Sei sulla pagina 1di 56

EAF-50t Electric Arc

Furnace

Technical Specifications

-0-
Contents

I. Technological conditions for 50t arc furnace. ......................................................................................... 2


II. Design technical parameters of 50t arc furnace .................................................................................... 3
III. Technical description for the electrical equipment of 50t electric arc furnace................................ 30
IV. Supply range of 50t electric arc furnace equipment........................................................................... 37
V. Accompanying spare parts for the equipment...................................................................................... 46
VI. Non-supply range45
VII. Design, manufacturing, quality control, outgoing-inspection and acceptance standard of
equipment..................................................................................................................................................... 46
VIII. Guarantee for equipment quality and performance ....................................................................... 47
. Technical documents and data delivery, technical service, equipment design, and supervision and
acceptance check ......................................................................................................................................... 49
X. Switchpoints of 50t arc furnace equipment .......................................................................................... 54
XI. Attached drawing ..................................................................................................

-1-
Technical Specifications for EAF-50t Arc Furnace
According to the technical requirements for 50t arc furnace equipment put forward by
Philippine Southern Steel Plant, the technological design scheme prepared by Shaanxi
Industrial Electric Furnace Manufacture Co., Ltd. is as follows: .

I. Technological conditions for 50t arc furnace

1. Process flow for electric furnace steelmaking


The steelmaking process and major equipment to be adopted are based on the selected steel
grade. The scheme is mainly for smelting of carbon steel the steelmaking process and the
major equipment are listed as follows:

1) Carbon steel

Arc furnace - LF - continuous casting

2. Arc furnace capacity and the tap to tap period

The relationship between the annual output of molten steel A and the electric furnace capacity
G is as follows:

24 60 B G N
A , where t

B - The annual working days of the electric furnace. The annual working days of the electric
furnace are 320 days and 320 days are adopted in this case. For the electric furnace and its
process, it is necessary to ensure sufficient maintenance time in order to implement high
power and high efficiency.

N - Number of the furnaces in the electric furnace workshop; two furnaces are to be built.

G - Average steel tapping of arc furnace; 55t on average.

- The tap to tap period of arc furnace; to be as per 68 min.

The actual annual output of molten steel by the two electric furnaces; to put the known data
into the above formula, we obtain the following,
24 60 320 55
A 2 =Approximately 745,411 tons.
68
Namely, the annual output of molten steel by these two 50t electric furnaces is about 745,411

-2-
tons.

3. Power consumption per ton of steel


To adopt the oxidation process to smelt structural steel with 50% steel scrap and 50%
molten iron , melting in the electric furnace and heating up to the temperature of tapping
(1630), the total power consumption shall be 610 kWh/t. Considering that the forced
oxygensupply by watercooled oxygen lance in furnace door is to be adopted, the total
oxygen blasting is 50Nm3, replacing about 180kWh of power; the energy provided by the
oxidation of graphite electrode is about 10kWh, and 50% molten iron , replacing about 200
KWh electrical energy.

The actual power consumption per ton of steel is 610-180-200-10=220 kWh

Namely, the actual electrical energy needed for melting, phosphorus removal and heating up
to the tapping temperature of 50% scrap steel and 50% molten iron in the arc furnace,
(1630) is 220 kWh/t (e.g. oxygen blasting50Nm3, metal charging 60%, electrical
consumption 160kWh/t).

4. Main technical and economic indexes of the electric furnace.

Main technical and economic indexes of the electric furnace are shown in Table 1-5.

Table 1-5 Main technical and economic indexes of arc furnace


Amount of Time of
transformer Average Max Cycle of Power Electrode
Type of oxygen oxygen
capacity tapping tapping smelting consumption of consumption
steel blasting blasting
/MVA output /t output /t /min smelting kWh/t /kg/t
/Nm /t
3
/min
Structural
22 55 60 68 220 <2.2 50
Steel
45

The key points to achieve the above indexes are: 1) Oxygen lance in furnace door; 2) the
secondary charging together with molten iron feeding thermal idle time should be less than 16
min.

The high-quality super high power graphite electrode shall be adopted.

II. Technical specifications and explanation of 50t electric arc furnace

1. Technical specifications for 50t electric arc furnace equipment

Technological conditions and technical parameters for 50t arc furnace

1.1 Technological conditions and main requirements

-3-
The process flow of electric arc furnace is: 50t arc furnace + 60tLF refining furnace +
continuous casting trinity process flow. Such techniques as furnace wall burner and
oxygen lance in furnace door are adopted in the arc furnace equipment and process. Carbon
steel is mainly produced.
Requirements for main process technical parameters of 50t arc furnace are shown in Table 2-1

Table 2-1 Requirements for main technical parameters of 50t arc furnace
No. Name Unit Parameter Remark
1 Number of furnaces in workshop Piece 2
2 Nominal capacity t 50 Alternating current
3 Average tapping of molten steel t 55
4 Max. tapping of molten steel t 60
5 EBT hot heel t 79
6 Tap to tap period Min 68 Mix 50% iron melt
7 Rated capacity of transformer MVA 22
8 Burner Piece 3 3-5 MW/piece

Requirements for main performance and technological guarantee values for the 50t arc
furnace equipment see Table 2-2

Table 2-2 Requirements for main performance and process guaranteed values of 50t arc
furnace equipment
No. Items to be checked Unit Parameter Remarks
1 Tap to tap period Min 68
2 Average tapping T 55
3 Average power factor 0.8
4 Three-phase impedance unbalanced coefficient % 5

1.2 Technical parameters on designing 50t arc furnace

According to Technological conditions and technical requirements, main technical parameters


of 50t arc furnace see Table 2-3

Table 2-3 Main technical parameters of 50t arc furnace


Name of technical
No. Specification /requirement Remarks
parameter
1 Nominal capacity 50t
Average
2 55t
tapping output
Quantity of EBT hot
3 79t
heel

-4-
Internal diameter of
4 5200mm
furnace shell
Rated capacity of the
5 22MVA Self-supply by user
transformer
Primary voltage of
6 34.5KV Frequency 60Hz
transformer
7 Secondary voltage 410V-320V-170V
17 grade electric pressure regulating
8 Voltage regulation mode
on load
9 Secondary rated current 39.692KA
10 Cooling mode Forced oil circulative water cooling
Three-phase impedance
11 5%
imbalance coefficient
Graphite electrode Super high power
12 450
diameter electrode
Electrode pitch circle
13 1200
diameter
Auto: hoist 6m/min fall 4m/min
14 Electrode lifting speed
Manual: hoist 9m/min; fall 6m/min
Max travel of electrode
15 3700mm
lifting
16 Tilting angle EBT tapping 20; slag tapping 12
Tapping; slag tapping 01/s; return
17 Furnace tilting speed
dumping 3/S
Hoisting height of
18 450mm
furnace roof
Lifting time of furnace
19 Hoisting 15sfall 20s
roof
Max Rotary angle of
20 75
furnace roof
Rotary time of furnace
21 Out/back 50s
roof
Dimension of the
22 1100mm800mm
furnace door
23 Hydraulic system
Working pressure 12MPa
Shenzhen Houghton
Working medium Water --glycol
Co., Ltd.
Oil tank electro-hydraulic
Electrode fluctuation
proportional valve
24 Pneumatic system
Consumption 5m3/min

-5-
pressure 0.4Mpa
25 Water-cooling system
Flow 620m3/h
Intake pressure 0.450.55MPa
Intake temperature 35
Temperature of backwater
Requirement for water
55
26
quality
PH value 78.5
Total hardness 10 DH
Suspended solid
Alkalinity
10mg/L

Chlorine ion Mean 60mg/L


60mg/L

Sulfuric ion
Conductance rate 50 mille Siemens /m
100mg/L

Hoisting weight of lower The weight of


27 90t
furnace body refractory is included

2. Technical description of 50t arc furnace

2.1 Outline of mechanical components of 50t arc furnace

Four bar linkage mode is applied in the mechanical structure of 50t arc furnace, and the layout
is the elevated type.

1) Furnace body

Furnace body is composed of upper furnace shell, lower furnace shell, furnace door
mechanism, eccentric bottom tapping mechanism, water-cooled furnace wall, intake and
backwater cut-off valve as well as metal flexible pipe. Detachable furnace shell is applied,
namely, it is possible for the furnace shell to be separated from the tilting cradle platform, and
it is also possible for the upper furnace shell to be separated from the lower one. 20g Seamless
frame structure with the wall thickness of water-cooled pipe12 is applied in the upper
furnace shell. The wall of water-cooled furnace is welded into water-cooled block with 20g
seamless pipe (the thickness is 8 ). Joints for the total water intake, backwater pipe of the
water-cooled furnace wall are arranged. The lower furnace shell is welded with steel plate
with thickness of 25mm, and the conic structure is applied at its bottom Taper pin is applied to
connect the upper furnace shell and the lower furnace shell. Taper pin is also applied to
connect the water-cooled furnace wall and the upper furnace. Water intake, backwater, total
water intake, total backwater pipe at each block of water cooled furnace wall are connected.
The flange is welded at the bottom of cylinder section of the lower furnace shell, the bore of
the flange shall be connected with tilting platform by taper pin, the furnace body is the

-6-
eccentric bottom tapping, and the furnace door is composed of furnace door and start-stop
mechanism. Additionally, the furnace door and drive shaft are cooled down by water pumping,
and the furnace door mechanism are closed and opened by the mode of hydraulic pressure
chain transition.

The basic composition of electric furnace body structure is shown in Table 2-4, and the main
technical parameters of electric furnace body are shown in Table 2-5.

Table 2-4 Basic composition of the shaft structure of electric furnace


No. Names of parts Quantity Description
1 Furnace body 1set
Frame of the upper furnace shell 1set
Water-cooled furnace wall 1set
Lifting mechanism of furnace door 1set Hydraulic type
Eccentric bottom tapping mechanism 1set Hydraulic type
Metal flexible pipe 1set
Water intake and backwater ball valve 1set
Lower furnace shell 1set

Table 2-5 Main technical parameter of the electric furnace body


No. Technical parameter Unit Specification/description
1 Internal diameter of furnace shell Mm 5200
Dimension of
Mm 18012
water-cooling frame pipe
Upper furnace Area of water-cooled
2 mm2
shell furnace wall
95%

Dimension of water-
Mm 7810
cooling furnace wall pipe
Thickness of steel plate Mm 25
Thickness of refractory at
Lower furnace Mm 700
3 the furnace bottom
shell
Molten steel volume mm3 7.5
Diameter of molten pool Mm 4300
4 Volume of melting pool (slag included) mm 3
9.2
5 Height of furnace shell Mm 3700
6 Dimension of furnace door Mm 1100800

2) Water-cooled furnace roof

The combination of big furnace roof and small central furnace roof is adopted in the furnace
roof, and two pieces are to be adopted in the design to facilitate transportation.

