Sei sulla pagina 1di 8

5838 Ind. Eng. Chem. Res.

2004, 43, 5838-5845

Risk-Based Design of a Regenerative Thermal Oxidizer


Micaela Demichela* and Norberto Piccinini
Centro Studi su Sicurezza Affidabilita` e Rischi (SAfeR), Politecnico di Torino, Dipartimento di Scienza dei
Materiali e Ingegneria Chimica, C.so Duca degli Abruzzi 24, 10129 Torino, Italy

Following an explosion in a piece of equipment [a thermal oxidizer (Loss Prev. Bull. 2003, 170,
8-10)] employed for the purification of gas streams contaminated by volatile flammable
compounds, a similar plant that is under construction was redesigned with a risk-based approach,
to increase both the reliability and operational safety of the regenerative thermal oxidizer (RTO)
and venting collection system (VCS). This paper, in particular, describes the methodologies that
were used and the results that were obtained in terms of the reduction of the frequency of
occurrence of the top event (TE) Explosion in the venting collection system. A recursive
operability analysis (ROA) was performed to identify primary events that could lead to a
possible explosion in the RTO or VCS, with their evolution toward the TE. Fault trees were
then directly derived from the ROA tables, through an intermediate logic diagram, the incidental
sequence diagram, and then quantified in order to assess the frequency of occurrence of a possible
explosion. The modifications that were suggested, thanks to the risk-based approach, should
reduce this frequency from 1.03 to 5.27 10-3 occurrences/year.

1. Risk-Based Approach in Design analyzed with the aim of identifying the critical com-
ponents and operations were as follows:
A valid quantitative approach to a risk-based engi- Painting Section. Cans are painted in a coater
neering design involves acquiring and incorporating all station, in a deco station, and then, on the inside, in an
of the possible knowledge on the design into the decision internal lacquering station (Figure 2). After each sta-
process.1-3 This means that empirical knowledge, phe- tion, the cans are conveyed to an oven (the drying step
nomenological knowledge, and intuitive knowledge must and Ross and internal bake ovens, respectively). Each
be incorporated in a probabilistic framework. oven has a chimney and its own collection system, which
In the case under study, the empirical knowledge that are identified by the numbers 11, 12, and 19 in Figure
was derived from an analysis of the accident that had 2.
occurred in a similar plant demonstrated the necessity
Venting Collection System (VCS). The VCS is
of a better understanding of the process, which was
about 73 m long and 1.5 m in diameter. With reference
obtained through a thermoanalysis of the process resi-
to Figure 2, the gases discharged from the ovens
dues. On the basis of this analysis and of the relevant
(pipeworks 11, 12, and 19) are collected in the main duct
technical standards, a number of plant modifications
and then conveyed to the RTO. The gases from the
were suggested. Their effectiveness was then assessed
internal lacquering stations, instead, are not conveyed
through a quantitative risk analysis (QRA).
to the RTO because the dusts that are generated
Starting from the basic knowledge of the plant as (classified as St 3, the most dangerous class according
formalized in a well-structured recursive operability to the Bartknecht classification7) are collected in a bag
analysis (ROA), it is possible to carry out a safety filter. VCS operating conditions are as follows:
analysis by turning the features of both the fault trees
(i) Flammable substances normally present in flue
(FTs) and event trees (ETs) into the best advantage, as
gases are at a concentration of about 0.1% of the lower
illustrated in the flowchart in Figure 1.4 This full
explosion limit (LEL).
integration of qualitative and quantitative methods
ensures the essential features for probabilistic safety (ii) The whole system works slightly under pressure
analysis, namely, in qualitative terms, systematism, thanks to a fan that is located downstream to the RTO.
completeness, and congruence, and, in numerical terms, (iii) The total flow rate of the flue gases is about
reliability and verification. 13 700 m3/h at 130 C in the main duct.
(iv) The solvent flow rate in the flue gases outweighs
5 kg/h.
2. Description of the Plant
RTO. The polluting charge is burnt in a combustion
Thermal oxidation is an effective way of handling fast chamber (Figure 3) that is built on five towers contain-
gas flows contaminated with relatively low concentra- ing ceramic saddle beds. A part of the sensible heat of
tions of volatile flammable compounds (VFCs) through the flue gases is recovered thanks to the cyclic operation
the use of a regenerative thermal oxidizer (RTO).5,6 In of the towers. In the inlet phase, the process air rises
the plant that was the subject of this study, RTO is through the beds and reaches a temperature that is
employed for the purification of gases extracted from close to the combustion chamber temperature (T 800
an aluminum can painting unit. The units that were C). Two methane burners are present in case extra heat
is needed.
* To whom correspondence should be addressed. Tel.: In the subsequent outlet phase, the flue gases pass
+39 011 5644629. Fax: +39 011 5644665. E-mail: micaela. down through the ceramic saddle beds. The beds thus
demichela@polito.it. absorb part of the sensible heat of the gases, and the
10.1021/ie0342208 CCC: $27.50 2004 American Chemical Society
Published on Web 08/25/2004
Ind. Eng. Chem. Res., Vol. 43, No. 18, 2004 5839

