Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
INTRODUCTION
systems are subject to constant disruptions created by abnormal conditions like random
load changes, faults by natural causes, and equipment failure (Horowitz & Phadke, 2008).
These abnormal conditions interrupt the reliable transmit of electricity. To protect the
power system, protective relays are essential to every power system design. It is the task
of protective relays to minimize the power outages and damages to the power system
ANSI C84.1-2011, the substation falls into a category of high voltage power system. The
substation uses a breaker-and-a-half bus system to supply to its loads. This bus system is
recommended to use in extra high voltage substations for increased service reliability
There are five transformers in the substation but only transformer 5 is part of the
study. Transformer 5 is newly built and was the result of a fast track scheme solution
when transformer 3 became non-operational. This transformer addition created a need for
a contractor to protect its line from faults. Since the newly built feeder is parallel to the
feeder connected to the transformer 4, a directional protection is needed for its protection.
Using directional equipment will ensure that there will still be a supply to the consumers
was contracted to commission the protection for this newly built line. The company built
seven protection panels; two main transformer protection panel, one feeder protection
panel, three circuit breaker failure protection panel, and one bay control unit. The feeder
protection panel, together with its relays, is the only panel which is part of this study.
3
In this protection scheme used by JEDDTECH, the feeder protection panel has
two primary protection relays. There is a need for multiple parallel primary protection in
a high voltage power system to ensure that any fault is cleared quickly (Alstom Grid,
2011). The main 1 uses MiCOM P14DL relay while Schneider Electric P127 relay is used
network than with non-directional overcurrent protection (Bertrand, 1998). Based on the
topology of the system, there is a need for a directional protection. The study determines
and assesses the settings of directional overcurrent and directional earth fault based on
the systems specifications. It will make sure that proper coordination with the other
performance of the relay based on its trip time and other relay characteristic (Alstom
Grid, 2011).
The study will help Jedd Technologies Inc. assess the directional overcurrent relay
settings they used to commission the feeder protection panel for the substation. It is to
ensure that proper coordination with the other relays in the substation is achieved.
Identifying the errors in the substations protection is needed so that proper changes can
The general objective of this study is to evaluate the coordination of the feeder
protection panel installed on the 69kV line connected to Transformer 5 of the 230kV
The study focuses on the determination and analysis of the settings of the Feeder
Both MiCOM P14Dl and Schneider Electric P127 are tested. Since the relays are parallel,
the determination of the correct settings to be used is the same for both relays but the
study. In determining the coordination, settings from the other relays in the substation is
used but changing the settings of the other relays is not part of the study.
The study was conducted at the 230kV Substation from July 11 to August 12,
2016 under the supervision of Engr. Reynan Garbriel N. Bugayong and Engr. Mark
Anthony B. Salvame.
5
2. THEORETICAL BACKGROUND
Electrical power system generates and supplies reliable and economical electricity
to the consumers (Elmore, 2003). Any abnormal conditions that would create outages will
disrupt daily activities of the consumers. Limiting these outages is the function of a
includes current transformer, voltage transformers, fuse, circuit breaker, relay or any
Zones of Protection
Protection system is arranged in zones to limit the part of the power system
disconnected when a fault occurs. The power system is divided by its zones for proper
protection. These zones can be categorized as protection for buses, feeders, generators,
transformers, motors, and capacitor bank (Blackburn & Domin, 2014). The zones should
overlap to ensure that no part of the power system is unprotected. It is necessary that the
primary zone protection operates faster than the backup zone protection to ensure proper
coordination. The zone protected in this study is the feeder which supplies Kalaw and
Ingasco substations.
6
Line Protection
means a lost in power which imposes an importance in the protection of the lines. The
most common relays used in protecting the line of a power system are differential,
distance, and overcurrent protection. Each relay has its advantages and requires different
parameters to clear a fault. The choice of relay to use for protection depends on the type
of the system.
flowing in a node should be zero. This is the same principle working for differential
protection. The CTs are placed on both ends of the line for current comparison. (Wright &
Christopoulos, 2013).
impedance which is proportional to the distance to the fault. The fault is evaluated by
protection is less susceptible to changes in the system conditions. It is also faster and
Overcurrent(OC) Protection
protect the system from overcurrent faults. It requires current as the parameter for both
sensing and measuring of fault current. (IEEE Power & Energy Society, 2009).
