the Shipbuilder is to deter-
keel plate. mine the length of the defective part, then a set of radiogra-
Provisions alteration to these rules may be accepted by the phies of the repaired joint and of adjacent parts is to be
Society when justified by the organisation of the Ship- taken. Where the repair has been decided by the inspection
builder or of the inspection department; the inspection is office of the Shipbuilder, the film showing the initial defect
then to be equivalent to that deduced from [6.3.2] to is to be submitted to the Surveyor together with the film
[6.3.5]. taken after repair of the joint.
Symbols
TB : Ships draft in light ballast condition, see Ch 5, 1.2.2 Fatigue check requirements
Sec 1, [2.4.3].
Where a fatigue check is to be carried out, the design
requirements specify (see Ch 7, Sec 4, [1.1]):
1 General
the locations (hot spots) where the stresses are to be cal-
1.1 Application culated and the fatigue check performed
1.1.3 Special structural details are those listed in [2] 1.4.1 Material requirements specify the material quality to
together with the specific requirements which are to be ful- be used for specific elements which constitute the detail,
filled. depending on their manufacturing procedure, the type of
Other structural details may be considered by the Society as stresses they are subjected to, and the importance of the
special details, when deemed necessary on the basis of the detail with respect to the ship operation and overall safety.
criteria in [1.1.1]. The criteria to be fulfilled in such cases
are defined by the Society on a case by case basis. In addition, these requirements specify where material
inspections are to be carried out.
1.1.4 As regards matters not explicitly specified in [2], the
Rule requirements are to be complied with in any event; in
particular: 1.5 Welding requirements
Part B, Chapter 4 for design principles and structural
arrangements 1.5.1 Welding requirements specify where partial or full T
penetration welding (see Ch 11, Sec 1, [2.4]) or any particu-
Part B, Chapter 7, for structural scantling
lar welding type or sequence is to be adopted. In addition,
Part B, Chapter 11 for construction and welding these requirements specify when welding procedures are to
requirements be approved.
the applicable requirements in Part D and Part E.
Since weld shape and undercuts are influencing factors on
1.2 Design requirements fatigue behaviour, fillet welds are to be elongated in the
direction of the highest stresses and care is to be taken to
1.2.1 General requirements avoid undercuts, in particular at the hot spots.
Design requirements specify:
the local geometry, dimensions and scantlings of the 1.6 Survey requirements
structural elements which constitute the detail
any local strengthening 1.6.1 Survey requirements specify where non-destructive
the cases where a fatigue check is to be carried out examinations of welds are to be carried out and, where this
according to Ch 7, Sec 4. is the case, which type is to be adopted.
Area
Reference tables
reference Area description Detail description Fatigue check
in Ch 11, App 2
number
1 Part of side extended: Connection of side longitudinal ordinary No Ch 11, App 2, Tab 1 to
longitudinally, between the stiffeners with transverse primary sup- Ch 11, App 2, Tab 6
after peak bulkhead and the porting members
collision bulkhead Connection of side longitudinal ordinary For L 170 m Ch 11, App 2, Tab 7 to
vertically, between 0,7TB stiffeners with stiffeners of transverse pri- Ch 11, App 2, Tab 13
and 1,15T from the baseline mary supporting members
Area
Reference tables
reference Area description Detail description Fatigue check
in Ch 11, App 2
number
1 Part of side extended: Connection of side longitudinal ordinary No Ch 11, App 2, Tab 1 to
longitudinally, between the stiffeners with transverse primary sup- Ch 11, App 2, Tab 6
after peak bulkhead and the porting members
collision bulkhead Connection of side longitudinal ordinary For L 170m Ch 11, App 2, Tab 7 to
vertically, between 0,7TB stiffeners with stiffeners of transverse pri- Ch 11, App 2, Tab 13
and 1,15T from the baseline mary supporting members
2 Part of inner side and longitudi- Connection of inner side or bulkhead No Ch 11, App 2, Tab 14 to
nal bulkheads in the cargo area longitudinal ordinary stiffeners with Ch 11, App 2, Tab 19
extended vertically above half transverse primary supporting members
tank height, where the tank
Connection of inner side or bulkhead For L 170m Ch 11, App 2, Tab 20 to
breadth exceeds 0,55B
longitudinal ordinary stiffeners with stiff- Ch 11, App 2, Tab 26
eners of transverse primary supporting
members
3 Double bottom in way of Connection of bottom and inner bottom For L 170m Ch 11, App 2, Tab 27 to
transverse bulkheads longitudinal ordinary stiffeners with Ch 11, App 2, Tab 29
floors
Connection of inner bottom with trans- For L 170m Ch 11, App 2, Tab 30
verse bulkheads or lower stools
4 Double bottom in way of Connection of inner bottom with hopper For L 170m Ch 11, App 2, Tab 32 to
hopper tanks tank sloping plates Ch 11, App 2, Tab 35
5 Lower part of transverse Connection of lower stools with plane For L 170m Ch 11, App 2, Tab 39 to
bulkheads with lower stools bulkheads Ch 11, App 2, Tab 45
Connection of lower stools with corru- For L 170m (not Ch 11, App 2, Tab 46 to
gated bulkheads for Ch 11, App 2, Ch 11, App 2, Tab 53
Tab 49 and Ch 11,
App 2, Tab 53)
6 Lower part of inner side Connection of hopper tank sloping plates For L 170m Ch 11, App 2, Tab 54 to
with inner side Ch 11, App 2, Tab 60
Area
Reference tables
reference Area description Detail description Fatigue check
in Ch 11, App 2
number
1 Part of side extended: Connection of side longitudinal ordinary No Ch 11, App 2, Tab 1 to
longitudinally, between the stiffeners with transverse primary sup- Ch 11, App 2, Tab 6
after peak bulkhead and the porting members
collision bulkhead Connection of side longitudinal ordinary For L 170 m Ch 11, App 2, Tab 7 to
vertically, between 0,7TB stiffeners with stiffeners of transverse pri- Ch 11, App 2, Tab 13
and 1,15T from the baseline mary supporting members
3 Double bottom in way of trans- Connection of bottom and inner bottom For L 170 m Ch 11, App 2, Tab 27 to
verse bulkheads longitudinal ordinary stiffeners with Ch 11, App 2, Tab 29
floors
Connection of inner bottom with trans- For L 170 m Ch 11, App 2, Tab 31
verse cofferdam bulkheads
4 Double bottom in way of hop- Connection of inner bottom with hopper For L 170 m Ch 11, App 2, Tab 36 to
per tanks tank sloping plates Ch 11, App 2, Tab 38
6 Lower part of inner side Connection of hopper tank sloping plates For L 170 m Ch 11, App 2, Tab 61,
with inner side Ch 11, App 2, Tab 62
Area
Reference tables
reference Area description Detail description Fatigue check
in Ch 11, App 2
number
3 Double bottom in way of trans- Connection of bottom and inner bottom For L 170m Ch 11, App 2, Tab 27 to
verse bulkheads longitudinal ordinary stiffeners with Ch 11, App 2, Tab 29
floors
Connection of inner bottom with trans- For L 170m Ch 11, App 2, Tab 30
verse bulkheads or lower stools
4 Double bottom in way of hop- Connection of inner bottom with hopper For L 170m Ch 11, App 2, Tab 32 to
per tanks tank sloping plates Ch 11, App 2, Tab 35
5 Lower part of transverse bulk- Connection of lower stools with plane For L 170m Ch 11, App 2, Tab 39 to
heads with lower stools bulkheads Ch 11, App 2, Tab 45
Connection of lower stools with corru- For L 170m (not Ch 11, App 2, Tab 46 to
gated bulkheads for Ch 11, App 2, Ch 11, App 2, Tab 53
Tab 49 and Ch 11,
App 2, Tab 53)
6 Lower part of inner side Connection of hopper tank sloping plates For L 170m Ch 11, App 2, Tab 54 to
with inner side Ch 11, App 2, Tab 60
7 Side frames Connection of side frames with hopper No Ch 11, App 2, Tab 63,
and topside tanks Ch 11, App 2, Tab 64
8 Topside tanks Connection of transverse corrugated No Ch 11, App 2, Tab 65
bulkheads with topside tanks
10 Hatch corners Deck plating in way of hatch corners No Ch 11, App 2, Tab 68
Ends of longitudinal hatch coamings No Ch 11, App 2, Tab 69,
Ch 11, App 2, Tab 70
Area
Reference tables
reference Area description Detail description Fatigue check
in Ch 11, App 2
number
1 Part of side extended: Connection of side longitudinal ordinary No Ch 11, App 2, Tab 1 to
longitudinally, between the stiffeners with transverse primary sup- Ch 11, App 2, Tab 6
after peak bulkhead and the porting members
collision bulkhead Connection of side longitudinal ordinary For L 170m Ch 11, App 2, Tab 7 to
vertically, between 0,7TB stiffeners with stiffeners of transverse pri- Ch 11, App 2, Tab 13
and 1,15T from the baseline mary supporting members
3 Double bottom in way of trans- Connection of bottom and inner bottom For L 170m Ch 11, App 2, Tab 27 to
verse bulkheads longitudinal ordinary stiffeners with Ch 11, App 2, Tab 29
floors
Connection of inner bottom with trans- For L 170m Ch 11, App 2, Tab 30
verse bulkheads or lower stools
4 Double bottom in way of hop- Connection of inner bottom with hopper For L 170m Ch 11, App 2, Tab 32 to
per tanks tank sloping plates Ch 11, App 2, Tab 35
5 Lower part of transverse bulk- Connection of lower stools with plane For L 170m Ch 11, App 2, Tab 39 to
heads with lower stools bulkheads Ch 11, App 2, Tab 45
Connection of lower stools with corru- For L 170m (not Ch 11, App 2, Tab 46 to
gated bulkheads for Ch 11, App 2, Ch 11, App 2, Tab 53
Tab 49 and Ch 11,
App 2, Tab 53)
6 Lower part of inner side Connection of hopper tank sloping plates For L 170m Ch 11, App 2, Tab 54 to
with inner side Ch 11, App 2, Tab 60
8 Topside tanks Connection of transverse corrugated No Ch 11, App 2, Tab 65
bulkheads with topside tanks
10 Hatch corners Deck plating in way of hatch corners No Ch 11, App 2, Tab 68
Ends of longitudinal hatch coamings No Ch 11, App 2, Tab 69,
Ch 11, App 2, Tab 70
Area
Reference tables
reference Area description Detail description Fatigue check
in Ch 11, App 2
number
1 Part of side extended: Connection of side longitudinal ordinary No Ch 11, App 2, Tab 1 to
longitudinally, between the stiffeners with transverse primary sup- Ch 11, App 2, Tab 6
after peak bulkhead and the porting members
collision bulkhead Connection of side longitudinal ordinary For L 170m Ch 11, App 2, Tab 7 to
vertically, between 0,7 TB stiffeners with stiffeners of transverse pri- Ch 11, App 2, Tab 13
and 1,15 T from the baseline mary supporting members
9 Cross decks Connection of cross decks with side No Ch 11, App 2, Tab 66
transverses
Connection between face plates of cross No Ch 11, App 2, Tab 67
decks and deck girders
10 Hatch corners Deck plating in way of hatch corners No Ch 11, App 2, Tab 68
Ends of longitudinal hatch coamings No Ch 11, App 2, Tab 69,
Ch 11, App 2, Tab 70
3 Grinding of welds for fatigue life where t is the plate thickness, in mm, at the weld toe being
ground.
improvement
For plate thickness less than 10 mm, grinding is generally
not allowed.
3.1 General
3.2.3 After grinding, the weld is to be inspected by the yard
3.1.1 The purpose of grinding is to smoothly blend the tran- quality control in order to check that the finished ground
sition between the plate and the weld face. surface is as smooth as possible, with no visible evidence of
the original weld toe or undercut or any grinding marks at
3.1.2 Grinding is generally to be burr grinding. However right angles to the weld toe line. In addition, the Society
other techniques of grinding may be considered by the may require measurements of the remaining thickness in
Society on a case by case basis. way of the ground weld.
SECTION 3 TESTING
1 Testing procedures of watertight 1.1.3 Testing of structures not listed in Tab 2 or Tab 3 is to
be specially considered by the Society.
compartments
1.2 General
1.1 Application
1.2.1 Tests are to be carried out in the presence of a Sur-
1.1.1 These test procedures are to confirm the watertight-
veyor at a stage sufficiently close to the completion of work,
ness of tanks and watertight boundaries, and the structural
with all the hatches, doors, windows, etc., installed and all
adequacy of tanks forming a part of the watertight subdivi-
the penetrations including pipe connections fitted, and
sions of ships. These procedures may also be applied to ver-
before any ceiling and cement work is applied over the
ify the weathertightness of structures and shipboard
joints. Specific test requirements are given in [1.6] and Tab
outfitting.
2. For the timing of the application of coating and the provi-
The tightness of all tanks and watertight boundaries of ships sion of safe access to joints, see [1.7], [1.8] and Tab 4.
during new construction and ships relevant to major con-
versions or major repairs is to be confirmed by these test
1.3 Definitions
procedures prior to the delivery of the ships.
Note 1: Major repair means a repair affecting structural integrity. 1.3.1 Structural test
1.1.2 All gravity tanks and other boundaries required to be A structural test is a test to verify the structural adequacy of
watertight or weathertight are to be tested in accordance tank construction. This may be a hydrostatic test or, where
with these procedures and proven tight and structurally the situation warrants, a hydropneumatic test.
adequate as follows:
1.3.2 Leak test
gravity tanks for their tightness and structural adequacy
A leak test is a test to verify the tightness of a boundary.
watertight boundaries other than tank boundaries for Unless a specific test is indicated, this may be a hydro-
their watertightness static/hydropneumatic test or an air test. A hose test may be
weathertight boundaries for their weathertightness. considered to be an acceptable form of leak test for certain
boundaries, as indicated by footnote (3) of Tab 2.
Note 1: Gravity tank means a tank that is subject to vapour pressure
not greater than 70 kPa. 1.3.3 Each type of structural and leak test is defined in Tab 1.
Tank or boundaries
Item Test type Test head or pressure Remarks
to be tested
1 Double bottom tanks (4) leak and structural The greater of:
(1) top of the overflow
2,4 m above top of tank (2)
bulkhead deck
2 Double bottom voids (5) leak See [1.6.4] to [1.6.6], as applicable Including pump room double
bottom and bunker tank pro-
tection double hull required
by MARPOL Annex I
3 Double side tanks leak and structural The greater of:
(1) top of the overflow
2,4 m above top of tank (2)
bulkhead deck
4 Double side voids leak See [1.6.4] to [1.6.6], as applicable
5 Deep tanks other than those leak and structural The greater of:
listed elsewhere in this Table (1) top of the overflow
2,4 m above top of tank (2)
6 Cargo oil tanks leak and structural The greater of:
(1) top of the overflow
2,4 m above top of tank (2)
top of tank plus setting of any
pressure relief valve (2)
7 Ballast holds of bulk carriers leak and structural The greater of:
(1) top of the overflow
top of cargo hatch coaming
8 Peak tanks leak and structural The greater of: After peak to be tested after
(1) top of the overflow installation of stern tube
2,4 m above top of tank (2)
9 a) Fore peak spaces with leak See [1.6.3] to [1.6.6], as applicable
equipment
b) Fore peak voids leak and structural To bulkhead deck After peak to be tested after
(1) (9) installation of stern tube
c) Aft peak spaces with equip- leak See [1.6.3] to [1.6.6], as applicable
ment
d) Aft peak voids leak See [1.6.4] to [1.6.6], as applicable
10 Cofferdams leak See [1.6.4] to [1.6.6], as applicable
11 a) Watertight bulkheads leak (8) See [1.6.3] to [1.6.6], as applicable (7)
b) Superstructure end bulkheads leak See [1.6.3] to [1.6.6], as applicable
12 Watertight doors below leak (6) (7) See [1.6.3] to [1.6.6], as applicable
freeboard or bulkhead deck
13 Double plate rudder blades leak See [1.6.4] to [1.6.6], as applicable
14 Shaft tunnels clear of deep tanks leak (3) See [1.6.3] to [1.6.6], as applicable
15 Shell doors leak (3) See [1.6.3] to [1.6.6], as applicable
16 Weathertight hatch covers and leak (3) (7) See [1.6.3] to [1.6.6], as applicable Hatch covers closed by tar-
closing appliances paulins and battens excluded
17 Dual purpose tank/dry cargo leak (3) (7) See [1.6.3] to [1.6.6], as applicable In addition to the structural
hatch covers test in item 6 or item 7
18 Chain lockers leak and structural Head of water up to top of chain pipe
Tank or boundaries
Item Test type Test head or pressure Remarks
to be tested
19 L.O. sump tanks and other similar leak See [1.6.3] to [1.6.6], as applicable
tanks/spaces under main engines
20 Ballast ducts leak and structural The greater of:
(1) ballast pump maximum pressure
setting of any pressure relief valve
21 Fuel oil tanks leak and structural The greater of:
(1) top of the overflow
2,4 m above top of tank (2)
top of tank plus setting of any
pressure relief valve (2)
bulkhead deck
(1) See [1.4.2], item a).
(2) The top of a tank is the deck forming the top of the tank, excluding any hatchways.
(3) Hose test may be also considered as a medium of the leak test. See [1.3.2].
(4) Including the tanks arranged in accordance with the provisions of Ch 2, Sec 2, [3.1.4].
(5) Including the duct keels and dry compartments arranged in accordance with the provisions of SOLAS, Regulations II-1/11.2 and
II-1/9.4 respectively, and/or the oil fuel tank protection and pump room bottom protection arranged in accordance with the pro-
visions of MARPOL Annex I, Chapter 3, Part A, Regulation 12A and Chapter 4, Part A, Regulation 22, respectively.
(6) Where watertightness of watertight doors has not been confirmed by a prototype test, a hydrostatic test (filling of the watertight
spaces with water) is to be carried out. See SOLAS Regulation II-1/16.2 and MSC/Circ.1176.
(7) As an alternative to the hose test, other testing methods listed in [1.6.7] to [1.6.9] may be acceptable, subject to adequacy of
such testing methods being verified. See SOLAS Regulation II-1/11.1. For watertight bulkheads (item 11 a)), alternatives to the
hose test may be used only where the hose test is not practicable.
(8) A structural test (see [1.4.2]) is also to be carried out for a representative cargo hold in case of cargo holds intended for in-port
ballasting. The filling level required for the structural test of such cargo holds is to be the maximum loading that will occur in-
port, as indicated in the loading manual.
(9) Structural test may be waived where it is demonstrated to be impracticable, to the satisfaction of the Society.
Item Type of ship/tank Structure to be tested Type of test Test head or pressure Remarks
1 Liquefied gas Integral tanks leak and structural See Pt D, Ch 9, Sec 4
carriers
Hull structure support-
ing membrane or
semi-membrane tanks
Independent tanks
type A
Independent tanks
type B
Independent tanks See Pt D, Ch 9, Sec 4
type C
2 Edible liquid tanks Independent tanks leak and structural The greater of:
top of the overflow
0,9 m above top of tank (1)
3 Chemical carriers Integral or independent leak and structural The greater of: An appropriate addi-
cargo tanks 2,4 m above top of tank (1) tional head is to be con-
top of tank plus setting of sidered where a cargo
any pressure relief valve (1) tank is designed for the
carriage of cargoes with
specific gravities greater
than 1,0
(1) Top of tank is deck forming the top of the tank excluding any hatchways.
Table 4 : Application of leak test, coating, and provision of safe access for the different types of welded joints
1.4 Structural test procedures d) Where structural adequacy of the tanks of a ship was
verified by structural testing as defined in Tab 1, the sub-
sequent ships in the series (i.e. sister ships built from the
1.4.1 Type and time of test
same plans, at the same shipyard) may be exempted
Where a structural test is specified in Tab 1 or Tab 2, a from the tank structural test, provided that:
hydrostatic test in accordance with [1.6.1] is acceptable.
watertightness of the boundaries of all the tanks is
Where practical limitations (strength of building berth, light
verified by leak tests, and thorough inspections are
density of liquid, etc.) prevent the performance of a hydro-
carried out
static test, a hydropneumatic test in accordance with [1.6.2]
may be accepted instead. structural testing is carried out for at least one tank
of each type among all the tanks of each sister ship.
A hydrostatic or hydropneumatic test for the confirmation of
Note 1: The provisions of item b) are to be applied instead of these
structural adequacy may be carried out while the ship is
provisions in case of boundaries of:
afloat, provided the results of a leak test are confirmed to be
satisfactory before the ship is set afloat. cargo spaces adjacent to compartments which are not
cargo spaces, for tankers and combination carriers, or
1.4.2 Testing schedule for new construction and segregated cargo tanks or pollutant cargo tanks, for the
major structural conversion or repair other types of ships.
a) The tank boundaries are to be tested from at least one additional tanks may require a structural test, as
side. The tanks for the structural test are to be selected deemed necessary after the structural test of the first
so that all the representative structural members are tank, or at the request of the attending Surveyor.
tested for the expected tension and compression. e) Sister ships built (i.e. keel laid) two years or more after
the delivery of the last ship of the series may be tested in
b) On each ship, structural tests are to be carried out on at
accordance with item d), at the discretion of the Society,
least one tank among a group of tanks having a struc-
provided that:
tural similarity (i.e. same design conditions, alike struc-
tural configurations with only minor localised general workmanship has been maintained (i.e. no
differences considered to be acceptable by the attend- discontinuity of shipbuilding, no significant changes
ing Surveyor), provided all the other similar tanks are in the construction methodology or technology at
tested for leaks by means of an air test. the yard, and shipyard personnel appropriately qual-
ified and demonstrating an adequate level of work-
The acceptance of a leak test (air test) instead of a struc- manship as determined by the Society), and
tural test does not apply to boundaries of:
an enhanced NDT programme is implemented for
cargo spaces adjacent to compartments which are the tanks not subject to the structural test.
not cargo spaces, for tankers and combination carri-
ers, or f) The watertight boundaries of spaces other than tanks
may be exempted from the structural test, provided that
segregated cargo tanks or pollutant cargo tanks, for the boundary watertightness of the exempted spaces is
the other types of ships. verified by leak tests and inspections. The tank structural
test is to be carried out and the requirements from item
c) Additional tanks may require a structural test, as a) to item e) are to be applied for ballast holds, chain
deemed necessary after the structural test of the first lockers, and for a representative cargo hold in case of
tank. cargo holds intended for in-port ballasting.
Table 1 : Typical butt weld plate edge preparation Table 2 : Typical butt weld plate edge preparation
(manual welding) - See Note 1 (manual welding) - See Note 1
3 G 9 mm
J
G = 3 mm 30 45
/
Single bevel butt
Single vee butt
G
J
t > 5 mm
G 3 mm G
J G 3 mm
R 3 mm
50 70
50 70
R 3 mm
4
/
4
/
4
/
G
J G 3 mm
R 3 mm
50 70
4
/
G
J G 3 mm
D R 3 mm
6 h t/3 mm
= 50
4
= 90
/
=
Table 3 : Typical lap joint, plug and slot welding (manual welding)
J
>
J b = 2 t2 + 25 mm
J J location of lap
joint to be
Fillet weld in joggled lap joint approved by the
Society
J > J
b 2 t2 + 25 mm
J J
Plug welding
t 12 mm 12 mm < t 25 mm
l L
= 60 mm = 80 mm
R = 6 mm R = 0,5 t mm
G
0
t
R 40 50 = 30
G = 12 mm G = t mm
L>2 L>2
Slot welding
l L
t 12 mm t > 12 mm
G = 20 mm G=2t
t = 80 mm = 100 mm
2 L 3 , max 250 mm 2 L 3 , max 250 mm
1 Contents
1.1 General
1.1.1 This Appendix includes the reference sheets for spe-
cial structural details, as referred to in Ch 11, Sec 2.
AREA 1: Side between 0,7TB and Connection of side longitudinal ordinary stiffeners with transverse
Sheet 1.1
1,15T from the baseline primary supporting members - No collar plate
SCANTLINGS: FATIGUE:
Net sectional area of the web stiffener according to Ch 4, Sec 3, [4.7]. Fatigue check not required.
CONSTRUCTION: NDE:
Web stiffener not compulsory. When fitted, its misalignment m with Visual examination 100%.
the web of the side longitudinal a / 50.
Cut-outs in the web free of sharps notches.
Gap between web and side longitudinal to be not greater than 4 mm.
Welding requirements:
- continuous fillet welding along the connection of web with side longitudinal,
- throat thickness according to Ch 11, Sec 1, [2.3.7]; in case of gap g greater than 2 mm, increase the throat thickness by:
0,7 (g 2) mm,
- weld around the cuts in the web at the connection with the longitudinal and the side shell,
- avoid burned notches on web.
AREA 1: Side between 0,7TB and Connection of side longitudinal ordinary stiffeners with transverse
Sheet 1.2
1,15T from the baseline primary supporting members - One collar plate
SCANTLINGS: FATIGUE:
Net sectional area of the web stiffener according to Ch 4, Sec 3, [4.7]. Fatigue check not required.
CONSTRUCTION: NDE:
Web stiffener not compulsory. When fitted, its misalignment m with the web Visual examination 100%.
of the side longitudinal a / 50.
Misalignment between web and collar plate tCP.
Cut-outs in the web free of sharps notches.
Gap between web and side longitudinal and between collar plate and side
longitudinal to be not greater than 4 mm.
Welding requirements:
- continuous fillet welding along the connection of web and collar plate with side longitudinal and at the lap joint between
web and collar plate,
- throat thickness according to Ch 11, Sec 1, [2.3.7]; in case of gap g greater than 2 mm, increase the throat thickness by:
0,7 (g 2) mm,
- weld around the cuts in the web at the connection with the longitudinal and the side shell,
- avoid burned notches on web.
Fillet welding of overlapped joint to be done all around.
AREA 1: Side between 0,7TB and Connection of side longitudinal ordinary stiffeners with transverse
Sheet 1.3
1,15T from the baseline primary supporting members - One large collar plate
SCANTLINGS: FATIGUE:
Net sectional area of the web stiffener according to Ch 4, Sec 3, [4.7]. Fatigue check not required.
CONSTRUCTION: NDE:
Web stiffener not compulsory. When fitted, its misalignment m with the web Visual examination 100%.
of the side longitudinal a / 50.
Misalignment between web and collar plate tCP.
Cut-outs in the web free of sharps notches.
Gap between web and side longitudinal and between collar plate and side
longitudinal to be not greater than 4 mm.
Welding requirements:
- continuous fillet welding along the connection of web and collar plate with side longitudinal and at the lap joint between
web and collar plate,
- throat thickness according to Ch 11, Sec 1, [2.3.7]; in case of gap g greater than 2 mm, increase the throat thickness by:
0,7 (g 2) mm,
- T joint connection of collar plate with side shell: see section A-A,
- weld around the cuts in the web at the connection with the longitudinal and the side shell,
- avoid burned notches on web.
Fillet welding of overlapped joint to be done all around.
AREA 1: Side between 0,7TB and Connection of side longitudinal ordinary stiffeners with transverse
Sheet 1.4
1,15T from the baseline primary supporting members - Two collar plates
SCANTLINGS: FATIGUE:
Net sectional area of the web stiffener according to Ch 4, Sec 3, [4.7]. Fatigue check not required.
CONSTRUCTION: NDE:
Web stiffener not compulsory. When fitted, its misalignment m with the web Visual examination 100%.
of the side longitudinal a / 50.
Misalignment between collar plates across the side longitudinal tCP / 2.
Cut-outs in the web free of sharps notches.
Gap between collar plates and side longitudinal to be not greater than 4 mm.
Welding requirements:
- continuous fillet welding along the connection of collar plates with side longitudinal and at the lap joint between web and
collar plates,
- throat thickness according to Ch 11, Sec 1, [2.3.7]; in case of gap g greater than 2 mm, increase the throat thickness by:
0,7 (g 2) mm,
- avoid burned notches on web.
Fillet welding of overlapped joint to be done all around.
AREA 1: Side between 0,7TB and Connection of side longitudinal ordinary stiffeners with transverse
Sheet 1.5
1,15T from the baseline primary supporting members - Two large collar plates
tW = web thickness of transverse primary supporting member
tCP = collar plate thickness
SCANTLINGS: FATIGUE:
Net sectional area of the web stiffener according to Ch 4, Sec 3, [4.7]. Fatigue check not required.
CONSTRUCTION: NDE:
Web stiffener not compulsory. When fitted, its misalignment m with the web Visual examination 100%.
of the side longitudinal a / 50.
Misalignment between collar plates across the side longitudinal tCP / 2.
Cut-outs in the web free of sharps notches.
Gap between collar plates and side longitudinal to be not greater than 4 mm.
Welding requirements:
- continuous fillet welding along the connection of collar plates with side longitudinal and at the lap joint between web and
collar plates,
- throat thickness according to Ch 11, Sec 1, [2.3.7]; in case of gap g greater than 2 mm, increase the throat thickness by:
0,7 (g 2) mm,
- T joint connection of collar plates with side shell: see section A-A,
- avoid burned notches on web.
Fillet welding of overlapped joint to be done all around.
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Web stiffener not compulsory. When fitted, its misalignment m with Visual examination 100%.
the web of the side longitudinal a / 50. Magnetic particle or dye penetrant examination: when
Misalignment between lugs across the side longitudinal tL / 2. deemed necessary depending on the quality of the lap
Misalignment at the butts within lug parts tL / 5. joint weld.
Gap between bulkhead plating and lugs to be not greater than
4 mm.
Welding requirements:
- continuous fillet welding along the connection of lugs with the side longitudinal and at the lap joints between web and lugs,
- throat thickness according to Ch 11, Sec 1, [2.3.7]; in case of gap g greater than 2 mm, increase the throat thickness by:
0,7 (g 2) mm,
- T joint connection of collar plates with side shell: see section A-A,
- welding sequence: 1 to 5 (see sketch).
AREA 1: Side between 0,7TB and Connection of side longitudinal ordinary stiffeners with stiffeners of
Sheet 1.7
1,15T from the baseline transverse primary supporting members - No bracket
SCANTLINGS: FATIGUE:
d to be as small as possible, maximum 35 mm recommended. Fatigue check to be carried out for L 170 m:
with non-watertight collar plate:
Kh = 1,30
K = 1,65
with full collar plate (watertight):
Kh = 1,25
K = 1,50
CONSTRUCTION: NDE:
Misalignment between side longitudinal and web stiffener t / 3. Visual examination 100%.
In case of fillet welding, misalignment may be as necessary to allow the
required fillet throat size, but t / 2. For bulbs, a misalignment of 6 mm may
be accepted.
