BILL NO. 8.0 ( CONTD.

PLASTER WORK AND FLOOR, WALL AND CEILING FINISHES ( CONTD. )

Item Description Qty. Unit Rate Amount


Rs. Cts.

600 x 300mm Non-skid floor tiles ( floor tiles supplied


by client ) for toilet & balony fixed on and including
12mm thick cement and sand ( 1 : 3 ) screeded bed
with and including faircutting,jointing and pointing.Rate
to include for grouting.

34 Ground floor. 28.00 M2

35 First floor. 38.00 M2

Granite

Flamed finished Granite (Granite supplied by client )


laid to the approved pattern on ornamental floor. Rate
to include for adehesive, jointing,pointing,mitre cutting
etc as per manufacturer's specifications and
instructions

36 Ground floor. 17.00 M2

Cement Rendering

37 3/4" Thick cement and sand rendering ( 1: 3 ) finished


smooth to receive carpet( carpet measured
separately ) in first floor. 610.00 M2

Bush Hammered Stone Paving.

38 1'-0" x 1'-0" Bush Hammered Stone paving ( Free


Lanka Granite or similar approved ) fixed on cement
and sand screeded bed (measured separately ) .
50.00 M2

Cement Block paving

39 Interlocking paving stones ( available at site ) laid on


well compacted quarry dust in vehicular access. Rate
shall include for preparation of existing filled earth to
required slopes etc., 275.00 M2

40 Interlocking paving tiles ( Amtrad / Royal pavers or


approved equivalent and to be match with available
paving tiles ) laid on well consolidated quarry dust
layer as per manufacturer's instructions and
specifications. Rate shall include for preparation of
existing filled earth to required slopes etc., 60.00 M
2

Skirtings

1/2'' Thick 4" high cement and sand (1:3) skirting


finished smooth with neat colour cement pigment.
Rate shall include for cut and polish on skirting.

41 In Semi basement floor 75.00 L.m.

42 In ground floor. 93.00 L.m.

Total Carried to Collection


8/4
82
BILL NO. 8.0 ( CONTD. )

PLASTER WORK AND FLOOR, WALL AND CEILING FINISHES ( CONTD. )

Item Description Qty. Unit Rate Amount


Rs. Cts.

100mm High glazed tile skirting (skirting tile supplied


by client) fixed on and including 12mm thick cement
and sand ( 1: 3 ) screeded backing.

43 In Semi basement floor 20.00 L.m.

44 In ground floor. 13.00 L.m.

Beds and Backing

1/2'' -3/4'' Thick cement and sand (1:3) screeded bed


in the following.

45 Ground floor. 17.00 M2

Total Carried to Collection

COLLECTION

Amount
Rs. Cts.

Page 8/1
Page 8/2
Page 8/3
Page 8/4
Page 8/5

TOTAL FOR PLASTER WORK AND OTHER


FLOOR, WALL AND CEILING FINISHES
Carried to Summary

8/5
83
BILL NO. 10.0 ( CONTD. )

PROVISIONAL SUMS ( CONTD. )

Item Description Qty. Unit Rate Amount


Rs. Cts.

14 Allow the Provisional Sum for supply and fixing of


100mm high Teak Timber skirtings. Rate shall include
for painting Sum 225,000.00

15 Allow the Provisional Sum of TV System EXCLUDED

16
Allow the Provisional Sum for Door access control
system Sum EXCLUDED

17 Allow the Provisional Sum for loose furniture and


equipments. Sum EXCLUDED

18 Allow the Provisional Sum for Airconditioning


Installation Sum 15,000,000.00

19 Allow the Provisional Sum for supply and laying of


carpets Sum 8,200,000.00

Total Carried to Collection 23,425,000.00

COLLECTION
Amount
Rs. Cts.

Page 10/1 0.00


Page 10/2 23,425,000.00

TOTAL FOR PROVISIONAL SUMS


Carried to Summary 23,425,000.00

10/2
87
BILL NO.11.0

ATTENDANCE ON PROVISIONAL SUMS

Item Description Qty. Unit Rate Amount


Rs. Cts.

13
Allow for attendance .% on Teak Timber Skirting Sum

14 Allow for attendance .% on Air-Conditioning


Installation Sum

15 Allow for attendance .% on Supply and


installation of carpet Sum

Total Carried to Collection

COLLECTION
Amount
Rs. Cts.