Overcurrent Protection is the simplest, the cheapest, but the most difficult to apply and
quickest to need readjustment or replacement after system changes in all the possible
protection for a feeder. There are three ways used in discriminating fault currents in an
to ensure the first circuit breaker that trips is nearest to the fault. The time interval
between each relay must ensure that the relay near the fault location must clear the fault
before upstream relays operate. Its major disadvantage is it takes longest clearing time for
difference in impedance between the source and the fault. The fault current varies with
the position of the fault. As the fault impedance gets higher, the current is lowered. The
relay nearest to the fault trips its breaker. The problem with this discrimination is if there
are no significant difference between two circuit breakers (Alstom Grid, 2011).
8
developed. The time of operation is inversely proportional to the fault current. For a large
difference of current between two ends of a line, faster operating times is used with relays
This type of overcurrent uses both time and current to clear a fault. One unique
feature of this protection is its wide range of currents and operating times. Since the
current is inversely proportional to time, the higher the fault current is the faster the
operating response of the relay. IDMT curves follow the operating time characteristic
from equation 2-1. Each international standard use different relay characteristic curves.
The constants of these curves are shown in table 2-1 while graphs from different
[( ) ]
t op=TD +L
I (Equation 2-1)
1
IS
where:
top is operating time
TD is the time dial
I is the fault current
IS is the pickup current
, , L are characteristic constants
9
The protection engineer chooses the type of curve depending on the need of the
power system. The correct type of curve will determine protection systems reliability.
The relay used in this study uses IDMT OC relay with directional features.
system. Directional overcurrent relay (67), which is used in this study, responds
differently for faults in reverse and forward direction. A relay with directional properties
determines the direction by comparing the phase angle relationship between current and
voltages. A current with forward direction means that current is in phase with the voltage.
Unfortunately, for phase to ground faults, the relationship of the phase voltage and
current will be mostly VAR flow preventing a correct assessment of directional flow
(Horak, 2006). To correct the issue, relays current and voltage detection is skewed in
unity power factor so that voltage is in phase with current when the condition occurs. The
angle setting to correct the problem is called relay characteristic angle (RCA).
A better explanation of the directional protection can be seen in the figure 2-1.
Both relay 1 and relay 2 are at set at forward direction. If a fault occurs below the line
where relay 1 is connected, only relay 1 will trip. Relay 2 will see a fault happening but
current can flow in both directions of a relay location. If non-directional relays are
applied to parallel feeders having a single generating source, any faults that might occur
on any one line will, regardless of the relay settings used, isolate both lines and
completely disconnect the power supply. With this type of system configuration, it is
necessary to apply directional relays at the receiving end and to grade them with non-
directional relays at the sending end, to ensure correct discriminative operation of the
Since the directional relays are comparing the phase difference between the
voltage and current inputs. This is standard connection for static, digital or numerical
relays. The Relay Characteristic Angle (RCA) is dependent on the angle by which the
input voltage is shifted to produce maximum relay sensitivity. Two types are available in
source needs the use of this RCA. The A phase relay element is supplied with I A current
and VBC displaced by 30 in an anti-clockwise direction. In this case, the relay maximum
sensitivity is produced when the current lags the system phase to neutral voltage by 60.
This connection gives a correct directional tripping zone over the current range of 30
leading to 150 lagging. The relay sensitivity at unity power factor is 50% of the relay
from the phase voltage. This connection gives a correct directional tripping zone over the
current range of 45 leading to 135 lagging. This connection is recommended for the
protection of transformer feeders that have n zero sequence source in front of the relay.
16
power system. It also requires the relay to pass a functionality test. Relay testing is done
to verify if the relays functions is acceptable to the required operating characteristics and
settings of the protection scheme. The test should be done in a controlled environment
and evaluated based on the efficiency of detecting the fault within its allowable time
test. This determined the trip time, operating current, and other characteristic settings of
Acceptance testing is done to make sure that the newly commissioned relays meet
the requirements needed for reliable protection. To evaluate the test results, a standard or
standard, the specifications provided by the relay manufacturer should be followed is the
standard for its acceptable time limits. For inverse definite minimum time (IDMT)
curves, the P14DL Manual suggests that the time deviation of the relay should only be
within +/- 5% of the computed time while of P127 is +/- 5% plus 30-50ms. For the relay
characteristic angle, both relays allow the directional boundary accuracy to be less than or
equal to 3 degrees.
