Sei sulla pagina 1di 13

w a t e r r e s e a r c h 4 5 ( 2 0 1 1 ) 2 4 1 e2 5 3

Available at www.sciencedirect.com

journal homepage: www.elsevier.com/locate/watres

Cost-effectiveness analysis of risk-reduction measures to


reach water safety targets

Andreas Lindhe a,*, Lars Rosen a, Tommy Norberg b, Olof Bergstedt a,c,
Thomas J.R. Pettersson a
a
Department of Civil and Environmental Engineering, Chalmers University of Technology, SE-412 96 Gothenburg, Sweden
b
Department of Mathematical Sciences, University of Gothenburg and Chalmers University of Technology, SE-412 96 Gothenburg, Sweden
c
Goteborg Vatten, Box 123, SE-424 23 Angered, Sweden

article info abstract

Article history: Identifying the most suitable risk-reduction measures in drinking water systems requires
Received 1 March 2010 a thorough analysis of possible alternatives. In addition to the effects on the risk level, also
Received in revised form the economic aspects of the risk-reduction alternatives are commonly considered impor-
20 May 2010 tant. Drinking water supplies are complex systems and to avoid sub-optimisation of
Accepted 16 July 2010 risk-reduction measures, the entire system from source to tap needs to be considered.
Available online 3 August 2010 There is a lack of methods for quantification of water supply risk reduction in an economic
context for entire drinking water systems. The aim of this paper is to present a novel
Keywords: approach for risk assessment in combination with economic analysis to evaluate
Risk reduction risk-reduction measures based on a source-to-tap approach. The approach combines
Fault tree analysis a probabilistic and dynamic fault tree method with cost-effectiveness analysis (CEA). The
Cost-effectiveness developed approach comprises the following main parts: (1) quantification of risk reduc-
Decision support tion of alternatives using a probabilistic fault tree model of the entire system; (2) combi-
Water safety plan nation of the modelling results with CEA; and (3) evaluation of the alternatives with respect
to the risk reduction, the probability of not reaching water safety targets and the
cost-effectiveness. The fault tree method and CEA enable comparison of risk-reduction
measures in the same quantitative unit and consider costs and uncertainties. The
approach provides a structured and thorough analysis of risk-reduction measures that
facilitates transparency and long-term planning of drinking water systems in order to
avoid sub-optimisation of available resources for risk reduction.
2010 Elsevier Ltd. All rights reserved.

1. Introduction When analysing risks to a drinking water supply, the entire


system needs to be considered to avoid overlooking important
Risk management of drinking water systems is becoming interactions between sub-systems and components. The
increasingly important worldwide. A safe and reliable World Health Organisation (WHO, 2008) thus concludes that
drinking water supply is vital for public health as well as for a holistic risk management approach, including the entire
economic development and other societal functions. Effi- system from catchment to consumer, is necessary to guar-
cient risk management of drinking water systems requires antee safe drinking water to consumers. Bartram et al. (2009),
a thorough evaluation of risk acceptance and identification the WHO (2008), Davison et al. (2005) and many others advo-
of the most suitable measures to reduce unacceptable risks. cate the preparation of Water Safety Plans (WSPs), in which

* Corresponding author. Tel.: 46 31 772 20 60; fax: 46 31 772 21 07.


E-mail address: andreas.lindhe@chalmers.se (A. Lindhe).
0043-1354/$ e see front matter 2010 Elsevier Ltd. All rights reserved.
doi:10.1016/j.watres.2010.07.048
242 w a t e r r e s e a r c h 4 5 ( 2 0 1 1 ) 2 4 1 e2 5 3

risks in source waters, treatment systems and distribution Gothenburg, Sweden. The risk associated with each of the
networks should be assessed and managed in an integrated, seven alternatives was compared to a politically established
from source to tap, manner. water safety target.
Implementation of WSPs requires relevant decision
support regarding how to manage existing risks. Since
drinking water systems are diverse and are exposed to a wide 2. Method
variety of risks, one single method or tool cannot be used
universally. A number of strategies and methods for risk In order to evaluate and compare risk-reduction measures, fault
assessment and risk management in drinking water supplies tree analysis was combined with cost-effectiveness analysis.
have been described, see e.g. MacGillivray et al. (2006), Rosen For each measure, a fault tree model was constructed to repre-
et al. (2007) and Pollard (2008). sent the entire water supply system structure. The set of fault
The WHO (2008) suggests that risk assessment in WSPs is tree models provided information on the alternatives effect on
made by ranking of hazards using a risk matrix (see also the risk level. A politically established water safety target was
Bartram et al., 2009; Davison et al., 2005). This type of quali- used to define an acceptable level of risk. Information on costs
tative (or semi-quantitative) method may be useful but have was obtained from an economic analysis and the cost-effec-
several limitations (e.g. Burgman, 2005; Cox, 2008). Risk tiveness of each alternative was calculated. To further evaluate
ranking methods can only in a limited way consider complex the alternatives, simplified cost-benefit calculations were con-
systems with interactions between components. Risk ranking ducted. The different parts of the applied method are presented
methods also assume a discrete nature of hazards, cannot in the subsequent sections.
provide quantitative estimates that can be compared with
performance targets, and typically lack procedures for sensi- 2.1. Conceptual model
tivity and uncertainty analysis. As an alternative to risk
ranking methods, Lindhe et al. (2009) presented a quantitative Drinking water systems are composed of a set of sub-systems
fault tree method for analysing entire drinking water systems. and components, e.g. raw water source, treatment plant and
In a risk evaluation and risk management context, this distribution system. Since these are interconnected, it is
method makes it possible to compare the risk level to important to have a conceptual understanding of how failure
acceptable levels in absolute terms and to estimate the effect events may occur, interact and finally cause problems to the
of risk-reduction measures quantitatively. consumers. Two important types of supply failure that may
The primary aims of this paper were to apply the fault tree affect the consumers are: (1) quantity failure, i.e. no water is
method presented by Lindhe et al. (2009) to model alternative delivered to the consumer; and (2) quality failure, i.e. water is
risk-reduction measures and to combine the results with delivered but it does not comply with quality standards
a cost-effectiveness analysis to provide decision support. (Fig. 1). The applied method can be used to model both types of
Economic resources are often limited and economic evalua- failure but in this paper only quantity failure was considered,
tion of measures is therefore an important part of the deci- i.e. the upper branch in Fig. 1.
sion-basis, see e.g. Levin and McEwan (2001) and Nas (1996). The causes of quantity failure may vary but were here cat-
Simplified cost-benefit calculations were also conducted to egorised into two main types (Fig. 1). Technical components in
allow for a broader economic analysis. Benefits and limita- the system, e.g. pumps or pipes, may break down and interrupt
tions with the applied approach were identified to evaluate the supply of water. Also quality-related events may occur that
the added value of combining quantitative risk assessment cause an unacceptable water quality (raw water or drinking
and economic evaluation. Seven alternative risk-reduction water) and if this is detected the water utility may decide to
measures were analysed for the drinking water system in stop the delivery of water. Consequently, when modelling