-7-
The comprises left-half roof, right-half roof, alloy receiving hopper mechanism, elbow for
dust removal and smoke discharge as well as central roof water-cooling ring. And the main
structural frame of left and right half roof shall be made into the shape of round ring with
19412 seamless steel pipe, which not only satisfies the requirements for strength of the
structural member but also can be used as total water intake and backwater pipeline.
Water-cooling pipelines shall be connected through the total water intake and backwater
pipeline.

Alloy receiving hopper mechanism, installed on the furnace roof, is composed of the hopper,
pneumatic valves, tipping tube and pneumatic system. The lower part of the tipping tube is
designed as the water-cooling structure. The pneumatic gate valve controls the start-stop
through electric directional-control valve of pneumatic system. When the alloy material is not
charged, the valve of the tipping tube should be closed to avoid the overflow of the smog. The
start stop of the gate valve is controlled by gas cylinder.

Water-cooling ring of central roof must be made into the inverse cone structure, and itself
shall be cooled by water pumping, the water intake and backwater pipes should all be
connected onto the total water intake and backwater pipes.

Small roof is of refractory knottier with three electrode openings (prepared by user).

The roof and inlet flux, pressure and the outlet water temperature of furnace body can be
tested by gauges and the results can be displayed on the computer.

The basic composition of water-cooled roof is shown in Table 2-6. The main technical
parameters of the water-cooled roof are shown in Table 2-7.

Table 2-6 Basic composition of water-cooled roof


No. Name of the parts Quantity Description
Including water-cooling frame and
1 Water-cooled roof body 1 set
water-cooling block
2 Small cover ring 1 piece To support the refractory materials
3 Metal flexible pipe 1 set
Water intake and backwater
4 1 set
ball valve
5 recevier device 1 set
Receiver hopper 1 piece
Tipping tube 1 piece It is water-cooling mechanism
Gravity valve plate 1 piece

Table 2-7 Main technical parameters of water-cooled roof


No. Technical parameter Unit Specification

-8-
/description
Dimension of water-cooling frame pipe Mm 19412
Dimension of water-cooling block pipe Mm 7010
Water-cooled External diameter of roof Mm
1
roof Height of roof Mm
5500

Diameter of electrode hole mm


1000

Electrode distribution ball diameter mm 1200


510

3 Receiving device Diameter of tipping tube mm 250

3) Furnace tilting mechanism

Furnace tilting mechanism is composed of cradle platform, tilting track, tilting hydraulic
cylinder and front bearing structure as well as platform bearing mechanism.

Cradle platform and cradle platform horizontal track are welded with steel plate. Cradle
platform is located at the side of tapping slag and adopts heat insulation protection with
bottom to avoid thermal deformation. The upper part of the tilting cradle platform is box-type
platform mechanism. There are two arc tracks with positioned pin in the bottom, and the
tilting track is the stripped plane one with drilling hole to facilitate accurate and reliable
positioning of arc track when rolling tilting furnace on plain rail. Synchronously, 4 positioned
pins are welded on the cradle platform to facilitate furnace installation.

The tilting hydraulic cylinder, controlled by proportional valve, consists of two piston
cylinders.

The lower bracket of the tilting hydraulic cylinder is fixed on the cement foundation and its
upper bracket is fixed on the lower part of cradle platform. The max. tilting angle is 20 while
tapping, and the inclined angle is 12 while tapping slag, the tilting speed is 0.8~1/s.
When the inclined angle of furnace body is 20, it is necessary to arrange the inclined angle
interlock protection device, and cut off the oil circuit immediately to avoid accidents resulting
from manual maloperation. The normal tapping inclined angle of eccentric bottom is 18,
and the rated steel molten can be spilled. In order to complete the operation of hot heel and
reserved slag, the special designs are made on the circuit of hydraulic tilting furnace, and thus,
it is possible to switch the operations in case of conventional tilt and quick tilt.

Hydraulic lock is equipped at two lower oil ports of tilting cylinders of furnace body to ensure
that the furnace body keeps motionless when the position of the tilting cylinder loses pressure ,
and thus, the safety of devices and the operators can be guaranteed.

The merits of the mechanism lie in the fact that such two control systems as manual control
handle and electric (switch) handle are arranged in the tapping process, which can improve
the reliability of tapping operation.

-9-
The front bearing mechanism is installed between stripe-shaped horizontal track and the
tilting oil tank to ensure that the arc furnace is in the horizontal state. The action of front
bearing mechanism is completed through driving of hydraulic cylinder. The platform bearing
mechanism on the cement foundation is installed under the tilting cradle platform. The
furnace shell cannot be shifted until the support of arc frame platform is protruded to prevent
the cradle platform from overturning. Smelting can be carried out only when the support of
arc frame platform is at the pin removal position and the horizontal mechanism has not in the
supporting state.

The basic composition of the tilting furnace mechanism is shown in Table 2-8. The main
technical parameter of the tilting furnace mechanism is shown in Table 2-9.

Table 2-8 Basic composition of the tilting furnace mechanism


No. Name of parts Quantity Description
1 Tilting cradle platform 1 Pc
2 Tilting track 2 Pcs.
3 Tilting hydraulic cylinder 2 Pcs. Piston cylinder
4 Front bearing mechanisms 1 set
5 Horizontal rear bearing mechanism 1 set
6 Rotary rail 1 Pcs.
7 Clinometer 1 set

Table 2-9 Main technical parameters of the tilting furnace mechanism


No. Technical parameter Unit Specification / description
Tilting angle o
EBT tapping 20/tapping slag 12
Titling
Tapping, tapping slag: 01/s
1 furance Tilting speed o
/s
resetting speed :3/s
mechnasim
mode PLC-Proportional valve
2 Inclinometer Scope of titling o
-15+20
Hydraulic cylinder Travel distance mm ~1400
3
of tilting furnace Diameter of piston mm 250
Front bearing Travel distance mm 450
4
hydraulic cylinder Diameter of piston mm 63
Rear bearing Travel distance mm 450
5
hydraulic cylinder Diameter of piston mm 63

4) Hoisting and rotary mechanism of roof

Hoisting and rotary mechanism of roof is composed of rotary frame, rotary track, rotary
hydraulic cylinder, hydraulic cylinder for hoisting of roof, chain pulley, chain, synchronizing
shaft and rotary interlock mechanism as well as column suspension clamp etc.

- 10 -
The rotary frame is welded with steel plate and connected on the tilting cradle platform by
rotating the big revolving plate. The three-phase column hole is drilled on the platform of two
layers. Two hoisting arms of the roof are welded on the upper layer platform of the rotary
frame, the lower part of which shall be cooled by water to avoid high temperature
deformation. The rotation of roof is driven by hydraulic cylinder.

The hydraulic cylinder, chain wheel, chain and synchronizing shaft of the lifting mechanism
are arranged on the hoisting arm separately. The two hoisting mechanism are connected
through synchronizing shaft so that 4 hoisting points of the roof can be hoisted synchronously
and make the roof stay horizontally in the process of hoisting. Lower part of the
synchronizing shaft is the water-cooling platform welded with steel plate, which is arranged
for operator and maintainers and also has the function of heat insulation on synchronizing
shaft. Since the water-cooling platform is connected onto the hoisting arm, and there is
guardrail at the external edge of the platform, the maintenance personnel can operate on the
operating platform across the ladder expediently.

On the Cradle platform, the rotary hydraulic cylinder makes the roof revolve by driving the
rotary frame.

The rotary interlock mechanism is installed on the side of the rotary frame, and the interlock
cylinder and the interlock weld are installed on the rotary frame, and the interlock bore seat is
welded on the cradle platform.

The basic composition of hoisting rotary mechanism for roof is shown in Table 2-10. The
main technical parameter of hoisting rotary mechanism for roof is shown in Table 2-11.

Table 2-10 The basic composition of hoisting rotary mechanism


No. Name of parts Quantity Description
1 Rotary frame of roof 1 nos.
2 Rotary mechanism of roof 1 set Four bar linkage mechanism
3 Hoisting mechanism of furnace 1set
4 Rotary interlock mechanism 2 sets
5 Rotary hydraulic cylinder 1 nos.
6 Hoisting hydraulic cylinder of roof 2 nos.
Chain pulley, chain, synchronizing
7 1 set
shaft
8 Post suspension tray 1 set
9 Limit switch 1 set

Table 2-11 Main technical parameters for hoisting & rotary mechanism of roof
No. Technical parameter Unit Specification description

- 11 -
Rotary angle o
~75
1 Rotation of roof Rotary speed /s
o
10
Control mode PLC-proportional valve
Height of lifting mm 450
2 Lifting of roof
Speed of lifting mm/s 100
Rotary hydraulic Travel distance mm 1200
4
cylinder Diameter of piston mm 140
Hydraulic cylinder Travel distance mm 450
5
of lifting Diameter of piston mm 125

5) Lifting mechanism of electrode

The lifting mechanism of the electrode is composed of lifting hydraulic cylinder of electrode,
lifting column of electrode, column lifting directive wheel devices, conducting cross arm,
electrode clamp, clamping butterfly spring as well as the parts of electrode relax hydraulic
cylinder, electrode sprinkling ring and clamp blowing.

Electrode lifting mechanism is the pipe-type mechanism; 45# steel is applied in the column
guide rail and its surface has better abrasion resistance after treatment of medium frequency
quenching. The upper bracket on the column is made of non-magnetic materials and the
column and cross arm have the better performance of insulation. Plunger piston hydraulic
cylinder is installed in the column; the automatic adjustment of the electrode lifting is realized
by electric hydraulic proportional valve, manual control can also be operated. The directional
wheel device can be adjusted from all directions to ensure the good operation of the electrode
lifting devices. Due to the fact that high power supply is applied, three-phase cross arm is
triangle shaped, and the heating of upper part of intermediate phase column is severe, it is
necessary to cool with water to avoid deformation of intermediate phase column and ensure
the reliable insulation of cross arm and column. The electrode lifting column guide rail adopts
medium carbon steel plate and suitable heat treatment process to enhance the abrasion
resistance and improve its service life.