Omicron CMC test provides function-based acceptance test and compare different
relay models with each other. Since the Test Universe follows IEC standard, the test used
to check the functionality of the relay is based on the IEC 60255 standard. The range of
3.1 Materials
System Specifications
devices such as current transformer, circuit breakers and relays used in this study are
18
shown in the single line diagram in Figure 3-1 is the CEDC substation single line
diagram.
transformer with Dyn1 setting to step down the voltage for its loads. Two relays are used
to protect the 69kV line from overcurrent and earth faults; MiCOM P14DL and Schneider
Electric P127. These relays need to be coordinated to the relays of Load A, Load B, Load
C and Transformer 5. Load A uses MiCOM P142 to protect its line, while Load B uses
SEL 351A and Load C uses Siemens 7SJ801. The upstream relay for Transformer 5 uses
MiCOM P643.
19
MiCOM P14DL and Schneider Electric P127 relays are used to protect the 69kV
feeder. Both are multifunctional relays that features directional overcurrent and
directional earth fault settings which contains three well known variants of IDMT
characteristic curves, as defined by IEC 60255-151; Standard Inverse, Very Inverse, and
Extremely Inverse.
Since MiCOM and Schneider are parallel relays, the settings in both relays are the
same. The settings JEDDTECH used for DOC is shown in Table 3-1 while Table 3-2
Table 3-3. Transformation Ratio Set in MiCOM P14DL and Schneider Electric P127
TRANSFORMATION RATIO
ITEM SETTINGS AS LEFT
Main VT Primary 40.25 kV
Main VT Secondary 115 V
Phase CT Primary 1200 A
Phase CT Secondary 5A
EF CT Primary 1200 A
EF CT Secondary 5A
C/S Input A-N
Main VT Location Line
The 69kV feeder protection panel is coordinated with the downstream relays of
Load A, Load B, and Load C feeders and with the transformer 5 DOC and DEF
protection. To determine if the panel is properly coordinated with the relays of the
system, the settings of the other relays of the The settings of the other relays to be used to
coordinate in the study can be seen in Tables 3-3 to 3-6. Load A can be While it needs to
be coordinated to tThe settings of the relays can be seen in the tables below. All the
settings given at the table was used to coordinate the feeder protection relay.
The transformer relay which is MiCOM P643 is the upstream relay while
MiCOM P142, SEL 351A, and SIEMENS 7SJ801 are downstream relays. The
coordination part of this study will consider the settings in these relays and coordinate
above the full load current (Birla, Maheshwari, & Gupta, 2006). The equation in solving
the full load current is shown in Equation 3-1 while the equation in solving the pick-up
MVA
I FL=
3 X V L
(Equation 3-1)
where:
IFL is full load current
MVA is MVA rating
VL is line voltage
( overload factor ) x I FL
I P= (Equation 3-2)
CTR
where:
IP is pick-up current
IFL is full load current
CTR is CT ratio
23
(Gers & Holmes, 2004). The pick-up current of directional earth-fault is typically within
10-40% of the full load current of the system being protected (Bakar, et al., 2014). The
overload factor used by JEDDTECH should be within the recommended range so that
There are many papers that uses MS EXCEL to perform the protection
The device comes with a testing software; Omicron Test Universe. Omicron Test
Universe
relay and its settings will operate correctly. The test device used is the Omicron
CMC256plus which comes with a testing software; Omicron Test Universe. Omicron Test
Universe has functions The Omicron QuickCMC was used to perform testing on the
relays pickup current while the Omicron Overcurrent was used to perform the
directionality of the relay in testing. Both test were used to in DOC and DEF tests.
3.2 Methods
Proper coordination within a power system is needed to make sure that no part of
the system is left unprotected. The initial step in determining the coordination is to gather
the data needed for the process which is the protection equipment settings of the system.