Figure 1. Flow chart to develop a quantitative safety analysis.

towers are then reset for the subsequent inlet phase. The accident started from a localized fire and rapidly
During this inversion phase, about half the volume of developed into an explosion, with the release of flam-
the towers is occupied by a plug flow of process air that mable gases and flames from several collapsed pipes.
has not yet reached the combustion chamber. A fraction An examination of the damage showed that ignition
of the flue gases is therefore withdrawn into the occurred in one of the towers.
chamber (purge phase). It is known that flue gases tend to deposit consider-
able quantities of flammable material along the inner
3. Empirical Knowledge: Analysis of the surfaces of the pipework (20 cm of resins was found
Accident inside the pipework). Furthermore, a thermoanalysis of
The accident occurred in a plant with a three-tower the deposits demonstrated that (i) the source of the
RTO used to abate volatile organic carbon emissions flammable atmosphere was the exothermic decomposi-
from a painting line that is almost identical with the tion of the deposits (if their quantity had been suf-
one described in this paper. Its safety only relied up a ficiently high, the LEL could have been reached) and
sprinkler extinguishing system with breakable bulb (ii) the self-igniting temperature of the vapors that were
detectors inside the VCS pipework. generated from the decomposition (about 450-480 C)
5840 Ind. Eng. Chem. Res., Vol. 43, No. 18, 2004

Figure 2. Flow sheet of the plant.

Figure 3. RTO.

Table 1. Flue Gas Composition and Flow Rates


chimney 11 chimney 12 chimney 19
concn flow rate concn flow rate concn flow rate
solvent [mg/Nm3] [g/h] [mg/Nm3] [g/h] [mg/Nm3] [g/h]
2-methoxyethanol 5.76 15.35 21.50 64.71
n-butanol 15.24 40.61 40.26 121.18 53.41 192.00
methyl isobutyl ketone 1.00 2.66
xylene (isomers) 13.25 26.68 8.31 25.01
2-butoxyethanol 25.87 68.41 151.88 457.15 54.55 196.13
other solvents (such as xylene) 279.50 744.86 913.80 2750.50 107.96 388.91

lay within the operating range of the towers (from nature and quantity of hydrocarbons in the 11, 12, and
137 C at the bottom to 810 C near the combustion 19 chimney flue gases, (ii) assessing the flammability
chamber). The results of the investigation highlighted properties of the pipework deposits and identifying their
the importance of determining the chemical and physi- pyrolysis products, and (iii) characterizing the decom-
cal characteristics of the substances that are present position process as a function of the temperature.
in the VCS, without neglecting the deposits that flue The flue gas samples that were drawn from each stack
gases may form. (11, 12, and 19), when analyzed through gas chroma-
tography, revealed the composition shown in Table 1.
4. Phenomenological Knowledge: Pipework residues were analyzed through differential
Thermoanalysis scanning calorimetry. The samples (five for each stack)
were heated from 20 to 450 C at a 10 C/min rate; all
Both the flue gases and the deposits were then of them showed a general endothermic behavior due to
characterized with the aim of (i) identifying both the pyrolysis phenomena at low temperatures (<150 C) and
Ind. Eng. Chem. Res., Vol. 43, No. 18, 2004 5841

Figure 4. Stack 11 samples analyzed through DSC.

