I) Status
II) Critical Areas & Action (Identifying the Responsibility and Time Frame)#
2) Procurement - .
3) Quality Related Issues
Page 1 of 3
Updates on progress and status by next meeting.
@ Foundry
Cooling time
Heat Treatment
Mechanical Testing
Radiography
Magnetic Particle Inspection
Despatch to MIL C,Mala.
@ MIL C
Machining
Die penetration tests
Pressure Tests
Assembly and Checks
Ultra sonic tests for forgings.
@ the foundry for Inspection of heat treatment and test procedures require the presence of QA reps from;
L&T,MIL C & NPCL thus the coordination and presence gets delayed.
As per discussion with MIL it is estimated that it takes between 30 to 45 days of pouring to receive the rough
components into MIL factory after all procedures, tests and clearances.
Page 2 of 3
Please find attached a folder comprising of;
Pouring details as on 15/8/16 at Sanmar ,Trichy.
(This will be updated with latest during next visit.)
MIL shall provide status on plugs & cages (trimmings) and seat ring forgings during our next visit
planned for 25th Thursday.
Page 3 of 3