Categories of supply failure Causes

Failure of components in the


Quantity failure (Q = 0) system (e.g. pumps or pipes)
No water is delivered to the
co nsum er Events related to unacceptable
water quality causing the water
utility to stop the delivery
Supp l y fa ilur e
Unacceptable water quality is
Quality failure (Q > 0, C) detected but no action is taken or
Water is delivered but does it is not possible to stop the delivery
not comply with water quality Unacceptable water quality is not
standards detected and no action is thus
possible
Q = Flow (Q = 0, no water is delivered to the consumer; Q > 0, water is delivered)
C = The drinking water does not comply with water quality standards

Fig. 1 e Categories of supply failure and their main causes (Lindhe et al., 2009).
w a t e r r e s e a r c h 4 5 ( 2 0 1 1 ) 2 4 1 e2 5 3 243

quantity failure in this paper, both failures of technical probability of failure is PF l/(l m). The probability of failure is
components and the quality-related failures were included. here identified with the probability that the system is down.
To model the drinking water system, a supply chain was This probability is typically time-dependent. However, in an
considered including the raw water sources, treatment plants ergodic system, it will tend to l/(l m) in the long run as time
and the distribution system. These sub-systems interact and approaches infinity. In reliability theory, the latter is often
failure in one part may be compensated for by other parts. For referred to as the unavailability of the system.
example, if the treatment plant fails to produce drinking The main reasons for using the failure rate (or mean
water, reservoirs in the distribution system and increased uptime) and mean downtime instead of direct estimations of
production at an additional treatment plant may prevent the probability of failure, was to facilitate relevant elicitation
quantity failure. However, the ability to compensate is limited of expert judgements and enable modelling of the systems
in time, due to limited reservoir volume. In some cases the dynamic behaviour. Information on probability of failure as
ability to compensate may not exist at all. well as failure rate and downtime can be calculated for each
event in the fault tree.
2.2. Fault tree analysis The two most common types of logic gates are the OR- and
AND-gates. The OR-gate describes a system where the
The fault tree method used here was developed to facilitate occurrence of one input event causes system failure. The
integrated and probabilistic risk analysis of entire drinking AND-gate describes a system where all input events have to
water systems, see Lindhe et al. (2009). A fault tree is a logic occur simultaneously to cause the system to fail. To be able to
diagram illustrating potential causes of system failure and consider the inherent ability of a system to compensate for
particularly how different events may interact to cause failure, Norberg et al. (2009) and Lindhe et al. (2009) formulated
system failure (e.g. Bedford and Cooke, 2001). The top event in two variants of the common type AND-gate. The first variant
the tree represents the critical system failure, in this case describes a situation where failure of one component may be
quantity-related supply failure. This event is further devel- compensated for by one or several other components during
oped until a required level of detail is reached. At the lowest a limited period. The second variant is similar to the first one,
level of the tree the basic events are found, where input data but with the addition that a compensating component that
are required. The capability of representing interactions has failed may recover and start to compensate again. Equa-
between critical system components makes fault tree models tions for calculating the probability of failure, failure rate and
powerful for analysis of entire drinking water systems. mean downtime at each intermediate level of the fault tree,
Traditionally, fault trees are used to calculate the probability are given in Table 1. Here, qi denotes the probability of failure
of system failure. The applied method also enables calculation on demand where compensating component i fails to start
of the risk level, see Section 2.3. A Markovian approach was compensating when needed, e.g. a reserve pump that cannot
used (Norberg et al., 2009) to represent the dynamic, i.e. time- be started when the main pump brakes down.
dependent, behaviour of the events (Rausand and Hyland, A schematic fault tree illustrating the basic structure of the
2004). Thus, variables failure rate l and mean downtime models used in this paper is shown in Fig. 2. Note that the top
(duration of failure) 1/m were used to define each basic event in event, supply failure, in the fault tree in Fig. 2 includes quantity
the model. The mean time to failure (uptime) is 1/l, hence the as well as quality failures, but in this study only quantity

Table 1 e Equations for calculating the output of the logic gates (Norberg et al., 2009). PF denotes the probability of failure, l
the mean failure rate and 1/m the mean downtime. For the variants of the AND-gate i [ 1 corresponds to the failure event
that may be compensated for by events i [ 2, ., n. For the second variant only one compensating event is considered, i [ 2.
OR-gate AND-gate
X
n X
n
l li m mi
i1 i1

Q
n Q
n
mi li
X
n X
n
i1
m li $ i1 l mi $
Q
n Q
n Q
n Q
n
i1 li mi  li
i1 li mi  mi i1 i1
i1 i1

l Yn
mi Y
n
PF 1 l li
lm l mi PF
i1 i l m i1 li mi

First variant of AND-gate Second variant of AND-gate

m m1 l1 l2 q2 m1 m2
PF $
l1 m 1 l2 m 1 m 2
l1 Y
n
li qi m 1
PF $
l1 m1 i2 li m1 m1 l1 q2 l2 m1 m2 l1 l2 1  q2 m1 m2
l
l1 m1 l2 m1 m2 1  PF
PF
l $m m1 l1 q2 l2 m1 m2 l1 l2 1  q2 m1 m2
1  PF m
l1 m1 l2 m1 m2 PF
244 w a t e r r e s e a r c h 4 5 ( 2 0 1 1 ) 2 4 1 e2 5 3

Supply failure

Raw water failure Treatment failure Distribution failure

Raw water quantity Treatment quantity Distribution quantity


failure (Q = 0) failure (Q = 0) failure (Q = 0)

Distribution quality
failure (Q > 0, C')
Quantity failure Quantity failure

Treatment fails to Distribution fails to


compensate compensate

Distribution fails to Treament quality


compensate failure (Q > 0, C')

Raw water quality


failure (Q > 0, C')
Quality failure

Distribution fails to
Quality failure
compensate

Treatment fails to
compensate OR-gate
First variant of AND-gate
Distribution fails to Q = flow (Q = 0, no water is delivered to the consumer; Q > 0 water is delivered)
compensate C' = The drinking water does not comply with water quality standards

Fig. 2 e Schematic fault tree including the main events that can be considered using the method (Lindhe, 2008).