Welding requirements:
- continuous fillet welding,
- weld around the stiffeners toes,
- fair shape of fillet at toes in longitudinal direction.
AREA 1: Side between 0,7TB and Connection of side longitudinal ordinary stiffeners with stiffeners of
Sheet 1.8
1,15T from the baseline transverse primary supporting members - One bracket
d
hw
Hot spots
h
hw
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment between side longitudinal, web stiffener and bracket t / 3. Visual examination 100%.
In case of fillet welding, misalignment may be as necessary to allow the
required fillet throat size, but t / 2. For bulbs, a misalignment of 6 mm may
be accepted.
Welding requirements:
- continuous fillet welding,
- weld around the stiffeners toes,
- fair shape of fillet at toes in longitudinal direction.
AREA 1: Side between 0,7TB and Connection of side longitudinal ordinary stiffeners with stiffeners of
Sheet 1.9
1,15T from the baseline transverse primary supporting members - One radiused bracket
d
hw
Hot spots
h
hw
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment between side longitudinal, web stiffener and bracket t / 3. Visual examination 100%.
In case of fillet welding, misalignment may be as necessary to allow the
required fillet throat size, but t / 2. For bulbs, a misalignment of 6 mm may
be accepted.
Welding requirements:
- continuous fillet welding,
- weld around the stiffeners toes,
- fair shape of fillet at toes in longitudinal direction.
AREA 1: Side between 0,7TB and Connection of side longitudinal ordinary stiffeners with stiffeners of
Sheet 1.10
1,15T from the baseline transverse primary supporting members - One bracket
d
hw
Hot spots
h
hw
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment between side longitudinal, web stiffener and bracket t / 3. Visual examination 100%.
In case of fillet welding, misalignment may be as necessary to allow the
required fillet throat size, but t / 2. For bulbs, a misalignment of 6 mm may
be accepted.
Welding requirements:
- continuous fillet welding,
- weld around the stiffeners toes,
- fair shape of fillet at toes in longitudinal direction.
AREA 1: Side between 0,7TB and Connection of side longitudinal ordinary stiffeners with stiffeners of
Sheet 1.11
1,15T from the baseline transverse primary supporting members - One radiused bracket
hw
h
Hot spots
hw
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment between side longitudinal, web stiffener and bracket t / 3. Visual examination 100%.
In case of fillet welding, misalignment may be as necessary to allow the
required fillet throat size, but t / 2. For bulbs, a misalignment of 6 mm may
be accepted.
Welding requirements:
- continuous fillet welding,
- weld around the stiffeners toes,
- fair shape of fillet at toes in longitudinal direction.
AREA 1: Side between 0,7TB and Connection of side longitudinal ordinary stiffeners with stiffeners of
Sheet 1.12
1,15T from the baseline transverse primary supporting members - Two brackets
hw
h
h
Hot spots
hw hw
d
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment between side longitudinal, web stiffener and brackets t / 3. Visual examination 100%.
In case of fillet welding, misalignment may be as necessary to allow the
required fillet throat size, but t / 2. For bulbs, a misalignment of 6 mm may
be accepted.
Welding requirements:
- continuous fillet welding,
- weld around the stiffeners toes,
- fair shape of fillet at toes in longitudinal direction.
Material requirements:
- material of brackets to be the same of longitudinals.
AREA 1: Side between 0,7TB and Connection of side longitudinal ordinary stiffeners with stiffeners of
Sheet 1.13
1,15T from the baseline transverse primary supporting members - Two radiused brackets
hw
h
h
Hot spots
R2
R1
d hw hw
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment between side longitudinal, web stiffener and brackets t /3. Visual examination 100%.
In case of fillet welding, misalignment may be as necessary to allow the
required fillet throat size, but t / 2. For bulbs, a misalignment of 6 mm may
be accepted.
Welding requirements:
- continuous fillet welding,
- weld around the stiffeners toes,
- fair shape of fillet at toes in longitudinal direction.
Material requirements:
- material of brackets to be the same of longitudinals.
AREA 2: Inner side and longitudinal Connection of inner side or bulkhead longitudinal ordinary stiffeners
Sheet 2.1
bulkheads above 0,5H with transverse primary supporting members - No collar plate
SCANTLINGS: FATIGUE:
Net sectional area of the web stiffener according to Ch 4, Sec 3, [4.7]. Fatigue check not required.
CONSTRUCTION: NDE:
Web stiffener not compulsory. When fitted, its misalignment m with the Visual examination 100%.
web of the longitudinal a / 50.
Cut-outs in the web free of sharps notches.
Gap between web and longitudinal to be not greater than 4 mm.
Welding requirements:
- continuous fillet welding along the connection of web with longitudinal,
- throat thickness according to Ch 11, Sec 1, [2.3.7]; in case of gap g greater than 2 mm, increase the throat thickness by:
0,7 (g 2) mm,
- weld around the cuts in the web at the connection with the longitudinal and the plating,
- avoid burned notches on web.
AREA 2: Inner side and longitudinal Connection of inner side or bulkhead longitudinal ordinary stiffeners
Sheet 2.2
bulkheads above 0,5H with transverse primary supporting members - One collar plate
SCANTLINGS: FATIGUE:
Net sectional area of the web stiffener according to Ch 4, Sec 3, [4.7]. Fatigue check not required.
CONSTRUCTION: NDE:
Web stiffener not compulsory. When fitted, its misalignment m with the web of Visual examination 100%.
the longitudinal a / 50.
Misalignment between web and collar plate tCP.
Cut-outs in the web free of sharps notches.
Gap between web and longitudinal and between collar plate and longitudinal
to be not greater than 4 mm.
Welding requirements:
- continuous fillet welding along the connection of web and collar plate with longitudinal and at the lap joint between web
and collar plate,
- throat thickness according to Ch 11, Sec 1, [2.3.7]; in case of gap g greater than 2 mm, increase the throat thickness by:
0,7 (g 2) mm,
- weld around the cuts in the web at the connection with the longitudinal and the plating,
- avoid burned notches on web.
Fillet welding of overlapped joint to be done all around.
AREA 2: Inner side and longitudinal Connection of inner side or bulkhead longitudinal ordinary stiffeners
Sheet 2.3
bulkheads above 0,5H with transverse primary supporting members - One large collar plate
SCANTLINGS: FATIGUE:
Net sectional area of the web stiffener according to Ch 4, Sec 3, [4.7]. Fatigue check not required.
CONSTRUCTION: NDE:
Web stiffener not compulsory. When fitted, its misalignment m with the web of Visual examination 100%.
the longitudinal a / 50.
Misalignment between web and collar plate tCP.
Cut-outs in the web free of sharps notches.
Gap between web and longitudinal and between collar plate and longitudinal
to be not greater than 4 mm.
Welding requirements:
- continuous fillet welding along the connection of web and collar plate with longitudinal and at the lap joint between web
and collar plate,
- throat thickness according to Ch 11, Sec 1, [2.3.7]; in case of gap g greater than 2 mm, increase the throat thickness by:
0,7 (g 2) mm,
- T joint connection of collar plate with the plating: see section A-A,
- weld around the cuts in the web at the connection with the longitudinal and the plating,
- avoid burned notches on web.
Fillet welding of overlapped joint to be done all around.
AREA 2: Inner side and longitudinal Connection of inner side or bulkhead longitudinal ordinary stiffeners
Sheet 2.4
bulkheads above 0,5H with transverse primary supporting members - Two collar plates
SCANTLINGS: FATIGUE:
Net sectional area of the web stiffener according to Ch 4, Sec 3, [4.7]. Fatigue check not required.
CONSTRUCTION: NDE:
Web stiffener not compulsory. When fitted, its misalignment m with the web of Visual examination 100%.
the longitudinal a / 50.
Misalignment between collar plates across the longitudinal tCP / 2.
Cut-outs in the web free of sharps notches.
Gap between collar plates and longitudinal to be not greater than 4 mm.
Welding requirements:
- continuous fillet welding along the connection of collar plates with longitudinal and at the lap joint between web and collar
plates,
- throat thickness according to Ch 11, Sec 1, [2.3.7]; in case of gap g greater than 2 mm, increase the throat thickness by:
0,7 (g 2) mm,
- avoid burned notches on web.
Fillet welding of overlapped joint to be done all around.
AREA 2: Inner side and longitudinal Connection of inner side or bulkhead longitudinal ordinary stiffeners
Sheet 2.5
bulkheads above 0,5H with transverse primary supporting members - Two large collar plates
SCANTLINGS: FATIGUE:
Net sectional area of the web stiffener according to Ch 4, Sec 3, [4.7]. Fatigue check not required.
CONSTRUCTION: NDE:
Web stiffener not compulsory. When fitted, its misalignment m with the web of Visual examination 100%.
the longitudinal a / 50.
Misalignment between collar plates across the longitudinal tCP / 2.
Cut-outs in the web free of sharps notches.
Gap between collar plates and longitudinal to be not greater than 4 mm.
Welding requirements:
- continuous fillet welding along the connection of collar plates with longitudinal and at the lap joint between web and collar
plates,
- throat thickness according to Ch 11, Sec 1, [2.3.7]; in case of gap g greater than 2 mm, increase the throat thickness by:
0,7 (g 2) mm,
- T joint connection of collar plates with the plating: see section A-A,
- avoid burned notches on web.
Fillet welding of overlapped joint to be done all around.
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Web stiffener not compulsory. When fitted, its misalignment m with the Visual examination 100%.
web of the longitudinal a / 50. Magnetic particle or dye penetrant examination:
Misalignment between lugs across the longitudinal tL / 2. when deemed necessary depending on the qual-
Misalignment at the butts within lug parts tL / 5. ity of the lap joint weld.
Gap between bulkhead plating and lugs to be not greater than 4 mm.
Welding requirements:
- continuous fillet welding along the connection of lugs with the longitudinal and at the lap joints between web and lugs,
- throat thickness according to Ch 11, Sec 1, [2.3.7]; in case of gap g greater than 2 mm, increase the throat thickness by:
0,7 (g 2) mm,
- T joint connection of collar plates with the plating: see section A-A,
- welding sequence: 1 to 5 (see sketch).
AREA 2: Inner side and longitudinal Connection of inner side or bulkhead longitudinal ordinary stiffeners
Sheet 2.7
bulkheads above 0,5H with stiffeners of transverse primary supporting members - No bracket
SCANTLINGS: FATIGUE:
d to be as small as possible, maximum 35 mm recommended. Fatigue check to be carried out for L 170 m:
with non-watertight collar plate:
Kh = 1,30
K = 1,65
with full collar plate (watertight):
Kh = 1,25
K = 1,50
CONSTRUCTION: NDE:
Welding requirements:
- continuous fillet welding,
- weld around the stiffeners toes,
- fair shape of fillet at toes in longitudinal direction.
d
hw
Hot spots
h
hw
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment between longitudinal, web stiffener and bracket t / 3. Visual examination 100%.
In case of fillet welding, misalignment may be as necessary to allow the
required fillet throat size, but t / 2. For bulbs, a misalignment of 6 mm
may be accepted.
Welding requirements:
- continuous fillet welding,
- weld around the stiffeners toes,
- fair shape of fillet at toes in longitudinal direction.
d
hw
Hot spots
h
hw
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment between longitudinal, web stiffener and bracket t / 3. Visual examination 100%.
In case of fillet welding, misalignment may be as necessary to allow the
required fillet throat size, but t / 2. For bulbs, a misalignment of 6 mm
may be accepted.
Welding requirements:
- continuous fillet welding,
- weld around the stiffeners toes,
- fair shape of fillet at toes in longitudinal direction.
AREA 2: Inner side and longitudinal Connection of inner side or bulkhead longitudinal ordinary stiffeners
Sheet 2.10
bulkheads above 0,5H with stiffeners of transverse primary supporting members - One bracket
d
hw
Hot spots
h
hw
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment between longitudinal, web stiffener and bracket t / 3. Visual examination 100%.
In case of fillet welding, misalignment may be as necessary to allow the
required fillet throat size, but t / 2. For bulbs, a misalignment of 6 mm
may be accepted.
Welding requirements:
- continuous fillet welding,
- weld around the stiffeners toes,
- fair shape of fillet at toes in longitudinal direction.
hw
h
Hot spots
hw
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment between longitudinal, web stiffener and bracket t / 3. Visual examination 100%.
In case of fillet welding, misalignment may be as necessary to allow the
required fillet throat size, but t / 2. For bulbs, a misalignment of 6 mm
may be accepted.
Welding requirements:
- continuous fillet welding,
- weld around the stiffeners toes,
- fair shape of fillet at toes in longitudinal direction.
AREA 2: Inner side and longitudinal Connection of inner side or bulkhead longitudinal ordinary stiffeners
Sheet 2.12
bulkheads above 0,5H with stiffeners of transverse primary supporting members - Two brackets
hw
h
h
Hot spots
hw hw
d
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment between longitudinal, web stiffener and brackets t / 3. Visual examination 100%.
In case of fillet welding, misalignment may be as necessary to allow the
required fillet throat size, but t / 2. For bulbs, a misalignment of 6 mm
may be accepted.
Welding requirements:
- continuous fillet welding,
- weld around the stiffeners toes,
- fair shape of fillet at toes in longitudinal direction.
Material requirements:
- material of brackets to be the same of longitudinals.
hw
h
h
Hot spots
R2
R1
d hw hw
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment between longitudinal, web stiffener and brackets t / 3. Visual examination 100%.
In case of fillet welding, misalignment may be as necessary to allow the
required fillet throat size, but t / 2. For bulbs, a misalignment of 6 mm
may be accepted.
Welding requirements:
- continuous fillet welding,
- weld around the stiffeners toes,
- fair shape of fillet at toes in longitudinal direction.
Material requirements:
- material of brackets to be the same of longitudinals.
AREA 3: Double bottom in way of Connection of bottom and inner bottom longitudinal ordinary stiffen-
Sheet 3.1
transverse bulkheads ers with floors - No bracket
Hot
spots
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment between webs of bottom and inner bottom longitudinal Visual examination 100%.
with floor stiffener t / 3.
In case of fillet weld, misalignment may be as necessary to allow the
required fillet leg size, but t / 2. For bulbs, a misalignment of 6 mm
may be accepted.
Welding requirements:
- floor stiffeners to be connected with continuous fillet welding to bottom and inner bottom longitudinals,
- weld all around the stiffeners,
- fair shape of fillet at toes in longitudinal direction.
AREA 3: Double bottom in way of Connection of bottom and inner bottom longitudinal ordinary
Sheet 3.2
transverse bulkheads stiffeners with floors - Brackets
Transverse
bulkhead
h
or
stool
Hot
spots
SCANTLINGS: FATIGUE:
h as necessary to allow the required fillet throat size, but 15 mm. Fatigue check to be carried out for L 170 m:
Kh = 1,30
K = 1,55
CONSTRUCTION: NDE:
Misalignment between webs of bottom and inner bottom longitudinal Visual examination 100%.
with floor stiffener t / 3.
In case of fillet weld, misalignment may be as necessary to allow the
required fillet leg size, but t / 2. For bulbs, a misalignment of 6 mm
may be accepted.
Welding requirements:
- floor stiffeners and brackets to be connected with continuous fillet welding to bottom and inner bottom longitudinals,
- partial penetration welding between stiffeners and brackets,
- weld all around the stiffeners and brackets,
- fair shape of fillet at toes in longitudinal direction.
AREA 3: Double bottom in way of Connection of bottom and inner bottom longitudinal ordinary
Sheet 3.3
transverse bulkheads stiffeners with floors - Radiused brackets
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment between webs of bottom and inner bottom longitudinal Visual examination 100%.
with floor stiffener t / 3.
In case of fillet weld, misalignment may be as necessary to allow the
required fillet leg size, but t / 2. For bulbs, a misalignment of 6 mm
may be accepted.
Welding requirements:
- floor stiffeners and brackets to be connected with continuous fillet welding to bottom and inner bottom longitudinals,
- partial penetration welding between stiffeners and brackets,
- weld all around the stiffeners and brackets,
- fair shape of fillet at toes in longitudinal direction.
Table 30 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
t = min ( t1 , t2 , t3 )
IN
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment (median lines) between floor and bulkhead (or stool) The following NDE are required:
plating t / 3. VE 100%,
Cut-outs for connections of the inner bottom longitudinals to double UE 35% of full penetration weld for absence of
bottom floors to be closed by collar plates welded to the inner bottom. cracks, lack of penetration and lamellar tears.
Welding requirements:
- bulkhead (or stool) plating and supporting floors generally to be connected with full penetration welding to inner bottom
plating (if not full penetration welding, the weld preparation is to be indicated on the approved drawings),
- special approval of the procedure on a sample representative of the actual conditions foreseen in production,
- welding sequence against the risk of lamellar tearing,
- weld finishing well faired to the inner bottom plating.
Material requirements:
- the strake of inner bottom plating in way of the connection is recommended to be of Z25/ZH25 quality. If a steel of such a
quality is not adopted, 100% UE of the plate in way of the weld is required prior to and after welding.
SX = KSX nX
t = min ( t1 , t2 , t3 )
IN
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment (median lines) between floor and bulkhead plating The following NDE are required:
t / 3, max 6 mm. VE 100%,
Cut-outs for connections of the inner bottom longitudinals to double UE 35% of full penetration weld for absence of
bottom floors to be closed by collar plates, welded to the inner bottom. cracks, lack of penetration and lamellar tears.
Welding requirements:
- bulkhead plating and supporting floors to be connected with full penetration welding to inner bottom plating,
- bulkhead vertical girders and bottom girders are to be connected with partial penetration to inner bottom plating for the
extension shown in the sketch,
- special approval of the procedure on a sample representative of the actual conditions foreseen in production,
- welding sequence against the risk of lamellar tearing,
- weld finishing well faired to the inner bottom plating.
Material requirements:
- the strake of inner bottom plating in way of the connection is to be of Z25/ZH25 or of a steel of the same mechanical per-
formances. In particular cases, grade E/EH steel may be accepted by the Society provided that the results of 100% UE of the
plate in way of the weld, carried out prior to and after welding, are submitted for review.
Table 32 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
a At hot spot B:
SX = KSX nX + KSYX nY
Inner bottom plating
a
ny
t2 tA = min (t1 , t2 , t3 ),
tB = minimum among:
- floor thickness,
d Smooth shaped weld - hopper transverse web thickness,
Girder - t 3.
t3
nx
Hot spot B
Section a - a
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment (median lines) between girder and sloping plate The following NDE are required:
tA / 3. VE 100%,
Misalignment (median lines) between floor and hopper trans- UE 25% of full penetration weld for absence of cracks, lack
verse web tB / 3. of penetration and lamellar tears.
Welding requirements:
- sloping plate to be connected with partial penetration welding to inner bottom plating,
- approval of the procedure on a sample representative of the actual conditions foreseen in production,
- welding sequence against the risk of lamellar tearing,
- weld finishing well faired to the inner bottom plating on tank side.
Material requirements:
- the strake of inner bottom plating in way of the connection is recommended to be of Z25/ZH25 quality. If a steel of such a
quality is not adopted, 100% UE of the plate in way of the weld is required prior to and after welding.
Table 33 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
AREA 4: Double bottom in way of hopper Connection of inner bottom with hopper tank sloping plates -
Sheet 4.2
tanks Prolonging brackets
t1 Sloping plate
Hot spots A
a 5
Inner bottom plating 5
a >
ny
t2 5 5
SCANTLINGS: FATIGUE:
Inner bottom plating to be prolonged within the hopper tank Fatigue check to be carried out for L 170 m:
structure by brackets as shown in the sketch. KSY = 2,4 where closed scallops
d 50 mm. 3,4 where open scallops
Guidance values, to be confirmed by calculations carried out KSX = 1,3
according to Ch 7, Sec 3: KSYX = 1,5
- thickness of the above brackets t2,
- b 0,4 times the floor spacing,
- 1,5 b.
CONSTRUCTION: NDE:
Misalignment (median lines) between girder and sloping plate The following NDE are required:
tA / 3. VE 100%,
Misalignment (median lines) between floor and hopper trans- UE 25% of full penetration weld for absence of cracks, lack
verse web tB / 3. of penetration and lamellar tears.
Welding requirement:
- sloping plate to be connected with partial penetration welding to inner bottom plating,
- brackets to be connected with full penetration welding to inner bottom plating,
- approval of the procedure on a sample representative of the actual conditions foreseen in production,
- welding sequence against the risk of lamellar tearing,
- weld finishing well faired to the inner bottom plating on tank side.
Material requirement:
- the strake of inner bottom plating in way of the connection is recommended to be of Z25/ZH25 quality. If a steel of such a
quality is not adopted, 100% UE of the plate in way of the weld is required prior to and after welding,
- material properties of prolonging brackets to be not less than those of the inner bottom plating.
Table 34 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
AREA 4: Double bottom in way of hopper Connection of inner bottom with hopper tank sloping plates -
Sheet 4.3
tanks Radiused construction
Hot spot A
a Hot spot stresses:
Full penetration
At hot spot A:
SY = KSY nY
a t At hot spot B:
ny SX = KSX nX + KSYX nY
400
mm
400 mm
400 mm
Full penetration tA = minimum thickness between those of the girder
and sloping plate,
Partial penetration tB = minimum among:
floor thickness,
hopper transverse web thickness,
girder thickness.
nx
Hot spot B
Section a - a
SCANTLINGS: FATIGUE:
Inner radius of the bent plate to be between 3,5 and 5 times the thick- Fatigue check to be carried out for L 170 m:
ness of the bent plate and to be indicated in the approved plan. KSY = 3,15
Transverse brackets extended to the closest longitudinals to be fitted on KSX = 1,30
each side of the girder, at mid-span between floors. KSYX = 2,05
Thickness of these brackets, in mm 9 + 0,03 L1 k1/2.
CONSTRUCTION: NDE:
Misalignment (median lines) between girder and sloping plate tA / 3. The following NDE are required:
Misalignment (median lines) between floor and hopper transverse web VE 100%,
tB / 3. UE 25% of full penetration weld for absence of
In floor or transverse webs, in way of the bent area, scallops to be cracks, lack of penetration and lamellar tears.
avoided or closed by collar plates.
Welding requirements:
- floors to be connected (see sketches):
with full penetration welding to the inner bottom for a length 400 mm,
with partial penetration welding to the girder for a length 400 mm,
with continuous fillet welding in the remaining areas,
- approval of the procedure on a sample representative of the actual conditions foreseen in production,
- welding sequence against the risk of lamellar tearing,
- welding procedures of longitudinal girder to the bent plate to be submitted to the Society for review, with evidence given that
there is no risk of ageing after welding,
- weld finishing of butt welds well faired to the inner bottom plating on ballast tank,
- fair shape of fillet at hot spots.
Material requirements:
- the radiused construction may be accepted provided that the folding procedure is submitted to the Society for review, with
evidence given that the mechanical properties and, in particular, the impact properties are not deteriorated by the folding
operation.
Table 35 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
AREA 4: Double bottom in way of hopper Connection of inner bottom with hopper tank sloping plates -
Sheet 4.4
tanks Radiused construction
a t = minimum among:
ny floor thickness,
tIB
hopper transverse web thickness,
a girder thickness,
nx
Hot spot B
Section a - a
SCANTLINGS: FATIGUE:
Inner radius of the bent plate to be between 3,5 and 5 times the thickness Fatigue check to be carried out for L 170 m:
of the bent plate and to be indicated in the approved plan. KSY = 3,85
d 40 mm. KSX = 1,30
Transverse brackets extended to the closest longitudinals to be fitted on KSYX = 4,50
each side of the girder, at mid-span between floors.
Thickness of these brackets, in mm 9 + 0,03 L1 k1/2.
CONSTRUCTION: NDE:
Misalignment (median lines) between floor and hopper transverse web Visual examination 100%.
t / 3.
In floor or transverse webs, in way of the bent area, scallops to be avoided
or closed by collar plates.
Welding requirements:
- floors to be connected with full penetration welding to the inner bottom plating for a length 5 tIB ,
- where girder is welded within the bent area, welding procedures to be submitted to the Society for review.
Material requirements:
- where girder is welded within the bent area, folding procedure to be submitted to the Society for review, with evidence given
that the mechanical properties and, in particular, the impact properties are not deteriorated by the folding operation.
t3
nx
Hot spot B
Section a - a
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment (median lines) between girder and sloping plate tA / 3, The following NDE are required:
max 6 mm. VE 100%,
Misalignment (median lines) between floor and hopper transverse web UE 35% of full penetration weld for absence of
tB / 3, max 6 mm. cracks, lack of penetration and lamellar tears.
Welding requirements:
- sloping plate to be connected with full penetration welding to inner bottom plating, except in way of void spaces where par-
tial penetration may be accepted,
- approval of the procedure on a sample representative of the actual conditions foreseen in production,
- welding sequence against the risk of lamellar tearing,
- weld finishing well faired to the inner bottom plating on tank side.
Material requirements:
- the strake of inner bottom plating in way of the connection is to be of Z25/ZH25 or of a steel of the same mechanical per-
formances. In particular cases, grade E/EH low temperature steel may be accepted by the Society provided that the results of
100% UE of the plate in way of the weld, carried out prior to and after welding, are submitted for review.
AREA 4: Double bottom in way of hopper Connection of inner bottom with hopper tank sloping plates -
Sheet 4.6
tanks Prolonging brackets
t1 Sloping plate
Hot spots A
a 5
Inner bottom plating 5
a >
ny
t2 5 5
AREA 4: Double bottom in way of hopper Connection of inner bottom with hopper tank sloping plates -
Sheet 4.7
tanks Radiused construction
Hot spot A
a Hot spot stresses:
Full penetration
At hot spot A:
SY = KSY nY
a t At hot spot B:
ny SX = KSX nX + KSYX nY
400
mm
400 mm
400 mm
Full penetration tA = minimum thickness between those of the girder
and sloping plate,
Partial penetration tB = minimum among:
floor thickness,
hopper transverse web thickness,
girder thickness.
nx
Hot spot B
Section a - a
SCANTLINGS: FATIGUE:
Inner radius of the bent plate to be between 3,5 and 5 times the thickness Fatigue check to be carried out for L 170 m:
of the bent plate and to be indicated in the approved plan. KSY = 3,15
Transverse brackets extended to the closest longitudinals to be fitted on KSX = 1,30
each side of the girder, at mid-span between floors. KSYX = 2,05
Thickness of these brackets, in mm 9 + 0,03 L1 k1/2.
CONSTRUCTION: NDE:
Misalignment (median lines) between girder and sloping plate tA / 3. The following NDE are required:
Misalignment (median lines) between floor and hopper transverse web VE 100%,
tB / 3. UE 25% of full penetration weld for absence of
In floor or transverse webs, in way of the bent area, scallops to be cracks, lack of penetration and lamellar tears.
avoided or closed by collar plates.
Table 39 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
ny
nx
Hot spot B
Section a - a
A = distance to be taken not less than the spacing of bulk-
head vertical webs
SCANTLINGS: FATIGUE:
Thickness of members above and below stool top plate to be not KSXY = 2,00
less than that of bulkhead vertical webs.
CONSTRUCTION: NDE:
Misalignment (median lines) between bulkhead plating and stool The following NDE are required:
side plating tA / 3. VE 100%,
Misalignment (median lines) between members above and below UE 35% of full penetration welds for absence of
stool top plate tB / 3. cracks, lack of penetration and lamellar tears.
Welding requirements:
- bulkhead and stool side plating generally to be connected with full penetration welding to stool top plate (if not full penetra-
tion welding, the weld preparation is to be indicated on the approved drawings),
- approval of the procedure on a sample representative of the actual conditions foreseen in production,
- welding sequence against the risk of lamellar tearing is recommended in case Z material is not adopted for the stool top
plate,
- weld finishing well faired to the stool top plate.
Material requirements:
- the stool top plate is recommended to be Z25/ZH25 quality. If a steel of such a quality is not adopted, 100% UE of the plate
in way of the weld is required prior to and after welding,
- material properties of:
the stool top plate,
the portion A of the stool side plating,
to be not less than those of the transverse bulkhead plating.
Table 40 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
AREA 5: Lower part of transverse bulkheads Connection of lower stools with plane bulkheads in way of
Sheet 5.2
with lower stools intermediate brackets
ny
nx
Hot spot B
Section a - a
A = distance to be taken not less than the spacing of
bulkhead vertical webs
Hot spot stresses:
At hot spot A:
SX = KSX nX
At hot spot B:
SY = KSY nY + KSXY nX
tA = min (t1 , t2 , t3 )
tB = minimum among:
thickness of member above stool top plate,
thickness of intermediate bracket,
t2 .
SCANTLINGS: FATIGUE:
d 1,5 t1. Fatigue check to be carried out for L 170 m:
t2 t1. KSX = 3,55
t3 t1 in portion A. KSY = 1,30
Thickness of intermediate brackets and members above stool top KSXY = 1,75
plate to be not less than that of bulkhead vertical webs.
CONSTRUCTION: NDE:
Misalignment (median lines) between bulkhead plating and stool side The following NDE are required:
plating tA / 3. VE 100%,
Misalignment (median lines) between intermediate bracket and mem- UE 35% of full penetration welds for absence of
ber above stool top plate tB / 3. cracks, lack of penetration and lamellar tears.
Intermediate brackets to be fitted in place and welded after the weld-
ing of the joint between the stool side plating and the stool top plate.
Table 41 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
AREA 5: Lower part of transverse bulkheads Connection of lower stools with plane bulkheads - Prolonging
Sheet 5.3
with lower stools brackets
ny
nx
Hot spot B
Section a - a
A = distance to be taken not less than the spacing of
bulkhead vertical webs
Hot spot stresses:
At hot spot A:
SX = KSX nX
At hot spot B:
SY = KSY nY + KSXY nX
tA = min (t1 , t2 , t3 )
tB = minimum among:
thickness of member above stool top plate,
thickness of member below stool top plate,
t2 .
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment (median lines) between stool top plate and stool side The following NDE are required:
plating tA / 3. VE 100%,
Misalignment (median lines) between members above and below UE 35% of full penetration welds for absence of
stool top plate tB / 3. cracks, lack of penetration and lamellar tears.
Welding requirements:
- stool side plating to be connected with full penetration welding to the bulkhead plating. Root gap to be checked along the
production steps as appropriate,
- brackets to be connected with full penetration welding to transverse bulkhead plating,
- full penetration weld of stool side plating to bulkhead plating to be welded first,
- welding sequence against the risk of lamellar tearing in the bulkhead plating is recommended.
Material requirements:
- the lower strake of transverse bulkhead plating is recommended to be Z25/ZH25 quality. If a steel of such a quality is not
adopted, 100% UE of the strake in way of the weld is required prior to and after welding,
- material properties of:
the stool top plate,
the portion A of the stool side plating,
to be not less than those of the transverse bulkhead plating,
- material properties of prolonging brackets to be not less than those of the bulkhead plating.