Table 2. Vapor Flammability in Air Streams (iii) Fireproofing system (FPS). An FPS endowed with
flammable vapor ignition combustion an alternating series of sprinklers and water spray
generation temp [C] temp [C] temp [C] nozzles was installed.10,11 The bulbs break at 160 C.
chimney 11 120-150 170-175 220-250 (iv) Deflagration vents (DVs) and protection barriers
chimney 12 210 280 >450 in the discharge area. The VCS venting system is made
chimney 19 210 300 >450 of 12 DVs, which were installed where flue gases change
flow direction. The blowoff area for the RTO was divided
one exothermic peak due to polymerization of the into five DVs, one for each tower.12,13
nonreacted paint between 150 and 230 C. In the
samples from stack 11 (the drying step), a second 6. Probabilistic Framework
exothermic peak was found between 230 and 320 C A ROA, an advanced development of the classical
(Figure 4) as a result of decomposition of the deposit to HazOp directed toward the elaboration of logic trees,
form flammable vapors. was used to verify the effectiveness of the proposed
The residues reach their glass transition at about 140 modifications.14,15
C; therefore, the residue can be considered as a liquid The ROA allows six TEs to be identified, these being
at higher temperatures. The vapor flammability in the critical operating states due to the nonintervention of
air stream was assessed, obtaining the results reported their protection systems following a process deviation.
in Table 2. Table 4 shows the portion of the ROA that relates to
TE 1: Explosion generated by the accumulation of
5. Process and Plant Modification deposits and their subsequent decomposition into VFC.
This was the only TE under study because it represents
Because there are a number of permanent sources of the sequence of events that could lead to an accident
ignition in the plant (production oven burners, RTO similar to the one that actually occurred.
combustion chamber burners, the high temperature in A detailed piping and instrumentation (P&I) diagram
the RTO ceramic saddle beds, and so on), it is necessary of the VCS is shown in Figure 5.
to maintain the flammable vapor concentrations at The relevant process variable is the VFC concentra-
levels lower than LEL to avoid fires and explosions. tion in the VCS. The deviation that was detected (high
The results of the thermoanalysis thus highlighted VFC concentration, 15% LEL) is caused by decomposi-
the effectiveness of combining the flows from the drying tion of the deposits. The consequence of this deviation
step (45 C) and the Ross oven (225 C). The resulting is a very high VFC concentration that forms in the
temperature of about 140 C allows a gradual decom- absence of the intervention of either the plant shutdown
position of the solid residues without generating gas (ASH-400) or the operator (alerted by AAH-400). The
mixtures in the flammability range. recursive mechanism is clearly visible in the next step:
consequence 3. very high VFC concentration, 35% LEL
The following safety measures have also been intro- becomes a deviation (shift from the third to the first
duced:8,9 column); the cause can only be due to the previous
(i) Periodic inspection and cleaning procedures. deviation, i.e., 3. high VFC concentration, 15% LEL
Through an inspection and housekeeping procedure, (shift from the first to the second column). This leads
the thickness of the deposits is maintained lower than to the identification of a new consequence that arises
2 cm in all of the VCS pipeworks. from the nonintervention protective means: Explosive
(ii) Flammability monitors (FMs). Four continuously mixture in the VCS. Failure of the DVs, because of
operating FMs were installed along the VCS pipework their damaging or design errors, results in TE 1.
and connected to the alarm and automatic plant shut- Development of Logic Trees. ROA both realizes
down devices, which are described in Table 3. the full value of the classic strong points of the method,
5842 Ind. Eng. Chem. Res., Vol. 43, No. 18, 2004

Table 3. FM Alarms and Shutdown Devices


alarm and interlock devices description
high concentration ASAH-400 shutdown and the conveyance of fresh air into the plant activated when all of the detectors
reach the threshold valuea
very high concentration ASAHH-400 alarm set at 35% of the LEL; shutdown occurs when all of the detectors (AI-401/404) reach
this threshold value at the same time; fresh air is conveyed into the plant,a the production
oven burners and the RTO are turned off, and the vent valves on the towers are opened
detector malfunctioning detectors automatically check their own operating conditions; a periodic calibration system
was installed on the line; each detector activates an alarm when it detects its own
malfunctioning; the shutdown device comes into operation if AI-401 and AI-404
malfunction at the same time, and fresh air is conveyed into the planta
a Opening of the XV-442 and XV-482 butterfly valves and deviation of the flue gases into the atmosphere.

Table 4. ROA of VCSa

a Asterisks indicate primary events. HE: human error.