Conduction cross arm is welded into water-cooling box-type structure by the application of
copper-steel composition plate. In accordance with the requirements of short net system
electric parameters, it is necessary to adopt triangle-shaped arrangement in the three-phase
cross arm and the cross arm should be cooled through water pumping inside. The connection
between the conduction cross arm and column should be pre-tensioning bolt mode, and a set
of special tool should be provided.

The main body of electrode clamping adopts red copper forging fittings and water-cooling
inside. Electrode unclasping brake is welded to be water-cooling mechanism by adopting
non-conducting magnetic austenite conductor stainless steel and the pressed block touched
with graphite electrode is insulated with the unclasping strip, then a layer of insulating

- 12 -
porcelain can be sprayed to ensure the reliable insulation. Electrode clamping relays on the
disc spring with small size and great elasticity and relax electrode is realized through
hydraulic cylinder compacting disc spring. The disc spring device and the relax hydraulic
cylinder are separate mechanisms and three phases can be switched to facilitate the
maintenance of hydraulic cylinder. Additionally, the electrode clamping head has the function
of automatic dust cleaning by compressing air.

The electrode spraying system is composed of stainless steel ring, water knockout drum and
valve as well as dashing system by compressive air.

The basic composition of the three-phase electrode lifting mechanism is shown in Table 2-12.
The main technical parameters of the electrode lifting mechanism are shown in Table 2-13.

Table 2-12 Basic composition of the three-phase electrode lifting mechanism


No. Name of parts Quantity Description
1 Electrode Lifting column 3 sets
2 Electrode Lifting Cylinder 3 sets
3 Lifting guide pulley 6 sets
4 Conduction cross arm 3 sets
5 Insulation members 3 sets
6 Connection members 3 sets Post and electrode cross arm
Electrode clamping
7 3 sets
device
Electrode enclapsing
3 nos
valve
Copper clip 3 nos
Single direction
3 nos
hydraulic cylinder
Used for interlocking the
Butterfly spring 3 sets
electrode
Clipping strip
3 sets
continous rod
Insulated material 1set
Water-cooling pipe 1 set
8 Electrode spraying devices 3 sets
9 Clip blowing device 3 sets

Table 2-13 Main technical parameters of the electrode lifting mechanism


No. Technical parameter Unit Specifiction /description
Electrode max upper or
1 Electrode lifting m/min 9m/6m/min
lower speed

- 13 -
Response time of the
ms 140
electrode
Control mode PLC-proportional valve
Electrode lifting Travel distance mm 3700
2
hydraulic cylinder Diameter of plunger piston mm 180
Diameter of electrode mm 450
3 Electode Ball diameter of the
mm 1200
electrode core
Travel distance mm 50
Electrode diameter of piston mm 200
4 releasing hydraulic Operation pressure MPa 9
cyclinder Clamping
kN 196
force

2.2 Water-cooling system and compressed air system

The cooling point of the water-cooling system for arc furnace comprises water use in such
circuits as transformer, copper pipe for electricity conducting, large cross section
water-cooling cable, conduction cross arm, electrode clamping head, electrode spraying, roof,
furnace wall, furnace door, furnace door frame, rotary frame lifting arm, rotary frame
platform, the upper electrode lifting intermediate-phase column and hydraulic station. Return
water with pressure is adopted for the water-using points of each circuit.

The main technical parameters of the water-cooling system see Table 2-14.

The header water inlet system is equipped with electric connecting pressure gauge, pressure
transmitter, hand stop valve, thermal resistance for temperature measurement and
electromagnetic flow meter; The flow switch and electromagnetic flowmeter are installed on
the crucial sub circuits such as water-cooled furnace wall, roof, conduction cross arm and
short net, and the thermometer and temperature sensor set on the return water subcircuits are
used for over temperature alarm.

Table 2-14 Main technical parameters for water-cooling system


No. Parameter Unit Specification /description
1 Total inflow system m3/h 620
2 Pressure of water inlet MPa 0.450.55
3 Pressure of return water MPa 0.2
4 Temperature of water penetration 35
5 Temperature of yielding water 55
6 Water consumption for accident Flux m3/h 150

- 14 -
Pressure Mpa 0.25

Compressed air is for pneumatic device, which provides roofs feeder hopper to start and stop
pneumatic cylinder, electrode clamping head and electrode spraying system. The system is
composed of pneumatic triplet, magnetic valve and pipeline, and the pressure of the system is
0.4-0.6Mpa.

2.2.1 Tipping device for hot metal ladle


2.2.1.1 Purpose and advantage
To place the hot metal ladle on the tipping frame and tip the hot metal adopting the tipping
cylinders on both sides, the hot metal shall steadily and uniformly flow into the arc furnace
through the hot metal chute-work so as to ensure the safety and reliability of the hot metal
flowing into the arc furnace and minimize the impact of the hot metal on the furnace lining.
The more important is that it shall not need power-cut and greatly save time for unscrewing
the furnace cover and improve the productivity and reduce the power consumption compared
with the unscrewing furnace top and pouring-in method.
2.2.1.2 Tipping device composition for hot metal
1. Cylinder seat, front seat 2 pieces respectively
2. Front and rear supports 2 pieces respectively
3. Tipping frame 1 piece
4. Hot metal chute-work 1 piece
5. Tipping cylinder 2 pieces
6. Water cooler 1 piece
7. Hot metal ladle 1 piece
8. Hydraulic device and operating stand 1 set
9. Other accessories

2.3 Hydraulic system

Hydraulic system serves as a hydraulic power device providing hydraulic drive for electrode
lifting and release, lifting and revolving of roof, furnace bodys tilting as well as the start-stop
of the furnace door and EBT steel tapping outlet.

1) Composition of hydraulic system

The hydraulic system is composed of such components as gasoline tank assembly, hydraulic

- 15 -
pump device, accumulator and control valve. The system is equipped with the filter such as
oil scavenger in order to improve the accuracy of the working medium of the system and the
operation reliability of the entire system. In order to meet the operation requirements of the
hydraulic system, the hydraulic system shall also be equipped with the hydraulic accessories
and the signal output unit components such as air filter, pressure gauge, pressure sensor,
pressure relay, hydraulic cooler and ball-type cut-off valve. In order to improve the control
accuracy and reliability, the system shall be equipped with individual cooling and circulation
circuit as well. All the joints of the hydraulic pipeline adopt 24conical ones.

2) Main performance parameters of the hydraulic system

The main performance parameters of the hydraulic system see Table 2-15.

Table 2-15 Main performance parameters of the hydraulic system of 50t arc furnace
Technical parameter Requirement Remark
Working medium Water-glycol Houghton(Shenzhen)Co.,
Ltd.
Working pressure of system 12MPa
Main pump generator capacity 30KW Two use one standby
Rated output of hydraulic pump 100L/min
Control voltage 24V
Effective volume of oil tank 4M3
Circulating pump
Capacity of generator 4KW
Working pressure 0.5MPa
Flux 50L/min
Intake pressure of cooling water 0.450.55MPa
Intake temperature of cooling water 35

3) Main control objectives and indexes of hydraulic system

Main control objectives and indexes of hydraulic system are shown in Table 2-16.

Table 2-16 Main hydraulic cylinders and indexes of 50t arc furnace
Name of hydraulic
No. Quantity Action Speed Remark
cylinder
up 15s
1 Lifting of roof 2 nos.
down 20s
Unscrew 20s
2 Rotation of roof 1 nos.
Screw 20s
Ascend automatically 6m/min Response
3 Electrode lifting 3 nos.
Descend automatically 4m/min 140ms

- 16 -
Ascend manually 9m/min
Descend manually 6m/min
01/s
4 Furnace body titling 2 nos. Tapping slag and inclining
03/s

4) Table for actions of all parts of hydraulic system

Actions of all parts of hydraulic are shown in Table 2-17.

Table 2-17 Actions of all parts of hydraulic system


Control
No. Name Forms of oil tank Remark
mode
1 Tilting of furnace body Manual Two way piston cylinder Operation bar
Horizontal front Two way rocking piston Alternation
2 Manual
support cylinder switch
Two way rocking piston Alternation
3 Horizontal rear support Manual
cylinder switch
Alternation
4 Arc frame locking Manual Two way piston cylinder
switch
Alternation
5 Hoisting of roof Manual Piston cylinder
switch
Two way piston cylinder Alternation
6 Rotary of roof Manual
switch
Automatic Alternation
7 Electrode lifting Plunger type cylinder
or manual switch
Alternation
8 Rotary locking Manual Two way piston cylinder
switch
Alternation
9 Electrode relaxing Manual One way piston cylinder
switch
Alternation
10 Maintenance platform Manual Two way piston cylinder
switch
Alternation
11 Eccentric bottom tapping Manual Two way piston cylinder
switch

5) Special precautions during design and manufacturing

Since the motive power of most actions of arc furnace equipment is provided by hydraulic
system, the reliability of the hydraulic system will impose a direct influence on the operation
rate and all consumption indexes of the arc furnace. To ensure the operation reliability of the
hydraulic system, the following measures shall be adopted in designing the hydraulic system.

a) The design and manufacturing of hydraulic system should comply with the principles of

- 17 -
simplicity, practicability, and reliability, and possess a higher integration, and facilitated
maintenance. The design of hydraulic station should meet the off-duty requirements.

b) The oil pump of the system adopts constant voltage variable pump with its configuration
mode as two-use and one-standby, 3 sets in total. Constant voltage variable delivery pump
adopts PARKER.

c) The stainless steel oil tank shall be adopted to reduce pollution of the hydraulic medium.

d) The proportional valve shall be adopted to control the electrodes lifting, furnace bodys
tilting and roofs rotation, and the rest are controlled by slide valve. PARKER shall be
adopted for proportional valve. There are three electrode-lifting valves, one furnace tilting
proportional valve as well as one roof rotary proportional valve.

e) Meanwhile, the following aspects shall be considered during the design of system:

f) In the unexpected state of power failure, the high-pressure liquid stored in the accumulator
shall enable the furnace body cradle platform incline to max. angle to return back to the
horizontal position, and enable the three-phase electrode to be lifted away from the surface of
molten steel.

g) Under the condition that power source is lost, the locking function is available to both
furnace body tilting circuit and electrode lifting circuit.

h) The electrode lifting control system has the function of automatic lifting to prevent the
electrode from being broken when it meets with non-conducting objects.

i) The selection of the hydraulic components is shown in Table 2-18.