The first step was to determine the correct pick up current of the relay for both DOC and
25
DEF. After setting the pickup current of the line, the time delay of the relay was
determined by the equation of the characteristic curve. The characteristic constants from
table 2-1 are considered in the equations. The IEC standard inverse curve equation is
equation 3-1. It is used in both Phase Overcurrent and Ground Overcurrent of MiCOM
P142, and Ground Overcurrent of SEL 351A. This curve is also used by the MiCOM
P643, MiCOM P14DL, and Schneider Electric P127 for both its DOC and DEF
protection.
0.14
t op=TMS 0.02
I
( )
IS
1
(Equation 3-3)
where:
top is operating time
TMS is the time delay settings
I is the fault current
IS is the pickup current
Equation 3-2 presents the equation of IEC Very Inverse curve. This is the
13.5
t op=TMS
I
( )
IS
1 (Equation 3-4)
where:
top is operating time
TMS is the time delay settings
I is the fault current
IS is the pickup current
substations. The North American IDMT standard characteristic curve, specifically ANSI
26
Very Inverse, was used in the SIEMENS 7SJ801 relay which protects Load C. The
[( ) ]
TD 19.61
t op= + 0.491
7 I 2
1 (Equation 3-5)
IS
where:
top is operating time
TD is the time dial
I is the fault current
IS is the pickup current
Equations 3-3 to 3-5 were used to plot a time-current curve (TCC) of the relays.
These equations are used to coordinate with the other relays of the system which is
step of the process is to determine if the relay the company commissioned will pass the
allowable time acceptance test. The Omicron CM256plus was used to determine if the
relay passes the standards. According to IEEE 60255, the manufacturer standards
determine if the relay commissioned pass the acceptance test. Omicron QuickCMC test
was used to determine the pickup time while the Omicron Overcurrent Test was used to
The pickup current of the relay is the first setting needed to be determined in the
study. From the substations specifications, the MVA rating is 100V and the line voltage is
69kV.
MVA
I FL=
3 X V L (Equation 3-1)
100 MVA
I FL=
3 X 69 kV
I FL=836.7395 A
To solve for the pickup current, Equation 3-2 was used. The overload factor used
by JEDDTECH is 1.1 to get the pick-up current for DOC. This overload factor is within
the range recommended by Gers & Holmes (2004). The full-load current of the system is
( overload factor ) x I FL
I P= (Equation 3-2)
CTR
1.1 x 836.7395 A
I P=
1200 /5
I P=3.835056136 A
The pick-up current to be set on the relays should be 3.84 A. However, the
relay settings only allow values of within the increments of 0.05 therefore the
nearest 0.05 increment should be set. The final pick-up current placed for DOC,
28
as seen in Table 3-2, is 3.85 A. 3.85 A is still within the range suggested by Gers
The directional earth fault pickup current is also calculated with the
Equation 3-2. The overload factor used by the company is 0.2. This factor is
( overload factor ) x I FL
I P= (Equation 3-2)
CTR
0.2 x 836.7395 A
I P=
1200 /5
I P=0.6972829338 A
The pickup current for the DEF settings should be 0.69728 A however the pickup
current input in the relays is limited to tenth decimal place, the current set is 700mA.
Since the pick-up current input in the relay is limited to tenth decimal place, the current
set is 700 mA. The final DEF settings left in the relay is seen Table 3-3.
After calculating the pickup current, coordination with the other relays is
needed to determine the correct TMS. Since most the relays to be coordinated use
have IEC Standard Inverse characteristic curve as well. The system is using
time-current curves for the upstream and downstream protective relays. To ensure
29
proper coordination, the time multiplier settings of the commissioned relay was
varied to determine the appropriate TMS for the system. Graphs with highest
downstream, should be the most appropriate value for TMS (Chung, Lu, Kao, &
Chou, 2008). As seen in Table 3-1, the TMS used by the company was 0.100
seconds.
Microsoft Excel was used to plot the time-current curves of the relays of
the system. The black represents the curve of the 69kV feeder relays while Load
A, Load B, and Load C relays is represented by green, gray, and blue curves
respectively. In Figure 4-1, the TMS of the 69kV feeder relay was set to 0.075
seconds.