namely, the systematic nature and completeness of the Nine minimal cut sets (MCSs) were obtained with
analysis, and enables simple checks to be made of the orders ranging from 5-7. The most critical ones were
real attainment of the objectives. In addition, direct as follows:
extraction of the incidental sequence diagram (ISD) MCS 1. (E01, E09, E11, E12, E13, E14) w
from an ROA provides an otherwise impossible check W1 ) 2.77 10-3 occurrences/year.
of the congruity of the analysis and a rapid development MCS 2. (E01, E04, E05, E09, E11, E12, E16) w
of FT and ET.4,14,15 The ISD in Figure 6 graphically W2 ) 9.94 10-4 occurrences/year.
represents the logical links within TE 1 (explosion), its MCS 3. (E01, E04, E05, E09, E13, E14, E16) w
primary causes, and nonintervention of the protection W3 ) 9.94 10-4 occurrences/year.
systems. ISD stops at the depth reached by ROA. When The whole frequency of occurrence of TE 1 was
the events that cause the nonintervention of protective W ) 5.27 10-3 occurrences/year.
means are fully develpoed, a FT is obtained (Figure 7). Because primary events E01 (nonintervention of DV)
A reduction and quantification of the FT was per- and E09 (nonobservation of cleaning procedures) appear
in all of the MCSs, it is clear that they indicate the
formed using ASTRA,16,17 a software that was developed
occurrence frequency of each MCS. It can therefore be
by JRC-Ispra. The failure rates and unavailability data
supposed that an even better result could be obtained
reported in Figure 7 come from the literature.18,19 All by keeping the thickness of the deposits down through-
of the components were considered to be unrepairable; out the VCS and designing appropriate DVs with their
the test time interval () for the protective systems was maintenance procedures.
6 months. The mission time was calculated considering The situation prior to the accident can be illustrated
5 working days/week. The common cause failures for by the FT of Figure 7 if event G12 is replaced by TE 1.
redundant components, mainly owing to the breakdown When the accident occurred, there were, in fact, no FMs
of plant utilities (power, air, etc.), were neglected with their respective high and very high VFC
because of a highly reliable independent system dedi- concentration alarms nor DVs. The frequency of occur-
cated to safety equipment. rence of a possible explosion in the plant where the
Ind. Eng. Chem. Res., Vol. 43, No. 18, 2004 5843

Figure 5. P&I diagram of the VCS.

Figure 6. ISD of TE 1.

accident occurred can be assessed through the calcula- The other TEs identified through the ROA are not
tion of the gate G12 frequency of occurrence because affected by the plant modifications suggested.
no protective means were installed. This results in an As can be seen in the flow sheet in Figure 1, the
expected number of failures (ENOF) (explosion) of 1.03 second logic tree that can be readily extracted from an
occurrences/year. The FTA results, therefore, confirm ROA is the ET. This diagram identifies, and in some
the effectiveness of the modifications of the risk-based cases quantifies, the possible consequences of an initiat-
design project and show further possibilities of improve- ing event. Account is also taken of the events that
ment. consist of the complete or partial intervention of the
5844 Ind. Eng. Chem. Res., Vol. 43, No. 18, 2004

Figure 7. FTA of TE 1.

Figure 8. ET for TE 1.

means of protection.4,14 The ET developed for this plant design approach was adopted. The empirical knowledge
(Figure 8) validated the intervention sequence of the obtained from the accident analysis highlighted the need
means used to protect the VCS. for a better phenomenological knowledge of the char-
acteristics and the behavior of the solid residues re-
7. Conclusions leased into VCS pipeworks from flue gases. This was
Following an explosion that occurred in an RTO of a achieved through the thermal analysis of the residues
can painting shop, a risk analysis was performed on a themselves.
similar plant in order to modify its design before it was It was found that the more dangerous residues were
constructed and the production started. A risk-based released by the drying flue gases and that, to control
Ind. Eng. Chem. Res., Vol. 43, No. 18, 2004 5845