Table 2-18 Selection of main hydraulic components of 50t arc furnace


Type of hydraulic components Manufacturers to be selected
Pump and proportional valve are
PARKER
included in the main hydraulic units
Filter of the system Wenzhou Leemin Hydraulic Machinery &
Electric Plant; BCB Filtration Technology Co.,
Ltd.
Oil tank hydraulic sealed components PARKER Busak+Shamban (Germany)

j) Hydraulic system is configured with cooling filter circulation circuit to ensure the operation
of the system within the normal range, and it can be guaranteed to automatically adjust the
temperature of the medium.

k) The sealing of the hydraulic cylinder shall be reliable, and the service life of sealing

- 18 -
components is shown in Table 2-19.

Table 2-19 Service lifers of sealing components of hydraulic cylinder


Furnace
Sealing Electrode Hoisting Rotary Electrode relax
tilting
components lifting cylinder cylinder of roof cylinder
furnace
Service life 12 months 12 months 12 months 12 months

6) Description of main functions of the hydraulic system

A) Oil tank assembly

a) Through primary calculation, the cubage of the stainless steel oil tank is 4m3.

b) Liquid meter and liquid level signal sender are arranged in the oil tank to alarm and signal
for the limit liquid levels. It also can take part in the control of PLC system.

c) There are two temperature controllers in the oil tank to alarm and signal for the upper and
lower limit temperatures. It also can take part in the control of PLC system.

d) The separate circulation filter cooling system is set in the oil tank, based on the control
requirement (12), and the medium of oil tank shall be filtered and cooled once per 30min to
meet the requirement of the hydraulic system for medium.

e) The oil tank is also equipped with such necessary accessories as air filter and drain.

B) Hydraulic pump device

a) The hydraulic system adopts 3 imported constant variable pumps with displacement of
100L/min, and its control mode is two-use and one-standby.

b) The driving power of the constant voltage variable pump is 30KW, which can meet the
requirement of the work pressure of the hydraulic system.

c) Every pump device is equipped with the pressure protection function and pressure filter to
ensure that high-accuracy working medium can be input to the system.

d) Hydraulic pump device is equipped with the hydraulic components such as single direction
valve and high-pressure spherical core cut-off valve and also equipped with hydraulic
accessories such as junction box.

e) Hydraulic pump device is equipped with pressure gauge, pressure measurement point and
pressure measurement device, and the tester can test the system at any moment.

- 19 -
c) Accumulator assembly

The main function of the accumulator is to satisfy the requirement of the high voltage liquid
reserved in the accumulator or to make the cradle platform return to the horizontal position in
the state of accident (or in the state of sudden power failure), and meet the requirement of
lifting the three-phase electrode 500mm away from the surface of molten steel.

D) Control valve unit

a) Control electrode lifting: Electrode lifting adopts 3 sets of electro-hydraulic proportional


valves, which automatically control three-phase electrode lifting respectively. Electrode lifting
control has self-locking function under the condition of losing power supply. Manual control
is utilized under special condition. Electrode lifting control circuit is furnished with pressure
sensors and can uplift automatically when meeting non-conductive objects to prevent
electrode from being broken.

b) Control rotation of roof: Adopt electro-hydraulic proportional reversal valve to make roof
realize slow start fast run slow control in the process of rotation.

c) Furnace body tilting adopts electro-hydraulic proportional reversal valve to meet the
requirement of fast tapping, slag-tapping, stability and reliability of furnace body. Meanwhile,
tilting control has self-locking function under the condition of losing power supply.

d) Control the unlocking of electrode: Adopt two-position four-way electromagnetic


directional valve with simple structure and reliable action.

e) Controls of other actions: Adopt slide valve to control them and different hydraulic
principles based on action control.

2.4. Oxygen lance

This set of system consists of furnace door carbon-oxygen lance and its accessories, fire wall
oxygen lance , carbon lance, oxygen valve station, hydraulic station, dusting system and PLC
control system, supervisor PC and cooling water system of furnace door carbon-oxygen
lance .

Automatic and manual operations of the whole system can be achieved.

All the key components shall adopt products with stable performances in order to ensure safe
and reliable operating of the whole system.

2.4.1 Furnace door carbon-oxygen lance system

- 20 -
2.4.1.1 Furnace door carbon-oxygen lance system consists of the following parts:

(1) Water-cooled oxygen lance and manipulator

(2) Hydraulic system

(3) Connection hose

(4) Cooling water system and monitoring (including water pressure, flow and water
temperature monitoring)

2.4.1.2 Main parameters of water-cooling oxygen lance and manipulator

Process parameters:

1) Oxygen supply strength: Max: 2500m3/h

2) Oxygen outlet speed: M=2.0-2.2

3) Oxygen work pressure: 1.0~1.2MPa(table)

4) Oxygen maximum pressure: <1.6MPa

5) Cooling water pressure: 0.5~0.7MPa

6) Cooling water flow: 80M3/h

7) Dusting speed: 10~50kg/min

Mechanical property of oxygen lance manipulator:

1) Maximum rotary angle of large arm: 90

2) Lifting travel of large arm: ~400mm

3) Speed of rotary cylinder: <20mm/s

4) Left-right tilt angle of oxygen lance : <20


5) Upper-lower tilt angle of oxygen lance : <8

6) Left-right tilt angle speed of oxygen lance : 0.5-1/s

- 21 -
7) Upper-lower tilt angle speed of oxygen lance : 0.5/s

8) There are two holes on the oxygen lance head: one is oxygen-injecting hole, the other
carbon-injecting hole.

2.4.1.3 Design features:

1) The included angle between oxygen jet expansion and surface of molten steel is 60.

2) Erection elevation of furnace door oxygen lance shall avoid that the height from oxygen
exit to steel liquid level is controlled about 200mm, or it can cause severe spraying of
molten steel and reduce the service efficiency of oxygen.

3) Oxygen lance head is coated with red copper.

4) Such medium as oxygen and cooling water adopt flexible metal tubes to complete the
connection between fixed end and movable end.

2.4.1.4 Connection hose

Such energy mediums as water and gas of water-cooling oxygen lance shall be connected
through stainless steel metal tubes with safe and reliable operating. Flexible metal tube is free
of warp. The system is set with header inlet water and header return water to supply oxygen.

Hydraulic energy medium of water-cooling oxygen lance can be connected through


high-pressure rubber hose.

2.4.1.5 Cooling water system

Furnace door system:

Equipment includes:

Inlet detection pipelines of cooling water system include pipeline, electro connecting pressure
gauge of inlet pressure, electromagnetic flow meter (Hermite);

Return water detection pipelines of cooling water system include pipeline, Pt100
Inlet pipe diameter of oxygen lance : DN80; (flange connection)
Backwater pipe diameter of Oxygen lance : DN80; (flange connection )

Furnace wall system: Taken from water-cooling frame of electric furnace. Supply inlet and
return water joints for oxygen lance and its water-cooling blocks respectively. (With stainless
steel ball valve)

- 22 -
Inlet pipe diameter of oxygen lance : DN32
Return water pipe diameter of oxygen lance : DN32
Inlet pipe diameter of oxygen lance water-cooled block: DN32
Backwater pipe diameter of oxygen lance water-cooled block: DN32

2.4.1.6 Composition of equipments

(1) Lance block of water-cooling supersonic oxygen lance ;


(2) Large arm of water-cooling oxygen lance ;
(3) Oxygen lance base;
(4) Driving and reversing, lifting, tilting mechanism of lance block;
(5) Hard tube and soft tube connecting various mediums
(6) Other accessories

2.4.2 Furnace wall oxygen lance

2.4.2.1 Equipment composition of furnace wall oxygen lance

(1) 3 sets of oxygen lance s + 2 sets of carbon lances


(2) Connecting flexible metal tube, fast joint, manual ball valve, etc.
(3) Specially made water-cooling module of oxygen lance

2.4.2.2 Parameters of oxygen lance

a) Oxygen max=~1200Nm3/h piece


b) Ma=2.1
c) Jet angle of oxygen: 35~45
d) Cooling water flow: 8m3/h.piece
e) Erection elevation: about 400~700mm (from steel liquid level)
f) Quantities: 3sets
g) Carbon lance: dusting speed 0~50kg/min
h) Quantities of carbon lance: 2sets

Technical description of coherent jet oxygen lance

Lance shall be mounted in the special water-cooling jacket in that water-cooling has a
protective effect on lance.

1) Outer diameter of lance body is ~120 mm, inner diameter is ~60 mm, adopting cooling
circulating water with high efficiency of thermal transmission.
2) Inner nozzle is furnished with copper sprinkler
3) Lance end is connected with process gas and cooling agent through flexible tube.

- 23 -
2.4.2.4 Water-cooling module

It is mounted on the furnace wall of electric furnace used for protecting oxygen lance .
Circulating water is in the same way with water-cooled furnace wall of electric furnace.

Specification: ~300*300mm
Mounted on water-cooled furnace wall
Quantities: 3 sets

2.4.3 Hydraulic station

Parameters shall meet the following requirements:


System work medium: water-glycol
Maximum work pressure: 8MPa
Work flow: 18L/min
Electric motor power: 3KW
Supply oxygen lance with its rotation (forward and backward), left tilting and right tilting,
elevating and falling hydraulic joints of its body.

2.4.4 Powder injection station:

Powder injection station provides carbon powder for carbon powder spray lance through
independent powder spraying system and sets 1 piece of carbon injection lance according to
the technological requirements. Powder injection station consists of pulverized coal injection
equipment, powder-storage warehouse, measuring system of electronic scale, valve and
control assembly. When the starting or stopping of powder spraying is needed, operating
personnel shall give corresponding orders. The starting or stopping of powder spraying shall
be controlled by PLC system based on the preset sequences and proceed automatically.

- Storage bunker of carbon powder


A storage bunker of carbon powder with capacity about 5 m3.

The storage bunker is enclosed. Bagged carbon powder can be added into the storage bunker.
The storage bunker is equipped with steel frame with ladder and is mounted with filter screen
as well.

- Conveying devices of carbon powder


Quantities: 3 (3 spraying blow pipelines can be installed)
Volume: 2.0m3
Delivery material: Carbon powder
Max. grain size: 3mm
Moisture of carbon grain: Max. 0.5%.