Table 42 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
AREA 5: Lower part of transverse bulkheads Connection of lower stools with plane bulkheads - Radiused
Sheet 5.4
with lower stools construction
ny
nx
Hot spot B
Section a - a
A = distance to be taken not less than the spacing of
bulkhead vertical webs
Hot spot stresses:
At hot spot A:
SX = KSX nX
At hot spot B:
SY = KSY nY + KSXY nX
tA = min (t1 , t2 , t3 )
tB = minimum among:
thickness of member above stool top plate,
thickness of member below stool top plate,
t2 .
SCANTLINGS: FATIGUE:
Inner radius of the bent plate to be between 3,5 and 5 times the thick- Fatigue check to be carried out for L 170 m:
ness of the bent plate and to be indicated in the approved plan. KSX = 3,30
t2 t1. KSY = 1,30
t3 t1 in portion A. KSXY = 2,25
Thickness of members above and below stool top plate to be not less
than that of bulkhead vertical webs.
CONSTRUCTION: NDE:
Misalignment (median lines) between stool top plate and stool side The following NDE are required:
plating tA / 3. VE 100%,
Misalignment (median lines) between members above and below UE 35% of full penetration welds, if any, for absence
stool top plate tB / 3. of cracks, lack of penetration and lamellar tears.
If not full penetration welding of stool top plate to bulkhead, the weld
preparation is to be indicated on the approved drawings.
Butt welds between transverse bulkhead and stool side plating at a
distance greater than 500 mm from the stool top plate.
Table 43 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
AREA 5: Lower part of transverse bulkheads Connection of lower stools with plane bulkheads in way of
Sheet 5.5
with lower stools intermediate brackets - Radiused construction
ny
nx
Hot spot B
Section a - a
A = distance to be taken not less than the spacing of
bulkhead vertical webs
Hot spot stresses:
At hot spot A:
SX = KSX nX
At hot spot B:
SY = KSY nY + KSXY nX
tA = min (t1 , t2 , t3 )
tB = minimum among:
thickness of member above stool top plate,
thickness of intermediate bracket,
t2 .
SCANTLINGS: FATIGUE:
Inner radius of the bent plate to be between 3,5 and 5 times the thickness of the Fatigue check to be carried out for L170m:
bent plate and to be indicated in the approved plan. KSX = 3,15
t 2 t 1. KSY = 1,30
t3 t1 in portion A. KSXY = 2,05
Thickness of intermediate brackets and members above stool top plate to be not
less than that of bulkhead vertical webs.
CONSTRUCTION: NDE:
Misalignment (median lines) between stool top plate and stool side plating tA / 3. The following NDE are required:
Misalignment (median lines) between intermediate bracket and member below VE 100%,
stool top plate tB / 3. UE 35% of full penetration welds, if any,
If not full penetration welding of stool top plate to bulkhead, the weld preparation for absence of cracks, lack of penetra-
is to be indicated on the approved drawings. tion and lamellar tears.
Intermediate brackets to be fitted in place and welded after the welding of the
joint between the stool top plate and the bulkhead plating.
Butt welds between transverse bulkhead and stool side plating at a distance
greater than 500 mm from the stool top plate.
Table 44 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
AREA 5: Lower part of transverse bulkheads Connection of lower stools with plane bulkheads - Radiused
Sheet 5.6
with lower stools construction
ny
nx
Hot spot B
Section a - a
A = distance to be taken not less than the spacing of
bulkhead vertical webs
Hot spot stresses:
At hot spot A:
SX = KSX nX
At hot spot B:
SY = KSY nY + KSXY nX
t = minimum among:
thickness of member above stool top plate,
thickness of member below stool top plate,
t2 .
SCANTLINGS: FATIGUE:
Inner radius of the bent plate to be between 3,5 and 5 times the thick- Fatigue check to be carried out for L 170 m:
ness of the bent plate and to be indicated in the approved plan. KSX = 4,50
d 40 mm. KSY = 1,30
t2 t1. KSXY = 5,60
t3 t1 in portion A.
Thickness of members above and below stool top plate to be not less
than that of bulkhead vertical webs.
CONSTRUCTION: NDE:
Misalignment (median lines) between members above and below The following NDE are required:
stool top plate t / 3. VE 100%,
If not full penetration welding of stool top plate to bulkhead, the weld UE 35% of full penetration welds, if any, for absence
preparation is to be indicated on the approved drawings. of cracks, lack of penetration and lamellar tears.
Butt welds between transverse bulkhead and stool side plating at a
distance greater than 500 mm from the stool top plate.
Material requirements:
- where stool top plate is welded within the bent area, folding procedure to be submitted to the Society for review, with evidence
given that the mechanical properties and, in particular, the impact properties are not deteriorated by the folding operation,
- material properties of:
the stool top plate,
the portion A of the stool side plating,
to be not less than those of the transverse bulkhead plating.
Table 45 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
AREA 5: Lower part of transverse bulkheads Connection of lower stools with plane bulkheads in way of
Sheet 5.7
with lower stools intermediate brackets - Radiused construction
t1 ny
Hot spots A
nx
Transverse Hot spot B
bulkhead
Stool top plate
a a
Section a - a
A = distance to be taken not less than the spacing of
t2 bulkhead vertical webs
a A At hot spot A:
SX = KSX nX
At hot spot B:
Intermediate a
SY = KSY nY + KSXY nX
bracket Lower
stool
t = minimum among:
thickness of member above stool top plate,
thickness of intermediate bracket,
t3 t2 .
SCANTLINGS: FATIGUE:
Inner radius of the bent plate to be between 3,5 and 5 times the thick- Fatigue check to be carried out for L 170 m:
ness of the bent plate and to be indicated in the approved plan. KSX = 3,85
d 40 mm. KSY = 1,30
t 2 t 1. KSXY = 4,50
t3 t1 in portion A.
Thickness of intermediate brackets and members above stool top
plate to be not less than that of bulkhead vertical webs.
CONSTRUCTION: NDE:
Misalignment (median lines) between intermediate bracket and mem- The following NDE are required:
ber above stool top plate t / 3. VE 100%,
If not full penetration welding of stool top plate to bulkhead, the weld UE 35% of full penetration welds, if any, for absence
preparation is to be indicated on the approved drawings. of cracks, lack of penetration and lamellar tears.
Intermediate brackets to be fitted in place and welded after the weld-
ing of the joint between the stool top plate and the bulkhead plating.
Butt welds between transverse bulkhead and stool side plating at a
distance greater than 500 mm from the stool top plate.
Material requirements:
- where stool top plate is welded within the bent area, folding procedure to be submitted to the Society for review, with evidence
given that the mechanical properties and, in particular, the impact properties are not deteriorated by the folding operation,
- material properties of:
the stool top plate,
the portion A of the stool side plating,
to be not less than those of the transverse bulkhead plating.
Table 46 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
Aa
t = min (tF , tT , tS ).
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment (median lines) between corrugation flanges and stool The following NDE are required:
side plating t / 3. VE 100%,
Distance from the edge of the stool top plate to the surface of the cor- UE 35% of full penetration welds for absence of
rugation flanges 1,5 tF. cracks, lack of penetration and lamellar tears.
Corrugation radius according to Ch 4, Sec 7, [3.1.3].
Welding requirements:
- corrugations and stool side plating generally to be connected with full penetration welding to stool top plate (if not full pene-
tration welding, the weld preparation is to be indicated on the approved drawings); root gap to be checked along the produc-
tion,
- welding sequence against the risk of lamellar tearing,
- start and stop welding away from the locations of corrugation bents,
- weld finishing well faired to the stool top plate, corrugation flanges and stool side plating.
Material requirements:
- the stool top plate is recommended to be of Z25/ZH25 quality. If a steel of such a quality is not adopted, 100% UE of the
plate in way of the weld is required prior to and after welding,
- material properties of:
the stool top plate,
the portion A of the stool side plating,
to be not less than those of the corrugation flanges.
Table 47 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
AREA 5: Lower part of transverse bulkheads Connection of lower stools with corrugated bulkheads -
Sheet 5.9
with lower stools Shedder plates 45
Aa
nx
Hot spot stress:
SX = KSX nX
tF = corrugation flange thickness,
tT = stool top plate thickness,
tS = stool side plating thickness,
tSH = shedder plate thickness,
tA = min (tF , tT , tS )
tB = min (tSH , tT , tS ).
SCANTLINGS: FATIGUE:
tT tF . Fatigue check to be carried out for L 170 m:
tS tF in portion A. KSX = 1,35
tSH 0,75 tF .
CONSTRUCTION: NDE:
Misalignment (median lines) between corrugation flanges and stool side The following NDE are required:
plating tA / 3. VE 100%,
Misalignment (median lines) between lower edge of shedder plates and stool UE 35% of full penetration welds for absence
side plating tB / 3. of cracks, lack of penetration and lamellar
Knuckled shedder plates are to be avoided. tears.
Distance from the edge of the stool top plate to the surface of the corrugation
flanges 1,5 tF .
Corrugation radius according to Ch 4, Sec 7, [3.1.3].
In ships with service notations combination carrier, oil tanker or chemical
tanker, closed spaces to be filled with suitable compound compatible with
the products carried.
WELDING AND MATERIALS:
Welding requirements:
- corrugations and stool side plating generally to be connected with full penetration welding to stool top plate (if not full pene-
tration welding, the weld preparation is to be indicated on the approved drawings); root gap to be checked along the produc-
tion,
- shedder plates to be connected with one side penetration, or equivalent, to corrugations and stool top plate,
- welding sequence against the risk of lamellar tearing,
- start and stop welding away from the locations of corrugation bents,
- weld finishing well faired to the stool top plate, corrugation flanges and stool side plating.
Material requirements:
- the stool top plate is recommended to be of Z25/ZH25 quality. If a steel of such a quality is not adopted, 100% UE of the
plate in way of the weld is required prior to and after welding,
- material properties of:
the shedder plates,
the stool top plate,
the portion A of the stool side plating,
to be not less than those of the corrugation flanges.
Table 48 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
AREA 5: Lower part of transverse bulkheads Connection of lower stools with corrugated bulkheads -
Sheet 5.10
with lower stools Shedder plates 55
Aa
nx
Hot spot stress:
SX = KSX nX
tF = corrugation flange thickness,
tT = stool top plate thickness,
tS = stool side plating thickness,
tSH = shedder plate thickness,
tA = min (tF , tT , tS ),
tB = min (tSH , tT , tS ).
SCANTLINGS: FATIGUE:
tT tF . Fatigue check to be carried out for L 170 m:
tS tF in portion A. KSX = 1,25
tSH 0,75 tF .
CONSTRUCTION: NDE:
Misalignment (median lines) between corrugation flanges and stool side The following NDE are required:
plating tA / 3. VE 100%,
Misalignment (median lines) between lower edge of shedder plates and stool UE 35% of full penetration welds for absence
side plating tB / 3. of cracks, lack of penetration and lamellar
Knuckled shedder plates are to be avoided. tears.
Distance from the edge of the stool top plate to the surface of the corrugation
flanges 1,5 tF .
Corrugation radius according to Ch 4, Sec 7, [3.1.3].
In ships with service notations combination carrier, oil tanker or chemical
tanker, closed spaces to be filled with suitable compound compatible with
the products carried.
WELDING AND MATERIALS:
Welding requirements:
- corrugations and stool side plating generally to be connected with full penetration welding to stool top plate (if not full pene-
tration welding, the weld preparation is to be indicated on the approved drawings); root gap to be checked along the produc-
tion,
- shedder plates to be connected with one side penetration, or equivalent, to corrugations and stool top plate,
- welding sequence against the risk of lamellar tearing,
- start and stop welding away from the locations of corrugation bents,
- weld finishing well faired to the stool top plate, corrugation flanges and stool side plating.
Material requirements:
- the stool top plate is recommended to be of Z25/ZH25 quality. If a steel of such a quality is not adopted, 100% UE of the
plate in way of the weld is required prior to and after welding,
- material properties of:
the shedder plates,
the stool top plate,
the portion A of the stool side plating,
to be not less than those of the corrugation flanges.
Table 49 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
AREA 5: Lower part of transverse bulkheads Connection of lower stools with corrugated bulkheads -
Sheet 5.11
with lower stools Gusset and shedder plates
Aa
Shedder plates nx
Hot spot stress:
SX = KSX nX
Gusset plates
tF = corrugation flange thickness,
tT = stool top plate thickness,
tS = stool side plating thickness,
a
hG tG = gusset plate thickness,
Stool top plate
tSH = shedder plate thickness,
A tA = min (tF , tT , tS ),
tB = min (tG , tT , tS ).
SCANTLINGS: FATIGUE:
tT tF . tS tF in portion A. Fatigue check not required.
tG tF . tSH 0,75 tF . hG a / 2.
CONSTRUCTION: NDE:
Misalignment (median lines) between corrugation flanges and stool side The following NDE are required:
plating tA / 3. VE 100%,
Misalignment (median lines) between lower edge of gusset plates and stool UE 35% of full penetration welds for absence
side plating tB / 3. of cracks, lack of penetration and lamellar
Distance from the edge of the stool top plate to the surface of the corrugation tears.
flanges 1,5 tF .
Corrugation radius according to Ch 4, Sec 7, [3.1.3].
In ships with service notations combination carrier, oil tanker or chemical
tanker, closed spaces to be filled with suitable compound compatible with
the products carried.
WELDING AND MATERIALS:
Welding requirements:
- corrugations and stool side plating generally to be connected with full penetration welding to stool top plate (if not full pene-
tration welding, the weld preparation is to be indicated on the approved drawings); root gap to be checked along the produc-
tion,
- gusset plates generally to be connected with full penetration welding to stool top plate (if not full penetration welding, the
weld preparation is to be indicated on the approved drawings) and with one side penetration, or equivalent, to corrugations
and shedder plates,
- shedder plates to be connected with one side penetration, or equivalent, to corrugations and gusset plates,
- welding sequence against the risk of lamellar tearing,
- start and stop welding away from the locations of corrugation bents,
- weld finishing well faired to the stool top plate, corrugation flanges and stool side plating.
Material requirements:
- the stool top plate is recommended to be of Z25/ZH25 quality. If a steel of such a quality is not adopted, 100% UE of the
plate in way of the weld is required prior to and after welding,
- material properties of:
the gusset plates,
the shedder plates,
the stool top plate,
the portion A of the stool side plating,
to be not less than those of the corrugation flanges.
Table 50 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
AREA 5: Lower part of transverse bulkheads Connection of lower stools with corrugated bulkheads -
Sheet 5.12
with lower stools Sloping stool top plate
Aa
nx
Hot spot stress:
Shedder plate
a SX = KSX nX
SCANTLINGS: FATIGUE:
tT tF . Fatigue check to be carried out for L 170 m:
tS tF in portion A. KSX = 1,90
tSH 0,75 tF .
CONSTRUCTION: NDE:
Misalignment (median lines) between corrugation flanges and stool side The following NDE are required:
plating tA / 3. VE 100%,
Misalignment (median lines) between lower edge of shedder plates and stool UE 35% of full penetration welds for absence
side plating tB / 3. of cracks, lack of penetration and lamellar
Knuckled shedder plates are to be avoided. tears.
Distance from the edge of the stool top plate to the surface of the corrugation
flanges 1,5 tF .
Corrugation radius according to Ch 4, Sec 7, [3.1.3].
In ships with service notations combination carrier, oil tanker or chemical
tanker, closed spaces to be filled with suitable compound compatible with
the products carried.
WELDING AND MATERIALS:
Welding requirements:
- corrugations and stool side plating generally to be connected with full penetration welding to stool top plate (if not full pene-
tration welding, the weld preparation is to be indicated on the approved drawings); root gap to be checked along the produc-
tion,
- shedder plates to be connected with one side penetration, or equivalent, to corrugations and stool top plate,
- welding sequence against the risk of lamellar tearing
- start and stop welding away from the locations of corrugation bents,
- weld finishing well faired to the stool top plate, corrugation flanges and stool side plating.
Material requirements:
- the stool top plate is recommended to be of Z25/ZH25 quality. If a steel of such a quality is not adopted, 100% UE of the
plate in way of the weld is required prior to and after welding,
- material properties of:
the shedder plates,
the stool top plate,
the portion A of the stool side plating,
to be not less than those of the corrugation flanges.
Table 51 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
AREA 5: Lower part of transverse bulkheads Connection of lower stools with corrugated bulkheads -
Sheet 5.13
with lower stools Brackets below stool top plate
A a,
B = bracket dimension.
tA = min (tF , tT , tS ).
tB = min (tW , tT , tS ).
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment (median lines) between corrugation flanges and stool side The following NDE are required:
plating tA / 3. VE 100%,
Misalignment (median lines) between corrugation webs and brackets below UE 35% of full penetration welds for absence
stool top plate tB / 3. of cracks, lack of penetration and lamellar
Distance from the edge of the stool top plate to the surface of the corrugation tears.
flanges 1,5 tF .
Corrugation radius according to Ch 4, Sec 7, [3.1.3].
Welding requirements:
- corrugations and stool side plating generally to be connected with full penetration welding to stool top plate (if not full pene-
tration welding, the weld preparation is to be indicated on the approved drawings); root gap to be checked along the produc-
tion,
- welding sequence against the risk of lamellar tearing,
- start and stop welding away from the locations of corrugation bents,
- weld finishing well faired to the stool top plate, corrugation flanges and stool side plating.
Material requirements:
- the stool top plate is recommended to be of Z25/ZH25 quality. If a steel of such a quality is not adopted, 100% UE of the
plate in way of the weld is required prior to and after welding,
- material properties of:
the stool top plate,
the portion A of the stool side plating,
to be not less than those of the corrugation flanges.
Table 52 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
AREA 5: Lower part of transverse bulkheads Connection of lower stools with corrugated bulkheads -
Sheet 5.14
with lower stools Shedder plates 45 and brackets below stool top plate
A a,
B = bracket dimension.
tF = corrugation flange thickness,
tW = corrugation web thickness,
tT = stool top plate thickness,
tS = stool side plating thickness,
tSH = shedder plate thickness,
tB = bracket thickness,
tA = min (tF , tT , tS )
tB = min (tSH , tT , tS )
tC = min (tW , tT , tB ).
SCANTLINGS: FATIGUE:
tT tF tS tF in portion A Bd Fatigue check to be carried out for L 170 m:
tSH 0,75 tF tB tW KSX = 1,25
CONSTRUCTION: NDE:
Misalignment (median lines) between corrugation flanges and stool side The following NDE are required:
plating tA / 3. VE 100%,
Misalignment (median lines) between lower edge of shedder plates and stool UE 35% of full penetration welds for absence
side plating tB / 3. of cracks, lack of penetration and lamellar
Misalignment (median lines) between corrugation webs and brackets below tears.
stool top plate tC / 3.
Knuckled shedder plates are to be avoided.
Distance from the edge of the stool top plate to the surface of the corrugation
flanges 1,5 tF .
Corrugation radius according to Ch 4, Sec 7, [3.1.3].
In ships with service notations combination carrier, oil tanker or chemical
tanker, closed spaces to be filled with suitable compound compatible with
the products carried.
WELDING AND MATERIALS:
Welding requirements:
- corrugations and stool side plating generally to be connected with full penetration welding to stool top plate (if not full pene-
tration welding, the weld preparation is to be indicated on the approved drawings); root gap to be checked along the produc-
tion,
- shedder plates to be connected with one side penetration, or equivalent, to corrugations and stool top plate,
- welding sequence against the risk of lamellar tearing
- start and stop welding away from the locations of corrugation bents,
- weld finishing well faired to the stool top plate, corrugation flanges and stool side plating.
Material requirements:
- the stool top plate is recommended to be of Z25/ZH25 quality. If a steel of such a quality is not adopted, 100% UE of the
plate in way of the weld is required prior to and after welding,
- material properties of:
the shedder plates,
the stool top plate,
the portion A of the stool side plating,
to be not less than those of the corrugation flanges.
Table 53 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
AREA 5: Lower part of transverse bulkheads Connection of lower stools with corrugated bulkheads -
Sheet 5.15
with lower stools Gusset and shedder plates and brackets below stool top plate
A a,
B = bracket dimension.
nx
Hot spot stress:
SX = KSX nX
tF = corrugation flange thickness,
tW = corrugation web thickness,
tT = stool top plate thickness,
tS = stool side plating thickness,
tG = gusset plate thickness,
tSH = shedder plate thickness,
tB = bracket thickness,
tA = min (tF , tT , tS )
tB = min (tG , tT , tS )
tC = min (tW , tT , tB ).
SCANTLINGS: FATIGUE:
tT tF tS tF in portion A tG tF tSH 0,75 tF Fatigue check not required.
tB tW hG a / 2 Bd
CONSTRUCTION: NDE:
Misalignment (median lines) between corrugation flanges and stool side plating tA / The following NDE are required:
3. VE 100%,
Misalignment (median lines) between lower edge of gusset plates and stool side plat- UE 35% of full penetration welds for
ing tB / 3. absence of cracks, lack of penetra-
Misalignment (median lines) between corrugation webs and brackets below stool top tion and lamellar tears.
plate tC / 3.
Distance from the edge of the stool top plate to the surface of the corrugation flanges
1,5 tF .
Corrugation radius according to Ch 4, Sec 7, [3.1.3].
In ships with service notations combination carrier, oil tanker or chemical tanker,
closed spaces to be filled with suitable compound compatible with the products car-
ried.
WELDING AND MATERIALS:
Welding requirements:
- corrugations and stool side plating generally to be connected with full penetration welding to stool top plate (if not full pene-
tration welding, the weld preparation is to be indicated on the approved drawings); root gap to be checked along the produc-
tion,
- gusset plates generally to be connected with full penetration to stool top plate (if not full penetration welding, the weld prep-
aration is to be indicated on the approved drawings) and with one side penetration, or equivalent, to corrugations and shed-
der plates,
- shedder plates to be connected with one side penetration, or equivalent, to corrugations and gusset plates,
- welding sequence against the risk of lamellar tearing
- start and stop welding away from the locations of corrugation bents,
- weld finishing well faired to the stool top plate, corrugation flanges and stool side plating.
Material requirements:
- the stool top plate is recommended to be of Z25/ZH25 quality. If a steel of such a quality is not adopted, 100% UE of the
plate in way of the weld is required prior to and after welding,
- material properties of:
the gusset plates,
the shedder plates,
the stool top plate,
the portion A of the stool side plating,
to be not less than those of the corrugation flanges.
Table 54 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
AREA 6: Lower part of inner side Connection of hopper tank sloping plates with inner side Sheet 6.1
ny
nx Hot spot B
Section a - a
A = distance to be taken not less than the spacing of side
transverses
tB = minimum among:
thickness of member above hopper tank top plate,
thickness of member below hopper tank top plate,
t2 .
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment (median lines) between inner side plating and hopper The following NDE are required:
tank sloping plate tA / 3. VE 100%,
Misalignment (median lines) between members above and below UE 25% of full penetration welds for absence of
hopper tank top plate tB / 3. cracks, lack of penetration and lamellar tears.
Welding requirements:
- inner side and hopper tank sloping plate generally to be connected with full penetration welding to hopper tank top plate (if
not full penetration welding, the weld preparation is to be indicated on the approved drawings),
- approval of the procedure on a sample representative of the actual conditions foreseen in production,
- welding sequence against the risk of lamellar tearing is recommended in case Z material is not adopted for the hopper tank
top plate,
- weld finishing well faired to the hopper tank top plate.
Material requirements:
- the hopper tank top plate is recommended to be Z25/ZH25 quality. If a steel of such a quality is not adopted, 100% UE of the
plate in way of the weld is required prior to and after welding,
- material properties of the portion A of the hopper tank sloping plate to be not less than those of the inner side plating.
Table 55 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
ny
nx
Hot spot B
Section a - a
A = distance to be taken not less than the spacing of side
transverses
Hot spot stresses:
At hot spot A:
SX = KSX nX
At hot spot B:
SY = KSY nY + KSXY nX
tA = min (t1 , t2 , t3 )
tB = minimum among:
thickness of member above hopper tank top plate,
thickness of intermediate bracket,
t2 .
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment (median lines) between inner side plating and hopper tank The following NDE are required:
sloping plate tA / 3. VE 100%,
Misalignment (median lines) between intermediate bracket and member UE 25% of full penetration welds for absence of
above hopper tank top plate tB / 3. cracks, lack of penetration and lamellar tears.
Intermediate brackets to be fitted in place and welded after the welding
of the joint between the hopper tank sloping plate and the hopper tank
top plate.
Welding requirements:
- inner side and hopper tank sloping plate generally to be connected with full penetration welding to hopper tank top plate (if
not full penetration welding, the weld preparation is to be indicated on the approved drawings),
- brackets to be connected with continuous fillet welding to plating and stiffeners,
- approval of the procedure on a sample representative of the actual conditions foreseen in production,
- welding sequence against the risk of lamellar tearing is recommended in case Z material is not adopted for the hopper tank
top plate,
- weld finishing well faired to the hopper tank top plate.
Material requirements:
- the hopper tank top plate is recommended to be Z25/ZH25 quality. If a steel of such a quality is not adopted, 100% UE of the
plate in way of the weld is required prior to and after welding,
- material properties of the portion A of the hopper tank sloping plate to be not less than those of the inner side plating.
Table 56 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
ny
nx
Hot spot B
Section a - a
A = distance to be taken not less than the spacing of side
transverses
Hot spot stresses:
At hot spot A:
SX = KSX nX
At hot spot B:
SY = KSY nY + KSXY nX
tA = min (t1 , t2 , t3 )
tB = minimum among:
thickness of member above hopper tank top plate,
thickness of member below hopper tank top plate,
t2 .
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment (median lines) between hopper tank top plate and hopper The following NDE are required:
tank sloping plate tA / 3. VE 100%,
Misalignment (median lines) between members above and below hop- UE 25% of full penetration welds for absence of
per tank top plate tB / 3. cracks, lack of penetration and lamellar tears.
Welding requirements:
- hopper tank sloping plate to be connected with full penetration welding to the inner side plating. Root gap to be checked
along the production steps as appropriate,
- prolonging brackets to be connected with full penetration welding to inner side plating,
- full penetration weld of hopper tank sloping plate to inner side plating to be welded first,
- welding sequence against lamellar tearing in the inner side plating is recommended.
Material requirements:
- the lower strake of inner side plating is recommended to be Z25/ZH25 quality. If a steel of such a quality is not adopted,
100% UE of the strake in way of the weld is required prior to and after welding,
- material properties of the portion A of the hopper tank sloping plate to be not less than those of the inner side plating,
- material properties of prolonging brackets to be not less than those of the inner side plating.
Table 57 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
ny
nx Hot spot B
Section a - a
A = distance to be taken not less than the spacing of side
transverses
SCANTLINGS: FATIGUE:
Inner radius of the bent plate to be between 3,5 and 5 times the thickness Fatigue check to be carried out for L 170 m:
of the bent plate and to be indicated in the approved plan. KSX = 3,30
t2 t1 . KSY = 1,30
t3 t1 in portion A. KSXY = 2,25
Thickness of members above and below hopper tank top plate to be not
less than that of side transverses.
CONSTRUCTION: NDE:
Misalignment (median lines) between hopper tank top plate and hopper The following NDE are required:
tank sloping plate tA / 3. VE 100%,
Misalignment (median lines) between members above and below hopper UE 25% of full penetration welds, if any, for
tank top plate tB / 3. absence of cracks, lack of penetration and
If not full penetration welding of hopper tank top plate to inner side, the lamellar tears.
weld preparation is to be indicated on the approved drawings.
Butt welds between inner side and hopper tank sloping plate at a distance
greater than 500 mm from the hopper tank top plate.
Welding requirements:
- welding sequence against the risk of lamellar tearing in the inner side plate is recommended,
- weld finishing well faired to the inner side plating and hopper tank sloping plate.
Material requirements:
- the radiused construction may be accepted provided that the folding procedure is submitted to the Society for review, with
evidence given that the mechanical properties and, in particular, the impact properties are not deteriorated by the folding
operation,
- material properties of the portion A of the hopper tank sloping plate to be not less than those of the inner side plating.
Table 58 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
ny
nx
Hot spot B
Section a - a
A = distance to be taken not less than the spacing of
side transverses
Hot spot stresses:
At hot spot A:
SX = KSX nX
At hot spot B:
SY = KSY nY + KSXY nX
tA = min (t1 , t2 , t3 )
tB = minimum among:
thickness of member above hopper tank top plate,
thickness of intermediate bracket,
t2 .
SCANTLINGS: FATIGUE:
Inner radius of the bent plate to be between 3,5 and 5 times the thickness Fatigue check to be carried out for L 170 m:
of the bent plate and to be indicated in the approved plan. KSX = 3,15
t2 t1 . KSY = 1,30
t3 t1 in portion A. KSXY = 2,05
Thickness of intermediate brackets and members above hopper tank top
plate to be not less than that of side transverses.
CONSTRUCTION: NDE:
Misalignment (median lines) between hopper tank top plate and hopper The following NDE are required:
tank sloping plate tA / 3. VE 100%,
Misalignment (median lines) between intermediate bracket and member UE 25% of full penetration welds, if any, for
above hopper tank top plate tB / 3. absence of cracks, lack of penetration and
If not full penetration welding of hopper tank top plate to inner side, the lamellar tears.
weld preparation is to be indicated on the approved drawings.
Intermediate brackets to be fitted in place and welded after the welding of
the joint between the hopper tank top plate and the inner side plating.
Butt welds between inner side and hopper tank sloping plate at a distance
greater than 500 mm from the hopper tank top plate.
Welding requirements:
- brackets to be connected with continuous fillet welding to plating and stiffeners,
- welding sequence against the risk of lamellar tearing in the inner side plate is recommended,
- weld finishing well faired to the inner side plating and hopper tank sloping plate.
Material requirements:
- the radiused construction may be accepted provided that the folding procedure is submitted to the Society for review, with
evidence given that the mechanical properties and, in particular, the impact properties are not deteriorated by the folding
operation,
- material properties of the portion A of the hopper tank sloping plate to be not less than those of the inner side plating.
Table 59 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
ny
nx
Hot spot B
Section a - a
A = distance to be taken not less than the spacing of side
transverses
Hot spot stresses:
At hot spot A:
SX = KSX nX
At hot spot B:
SY = KSY nY + KSXY nX
SCANTLINGS: FATIGUE:
Inner radius of the bent plate to be between 3,5 and 5 times the thickness Fatigue check to be carried out for L 170 m:
of the bent plate and to be indicated in the approved plan. KSX = 4,50
d 40 mm. KSY = 1,30
t2 t1 . KSXY = 5,60
t3 t1 in portion A.