their decomposition in order to avoid the formation of (2) Galvagni, R.; Clementel, S. Risk Analysis as an instrument
vapor mixtures within flammable limits, the tempera- of design. In Safety Design Criteria for Industrial Plant; Cumo,
ture of the flue gases must be kept at around 140 C. M., Naviglio, A., Eds.; CRC Press: Boca Raton, FL, 1989.
(3) Antona, E.; Fragola, J.; Galvagni, R. Risk-based decision
To maintain this temperature, the drying step flue analysis in design. 4th SRA Europe Conference, Rome, Italy, Oct
gases were collected in the same duct as those from the 18-20, 1993.
Ross oven. (4) Piccinini, N.; Scarrone, M.; Ciarambino, I. Probabilistic
A number of preventive and protective measures was analysis of transient events by an event tree directly extracted
also suggested: (i) periodic inspection and cleaning from operability analysis. J. Loss Prev. Process Ind. 1994, 7, 23-
procedures; (ii) FMs; (iii) FPS; (iv) DVs and protection 32.
(5) Waldern, P. J.; Nutcher, P.; Lewandowski, D. Options for
barriers in the discharge area. These measures were VOC reduction in a Regenerative Thermal Oxidizer (RTO). Emerg-
included in a probabilistic framework in order to verify ing Solution VOC Air Toxic Control; Air and Waste Management
their effectiveness. Association: Pittsburgh, PA, 1996; pp 462-483.
The ENOF (explosion) was assessed through the (6) Self, F. E.; Hill, J. D. Safety considerations when treating
quantitative solution of a FT that was directly drawn VOC streams with Thermal Oxidizer. AIChE 1997 Spring National
from the tables of a ROA performed on the plant. The Meeting Case Histories and Miscellaneous Topics; AIChE 31st
Annual Loss Prevention Symposium, Houston, TX, Mar 1997.
value decreased by 3 orders of magnitude when the (7) Eckhoff, R. K. Dust Explosions in Process Industries;
suggested preventive and protective measures were Butterworths-Heinemann: Oxford, 1991.
considered: from 1.03 occurrences/year (for the plant (8) Clark, D. G.; Sylvester, R. W. Ensure Process Vent Collec-
in which the explosion occurred) to 5.3 10-3 occur- tion System Safety. Chem. Eng. Prog. 1996, 1, 65-77.
rences/year. This value thus confirms the effectiveness (9) Thomas, C. D.; Schoenmaker, G. Implement Proper Furnace
of the suggested measures and also the one of the risk- Safety Interlocks. Chem. Eng. Prog. 1996, 7, 45-49.
(10) National Fire Protection Association. Installation of Sprin-
based approach as a tool to improve plant design. kler Systems; National Fire Protection Association: Boston, 1994;
p 13.
Acknowledgment (11) National Fire Protection Association. Water Spray Fixed
Systems for Fire Protection; National Fire Protection Association:
An early version of this study was presented at the Boston, 1994; p 15.
ESREL 2001 European Conference.20 (12) National Fire Protection Association. Standard on Venting
of Deflagration; National Fire Protection Association: Boston,
1994; p 68.
Notation
(13) National Fire Protection Association. Standard on Explo-
DSC ) differential scanning calorimetry sion Prevention Systems; National Fire Protection Association:
DV ) deflagration vent Boston, 1992; p 69.
ENOF ) expected number of failures (14) Piccinini, N.; Ciarambino, I. Operability analysis devoted
to the development of logic trees. Reliab. Eng. Syst. Saf. 1997, 55
ET ) event tree (3), 227-241.
FM ) flammability monitor (15) Demichela, M.; Marmo, L.; Piccinini, N. Recursive Oper-
FPS ) fireproofing system ability Analysis Of Systems With Multiple Protection Devices.
FT ) fault tree Reliab. Eng. Syst. Saf. 2002, 77, 301-308.
FTA ) fault tree analysis (16) Contini, S.; de Cola, G.; Wilikens, M.; Cojazzi, G. ASTRA,
HE ) human error an integrated tool set for complex systems dependability studies.
ISD ) incidental sequences diagram Workshop on Tool Support for System Specification, Development
JRC ) Joint Research Center-Ispra (VA), Italy and Verification, Malente, Germany, 1998.
LEL ) lower explosion limit (17) Contini, S. Recenti Sviluppi metodologici dellanalisi degli
alberi di guasto. Valutazione e gestione del rischio negli insedia-
MCS ) minimal cut set menti civili e industriali, Convegno nazionale VGR 98, Pisa, Oct
Q ) unavailability 1998.
QRA ) quantitative risk analysis (18) Center for chemical process safety of the AIChE. Guide-
) test time interval lines for process equipment reliability data; AIChE: New York,
ROA ) recursive operability analysis 1989.
RTO ) regenerative thermal oxidizer (19) Procaccia, H.; Arsenis, S. P.; Aufort, P. European Industrial
VCS ) venting collection system Reliability Data bank, 3rd ed.; Crete University: Iraklion, 1998.
VFC ) volatile flammable compound (20) Piccinini, N.; Quattrini, A.; Rapone, N. The Safety of A
TE ) top event Regenerative Thermal Oxidiser and its Venting Collection System.
ESREL 2001, Torino, Italy, Sept 16-20, 2001.
W, W ) occurrence frequency
) failure rate
) repair rate
Received for review October 29, 2003
Revised manuscript received June 9, 2004
Literature Cited Accepted June 17, 2004
(1) Turney, R. Explosion within a thermal oxidizer. Loss Prev.
Bull. 2003, 170, 8-10. IE0342208

Potrebbero piacerti anche