failures were analysed (see Section 2.1). The fault tree models calculations were performed by Monte Carlo simulations
used in this study included approximately 120 basic events (10,000 iterations), see Section 4.3. The exponential rates l and
and about 100 logic gates. m were modelled by Gamma densities. The proportion of
consumers affected (CF) and the probability of failure on
demand (q) were modelled by Beta densities. The Gamma and
2.3. Risk expressed as Customer Minutes Lost (CML)
Beta distributions facilitate a Bayesian approach, where new
information, e.g. monitoring data, can be used for a mathe-
The risk (R) was estimated in terms of Customer Minutes Lost
matically formal updating of previous knowledge. The Monte
(CML). In this application CML corresponds to the number of
Carlo simulations facilitate two important types of analyses:
minutes per year the average consumer is not supplied with
(1) sensitivity analysis of contributions to the total uncertainty
drinking water. Risk was defined as the estimated value of
from uncertainties in basic events; and (2) analysis of the
CML, which is equal to the calculated mean value.
probability of not meeting established safety targets.
A comprehensive description of the risk measure CML is
presented by Lindhe et al. (2009). This measure has been used
in, for example, the Netherlands as a performance indicator 2.5. Modelling risk reduction
within the water industry and is commonly used in the energy
sector (Blokker et al., 2005). It can be shown that the risk As a basis for this work an existing fault tree model of the
should be calculated as R PF$CF, where PF is the probability of drinking water system in Gothenburg was used (Lindhe, 2008;
failure and CF is the proportion of all consumers affected Lindhe et al., 2008). The existing model was reconstructed and
(Lindhe et al., 2009). The consequence, i.e. proportion of all updated in order to represent the system with the risk-
consumers affected, was defined for n events in the fault tree reduction measures implemented. Changes were made with
where the top event was divided into well-defined categories respect to: (1) fault tree structure, i.e. events and logic gates
of events. Consequently, the total risk was calculated as were added and/or removed; (2) input data, i.e. new input data
X
n representing the situation as if measures have been imple-
R PFk CFk (1) mented. The effect of each measure (Ej), i.e. the achieved risk
k1
reduction measured in CML units, was calculated as
2.4. Uncertainties
Ej R0  Rj (2)

To enable uncertainty analysis all input parameters were where R0 is the risk level prior to any measures and Rj is
expressed as probability density functions and the the residual risk after alternative j has been implemented.
w a t e r r e s e a r c h 4 5 ( 2 0 1 1 ) 2 4 1 e2 5 3 245

The risk levels R0 and Rj were calculated according to discount rate (3%). A positive net benefit implies that the
Equation (1). alternative is desirable. In this application a simplified CBA
was performed and the only benefit included in the calcula-
tions was the alternatives effect on the risk level (Ej). Conse-
2.6. Cost-effectiveness analysis
quently, the benefit was calculated as
Cost-effectiveness analysis (CEA) can be described as a tool to  
Bjt Ej cn R0  Rj cn (6)
identify what alternative meets a specified target to the lowest
cost (e.g. Levin and McEwan, 2001). However, a CEA may also where R0 is the risk level prior to any measures, Rj is the
provide additional information that can be used in the deci- residual risk for alternative j, c is the economic value of 1 min
sion-making process. The main purpose of CEA is to provide additional water supply per year and consumer and n is the
a combined, not separate, and proper assessment of both the total number of consumers. The value of c thus represents the
costs and the effects. The fault tree models were used to cost an average consumer is willing to pay per year to reduce
estimate the effect of the measures (Ej). To estimate the total the time of interruption by 1 min, i.e. one CML, per year. In
cost of each alternative, possible costs for planning, con- a complete CBA the objective function (Fj) represents the net
structing and maintenance were identified and assessed. present benefit value expressed in monetary units. In this
Costs were assessed considering similar actions within other application, only the change in risk level was considered as
projects. All alternatives were analysed based on a 100 year a benefit. No consideration was taken to when in time this
time horizon (T) and since costs (Cjt) occur over several years, change occurs. Furthermore, the benefit was not valued in
the present value (Cj) was calculated according to Equation (3). monetary units, i.e. the value of c was not determined.
Recommendations regarding discount rates to be used in Instead, the objective function was plotted as a function of c,
economic analyses vary. Stern (2007) advocates a discount i.e. Fj(c). This illustrates how the economic valuation of the
rate of 1.4% for analyses linked to climate changes and the effect may affect the selection of alternatives and clearly
Swedish Environmental Protection Agency (Lindstedt et al., shows break-even points of different alternatives.
2003) recommends a rate of 4% to be used when assessing
environmental consequences. In this study a discount rate (r)
of 3% was used. A sensitivity analysis of the discount rate was 3. Case study site
also performed.

X
T 3.1. System description
Cjt
Cj t1
(3)
t1 1 r
The drinking water system in Gothenburg, Sweden, was used
A cost-effectiveness ratio (CER) was calculated for each to exemplify method application. The supply system is based
alternative. The ratio corresponds to the cost required to solely on surface water, includes two treatment plants, and
obtain a single unit of effect, i.e. reduction of one CML. The has approximately 500,000 consumers. A schematic descrip-
effect (Ej) was calculated according to Equation (2) and was tion of the raw water system in Gothenburg is given in Fig. 3.
assumed to be constant over time. Therefore, the yearly effect The main raw water source is the Gota Alv River. In addition,
did not need to be discounted or summed up over the chosen two smaller interconnected lakes (main reservoir lakes in Fig. 3)
time horizon in order to provide the correct relation between are used for intermediate storage of water and to improve the
the final CER values of the alternatives. The calculation of CER water quality. Approximately half of the water taken from the
could therefore be simplified to Equation (4). For a discussion river is transferred directly to treatment plant no 1. The other
regarding discounting effects in a CEA, when the effect is not half is transferred via a 12 km rock tunnel to the main reser-
constant over time, see e.g. Ramsey et al. (2005) and Brouwer voir lakes. From the main reservoir lakes, water is pumped to
and Koopmanschap (2000). treatment plant no 2. Due to the variable quality of the river
water, the intake is closed 100 days a year on average (e.g.
Cj Astrom et al., 2007). Decisions to close the intake are based on
CERj (4)
Ej online monitoring and reports from operating bodies
upstream, e.g. industries and municipalities.
2.7. Cost-benefit analysis When the intake from the river is closed, the main reser-
voir lakes supply both treatment plants. During long periods
For assessing whether an action is societally beneficial, a cost- (weeks) of closure of the intake, water from a reservoir in an
benefit analysis (CBA) can be conducted. In contrast to CEA, additional raw water supply system (lower additional reservoir
CBA aims to determine the cost as well as the effect and other in Fig. 3) can be pumped to the main reservoir lakes or directly
benefits in monetary units (e.g. Johansson, 1993; Nas, 1996). to treatment plant no 2. However, the situation where treat-
The result of a CBA may be presented as ment plant no 1 has no alternative raw water supply of its own
makes the system vulnerable.
X
T
1  
Fj t1
Bjt  Cjt (5)
t1 1 r
3.2. Acceptable risk
where Fj is an objective function representing the net benefit
of alternative j, Bjt and Cjt are the streams of benefits and costs The City of Gothenburg has defined quantitative water safety
over time, T is the time horizon (100 years) and r is the targets as a basis for long-term planning of investments and
246 w a t e r r e s e a r c h 4 5 ( 2 0 1 1 ) 2 4 1 e2 5 3