Thickness of members above and below hopper tank top plate to be not
less than that of side transverses.
CONSTRUCTION: NDE:
Misalignment (median lines) between members above and below hopper The following NDE are required:
tank top plate t / 3. VE 100%,
If not full penetration welding of hopper tank top plate to inner side, the UE 25% of full penetration welds, if any, for
weld preparation is to be indicated on the approved drawings. absence of cracks, lack of penetration and
Butt welds between inner side and hopper tank sloping plate at a distance lamellar tears.
greater than 500 mm from the hopper tank top plate.
Material requirements:
- where hopper tank top plate is welded within the bent area, folding procedure to be submitted to the Society for review, with evi-
dence given that the mechanical properties and, in particular, the impact properties are not deteriorated by the folding operation,
- material properties of the portion A of the hopper tank sloping plate to be not less than those of the inner side plating.
Table 60 : OIL TANKERS, CHEMICAL TANKERS, BULK CARRIERS, ORE CARRIERS, COMBINATION CARRIERS
t1 ny
Hot spots A
nx Hot spot B
Hopper tank Inner side
top plate
a a Section a - a
A = distance to be taken not less than the spacing of side
t2 transverses
a A At hot spot A:
SX = KSX nX
At hot spot B:
Intermediate a
SY = KSY nY + KSXY nX
bracket Sloping
plate t = minimum among:
thickness of member above hopper tank top plate,
thickness of intermediate bracket,
t3 t2 .
SCANTLINGS: FATIGUE:
Inner radius of the bent plate to be between 3,5 and 5 times the thickness Fatigue check to be carried out for L 170 m:
of the bent plate and to be indicated in the approved plan. KSX = 3,85
d 40 mm. KSY = 1,30
t2 t1 . KSXY = 4,50
t3 t1 in portion A.
Thickness of intermediate brackets and members above hopper tank top
plate to be not less than that of side transverses.
CONSTRUCTION: NDE:
Misalignment (median lines) between intermediate bracket and member The following NDE are required:
above hopper tank top plate t / 3. VE 100%,
If not full penetration welding of hopper tank top plate to inner side, the UE 25% of full penetration welds, if any, for
weld preparation is to be indicated on the approved drawings. absence of cracks, lack of penetration and
Intermediate brackets to be fitted in place and welded after the welding of lamellar tears.
the joint between the hopper tank top plate and the inner side plating.
Butt welds between inner side and hopper tank sloping plate at a distance
greater than 500 mm from the hopper tank top plate.
Material requirements:
- where hopper tank top plate is welded within the bent area, folding procedure to be submitted to the Society for review, with evi-
dence given that the mechanical properties and, in particular, the impact properties are not deteriorated by the folding operation,
- material properties of the portion A of the hopper tank sloping plate to be not less than those of the inner side plating.
AREA 6: Lower part of inner side Connection of hopper tank sloping plates with inner side Sheet 6.8
ny
nx Hot spot B
Section a - a
tB = minimum among:
thickness of member above hopper tank top plate,
thickness of member below hopper tank top plate,
t2 .
SCANTLINGS: FATIGUE:
Thickness of members above and below hopper tank top plate to be K SXY = 2,00
not less than that of side transverses.
CONSTRUCTION: NDE:
Misalignment (median lines) between inner side plating and hopper The following NDE are required:
tank sloping plate tA / 3, max 6 mm. VE 100%,
Misalignment (median lines) between members above and below UE 35% of full penetration welds for absence of
hopper tank top plate tB / 3, max 6 mm. cracks, lack of penetration and lamellar tears.
Welding requirements:
- inner side and hopper tank sloping plate to be connected with full penetration welding to hopper tank top plate, except in
way of void spaces where partial penetration may be accepted,
- approval of the procedure on a sample representative of the actual conditions foreseen in production,
- welding sequence against the risk of lamellar tearing is recommended in case Z material is not adopted for the hopper tank
top plate,
- weld finishing well faired to the hopper tank top plate.
Material requirements:
- the hopper tank top plate is to be of Z25/ZH25 or of a steel of the same mechanical performances. In particular cases, grade
E/EH low temperature steel may be accepted by the Society provided that the results of 100% UE of the plate in way of the
weld, carried out prior to and after welding, are submitted for review,
- material properties of the portion A of the hopper tank sloping plate to be not less than those of the inner side plating.
ny
nx
Hot spot B
Section a - a
A = distance to be taken not less than the spacing of side
transverses
Hot spot stresses:
At hot spot A:
SX = KSX nX
At hot spot B:
SY = KSY nY + KSXY nX
tA = min (t1 , t2 , t3 )
tB = minimum among:
thickness of member above hopper tank top plate,
thickness of intermediate bracket,
t2 .
SCANTLINGS: FATIGUE:
d 1,5 t1 . Fatigue check to be carried out for L 170 m:
t2 t1 . KSX = 3,55
t3 t1 in portion A. KSY = 1,30
Thickness of intermediate brackets and members above hopper tank top KSXY = 1,75
plate to be not less than that of side transverses.
CONSTRUCTION: NDE:
Misalignment (median lines) between inner side plating and hopper tank The following NDE are required:
sloping plate tA / 3, max 6 mm. VE 100%,
Misalignment (median lines) between intermediate bracket and member UE 35% of full penetration welds for absence of
above hopper tank top plate tB / 3, max 6 mm. cracks, lack of penetration and lamellar tears.
Intermediate brackets to be fitted in place and welded after the welding of
the joint between the hopper tank sloping plate and the hopper tank top
plate.
Connection of side frames with hopper and topside tanks - Symmetric face
AREA 7: Side frames Sheet 7.1
plate frame with integral brackets
! "
#$ %#&'%(
tw = fitted thickness, in mm, of side frame web tw,min = (7,0 + 0,03 L1) mm
bF = bracket flange width, in mm tF = bracket flange thickness, in mm.
SCANTLINGS: FATIGUE:
Thickness of lower bracket, in mm, max (tw , tw, min + 2). Fatigue check not required.
Thickness of upper bracket, in mm, max (tw , tw, min ).
Section modulus of the frame with the upper or lower bracket, at the locations shown in the
sketch, to be not less than twice the section modulus required for the frame mid-span area.
Dimensions of lower and upper brackets to be not less than those shown in the sketch.
Structural continuity with the upper and lower end connections of side frames is to be ensured
within hopper tanks and upper wing tanks by connecting brackets.
Frame flange to be curved (not knuckled) at the connection with the end brackets, r 0,4 bF2 / tF .
Ends of flange to be sniped.
CONSTRUCTION: NDE:
Misalignment between frame web and the connecting brackets The following NDE are required:
inside hopper tank and upper wing tank t / 3, where t is the mini- VE 100%, with particular care for fillet shape and
mum thickness among those of the connected elements. undercuts on the plating at the soft toes,
Soft toe: tapering of frame flange at ends: thickness 1:3, width 1:5. ME or dye penetrant depending on the results of VE.
WELDING AND MATERIALS:
Welding requirements:
- frames and brackets to be connected with continuous fillet welding to side plating, hopper tank and upper wing tank plating,
with throat thickness to be not less than:
0,45 t in zone a,
0,40 t in zone b,
where t is the minimum thickness between those of the two connected elements,
- welding sequence to minimise restraints at the frame butt joints, i.e.:
leaving about 200 mm unwelded, each side of butt joint, of the connections between frame web and side plating and
between frame web and flange,
performing the frame butt joints,
completing the fillet welding,
- turn the fillet weld all around the end of integral brackets and scallops giving an elongated shape, well faired to the plating,
- avoid burned notches at the scallops, if existing, in way of frame flange butt joints; if scallops not adopted, care to be taken to
avoid end defects at web butt joints.
Connection of side frames with hopper and topside tanks - Non symmetric face
AREA 7: Side frames Sheet 7.2
plate frame with separate brackets
$"%
$ '
!" ##
"& "
tw = fitted thickness, in mm, of side frame web tw,min = (7,0 + 0,03 L1) mm
bF = bracket flange width, in mm tF = bracket flange thickness, in mm.
SCANTLINGS: FATIGUE:
Thickness of lower bracket, in mm, max (tw , tw, min + 2). Fatigue check not required.
Thickness of upper bracket, in mm, max (tw , tw, min ).
Section modulus of the frame with the upper or lower bracket, at the locations shown in the sketch,
to be not less than twice the section modulus required for the frame mid-span area.
Dimensions of lower and upper brackets to be not less than those shown in the sketch.
Structural continuity with the upper and lower end connections of side frames is to be ensured
within hopper tanks and upper wing tanks by connecting brackets.
Ends of flange to be sniped.
z 50 mm.
CONSTRUCTION: NDE:
Misalignment between frame brackets and the connecting brackets The following NDE are required:
inside hopper tank and upper wing tank t / 3, where t is the mini- VE 100%, with particular care for fillet shape and
mum thickness among those of the connected elements. undercuts on the plating at the soft toes,
Bracket overlap: 1,5 d, in mm. ME or dye penetrant depending on the results of VE.
Soft toe: tapering of frame flange at ends: thickness 1:3, width 1:5.
WELDING AND MATERIALS:
Welding requirements:
- frames and brackets to be connected with continuous fillet welding to side plating, hopper tank and upper wing tank plating,
with throat thickness to be not less than:
0,45 t in zone a,
0,40 t in zone b,
where t is the minimum thickness between those of the two connected elements,
- brackets to be connected with continuous fillet welding to frames, with throat thickness to be not less than half thickness of
brackets,
- welding procedure of frame butt joint, if any, to be approved with particular care for the welding of the bulbs and of the corner in
case of L sections,
- welding sequence to minimise restraints at the frame butt joints, i.e.:
leaving about 200 mm unwelded, each side of butt joint, of the connections between frame web and side plating and
between frame web and flange,
performing the frame butt joints,
completing the fillet welding,
- turn the fillet weld all around the end of integral brackets and scallops giving an elongated shape, well faired to the plating,
- avoid burned notches at fillet welds of overlapped joints and at scallops.
AREA 8: Topside tanks Connection of transverse corrugated bulkheads with topside tanks Sheet 8.1
SCANTLINGS: FATIGUE:
A transverse web or an intercostal reinforcement is to be fitted inside the top- Fatigue check not required.
side tank in line with the flanges of corrugation and the upper stool side plat-
ing. Its arrangement is to be indicated in the approved plan.
CONSTRUCTION: NDE:
Welding requirements:
- bulkhead plating to be connected with continuous fillet welding to topside plating and upper stool plating, full penetration weld
is recommended in way of corner of vertical and inclined plating of upper wing tank,
- throat thickness = 0,45 t, where t is the minimum thickness between those of the two connected elements,
- gap at T joint reduced to the minimum,
- welding sequence to minimise restraints.
AREA 9: Cross decks Connection of cross decks with side transverses Sheet 9.1
Cross deck
Side transverse
SCANTLINGS: FATIGUE:
Cross deck strips between hatches to be suitably overlapped at ends. Fatigue check not required
Stresses due to forces transmitted by cross deck strips to web frames
calculated taking into account frame openings.
CONSTRUCTION: NDE:
Misalignment between brackets and webs of cross decks and web frames The following NDE are required:
t / 3. Visual examination 100%, with particular care for:
- fillet shape and undercuts at ends of brackets, if
grinding on plating is not adopted,
- quality of cuts at bracket free edge,
UE 100% of full penetration welds, if any, for absence
of cracks, lack of penetration and lamellar tears.
Welding requirements:
- cross deck structures to be connected with continuous fillet welding to web frame structures, full penetration weld recommended
in areas indicated in the sketch,
- throat thickness = 0,45 t, where t is the minimum thickness between those of the two connected elements,
- turn the fillet weld all around the bracket ends giving an elongated shape, well faired to the frame and cross deck, avoiding
notches; grinding recommended.
AREA 9: Cross decks Connection between face plates of cross decks and deck girders Sheet 9.2
B = min (B1 , B2 )
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Welding requirements:
- brackets to be connected with full penetration welding to deck girder and cross deck face plates,
- welds recommended to be continued on auxiliary pieces temporarily fitted at both end of each joint, to be cut away; joint ends
to be carefully ground.
AREA 10: Hatch corners Deck plating in way of hatch corners Sheet 10.1
SCANTLINGS: FATIGUE:
Insert plates with circular profiles in general to be fitted in way of corners of Fatigue check not required.
hatchways located within the cargo area. The radius of circular corners to be
in accordance with Ch 4, Sec 6, [6.2.1].
Insert plates not required in way of corners of hatchways located in the above
positions, where corners have an elliptical or parabolic profile according to
Ch 4, Sec 6, [6.2.2].
Where insert plates are required, their thickness to be defined according to
Ch 4, Sec 6, [6.2.3] and their extension to be such that d1 , d2 , d3 and d4 s,
s being the ordinary frame spacing.
CONSTRUCTION: NDE:
Corners of insert plates to be rounded, unless corresponding to joints of deck The following NDE are required:
strakes. VE 100%,
Insert cut edges to be carefully executed. RE / UE in areas indicated in the sketch.
Welding requirements:
- welds recommended to be continued on auxiliary pieces temporarily fitted at the free end of each joint, to be cut away; the
joint ends are to be carefully ground.
Materials requirements:
- insert plate material of same or higher quality than the adjacent deck plating, depending on the insert thickness according to
Ch 4, Sec 1, [2].
AREA 10: Hatch corners Ends of longitudinal hatch coamings - Bracket welded to deck plating Sheet 10.2
tA = minimum among:
- thickness of bracket flange at
lower end,
- deck plating thickness,
- under deck transverse stiffener
web thickness,
tB = minimum among:
- bracket web thickness,
- deck plating thickness,
- thickness of the under deck longi-
tudinal member.
SCANTLINGS: FATIGUE:
An additional under deck transverse stiffener is to be fitted in way of Fatigue check not required.
termination bracket toe, where the toe is clear of normal stiffener.
CONSTRUCTION: NDE:
Misalignment between bracket flange and under deck transverse The following NDE are required:
stiffener tA / 3. VE 100%, with particular care for the weld shape and
Misalignment between bracket and under deck longitudinal undercuts on deck plating at the bracket flange connec-
tB / 3. tion,
UE 100% of full penetration welds for absence of cracks,
lack of penetration and lamellar tears.
Welding requirements:
- bracket flange to be connected with full penetration welding to deck plating, with half V bevel and weld shape elongated on
deck plating (see sketch),
- ends of bracket webs to be connected with full penetration welding to deck plating for the extension shown in the sketch, with
half X bevel,
- under deck transverse stiffener to be connected with full penetration welding to deck plating in way of the bracket flange,
- care is to be taken to ensure soundness of the crossing welds at the bracket toe, if the case, adopting small scallop to be closed by
welding.
AREA 10: Hatch corners Ends of longitudinal hatch coamings - Bracket sniped at deck plating Sheet 10.3
t = minimum among:
- bracket web thickness,
- deck plating thickness,
- thickness of the under deck
longitudinal member.
SCANTLINGS: FATIGUE:
CONSTRUCTION: NDE:
Misalignment between bracket and under deck longitu- The following NDE are required:
dinal tB / 3. VE 100%, with particular care for the weld shape and undercuts
Soft toe: tapering of bracket flange at ends: thickness on deck plating,
1:3, width 1:5. UE 100% of full penetration welds for absence of cracks, lack of
penetration and lamellar tears.
Welding requirements:
- ends of bracket webs to be connected with full penetration welding to deck plating for the extension shown in the sketch, with
half X bevel.
Part C
Machinery, Electricity, Automation and
Fire Protection
Chapters 1 2 3 4
Chapter 1 MACHINERY
Chapter 2 ELECTRICAL INSTALLATIONS
Chapter 3 AUTOMATION
Chapter 4 FIRE PROTECTION, DETECTION AND EXTINCTION
Section 6 Gearing
1 General 106
1.1 Application
1.2 Documentation to be submitted
2 Design of gears - Determination of the load capacity of
cylindrical gears 109
2.1 Symbols, units, definitions
2.2 Principle
2.3 General influence factors
2.4 Calculation of surface durability
2.5 Calculation of tooth bending strength
2.6 Calculation of scuffing resistance
Section 8 Propellers
1 General 149
1.1 Application
1.2 Definitions
1.3 Documentation to be submitted
1 General 157
1.1 Application
2 Design of systems in respect of vibrations 157
2.1 Principle
2.2 Modifications of existing plants
3 Torsional vibrations 157
3.1 Documentation to be submitted
3.2 Definitions, symbols and units
3.3 Calculation principles
3.4 Permissible limits for torsional vibration stresses in crankshaft, propulsion
shafting and other transmission shafting
3.5 Permissible vibration levels in components other than shafts
3.6 Torsional vibration measurements
1 General 162
1.1 Application
1.2 Documentation to be submitted
1.3 Definitions
1.4 Symbols and units
1.5 Class of piping systems
2 General requirements for design and construction 164
2.1 Materials
2.2 Thickness of pressure piping
2.3 Calculation of high temperature pipes
2.4 Junction of pipes
2.5 Protection against overpressure
2.6 Flexible hoses and expansion joints
2.7 Valves and accessories
Section 12 Thrusters
1 General 253
1.1 Application
1.2 Definitions
1.3 Thrusters intended for propulsion
1.4 Documentation to be submitted
2 Design and Construction 253
2.1 Materials
2.2 Transverse thrusters and azimuth thrusters
2.3 Water-jets
2.4 Alarm, monitoring and control systems
Section 14 Turbochargers
1 General 259
1.1 Application
1.2 Documentation to be submitted
1.3 Definition
2 Design and construction 259
2.1 Materials
2.2 Design
2.3 Monitoring
3 Arrangement and installation 260
3.1 General
4 Type tests, material tests, workshop inspection and testing,
certification 260
4.1 Type tests
4.2 Material tests
4.3 Workshop inspections and testing
4.4 Certification
Chapter 1
MACHINERY
For joints between plates having a difference in thickness 2.5 Ambient conditions
greater than 3 mm, a taper having a length of not less than 4
times the difference in thickness is required. Depending on 2.5.1 Machinery and systems covered by the Rules are to
the type of stress to which the joint is subjected, a taper be designed to operate properly under the ambient condi-
equal to three times the difference in thickness may be tions specified in Tab 2, unless otherwise specified in each
accepted. Section of this Chapter.
T-joints on scalloped edges are not permitted.
Lap-joints and T-joints subjected to tensile stresses are to Table 2 : Ambient conditions
have a throat size of fillet welds equal to 0,7 times the thick-
ness of the thinner plate on both sides. AIR TEMPERATURE
In the case of welded structures including cast pieces, the Location, arrangement Temperature range, in C
latter are to be cast with appropriate extensions to permit
In enclosed spaces between 0 and +45 (2)
connection, through butt-welded joints, to the surrounding
structures, and to allow any radiographic and ultrasonic On machinery components, According to specific
examinations to be easily carried out. boilers local conditions
In spaces subject to higher or
Where required, preheating and stress relieving treatments
lower temperatures
are to be performed according to the welding procedure
specification. On exposed decks between 25 and +45 (1)
2.7 Astern power for ships assigned with a restricted navigation nota-
tion which are not intended to comply with SOLAS
2.7.1 Sufficient power for going astern is to be provided to Convention, or whenever special precautions are
secure proper control of the ship in all normal circum- taken to the Society's satisfaction, provided that,
stances. from previously effected checks, it is evident that the
temperature of spaces where fuel oil is stored or
In order to maintain sufficient manoeuvrability and secure
employed will be at least 10C below the fuel oil
control of the ship in all normal circumstances, the main
flash point at all times. However, it has to be accept-
propulsion machinery is to be capable of reversing the
able also for the National Authority of the country in
direction of thrust so as to bring the ship to rest from the
which the ship is to be registered
maximum service speed. The main propulsion machinery is
to be capable of maintaining in free route astern at least b) In cargo ships, for installation specially approved for the
70% of the ahead revolutions. use of crude oil or slop as fuel for tanker boilers (refer-
Where steam turbines are used for main propulsion, they ence is made to IACS requirement M 24)
are to be capable of maintaining in free route astern at least
70% of the ahead revolutions for a period of at least c) In cargo ships, for installation specially approved for use
15 minutes. of boil-off gas as fuel for boilers or propulsion engines,
which is allowed on gas carriers, subject to the require-
For main propulsion systems with reversing gears, controlla- ments of Pt D, Ch 9, Sec 16.
ble pitch propellers or electrical propeller drive, running
astern is not to lead to an overload of propulsion machinery.
2.9.2 Machineries and piping systems for the usage of fuel
During the sea trials, the ability of the main propulsion oil having a flashpoint less than 60C shall also comply
machinery to reverse the direction of thrust of the propeller with the following:
is to be demonstrated and recorded (see also Ch 1, Sec 15).
a) For oil fuel having a flashpoint of less than 60C but not
less than 43C, oil tanks except those arranged in dou-
2.8 Safety devices ble bottom compartments shall be located outside of
machinery spaces of category A
2.8.1 Where risk from overspeeding of machinery exists,
means are to be provided to ensure that the safe speed is b) For oil fuel having a flashpoint of less than 43C, where
not exceeded. permitted, the following provisions are to be complied
with:
2.8.2 Where main or auxiliary machinery including pres-
sure vessels or any parts of such machinery are subject to Oil tanks are to be located outside machinery
internal pressure and may be subject to dangerous over- spaces and the arrangements adopted have to be
pressure, means shall be provided, where practicable, to specially approved by the Society
protect against such excessive pressure.
Provisions for the measurement of oil temperature
2.8.3 Main turbine propulsion machinery and, where appli- should be provided on the suction pipe of oil fuel
cable, main internal combustion propulsion machinery and pump
auxiliary machinery shall be provided with automatic shut-
Stop valves and/or cocks are to be provided to the
off arrangements in the case of failures, such as lubricating
inlet side and outlet side of the oil fuel strainers
oil supply failure, which could lead rapidly to complete
breakdown, serious damage or explosion. Pipe joints of welded construction or of circular
The Society may permit provisions for overriding automatic cone type or spherical type union joint are to be
shut-off devices. applied as much as possible.
See also the specific requirements given in the other Sec-
tions of this Chapter. 3 Arrangement and installation on board
2.9 Fuels
3.1 General
2.9.1 Fuel oils employed for engines and boilers are, in
general, to have a flash point (determined using the closed 3.1.1 Provision shall be made to facilitate cleaning, inspec-
cup test) of not less than 60C, except for the following: tion and maintenance of main propulsion and auxiliary
machinery, including boilers and pressure vessels.
a) Fuel oils having a flash point of less than 60C but not
less than 43C may be accepted in following cases: Easy access to the various parts of the propulsion machinery
for engines driving emergency generators is to be provided by means of metallic ladders and gratings
fitted with strong and safe handrails.
for feeding the emergency fire pump's engines and
the auxiliary machines which are not located in the Spaces containing main and auxiliary machinery are to be
machinery spaces of category A provided with adequate lighting and ventilation.
3.2 Floor plating and gratings and the operation of the machinery. Any other machinery
space shall be adequately ventilated appropriate for the
3.2.1 The floor plating and gratings in machinery spaces purpose of that machinery space.
are to be metallic, divided into easily removable panels. The ventilation of machinery spaces is to be supplied
through suitably protected openings arranged in such a way
3.2.2 The floor plating of normal passageways in machinery that they can be used in all weather conditions, taking into
spaces of category A shall be made of steel. account Reg. 17(3) and Reg. 19 of the 1966 Load Line Con-
vention as amended by the Protocal of 1988.
3.3 Bolting down Special attention is to be paid both to air delivery and
extraction and to air distribution in the various spaces. The
3.3.1 Bedplates of machinery are to be securely fixed to the quantity and distribution of air are to be such as to satisfy
supporting structures by means of foundation bolts which machinery requirements for developing maximum continu-
are to be distributed as evenly as practicable and of a suffi- ous power.
cient number and size so as to ensure proper fitting.
The ventilation is to be so arranged as to prevent any accu-
Where the bedplates bear directly on the inner bottom plat- mulation of flammable gases or vapours.
ing, the bolts are to be fitted with suitable gaskets so as to
ensure a tight fit and are to be arranged with their heads
within the double bottom. 3.7 Hot surfaces and fire protection
Continuous contact between bedplates and foundations 3.7.1 Surfaces, having temperature exceeding 60C, with
along the bolting line is to be achieved by means of chocks which the crew are likely to come into contact during oper-
of suitable thickness, carefully arranged to ensure a com- ation are to be suitably protected or insulated.
plete contact.
Surfaces of machinery with temperatures above 220C, e.g.
The same requirements apply to thrust block and shaft line steam, thermal oil and exhaust gas lines, silencers, exhaust
bearing foundations. gas boilers and turbochargers, are to be effectively insulated
with non-combustible material or equivalently protected to
Particular care is to be taken to obtain levelling and general
prevent the ignition of combustible materials coming into
alignment between the propulsion engines and their shaft-
contact with them. Where the insulation used for this pur-
ing (see Ch 1, Sec 7).
pose is oil absorbent or may permit the penetration of oil,
the insulation is to be encased in steel sheathing or equiva-
3.3.2 Chocking resins are to be type approved.
lent material.
3.3.3 Where stays are provided for fixing the upper part of Fire protection, detection and extinction is to comply with
engines to the ships structure in order, for example, to the requirements of Part C, Chapter 4.
reduce the amplitude of engine vibrations, such stays are to
be so designed as to prevent damage to these engines fur- 3.7.2 Incinerators (except those exclusively intended to
ther to deformation of the shell plating in way of the said burn oil residue), as well as thermal fluid heaters, are to be
stays. The stays are to be connected to the hull in such a located in rooms other than the following spaces:
way as to avoid abnormal local loads on the structure of the propulsion plant and auxiliary spaces
ship.
steering gear room
rooms containing electric generating sets (including the
3.4 Safety devices on moving parts
emergency generating set) or containing the main or the
emergency switchboard
3.4.1 Suitable protective devices on access restrictions are
to be provided in way of moving parts (flywheels, cou- rooms containing hydraulic equipment
plings, etc.) in order to avoid accidental contact of person- engine control room
nel with moving parts.
engineers' and electricians' workshops.
3.5 Gauges 3.7.3 As far as practicable, the hydraulic power units are
not to be located in machinery spaces containing the boil-
3.5.1 All gauges are to be grouped, as far as possible, near ers, main engine, its auxiliaries or other sources of ignition.
each manoeuvring position; in any event, they are to be Unless otherwise specified, the hydraulic systems are to
clearly visible. comply with the provision of Ch 1, Sec 10, [14].
3.6 Ventilation in machinery spaces 3.8 Machinery remote control, alarms and
safety systems
3.6.1 Machinery spaces of Category A shall be adequately
ventilated so as to ensure that when machinery or boilers 3.8.1 For remote control systems of main propulsion
therein are operating at full power in all weather conditions machinery and essential auxiliary machinery and relevant
including heavy weather, an adequate supply of air is main- alarms and safety systems, the requirements of Part C, Chap-
tained to the spaces for the safety and comfort of personel ter 3 apply.
4 Tests and trials tests are to be carried out in accordance with the provisions
of NR216 Materials and Welding, relative to incomplete
tests.
4.1 Works tests
All boilers, all parts of machinery, all steam, hydraulic,
4.1.1 Equipment and its components are subjected to pneumatic and other systems and their associated fittings
works tests which are detailed in the relevant Sections of which are under internal pressure shall be subjected to
this Chapter. The Surveyor is to be informed in advance of appropriate tests including a pressure test before being put
these tests. into service for the first time as detailed in the other Sections
Where such tests cannot be performed in the workshop, the of this Chapter.
Society may allow them to be carried out on board, pro-
vided this is not judged to be in contrast either with the gen- 4.2 Trials on board
eral characteristics of the machinery being tested or with
particular features of the shipboard installation. In such 4.2.1 Trials on board of machinery are detailed in Ch 1,
cases, the Surveyor is to be informed in advance and the Sec 15.
All other engines are to be designed and constructed the method of injection (direct or indirect injection)
according to sound marine practice, with the equipment the kind of fuel (liquid, gaseous or dual-fuel)
required in [2.3.4], and delivered with the relevant works
certificate (see NR216 Materials and Welding, Ch 1, Sec 1, the working cycle (4-stroke, 2-stroke)
[4.2.3]). the gas exchange (naturally aspirated or supercharged)
Engines intended for propulsion of lifeboats and compres- the maximum continuous power per cylinder at the cor-
sion ignition engines intended for propulsion of rescue responding speed and/or brake mean effective pressure
boats are to comply with the relevant Rule requirements. corresponding to the above-mentioned maximum con-
tinuous power
Additional requirements for control and safety systems for the method of pressure charging (pulsating system or
dual fuel engines are given in Ch 1, App 2. constant pressure system)
In addition to the requirements of this Section, those given the charging air cooling system (with or without inter-
in Ch 1, Sec 1 apply. cooler, number of stages, etc.)
cylinder arrangement (in-line or V-type).
1.2 Documentation to be submitted
1.3.2 Engine power
1.2.1 The Manufacturer is to submit to the Society the doc- The maximum continuous power is the maximum power at
uments listed in Tab 1 for engine type approval. ambient reference conditions [1.3.3] which the engine is
capable of delivering continuously, at nominal maximum
Plans listed under items 2 and 3 in Tab 1 are also to contain speed, in the period of time between two consecutive over-
details of the lubricating oil sump in order to demonstrate hauls.
compliance with Ch 1, Sec 1, [2.4].
Power, speed and the period of time between two consecu-
Where changes are made to an engine type for which the tive overhauls are to be stated by the Manufacturer and
documents listed in Tab 1 have already been examined or agreed by the Society.
approved, the engine Manufacturer is to resubmit to the The rated power is the maximum power at ambient refer-
Society for consideration and approval only those docu- ence conditions [1.3.3] which the engine is capable of
ments concerning the engine parts which have undergone delivering as set after works trials (fuel stop power) at the
substantial changes. maximum speed allowed by the governor.
If the engines are manufactured by a licensee, the licensee The rated power for engines driving electric generators is
is to submit, for each engine type, a list of all the drawings the nominal power, taken at the net of overload, at ambient
specified in Tab 1, indicating for each drawing the relevant reference conditions [1.3.3], which the engine is capable of
number and revision status from both licensor and licensee. delivering as set after the works trials [4.5].
1.3.3 Ambient reference conditions by the use of jigs and automatic machines designed to
The power of engines as per [1.1.1] a), b) and c) is to be machine parts to close tolerances for interchangeability,
referred to the following conditions: and which are to be verified by the manufacturer on a
regular basis.
barometric pressure = 0,1 MPa
1.3.6 Low-Speed Engines means diesel engines having a
relative humidity = 60% rated speed of less than 300 rpm.
ambient air temperature = 45C Medium-Speed Engines means diesel engines having a
sea water temperature (and temperature at inlet of sea rated speed of 300 rpm and above, but less than 1400 rpm.
water cooled charge air cooler) = 32C. High-Speed Engines means diesel engines having a rated
speed of 1400 rpm and above.
