Sei sulla pagina 1di 8

Palestinian & Sudanese

School
Project Narrative & Scope of Work

POWERMECH ENGINEERING W.L.L


DOHA, QATAR
Palestinian & Sudanese School

PROJECT NARRATIVE & SOW


The project Titled as Construction of Palestinian & Sudanese School is
located in Doha, Qatar. MEP Sub-Contractor POWERMECH ENGINEERING is
responsible to perform all Mechanical, Plumbing, Fire Fighting, Electrical (ELV)
works inside and outside of school building.

This project comprises of two school buildings Palestinian School and


Sudanese School.

EPIC Engineering, Procurement, Installation and Commissioning is under the


scope of MEP sub-contractor.

ENGINEERING:

Engineering of MEP works include preparation of Shop Drawings in


coordination with civil drawings.

Shop Drawings include following areas;

Lightening & Earthing


Lighting & power
Power Containment
ELV system (Fire alarm, CCTV, Public address and voice alarm,
Telephone )
Plumbing system
Drainage System
Fire Fighting System
HVAC System
Chilled Water System
Coordination of all System

PROCUREMENT:

Procurement of all materials required to complete MEP works after completion


of engineering works.

Engineering for procurement include;

Submission of Material submittals as per project specification and Bill of


Quantities which are required to get the approval from Consultant.

Procurement is divided into Two Sections:

Long Lead Items


Short Lead Items

Long Lead items include major equipment to be installed and require long
lead time to deliver to site

1 | Page
Palestinian & Sudanese School
Short Lead items include all those items which are delivered to site partially
as per site requirement and time taken for delivery of items is short.

PALESTINAIN SCHOOL: (B+G+2)


Palestinian School is having Basement, Ground, 1 st Floor, 2nd Floor and Roof.
The whole building is divided into different Zones named as;

Zone-A
Zone-B
Zone-C
Zone-D
Zone-E

Basement:

Builders work e.g. installation of sleeves, conduits will be performed before


casting of concrete.
Chipping or coring of concrete is not the part of MEP scope.

Earting of system and Under-ground drainage pipes is subject to be


completed before completion of casting of basement.

Basement floor include following areas where MEP activities will be


performed:

Transformer Room
MV Room
Pump Room
Q-Tel Room
Services area & Hall

These areas include Installation of major equipment like ;

Installation of Transformer, MV panels, Pumps, Bus duct, Power facto Panel.


Other MEP activities will be under the division of plumbing & drainage, Fire
Fighting system, HVAC system and Fire alarm, CCTV system.

Major activities are as follows;

Installation of PVC conduits


Installation of ELV wiring & Cables
Installation of Light fixtures
Installation of Plumbing, Drainage , Fire Fighting Pipes & Supports
Installation of HVAC duct, Insulation , AHUs and FCUs
Installation of Final fix accessories like Switch & Sockets, Sprinklers ,
Fire Alarm devices
Installation of Chilled water pipes and Insulation
Testing of Pipes & ducts
Testing & Commissioning of all equipment and complete system

2 | Page
Palestinian & Sudanese School
All above mentioned activities are dependent on completion of civil work.
Builders work go hand in hand with civil work. Any delay in civil may effect
MEP activities to get delay and may lead to project delay.

Ground Floor to 2nd Floor :

Builders work e.g. installation of sleeves, conduits will be performed before


casting of concrete.
Chipping or coring of concrete is not the part of MEP scope.

Ground to 2nd floor include following areas where MEP activities will be
performed:

Class Rooms
Electrical Rooms
Offices
Hall ways
Library
Staircase
IT Rooms
Music Labs

Major activities are as follows;

Installation of PVC conduits


Installation of ELV wiring & Cables
Installation of Light fixtures
Installation of Plumbing, Drainage , Fire Fighting Pipes & Supports
Installation of HVAC duct, Insulation , AHUs and FCUs
Installation of Final fix accessories like Switch & Sockets, Sprinklers ,
Fire Alarm devices
Installation of Chilled water pipes and Insulation
Installation of Sanitary wares
Testing of Pipes & ducts
Testing & Commissioning of all equipment and complete system

Lower Roof & Upper Roof :

Builders work e.g. installation of sleeves, conduits will be performed before


casting of concrete.
Chipping or coring of concrete is not the part of MEP scope.