Supply from large lake,


Existing water source / reservoir
alternative 3
Possible future water source Supply from small
lakes, alternative 2
Water treatment plant
Raw water distribution
Upper additional
Possible future raw water
distribution reservoir

Watercourse

ce
Main reservoir lakes

ur
so
er
at
w
w
ra
n
ai
M

Lower additional
Water treatment Water treatment reservoir
plant no 1 plant no 2

Fig. 3 e Schematic description of the Gothenburg raw water system. Possible future raw water supplies included in the
analysis are further described in Section 3.4.

reinvestments (Goteborg Vatten, 2006). These targets were 3.4.1. Alt. 1: increased treatment capacity
compiled and suggested by the water utility organisation and The treatment capacity is increased at both treatment plants
then decided by the politicians in the city. Hence, the targets so that each plant manages to produce up to the average
are confirmed at the political level and can be considered as total water demand. Consequently, each plant will get an
acceptable levels of risk. The target used in this analysis is: enhanced ability to compensate for shortage in raw water
Duration of interruption in delivery to the average consumer shall, supply and failures in the other treatment plant. To model
irrespective of the reason, be less than a total of 10 days in 100 years. the increased treatment capacity, no additional events or
For the average consumer this translates to a target value of changes in the fault tree structure were needed. However,
144 annual CML. the input data was changed for four events describing the
plants ability to compensate for failure. Also the conse-
3.3. Current situation quences for four events were changed. Based on statistical
data on water demand and estimations regarding the reli-
Previous risk analyses have shown high probability of inter- ability of the treatment plants, the time for compensation
ruption in the supply to one of the two treatment plants due to (i.e. time to failure or uptime, 1/l) was estimated to 3e120
failures in the raw water system (Lindhe, 2008; Lindhe et al., days (90%-interval). The probability of failure on demand
2008; Rosen and Steier, 2006). The maximum capacity of was estimated to 0.0025e0.01 (90%-interval). The increased
each plant is far below the average demand of the city and treatment capacity may also reduce the number of
drinking water storage is well below the daily need. An addi- consumers affected when a failure occurs. Thus, the number
tional analysis of the dominating failure scenario showed that of people affected were estimated to 6,500e33,900 (90%-
increased treatment capacity would reduce the risk of exten- interval) for four events.
sive delivery interruptions to an acceptable level, and that the
raw water supply would not be a limiting factor in this 3.4.2. Alt. 2: supply from small lakes
scenario. As a result, increased treatment capacity is consid- Some fairly pristine lakes are regulated to increase the flow in
ered as a possible risk-reduction measure. However, there are a small river for transfer to the drinking water system. These
other scenarios, including pollution of the reservoir lakes, lakes contain relatively large water volumes but their water-
where additional raw water sources would be crucial for shed is too small for a continuous supply. The lakes will work
sufficient drinking water production. Several options for as reservoir lakes and water from the connected river will be
additional raw water sources have been identified. pumped into the existing raw water system (Fig. 3). The lakes
were included in the fault tree model as an alternative water
3.4. Risk-reduction alternatives source for each treatment plant, modelled using AND-gates.
To cause failure, all water sources have to be unavailable
The three main risk-reduction measures considered relevant simultaneously for the specific treatment plant. For treatment
for the system and included in this study are increased plant no 2 some events had to be restructured to consider that
treatment capacity, supply from small lakes and supply from failures in the existing system also may cause the new water
a large lake. In addition to the three separate measures, also source to become unavailable. When only treatment plant no
four combinations of these were analysed, see also Rosen 1 is supplied the uptime was estimated to 25e35 days and for
et al. (2010). All alternatives are presented below and the both plants it is 8e18 days (90%-intervals). For both cases the
possible raw water supplies are illustrated in Fig. 3. downtime was estimated to 7e60 days (90%-interval).
w a t e r r e s e a r c h 4 5 ( 2 0 1 1 ) 2 4 1 e2 5 3 247

3.4.3. Alt. 3: supply from large lake the average consumer. In Fig. 4 an uncertainty distribution of
The largest lake in the area is regulated and a pipeline is the calculated risk level and its relation to the safety target are
constructed for raw water transfer to the drinking water presented. The probability of not meeting the target value was
system (Fig. 3). The lake may provide a high availability to raw calculated to be 0.84. Consequently, the current system most
water but failures may occur due to: (1) unacceptable water likely has an unacceptable risk level and measures are thus
quality, e.g. pollution events; (2) insufficient supply of water required.
due to dry periods and legal restrictions; and (3) failure of
technical components making transfer of water to the treat- 4.2. Risk reduction
ment plants impossible. All three events were assessed to
have the same uptimes of 5e15 years and downtimes of 5e30, The mean value and percentiles of the empirical distributions
1e30 and 0.5e2 days respectively (90%-intervals). The large of the current risk level and the residual risk levels after
lake was included in the fault tree in the same way as the implementation of the different measures are presented in
small lakes in alternative 2. However, an OR-gate was also Fig. 5. The histograms in Fig. 5 illustrate uncertainties in risk
used to consider that the lake will become unavailable if one values, originating from uncertainties in input data. Based on
of the three events listed above occurs. the histograms it can be concluded that for some alternatives
(alt. 2, 3 and 6) the probability of exceeding the safety target is
3.4.4. Alt. 4e7: combinations of measures substantial, whereas for others (alt. 1, 4, 5 and 7) the proba-
Alternatives 4e7 are combinations of the first three measures. bility is considerably lower. If the estimated risk (mean value)
Consequently, the fault tree models representing these alter- is used as a criterion to select what alternatives that meet the
native are combinations of the changes presented above. The safety target, only alternatives 1, 4, 5 and 7 should be
following combinations were considered: approved. Although the mean risk level is below the safety
target, there may be a probability of exceeding the target value
- Alt. 4: Combination of alternatives 1 and 2. that cannot be ignored. Based on the uncertainties of the risk
- Alt. 5: Combination of alternatives 1 and 3. levels, the probably of exceeding the safety target was calcu-
- Alt. 6: Combination of alternatives 2 and 3. lated for each alternative (Fig. 6). A highest acceptable prob-
- Alt. 7: Combination of alternatives 1, 2 and 3. ability of not meeting the target value should be considered,
since it influences what alternatives can be accepted. For
example, an acceptable probability of 0.10 makes alternative 1
4. Results acceptable, whereas a probability of 0.05 disqualifies it (see
also Section 5).
4.1. Current system The risk reduction, i.e. effect, of the different alternatives
can be seen from Fig. 5. Among the tree alternatives that are
Previous studies of the current system structure have shown not combinations of measures (alt. 1e3), increased treatment
a significant probability of failures that may cause severe capacity (alt. 1) has the largest effect on the risk. The risk level
supply interruptions. Furthermore, it has been concluded that is reduced from 612 to 81 CML and the probability of not
the raw water supply contributes most to the risk. A risk level meeting the safety target is reduced from 0.84 to 0.08. Among
of 612 CML (mean value) was calculated using the fault tree the alternative raw water sources (alt. 2 and 3), the large lake
model of the current system. This level is clearly above the (alt. 3) is most effective with respect to both the mean risk
specified water safety target of 144 CML per year for level and the probability of not meeting the target. However,