In the case of ships assigned with a navigation notation
other than unrestricted navigation, different temperatures 2 Design and construction
may be accepted by the Society.
The engine Manufacturer is not expected to provide the 2.1 Materials and welding
above ambient conditions at a test bed. The rating is to be
adjusted according to a recognised standard accepted by 2.1.1 Crankshaft materials
the Society. In general, crankshafts are to be of forged steel having a ten-
sile strength not less than 400 N/mm2 and not greater than
1.3.4 Same type of engines 1000 N/mm2.
Two diesel engines are considered to be of the same type The use of forged steels of higher tensile strength is subject
when they do not substantially differ in design and con- to special consideration by the Society in each case.
struction characteristics, such as those listed in the engine The Society, at its discretion and subject to special condi-
type definition as per [1.3.1], it being taken for granted that tions (such as restrictions in ship navigation), may accept
the documentation concerning the essential engine compo- crankshafts made of cast carbon steel, cast alloyed steel of
nents listed in [1.2] and associated materials employed has appropriate quality and manufactured by a suitable proce-
been submitted, examined and, where necessary, approved dure having a tensile strength as follows:
by the Society. a) between 400 N/mm2 and 560 /mm2 for cast carbon steel
1.3.5 Mass production b) between 400 N/mm2 and 700 N/mm2 for cast alloyed
steel.
Mass production applies to engines having a cylinder bore
The Society, at its discretion and subject to special condi-
not exceeding 300 mm and produced:
tions (such as restrictions in ship navigation), may also
in large quantity under quality control of material and accept crankshafts made of cast iron for mass produced
parts according to a programme specified by the engine engines of a nominal power not exceeding 110 kW with a
manufacturer and agreed by the Society significative in-service behaviour either in marine or indus-
try. The cast iron is to be of SG type (spheroidal graphite) b) Engines having a cylinder bore not exceeding 250 mm,
of appropriate quality and manufactured by a suitable pro- are to have at least one valve near each end, but over
cedure. eight crankthrows, an additional valve is to be fitted
near the middle of the engine. Engines having a cylinder
2.1.2 Welded frames and foundations bore exceeding 250 mm, but not exceeding 300 mm,
Steels used in the fabrication of welded frames and bed- are to have at least one valve in way of each alternate
plates are to comply with the requirements of NR216 Mate- crankthrow, with a minimum of two valves. Engines
rials and Welding. having a cylinder bore exceeding 300 mm are to have at
least one valve in way of each main crankthrow.
Welding is to be in accordance with the requirements of Ch
1, Sec 1, [2.2]. c) Additional relief valves are to be fitted on separate
spaces of the crankcase, such as gear or chain cases for
camshaft or similar drives, when the gross volume of
2.2 Crankshaft
such spaces is 0,6 m3 or above. Scavenge spaces in
open connection to the cylinders are to be fitted with
2.2.1 Check of the scantling
explosion relief valves.
The check of crankshaft strength is to be carried out in
accordance with Ch 1, App 1. d) The free area of each relief valve is not to be less than
45 cm2.
2.3 Crankcase e) The combined free area of the valves fitted on an engine
is not to be less than 115 cm2 per cubic metre of the
2.3.1 Strength crankcase gross volume. (See Note 1).
Crankcase construction and crankcase doors are to be of
sufficient strength to withstand anticipated crankcase pres- f) Crankcase explosion relief valves are to be provided
sures that may arise during a crankcase explosion taking with lightweight spring-loaded valve discs or other
into account the installation of explosion relief valves quick-acting and self closing devices to relieve a crank-
required by [2.3.4]. Crankcase doors are to be fastened suf- case of pressure in the event of an internal explosion
ficiently securely for them not be readily displaced by a and to prevent any inrush of air thereafter.
crankcase explosion. g) The valve discs in crankcase explosion relief valves are
to be made of ductile material capable of withstanding
2.3.2 Ventilation and drainage the shock of contact with stoppers at the full open posi-
Ventilation of crankcase, and any arrangement which could tion.
produce a flow of external air within the crankcase, is in
principle not permitted. h) Crankcase explosion relief valves are to be designed
and constructed to open quickly and to be fully open at
Vent pipes, where provided, are to be as small as practica- a pressure not greater than 0,02 MPa.
ble. If provision is made for the forced extraction of gases
from the crankcase (e.g. for detection of explosive mix- i) Crankcase explosion relief valves are to be provided
tures), the vacuum in the crankcase is not to exceed: with a flame arrester that permits flow for crankcase
pressure relief and prevents passage of flame following a
2,5 10-4 MPa crankcase explosion.
To avoid interconnection between crankcases and the pos-
j) Crankcase explosion relief valves are to be type tested in
sible spread of fire following an explosion, crankcase venti-
a configuration that represents the installation arrange-
lation pipes and oil drain pipes for each engine are to be
ments that will be used on an engine.
independent of any other engine.
The purpose of type testing crankcase explosion valves
2.3.3 Warning notice is:
A warning notice is to be fitted, preferably on a crankcase
to verify the effectiveness of the flame arrester
door on each side of the engine, or alternatively on the con-
trol stand. to verify that the valve closes after an explosion
This warning notice is to specify that whenever overheating to verify that the valve is gas/air tight after an explo-
is suspected in the crankcase, the crankcase doors or sight sion
holes are not to be opened until a reasonable time has to establish the level of overpressure protection pro-
elapsed after stopping the engine, sufficient to permit ade- vided by the valve.
quate cooling of the crankcase.
Where crankcase relief valves are provided with
2.3.4 Crankcase explosion relief valves arrangements for shielding emissions from the valve fol-
lowing an explosion, the valve is to be type tested to
a) Diesel engines of a cylinder diameter of 200 mm and
demonstrate that the shielding does not adversely affect
above or a crankcase gross volume of 0,6 m3 and above the operational effectiveness of the valve.
are to be provided with crankcase explosion relief
valves in accordance with the following requirements. Type testing procedure is to comply with Ch 1, App 4.
k) Crankcase explosion relief valves are to be provided Evidence of study to justify the selected location of
with a copy of the manufacturer's installation and main- sample points and sample extraction rate (if applica-
tenance manual that is pertinent to the size and type of ble) in consideration of the crankcase arrangements
valve being supplied for installation on a particular and geometry and the predicted crankcase atmos-
engine. phere where oil mist can accumulate
The manual is to contain the following information: The manufacturers maintenance and test manual
description of valve with details of function and Information relating to type or in-service testing of
design limits the engine with engine protection system test
copy of type test certification arrangements having approved types of oil mist
detection equipment
installation instructions
maintenance in service instructions to include test- c) A copy of the oil mist detection equipment maintenance
ing and renewal of any sealing arrangements and test manual required by b) is to be provided on
board ship
actions required after a crankcase explosion.
d) Oil mist detection and alarm information is to be capa-
l) A copy of the installation and maintenance manual
ble of being read from a safe location away from the
required in i) above is to be provided on board the unit.
engine
m) Valves are to be provided with suitable markings that
e) Each engine is to be provided with its own independent
include the following information:
oil mist detection arrangement and a dedicated alarm
name and address of manufacturer
f) Oil mist detection and alarm systems are to be capable
designation and size of being tested on the test bed and board under engine
month/year of manufacture at standstill and engine running at normal operating
conditions in accordance with test procedures that are
approved installation orientation.
acceptable to the classification society
Note 1: The total volume of the stationary parts within the crank-
case may be discounted in estimating the crankcase gross volume g) The oil mist detection arrangements are to provide an
(rotating and reciprocating components are to be included in the alarm indication in the event of a foreseeable functional
gross volume). failure in the equipment and installation arrangements
2.3.5 Oil mist detection h) The oil mist detection system is to provide an indication
that any lenses fitted in the equipment and used in
a) Oil mist detection arrangements (or engine bearing tem- determination of the oil mist level have been partially
perature monitors or equivalent devices) are required: obscured to a degree that will affect the reliability of the
for alarm and slow down purposes for low speed information and alarm indication
diesel engines of 2250 kW and above or having cyl- i) Where oil mist detection equipment includes the use of
inders of more than 300 mm bore programmable electronic systems, the arrangements are
for alarm and automatic shutoff purposes for to be in accordance with individual classification soci-
medium and high speed diesel engines of 2250 kW ety requirements for such systems
and above or having cylinders of more than 300 mm j) Plans of showing details and arrangements of oil mist
bore detection and alarm arrangements are to be submitted
Oil mist detection arrangements are to be of a type for approval in accordance withTab 1 under item 29
approved and tested in accordance with Ch 3, App 1
k) The equipment together with detectors is to be tested
and comply with b) to c) below. Engine bearing temper-
when installed on the test bed and on board ship to
ature monitors or equivalent devices used as safety
demonstrate that the detection and alarm system func-
devices have to be of a type approved by classification
tionally operates. The testing arrangements are to be to
societies for such purposes
the satisfaction of the classification society
Note 1: An equivalent device for high speed engines could be
interpreted as measures applied to high speed engines where l) Where sequential oil mist detection arrangements are
specific design features to preclude the risk of crankcase explo- provided the sampling frequency and time is to be as
sions are incorporated. short as reasonably practicable
b) The oil mist detection system and arrangements are to m) Where alternative methods are provided for the preven-
be installed in accordance with the engine designers tion of the build-up of oil mist that may lead to a poten-
and oil mist manufacturers instructions/recommenda- tially explosive condition within the crankcase details
tions. The following particulars are to be included in the are to be submitted for consideration of individual clas-
instructions: sification societies. The following information is to be
included in the details to be submitted for considera-
Schematic layout of engine oil mist detection and
tion:
alarm system showing location of engine crankcase
sample points and piping or cable arrangements Engine particulars type, power, speed, stroke, bore
together with pipe dimensions to detector and crankcase volume
Details of arrangements prevent the build up of a) All external high pressure fuel delivery lines between the
potentially explosive conditions within the crank- high pressure fuel pumps and fuel injectors are to be
case, e.g., bearing temperature monitoring, oil protected with a shielded piping system capable of con-
splash temperature, crankcase pressure monitoring, taining fuel from a high pressure line failure.
recirculation arrangements
A shielded pipe incorporates an outer pipe into which
Evidence to demonstrate that the arrangements are the high pressure fuel pipe is placed forming a perma-
effective in preventing the build up of potentially nent assembly.
explosive conditions together with details of in-serv-
ice experience The shielded piping system is to include a means for col-
lection of leakages and arrangements are to be provided
Operating instructions and the maintenance and test for an alarm to be given in the event of a fuel line failure.
instructions
If flexible hoses are used for shielding purposes, these
n) Where it is proposed to use the introduction of inert gas are to be approved by the Society.
into the crankcase to minimise a potential crankcase
explosion, details of the arrangements are to be submit- When in fuel oil return piping the pulsation of pressure
ted to the classification society for consideration. with peak to peak values exceeds 2 MPa, shielding of
this piping is also required as above.
2.4 Scavenge manifolds b) For ships classed for restricted navigation, the require-
ments under a) may be relaxed at the Societys discre-
2.4.1 Fire extinguishing tion.
For two-stroke crosshead type engines, scavenge spaces in
open connection (without valves) to the cylinders are to be 2.5.3 Lubricating oil system
connected to a fixed fire-extinguishing system, which is to Efficient filters are to be fitted in the lubricating oil system
be entirely independent of the fire-extinguishing system of when the oil is circulated under pressure.
the machinery space.
In such lubricating oil systems for propulsion machinery, fil-
2.4.2 Blowers ters are to be arranged so that an uninterrupted supply of fil-
Where a single two-stroke propulsion engine is equipped tered lubricating oil is ensured during cleaning operations
with an independently driven blower, alternative means to of the filter equipment, except when otherwise stated in Ch
drive the blower or an auxiliary blower are to be provided 1, Sec 10.
ready for use. Relief valves discharging back to the suction of the pumps
or other equivalent means are to be fitted on the delivery
2.4.3 Relief valves side of the pumps.
Scavenge spaces in open connection to the cylinders are to
be fitted with explosion relief valves in accordance with The relief valves may be omitted provided that the filters
[2.3.4]. can withstand the maximum pressure that the pump may
develop.
Unless otherwise stated in Ch 1, Sec 10, propulsion engines b) When two-stroke propulsion engines are supercharged
are to be equipped with external connections for standby by exhaust gas turbochargers which operate on the
pumps for: impulse system, provision is to be made to prevent bro-
ken piston rings entering turbocharger casings and caus-
fuel oil supply
ing damage to blades and nozzle rings.
lubricating oil and cooling water circulation.
Figure 1 : Limiting curves for loading 4-stroke diesel engines step by step from no load to rated power
as a function of the brake mean effective pressure
100
90
80
Load increase referred to rated power [%]
70
60
Limiting curve for
3rd load step
50
40
Limiting curve for
2nd load step
30
20
Limiting curve for
1st load step
10
0
0.6 0.8 1,0 1,2 1,4 1,6 1,8 2,0 2,2 2,4
Mep at rated power of diesel engine [MPa]
This also applies to generators to be operated in parallel c) Electronic governors for auxiliary engines driving elec-
and where the power is to be transferred from one gen- tric generators
erator to another, in the event that any one generator is In the event of a fault in the electronic governor system
to be switched off. the fuel admission is to be set to zero.
e) When the rated power is suddenly thrown off, steady Alarms are to be fitted to indicate faults in the governor
state conditions should be achieved in not more than system.
5 s.
The acceptance of electronic governors fitted on
f) Emergency generator sets must satisfy the governor con- engines driving emergency generators will be consid-
ditions as per items a) and b) when: ered by the Society on a case by case basis.
their total consumer load is applied suddenly, or
their total consumer load is applied in steps, subject 2.7.8 Summary tables
to the maximum step load is declared and demon- Diesel engines installed on ships without automation nota-
strated. tions are to be equipped with monitoring equipment as
detailed in Tab 2 or Tab 3 for main propulsion, in Tab 4 for
g) For alternating current generating sets operating in par-
auxiliary services and in Tab 5 for emergency respectively.
allel, the governing characteristics of the prime movers
are to be such that, within the limits of 20% and 100% For ships classed for restricted navigation, the acceptance of
total load, the load on any generating set will not nor- a reduction in the monitoring equipment required in Tab 2,
mally differ from its proportionate share of the total load Tab 3 and Tab 4 may be considered.
by more than 15% of the rated power in kW of the larg- The alarms are to be visual and audible.
est machine or 25% of the rated power in kW of the
individual machine in question, whichever is the lesser. The indicators are to be fitted at a normally attended posi-
tion (on the engine or at the local control station).
For alternating current generating sets intended to oper-
ate in parallel, facilities are to be provided to adjust the
governor sufficiently finely to permit an adjustment of 3 Arrangement and installation
load not exceeding 5% of the rated load at normal fre-
quency. 3.1 Starting arrangements
Note 1: Steady state conditions are those at which the envelope of
speed variation does not exceed 1% of the declared speed at the 3.1.1 Mechanical air starting
new power.
a) Air starting the main and auxiliary engines is to be
2.7.6 Overspeed protective devices of auxiliary arranged in compliancez with Ch 1, Sec 10, [17.3.1].
engines driving electric generators b) The total capacity of air compressors and air receivers is
In addition to the speed governor, auxiliary engines of rated to be in compliance with Ch 1, Sec 10, [17.3.2] and Ch
power equal to or greater than 220 kW driving electric gen- 1, Sec 10, [17.3.3].
erators are to be fitted with a separate overspeed protective c) The main starting air arrangements for main propulsion
device, with a means for manual tripping, adjusted so as to or auxiliary diesel engines are to be adequately pro-
prevent the rated speed from being exceeded by more than tected against the effects of backfiring and internal
15%. explosion in the starting air pipes. To this end, the fol-
This device is to automatically shut down the engine. lowing safety devices are to be fitted:
An isolating non-return valve, or equivalent, at the
2.7.7 Use of electronic governors
starting air supply connection to each engine.
a) Type approval
A bursting disc or flame arrester:
Electronic governors and their actuators are to be type
approved by the Society. - in way of the starting valve of each cylinder, for
direct reversing engines having a main starting
b) Electronic governors for main propulsion engines air manifold
If an electronic governor is fitted to ensure continuous - at least at the supply inlet to the starting air man-
speed control or resumption of control after a fault, an ifold, for non-reversing engines.
additional separate governor is to be provided unless
the engine has a manually operated fuel admission con- The bursting disc or flame arrester above may be
trol system suitable for its control. omitted for engines having a bore not exceeding
230 mm.
A fault in the governor system is not to lead to sudden
major changes in propulsion power or direction of pro- Other protective devices will be specially considered by
peller rotation. the Society.
Alarms are to be fitted to indicate faults in the governor The requirements of this item c) do not apply to engines
system. started by pneumatic motors.
The acceptance of electronic governors not in compli- d) Compressed air receivers are to comply with the
ance with the above requirements will be considered by requirements of Ch 1, Sec 3. Compressed air piping and
the Society on a case by case basis, when fitted on ships associated air compressors are to comply with the
with two or more main propulsion engines. requirements of Ch 1, Sec 10.
b) Electrical starting arrangements for auxiliary engines are The source of stored energy shall be protected to pre-
to have two separate storage batteries or may be sup- clude critical depletion by the automatic starting system,
plied by two separate circuits from main engine storage unless a second independent means of starting is pro-
batteries when these are provided. In the case of a single vided. In addition, a second source of energy shall be
auxiliary engine, one battery is acceptable. The com- provided for an additional three starts within 30 min-
bined capacity of the batteries is to be sufficient for at utes, unless manual starting can be demonstrated to be
least three starts for each engine. effective.
c) The starting batteries are only to be used for starting and c) The stored energy is to be maintained at all times, as fol-
for the engines alarm and monitoring. Provision is to be lows:
made to maintain the stored energy at all times. electrical and hydraulic starting systems shall be
maintained from the emergency switchboard
d) Each charging device is to have at least sufficient rating
for recharging the required capacity of batteries within 6 compressed air starting systems shall be provided in
hours. accordance with Ch 1, Sec 10, [17.3.4].
d) Where automatic starting is not required, manual start- 4.1.2 At the request of the Manufacturer, an increase in
ing, such as manual cranking, inertia starters, manually power and/or mean effective pressure up to a maximum of
charged hydraulic accumulators, or powder charge car- 10% may be accepted by the Society for an engine previ-
tridges, is permissible where this can be demonstrated ously subjected to a type test without any further such test
as being effective. being required, provided the engine reliability has been
e) When manual starting is not practicable, the require- proved successfully by the service experience of a sufficient
ments of b) and c) are to be complied with, except that number of engines of the same type.
starting may be manually initiated. For the purpose of the acceptance of the above perform-
ance increase, the Manufacturer is in any case to submit for
3.2 Turning gear examination and, where necessary, approval, the documen-
tation listed in [1.2] relevant to any components requiring
3.2.1 Each engine is to be provided with hand-operated modification in order to achieve the increased performance.
turning gear; where deemed necessary, the turning gear is to
be both hand and mechanically-operated. 4.1.3 If an electronically controlled diesel engine has been
type tested as a conventional engine the Society may waive
The turning gear engagement is to inhibit starting opera-
tests required by this article provided the results of the indi-
tions.
vidual tests would be similar.
3.3 Trays
4.2 Type tests of non-mass produced
3.3.1 Trays fitted with means of drainage are to be provided engines
in way of the lower part of the crankcase and, in general, in
way of the parts of the engine, where oil is likely to spill in 4.2.1 General
order to collect the fuel oil or lubricating oil dripping from Upon finalization of the engine design for production of
the engine. every new engine type intended for the installation on
board ships, one engine is to be presented for type testing as
3.4 Exhaust gas system required below.
A type test carried out for a particular type of engine at any
3.4.1 In addition to the requirements given in Ch 1, Sec 10, place at any manufacturer will be accepted for all engines
the exhaust system is to be efficiently cooled or insulated in of the same type built by licensees and licensors.
such a way that the surface temperature does not exceed
Engines which are subjected to type testing are to be tested
220C (see also Ch 1, Sec 1, [3.7]).
in accordance to the scope as specified below.
The engine Manufacturer is to compile all results and meas- along the nominal (theoretical) propeller curve
urements for the engine tested during the type test in a type and at constant speed, for propulsion engines
test report, which is to be submitted to the Society.
at constant speed, for engines intended for gen-
erating sets.
4.2.2 Stage A - Internal tests (function tests and
collection of operating data) 2) The limit points of the permissible operating range.
During the internal tests the engine is to be operated at the These limit points are to be defined by the engine
load points considered important by the engine Manufac- Manufacturer.
turer and the relevant operating values are to be recorded
The maximum continuous power P is defined in
(see item a)).
[1.3.2].
The load points may be selected according to the range of b) Tests under emergency operating conditions
application (see Fig 2).
For turbocharged engines, the achievable continuous
If an engine can be satisfactorily operated at all load points output is to be determined for a situation when one tur-
without using mechanically driven cylinder lubricators, this bocharger is damaged, i.e.:
is to be verified.
for engines with one turbocharger, when the rotor is
For engines which may operate of heavy fuel oil, the suita- blocked or removed
bility for this will have to be proved in an appropriate form, for engines with two or more turbochargers, when
at Manufacturers (Licensor or Licensee) testbed in general, the damaged turbocharger is shut off.
but, where not possible, latest on board for the first engine
to be put into service. 4.2.3 Stage B - Type approval tests in the presence
of the Surveyor
a) Functional tests under normal operating conditions
During the type test, the tests listed below are to be carried
Functional tests under normal operating conditions out in the presence of the Surveyor and the results are to be
include: recorded in a report signed by both the engine Manufac-
turer and the Surveyor.
1) The load points 25%, 50%, 75%, 100% and 110%
of the maximum continuous power for which type Any departures from this programme are to be agreed upon
approval is requested, to be carried out: by the engine Manufacturer and the Society.
110 100
3 3a
Maximum continuous power
100 3 2
1 90
4
90
% 80
00 1 Range of continuous operation
e = 1 00%
80 rq
u =15
To .p.e
b.m
6
9 70 2 Range of intermittent operation
Power (%)
70
3 Range of short-time
2 overload operation
60
60
1 4 Nominal propeller curve
7 50
50
10
40 40
30
30
8 11
4
Rotational Speed (%) 100 103,2
The operating time per load point depends on the For engines intended to be used for emergency services,
engine characteristics (achievement of steady-state con- supplementary tests may be required to the satisfaction
dition) and the time for collection of the operating val- of the Society. In particular, for engines intended to
ues. drive emergency generating sets, additional tests and/or
documents may be required to prove that the engine is
Normally, an operating time of 0,5 hour per load point capable of being readily started at a temperature of 0C.
can be assumed.
At the maximum continuous power as per the following 4.2.4 Evaluation of test results
item 1) an operating time of two hours is required. Two The results of the tests and checks required by [4.2.3] will
sets of readings are to be taken at a minimum interval of be evaluated by the attending Surveyor. Normally the main
one hour. operating data to be recorded during the tests are those
1) Test at maximum continuous power P: i.e. 100% listed in [4.3.4].
output at 100% torque and 100% speed, corre-
In particular, the maximum combustion pressure measured
sponding to load point 1 in the diagram in Fig 2.
with the engine running at the maximum continuous power
2) Test at 100% power at maximum permissible speed, P is not to exceed the value taken for the purpose of check-
corresponding to load point 2 in the diagram in Fig 2. ing the scantlings of the engine crankshaft, according to the
applicable requirements of Ch 1, App 1.
3) Test at maximum permissible torque (normally
110% of nominal torque T) at 100% speed, corre- The values of temperatures and pressures of media, such as
sponding to load point 3 in the diagram in Fig 2; or cooling water, lubricating oil, charge air, exhaust gases, etc.,
test at maximum permissible power (normally 110% are to be within limits which, in the opinion of the Surveyor,
of P) and speed according to the nominal propeller are appropriate for the characteristics of the engine tested.
curve, corresponding to load point 3a in the dia-
gram in Fig 2. 4.2.5 Stage C - Inspection of main engine
components
4) Test at minimum permissible speed at 100% of
torque T, corresponding to load point 4 in the dia- Immediately after the test run as per [4.2.3], the compo-
gram in Fig 2. nents of one cylinder for in-line engines, and two cylinders
for V-type engines, are to be presented for inspection to the
5) Test at minimum permissible speed at 90% of torque
Surveyor.
T, corresponding to load point 5 in the diagram in
Fig 2. The following main engine components are to be inspected:
6) Tests at part loads, e.g. 75%, 50%, 25% of maxi- piston removed and dismantled
mum continuous power P and speed according to crosshead bearing, dismantled
the nominal propeller curve, corresponding to load
points 6, 7 and 8 in the diagram in Fig 2; and tests at crank bearing and main bearing, dismantled
the above part loads and at speed n with constant cylinder liner in the installed condition
governor setting, corresponding to load points 9, 10 cylinder head and valves, disassembled
and 11 in the diagram in Fig 2.
control gear, camshaft and crankcase with opened covers.
b) Tests under emergency operating conditions
Where deemed necessary by the Surveyor, further disman-
These are tests at maximum achievable power when tling of the engine may be required.
operating along the nominal propeller curve and when
operating with constant governor setting for speed n, in
emergency operating conditions as stated in [4.2.2] b). 4.3 Type tests of mass produced engines
c) Functional tests 4.3.1 General
1) Lowest engine speed according to nominal propeller Mass produced engines as defined in [1.3.5] are to be sub-
curve jected to type tests in the presence of the Surveyor in
2) Starting tests, for non-reversible engines and/or start- accordance with requirements [4.3.2] to [4.3.5].
ing and reversing tests, for reversible engines Omission or simplification of the type tests may be consid-
3) Governor test ered for engines of well known type.
4) Testing the safety system, particularly for overspeed The selection of the engine to be tested from the production
and low lub. oil pressure line is to be agreed upon with the Surveyor.
4.3.2 Type test In the case of engines which are to be type approved for dif-
The programme of the type test is to be in general as speci- ferent purposes and performances, the programme and
fied below, P being the maximum continuous power and n duration of the type test will be decided by the Society in
the corresponding speed. The maximum continuous power each case to cover the whole range of engine performances
is that stated by the engine Manufacturer and accepted by for which approval is requested, taking into account the
the Society, as defined in [4.2.2]. most severe values.
a) 80 hours at power P and speed n 4.3.4 During the type test, at least the following particulars
are to be recorded:
b) 8 hours at overload power (110% of power P)
a) ambient air temperature, pressure and atmospheric
c) 10 hours at partial loads (25%, 50%, 75% and 90% of humidity in the test room
power P)
b) cooling raw water temperature at the inlet of heat
d) 2 hours at intermittent loads exchangers
e) starting tests c) characteristics of fuel and lubricating oil used during the
test
f) reverse running for direct reversing engines
d) engine speed
g) testing of speed governor, overspeed device and lubri- e) brake power
cating oil system failure alarm device
f) brake torque
h) testing of the engine with one turbocharger out of g) maximum combustion pressure
action, when applicable
h) indicated pressure diagrams, where practicable
i) testing of the minimum speed along the nominal (theo-
i) exhaust smoke (with a smoke meter deemed suitable by
retical) propeller curve, for main propulsion engines
the Surveyor)
driving fixed pitch propellers, and of the minimum
speed with no brake load, for main propulsion engines j) lubricating oil pressure and temperature
driving controllable pitch propellers or for auxiliary k) cooling water pressure and temperature
engines.
l) exhaust gas temperature in the exhaust manifold and,
The tests at the above-mentioned outputs are to be com- where facilities are available, from each cylinder
bined together in working cycles which are to be repeated
in succession for the entire duration within the limits indi- m) minimum starting air pressure necessary to start the
cated. engine in cold condition.
In addition to the above, for supercharged engines the fol-
In particular, the overload test, to be carried out at the end
lowing data are also to be measured and recorded:
of each cycle, is to be of one hours duration and is to be
carried out alternately: turbocharger speed
at 110% of the power P and 103% of the speed n air temperature and pressure before and after turbo-
charger and charge air coolers
at 110% of the power P and 100% of the speed n.
exhaust gas temperatures and pressures before and after
The partial load tests specified in c) are to be carried out: turbochargers and cooling water temperature at the inlet
along the nominal (theoretical) propeller curve and at of charge air coolers.
constant speed, for propulsion engines
4.3.5 Inspection of main engine components and
at constant speed, for engines intended for generating
sets. evaluation of test results
The provisions of [4.2.4] and [4.2.5] are to be complied
For engines intended to be used for emergency services, with, as far as applicable.
supplementary tests may be required, to the satisfaction of
the Society. In particular, for engines intended to drive
emergency generating sets, additional tests and/or docu-
4.4 Material and non-destructive tests
ments may be required to prove that the engine is capable
4.4.1 Material tests
of being readily started at a temperature of 0C, as required
in [3.1.3]. Engine components are to be tested in accordance with Tab
6 and in compliance with the requirements of NR216 Mate-
In the case of prototype engines, the duration and pro- rials and Welding.
gramme of the type test will be specially considered by the
Magnetic particle or liquid penetrant tests are required for
Society.
the parts listed in Tab 6 and are to be effected by the Manu-
4.3.3 In cases of engines for which the Manufacturer sub- facturer in positions agreed upon by the Surveyor, where
mits documentary evidence proving successful service Manufacturers experience shows defects are most likely to
experience or results of previous bench tests, the Society, at occur.
its discretion, may allow a type test to be carried out in the The magnetic particle test of tie rods/stay bolts is to be car-
presence of the Surveyor according to a programme to be ried out at each end, for a portion which is at least twice the
agreed upon in each instance. length of the thread.
For important structural parts of engines, in addition to the are to be subjected to hydrostatic tests at 1,5 times the max-
above-mentioned non-destructive tests, examination of imum working pressure, but not less than 0,4 MPa.
welded seams by approved methods of inspection may be
required.
4.5 Workshop inspections and testing
Where there are grounds to doubt the soundness of any
engine component, non-destructive tests using approved 4.5.1 General
detecting methods may be required.