- 24 -
Delivery flow of carbon powder: Max. flow can reach 50 kg/min for per line
Consumption of N2 or compressed air consumption: About 300 Nm3/h for spraying
blow.

2.4.5 Oxygen valve station

This system is set with oxygen lance valve station of furnace door. Design shall be made for
each subcircuit according to the following principles:

Install flow measuring and adjusting devices for oxygen on each circuit.
Install pressure stabilizing and setting devices for oxygen on each circuit.
Control oxygen on each circuit separately.

Oxygen valve station consists of regulating valve, flow meter, differential pressure transducer,
pressure transducer, pneumatic ball valve, manual ball valve and cut-off valve, all of which
are necessary for the adjusting system of oxygen flow. The whole process of spraying oxygen
is controlled automatically through PLC control system in the smelting process.

Pneumatic membrane regulating valve is adopted on each subcircuit to synchronously adjust


oxygen flow and pressure to the value set and to provide stable pressure for supersonic
oxygen lance .

Orifice flow meter is adopted on each sub circuit for flow measurement and pressure
detection.

This system has the following oxygen sub circuits:


1) Oxygen control subcircuits of furnace door oxygen lance

-Each sub circuit mainly contains: manual oxygen cut-off valve 1 set
-Pneumatic membrane regulating valve 1 set
-Orifice flow meter 1 set
-Pneumatic control spheric valve 1 set
-Manual spheric valve 1 set
-Stainless steel conduit 1 set
-Pneumatic control air path 1 set
-Other accessories 1 set

Select types of equipments: Pneumatic membrane regulating valve selects Japan (Wuxi) tool
products and flow detection system adopts Sichuan Instrument and YOKOGAWA or E+H
products. Other valves adopt SHKVC products.

( 2 ) Oxygen control sub circuits of furnace wall oxygen lance

- 25 -
-Each sub circuits mainly contains: manual oxygen cut-off valve 1 set
-Pneumatic membrane regulating valve 1 set
-Orifice flowmeter 1 set
-Pneumatic control spheric valve 1 set
-Manual spheric valve 1 set
-Stainless steel conduit 1 set
-Pneumatic control air path 1 set
-Other accessories 1 set

Select types of equipments: Pneumatic membrane regulating valve selects Japan (Wuxi) tool
products and flow detection system adopts Sichuan Instrument and YOKOGAWA or E+H
products. Other valves adopt SHKVC products.

2.4.6. Control system:

This system adopts SIMATIC S7-300 PLC and forms the control system of integration of
electric-instrument. All inner wirings reach terminals and mainly perform program control on
such equipments as carbon-oxygen lance, powder injection station, oxygen valve station,
nitrogen (air) valve station, and hydraulic system. Joint is reserved for signaling with control
system of electric furnace in this system.

The detailed configuration for PLC cabinet sees the table below (Models are identical with
PLC of electric furnace)

External dimensions of PLC cabinet: 10006002200 (Doors in front and at back)

Quantity: 1 set for each electric furnace

Description Unit Quantity


PS307 5A power supply Piece To be determined
CPU314 Piece To be determined
Memory card 64K Piece To be determined
Guide rail 530mm Piece To be determined
32 points input Piece To be determined
32points output Piece To be determined
8 points AI Piece To be determined
4points AO Piece To be determined
CP5611 Piece To be determined
20pin connector Piece To be determined
40pin connector Piece To be determined
Programming software(step7) Set 1
Configuration software(Wincc) Set 1

- 26 -
Electrical cabinet Nos. 1

In charge of the HMI design of electric furnace oxygen lance system. Programming software
adopts WINCC6.0 (Models are identical with PLC of electric furnace).

2.4.7 Host computer system, namely, operator station (HMI)

According to the requirement of smelting technology, program control is performed on


oxygen spraying blow and process data are collected. Supervisor PC system adopts IPC, basic
configuration of which refers to: CPU P4 1GHz above, 1G Memory, 16M Graphic memory,
40G Hard disk, 40XCDROM, 17TFT, Programming software Wincc6.0.

Communication between PLC and host computer adopts PROFIBUS bus. Communication
between oxygen lance system and microcomputer system on the electric furnace adopts
PROFIBUS communication joint to transmit data. (Models are identical with PLC of electric
furnace)

HMI are as follows:

They are used to display main operational parameters of whole electric furnace
oxygen-supply equipments, including:

Running state of oxygen lance equipments/running state of oxygen control/running state of


cooling water/running state of nitrogen system/running state of hydraulic system/gas
consumption and accumulative measurement of this furnace smelting.

The system can set and trace the operation mode of oxygen lance in real time and TFT image
is set with oxygen-supply curve.

Functions of computer system

Functions of monitoring software of host computer are as follows:

( 1 ) On-line monitoring of equipment running condition;


( 2 ) On-line alarming is performed for equipment fault;
( 3 ) Automatic control is performed for oxygen use process;
( 4 ) Manual intervene function

3 burners of furnace wall oxygen are mounted on furnace body and pore for burners and fixed
bearing of burners are opened and installed on furnace jacket to ensure the normal use and
convenient mounting and dismounting of burners.

Furnace door carbon-oxygen lance is water-cooling type and has functions of front and back

- 27 -
expansion, left and right rotation, and up and down adjustment. Oxygen-supply system
contains pressure-regulating valve, flow regulating valve, etc.

Basic composition of water-cooling oxygen lance is shown in Table 2-20. Main technical
parameters of water-cooling oxygen lance see Table 1-21.

Table 1-20 Basic composition of water-cooling oxygen lance


No. Names of parts Quantity Description
1 Supporting mechanism of oxygen lance 1 set
2 Clamping device of oxygen lance barrel 1 set
3 Feeding device of oxygen lance barrel 1 set
4 Swing mechanism of lance barrel 1 set
5 Regulating valve platform of oxygen 1 nos.
6 water-cooled stop plate 1 nos.
7 Hydraulic system 1 set

Table 1-21 Main technical parameters of water-cooling oxygen lance


No. Technical parameters Unit Specifications/description
Water-cooling
1
oxygen lance
Oxygen-blowing quantities Nm3/t 4555
Max. flow of oxygen Nm /h3
2500
Swing angle
2 of lance Rotary angle
barrel
90

Horizontal tilting angle


Vertical tilting angle
15
15

2.4.8 Operation desk

It is used to control the running of oxygen lance system and stainless mesa. On the desk are
operation buttons of furnace door oxygen lance, cooling water, oxygen and nitrogen or
compressed air alarm.

Interference in accidental state of whole system is considered for furnace wall on the furnace
foreground.

Wireless remote controller is adopted to operate and control furnace door carbon-oxygen
lance .

2.4.9 Medium pipeline and other erection materials

- 28 -
Medium pipeline of oxygen lance system consists of running piping of oxygen and cooling
water piping of oxygen lance . Other erection materials roof all materials including electrical
erection materials.

2.5 Short net system

Short net consists of flexible compensator, water-cooled conductive copper pipe, large section
water-cooled cable, copper-steel composite conductive cross arm and cable joint after
transformer has inclined out of copper pipe twice. Strutting pieces adopt nonmagnetic steel
plate bracket and insulator. Flexible compensator adopts soft strand cable.

Main technical parameters: impedance value of short net is 0.65+j2.75m and


unbalancedness degree of three-phase impedance is 5%.

Adoption of flexible compensator and large section water-cooling cable can simplify the
structure of short net, lower the impedance of short net, and reduce the workload of
maintenance as well.

Short net system (including conductive cross arm) shall adopt triangle layout to guarantee that
unbalanced coefficient of three-phase impedance is controlled within 5%. Water-cooling cable
shall select large section ones with area of 2400mm2 with 4 pieces for each phase.

The basic composition of short net system of electric furnace sees Table 2-22. Main technical
parameters of short net system see Table 2-23.

Table 2-22 Basic composition of short net system of electric furnace


No. Name of parts Quantity Description
Water-cooling
1 12 pieces
cable
Adopt ones with 2mm outcoating
Rubber flexible pipe 12 pieces
silicon rubber and spacer ring
Attached with cooling water
Steel terminal 12 nos.
connecting mechanism
Bolt 1 set Made by nonmagnetized steel
2 Flexible compensator 12 nos. Soft steel strand
3 Water-cooled conductive copper pipe 12 pieces Triangle layout
Made by nonmagnetic steel,
4 Stainless steel bracket 1 set
attached with nonmagnetic bolt
5 Insulative component 1 set Used for supporting structures
6 Sealing plate 1 set

- 29 -
Table 2-23 Main technical parameters of short net system
No. Technical parameter Unit Specification/
Description
1 Rated current kA 39.692
2 Max. current density in tubular bus bar A/mm2 4.5
Number for every
PCS 4
3 Compensator phase
Max. current density A/mm2 3.5
Number for every
PCS 4
4 Water-cooled cable phase
Max. current density A/mm2 4.5

III. Technical description for electrical equipments of 50t electric arc furnace

1. High voltage power supply system

High voltage power supply system (abbreviated as the metal-clad switchgear) consists of
incoming cabinet (High-voltage fuse, voltage transformer, etc.); hand buggy vacuum switch
cabinet (consisting of vacuum circuit breaker, current transformer, etc.); hand buggy
over-voltage protection cabinet (consisting of over-voltage protection devices) and three-side
high voltage cabinet.

The system has a set of alternate hand buggy vacuum switch (excluded in supply scope).
When the work high voltage vacuum switch is at fault (or frequency of use reaches limit
value), vacuum handcart can be pulled out for maintenance or change and standby handcart be
put into use for shortening the time of blow-off due to failures.

High-voltage side secondary measurement circuit is set with high- voltage, high-voltage
current, power factor, active power, and measurement of active electrical degree and reactive
electrical degree. Active electrical degree and reactive electrical degree of each furnace of
steel can be consulted on HMI interface LCD of EAF furnace.

Secondary protection circuit is furnished with perfect protection measures as over-current


protection, under voltage protection and transformer heavy gas, oil temperature limit, and
coolers failure.