100
10
1
1 10 100
operating time (seconds)
0.1
0.01
The TMS of the tcc curve of the relay for Figure 4-2 was set to 0.100 seconds.
100
10
1
1 10 100
operating time (seconds)
0.1
0.01
Figure 4-3 shows the graph of the 69kV relay set to 0.125 TMS. The intersection
with any of the downstream relays was higher with this setting in comparison to the two
graphs before but the intersection between the transformer relay was much lower.
31
100
10
1
1 10 100
operating time (seconds)
0.1
0.01
Base on the figures, the best TMS is 0.100 seconds. Figure 4-2 shows that
the first intersection is between 6 to 7 multiple of current. This is safe because the
maximum available fault current for the system is 4025 A which is 4.36 multiple
of pickup current. This means that it is impossible to reach any fault current
higher than 4025 A. Choosing 0.075 TMS or 0.125 TMS will put the intersection
below the maximum available fault current which means that there is a possibility
for miscoordination.
32
Like the coordination of directional overcurrent, the trip time of the downstream
relays should always be lower than the trip time of the 69kV feeder relay. The figures
below show different TMS values for the 69kV feeder relays; Figure 4-4 has 0.75 TMS,
Figure 4-5 has 0.0100 TMS, Figure 4-6 has 0.125 TMS, and Figure 4-7 has 0.150 TMS.
100
10
1
1 10 100
0.1
100
10
1
1 10 100
0.1
100
10
1
1 10 100
0.1
1000
100
1
1 10 100
0.1
The company used 0.100 TMS for DEF but, based on the figures, 0.125 TMS
using Omicron CMC256plus, is performed to check if the relay and its settings
will operate correctly. For both DOC and DEF, the Omicron QuickCMC was used
to perform testing on the relays characteristic curve and the Omicron Overcurrent
checking if the time-current curve behaves similar with its characteristic curve. The curve
that was set in the relay was IEC standard inverse curve. Using Omicron QuickCMC,
nine test points are considered. The points used started from 4.500A with an increment of
1.000A for every test point until 12.500A. Figure 4-8 and Figure 4-9 shows a sample test
point used. The full test report for MiCOM P14Dl can be seen in Appendix A while
Figure 4-8. Fault Calculator Settings for the Sample Test Point for DOC
Figure 4-9. Phasor diagram of the sample test point for DOC
4-1. In the same table, the trip time results are compared to the theoretical trip
TRIP TIME
SECONDARY
COMPUTED ACCURACY
INJECTION TEST
TEST RESULTS USING SI CURVE ERROR
CURRENT
FOMULA
4.500 A 4.511 sec 4.480 sec 0.69 %
5.500 A 1.993 sec 1.956 sec 1.15 %
6.500 A 1.373 sec 1.330 sec 3.27 %
7.500 A 1.076 sec 1.043 sec 3.19 %
8.500 A 0.913 sec 0.877 sec 4.12 %
9.500 A 0.811 sec 0.768 sec 5.60 %
10.500 A 0.721 sec 0.691 sec 4.38 %
11.500 A 0.655 sec 0.633 sec 3.52 %
12.500 A 0.624 sec 0.587 sec 6.23 %
37
its computed trip time. Looking at table 4-4, there are 4 points out of 9 that is out of
bounds of the accepted 4% timing accuracy error. To better illustrate the test points,
Figure 4-10 shows the graph of the test points represented by yellow curve.