In addition to the type test, diesel engines are to be sub-
Engines of a cylinder diameter not exceeding 300 mm may jected to works trials, normally witnessed by the Surveyor
be tested according to an alternative survey scheme. except where an Alternative Inspection Scheme has been
granted or where otherwise decided by the Society on a
4.4.2 Hydrostatic tests case by case basis.
Parts of engines under pressure are to be hydrostatically For all stages at which the engine is to be tested, the rele-
tested at the test pressure specified for each part in Tab 7. vant operating values are to be measured and recorded by
The following parts of auxiliaries which are necessary for the engine Manufacturer.
operation of engines as per [1.1.1] a), b) and c): In each case all measurements conducted at the various
cylinders, cylinder covers, coolers and receivers of inde- load points are to be carried out at steady operating condi-
pendent air compressors tions.
water, oil and air coolers (tube bundles or coils, shells The readings for 100% of the rated power P at the corre-
and heads) not fitted on the engine and filters sponding speed n are to be taken twice at an interval of at
independently driven lubricating oil, fuel oil and water least 30 minutes.
pumps At the discretion of the Surveyor, the programme of trials
pressure pipes (water, lubricating oil, fuel oil, and com- given in [4.5.2], [4.5.3] or [4.5.4] may be expanded
pressed air pipes), valves and other fittings depending on the engine application.
4.5.2 Main propulsion engines driving propellers 4.5.3 Engines driving electric generators used for
main propulsion purposes
Main propulsion engines are to be subjected to trials to be
Engines driving electric generators are to be subjected to tri-
performed as follows:
als to be performed with a constant governor setting, as fol-
a) at least 60 min, after having reached steady conditions, lows:
at rated power P and rated speed n a) at least 50 min, after having reached steady conditions,
at 100% of rated power P and rated speed n
b) 30 min, after having reached steady conditions, at
110% of rated power P and at a speed n equal to 1,032 b) 30 min, after having reached steady conditions, at
of rated speed 110% of rated power and rated speed
Note 1: After running on the test bed, the fuel delivery system of
Note 1: After running on the test bed, the fuel delivery system is to diesel engines driving electric generators is to be adjusted such
be so adjusted that the engine cannot deliver more than 100% that overload (110%) power can be produced but not
of the rated power at the corresponding speed (overload power exceeded in service after installation on board, so that the gov-
cannot be obtained in service). erning characteristics, including the activation of generator
protective devices, can be maintained at all times.
c) tests at 90%, 75%, 50% and 25% of rated power P, in
accordance with the nominal propeller curve c) 75%, 50% and 25% of rated power P
d) idle run
d) starting and reversing maneuvres
e) starting tests
e) testing of governor and independent overspeed protec- f) testing of the speed governor ( [2.7.5]) and independent
tive device overspeed protective device
f) shutdown devices. g) shutdown devices.
4.5.4 Engines driving auxiliary machinery The Society reserves the right to consider the test carried out
Engines driving auxiliary machinery are to be subjected to on one engine type valid also for engines having a different
the tests stated in [4.5.2] or [4.5.3] for variable speed and cylinder arrangement, following examination of suitable,
constant speed drives, respectively. detailed documentation submitted by the Manufacturer and
Note 1: After running on the test bed, the fuel delivery system of including bench test results.
diesel engines driving electric generators is to be adjusted such that
overload (110%) power can be produced but not exceeded in serv- 4.6.2 Testing certification
ice after installation on board, so that the governing characteristics, a) Mass produced engines
including the activation of generator protective devices, can be ful-
Works certificates (W) (see NR216 Materials and Weld-
filled at all times.
ing, Ch 1, Sec 1, [4.2.3]) are required for components
4.5.5 Inspection of engine components and tests indicated in Tab 6 and Tab 7. Societys certifi-
Random checks of components to be presented for inspec- cate (C or CA) (see NR 216 Ch1, Sec1, [4.2]) is required
tion after the works trials are left to the discretion of each for works trials as per [4.5].
Society. b) Other engines
Societys certificates (C) (see NR216 Materials and
4.5.6 Parameters to be measured
Welding, Ch 1, Sec 1, [4.2.1]) are required for material
The data to be measured and recorded, when testing the tests of components in Tab 6 and for works trials as per
engine at various load points, are to include all necessary [4.5].
parameters for engine operation. The crankshaft deflection
is to be verified when this check is required by the Manu- Works certificates (W) (see NR216 Materials and Weld-
facturer during the operating life of the engine. ing, Ch 1, Sec 1, [4.2.3]) are required for non-destruc-
tive and hydrostatic tests of components in Tab 6 and
4.5.7 Testing report Tab 7.
In the testing report for each engine the results of the tests In both cases a) and b), the Manufacturer is to supply:
carried out are to be compiled and the reference number a) the following information:
and date of issue of the Type Approval Certificate (see
engine type
[4.6]), relevant to the engine type, are always to be stated;
the testing report is to be issued by the Manufacturer and rated power
enclosed with the testing certificate as per [4.6]. rated speed
driven equipment
4.6 Certification operating conditions
4.6.1 Type Approval Certificate and its validity list of auxiliaries fitted on the engine
After the satisfactory outcome of the type tests and inspec- b) a statement certifying that the engine is in compliance
tions specified in [4.2] or [4.3], the Society will issue to the with that type tested. The reference number and date of
engine manufacturer a "Type Approval Certificate" valid for the Type Approval Certificate are also to be indicated in
all engines of the same type. the statement.
Pressure equipment means pressure vessels, piping ( Ch c) equipment comprising casings or machinery where the
1, Sec 10), safety accessories and pressure accessories. dimensioning, choice of material and manufacturing
rules are based primarily on requirements for sufficient
1.1.2 Overpressure risk strength, rigidity and stability to meet the static and
dynamic operational effects or other operational charac-
Where main or auxiliary boilers and other pressure vessels
teristics and for which pressure is not a significant
or any parts thereof may be subject to dangerous overpres-
design factor. Such equipment may include:
sure, means are to be provided where practicable to protect
against such excessive pressure. engines including turbines and internal combustion
engines
1.1.3 Propulsion capability steam engines, gas/steam turbines, turbo-generators,
Means are to be provided whereby normal operation of compressors, pumps and actuating devices
main boilers can be sustained or restored even through one
d) small pressure vessels included in self-contained
of the essential auxiliaries become inoperative. Special con-
domestic equipment.
sideration is to be given to the malfunctioning of:
the source of steam supply
1.3 Definitions
the boiler feed water systems
the fuel oil supply system for boilers 1.3.1 Pressure vessel
the mechanical air supply for boilers. Pressure vessel means a housing designed and built to
contain fluids under pressure including its direct attach-
However the Society, having regard to overall safety consid- ments up to the coupling point connecting it to other equip-
erations, may accept a partial reduction in propulsion capa- ment. A vessel may be composed of more than one
bility from normal operation. chamber.
c) Spheroidal cast iron is not to be used for parts having a by the Society as per [1.5], the material specifications are to
design temperature T exceeding 350C. be in compliance with the requirements of the standard used.
d) Bronze is not to be used for parts having design temper-
ature T exceeding 220C for normal bronzes and 260C 2.3 Permissible stresses
for bronzes suitable for high temperatures. Copper and
aluminium brass are not to be used for fittings with
design temperature T above 200C and copper-nickel 2.3.1 The permissible stresses K, in N/mm2, for steels, to be
fittings with design temperature T exceeding 300C. used in the formulae of this Article, may be determined
from Tab 7, Tab 8, Tab 9 and Tab 10, where Rm is the ulti-
2.2.5 Alternative materials mate strength of the material, in N/mm2. For intermediate
In the case of boilers or pressure vessels constructed in values of the temperature, the value of K is to be obtained
accordance with one of the standards considered acceptable by linear interpolation.
Table 7 : Permissible stresses K for carbon steels intended for boilers and thermal oil heaters
Carbon steel T (C) 50 100 150 200 250 300 350 400
Rm = 360 N/mm 2 t 15 mm 133 109 107 105 94 77 73 72
Grade HA 15 mm < t 40 mm 128 106 105 101 90 77 73 72
40 mm < t 60 mm 122 101 99 95 88 77 73 72
Rm = 360 N/mm 2 t 15 mm 133 127 116 103 79 79 72 69
Grades HB, HD 15 mm < t 40 mm 133 122 114 102 79 79 72 69
40 mm < t 60 mm 133 112 107 99 79 79 72 69
Rm = 410 N/mm2 t 15 mm 152 132 130 126 112 94 89 86
Grade HA 15 mm < t 40 mm 147 131 124 119 107 94 89 86
40 mm < t 60 mm 141 120 117 113 105 94 89 86
Rm = 410 N/mm2 t 15 mm 152 147 135 121 107 95 88 84
Grades HB, HD 15 mm < t 40 mm 152 142 133 120 107 95 88 84
40 mm < t 60 mm 152 134 127 117 107 95 88 84
Rm = 460 N/mm 2 t 15 mm 170 164 154 139 124 111 104 99
Grades HB, HD 15 mm < t 40 mm 169 162 151 137 124 111 104 99
40 mm < t 60 mm 162 157 147 136 124 111 104 99
Rm = 510 N/mm 2
t 60 mm 170 170 169 159 147 134 125 112
Grades HB, HD
Table 8 : Permissible stresses K for carbon steels intended for other pressure vessels
Carbon steel T (C) 50 100 150 200 250 300 350 400
Rm = 360 N/mm2 t 15 mm 133 117 115 112 100 83 78 77
Grade HA 15 mm < t 40 mm 133 114 113 108 96 83 78 77
40 mm < t 60 mm 130 108 105 101 94 83 78 77
Rm = 360 N/mm2 t 15 mm 133 133 123 110 97 85 77 73
Grades HB, HD 15 mm < t 40 mm 133 131 122 109 97 85 77 73
40 mm < t 60 mm 133 119 115 106 97 85 77 73
Rm = 410 N/mm2 t 15 mm 152 141 139 134 120 100 95 92
Grade HA 15 mm < t 40 mm 152 134 132 127 114 100 95 92
40 mm < t 60 mm 150 128 121 112 112 100 95 92
Rm = 410 N/mm 2 t 15 mm 152 152 144 129 114 101 94 89
Grades HB, HD 15 mm < t 40 mm 152 152 142 128 114 101 94 89
40 mm < t 60 mm 152 143 139 125 114 101 94 89
Rm = 460 N/mm2 t 15 mm 170 170 165 149 132 118 111 105
Grades HB, HD 15 mm < t 40 mm 170 170 161 147 132 118 111 105
40 mm < t 60 mm 170 167 157 145 132 118 111 105
Rm = 510 N/mm2
t 60 mm 189 189 180 170 157 143 133 120
Grades HB, HD
Table 9 : Permissible stresses K for alloy steels intended for boilers and thermal oil heaters
Alloy steel T(C) 50 100 150 200 250 300 350 400 450 475 500 525 550 575 600
0,3Mo t 60 mm 159 153 143 134 125 106 100 94 91 89 87 36
1Cr 0,5Mo t 60 mm 167 167 157 144 137 128 119 112 106 104 103 55 31 19
2,25Cr 1Mo (1) t 60 mm 170 167 157 147 144 137 131 125 119 115 112 61 41 30 22
2,25Cr 1Mo (2) t 60 mm 170 167 164 161 159 147 141 130 128 125 122 61 41 30 22
(1) Normalised and tempered
(2) Normalised and tempered or quenched and tempered
Table 10 : Permissible stresses K for alloy steels intended for other pressure vessels
Alloy steel T(C) 50 100 150 200 250 300 350 400 450 475 500 525 550 575 600
0,3Mo t 60 mm 159 159 153 143 133 113 107 100 97 95 93 38
1Cr 0,5Mo t 60 mm 167 167 167 154 146 137 127 119 113 111 110 59 33 20
2,25Cr 1Mo (1) t 60 mm 183 174 167 157 154 146 140 133 127 123 119 65 44 32 23
2,25Cr 1Mo (2) t 60 mm 174 174 174 172 170 157 150 139 137 133 130 65 44 32 23
(1) Normalised and tempered
(2) Normalised and tempered or quenched and tempered
in special cases, the Society reserves the right to a) When the ratio external diameter/inside diameter is
equal to or less than 1,5, the minimum thickness of
apply values of permissible stress K lower than those
cylindrical shells is given by the following formula:
specified above, in particular for lifting appliance
devices and steering gear devices pD
t = -------------------------
( 2K p )e
in the case of boilers or other steam generators, the
where:
permissible stress K is not to exceed 170 N/mm2
p : Design pressure, in MPa
for materials other than those listed above the per-
D : Inside diameter of vessel, in mm
missible stress is to be agreed with the Society on a
case by case basis. K : Permissible stress, in N/mm2, obtained as
specified in [2.3]
e : Efficiency of welded joint, the value of
2.4 Cylindrical, spherical and conical shells
which is given in [2.4.2].
with circular cross-sections subject to
internal pressure b) The minimum thickness of shells having ratio external
diameter/inside diameter exceeding 1,5 is subject of
special consideration.
2.4.1 Cylindrical shell thickness
2.4.4 Spherical shells
a) The minimum thickness of cylindrical, spherical and
conical shells with circular cross-sections is not to be a) When the ratio external diameter/inside diameter is
less than the value t, in mm, calculated by one of the equal to or less than 1,5, the minimum thickness of
following formulae, as appropriate. Cylindrical tube spherical shells is given by the following formula:
plates pierced by a great number of tube holes are to pD
t = -------------------------
have thickness calculated by the applicable formulae in ( 4K p )e
[2.4.3], [2.4.4], [2.4.5] and [2.9.2].
For the meaning of the symbols, see [2.4.3].
b) The thicknesses obtained by the formulae in [2.4.3], b) The minimum thickness of shells having ratio external
[2.4.4] and [2.4.5] are net thicknesses, as they do not diameter/inside diameter exceeding 1,5 is subject of
include any corrosion allowance. The thickness special consideration.
obtained by the above formulae is to be increased by
0,75 mm. See also [2.4.7]. 2.4.5 Conical shells
a) The following formula applies to conical shells of thick-
Table 11 : Efficiency of unpierced shells ness not exceeding 1/6 of the external diameter in way
of the large end of the cone:
Case e pD
t = -------------------------------------------
Seamless shells 1,00 ( 2K p )e cos
Shells of class 1 vessels (1) 1,00 For the meaning of the symbols, see [2.4.3].
Shells of class 2 vessels (with partial radiographic 0,85 D is measured in way of the large end of the cone and
examination of butt-joints) is the angle of slope of the conical section of the shell to
the pressure vessel axis (see Fig 1). When exceeds
Shells of class 2 vessels with actual thickness 0,75
15 mm (without radiographic examination of
75, the shell thickness is to be taken as required for flat
butt-joints) heads, see [2.7].
(1) In special cases the Society reserves the right to take a b) The minimum thickness of shells having thickness
factor e < 1, depending on the welding procedure exceeding 1/6 of the external diameter in way of the
adopted for the welded joint. large end of the cone is subject of special consideration.
c) Conical shells may be made of several ring sections of
2.4.2 Efficiency decreasing thickness. The minimum thickness of each
section is to be obtained by the formula in a) using for D
a) The values of efficiency e to be used in the formulae in the maximum diameter of the considered section.
[2.4.3], [2.4.4] and [2.4.5] are indicated in Tab 11.
d) In general, the junction with a sharp angle between the
b) The manufacturer may propose a factor e lower than conical shell and the cylindrical or other conical shell,
those indicated in Tab 11 where consistent with the fac- having different angle of slope, is not allowed if the
tor used in the formulae of [2.4.3], [2.4.4] and [2.4.5] angle of the generating line of the shells to be assem-
and with the provisions of specific requirements accord- bled exceeds 30.
ing to class as per [4.9], [4.10] or [4.11]. The proposed e) The shell thickness in way of knuckles is subject of spe-
efficiency factor is to be agreed by the Society. cial consideration by the Society.
t
t
H : External depth of head, in mm, measured
CONE / CYLINDER
SOLID KNUCKLE
CONE / CYLINDER from the start of curvature at the base.
WELDED KNUCKLE
b) Torispherical heads:
CONE / CONE CONE / CONE
WELDED KNUCKLE
RIN D
SOLID KNUCKLE
rIN 0,1 D
D D
rIN 3 t
radiused
H 0,18 D
t t where:
RIN : Internal radius of the spherical part, in mm
rIN : Internal knuckle radius, in mm
H : External depth of head calculated by the fol-
lowing formula (see Fig 2 (b)):
2.4.6 Minimum thickness of shells H = RE [(RE 0,5 D) (RE + 0,5 D 2 rE)]0,5
Irrespective of the value calculated by the formulae in where:
[2.4.3], [2.4.4] or [2.4.5], the thickness t of shells is not to RE : External radius of the spherical
be less than one of the following values, as applicable: part, in mm
for pressure vessels: t = 3 + D/1500 mm rE : External knuckle radius, in mm.
for unpierced plates of boilers: t = 6,0 mm
for boiler cylindrical tube plates: t = 9,5 mm. 2.5.3 Required thickness of solid dished heads
a) The minimum thickness of solid (not pierced) hemi-
No corrosion allowance needs to be added to the above
spherical, torispherical, or ellipsoidal unstayed dished
values.
heads, subject to pressure on the concave (internal)
2.4.7 Corrosion allowance side, is to be not less than the value t, in mm, calculated
The Society reserves the right to increase the corrosion by the following formula:
allowance value in the case of vessels exposed to particular pDC
t = ------------
accelerating corrosion conditions. The Society may also 2Ke
consider the reduction of this factor where particular meas- where:
ures are taken to effectively reduce the corrosion rate of the
vessel. C : Shape factor, obtained from the graph in Fig
3, as a function of H/D and t/D.
2.5 Dished heads subject to pressure on the For other symbols, see [2.4.3].
concave (internal) side b) The thickness obtained by the formula in item a) is net
thickness, as it does not include any corrosion allow-
2.5.1 Dished head for boiler headers ance. The thickness obtained by the above formula is to
Dished heads for boiler headers are to be seamless. be increased by 0,75 mm. See also [2.4.7].
r r
IN E
2t
R R
IN E
a
D
D
3,5
2,5 -0.5
d.(t.D)
=5.0
2
=4.0
1,6 =3.0
t/D
0.002
0.005
0.01
0.02 1,2 =2.0
0.04
1
0,9
0,8 =1.0
0,7
0,6 =0.5
0,5
0,18 0,2 0,3 0,4 0,5 H/D
where: RIN
s
(a) rIN (b) rIN
2t
2t
t
t
s
rIN
2t 2t rIN
(c) (d)
t1
t1 t1
t
t
t1
rIN
t1 3t 1,5t
1,5t 4t
rIN
(e) (f)
St
Types shown in (a), (b) and (c) are acceptable for all pressure vessels.
Type shown in (d) is acceptable for class 2 and class 3 pressure vessels.
Types shown in (e) and (f) are acceptable for class 3 pressure vessels only.
t2
t
3t 0 r
3t 0
r = 0,2t 0,5t
D t0 D t1 D
t0
t1
t1
t1 D t1 D t1 D
t1 D t1 D
(g) (h)
D
t1 D t1 D
t1
(j) (k)
(i)
t1 t
t
t1 D
D t1
(l) (m)
D h
D
N
t
t
t1 t1
(n) (o)
2.8 Openings and branches (nozzles) by reinforcing pads or rings analogous to increasing
the wall thickness: see Fig 12 and Fig 13
2.8.1 Nozzles thickness
by a combination of previous reinforcement
a) The thickness eb , in mm, of nozzles attached to shells
and headers of boilers is not to be less than: b) Definitions
d
e b = -----E- + 2 ,5 Effective lengths rs required for calculation of efficiency
25
and of compensations is to be taken as:
where dE is the outside diameter of nozzle, in mm.
The thickness of the nozzle is, however, to be not less rs = min ( Dt a, s1)
than the thickness required for the piping system
where:
attached to the vessel shell calculated at the vessel
design pressure, and need not to be greater than the D : Outside diameter, in mm
thickness of the shell to which it is connected.
ta : Available thickness, in mm
b) The thickness of the nozzle attached to shells and head-
ers of other pressure vessels is not to be less than the s1 : Transition length, in mm, according to Fig 9
thickness required for the piping system attached to the
and Fig 10
vessel shell calculated at the vessel design pressure, and
need not be greater than the thickness of the shell to
which it is connected. Figure 9 : Reinforcement by increasing the
wall thickness of the main body with opening
c) Where a branch is connected by screwing, the thickness
of the nozzle is to be measured at the root of the thread.
rs d s1
2.8.2 Nozzle connection to vessel shell
a) In general, the axis of the nozzle is not to form an angle
greater than 15 with the normal to the shell.
Af
30
ers
b) Fig 30, Fig 31, Fig 32 and Fig 33 show some typical
acceptable connections of nozzles to shells. Other types
of connections are to be considered by the Society on a
case by case basis.
dos
dis
a) In general, the largest dimensions of the openings in
shells are not to exceed:
Ap
for shells up to 1500 mm in diameter DE:
1/2 DE , but not more than 500 mm
for shells over 1500 mm in diameter DE:
Figure 10 : Reinforcement by set-through
1/3 DE , but not more than 1000 mm,
and full penetration welded branch
where DE is the vessel external diameter, in mm.
dob
Greater values may be considered by the Society on a
case by case basis. dib
bo
A fb
2.8.4 Openings compensation in cylindrical shells
b1
rb
Afs
ers
a) Compensation methods 30
methods:
erb s1 so
by increasing the wall thickness of main body com-
pared with that of the cylindrical shell without open-
dos
dis
bo
Afb
Afs rs where:
ers
b1
rb
Full case
dis
dis
er
er
p
er
erb
s
s
er
er
er
erb erb
erb dib dib
is
s
is
d
i
d
dib
a) set through welded branch b) set in welded branch c) set on welded branch
d
ib
e rb
ers
< 45
dis
area I area II
Figure 15 : Angle definition
for cylindrical shell with non-radial branch
dib erb
erb
ers
< 45
dis
a : Circumferential direction
b : Longitudinal direction
c) The opening is to be so situated that its projection, or its the position of non-compensated openings in the
reinforcement projection in the case of compensated heads is to be as shown in Fig 17
openings, is completely contained inside a circle having
for flanged openings, the radius r of the flanging (see
its centre at the centre of the head and a diameter of
Fig 17) is not to be less than 25 mm
0,8 D, D being the external diameter of the head (see
Fig 17). However, a small reinforced opening for drain- the thickness of the flanged part may be less than the
age may be accepted outside the indicated area. Rule thickness.
d1 lae:
l = 0,5 d
2t
l = (2 RIN t)0,5
where:
D
d : Diameter of the opening, in mm
Not less than RIN : Internal radius of the spherical part, in mm,
the diameter of
the smaller opening
in the case of hemispherical or torispherical
heads
In the case of ellipsoidal heads, RIN is to be
calculated by the following formula (see Fig
2 (a):
4 4 2 2 32
[a x (a b )]
R IN = ------------------------------------------------
4
-
a b
where;
a : Half the major axis of the ellipti-
cal meridian section of the
head, in mm
b : Half the minor axis of the above
section, in mm
2.8.6 Opening compensation in dished heads x : Distance between the centre of
a) Where openings are cut in dished heads and the pro- the hole and the rotation axis of
posed thickness of the head is less than that calculated the shell, in mm.
by the formula in [2.5.3] with the greatest of the shape b) In the case of nozzles or pads welded in the hole, the
factor C according to [2.5.3] the opening is to be com- section corresponding to the thickness in excess of that
pensated. required is to be considered for the part which is subject
b) Fig 30, Fig 31, Fig 32 and Fig 33 show typical connec- to pressure and for a depth h, in mm, both on the exter-
tions of nozzles and compensating rings. nal and internal sides of the head, not greater than:
(dB tB)0,5
c) The opening is considered sufficiently compensated
when the head thickness t is not less than that calcu- where dB and tB are the diameter of the opening and the
lated in accordance with [2.5.3] and using the shape- thickness of the pad or nozzle, in mm, respectively.
factor C obtained from the graph in Fig 3 using the c) The area of the welding connecting nozzle and pad
value: reinforcements may be considered as a compensating
section.
d A
---- ( t D ) 0 ,5
t d) If the material of reinforcement pads, nozzles and col-
lars has a permissible stress lower than that of the head
instead of: material, the area A, to be taken for calculation of the
d(t D)0,5 coefficient C, is to be reduced proportionally.
e) add to it the area of the compensating plate (if any)
additional strength of material having a higher allowable
stress than that of the flat end plate
Welds attaching branches and compensating plates are to
ecp : Thickness calculated in accordance with equation in
be capable of transmitting the full strength of the reinforcing
[2.8.1] for the part under consideration
area and all other loadings to which they may be subjected.
ecb : Thickness calculated taking efficiency = 1
2.8.10 Covers b : The smaller of the two values:
a) Circular, oval and elliptical inspection openings are to 2,5 erep and (2,5 eb + erp)
be provided with steel covers. Inspection openings with s : The greater of the two values:
a diameter not exceeding 150 mm may be closed by (erep + 75) and (dib / 4)
blind flanges.
Area Y is not to be less than area X.
b) The thickness of the opening covers is not to be less Note 1 : The compensating plate is required only in cases where
than the value t, in mm, given by the following formula: area Y would otherwise be less than area X.
b/a 1,00 1,05 1,10 1,15 1,20 1,25 1,30 1,40 1,50 1,60
C 0,206 0,220 0,235 0,247 0,259 0,271 0,282 0,302 0,321 0,333
b/a 1,70 1,80 1,90 2,00 2,50 3,00 3,50 4,00 4,50 5,00
C 0,344 0,356 0,368 0,379 0,406 0,433 0,449 0,465 0,473 0,480
S
=
Table 14 : Coefficient m
d/s 0,30 0,35 0,40 0,45 0,50 0,55 0,60 0.65 0,70 0,75 0,80
m 0,137 0,175 0,220 0,274 0,342 0,438 0,560 0,740 1,010 1,420 2,060
2.9 Regular pattern openings - Tube holes row is parallel to the cylinder generating line;
= 90 for circumferential hole row)
2.9.1 Definition
m : Coefficient depending upon the ratio d/s, as
Openings may be considered as regular pattern openings obtained from Tab 14. For intermediate values
when not less than three non isolated openings are dis- of d/s, the value of m is to be obtained by linear
posed in regularly staggered rows in longitudinal or circular interpolation.
direction of a shell.
The value of e actually used is to be the smallest calculated
In such a case, instead of a direct calculation of the com- value for either longitudinal, diagonal or circumferential
pensation of openings, the thickness of the shell could be rows of holes.
calculated by application of applicable formulae given in
[2.4], [2.5] with a reduced efficiency e as indicated in
2.9.3 Welded shells with tube holes and efficiency
[2.9.2] and [2.9.3].
factor of different hole patterns
This requirement apply for pressure vessels and for boiler. Where shells have welding butts and/or different groups of
hole patterns, the value to be assumed for the efficiency e in
2.9.2 Efficiency factor of tube holes in cylindrical the formulae is the minimum of the values calculated sepa-
tube plates
rately for each type of welding (as per [2.4.2]) and for each
The efficiency factor e of pipe holes in cylindrical shells configuration of holes (as per [2.9.1]).
pierced by tube holes is to be determined by direct calcula-
tion or by another suitable method accepted by the Society. 2.9.4 Rectangular section headers
In the case of cylindrical holes of constant diameter and
radial axis, the efficiency factor e may be determined by the a) For seamless type headers of rectangular section design,
following formula (see Fig 19): the wall thickness t, in mm, in way of corner fillets and
the thickness t1, in mm, of any drilled wall is not to be
1 less than those given by the following formulae, as
e = ----------------------------------------------------------------------------------------------
s
----------- ( 1 ( 0 ,5 sin2 ) ) + m sin 2 appropriate (see Fig 20):
sd
0 ,5
100pM
where: t = ---------------------1
K
s : Pitch of the hole row considered, in mm 100pM 0 ,5
t 1 = ---------------------2
eK
d : Diameter of holes, in mm. The hole diameter d
may be reduced by the amount Y/ecp where Y is
where (see also Fig 20):
the compensating area, in mm2, of nozzle and
welds and ecp the calculated unpierced shell t : Wall thickness at the corners, in mm
thickness, see [2.8.9] and Fig 18
t1 : Thickness of drilled wall, in mm
: Angle between the axis of hole row considered
and the axis of the cylinder ( = 0 if the hole p : Design pressure, in MPa
2a
?
s d 2b
K : Permissible stress, in N/mm2, obtained as where is the angle between the axis of the
specified in [2.3] diagonal row of the holes under considera-
a : Internal half width of the header, in a direc- tion and the axis of the header, in the case of
tion parallel to the wall under consideration, a staggered pattern of holes.
in mm b) The thickness obtained by the formulae in a) is net
b : Internal half width of the header, in a direc- thickness, as it does not include any corrosion allow-
tion normal to the wall under consideration, ance. The thickness obtained by the above formula is to
in mm be increased by 1,5 mm. See also [2.4.7].
c : Distance between the axis of the hole row
considered and the centreline of the header 2.10 Water tubes, superheaters and
wall, in mm economiser tubes of boilers
e : Efficiency factor of holes in the wall, deter-
2.10.1
mined by the following formulae:
a) The thickness of tubes of evaporating parts, economisers
sd
e = ----------- for d < a and superheaters exposed to gases which are subject to
s
internal pressure is not to be less than the value t given
s 0 ,67d
e = ------------------------ for a d < 1 ,3a by the following formula:
s
s 0 ,33d pd
e = ------------------------ for d 1 ,3a t = ----------------- + 0 ,3
s 2K + p
where: where:
s : Pitch of the holes, in mm, of the p : Design pressure, in MPa
longitudinal or diagonal row K : Permissible stress, in N/mm2, obtained as
under consideration. For a stag- specified in [2.3]
gered pattern of holes the pitch
d : Outside diameter of tube, in mm.
of the diagonal row is to be con-
sidered However, irrespective of the value calculated by the for-
mulae in item a), the thickness t of tubes is not to be less
d : Diameter of the holes, in mm
than the values given in Tab 15.
M1 : Coefficient to be calculated by the following
b) The values of t determined by the above-mentioned for-
formula:
mula are to be considered as theoretical values for
a 2 + b 2 ab straight tubes, not taking account of the manufacturing
M 1 = ------------------------------
50 tolerance. Where the tubes are not sized precision
M2 : Coefficient (to be taken always positive) to tubes, the thickness calculated by the formula in item a)
be calculated by one of the following for- is to be increased by 12,5% to take into account the
mulae, as appropriate: manufacturing tolerance. For bent tubes, the thickness
of the thinner part in way of the bend is not to be less
For a non-staggered pattern of holes: than that given by the formula.
1 3 c) Whenever abnormal corrosion and erosion may occur
b 2 --- a 2 ab + --- c 2
2 2
M 2 = ------------------------------------------------- during service, the corrosion constant of 0,3 in the for-
50
mula may be increased to the satisfaction of the Society.