The principle of high voltage power supply system is shown in the attached drawing. Main
parameters of high pressure switch cabinet equipments are as follows:

1) Voltage transformer

Table 3-1 Main technical parameters of voltage transformer


- 30 -
Transformation ratio 35000/3- 100 /3 -100/3 kV
Basically secondary coil 100/3
Capacity 30VA
Accuracy 0.5 grade

2) Vacuum circuit breaker

Table 3-2 Main technical parameters of vacuum circuit breaker


Model VD4-1600-31.5(ABB)
Rated voltage 35kV/60Hz
Max voltage 35kV
Rated current 1600A
Rated current of short-circuit break 31.5kA
Rated withstand voltage of lightning impulse 185kV
Rated withstand voltage of power frequency (1m) 95KV
Mechanical life 10000
Spring operation (motor or manual
Operation mode
energy storage)
Rated voltage of energy-storage motor DC220V/AC220V
Energy-storage time 15s

3) Current transformer

Table 3-3 Main technical parameters of current transformer


Specification 800/5A
Rated voltage 35kV/60Hz
Transformation ratio 800/5A

4) Combinatorial over-voltage protective device

Table 3-4Main technical parameters


Model DCB-Z/35
Rated voltage of the system 35KV

2. Transformer of 50t electric arc furnace

Transformer of 50t electric arc furnace adopts the 22MVA transformer, including other
auxiliary equipments of the old transformer. (e.g: oil water cooler and control casing of
transformer and all the control signal drawings of old transformers and oil water cooler shall
be provided for the equipment modifier.)

According to the technological conditions and requirements of 50t electric arc furnace, main

- 31 -
parameters of the old transformer see Table 3-7 respectively.

Table 3-7 Main parameters of old transformer


Names of
Specification Names of parameters Requirement
parameters
Model of
22MVA/34.5KV Operation conditions Indoor
transformer
Rated capacity 22MVA Cooling mode OFWF
Secondary rated On-load voltage
410V-320V-170V Voltage regulation mode
voltage regulation of 17 grades
Secondary rated
39.692KA Connection group code Yd11
voltage
Frequency/phase Modes of leading in
60Hz/3 Jacking and ejecting
numbers and outgoing wires
Impedance
~7% Insulation level LI200AC85/AC5
voltage-drop

3. Technical description for low-voltage electrical system of 50t electric arc furnace

Low voltage electrical system of electric furnace consists of low voltage switch cabinet and
automatic control system with such features as:

(1) Adopt Siemens S7-300 PLC with high reliability.


(2) Adopt transducer of current and voltage with Hall high-precision and high-isolation
voltage.
(3) Isolate all the input and output signals completely.
(4) Adjuster shall adopt self adaptive PID algorithm and automatically revise PID parameter
on line to ensure that the system is stable in every stage of smelting and three-phase power
is balanced.

3.1 Setting of low-voltage electrical system board and cabinet

Board and cabinet of 50t electric furnace are shown in Table 3-8.

Table 3-8 Board and cabinet of 50t electric furnace


No. Name Quantity Installation site
1 Low voltage incoming cabinet 1 Master-control room
2 Power cabinet 1 Master-control room
3 Measurement cabinet 1 Master-control room
4 PLC cabinet of electrode control 1 Master-control room
5 PLC cabinet of furnace body action 1 Master-control room
6 DC supply cabinet 1 Master-control room

- 32 -
7 Hydraulic Cabinet (ET200) 1 Hydraulic room
8 Main operating console (ET200) 1 Master-control room
9 Front furnace operating console 1 Front furnace platform
10 Back furnace operating console 1 Back furnace platform
11 Computer console (Stainless steel panel) 1 Master-control room

1) Low-voltage incoming cabinet

Accept the power supply of low-voltage system from workshop substation (three-phase
four-wire 440/260V). Supply power for the power-driven equipments in the supply range. The
main knife-blade switch and main circuit breaker are inside the cabinet and shall be connected
to the circuit breakers of each line through low-voltage busbar (dynamic cabinet, etc.)

2) Power Cabinet

Low-voltage busbar shall be led to the low-voltage incoming cabinet and supply power
through the branch circuit breakers for the following: eliminator power of high-voltage
vacuum switch on-off, auxiliary control device, carbon-oxygen lance, charging system motor,
converter, and hydraulic system electric igniters.

After the power is stabilized by another circuit through isolation transformer and UPS direct
current 24V, it shall be supplied for electrode control PLC, furnace body PLC, and direct
current 24V power-driven equipments.

3) Signal measuring cabinet (to be determined)

Signal transducers such as built-in voltage meter, ammeter, energy meter, overcurrent relay,
temperature, pressure, flow, ect., which are used for display of current once, voltage once,
active electrical degree, reactive electrical degree, active power, and power factor. Secondary
over-current protection;

4) Electrode control PLC cabinet

Inside are a set of PLC, arc current transducer, arc voltage transducer, programmable
controller modular and exit relay. Collecting, handling, output of various signals related to
electrode control shall be done by the devices in the cabinet.

5) Furnace body action PLC cabinet

Inside are PLC and relay. Various signals, collected on the arc furnace site, such as position,
temperature, flow, and operating instructions, shall be sent to the PLC in the cabinet and, after
the processing of PLC program, corresponding output signals shall be sent to the executive
module to fulfill the corresponding actions.
- 33 -
6) DC supply cabinet

Supply 40Ah DC power supply and operation power supply of HV switchboard vacuum
circuit breaker.

7) Hydraulic cabinet

A set of ET200PLC is mounted inside; Start/stop buttons of hydraulic pump and circulating
pump as well as pump run indication and alarm indication of hydraulic station are mounted on
the slab. In the cabinet is arranged a suit of Siemens ET200 which is communicated with
CPU315 through Profibus. Working conditions of hydraulic station are displayed on HMI.

8) Master operating console

A set of ET200PLC is mounted inside. Master operating console contains: arc current display,
arc voltage display, shift control and display of transformer, setting and display of arc current,
control of vacuum switch on-off, electrode lifting, automatic control, status indication of main
equipments, etc. Any operation in the process of electric furnace smelting shall be done on the
master operating console.

9) Front-furnace operating console

Roof ascending, descending, uncovering, turning, furnace body front tilting, back tilting,
horizontal supporting move, rotary lock-in, furnace door opening, closing control, three-phase
electrode loosening, charging valve control, etc.

10) Back-furnace operating console

Rapid front tilting and back tilting of operation furnace body, opening, closing, and
maintenance console rotation of tapping hole, and tapping vehicle control.

11) Computer console

Stainless steel panel. Two sets of IPC, keyboards, mice, and displays are placed on this
platform where operators can perform operation. With convenient operation, working
conditions of the furnace can be seen clearly on HMI. The two sets of IPC shall be hot
standby for each other.

3.2 Automatic control system

3.2.1 General structure of control system

- 34 -
Automatic control system of electric furnace adopts the computer distributed control system.
Programmable controllers applied for electrode control and furnace body action and industrial
control computer of monitoring shall be connected together through PROFIBUS.

3.2.2 Computer hardware and software configuration

1) Programmable controller

Adopt S7-300 series programmable control of SIEMENS Company.

2) HMI station

Select Dyer work station (CPU P4/3.0G, Memory 1G, Hard Disk 160G, CD-ROM 40X)

3) Display

Adopt Samsung 17LCD.

4) Printer

Samsung A4 laser printer.

5) UPS power supply

Select Santak company UPS power supply (5KVA/30min)

6) System software

Operating system: WindowsXP


Configuration software: WINCC6.0 (1024 Point)
Programming software: STEP7 5.4 (Authorized)

3.2.3 Functions of computer control system

1) Basic automation

Basic automation system mainly completes the following functions: collecting process
variable, system state, line data process of inlet and outlet, logical decision, closed circuit
control signals, output system state, action orders, control signals, etc.

Electrode control is an important part in the basic automation. Quick and accurate electrode
control is a key of shortening smelting period, saving electric energy, and lowering electrode
consumption.

- 35 -
Constant Impedance Control shall be adopted to reduce the mutual influence of three-phase
electrodes as possible.

Given U indicates arc voltage, and I indicates arc current, control deviation shall be defined
as:

e=KUU-K1I

Among which, Ku is voltage coefficient, decided by voltage grade; Ki is current coefficient,


decided by expected arc current.

Control aims at making control deviation tend to zero, that is e=KuU-KII=0

So:

Constant impedance control strategy can not be removed though it can reduce the mutual
influence of three-phase electrodes. Control structure of feed forward and feedback is utilized
to reduce unnecessary electrode control.

Feedback loop adopts self-adaptive PID control calculation (Here self-adaptation mainly
solves such problems as unknown system parameter, arc amplification parameter
time-variation, and stochastic disturbance).

Feed forward loop is used to calculate the additional compensation signals of this phase
control when two-phase current changes.

Electrode control system shall ensure that the spot welding is smooth and arc short-circuit
one-phase can be removed rapidly but not break the arc. For electric furnace, electrode can lift
automatically if electrode end touches non-conductive charge (mounting pressure sensor is
necessary in hydraulic pipeline).

2) HMI display

On the operation station, human-computer conversation can be conducted, and computer can
show the failure information and running status and give the corresponding operation guide.
Computer can also receive the operation orders from the keyboard and set expected value and
confirmation of empirical value to facilitate operation, optimize the set value, fault shaping.
Main sheets and images are shown in Table 3-9.