1800
P05
1600 Mean
0.05
P95
1400

0.04 1200

1000
CML
Probability

0.03
800
612
0.02 600

364
400

0.01 200
188 182
81 59 52 50
0
0 0 1 2 3 4 5 6 7
0 500 1000 1500 2000 Alternative
CML
Fig. 5 e Histograms showing mean, 5- and 95-percentiles
Fig. 4 e Uncertainty distribution of the risk for the current of simulated risk levels for the current situation (0) and the
system. The safety target (144 CML per year for the average seven alternatives (1e7). The mean values are given at the
consumer) is indicated by a solid vertical line (Lindhe et al., mean value bars and the safety target (144 CML) is
2009). indicated by a solid horizontal line.
248 w a t e r r e s e a r c h 4 5 ( 2 0 1 1 ) 2 4 1 e2 5 3

1 that when the treatment capacity has been increased the raw
water system is no longer the dominating contributor to the
0.84
total risk level. Thus, after installing increased treatment
0.8 0.73 capacity also measures in the treatment and distribution
systems will be important for further risk reduction.
0.6
P(R>Rc)

0.42 0.41
4.3. Uncertainty analysis
0.4

The fault tree method is probabilistic to include uncertainties in


0.2 input data, which makes it possible to analyse uncertainties in
0.08
0.05 0.04 0.04 results. In addition, it is important to evaluate the uncertainties
0 depending on the selected number of iterations in the Monte
0 1 2 3 4 5 6 7 Carlo simulations. If not enough iterations are made, the stan-
Alternative dard error of the mean (estimate) will be high, resulting in a low
Fig. 6 e Probabilities of exceeding the acceptable risk level accuracy of the calculations. Non-parametric bootstrapping
(Rc) defined by the water safety target (144 CML) for current (e.g. Efron and Tibshirani, 1993) was used to evaluate the
situation (0) and the seven alternatives (1e7). uncertainties in the simulation results. This means that
statistics were sampled empirically by repeatedly sampling
data. Thus, the model data (10,000 iterations) were sampled
both the small lakes (alt. 2) and the large lake (alt. 3) have risk once and new samples were then created by resampling from
levels (364 and 188 CML respectively) above the acceptable this data set. In total 1000 resamplings were made, each
level and the probability of exceeding it is considerable, 0.73 including 10,000 samples. Replacement was applied so that
and 0.42 respectively. each sample can be resampled more than once.
Combining increased treatment capacity with either By means of bootstrapping the 95 percent upper confidence
regulation of the small lakes (alt. 4) or the large lake (alt. 5) limit (UCL95) of the mean was calculated for the risk values and
results in further reduction of the risk level, from 81 CML to 65 for the probabilities of exceeding the safety target (Fig. 7). The
and 54 CML respectively. These levels are clearly below the bars in both plots in Fig. 7 show small differences between
target value. The probability of exceeding the safety target is mean and UCL95 values. Thus, simulations based on 10,000
0.05 for alternative 4 and 0.04 for alternative 5. iterations were considered to give results with acceptable
Regulation of both the large and small lakes without uncertainty since using UCL95 instead of mean values when
measures in the treatment plants (alt. 6) results in a risk level comparing risk levels with the safety target does not affect the
of 187 CML. This is above the safety target and the probability results. Values close to target values are especially important to
of not meeting the target value is 0.41. scrutinise. The estimated value of the probability of exceeding
Combining all measures (alt. 7) provides the greatest risk the safety target is close to, or equal to, 0.05 for alternatives 4, 5
reduction, however, not substantially larger than for alterna- and 7 (Fig. 6). The UCL95 values are only slightly larger (0.05 for
tives 4 and 5. The three alternatives (4, 5 and 7) have a proba- all alternatives) and due to the probabilistic approach applied,
bility of 0.04 or 0.05 of not meeting the safety target. The main with uncertainties in input data, values close to target values
reason for the small difference between the alternatives is should be evaluated with cautiousness.

Risk levels Comparison with water safety target


a 400 b 0.8

350 0.7

300 0.6

250 0.5
P(R>Rc)
CML

200 0.4

150 0.3

100 0.2

50 0.1

0 0
1 2 3 4 5 6 7 1 2 3 4 5 6 7
Alternative Alternative

Fig. 7 e Mean (light colours) and UCL95 values (dark colours) of risk levels (a) and probabilities of exceeding the safety targets
(b) for the alternatives.
w a t e r r e s e a r c h 4 5 ( 2 0 1 1 ) 2 4 1 e2 5 3 249

900 Combining the cost and effect of each alternative, the cost-
1% effectiveness ratio (CER) was calculated (Fig. 9). Based only on
800 2% the CER, alternative 2 is clearly more cost-effective than the
3% others. However, since also the safety target and the ability of
700 4% the alternatives to meet the target have to be considered,
5%
further evaluation is required (see Section 5).
600
Cost [MSEK]