100
10
1
1.15
0.1
69kV Load A
Load B Load C
Transformer 5 Curve Test - MiCOM P14DL
As seen in Figure 4-10, the test curve behaves similarly with the theoretical test
curve. Although 4 test points is not within the 4% timing accuracy error, the system is
The same test points used to test MiCOM P14DL were used in Schneider Electric
P127 testing since the relays have the same characteristic settings. The summary of the
TRIP TIME
SECONDARY
COMPUTED ACCURACY
INJECTION TEST
TEST RESULTS USING SI CURVE ERROR
CURRENT
FOMULA
4.500 A 4.600 sec 4.480 sec 2.67 %
5.500 A 2.008 sec 1.956 sec 2.68 %
6.500 A 1.370 sec 1.330 sec 3.04 %
7.500 A 1.078 sec 1.043 sec 3.38 %
8.500 A 0.908 sec 0.877 sec 3.55 %
9.500 A 0.799 sec 0.768 sec 4.03 %
10.500 A 0.727 sec 0.691 sec 5.25 %
11.500 A 0.666 sec 0.633 sec 5.26 %
12.500 A 0.624 sec 0.587 sec 6.23 %
Like the test points in the previous relay, the accuracy error was computed to
determine if the tripped time is within the standard range. There are also 4 out of 9 points
that went out of range. The characteristic curve of the test set is represented by the light
100
10
1
1.15
0.1
Figure 4-11. DOC Curve Test Results for Schneider Electric P127
It can be seen in Figure 4-11 that the test curve behaves like the theoretical curve
After testing the curve trip settings, the testing of the directionality of the relay
was done using the Omicron Overcurrent Test. The test checked for trip time when
overcurrent occurs at each phase, in two phases and in three phases. There are 7 possible
overcurrent type (A-B, B-C, C-A, A-B-C, A, B, C) with 32 test points each totaling to
224 test points. The injected currents and its results can be seen in Appendix B for
MiCOM P14DL and Appendix F for Schneider Electric P127. The same currents are
injected in both relays but they produced different trip times. Sample test points are
shown in Figure 4-12 while its test result is seen in Figure 4-13 for MiCOM and Figure
The sample test points used A-B type overcurrent with angle of 0 degrees and 45
degrees. The magnitudes of current used in any degree of test point is 6.00A, 7.00A,
8.00A, and 9.00A. The minimum and maximum trip time can also be seen in the Figure
4-12. This range is used to assess the trip time of the test result. The test result of the
sample test points for MiCOM can be seen in Figure 4-13 and Figure 4-14 shows test
Figure 4-13. Sample test points of MiCOM P14DL test resuls for directionality
41
Figure 4-14. Test result of sample test points for Schneider Electric P127.
The test points are also plotted in the test report. The test points are
illustrated through graphs with same angle and overcurrent type. A sample graph
for forward direction can be seen in Figure 4-15 while a reverse direction graph is
seen in Figure 4-16. These graphs represent both MiCOM and Schneider relays
test results.
inverse curve. The light blue is the acceptable trip time range of the relay. At the
90degrees angle, the relays should trip since it is in forward direction. Figure 4-16 shows
a sample a relay that was injected with the currents, represented by green arrows, but
there is no tripping because the angle was in reverse direction. The graphs of the tested
angles that trip and did not trip is summarized in Table 4-3.
All the types of overcurrent has the same response that is summarized in Table 4-
3. Overcurrent with angle difference from 45 degrees to 180 degrees showed no tripping
degrees, -135 degrees, -90 degrees, and -45 degrees show forward direction overcurrent
All the overcurrent that tripped in the test results showed overcurrent with
forward direction while reverse direction overcurrents have no response form the relays.
To include all the possible angles, Figure 4-18 show that shows all the correct tripping
angles in the forward operating region and reverse operating region at 30degrees RCA.
44
The summary in Table 4-3 can be represented by Figure 4-18. Based on Figure 4-
18, the trip results shown in Table 4-3 follow the appropriate trip settings with respect to
the direction of the overcurrent injected. It is necessary that the tests show correct
tripping with respect to the direction of the overcurrent so that proper discrimination is
achieved. The magnitude is important in determining the how fast the tripping response
time should be but the direction will determine the need for tripping and help provide the
The settings of the directional earth fault relay can be seen in table 3-3. Like the
directional overcurrent tests, two sets of tests were done. The use of Omicron QuickCMC
for the IDMT curve test and Omicron Overcurrent for the directionality test. A
comparison between the test results trip time and the computed can be seen in figure 4-3.
The analysis is the same for DOC and DEF test but different values was used.