Table 3-9 Main sheets and images


No. Contents of images No. Contents of images

- 36 -
1 Loading condition of scrap steel 10 Accumulation of energy input
Electric furnace power supply system
2 Accessories adding condition 11
drawing
3 Power supply condition 12 Electrode control status drawing
Oxygen-blowing condition and Schematic plan of furnace body of
4 13
accumulation electric furnace
Schematic plan of spraying blow
5 Time record of smelting period 14
status of oxygen
Record of molten steel temperature
6 15 Cooling water system drawing
measurement
Record of testing results of molten steel
7 16 Cooling water system drawing
components
8 Weight of molten steel 17 State table of input/output points

9 Energy-set curves 18

3.2.4Input and output signals statistics of computer control system

1) Analog input 32 line

2) Analog output 5 line

3) Switching value input 158 point

4) Switching value output 162 point

IV. Supply scope of 50t electric arc furnace equipment

- 37 -
Table 4-1 Detailed list of supplying 50t electric arc furnace equipment

Basic Basic Detailed


No. Item Quantity Weight/ton Supply Installation Debugging Remark
information design design

1 Furnace body 1 set S S S S S S


Upper furnace shell
(pipe type water 1 set S S S S S S
cooling)
Lower furnace shell 1 set S S S S S S
Water-cooled furnace
1 set S S S S S S
wall
Furnace door
1 set S S S S S S
mechanism
Eccentric bottom
1 set S S S S S S
mechanism
Metal flexible pipe 1 set S S S S S S

Connector 1 set S S S S S S

2 Water-cooled roof 1 set S S S S S S

Roof 1 set S S S S S S

Central water-cooling 1 set S S S S S S


Alloy
1 set S S S S S S
feeder mechanism

- 38 -
3 Tilting furnace device 1 set S S S S S S

Cradle platform 1 set S S S S S S

Tilting rail 2 set S S S S S S


Front supporting
1 set S S S S S S
mechanism
Back supporting
1 set S S S S S S
mechanism
Tilting furnace oil tank
2 sets S S S S S S
and connector
Hydraulic connecting
1 set S S S S S S
flexible pipe
Roof hoisting and
4 1 set S S S S S S
revolving device
Revolving bracket and
1 set S S S S S S
revolving mechanism
Maintenance platform 1 set S S S S S S

Guiding rolling wheel 12 sets S S S S S S


Roof hoisting
1 set S S S S S S
Mechanism
Roof
2 sets S S S S S S
Hoisting oil tank
Revolving oil tank 1 set S S S S S S

- 39 -
Locking device 1 set S S S S S S

Guardrail 1 set S S S S S S

Post bracket 1 set S S S S S S


Electrode lifting
5 1 set S S S S S S
mechanism
Intermediate-phase
1 set S S S S S S
conductive cross arm
Side-phase conductive
2 set S S S S S S
cross arm
Electrode clamping
head 3 sets S S S S S S

Electrode band type


3 sets S S S S S S
brake
Electrode clamping
3 sets S S S S S S
device
Middle-phase lifting
1 set S S S S S S
post
Side-phase lifting post 2 sets S S S S S S
Electrode lifting oil
3 sets S S S S S S
tank
Insulation component 3 sets S S S S S S

Electrode spray ring 3 sets S S S S S S

- 40 -
Hydraulic flexible pipe 1 set S S S S S S

6 Short net 1 set S S S S S S

Flexible connection 12 sets S S S S S S


Conduction
12 sets S S S S S S
Copper pipe
Water-cooling cable 12 sets S S S S S S

Stainless steel bracket 1 set S S S S S S

Insulation component 1 set S S S S S S

7 Hydraulic system 1 set S S S S S S Haimen oil power

Proportional valve 5 sets S S S S S S PARKER


Constant voltage Two use
variance plunger one S S S S S S PARKER
pump standby
Stainless steel oil tank 1 set S S S S S S

Accumulator 1 set S S S S S S
Various of action
1 set S S S S S S
valves
Cooling device 1 set S S S S S S

Other various of valves 1 set S S S S S S

- 41 -
8 Water-cooling system 1 set S S S S S S

Flux meter 2 sets S S S S S S

Pressure transmitter 1 set S S S S S S


Temperature
1 set S S S S S S
transmitter
Pressure gauge 2 sets S S S S S S

Temperature gauge 12 sets S S S S S S

Distribution reservoir 1 set S S S S S S

Various of Valves 1 set S S S S S S


Compressed air
9 1 set S S S S S S
device
Valve stand 1 set S S S S S S

Pneumatic triplet 1 set S S S S S S

Magnetic valve 1 set S S S S S S

Valve 1 set S S S S S S
Self-prepared by
10 Transformer
user
Low voltage Schneider
11 1 set S S S S S S
electric control system components

- 42 -
1# distribution
1 Pc. S S S S S S
cabinet
2# distribution cabinet 1 Pc. S S S S S S
Hydraulic control
1 Pc. S S S S S S
cabinet
Signal measurement
1 Pc. S S S S S S
cabinet
Main operation console 1 Pc. S S S S S S

PLCcabinet 1 Pc. S S S S S S

PLCcabinet 1 Pc. S S S S S S
Front furnace operating
1 Pc. S S S S S S
console
Back furnace operating
1 Pc. S S S S S S
console
Determined on site
Site operating box 1 Pc. S S S S S S
situation
Including power
Temperature
1 set S S S S S S display instrument
measurement device
of large-screen
Xian High Voltage
Apparatus
35KV high voltage
12 1 set S S S S S S Research
system
Institute.
Xian HighVoltage

- 43 -
Switch Co., Ltd

Incoming cabinet 1 Pc. S S S S S S


KYN-40.5 Cabinet
Circuit breaker cabinet 1 Pc. S S S S S S
type
Protection cabinet 1 Pc. S S S S S S
Rechargeable
DC Supply Cabinet 1 Pc. S S S S S S
Batteries
13 Automation system 1 set S S S S S S
Electrode control PLC
1 set S S S S S S S7--300
of electric arc furnace
Ontology control PLC
1set S S S S S S S7--300
of electric arc furnace
HMI 2 sets S S S S S S

Main control console 1 set S S S S S S


EBT maintenance
14 1 set S S S S S S
platform
Furnace door and
15 furnace wall oxygen 1 set S S S S S S
lance
Furnace door carbon
oxygen lance and 1 set S S S S S S
accessories

- 44 -
Furnace wall oxygen
3 sets S S S S S S
lance and accessories
Furnace wall carbon
2 sets S S S S S S
lance and accessories
Oxygen valve station 1 set S S S S S S
Powder injection
1 set S S S S S S
system
Hydraulic station 1 set S S S S S S

Cooling water system 1 set S S S S S S


PLC and control
1 set S S S S S S
system
Electrode lengthen
16 4pieces S S S S S S
station

Note: S represents supplier, B represents purchaser.

- 45 -
V. Carried spares

List of carried spares of the equipment provided by seller to purchaser


Name of spare parts and Quantity of equipment used Quantity of random
No.
components (single set ) spare parts
1 Sealing components gas One set respectively 2 sets respectively
cylinder and oil cylinder
2 O-type sealing component One set respectively 2 sets

3 Electrode clamping head 3 pieces 1 piece

4 Electrode band type brake 3 pieces 1 piece

5 Cross arm insulation 3 sets 1 set


component
6 Proportional valve 5 pieces 2 pieces

VI. Non-supply scope

The general non-supply scope sees Table 6-1.

Table 6-1 Non-supply scope of 50t arc furnace


No. Name of non-supply articles No. Name of non-supply articles
1 Refractory needed by the 5 Transformer, transformer rail and accessories
equipment
2 Graphite electrode 6 Anchor bolt and other unforeseeable
materials needed in the erection of equipment
3 Various lubricant grease, 7 HV cable between electrical equipments such as
hydraulic transmission medium transformer and HV cabinet and its conduit
and other energy medium fastener, fence and relevant installation
materials
4 Various alloy materials and
slag charges for production

VII. Design, manufacturing, quality control, outgoing-inspection and acceptance


standard of equipments

1) GB/T 10067.1-2005 Basic specifications for electro heat installations-General


2) GB/T10067.2-2005Basic specifications for electro heat installations - Steelmaking
arc furnaces

- 46 -
3) GB5959.1-2005 Safety in electro heat installations -General
4) GB5959.2-1998 Safety in electro heat installations - Particular requirements for
arc furnace installations
5) GB50056-1993 Code for design of electric equipment of electro heat installations
6) GB5083-1999 General rules for designing the production facilities
in accordance with safety and health requirements
7) GB/T 1066.1-2004 Test methods for electro heat installations
8) GB/T 4879-1999 Rust cover packaging
9) JB/T 5000.1-1998 The heavy mechanical general techniques and standards - Product
Inspection
10) JB/T 5000.2-1998 The heavy mechanical general techniques and standards - Fire-cutting
11) JB/T 5000.3-1998 The heavy mechanical general techniques and standards - Welding
12) JB/T 5000.6-1998 The heavy mechanical general techniques and standards - Steel
castings
13) JB/T 5000.8-1998 The heavy mechanical general techniques and standards - Forging
14) JB/T 5000.9-1998 The heavy mechanical general techniques and standards-Cutting
15) JB/T5000.10-1998 The heavy mechanical general techniques and standards - Assembly
16) JB/T10358-2002 Water-cooled electric cables for industrial electroheat installations
17) ISO90012000 Standards of Quality Management System

VIII. Guarantee for equipment quality and performance

1. Basic requirement

Supplier shall undertake general technical responsibility for the equipments in the contract,
that is, supplier shall take total responsibility for equipments of this project and design,
manufacturing, installation, debugging, assessment index as well as completion acceptance
check index of electrical automation system and the specified contents in this project.

Supplier shall finish the preliminary sketch of equipments within 15 days and conduct
technical exchange with purchaser. Supplier shall provide purchaser with the design data of
whole set of technological arrangement plan, civil foundation loading diagram, auxiliary
works and public works (including: cooling circulating water, oxygen, compressed air and
hydraulic system, etc.) construction drawings of technological equipments.

Supplier shall bear full responsibility for the completeness and correctness of the data
submitted.

The equipments to be provided shall have characteristics of economy and reliability and
conform to the energy-saving requirements.

Supplier must be ensure that the whole set of equipment are delivered according to the work
schedule in this project and shall undertake total responsibility for the timeliness, correctness

- 47 -
and completeness of the referred technical requirement. In the whole process of the works
implementation, supplier shall be responsible for the coordination between suppliers who
supply the relevant parts and components of complete set equipments.

The supplier shall provide the function index or technical index, products quality and
technological property of the main equipments. The measuring methods and conditions of
corresponding guarantee value shall be put forward as well to ensure that the provided
property index can meet the requirement.

Supplier should guarantee the safety facilities of the whole installations shall be complete,
reliable, and in conformity with the national safety technical standard, put forward safety
countermeasures for insecurity factors, and offer emergency plans for the contingent safety
accidents.

Prior to construction of the project, supplier shall provide component drawings and various
technical materials of the equipments for the project department in favor of the quality
monitoring in the construction. Any variation of project in the construction shall not be
executed until the confirmation of the project department. After completion of the project,
relevant technical data (including equipment operation instruction, equipment drawing,
technical characteristics description, etc.) shall be revised for the confirmed variation before
acceptance to ensure the correctness and completeness of drawings and various technical data,
scientificness, progressiveness and rationality of the project..

This project generally belongs to the turnkey project, which is installed, debugged, delivered
and accepted (excluding equipment foundation construction) by supplier. Purchaser shall
provide overall cooperation. After approval, both parties sign the handover and acceptance
check agreement.

After equipment supply contract comes into effect, supplier shall install and debug equipment
at the scheduled time.