4.5. Cost-benefit
500
The net benefit of all alternatives is presented in Fig. 10 as
400
a function of the economic value of 1 min additional water
supply per year and consumer. If the economic value of risk
300
reduction (c) is lower than 0.03 SEK, only alternative 2
200 provides a positive net benefit. From a strict cost-benefit
approach only alternatives resulting in a positive net benefit
100 should be approved. In this application, however, the only
benefit included was the risk reduction. Consequently, Fig. 10
0 should mainly be used to identify and discuss differences
7 5 6 3 4 1 2
between the alternative measures. It can, for example, be
Alternative
seen that whether the value of c is above or below the
Fig. 8 e Ranked costs (Cj) for the seven alternatives using intersection points at 0.06 and 0.13 clearly affects the rela-
different discount rates. The alternatives are ranked from tionship between the alternatives. Furthermore, if c is
highest to lowest cost. The 3% discount rate was used for approximately 0.07 SEK or higher, all alternatives result in
the subsequent calculations. a positive net benefit (Fig. 10).
As an example, the value of c has to be at least 0.033 SEK
for alternative 1 to result in a positive net benefit. This
4.4. Cost-effectiveness alternative reduces the risk by 531 CML, which result in
a total cost per year and consumer of 17.5 SEK. This figure can
The total cost of each alternative based on different discount be compared to the annual cost for drinking water, which is
rates is presented in Fig. 8 (10 SEK w 1 EUR; w 1.2 USD). In Fig. 8 approximately 400 SEK per consumer in Gothenburg. In
the costs for the alternatives are showed in ranked order. addition to this cost there is a fixed service cost for drinking
Ranked from highest to lowest cost the alternatives are sorted water and wastewater, which is 2542 SEK per year for
as: 7, 5, 6, 3, 4, 1 and 2. It can be seen that the order does not a single-family house.
change with respect to the discount rate. It can also be seen in Alternatives 2, 3 and 6 do most likely not meet the safety
Fig. 8 that a change in discount rate has the largest affect on target (Figs. 5 and 6). Among the remaining options, alter-
high costs. In the subsequent calculations the 3% discount natives 1 and 4 as well as 5 and 7 have similar net benefits.
rate was used. If the alternative of increased treatment The first set of alternatives (alt. 1 and 4) is mainly charac-
capacity (alt. 1) is chosen, this will probably include additional terised by the large risk reduction by increased treatment
actions aimed at reducing odour problems and improving the capacity, while the second set (alt. 5 and 7) is characterised
working environment. The costs, and benefits, included in by the high cost of regulating the large lake. The difference
this analysis are only the ones related to actions needed to between these sets of alternatives is fairly similar over the
increase the treatment capacity. range of c values included in Fig. 10. At c equal to 0.1 SEK the
difference is approximately 340 MSEK. Thus, if the large lake
1.5 provides additional benefits (i.e. not included in this anal-
ysis) of more than 340 MSEK, alternatives 5 and 7 may result
1.16 1.17 in the highest net benefits. Furthermore, if c is equal to
approximately 2.5 SEK alternative 7 becomes most
CER [MSEK/CML]

1 0.88 beneficial.
0.87

0.53 0.52 5. Discussion


0.5
The results clearly show that the risk for the current system is
not acceptable and that measures are required. What risk-
0.04 reduction measure to select depends on the criteria for the
0 decision. A summary of the alternatives is presented in Table
1 2 3 4 5 6 7
2 and it is indicated whether the estimated risks (Rj) exceed
Alternative
the target value of 144 CML (Rc) or not. Furthermore, two
Fig. 9 e Cost-effectiveness ratio (CER) for the seven examples of a certainty criterion are included, representing
alternatives. the highest acceptable probability of not meeting the target
250 w a t e r r e s e a r c h 4 5 ( 2 0 1 1 ) 2 4 1 e2 5 3

a 1500 300

Alt. 4
b

Net Benefit [MSEK]


Alt. 1
250

1000

200
Net Benefit [MSEK]

150
500 0.05 0.055 0.06 0.065
c [SEK]

550

c
Alt. 2 Alt. 3
0

Net Benefit [MSEK]


Alt. 1
Alt. 6
Alt. 2 500
Alt. 3
Alt. 5 Alt. 4
500
Alt. 5
Alt. 7 Alt. 6
Alt. 7
450
0 0.05 0.1 0.15 0.2 0.12 0.125 0.13 0.135
c [SEK] c [SEK]

Fig. 10 e Net benefit of alternatives as a function of the economic value of 1 min additional water supply per year and
consumer (c). In Figure (a) all alternatives are included and in Figures (b) and (c) the two intersection points have been
zoomed in. The same legend is used in all figures.

value, i.e. P(Rj > Rc). The probabilities used in our example are lowest cost. However, to fully understand the results a couple
0.10 and 0.05. It should be emphasised that the decision- of different aspects have to be considered, see below.
makers have to define the certainty criterion; it is not the task
of the risk analysts. As can be seen in Table 2 alternatives 2, 3 5.1. Target values and the CER
and 6 exceed both probabilities. Alternative 1 may be accepted
if the certainty criterion is represented by the highest (0.10) Although an alternative results in a low CER, such as alternative
probability. Thus, the required level of certainty has an impact 2, it cannot be considered cost-effective if the acceptable level
on what alternatives that can be accepted. of risk is exceeded (Table 2). In the kind of case study performed
Among the three alternatives meeting all criteria (alt. 4, 5 here, a predefined target value is necessary for a CEA to be
and 7), increased treatment capacity in combination with useful. If the aim is to achieve the largest risk reduction for
regulation of the small lakes (alt. 4) has the lowest cost and a certain amount of money, irrespective of the residual risk, no
CER. Hence, if the certainty criterion is represented by an target value is needed. However, to consider both the cost and
acceptable probability of 0.05, alternative 4 is the most cost- effect in a sensible way, a target value is required.
effective alternative. If the certainty criterion is represented If no target value exists and only the CER values are ana-
by an acceptable probability of 0.10, increased treatment lysed, this may cause (i) insufficient risk reduction as well as
capacity alone (alt. 1) is most cost-effective since it has the (ii) unnecessarily large reduction. The first case (i) is

Table 2 e Summary of risk levels (Rj), probabilities of not meeting the safety target P (Rj > Rc), costs (Cj) and cost-
effectiveness ratios (CERj) for the alternatives. The safety target value is 144 CML. For the probability of not meeting the
safety target two example criteria are used (0.10 and 0.05). Bold values indicate that the criterion is not met.
Criterion 144 0.10 0.05

Alternative Rj [CML] P(Rj>Rc) P(Rj>Rc) Cj [MSEK] CERj [MSEK/CML]