The test results for Omicron QuickCMC of MiCOM relay can be seen in
Appendix C while Appendix G for Schneider relay. The DEF curve test considered 12
test points from 1.500A to 12.500A with 1.00A increment. A sample test point from
Appendix C can be seen in Figure 4-19 and Figure 4-20. This test point is also used to
Figure 4-19. Fault Calculator Settings for Sample Test Point for DEF
Figure 4-20. Phasor diagram of the sample test point for DEF
Figure 4-19 shows the values of an earth fault at phase A. Unlike the DOC
test points which used a three-phase overcurrent to test the curve settings of the
46
relays, the DEF test points used an earth fault at phase A of the injected current.
Figure 4-20 shows the phasor diagram of the test point. The summary of all the
test points trip time of both relays can be seen in Table 4-4.
TRIP TIME
SECONDARY
TEST RESULTS of COMPUTED
INJECTION TEST TEST RESULTS of
Schneider Electric USING SI CURVE
CURRENT MiCOM P14DL
P127 FOMULA
1.500 A 0.952 sec 0.952 sec 0.911 sec
2.500 A 0.581 sec 0.578 sec 0.542 sec
3.500 A 0.466 sec 0.467 sec 0.427 sec
4.500 A 0.406 sec 0.401 sec 0.369 sec
5.500 A 0.365 sec 0.363 sec 0.332 sec
6.500 A 0.339 sec 0.342 sec 0.307 sec
7.500 A 0.322 sec 0.321 sec 0.288 sec
8.500 A 0.304 sec 0.304 sec 0.273 sec
9.500 A 0.300 sec 0.299 sec 0.261 sec
To illustrate the test results, the MiCOM test result is graphed with the tcc of the
other relays in Figure 4-21 while Figure 4-22 shows the test result for Schneider.
47
10
0.1
10
0.1
Figure 4-22. DEF curve test results for Schneider Electric P127.
Both graphs show that they follow the trend of the theoretical characteristic curve.
The difference in trip time for both relays as compared to the theoretical value gets larger
as the current increases. This becomes more ideal to the coordination since the
intersection point of the relay gets further from the pickup point.
The test for directionality of DEF is done using the same test in DOC, Omicron
Overcurrent Test. There are only 96 test points used; 32 test point for three earth fault
types (A-N, B-N, C-N). Sample test points use for directionality testing is shown in
Figure 4-23. The full results of the test can be seen in Appendix D for MiCOM P14DL
Like DOC the magnitude of the injected currents are the same. The maximum and
minimum trip time can also be seen in the figure above. The assesment of MiCOM
Figure 4-24. Sample test points of MiCOM P14DL test results for directionality of DEF
From Figure 4-24, one test point failed the test. The test point tripped but because
the actual trip time of the relay is not within the range of acceptable trip time it failed the
test. The graph of the A-N type sample test is shown in Figure 4-25.
Aside for the trip point presented in Figure 4-25 three more have failed the
test. All the failed test points for both MiCOM and Schneider is summarized in
Table 4-6.
50
Table 4-6. Failed Test Points for Directionality of Earth Fault Relay
Although the test points tripped in the right direction, the trip time was not
within the range. All the test points follow correct direction trippingin Table 4-3.
Figure 4-18 represents the same directions of both relays. the correct
directionalityIt is seen in Table 4-6 that the failed points are different in both
relays. This is the reason why parallel relays are placed for its protection so that if
one relay fails another relay can respond. The faster trip time between the relays
will result to the trip time of the circuit breaker. Since in any of the failed trip time
the other relay worked perfectly the whole line is still protected by the relays
commissioned by JEDDTECH.
functionality test done through secondary current injection test. Omicron Test
the relay. For both directional overcurrent and directional earth fault, some test
points did not pass the acceptable timing accuracy difference. Generally, the curve
produced from the test points behave like IEC Standard Inverse curve. It can also
51
be seen from the graphs that as the fault current increase the difference between
the test results and the computed increases. The accuracy of the relays trip time
the directional overcurrent relay, there are no test points that failed. While in the
directional earth fault, 3 points failed. These points failed the test because the trip
time was not within the range of the accepted trip time. All test points, even those
out of bounds within the accepted trip time range, showed correct directionality.