Basement floor include following areas where MEP activities will be


performed:

Technical Rooms
Lift Room
Chillers Yard
Water Tanks

3 | Page
Palestinian & Sudanese School
Major activities are as follows;

Installation of PVC conduits


Installation of ELV wiring & Cables
Installation of Light fixtures
Installation of Plumbing, Drainage , Fire Fighting Pipes & Supports
Installation of Chillers and Chilled Water Pumps
Installation of Final fix accessories like Switch & Sockets, Sprinklers ,
Fire Alarm devices
Installation of Chilled water pipes and Insulation
Testing of Pipes & ducts
Testing & Commissioning of all equipment and complete system

External Building :

Palestinian School External building include following areas where MEP


activities will be performed:

Multi-purpose Hall
Guard House
Break Water Tank & Pump room

Major activities are as follows;

Installation of PVC conduits


Installation of ELV wiring & Cables
Installation of Light fixtures
Installation of Plumbing, Drainage , Fire Fighting Pipes & Supports
Installation of HVAC/ Dx split AC as per drawings
Installation of Final fix accessories like Switch & Sockets, Sprinklers ,
Fire Alarm devices
Installation of Chilled water pipes and Insulation
Testing of Pipes & ducts
Testing & Commissioning of all equipment and complete system

SUDANESE SCHOOL: (G+1)


Sudanese School is having Ground, 1st Floor and Roof. The whole building is
divided into different Blocks named as;

Block-1
Block-2
Block-3

Ground Floor to 1st Floor :

Builders work e.g. installation of sleeves, conduits will be performed before


casting of concrete.

4 | Page
Palestinian & Sudanese School
Chipping or coring of concrete is not the part of MEP scope.

Ground to 1st floor include following areas where MEP activities will be
performed:

Class Rooms
Electrical Rooms
Offices
Hall ways
Library
Staircase
IT Rooms
Lounge & Entrance area

Major activities are as follows;

Installation of PVC conduits


Installation of ELV wiring & Cables
Installation of Light fixtures
Installation of Plumbing, Drainage , Fire Fighting Pipes & Supports
Installation of HVAC duct, Insulation , AHUs and FCUs
Installation of Final fix accessories like Switch & Sockets, Sprinklers ,
Fire Alarm devices
Installation of Chilled water pipes and Insulation
Installation of Sanitary Wares
Testing of Pipes & ducts
Testing & Commissioning of all equipment and complete system

Upper Roof :

Builders work e.g. installation of sleeves, conduits will be performed before


casting of concrete.
Chipping or coring of concrete is not the part of MEP scope.

Basement floor include following areas where MEP activities will be


performed:

Technical Rooms
Lift Room
Chillers Yard
Water Tanks

Major activities are as follows;

Installation of PVC conduits


Installation of ELV wiring & Cables
Installation of Light fixtures
Installation of Plumbing, Drainage , Fire Fighting Pipes & Supports
Installation of Chillers and Chilled Water Pumps

5 | Page
Palestinian & Sudanese School
Installation of Final fix accessories like Switch & Sockets, Sprinklers ,
Fire Alarm devices
Installation of Chilled water pipes and Insulation
Testing of Pipes & ducts
Testing & Commissioning of all equipment and complete system

External Building :

Sudanese School External building include following areas where MEP


activities will be performed:

Sports Hall
Guard House
Substation
Accommodation Building (G+1)

Substation Activities:

It includes ;

Installation of Transformer
Installation of MV/LV panels
Installation of Power Factor Panels
Cabling & Termination
Installation of FM200
Installation of HVAC System

Major activities for other building are as follows;

Installation of PVC conduits


Installation of ELV wiring & Cables
Installation of Light fixtures
Installation of Plumbing, Drainage , Fire Fighting Pipes & Supports
Installation of HVAC/ Dx split AC as per drawings
Installation of Final fix accessories like Switch & Sockets, Sprinklers ,
Fire Alarm devices
Installation of Chilled water pipes and Insulation
Testing of Pipes & ducts
Testing & Commissioning of all equipment and complete system

TESTING & COMMISSIOING:

It includes complete system Start-Up for hand over to Main Contractor;

Electrical Equipment Energization


Small power, ELV system energization
Fire Alarm system T&C
Fire Fighting system T&C (Include testing of FF pumps and Pipes)
Plumbing & Drainage T&C (Include testing of Pumps & Pipes)

6 | Page
Palestinian & Sudanese School
HVAC System T&C (Flushing of system, equipment testing and Water & air
balancing)

7 | Page

Potrebbero piacerti anche