1. Increased capacity 81 0.08 0.08 280 0.53


2. Supply from small lakes 364 0.73 0.73 9 0.04
3. Supply from large lake 188 0.42 0.42 372 0.87
4. Combination of alt. 1 and 2 59 0.05 0.05 289 0.52
5. Combination of alt. 1 and 3 52 0.04 0.04 652 1.16
6. Combination of alt. 2 and 3 182 0.41 0.41 381 0.88
7. Combination of alt. 1, 2 and 3 50 0.04 0.04 661 1.17
w a t e r r e s e a r c h 4 5 ( 2 0 1 1 ) 2 4 1 e2 5 3 251

combined with only the large lake (alt. 5) a risk reduction


Table 3 e Example of two fictitious alternatives to
illustrate limitations with the CER. For each alternative almost equivalent to alternative 7 is obtained. Increased
the residual risk (Rj), cost (Cj) and cost-effectiveness ratio treatment capacity in combination with the small lakes (alt. 4)
(CERj) are presented. The current risk level (R0) is assumed also results in similar residual risk. The only combination of
to be the same as in the case study (612 CML). measures not meeting the target value is the combination of
Alternative Rj [CML] Cj [MSEK] CERj [MSEK/CML] the large and small lakes (alt. 6). This alternative provides
limited additional risk reduction compared to using the large
A 144 420 0.90
lake only (alt. 3). Thus, including the large lake, solely or
B 12 450 0.75
combined with increased treatment capacity, the small lakes
provide only marginal additional risk reduction. Considering
the effect and the cost, alternatives 1 and 4 seems to be the
exemplified by alternative 2 in this application (Table 2).
best options.
Although the safety target is not met the CER may seem
A major advantage of the applied method is the possibility
favourable if the cost, in relation to the effect, is low. The
to measure each alternatives effect on the risk using the same
second case (ii) may, for example, occur if one alternative
unit (CML). The use of CML as a performance indicator is
reduces the risk far below the acceptable level and another
common in the energy sector and has been used in the
alternative reduces the risk just to the target value. In Table 3
drinking water sector in the Netherlands. This study shows
two alternatives are presented as examples to illustrate this
that CML is an applicable unit to be used when evaluating and
possible problem. Alternative A reduces the risk just to the
comparing measures for reducing water supply interruptions,
acceptable level of 144 CML to a cost of 420 MSEK. Alternative B
i.e. quantity failures. However, alternatives may have other
on the other hand, reduces the risk to a level of 12 CML but to
positive effects that are not related to quantity failure. For
a cost of 450 MSEK. Since the safety target is 144 CML, both
example, regulation of the large lake will most probably also
alternatives provide an acceptable risk. To simplify the
provide a raw water of better and more stable quality
example we do not consider uncertainties in risk levels and
compared to the current main raw water source. The cost-
costs. If the CER values are compared, alternative B appears to
benefit calculations (Fig. 10) show that a costly alternative
be most cost-effective (Table 3). However, alternative A meets
may result in a positive net benefit if the value of risk reduc-
the safety target to a lower cost. One may argue that there is
tion is high or large benefits are obtained. If a full CBA would
no use of reducing the risk below the acceptable risk level. It
have been performed, it may not have provided recommen-
would be better to use these resources for other purposes.
dations similar to those of the CEA, e.g. because of possible
Consequently, the CER should be used to illustrate the cost of
health benefits provided by the large lake but not considered
reducing the risk one unit but not as the single criterion for
in the CEA. The reduced quality risk, i.e. related to human
evaluating alternatives.
health effects, was not considered in this analysis but could
An alternative way of calculating the effect (Ej) could be
also be assessed using the fault tree method.
used to avoid the problem with CER values described above. By
Another aspect not explicitly included in the CEA is the
not considering risk reduction below the safety target (Rc), the
time for implementing measures. For example, the inclusion
effect could be calculated as
of the large lake is expected to be a rather complicated and
long process, for various reasons. Assume that increased
 
Ej min R0  Rj ; R0  Rc (7) treatment capacity combined with the large lake (alt. 5) is
selected as the most suitable alternative. Furthermore,
increased treatment capacity by itself is not associated with
where R0 is the risk level prior to any measures, Rj the residual
an acceptable risk. Since the large lake takes a long time to
risk for alternative j. Thus, the largest possible effect is R0Rc.
implement, it might be reasonable to first combine increased
Using Equation (7) for the two examples in Table 3, results in
treatment capacity with the small lakes (alt. 4). Thus, when
a CER of 0.96 for alternative B and no changes for alternative A.
the large lake is installed, the small lakes may be excluded. In
Based on the alternative approach alternative A is most cost-
this way the risk is not unacceptable during the installation of
effective (0.90 < 0.96).
the large lake.
The CEA, as applied here, includes one criterion related to
5.2. Aspects included the risk level and one to the cost. To further develop the
approach, additional criteria can be included and a multi-
Considering only the three first alternatives, increased treat- criteria decision analysis (MCDA) applied. A MCDA would
ment capacity (alt. 1) provides a substantial risk reduction make it possible to include additional types of risk, such as the
compared to the alternative raw water supplies (alt. 2 and 3). It quality risk, and also additional criteria for evaluating the
can be concluded that the capacity of the treatment plants is performance of alternative measures. One criterion could be
a bottleneck in the system that cannot be solved only by linked to, for example, the time it takes to implement
increased access to raw water. Although increased treatment measures. If the aim is to evaluate how well alternative
capacity has a large effect on the risk level, additional measures measures contribute to a sustainable supply system, they can
may be needed depending on the required level of certainty. be assessed based on criteria linked to environmental,
The combination of increased treatment capacity and both economic and socio-cultural dimensions. In a MCDA it is also
the large and small lakes (alt. 7) provides the largest risk possible to take into account that all criteria may not be
reduction. However, if increased treatment capacity is regarded as equally important.
252 w a t e r r e s e a r c h 4 5 ( 2 0 1 1 ) 2 4 1 e2 5 3

