PROGRESS REPORT FOR THE PERIOD ENDING AP

Name of Contract CONSTRUCTION OF THE THOMAZO BRIDGE

Contract 1. Demolition and disposal of two bridge abutments and bridge de


Description/Scope of 2. Construction of two new bridge abutments and bridge deck on
Works 3. Construction of retaining walls to protect river banks
4. Construction of temporary by-pass roads
5. Construction of pedestrian sidewalks

Funding for Works TOTAL (EC$) CDB (EC$)


$5,623,617.04 $4,890,101.77

Contractor Integrated Development and Construction

Supervising
Engineer/Consultant Caribbean Consulting Engineers

Contract Start Date 25 July 2016

Revised Start Date 26 September 2016

Contract Time for


Completion 360 calendar days

Contract End date 21 September 2017

Contract Price (Works)


(EC$) $5,623,617.04

Variations to date
(Works) $0.00
Revised Contract Price
(Works) $5,623,617.04

Extensions of time
granted to date NONE

Estimated Percentage
Completion to date 13%

Summary of Progress 1. Setting of Site Office for Project Manager - 100%


to date 2. Construction of By-Pass Road - 100% Note: Bypass Road was o
Bridge Works
1. Demolition - 100%
2. Excavation - 15%

Works (EC$)
Payments certified to CDB (EC$) G
date 795,595.32
Problems/Delays/ The Project is now 51/2 months behind schedule .
Challenges The Project Manger, Mr. Abel Martinez is no longer with the Project
New Project Manger will assume post by May 28th, 2017.

Summary of projected 1. Excavation for abutment wall continues.


activities to next Piling starts.
reporting period
IOD ENDING APRIL 28TH, 2017

AZO BRIDGE

utments and bridge deck


s and bridge deck on piled foundation
river banks

GOSL (EC$)
$733,515.27
e: Bypass Road was opeded on April 9th, 2017

Works (EC$)
GOSL (VAT) (EC$)
114,567.60

onger with the Project. The Contractor indicated that the


28th, 2017.

2.