For a staggered pattern of holes:
d) The thickness of tubes which form an integral part of the
1 boiler and which are not exposed to combustion gases
b --- a 2 ab
2
2 is to comply with the requirements for steam pipes (see
M 2 = --------------------------------- cos
50 Ch 1, Sec 10, [15]).
b) When the end is supported in its centre by an uptake, C1 = 704 for plates supported by flanges or
the minimum thickness t, in mm, is to be calculated equivalent
with the following formula: C2 : C2 = 0 when no doublers are fitted
pR C2 = 0,85 when a complete doubling plate
t = 0 ,77 --------I
K is fitted, adequately joined to the base plate.
The value of D is to be in accordance with the following or points of tangency of the circle with
provisions: the contour line). To this end, the con-
In the parts of the flat heads between the stays: tour of the part under consideration is to
D : D = diameter, in mm, of the largest cir- be drawn at the beginning of the flang-
cle which can be drawn through the ing or connection curve if its inside
centre of at least three stays without radius does not exceed 2,5 times the
enclosing any other stay, where the stays thickness of the plate, or, where such
are not evenly spaced (see Fig 21); or radius is greater, at the above-mentioned
distance (of 2,5 times the thickness of
D = (a2 + b2)0,5 where the stays are
the plate) from the ideal intersection
evenly spaced, considering the most
with other surfaces (see Fig 21).
unfavourable condition,
where: c) When applying the formulae for calculation of thickness
a : Distance between two adja- of heads covered by this sub-article, the position of
cent rows of stays, in mm plates in the most unfavourable condition is to be con-
b : Pitch of stays in the same sidered.
row, in mm
d) Where various types of supports are provided, the value
In the parts of the flat heads between the stays and of C1 should be the arithmetic mean of the values of C1
the boundaries, where flat heads are generally sup- appropriate to each type of support.
ported by flanges or shapes, or connected to other
parts of the boiler: e) The thickness obtained by the formulae in a), is net
D : Diameter, in mm, of the largest circle thickness, as it does not include any corrosion allow-
which can be drawn through not less ance. The thickness obtained by the above formula is to
than three points of support (stay centres be increased by 1 mm. See also [2.4.7].
Figure 21 :
> "
= =
>
Key:
1 : Boundaries of areas supported by individual stays
2 : To establish the area supported by bar stays or stay tubes in boundary rows, the boundary of the loaded area is to terminate at the
centre of the associated main circle
3 : Main circles, diameter b
4 : Bar stays
5 : Stay tubes
6 : Termination of boundary areas where stay tubes are situated in the boundary rows only.
t
pL ( L s )l n + 2
t = ------------------------2- -------------
0 ,25R m a n + 1
50
where:
p : Design pressure, in MPa
a : Depth of the girder plate at mid-length, in t
t
mm
DA
L : Length of girder between supports, in mm
s : Pitch of stays, in mm
n : Number of stays on the girder t
l : Distance between centres of girders, in mm
Rm : Minimum ultimate tensile strength of the 2.12.5 Fire tubes
material used for the plates, in N/mm2.
a) The thickness of fire tubes subject to external pressure in
The above formulae refer to the normal arrangement cylindrical boilers is not to be less than the value t, in
where: mm, calculated by the following formula:
the stays are regularly distributed over the length L
pd
t = ------------------- + 1 ,8
the distance from the supports of the outer stays 0 ,15R m
does not exceed the uniform pitch s
where:
when the tops of the combustion chambers are con-
nected to the sides with curved parts with an exter- p : Design pressure, in MPa
nal radius less than 0,5 l, the distance of end girders
from the inner part of the side surface does not d : Outside diameter of tube, in mm
exceed l Rm : Minimum ultimate tensile strength of the
when the curvature radius mentioned under item tube material, in N/mm2.
just above exceeds 0,5 l, the distance of the end
The minimum acceptable thickness is given in Tab 16.
girders from the beginning of the connection does
not exceed 0,5 l. b) The values of t determined by the above-mentioned for-
In other cases a direct calculation is to be made using a mula are to be considered as theoretical values for
safety factor not less than 5, with respect to the mini- straight tubes, not taking account of the manufacturing
mum value of the tensile strength Rm. tolerance. Where the tubes are not sized precision
tubes, the thickness calculated by the formula in a) is to
i) Ogee rings
be increased by 12,5% to take into account the manu-
The thickness of ogee rings connecting the furnaces to facturing tolerance. In the case of bent tubes, the thick-
the shell in vertical auxiliary boilers (see Fig 22), where ness of the thinner part in way of the bend is not to be
the latter support the weight of the water above the fur- less than that given by the above formula.
nace, is not to be less than the value t, in mm, given by
the following formula: c) Whenever abnormal corrosion and erosion may occur
during service the corrosion constant of 1,8 in the for-
0 ,5
t = [ 1 ,02 10 3 pD A ( D A d A ) ] +1 mula may be increased to the satisfaction of the Society.
Table 16 : Minimum thickness of fire tubes E : Elastic modulus, in MPa, at design tempera-
ture T, in C, and equal to:
Nominal outside diameter Lowest nominal thickness t E = 208800 93,4 T
d 88,9 3,00 b) Stiffeners
88,9 < d 114,3 3,15 Stiffeners welded to furnaces tubes according to a stand-
114,3 < d 139,7 3,50 ard accepted by the Society may be considered as pro-
viding effective stiffening (reduction of L in upper
139,7 < d 168,3 3,99 formulae).
RS,MIN : Value of the minimum yield strength (ReH), or Figure 24 : Dished concave ends
0,2% proof stress (Rp 0,2), at the ambient temper- 0,5 D E
ature, in N/mm2. In no case is the value RS,MIN to
exceed:
0,75 Rm for normalised steels
0,90 Rm for quenched and tempered steels.
t
2.13.3 Dished heads
Dished ends are to comply with the following requirements:
h1
a) Hemispherical ends: the thickness of the ends is to be
not less than the thickness calculated for spherical shells
in accordance with [2.4.4]
b) Convex ends: see Fig 23 t1
t2
c) Concave base ends: see Fig 24 r
h2
t3
d) Ends with openings: see Fig 25
e) Other types of ends are to be specially considered by t1 > 1,7 t t2 > 2 t t3 > 2 t
the Society. h1 > 6 t h2 > 0,12 DE r > 0,075 DE
t t
t1
H
t t
r
r
r
t2 H t2
H
0,5DE 0,5DE
t t
0,5DE
t
t t
0,5 D E
h1 h1
t1 t1 0,25 H/D E 0,5 t 1 1,5t r 0,35D E
r t2 r t2
H
H 2.14.2 Thermal oil heat exchangers
The provisions of [2.14.1] apply also to thermal oil heat
0,5DE 0,5DE
exchangers. However, irrespective of the thickness obtained
H/DE 0,20 r 0,075DE t1 1,25 t t2 1,5 t h1 6 t by the formula in [2.10.1], the tube thickness of oil fired
and exhaust fired thermal oil heaters is to be not less than
the values indicated in Tab 17.
2.14 Heat exchangers Table 17 : Minimum thickness of
thermal oil heat exchanger tubes
2.14.1 Scantlings
Outside Minimum thickness, in mm, of tubes
a) Vessels are to be designed in accordance with the appli-
diameter, subject to internal pressure of oil fired and
cable requirements stated in [2.4] and [2.5].
in mm exhaust fired thermal oil heaters
b) Tubes are to be designed in accordance with [2.10.1]. < 63,5 2,4
c) Tube plates are to be designed in accordance with a 70 - 89 2,9
standard accepted by the Society. > 89 3,6
3.2.3 Miscellaneous safety valve requirements exhaust manifolds are to be led to the open and are
a) Safety valves operated by pilot valves to be adequately supported and fitted with suitable
expansion joints or other means so that their weight
The arrangement on the superheater of large relieving
does not place an unacceptable load on the safety
capacity safety valves, operated by pilot valves fitted in
valve bodies.
the saturated steam drum, is to be specially considered
by the Society. e) Steam generator heated by steam
b) Safety valve setting Steam heated steam generators are also to be protected
safety valves are to be set under steam in the pres- against possible damage resulting from failure of the
ence of the Surveyor to a pressure not higher than heating coils. In this case, the area of safety valves cal-
1,03 times the design pressure culated as stated in [3.2.2] may need to be increased to
the satisfaction of the Society, unless suitable devices
safety valves are to be so constructed that their set-
limiting the flow of steam in the heating coils are pro-
ting may not be increased in service and their spring
vided.
may not be expelled in the event of failure. In addi-
tion, safety valves are to be provided with simple
3.2.4 Other requirements
means of lifting the plug from its seat from a safe
position in the boiler or engine room Access arrangement
where safety valves are provided with means for reg- a) Boilers are to be provided with openings in sufficient
ulating their relieving capacity, they are to be so fit- number and size to permit internal examination, clean-
ted that their setting cannot be modified when the ing and maintenance operations. In general, all pressure
valves are removed for surveys. vessels which are part of a boiler with inside diameter
c) Safety valve fitting on boiler exceeding 1200 mm, and those with inside diameter
exceeding 800 mm and length exceeding 2000 mm, are
the safety valves of a boiler are to be directly con-
to be provided with access manholes.
nected to the boiler and separated from other valve
bodies b) Manholes are to be provided in suitable locations in the
where it is not possible to fit the safety valves shells, headers, domes, and steam and water drums, as
directly on the superheater headers, they are to be applicable. The net (actual hole) dimension of ellipti-
mounted on a strong nozzle fitted as close as practi- cal or similar manholes is to be not less than 300mm x
cable to the superheater outlet. The cross-sectional 400mm. The net diameter of circular manholes
area for passage of steam through restricted orifices (actual hole) cannot be less than 400 mm. The edges of
of the nozzles is not to be less than 1/2 the aggregate manholes are to be adequately strengthened to provide
area of the valves, calculated with the formulae of compensation for vessel openings in accordance with
[2.3.2] when C 10, and not less than the aggregate [2.8.4], [2.8.6] and [2.8.9], as applicable.
area of the valves when C > 10 c) In pressure vessels which are part of a boiler and are not
safety valve bodies are to be fitted with drain pipes covered by the requirement in item a) above, or where
of a diameter not less than 20 mm for double valves, an access manhole cannot be fitted, at least the follow-
and not less than 12 mm for single valves, leading to ing openings are to be provided, as far as practicable:
the bilge or to the hot well. Valves or cocks are not head holes: minimum dimensions:
to be fitted on drain pipes.
220mm x 320mm (320 mm diameter if circular)
d) Exhaust pipes
handholes: minimum dimensions: 87mm x 103mm
the minimum cross-sectional area of the exhaust
pipes of safety valves which have not been experi- sight holes: minimum diameter: 50 mm.
mentally tested is not to be less than C times the
d) Sight holes may only be provided when the arrangement
aggregate area A
of manholes, head holes, or handholes is impracticable.
the cross-sectional area of the exhaust manifold of
safety valves is to be not less than the sum of the e) Covers for manholes and other openings are to be made
areas of the individual exhaust pipes connected to it of ductile steel, dished or welded steel plates or other
approved design. Grey cast iron may be used only for
silencers fitted on exhaust manifolds are to have a
small openings, such as handholes and sight holes, pro-
free passage area not less than that of the manifolds
vided the design pressure p does not exceed 1 MPa and
the strength of exhaust manifolds and pipes and the design temperature T does not exceed 220C.
associated silencers is to be such that they can with-
stand the maximum pressure to which they may be f) Covers are to be of self-closing internal type. Small
subjected, which is to be assumed not less than 1/4 opening covers of other type may be accepted by the
of the safety valve setting pressure Society on a case by case basis.
in the case that the discharges from two or more g) Covers of the internal type are to have a spigot passing
valves are led to the same exhaust manifold, provi- through the opening. The clearance between the spigot
sion is to be made to avoid the back pressure from and the edge of the opening is to be uniform for the
the valve which is discharging influencing the other whole periphery of the opening and is not to exceed
valves 1,5 mm.
h) Closing devices of internal type covers, having dimen- Feed check valves
sions not exceeding 180mm x 230mm, may be fitted
a) Each fired boiler supplying steam to essential services is
with a single fastening bolt or stud. Larger closing
to be fitted with at least two feed check valves con-
devices are to be fitted with at least two bolts or studs.
nected to two separate feed lines. For unfired steam gen-
i) Covers are to be designed so as to prevent the disloca- erators a single feed check valve may be allowed.
tion of the required gasket by the internal pressure. Only
b) Feed check valves are to be secured directly to the
continuous ring gaskets may be used for packing.
boiler or to an integral economiser. Water inlets are to
Fittings be separated. Where, however, feed check valves are
a) In general, cocks and valves are to be designed in accord- secured to an economiser, a single water inlet may be
ance with the requirements in Ch 1, Sec 10, [2.7.2]. allowed provided that each feed line can be isolated
b) Cocks, valves and other fittings are to be connected without stopping the supply of feed water to the boiler.
directly or as close as possible to the boiler shell. c) Where the economisers may be bypassed and cut off
c) Cocks and valves for boilers are to be arranged in such a from the boiler, they are to be fitted with pressure-limit-
way that it can be easily seen when they are open or ing type valves, unless the arrangement is such that
closed and so that their closing is obtained by a clock- excessive pressure cannot occur in the economiser
wise rotation of the actuating mechanism. when cut off.
Boiler burners d) Feed check valves are to be fitted with control devices
Burners are to be arranged so that they cannot be with- operable from the stokehold floor or from another
drawn unless the fuel supply to the burners is cut off. appropriate location. In addition, for water tube boilers,
at least one of the feed check valves is to be arranged so
Allowable water levels as to permit automatic control of the water level in the
a) In general, for water tube boilers the lowest permissible boiler.
water level is just above the top row of tubes when the e) Provision is to be made to prevent the feed water from
water is cold. Where the boiler is designed not to have getting in direct contact with the heated surfaces inside
fully submerged tubes, when the water is cold, the low- the boiler and to reduce, as far as possible and neces-
est allowable level indicated by the manufacturer is to sary, the thermal stresses in the walls.
be indicated on the drawings and submitted to the Soci-
Drains
ety for consideration.
Each superheater, whether or not integral with the
b) For fire tube boilers with combustion chamber integral
boiler, is to be fitted with cocks or valves so arranged
with the boiler, the minimum allowable level is to be at
that it is possible to drain it completely.
least 50 mm above the highest part of the combustion
chamber. Water sample
c) For vertical fire tube boilers the minimum allowable a) Every boiler is to be provided with means to supervise
level is 1/2 of the length of the tubes above the lower and control the quality of the feed water. Suitable
tube sheet. arrangements are to be provided to preclude, as far as
Steam outlets practicable, the entry of oil or other contaminants which
a) Each boiler steam outlet, if not serving safety valves, may adversely affect the boiler.
integral superheaters and other appliances which are to b) For this purpose, boilers are to be fitted with at least one
have permanent steam supply during boiler operation, is water sample cock or valve. This device is not to be
to be fitted with an isolating valve secured either connected to the water level standpipes.
directly to the boiler shell or to a standpipe of substan-
tial thickness, as short as possible, and secured directly c) Suitable inlets for water additives are to be provided in
to the boiler shell. each boiler.
c
1 4
B 6
A
A
D
F
B
3
9
E
A
8 7
Key
1 : Nozzle (set in); 2 : Flange; 3 : Nozzle (set on); 4 : Reinforcing plate; 5 : Non-pressure part;
6 : Pad (set in); 7 : Pad (set on); 8 : Manhole frame; 9 : Flat plate.
4.2.2 Shell longitudinal and circumferential welds tapering of the shell made as indicated in [2.5.6] is
Longitudinal and circumferential joints are to be welded wholly in the hemisphere.
from both sides of the plate. Welding from one side may be b) For torispherical ends made of parts assembled by weld-
allowed only when there is evidence that the welding proc- ing, no welded joint is normally admitted along a paral-
ess permits a complete penetration and a sound weld root. lel in the knuckle nor at a distance less than 50 mm
If a backing strip is used, it is to be removed after welding from the beginning of the knuckle.
and prior to any non-destructive examination. However, the
backing strip may be retained in circumferential joints of 4.2.5 Welding location
class 2 vessels, having a thickness not exceeding 15 mm, The location of main welded joints is to be chosen so that
and of class 3 vessels, provided that the material of the these joints are not submitted to appreciable bending stresses.
backing strip is such as not to adversely affect the weld.
4.2.6 Accessories and nozzles
4.2.3 Plates of unequal thickness a) Attachment of accessories by welds crossing main
a) If plates of unequal thickness are butt-welded and the welds or located near such welds is to be avoided;
difference between thicknesses is more than 3 mm, the where this is impracticable, welds for attachment of
thicker plate is to be smoothly tapered for a length equal accessories are to completely cross the main welds
to at least four times the offset, including the width of rather than stop abruptly on or near them.
the weld. For longitudinal joints the tapering is to be b) Openings crossing main joints or located near main
made symmetrically on both sides of the plate in order joints are also to be avoided as far as possible.
to obtain alignment of middle lines. c) Doubling plates for attachment of accessories such as fix-
b) If the joint is to undergo radiographic examination, the ing lugs or supports are to be of sufficient size to ensure
thickness of the thicker plate is to be reduced to that of an adequate distribution of loads on pressure parts; such
the thinner plate next to the joint and for a length of at doubling plates are to have well rounded corners. Attach-
least 30 mm. ment of accessories such as ladders and platforms
directly on the walls of vessels such that they restrain
4.2.4 Dished heads their free contraction or expansion is to be avoided.
a) For connection of a hemispherical end with a cylindri- d) Welded connections of nozzles and other fittings, either
cal shell, the joint is to be arranged in a plane parallel to with or without local compensation, are to be of a suita-
that of the largest circle perpendicular to the axis of the ble type, size and preparation in accordance with the
shell and at such a distance from this plane that the approved plans.
(a) (b)
t t
t
(c) (d)
(D)
(e) (f)
4.2.7 Connections of stays to tube plates 4.3 Miscellaneous requirements for fabrica-
a) Where stays are welded, the cross-sectional area of the tion and welding
weld is to be at least 1,25 times the cross-section of the stay.
b) The cross-sectional area of the end welding of welded 4.3.1 Welding position
stay tubes is to be not less than 1,25 times the cross-sec-
tional area of the stay tube. a) As far as possible, welding is to be carried out in the
downhand horizontal position and arrangements are to
4.2.8 Type of weldings be foreseen so that this can be applied in the case of cir-
Fig 28, Fig 29, Fig 30, Fig 31, Fig 32, Fig 33, Fig 34, Fig 35, cumferential joints.
Fig 36 and Fig 37 indicate the type and size of weldings of
typical pressure vessel connections. Any alternative type of b) When welding cannot be performed in this position,
welding or size is to be the subject of special consideration tests for qualification of the welding process and the
by the Society. welders are to take account thereof.
25
20
3mm
3mm
(g) 25 (h)
(i)
t
t
(j) (k)
!
%&"'()* +()*
, -#
"
#
, & #
$
, .
#
#
#
, /
#
# 0
#
#
#
t t
is the greater
is the greater
t/3 or 6 mm
t/3 or 6 mm
whichever
whichever
t t
t
See sketch (a)
(e) (f)
t t
90
t
(g)
90
(h) (i)
(j)
t t
To be used only for nozzles of
small thickness and diameter
t t
t
t
0,7 t
(k) (l)
t t
t/3 or 6 mm
t/3 or 6 mm
t t
whichever whichever
is the greater is the greater
(m) (n)
t t
t/3 or 6 mm
t/3 or 6 mm
t t
whichever
whichever
is the greater is the greater
0,7 t
(o) (p)
t t
t Remove by mechanical
(q) (r) means after welding
Note: Where preparations of Fig 33 are carried out, the shell is to be carefully inspected to ascertain the absence of lamination.
t or 5 mm
(a) whichever
is greater
(b)
t
t
t
(c) t or 5 mm t or 5 mm
whichever whichever
is greater is greater
(d)
1,5t or 6 mm
1,5t or 6 mm
whichever
whichever
is greater
is greater
t
1,5t or 6 mm
(e) (f) whichever
is greater
t or 5 mm
whichever
is greater
t
(g)
0-3 mm
0,7 t
t
t
0,7 t
(a) (b)
t/3 or 6 mm
whichever is greater
t
(c)
t1
t2
t2
0,7 t
(d) (e)
60
a = t/3 or 6 mm (g)
whichever is the greater
(f)
Preparation shown on sketches (d), (e)
and (f) are to be used when the joint is
t
(h)
1,5 mm
1,5 mm 1,5 mm
a = d/4 1,5 mm a = d/5
40
d
d
a
a
6 mm 6 mm
a
a
d
d
t t
t1 > 0,75 t t1 > 0,75 t
t1 /3 t1 /3
(d) (e)
t + 3 mm 3 mm
t
(f) t
(g)
a) Welded joints are to have a smooth surface without a) Abutting of parts to be welded is to be such that surface
under-thickness; their connection with the plate surface misalignment of plates does not exceed:
is to be gradual without undercutting or similar defects.
10% of the thickness of the plate with a maximum of
b) The weld reinforcement of butt welds, on each side of 3 mm for longitudinal joints
the plate, is not to exceed the following thickness:
10% of the thickness of the plate plus 1 mm with a
2,5 mm for plates having a thickness not exceeding maximum of 4 mm for circumferential joints.
12 mm
b) For longitudinal joints, middle lines are to be in align-
3 mm for plates having a thickness greater than ment within 10% of the thickness of the thinner plate
12 mm but less than 25 mm with a maximum of 3 mm.
5 mm for plates having a thickness at least equal to c) Plates to be welded are to be suitably retained in posi-
25 mm. tion in order to limit deformation during welding. The
arrangements are to be such as to avoid modification of
the relative position of parts to be welded and misalign-
4.4 Preparation of parts to be welded ment, after welding, exceeding the limits indicated
above.
4.4.1 Preparation of edges for welding
d) Temporary welds for abutting are to be carried out so
a) Grooves and other preparations of edges for welding are that there is no risk of damage to vessel shells. Such
to be made by machining, chipping or grinding. Flame welds are to be carefully removed after welding of the
cutting may also be used provided that the zones dam- vessel and before any heat treatment. Non-destructive
aged by this operation are removed by machining, chip- testing of the corresponding zones of the shell may be
ping or grinding. For alloy steel plates, preheating is to required by the Surveyor if considered necessary.
be provided, if needed, for flame cutting.
e) Accessories such as doubling plates, brackets and stiff-
b) Edges prepared are to be carefully examined to check eners are to be suitable for the surface to which they are
that there are no defects detrimental to welding. to be attached.
Applications at temperatures less than the ambient tempera- 4.7.5 Execution of heat treatment
ture and/or steels other than those indicated above are to be Furnaces for heat treatments are to be fitted with adequate
the subject of special consideration by the Society. means for controlling and recording temperature; tempera-
Stress relieving heat treatment is not to be required when tures are to be measured on the vessel itself. The atmos-
the minimum temperature of the fluid is at least 30C higher phere in the furnaces is to be controlled in order to avoid
than the KV-notch impact test temperature specified for the abnormal oxidation of the vessel.
steel; this difference in temperature is also to be complied
4.7.6 Treatment of test plates
with for welded joints (both in heat-affected zones and in
weld metal). Test plates are normally to be heated at the same time and
in the same furnace as the vessel.
Pressure vessels and pipes of class 3 and associated parts
When separate heat treatment of test plates cannot be
are not required to be stress relieved, except in specific
avoided, all precautions are to be taken such that this treat-
cases.
ment is carried out in the same way as for the vessel, specif-
ically with regard to the heating rate, the maximum
4.7.3 Heat treatment procedure
temperature, the duration for maintaining this temperature
The temperature of the furnace at the time of introduction of and the cooling conditions.
the vessel is not to exceed 400C.
4.7.7 Welding after heat treatment
a) The heating rate above 400C is not to exceed:
a) Normally, welding after heat treatment is only allowed if:
220C per hour if the maximum thickness is not
more than 25 mm, or the throat of welding fillets does not exceed 10 mm
the largest dimension of openings in the vessel for
(5500 / tA)C per hour, with a minimum of 55C per
the accessories concerned does not exceed 50 mm.
hour, if the maximum thickness tA , in mm, is more
than 25 mm b) Any welding of branches, doubling plates and other
accessories on boilers and pressure vessels after heat
b) The cooling rate in the furnace is not to exceed: treatment is to be submitted for special examination by
280C per hour if the maximum thickness is not the Society.
more than 25 mm, or
(7000 / tA)C per hour, with a minimum of 55C 4.8 Welding samples
per hour, if the maximum thickness tA , in mm, is
4.8.1 Test plates for welded joints
more than 25 mm.
a) Test plates of sufficient size, made of the same grade of
Unless specially justified, heat treatment temperatures and steel as the shell plates, are to be fitted at each end of
duration for maintaining these temperatures are to comply the longitudinal joints of each vessel so that the weld in
with the values in Tab 19. the test plates is the continuation of these welded joints.
There is to be no gap when passing from the deposited
Table 19 : Heat treatment procedure metal of the joint to the deposited metal of the test plate.
b) The bend test pieces are to be bent through an angle of b) Fillet welds for parts such as doubling plates, branches
180 over a former of 4 times the thickness of the test or stiffeners are to undergo a spot magnetic particle test
piece. There is to be no crack or defect on the outer sur- for at least 10% of their length. If magnetic particle tests
face of the test piece exceeding in length 1,5 mm trans- cannot be used, it is to be replaced by liquid penetrant
versely or 3 mm longitudinally. Premature failure at the test.
edges of the test piece is not to lead to rejection. As an c) Welds for which non destructive tests reveal unaccepta-
alternative, the test pieces may be bent through an angle ble defects, such as cracks or areas of incomplete
of 120 over a former of 3 times the thickness of the test fusion, are to be rewelded and are then to undergo a
piece. new non destructive examination
c) The impact energy measured at 0C is not to be less
than the values given in NR216 Materials for the steel 4.9.3 Number of test samples
grade concerned. a) During production, at least one test plate for each 20 m
d) The test piece for macrographic examination is to per- of length (or fraction) of longitudinal weldings is to be
mit the examination of a complete transverse section of tested as per [4.8.2].
the weld. This examination is to demonstrate good pen- b) During production, at least one test plate for each 30 m
etration without lack of fusion, large inclusions and sim- of length (or fraction) of circumferential welding is to be
ilar defects. In case of doubt, a micrographic tested as per [4.8.2].
examination of the doubtful zone may be required.
c) When several vessels made of plates of the same grade
4.8.3 Re-tests of steel, with thicknesses varying by not more than 5
mm, are welded successively, only one test plate may
a) If one of the test pieces yields unsatisfactory results, two be accepted per each 20 m of length of longitudinal
similar test pieces are to be taken from another test joints (or fraction) and per each 30 m of circumferential
plate. welding (or fraction) provided that the welders and the
b) If the results for these new test pieces are satisfactory welding process are the same. The thickness of the test
and if it is proved that the previous results were due to plates is to be the greatest thickness used for these ves-
local or accidental defects, the results of the re-tests may sels.
be accepted.
4.10 Specific requirements for class 2 ves-
4.9 Specific requirements for class 1 ves- sels
sels
4.10.1 General
4.9.1 General For vessels whose scantlings have been determined using an
The following requirements apply to class 1 pressure ves- efficiency of welded joint e greater than 0,90, see [4.9.1].
sels, as well as to pressure vessels of other classes whose
4.10.2 Non-destructive tests
scantling has been determined using an efficiency of
welded joint e greater than 0,90. All longitudinal and circumferential joints of class 2 vessels
are to be subjected to radiographic or equivalent examina-
4.9.2 Non-destructive tests tion to an extent of 10% of each weld length. This examina-
tion is to cover all the junctions between welds.
a) All longitudinal and circumferential joints of class 1 ves-
sels are to be subject of 100% radiographic or equiva- This extension may be increased at the Society's discretion
lent examination with the following exceptions: depending on the actual thickness of the welded plates.
for pressure vessels or parts designed to withstand For actual thickness 15 mm, this examination can be
external pressures only, at the Societys discretion, omitted. In this case, the value of the efficiency should be as
the extent may be reduced up to approximately 30% indicated in Tab 11.
of the length of the joints. In general, the positions
included in the examinations are to include all 4.10.3 Number of test samples
welding crossings In general, the same requirements of [4.9.3] apply also to
for vessels not intended to contain toxic or danger- class 2 pressure vessels. However, test plates are required
ous matters, made of carbon steels having thickness for each 50 m of longitudinal and circumferential weldings
below 20 mm when the joints are welded by (or fraction).
approved automatic processes at the Societys dis-
cretion, the extent may be reduced up to approxi- 4.11 Specific requirements for class 3 ves-
mately 10% of the length of the joints. In general, sels
the positions included in the examinations are to
include all welding crossings 4.11.1 For vessels whose scantlings have been determined
for circumferential joints having an external diame- using an efficiency of welded joint e greater than 0,90, see
ter not exceeding 175 mm, at the Societys discre- [4.9.1].
tion, the extent may be reduced up to approximately Heat treatment, mechanical tests and non-destructive tests
10% of the total length of the joints. are not required for welded joints of other class 3 vessels.
5 Design and construction - Control c) Where level indicators are not fixed directly on the boiler
shell, but on level pillars, the internal diameter of such
and monitoring
pillars is not to be less than the value dN given in Tab 20.
Level pillars are to be either fixed directly on the boiler
5.1 Boiler control and monitoring system shell or connected to the boiler by pipes fitted with cocks
secured directly to the boiler shell. The internal diameter
5.1.1 Local control and monitoring
of these pipes dC is not to be less than the values given in
Means to effectively operate, control and monitor the oper-
Tab 20. The upper part of these pipes is to be arranged so
ation of oil fired boilers and their associated auxiliaries are
that there is no bend where condense water can accumu-
to be provided locally. The functional condition of the fuel,
late. These pipes are not to pass through smoke boxes or
feed water and steam systems and the boiler operational
uptakes unless they are located inside metallic ducts hav-
status are to be indicated by pressure gauges, temperature
ing internal diameter exceeding by not less than 100 mm
indicators, flow-meter, lights or other similar devices.
the external diameter of the pipes. Fig 38 shows the
5.1.2 Emergency shut-off sketch of a level pillar arrangement.
Means are to be provided to shut down boiler forced draft
or induced draft fans and fuel oil service pumps from out- Figure 38 : Level pillar arrangement
side the space where they are located, in the event that a cock
fire in that space makes their local shut-off impossible.