Page 11/1
Page 11/2

TOTAL FOR ATTENDANCE ON


PROVISIONAL SUMS
Carried to Summary

11/2
88 ( A )
BILL NO. 12.0

PRIME COST SUMS

Item Description Qty. Unit Rate Amount


Rs. Cts.

1 Allow the Prime Cost Sum for supply of Flame


2
finished Granite ( 17 M ) Sum 300,000.00

2 Allow the Prime Cost Sum for supply of Sanitary


fittings and vanity tops. Sum 600,000.00

3 Allow the Prime Cost Sum for supply of Luminaires. Sum 4,000,000.00

4
Allow the Prime cost Sum for supply of
600 x 300mm glazed wall tiles ( Rs.5200/- per Sq.m. ) Sum 625,000.00

5 Allow the Prime cost Sum for supply of


600 x 600mm non-skid floor tiles ( Rs.5100/- per
Sq.m. ) Sum 750,000.00

6 Allow the Prime cost Sum for supply of


600 x 600mm Rustic non-skid floor tiles ( Rs.4800/-
per Sq.m. ) Sum 3,525,000.00

7
Allow the Prime cost Sum for supply of 600 x 300mm
Rustic non-skid floor tiles ( Rs.5000/- per Sq.m. ) Sum 330,000.00

8 Allow the Prime cost Sum for supply of 100mm high


skirting tiles Sum 20,000.00

9 Allow the Prime Cost Sum for obtaining statutory


approvals and connections. ( Electrical/ Water/ Sewer
and Storm water ) Sum Excluded

10 Allow the Prime Cost Sum for obtaining drainage


certificate from statutory board. Sum Excluded

TOTAL FOR PRIME COST SUMS


Carried to Summary 10,150,000.00

12/1
89
BILL NO. 13.0

ATTENDANCE FEE ON PRIME COST SUMS

Item Description Qty. Unit Rate Amount


Rs. Cts.

1 Allow for attendance fee.% on supply of Sanitary


Fittings Sum

2 Allow for attendance fee.% on supply of


Luminaires Sum

3 Allow for attendance fee.% on supply of Flame


finised granite. Sum

4 Allow for attendance fee.% on supply of 600 X


300MM glazed wall tiles. Sum 6.0%

5 Allow for attendance fee .% on 600 x 600 non- Sum


skid floor tiles. ( Rs. 4850/= per M2 ) 6.0%

6 Allow for attendance fee ..% on 600x 600


Rustic non-skid floor tiles. ( Rs. 4300/= per M2 ) Sum

7 Allow for attendance fee ..% on 600x 300


Rustic non-skid floor tiles. ( Rs. 4300/= per M2 ) Sum 6.0%

8 Allow for attendance fee ..% on skirting tiles Sum

TOTAL FOR ATTENDANCE ON PRIME COST


SUMS
Carried to Summary

13/1
90
PROPOSED RESTAURANT & ENTRANCE LOBBY.
FOR THILANKA HOTEL (PVT) LTD, AT NO. 3, SANGAMITTA MAWATHA, KANDY

BILL OF QUANTITIES

SUMMARY

Amount
Rs. Cts.

BILL NO. 1.0 - PRELIMINARIES

BILL NO. 2.0 - DEMOLITION

BILL NO. 3.0 - EXCAVATION AND EARTHWORK

BILL NO. 4.0 - CONCRETE WORK

BILL NO. 5.0 - MASONRY

BILL NO. 6.0 - ASPHALT WORK

BILL NO. 7.0 - ALUMINIUM JOINERY

BILL NO. 8.0 - PLASTER WORK AND OTHER FLOOR


WALL AND CEILING FINISHES

BILL NO. 9.0 - PAINTING

BILL NO. 10.0 - PROVISIONAL SUMS ( Not to be added to the Bid Amount )

BILL NO. 11.0 - ATTENDANCE ON PROVISIONAL SUMS

BILL NO. 12.0 - PRIME COST SUMS ( Not to be added to the Bid Amount )

BILL NO. 13.0 - ATTENDANCE FEE ON PRIME COST SUMS

BILL NO. 14.0 - DAY WORKS

ADD : 15% CONTINGENCIES

ADD : 12% VAT

TOTAL AMOUNT CARRIED TO FORM OF BID

Total Amount ( in words ) ..


..

96