5.3. Uncertainties and cost planning of drinking water systems in order to avoid sub-
optimisation of available resources for risk reduction.
The uncertainty analysis of the costs was related to the
discount rate. By calculating the present value for each alter-
native using different discount rates, the sensitivity of the
Acknowledgements
results with respect to this variable was analysed. Although
uncertainties in input data are not considered, this type of
This research was sponsored by The Swedish Water &
analysis is important to know whether the value of parame-
Wastewater Association, the City of Gothenburg and the
ters affects the final prioritisation of alternatives.
TECHNEAU project, a EC-funded FP6 project (www.techneau.
org). We would like to thank the City of Gothenburg for its
5.4. The method valuable and fruitful collaboration. We also appreciate
the comments and suggestions given by the anonymous
The applied fault tree analysis in combination with CEA reviewers.
illustrates its possibilities as a decision support tool for struc-
tured comparison of alternative risk-reduction measures. The
fault tree analysis makes it possible to model alternatives that
references
influence different parts of a system and to quantify the risk
reduction. The method facilitates two very important anal-
Astrom, J., Pettersson, T.J.R., Stenstrom, T.A., 2007. Identification
yses: (1) analysis of the risk reduction provided by a specific
and management of microbial contaminations in a surface
measure; and (2) analysis of the uncertainty of the risk esti-
drinking water source. Journal of Water and Health 5 (Suppl.
mate, which enables an estimation of the probability of not 1), 67e79.
meeting acceptable risk levels. Combination of the quantita- Bartram, J., Corrales, L., Davison, A., Deere, D., Drury, D.,
tive fault tree analysis and economic evaluation provides Gordon, B., Howard, G., Rinehold, A., Stevens, M., 2009. Water
transparency and a basis for long-term planning of drinking Safety Plan Manual: Step-By-Step Risk Management for
water systems. Drinking-Water Suppliers. World Health Organization,
Geneva.
Bedford, T., Cooke, R.M., 2001. Probabilistic Risk Analysis:
Foundations and Methods. Cambridge University Press,
6. Conclusions Cambridge.
Blokker, M., Ruijg, K., de Kater, H., 2005. Introduction of
a substandard supply minutes performance indicator. Water
The main conclusions of this study are: Asset Management International 1 (3), 19e22.
Brouwer, W.B.F., Koopmanschap, M.A., 2000. On the economic
- The fault tree method enables comparison of risk-reduction foundations of CEA. Ladies and gentlemen, take your
alternatives in the same quantitative unit and for an entire positions! Journal of Health Economics 19 (4), 439e459.
drinking water system from source to tap. Interactions Burgman, M.A., 2005. Risks and Decisions for Conservation and
Environmental Management. Cambridge University Press,
between events and components of the system can be
Cambridge.
modelled in a realistic way. Furthermore, the probabilistic
Cox, A.L., 2008. Whats wrong with risk matrices? Risk Analysis 28
approach enables comparisons with safety targets and the (2), 497e512.
probability of exceeding these target values can be calculated. Davison, A., Howard, G., Stevens, M., Callan, P., Fewtrell, L.,
- A CEA provides useful information by combing the effect Deere, D., Bartram, J., 2005. Water Safety Plans: Managing
and cost. However, it is important to understand existing Drinking-Water Quality from Catchment to Consumer. WHO/
pitfalls when interpreting the results. For example, alter- SDE/WSH/05.06. World Health Organization, Geneva.
Efron, B., Tibshirani, R., 1993. An Introduction to the Bootstrap.
natives may provide additional benefits not considered in
Chapman & Hall, New York.
the CEA and alternatives cannot be evaluated solely based Goteborg Vatten, 2006. Action Plan Water: Long-term Goals for
on cost-effectiveness ratios. the Water Supply in Gothenburg (In Swedish) City of
- A CEA requires a safety target representing the acceptable Gothenburg.
level of risk. In addition to the target value it is also impor- Johansson, P.-O., 1993. Cost-benefit Analysis of Environmental
tant to consider the highest acceptable probability of not Change. Cambridge University Press, Cambridge, New York.
meeting the target value, i.e. a certainty criterion. Levin, H.M., McEwan, P.J., 2001. Cost-effectiveness Analysis:
Methods and Applications, second ed. Sage Publications,
- A multi-criteria decision analysis could be applied to further
Thousand Oaks, California.
develop the applied approach and include additional Lindhe, A., 2008. Integrated and probabilistic risk analysis of
criteria for evaluating the performance of risk-reduction drinking water systems, Licentiate Thesis No. 2008:8,
measures. Chalmers University of Technology, Goteborg.
Lindhe, A., Rosen, L., Norberg, T., Bergstedt, O., 2009. Fault
Combining quantitative risk analysis tools, such as the tree analysis for integrated and probabilistic risk analysis
of drinking water systems. Water Research 43 (6),
applied fault tree method and economic evaluation, provides
1641e1653.
a powerful tool for decision-makers. A combined quantitative
Lindhe, A., Rosen, L., Norberg, T., Petterson, T.J.R., Bergstedt, O.,
risk assessment and economic evaluation can provide Astrom, J., Bondelind, M., 2008. Integrated risk analysis from
a structured and thorough analysis of risk-reduction source to tap: Case study Goteborg, In: 6th Nordic Drinking
measures that facilitates transparency and long-term Water Conference, pp. 231e241.
w a t e r r e s e a r c h 4 5 ( 2 0 1 1 ) 2 4 1 e2 5 3 253

Lindstedt, U., Ingelsson, M., Engleryd, A., 2003. Consequence Rausand, M., Hyland, A., 2004. System Reliability Theory:
Analysis Step-By-Step: Guidance on Economic Consequence Models, Statistical Methods, and Applications, second ed.
Analysis for the Environmental Protection Agency (In Swedish). Wiley-Interscience, N.J.
Swedish Environmental Protection Agency, Stockholm. Rosen, L., Hokstad, P., Lindhe, A., Sklet, S., Rstum, J., 2007.
MacGillivray, B.H., Hamilton, P.D., Strutt, J.E., Pollard, S.J.T., 2006. Generic FRAMEWork and Methods for Integrated Risk
Risk analysis strategies in the water utility sector: an Management in Water Safety Plans. Deliverable no. D 4.1.3, D
inventory of applications for better and more credible decision 4.2.1, D 4.2.2, D 4.2.3. TECHNEAU.
making. Critical Reviews in Environmental Science and Rosen, L., Lindhe, A., Bergstedt, O., Norberg, T., Pettersson, T.J.
Technology 36 (2), 85e139. R., 2010. Comparing risk-reduction measures to reach
Nas, T.F., 1996. Cost-benefit Analysis: Theory and Application. water safety targets using an integrated fault tree model.
Sage Publications, Thousand Oaks, Calif. Water Science and Technology: Water Supply 10 (3),
Norberg, T., Rosen, L., Lindhe, A., et al., 2009. Added value in fault 428e436.
tree analyses. In: Martorell, S. (Ed.), Safety, Reliability and Risk Rosen, L., Steier, K., 2006. Risk Analysis: Interruptions in Raw
Analysis: Theory, Methods and Applications. Taylor & Francis Water Supply to the Gothenburg Drinking Water System (In
Group, London, pp. 1041e1048. Swedish), Consulting report, Contract no. 1310786. SWECO
Pollard, S.J.T., 2008. Risk Management for Water and Wastewater VIAK AB.
Utilities. IWA Publishing, London. Stern, N., 2007. The Economics of Climate Change: The Stern
Ramsey, S., Willke, R., Briggs, A., Brown, R., Buxton, M., Review. Cambridge University Press, Cambridge.
Chawla, A., Cook, J., Glick, H., Liljas, B., Petitti, D., Reed, S., WHO, 2008. Guidelines for Drinking-Water Quality [Electronic
2005. Good research practices for cost-effectiveness analysis Resource]: Incorporating First and Second Addenda. In:
alongside clinical trials: the ISPOR RCT-CEA task force report. Recommendations, third ed., vol. 1. World Health
Value in Health 8 (5), 521e533. Organization, Geneva.

Potrebbero piacerti anche