Table 24 : Incinerators
6.3.4 A bursting disk discharging to suitable waste steam pipe 7 Design requirements for boil-off gas
is to be fitted in addition to the valve. The alternative arrange-
combustion units
ments for ensuring pressure relief in the event of solid matter
on the valve and guide are to function at a pressure not
exceeding 1.25 times the economizer approved design pres- 7.1 Operating cases
sure and are to have sufficient capacity to prevent damage to
7.1.1 Gas combustion units are to be capable of operating
the economizer when operating at its design heat input level.
at least in the following conditions:
6.3.5 To avoid the accumulation of solid matter deposits on a) for gas carriers:
the outlet side of safety valves and bursting discs, the dis- normal boil-off handling in laden conditions
charge pipes and safety valve/bursting disk housings are to
reduced boil-off handling in ballast conditions
be fitted with drainage arrangements from the lowest part,
directed with continuous fall to a position clear of the econ- during inerting and purging operations.
omizer where it will not pose threats to either personnel or b) for gas-fuelled ships:
machinery. No valves or cocks are to be fitted in the drain- boil-off handling during periods of slow steaming
age arrangements. and/or no consumption from propulsion or other
services of the ship
6.3.6 Full details of the proposed arrangements to satisfy
[6.3.1] to [6.3.5] are to be submitted for approval. during LNG bunkering, inerting and purging opera-
tions.
6.4 Pressure indication
7.2 Availability
6.4.1 Every shell type economizer is to be provided with a
means of indicating the internal pressure. A means of indi- 7.2.1 Main components of the GCU(s):
cating the internal pressure is to be located so that the pres- mechanical non-static components such as fans,
sure can be easily read from any position from which the electronic cards pertaining to the control and monitor-
pressure may be controlled. ing system,
are to be duplicated so that the nominal capacity of the
6.5 Lagging GCU(s) can be sustained or restored in case of single failure
of such components.
6.5.1 Every shell type economizer is to be provided with
removable lagging at the circumference of the tube end 7.2.2 The time necessary to restore the GCU operation in
plates to enable ultrasonic examination of the tube plate to case of a component failure is to be consistent with the
shell connection. expected operating profile of the GCU and with the
increase rate of the pressure in the tanks. In this respect,
6.6 Feed water spare components ready for installation in a short time may
be considered in lieu of duplicated components.
6.6.1 Every economiser is to be provided with arrange-
ments for pre-heating and de-aeration, addition of water
7.3 Gas combustion equipment
treatment or combination thereof to control the quality of
feed water to within the manufacturers recommendations. 7.3.1 General
The gas combustion unit is to exhibit no visible flame.
6.7 Operating instructions
7.3.2 Flue gas temperature
6.7.1 The manufacturer is to provide operating instructions The flue gas temperature at the GCU outlet, after possible
for each economiser which is to include reference to: dilution, is not to exceed 535C.
Feed water treatment and sampling arrangements Note 1: The attention is drawn to certain national or international
Operating temperatures exhaust gas and feed water rules that may impose different temperature limits.
temperatures In case of emergency shut-down of the GCU, the flue gas
Operating pressure temperature is not to exceed the aforementioned value.
Inspection and cleaning procedures Otherwise, an emergency water cooling system is to be pro-
vided.
Records of maintenance and inspection
The need to maintain adequate water flow through the 7.3.3 Combustion chamber
economiser under all operating conditions The combustion chamber is to be of suitable form such as
Periodical operational checks of the safety devices to be not to present pockets where gas may accumulate.
carried out by the operating personnel and to be docu- The flame length is to remain within the gas combustion
mented accordingly chamber in all expected operating cases, irrespective of the
Procedures for using the exhaust gas economiser in the gas composition and gas pressure.
dry condition The combustion chamber is to be fitted with at least two
Procedures for maintenance and overhaul of safety flame monitoring devices, one for the alarm activation and
valves. one to shut off the gas supply in the case of flame failure.
The gas piping system fitted to the GCU is to comply with 8.1 Foundations
the relevant provisions of IGC Code, Chapter 16 or IGF
8.1.1 For boilers and pressure vessels bolting down to their
Code, Section 9, as appropriate.
foundations, see Ch 1, Sec 1, [3.3.1]. Where necessary, they
are also to be secured to the adjacent hull structures by suit-
7.4.2 Inerting able ties.
Provisions are to be made for inerting and gas-freeing the Where chocks are required to be fitted between the boilers
portion of the gas piping system located in the GCU com- and their foundations, they are to be of cast iron or steel.
partment.
8.2 Boilers
Note 1: Where it is demonstrated that the natural gas-freeing of the
GCU burner and of its gas supply piping is efficient, the connection 8.2.1 Thermal expansion
to the inert gas system may be omitted, subject to the flag authori- Means are to be provided to compensate thermal expansion
ties agreement. of boilers.
b) The minimum distance of vertical tube boilers from dou- 9.1.2 Boilers, other steam generators, and oil fired
ble bottoms not intended to carry oil may be 200 mm. and exhaust gas thermal oil heaters
In addition to the requirement in [9.1.1], testing of materials
8.2.4 Minimum distance of boilers from ceilings intended for the construction of pressure parts of boilers,
other steam generators, oil fired thermal oil heaters and
a) A space sufficient for adequate heat dissipation is to be exhaust gas thermal oil heaters is to be witnessed by the
provided on the top of boilers. Surveyor.
b) Oil tanks are not permitted to be installed in spaces 9.1.3 Class 1 pressure vessels and heat exchangers
above boilers. In addition to the requirement in [9.1.1], testing of materials
intended for the construction of class 1 pressure parts of
8.2.5 Installation of boilers on engine room flats pressure vessels and heat exchangers is to be witnessed by
the Surveyor.
Where boilers are installed on an engine room flat and are
not separated from the remaining space by means of a This requirement may be waived at the Societys discretion
watertight bulkhead, a coaming of at least 200 mm in for mass produced small pressure vessels (such as accumu-
height is to be provided on the flat. The area surrounded by lators for valve controls, gas bottles, etc.).
the coaming may be drained into the bilge.
9.2 Workshop inspections
8.2.6 Drip trays and gutterways
9.2.1 Boilers and individually produced class 1 and
Boilers are to be fitted with drip trays and gutterways in way of 2 pressure vessels
burners so arranged as to prevent spilling of oil into the bilge. The construction, fitting and testing of boilers and individu-
ally produced class 1 and 2 pressure vessels are to be
8.2.7 Hot surfaces attended by the Surveyor, at the builder's facility.
Hot surfaces with which the crew are likely to come into 9.2.2 Mass produced pressure vessels
contact during operation are to be suitably guarded or insu-
Construction of mass produced pressure vessels which are
lated. See Ch 1, Sec 1, [3.7.1].
type approved by the Society need not be attended by the
Surveyor.
8.2.8 Registers fitted in the smoke stacks of oil fired
boilers
9.3 Hydrostatic tests
Where registers are fitted in smoke stacks, they are not to
obstruct more than two thirds of the cross-sectional area of 9.3.1 General
gas passage when closed. In addition, they are to be pro- Hydrostatic tests of all class 1, 2 and 3 pressure vessels are
vided with means for locking them in open position when to be witnessed by the Surveyor with the exception of mass
the boiler is in operation and for indicating their position produced pressure vessels which are built under the condi-
and degree of opening. tions stated in [9.2.2].
In general, all weldings are to be carried out by qualified 2.4.2 Overspeed devices
welders in accordance with qualified welding procedures a) Each main and auxiliary turbine is to be provided with
and using approved consumables. an overspeed protective device to prevent the rotational
speed from exceeding the maximum rotational by more
than 15%. The device is to be actuated by the turbine
2.4 Control, monitoring and shut-off devices shaft.
b) Where two or more steam turbines are coupled to the
2.4.1 Governors same gear wheel, the Society may accept the fitting of
a) Turbines for main propulsion machinery equipped with only one overspeed device for all the coupled turbines.
controllable pitch propellers, disengaging couplings or c) For turbines driving electric generators, the overspeed
electrical transmission systems are to be fitted with an protective device mentioned in a) is also to be fitted
additional speed governor which, in the event of a sud- with a means for manual tripping.
den loss of load, prevents the revolutions from increas- d) Where exhaust steam from auxiliary systems is led to
ing to the trip speed. the main turbine, provision is to be made to cut off the
steam automatically when the overspeed protective
b) The speed increase of turbines driving electric genera- device is activated.
tors -except those for electrical propeller drive- resulting
from a change from full load to no-load may not exceed 2.4.3 Rotor axial displacement
5% on the resumption of steady running conditions. The A quick-closing valve is to be provided which automatically
transient speed increase resulting from a sudden change shuts off the steam supply in the event of axial displacement
from full load to no-load conditions is not to exceed of the rotor beyond the permissible limits stated by the man-
10% and is to be separated by a sufficient margin from ufacturer. The device controlling the valve is to be actuated
the trip speed. by the turbine shaft.
2.4.4 Emergency oil supply rise to significant movements between reduction gears and
turbines. In any event, such movements are to be absorbed
For the emergency lubricating oil supply, see Ch 1, Sec 10,
by suitable couplings.
[12.5].
3.1 Foundations 3.9.1 Main and auxiliary turbines are to be fitted with calli-
pers and micrometers of a suitable type for verifying the
3.1.1 Shipyards and Manufacturers are to take care that alignment of rotors and pinion and gear-wheel shafts.
foundations of turbines and connected reduction gears are This check is to be performed to the Surveyors satisfaction
to be designed and built so that hull movements do not give at the time of installation.
4 Material tests, workshop inspection thermal stability test of rotor (see [4.2.6])
and testing, certification rotor balancing and overspeed test (see [4.2.7] and
[4.2.8])
4.1 Material tests shop trials (see [4.2.9]).
15% above the maximum design speed. 4.3.3 Type approved turbines
For mass produced turbines which are requested to be type
The Society may waive this requirement provided that it can approved by the Society, the tests and trials on a prototype
be demonstrated by the manufacturer, using an acceptable are to be carried out in the presence of the Surveyor as
direct calculation procedure, that the rotor is able to safely stated in [4.3.1]. The minimum required attendance of the
withstand the above values of overspeed and that rotors are Surveyor at the production tests and trials will be agreed
free from defects, as verified by means of non-destructive between the manufacturer and the Society on a case by
tests. case basis.
1.1 Application 1.2.1 Rated power is the maximum constant power that the
turbine can develop at constant speed in the range of air
1.1.1 Propulsion turbines and turbines for essential
inlet temperature between 0C and 35C. This power is to
services
The requirements of this Section apply to: be considered with 0 intake and exhaust losses and with an
air relative humidity of 60%.
a) all propulsion turbines
b) turbines intended for auxiliary services essential for
safety and navigation. 1.3 Documentation to be submitted
1.1.2 Turbines for auxiliary generators
1.3.1 For propulsion turbines and turbines intended for
In addition to the requirements contained in this Section,
auxiliary turbines driving electric generators are to comply driving machinery for essential services, the plans listed in
with the applicable requirements of Ch 3, Sec 3. Tab 1 are to be submitted.
1.1.3 Type approval The listed constructional plans are to be complete with all
Turbines intended for propulsion and essential services are dimensions and are to contain full indication of the types of
to be type approved by the Society. materials used.
2.3.9 Fuel
a) Where the turbine is designed to burn non-distillate
2.5 Control, monitoring and shut-off devices
fuels, a fuel treatment system is to be provided to
remove, as far as practicable, the corrosive constituents 2.5.1 Control and monitoring arrangement
of the fuel or to inhibit their action in accordance with For each main propulsion system, the associated control
the manufacturers specification. and monitoring equipment is to be grouped together at
b) Suitable means are to be provided to remove the depos- each location from which the turbine may be controlled.
its resulting from the burning of the fuel while avoiding
abrasive or corrosive action, if applicable. 2.5.2 Governors and speed control system
c) Gas turbines burning boil-off gases of liquefied gas a) Propulsion turbines which may be operated in no-load
cargo tanks will be specially considered by the Society conditions are to be fitted with a control system capable
taking into account the requirements of Pt D, Ch 9, Sec of limiting the speed to a value not exceeding 10% of
16. the maximum continuous speed.
2.3.10 Start-up equipment b) Turbines for main propulsion machinery equipped with
a) Gas turbines are to be fitted with start-up equipment controllable pitch propellers, disengaging couplings or
enabling them to be started up from the "shutdown" an electrical transmission system are to be fitted with a
condition. speed governor which, in the event of a sudden loss of
b) Provisions are to be made so that any dangerous accu- load, prevents the revolutions from increasing to the trip
mulation of liquid or gaseous fuel inside the turbines is speed.
thoroughly removed before any attempt at starting or c) In addition to the speed governor, turbines driving elec-
restarting. tric generators are to be fitted with a separate overspeed
c) Starting devices are to be so arranged that firing opera- protective device, with a means for manual tripping,
tion is discontinued and the main fuel valve is closed adjusted so as to prevent the rated speed from being
within a pre-determined time when ignition is failed. exceeded by more than 15%.
d) The minimum number of starts is to be such as to satisfy
d) The speed increase of turbines driving electric genera-
the requirements of Ch 1, Sec 1, [1.4.5].
tors - except those for electrical propeller drive - result-
2.3.11 Astern power ing from a change from full load to no-load is not to
For main propulsion machinery with reverse gearing, con- exceed 5% on the resumption of steady running condi-
trollable pitch propellers or an electrical transmission sys- tions. The transient speed increase resulting from a sud-
tem, astern running is not to cause any overloading of the den change from full load to no-load conditions is not
propulsion machinery. to exceed 10% and is to be separated by a sufficient
margin from the trip speed. Alternative requirements
2.3.12 Emergency operation may be considered by the Society on a case by case
a) In installations with more than one propeller and con- basis based on the actual turbine design and arrange-
nected shafting and more than one turbine, the failure of ment.
any gas turbine unit connected to a shafting line is not
to affect the continued, independent operation of the 2.5.3 Monitoring system
remaining units. The main operating parameters (pressure, temperature, rpm,
b) In installations with only one propeller and connected etc.) are to be adequately monitored and displayed at the
shafting, driven by two or more main turbines, care is to control console.
be taken to ensure that, in the event of one of the tur-
bines failing, the others are able to continue operation 2.5.4 Emergency shut-off
independently.
a) An emergency push-button shut-off device is to be pro-
c) Ships classed for unrestricted service and fitted with vided at the control console.
only one propeller and connected shafting driven by a
gas turbine are to be provided with means to ensure b) Any shut-off device provided in pursuance of the above
emergency propulsion in the event of failure of the main is to shut off the fuel supply as near the burners as possi-
turbine. ble.
c) Stage C - Inspection of main turbine components. 2) test at maximum permissible torque (normally 110%
After completion of the test programme, the main turbine of nominal torque T) at 100% speed; or test at maxi-
components are to be inspected. mum permissible power and speed according to the
nominal propeller curve.
The turbine manufacturer is to compile all results and meas-
urements for the turbine tested during the type test in a type 3) tests at partial loads, e.g. 75%, 50%, 25% of maxi-
test report, which is to be submitted to the Society. mum continuous power P and speed according to
the nominal propeller curve.
4.2.2 Stage A - Internal tests (functional tests and b) Additional tests
collection of operating data)
test at lowest turbine speed according to the nomi-
a) During the internal tests the turbine is to be operated at
nal propeller curve
the load points considered important by the turbine
manufacturer and the relevant operating values are to starting tests
be recorded. governor tests
b) The load points may be selected according to the range testing and rating of the safety systems.
of application.
c) Functional tests under normal operating conditions 4.2.4 Evaluation of test results
include: The results of the tests and checks required by Ch 1, Sec 2,
[4.2.3] will be evaluated by the attending Surveyor. Nor-
1) The load points 25%, 50%, 75%, 100% of the rated
mally the main operating data to be recorded during the
power for which type approval is requested, to be
tests are those listed in Ch 1, Sec 2, [4.3.4].
carried out:
along the nominal (theoretical) propeller curve The values of temperatures and pressures of media, such as
and at constant speed, for propulsion turbines cooling media, lubricating oil, exhaust gases, etc., are to be
within limits which, in the opinion of the Surveyor, are
at constant speed, for turbines intended for gen- appropriate for the characteristics of the turbine tested.
erating sets.
2) The limit points of the permissible operating range. 4.2.5 Stage C - Inspection of turbine components
These limit points are to be defined by the turbine Immediately after the test run as per Ch 1, Sec 2, [4.2.3], a
manufacturer. selected number of components agreed between the manu-
facturer and the Society are to be presented for inspection
d) An alternative testing program may be agreed between to the Surveyor.
the manufacturer and the Society on a case by case
basis.
4.3 Type tests of turbines admitted to an
4.2.3 Stage B - Type approval tests in the presence alternative inspection scheme
of the Surveyor
During the type test, the tests listed below are to be carried 4.3.1 General
out in the presence of the Surveyor and the results are to be Turbines admitted to testing and inspections according to
recorded in a report signed by both the turbine manufac- an alternative inspection scheme (see NR216 Materials and
turer and the Surveyor. Welding, Ch 1, Sec 1, [3.2]) are to be type tested in the
Any departures from this programme are to be agreed upon presence of the Surveyor in accordance with the following
by the manufacturer and the Society. requirements.
a) Load points The selection of the turbine to be tested from the production
line is to be agreed upon with the Surveyor.
The load points at which the turbine is to be operated
according to the power/speed diagram are those listed 4.3.2 Type test
below. The data to be measured and recorded when
testing the turbine at various load points are to include The programme of the type test is to be in general as speci-
all necessary parameters for turbine operation. fied below, P being the rated power and n the correspond-
ing speed.
The operating time per load point depends on the tur-
bine characteristics (achievement of steady-state condi- Any departures from this programme are to be agreed upon
tion) and the time for collection of the operating values. by the manufacturer and the Society.
Normally, an operating time of 0,5 hour per load point a) 6 hours at full power
can be assumed. b) 10 hours shared at different partial loads (25%, 50%,
At the maximum continuous power as per the following 75% and 90% of power P);
item (1) an operating time of two hours is required. Two
c) 2 hours at intermittent loads
sets of readings are to be taken at a minimum interval of
one hour. d) starting tests
1) test at maximum continuous power P: i.e. 100% e) testing of speed governor, overspeed device and lubri-
output at 100% torque and 100% speed. cating oil system failure alarm device
f) testing of the minimum speed along the nominal (theoret- c) characteristics of the fuel and lubricating oil used during
ical) propeller curve, for main propulsion turbines driving the test
fixed pitch propellers, and of the minimum speed with no
d) turbine speed
brake load, for main propulsion turbines driving control-
lable pitch propellers or for auxiliary turbines. e) brake power
The tests at the above-mentioned outputs are to be com- f) brake torque
bined together in working cycles which are to be repeated
g) intake and exhaust losses
in succession for the entire duration within the limits indi-
cated. h) lubricating oil pressure and temperature
In particular, the full power test is to be carried out at the i) exhaust gas temperature in locations of the flow gas
end of each cycle. path selected by the manufacturer
The partial load tests specified in (b) are to be carried out: j) minimum starting air pressure and flow rate necessary to
purge and start the turbine in cold condition, if applica-
along the nominal (theoretical) propeller curve and at ble.
constant speed, for propulsion turbines
4.3.5 Inspection of main turbine components and
at constant speed, for turbines intended for generating evaluation of test results
sets.
The provisions of Ch 1, Sec 2, [4.2.4] and Ch 1, Sec 2,
In the case of prototype turbines, the duration and pro- [4.2.5] are to be complied with, as far as applicable.
gramme of the type test will be specially considered by the
Society. 4.4 Material tests
4.3.3 Alternatives 4.4.1 The materials for the construction of the parts listed in
Tab 3 are to be tested in compliance with the requirements
In cases of turbines for which the manufacturer submits
of NR216 Materials and Welding.
documentary evidence proving successful service experi-
ence or results of previous bench tests, the Society may, at Magnetic particle or liquid penetrant tests are required for
its discretion, allow a type test to be carried out, in the pres- the parts listed in Tab 3 and are to be effected by the Manu-
ence of the Surveyor according to a programme to be facturer in positions agreed upon by the Surveyor, where
agreed upon in each instance. Manufacturers experience shows defects are most likely to
occur.
4.3.4 Data to be recorded For important structural parts of the turbine, in addition to
During the type test, at least the following particulars are to the above-mentioned non-destructive tests, examination of
be recorded: welded seams by approved methods of inspection may be
required.
a) ambient air temperature, pressure and atmospheric
humidity in the test room Where there are grounds to doubt the soundness of any tur-
bine component, non-destructive tests using approved
b) cooling medium temperature at the inlet of the turbine detecting methods may be required.
4.5 Inspections and testing during con- 4.5.5 Overspeed test of rotors
struction Finished rotors, complete with all fittings and blades, are to
be subjected for at least 3 minutes to an overspeed test at
the greater of the following values:
4.5.1 Inspections during construction
5% above the setting speed of the overspeed tripping
The following inspections and tests are to be carried out in device
the presence of a Surveyor during the construction of all tur- 15% above the maximum design speed.
bines which are indicated in [1.1.1]. For on-board trials see
The Society may waive this requirement provided that it can
Ch 1, Sec 15, [3.8]. be demonstrated by the manufacturer, using an acceptable
Material tests as required (see Ch 1, Sec 4, [4.1]) direct calculation procedure, that the rotor is able to safely
withstand the above overspeed values and that rotors are
Welding fabrication (see [4.5.2]) free from defects, as verified by means of non-destructive
tests.
Hydrostatic tests (see [4.5.3])
4.5.6 Shop trials
Rotor balancing and overspeed test (see [4.5.4] and For shop trials, see [4.2.3] and [4.3.2].
[4.5.5])
SECTION 6 GEARING
1 General methods for the design of bevel gears could be taken into
consideration by the Society.
1.1 Application Additional requirements for gears fitted to ships having an
ice notation are given in Part E, Chapter 8.
1.1.1 Unless otherwise specified, the requirements of this
Section apply to:
1.2 Documentation to be submitted
reduction and/or reverse gears intended for propulsion
plants with a transmitted power of 220 kW and above
1.2.1 Documents
other reduction and step-up gears with a transmitted
Before starting construction, all plans, specifications and cal-
power of 110 kW and above.
culations listed in Tab 1 are to be submitted to the Society.
The provisions of Article [2] apply only to cylindrical invo-
lute spur or helical gears with external or internal teeth. 1.2.2 Data
The provisions of Article [4] apply only to bevel gears The data listed in Tab 2 or Tab 3 and in Tab 4 are to be sub-
(straight or oblique teeth). Application of other specific mitted with the documents required in [1.2.1].
Values
Symbol Unit Description
Pinion Wheel
a mm Operating centre distance
bB mm Common face width (for double helix gear, width of one helix)
Q - Gearing quality class according to ISO 1328-1 1997
bS mm Web thickness
sR mm Rim thickness
Rm,rim N/mm 2 Ultimate tensile strength of the rim material
B mm Total face width of double helix gears, including gap
ds mm Shrinkage diameter
mn mm Normal module
n deg or rad Normal pressure angle at reference cylinder
deg or rad Helix angle at reference cylinder
x - Addendum modification coefficient
z - Number of teeth
P kW Transmitted power
n rpm Rotational speed
da mm Tip diameter
a0 mm Tip radius of the tool
hfp mm Basic rack dedendum
HRC - Rockwell hardness
RZf m Mean peak-to-valley flank roughness of the gear pair
RZ m Mean peak-to-valley roughness of the gear pair
Re,s N/mm 2 Minimum yield strength of the shaft material
40 mm /s 2 Nominal kinematic viscosity of oil at 40C
pr mm Protuberance of the tool
q mm Material allowance for finish machining
dext mm External shaft diameter
dint mm Internal shaft diameter
mm Bearing span
ZE 1/2
N /mm Elasticity factor
Values
Symbol Unit Description
Pinion Wheel
Q - Gearing quality class according to ISO 1328-1 1997
sR mm Rim thickness
ds mm Shrinkage diameter
b mm Common face width (for double helix gear width of one helix)
mmn mm Mean normal module
n deg or rad Normal pressure angle
m deg or rad Mean helix angle
z - Actual number of teeth
deg or rad Pitch angle
Values
Symbol Unit Description
Pinion Wheel
xh - Addendum modification coefficient
xs - Thickness modification coefficient
haP mm Addendum of the basic rack tooth profile
hfP mm Dedendum of the basic rack tooth profile
a0 mm Cutter edge radius
rc0 mm Cutter radius
P kW Transmitted power
n rpm Rotational speed
HRC - Rockwell hardness
RZf m Mean peak-to-valley flank roughness of the gear pair
RZ m Mean peak-to-valley roughness of the gear pair
Re,s N/mm 2 Minimum yield strength of the shaft material
40 mm /s 2 Nominal kinematic viscosity of oil at 40C
pr mm Protuberance of the tool
q mm Material allowance for finish machining
dext mm External shaft diameter
dint mm Internal shaft diameter
mm Bearing span
ZE 1/2
N /mm Elasticity factor
Machining
No modification
Central crowning fma
Central crowning fma + fsh
Helix correction
Helix correction + crowning
End relief
Maximum base pitch deviation of the wheel
With optimum profile correction
Material Pinion Wheel
St Wrought normalized low carbon steels
Normalized low carbon steels / cast steels
St (Cast) Cast steels
GTS (Perl.) Black malleable cast iron (perlitic structure)
GGG (Perl.) Nodular cast iron (perlitic structure)
GGG (Bai.) Cast iron materials Nodular cast iron (bainitic structure)
GGG (ferr.) Nodular cast iron (ferritic structure)
GG Grey cast iron
V Through-hardened wrought steels Carbon steels, alloy steels
V (cast) Through-hardened cast steels Carbon steels, alloy steels
Eh Case-hardened wrought steels
IF Flame or induction hardened wrought or cast steels
NT (nitr.) Nitrided wrought steels/nitrided steels Nitriding steels
NV (nitr.) /nitrided through-hardening steels Through-hardening steels
NV (nitrocar.) Wrought steels, nitrocarburized Through-hardening steels
(1) A quill shaft is a torsionally flexible shaft intended to improve the load distribution between the gears.
Re,s : Minimum yield strength of the shaft material, in For internal gear, z2, a, d2, da2, db2, x2 and dw2 are to be
N/mm2 taken negative.
RZ : Mean peak-to-valley roughness of the gear pair, z
in m u = -----2
z1
RZf : Mean peak-to-valley flank roughness of the gear Note 1: u > 0 for external gears, u < 0 for internal gears.
pair, in m
tan
sR : Rim thickness, in mm tan t = ---------------n
cos
T : Transmitted torque, in kN.m
zi mn
d i = ---------------
u : Reduction ratio cos
v : Linear velocity at pitch diameter, in m/s d bi = d i cos t
x : Addendum modification coefficient
2a
d w1 = -------------
z : Number of teeth 1+u
zn : Virtual number of teeth 2au
d w2 = ------------------
a : Transverse profile angle at tooth tip 1+u
Subscripts: n1 d1
The cylindrical gears for marine application are to com- Table 6 : Load sharing factor K
ply with the following restrictions:
Type of gear K
1,2 < < 2,5
Dual tandem without quill shaft (1) 1,15
< 30 gear
with quill shaft (1) 1,10
sR > 3,5 mn Epicyclic with 3 planetary gears and less 1,00
gear
The relevant formulae are provided in [2.4] and [2.5]. with 4 planetary gears 1,20
with 5 planetary gears 1,30
The influence factors common to the formulae are given
in [2.3]. with 6 planetary gears and more 1,40
(1) A quill shaft is a torsionally flexible shaft intended to
b) Gears, for which the conditions of validity of some fac- improve the load distribution between the gears.
tors or formulae are not satisfied, will be given special
consideration by the Society.
2.3.4 Dynamic factor KV (method B)
c) Other methods of determination of load capacity will be The dynamic factor KV accounts for the additional internal
given special consideration by the Society. Any alterna- dynamic loads acting on the tooth flanks and due to the
tive calculations are to comply with the international vibrations of the pinion and the wheel.
standards ISO 6336.
The calculation of the dynamic factor KV is defined in Tab 7,
where:
2.3 General influence factors N : Resonance ratio, i.e. ratio of the pinion speed to
the resonance speed:
2.3.1 General
N = n1 / nE1, with:
General influence factors are defined in [2.3.2], [2.3.3], nE1 : Resonance speed, in rpm, defined
[2.3.4], [2.3.5] and [2.3.6]. Alternative values may be used by the following formula:
provided they are derived from appropriate measurements.
30000 c
n E1 = ---------------- ---------
-
2.3.2 Application factor KA z 1 m red
The load sharing factor K accounts for the uneven sharing Ns = 0,85
of load on multiple path transmissions, such as epicyclic if Ft KA / b < 100 N/mm:
gears or tandem gears.
Ft KA
N s = 0,5 + 0,35 -------------
The values of K are given in Tab 6. 100b
Note 1:
BP : Non-dimensional parameter taking into account the effect of tooth deviations and profile modifications:
c f pb, eff
B P = --------------------------
-
KA ( Ft b )
with:
c : Single stiffness defined in Tab 9
fpb,eff : Effective base pitch deviation, in m, equal to: fpb,eff = fpb y
with fpb defined in Tab 14 and y defined in Tab 15
Bf : Non-dimensional parameter taking into account the effect of tooth deviations and profile modifications:
Bf = BP
Bk : Non-dimensional parameter taking into account the effect of tooth deviations and profile modifications:
c C a
B k = 1 ---------------------
-
KA Ft b
with:
Hlim 2
C a = ------ -----------
- ( 18,45 ) + 1,5
1
18 97
When material of the pinion is different from that of the wheel: Ca = 0,5 (Ca1 + Ca2)
Cv1 : Factor for pitch deviation effects: Cv1 = 0,32
Cv2 : Factor for tooth profile deviation effects:
if 1 < 2 : Cv2 = 0,34
if 2 < : Cv2 = 0,57 / ( 0,3)
Cv3 : Factor for cyclic variation effect in mesh stiffness:
if 1 < 2 : Cv3 = 0,23
if 2 < : Cv3 = 0,096 / ( 1,56)
Cv5 : Factor: Cv5 = 0,47
Cv6 : Factor:
if 1 < 2 : Cv6 = 0,47
if 2 < : Cv6 = 0,12 / ( 1,74)
Cv7 : Factor:
if 1 < 1,5 : Cv7 = 0,75
if 1,5 < 2,5 : Cv7 = 0,125 sin[ ( 2)] + 0,875
if 2,5 < : Cv7 = 1
2
d a1 + d f1 2 ( d f1 + d a1 )
2 ( d fi 2 s Ri ) m red = --- --------------------
- -----------------------------------------------------------------------------------------
-
sRi 0 q i = -------------------------------------
- 8 2d b1 1 1
d fi + d ai 4 -----------------------------
4
+ ---------------------------------------
4
-
2
( 1 q1 ) 1 ( 1 q2 ) 2 u
Note 1:
i is the density of gearing material ( = 7,83 106 for steel)