Equipment supplier shall undertake the responsibility of 3 guarantees. The whole length of
warranty is 12 months after the equipments are put into service. If the equipments
malfunction within warranty period, supplier shall come to fix them within 5 days upon
receiving notice.

Supplier shall furnish the purchaser with 2 copies of perfect equipment operation
specifications and maintenance and routine specifications upon the completion and
acceptance check.

2. Equipment performance assurance

Ensure the operation stability of electrical control system, meters, water-cooling system,

- 48 -
mechanical system and hydraulic system of electric furnace. Ensure that various parts and
components meet the requirements of working conditions.

Ensure that each parameter of electric furnace is set to meet the requirements.

2.1 Guarantee of equipment performance and testing method see Table 8-1
Guarantee
No. Items Unit Testing method
value
1 Response time of electrode control s 0.15 Stop watch
unbalanced degree of three-phase
2 % 5% Short-circuit test
impedance
Front furnace
6 Tap to tap period min 100
record
Front furnace
7 Electricity consumption of smelting KWh/t 380
record
Front furnace
8 Mean tapping output t 55
record
9 Electrode consumption Kg/t 3.0 Weigh

Note:
1) Under the normal working conditions, 10 furnaces shall be measured continuously.

2) The check and test for such indexes as smelting period and smelting power consumption
shall be realized under the conditions that the total volume of oxygen lance of furnace door,
furnace wall burner (three burners), oxygen blasting possessed on site is over 40Nm3, the
second steel scrap together with the molten steel charging, and the non-electrifying period of
material loading and tapping shall not be over 18min.

3) The furnace body shall be placed by referring to the furnace dimensions provided by seller.

4) 3.0kg/t below shall be reached when domestic high-quality super high power graphite
electrode is utilized.

IX. Technical documents and data delivery, technical service, equipment design, and
supervision and acceptance check

1. Technical documents and data delivery

Within one month after the contract comes into force, all design shall be completed, and the
purchaser shall censor drawings and technology and execute quality control. The two parts
sign a censoring memoir as the supplement of the contract technical agreement. The supplier
shall supply the following data to the purchaser:

- 49 -
1 Drawings: Drawings in terms of mechanical parts, hydraulic parts, electrical parts,

metering parts, computer parts and key parts and wearing parts. Electrical data includes:

outgoing-inspection data, electric principle map (including PLC procedure), erection and
completion diagram, a set of PLC software and hardware data (genuine STEP7V5.3,
WINCC6.0) of electrical elements.

2 Data: Operation instruction.

3 Standard equipments: Erection diagram samples of standard equipments or parts.

4 The drawings, data and electronic documents are provided by supplier.

List of technical data provided by supplier to purchaser is shown in Table9-1 after the contract
comes into force.

Note:

1 If the technical data that purchaser needs exceeds the above-mentioned range, supplier

shall meet them after approval of both parties.

2 According to the specified date, supplier and purchaser shall submit the complete

technical data to ensure the requirements of general progress of the project.

3 Supplier and purchaser shall be responsible for the reliability, completeness, accuracy of

data provided by them.

4 In the future design liaison, meeting minutes signed by two parties, agreement, and fax

shall be regarded as valid parts of technical accessories.

5 Completion data shall be provided after heat test.

Table 9-1 List of technical data to be provided to the supplier from the supplier after
contract comes into effect

Submittal
Submittal Receiving
No. Content time/delivery
copies unit
mode
General layout diagram ( including general
1 drawing of electric furnace) - preliminary 1 month 4 Acquirer
design drawing
General layout diagram of electric furnace 4
2 1 month Acquirer
(plain view drawing and elevation drawing):

- 50 -
includes location dimension between furnace
and transformer room, transformer room, high
and low voltage distribution room,
master-control room, location and site of
hydraulic room, etc. - final design drawing
General drawing of electric furnace(plain
view drawing and elevation drawing ):
3 location and elevation of material-feeder nose, 4 Acquirer
1 month
main technical parameters of furnace, etc. -
final design drawing
Foundation drawing and force diagram of 4
4 1 month Acquirer
electric furnace-preliminary design drawing
Foundation drawing and force diagram of
electric furnace: includes load of various 4
5 1 month Acquirer
components, bolt (hole) size, external
dimension, mutual location, elevation, etc.
Detailed electrical parameters of high voltage
electrical equipment: single-line system 4
6 1 month Acquirer
drawing of high and low voltage; principle
system drawing of high and low voltage.
Terminal drawing of high and low voltage
cabinet, console, etc. ( clearly marking cable 4
7 2 months Acquirer
number, model, specification, core number
and direction)
Electric furnace platform and periphery pore 4
8 1 month Acquirer
drawing
Data of relevant embedded members of civil 4
9 1 month Acquirer
design: size, location, load, etc.
Parameter sheet of power medium (electricity, 4
10 1 month Acquirer
liquid, water, gas).
System drawings of hydraulic, compressed air 4
11 1 month Acquirer
and cooling water.
List of erection materials( including water, 4
12 2 months Acquirer
gas, hydraulic system)
System drawings of hydraulic, cooling water
13 and compressed air together with pipeline 2 months 4 Acquirer
drawings of high and low voltage system.
Joint data of mediator pipeline(joint is set 4
14 2 months Acquirer
within 1.5m from equipment distributor )
All the erection diagrams and wearing parts
15 and components drawings of mechanical 2 months 4 Acquirer
equipments.

- 51 -
Instruction book of equipment installation, 4
16 3 months Acquirer
operation and maintenance.

2. Technical service

(1)Equipments shall be processed and manufactured based on the relevant technical


standards of contract, technical agreement and enterprise. Quality of products shall comply
with technical standards of enterprise outgoing-inspection acceptance. The basic technical
conditions of GB10067.2-88 national electro thermal equipments shall be strictly executed for
general technical requirements, inspection specification, testing method, and equipment safety
which are not clearly specified in the contract.

(2)Host machine, subsidiary and auxiliary equipments shall be attached with Certificate of
Conformity for products inspection and related data. Directional purchase of the key matching
parts shall be verified by the purchaser and the quality of products shall be the sellers
responsibility.

(3)Carry out Project Manager Responsibility System and assign special persons responsible
for quality control thoroughly.

(4)The drawing design shall be checked up strictly, which shall be revised and verified
repeatedly. The experts concerned from the purchaser shall be invited to censor the design
scheme after completion of drawing design.

(5)After feeding, special inspectors are assigned to strictly check up the quality for each
sector and each working procedure. Unqualified products are forbidden to enter the next one
working procedure.

(6)The purchaser shall conduct supervision on the manufacturing procedures of products


according to the requirement. The seller shall cooperate with the supervisors and provide
accommodation for them.

(7)The technical personnel urgently needed in the period of on-site installation and
debugging shall come to the site within 5 days.

(8)Those technical service personnel, who are sent out to handle problems, are familiar with
the business and shall solve problems of installation for users.

(9)The questions raised by relevant personnel from purchaser shall be handled in time. The
questions need to be explained shall be answered on occasion.

(10)The purchasers supervision shall be accepted in the construction period.

- 52 -
(11)Training

The supplier is responsible to conduct technical training to operation personnel, technical


personnel and maintenance personnel from purchaser for free.

The training is conducted on the purchasers factory site after acceptance check of equipment
installation.

The training mainly contains: operation technique, program and maintenance, which shall be
known and grasped.

The supplier shall provide the relevant technical materials and audio-visual materials for the
training personnel with the purpose of finishing the training smoothly.

3. Supervision and acceptance check

(1) The purchaser shall conduct supervision on the manufacturing procedures of products
according to the requirements and the supplier shall cooperate with the supervisors and
provide accommodation for them.

(2) The purchaser shall prepare the outline for acceptance check, which shall be deemed as
the acceptance standards on the revision and approval of the supplier according to the
requirement of tender outline and main technical index, technological plane layout, equipment
manufacture standards and stipulations of state relevant industries, state relevant environment
protection, industrial sanitation and firefight.

(3) Equipments acceptance check includes pre-acceptance check and final acceptance check.

(4) Purchaser decides on whether to conduct pre-acceptance check based on the production
schedule, pre-acceptance check shall be done on the sellers site, and delivery and acceptance
are done by seller. Purchaser assigns the experts to supervise the acceptance check. After
approval, the representatives from both parties sign the handover agreement that will come
into force upon signatures.

(5) The final acceptance check is conducted on buyers installation site by suppliers expert
together with purchasers engineer, and completion agreement shall come into force upon
signatures of two representatives.

(6) Contents and standards of acceptance check

(7) Acceptance check shall be performed based on suppliers outgoing-inspection standards


and technical agreement and acceptance check outline stipulated by purchaser and supplier.

- 53 -
(8) After the installation and debugging on site, the purchaser shall make overall acceptance
check on equipment performances and technical indexes.

(9) The supplier shall offer two copies of outgoing-inspection certifications of the equipments.
(Including various record texts of inspection and test)

X. Boundary of 50t arc furnace equipment

Design the boundary points in the factory buildings.

Medium pipeline

-Cooling water system: flange of cooling water distributor of the supplier and inlet and
outlet joints of return water

-Compressed air system: flange of gas valve station joint


-Oxygen system: flange of gas valve station joint

Electrical equipment

-For low voltage equipment, the designed boundary point should be at the upper static
contact of input knife air switch, purchaser shall take charge of leading the low voltage
power to the upper incoming end of knife switch/air open in the low voltage cabinet of the
master control room.

-For high voltage equipment, boundary point should be designed for first side voltage of the
transformer. Purchaser shall take charge of leading the high voltage power supply to the
primary electric wiring socket of the transformer.

All the other intermediate wirings and pipelining related to the electrical system are in the
charge of supplier.

Automatic control system

Automatic control system inside the arc furnace system is provided by the supplier. The
boundary point with joints of other systems in the workshop is the joint of corresponding
electrical equipments.

Others

The buyer is responsible for supplying the entire medium oil.

The purchaser is responsible for supplying such embedded parts as embedded anchor bolt, nut,

- 54 -
washer, transformer vehicle guide rail and its embedded parts and those of short net system.

If flange connection is needed in the pipelines between joints and equipment, the supplier
shall provide the matching flanges and bolts and corresponding pipelines. The supplier shall
bear the responsibility for the integrity of equipment that supplied, if omitted items exist,
supplier shall make them up for free of charge.

- 55 -

Potrebbero piacerti anche