Although some test points trip time was not within the acceptable trip
time range, the test results of both DOC and DEF showed correct characteristic
settings. The general assessment, since the relay still showed correct characteristic
6. RECOMMENDATION
The use of the same characteristic curve should be implemented to ensure the
proper coordination among relays. The relays in the considered did not use same
characteristic curves. It would be better if the settings of the other relays in the power
The use of powerful simulation tools can also be implemented to check the
coordination of the system. The directional properties of the relays would easily be seen
in this simulations tools. It would be better if the upstream relays are also considered. The
installation of other relay protection elements can be performed to better the protection of
7. REFERENCES
ALSTOM GRID. (2011). Network Protection & Automation Guide. Alstom Grid.
American National Standard For Electric Power Systems and Equipment - Voltage
Ratings (60 Hz). (2006). ANSI C84.1-2011.
Bakar, A. A., Ooi, B., Govindansamy, P., Tan, C., Illias, H. A., & Mokhlis, H. (2014).
Directional overcurrent and earth-fault protections for a biomass microgrid
system in Malaysia. Int J Electr Power Energy Syst.
Bakshi, U. A., & Bakshi, M. V. (2008). Protection and Switchgear. Pune, India: Technical
Publications Pune.
Birla, D., Maheshwari, R. P., & Gupta, H. O. (2006). A New Nonlinear Directional
Overcurrent Relay Coordination Technique, and Banes and Boons of Near-End
Faults Based Approach. IEEE Transaction on Power Delivery, 1176-1182.
Chung, J.-L., Lu, Y., Kao, W.-S., & Chou, C.-J. (2008). Study of Solving the
Coordination Curve Intersection of Inverse-Time Overcurrent Relays in
Subtransmission Systems. IEEE Trans. on Power, vol. 23, no. 4, pp. 17801788.
Elmore, W. (2003), Protective Relaying Theory and Applications 2 nd ed. New York:
Marcel Dekker.
Gers, J. M., & Holmes, E. J. (2004). Protection of Electricity Distribution Networks. IEE
Power and Enery series 47.
EEE POWER & ENERGY SOCIETY. (2009). IEEE Std C37.233-2009. IEEE Guide for
Power System Protection Testing. New York: Institute of Electrical and
Electronics Engineers (IEEE). doi:10.1109/IEEESTD.2009.5352213
Martin, C., Chase, S., Nguyen, T.-X., Hawaz, D., Pope, J., & Labuschagne, C. (2005).
Bus Protection Considerations for Varous Bus Types. 69th Annual Georgia Tech
Protective Relaying Conference. Atlanta, Georgia.
References
Alstom Grid. (2011). Network Protection & Automation Guide. Alstom Grid.
American National Standard For Electric Power Systems and Equipment - Voltage
Ratings (60 Hz). (2006). ANSI C84.1-2011.
Bakar, A. A., Ooi, B., Govindansamy, P., Tan, C., Illias, H. A., & Mokhlis, H. (2014).
Directional overcurrent and earth-fault protections for a biomass microgrid
system in Malaysia. Int J Electr Power Energy Syst.
Bakshi, U. A., & Bakshi, M. V. (2008). Protection and Switchgear. Pune, India: Technical
Publications Pune.
54
Birla, D., Maheshwari, R. P., & Gupta, H. O. (2006). A New Nonlinear Directional
Overcurrent Relay Coordination Technique, and Banes and Boons of Near-End
Faults Based Approach. IEEE Transaction on Power Delivery, 1176-1182.
Chung, J.-L., Lu, Y., Kao, W.-S., & Chou, C.-J. (2008). Study of Solving the
Coordination Curve Intersection of Inverse-Time Overcurrent Relays in
Subtransmission Systems. IEEE Trans. on Power, vol. 23, no. 4, pp. 17801788.
Gatdula, D. L. (2008, February 1). philstar.com. Retrieved from The Philippine Star:
http://www.philstar.com/business/41908/meralco-takes-over-clark-power-firm
Gers, J. M., & Holmes, E. J. (2004). Protection of Electricity Distribution Networks. IEE
Power and Enery series 47.
Martin, C., Chase, S., Nguyen, T.-X., Hawaz, D., Pope, J., & Labuschagne, C. (2005).
Bus Protection Considerations for Varous Bus Types. 69th Annual Georgia Tech
Protective Relaying Conference. Atlanta, Georgia.