CANVASS OF MATERIALS

SGM
Description of Materials Unit Unit cost

1. FOUNDATION, CONCRETE COLUMNS, BEAMS AND


CONCRETE HOLLOW BLOCKS WALLS

Portland Cement BAG 203.00


Sand (S-1) CU.M. 200.00
Gravel or Crushed Stones (G-1) CU.M. 258.00
Earth Fill (MIX) CU.M. 200.00
C.H.B. 4" PIECE 7.00
5" PIECE
6" PIECE
Steel Reinforcing Bars, Deformed
10mmX6.00 meters PIECE 124.00
12mmX6.00 meters PIECE 179.00
16mmX6.00 meters PIECE 318.00
Wire No. 16 for Tying KILO 50.00
Common Wire Nails: 50mm(2") KILO 50.00
75mm(3") KILO 50.00
100mm(4") KILO 50.00
125mm(5") KILO 50.00
Finishing Nails: 31mm(1-1/4") KILO 55.00
50mm(2") KILO 55.00
63mm(2-1/2") KILO 55.00
Concrete Nails, 75mm(3") KILO 70.00
Form lumber: (GOOD) BD.FT. 32.00
Form lumber:(COCO) BD.FT. 18.00
Marine Plywood, 1/4"X4'X8' SHEET 305.00
Ordinary Plywood, 1/4"X4'X8' SHEET 290.00
Plyboard, 3/4" X4" X8' SHEET 750.00

2. ROOFING MATERIALS
3/16" X2"X2" ANGLE BAR (6m) PIECE 520.00
1/4" X2"X2" ANGLE BAR (6m) PIECE 590.00
3/16" X1"X1" ANGLE BAR (6m) PIECE 242.00
2"X 3" ST. C-PURLINS (1mm) PIECE 309.00
2"X 6" ST. C-PURLINS (1mm) PIECE 450.00
2"X4" ST. C-PURLINS (1mm) PIECE 360.00
corrugated G.I sheet PIECE 320.00
RIDGE ROLL METER
FLASHING METER
VALLEY ROLL PIECE
Gutter(Spanish Type) PIECE 120.00
Hardi-Flex building board 1/4 BD.FT. 383.00
Long Span Steel Bricks per meter
Plain GI Ridge Roll and Hip Roll, Ga. 0.4mm PIECE
G.I. Sheet, Ga. 26 PIECE
Vulcaseal Sealant LITER
PVC Pipes downspout, (3" dia. X 10') PIECE 150.00
PVC Elbows , (3" dia. X 10') PIECE 40.00
PVC Solvent Cement LITER 100.00
G.I RIVET KILO 275.00
hack saw blade (ordinary) PIECE
Welding rod KILO
3. PLUMBING PIPES AND FITTINGS

Sanitary Pipes and Fittings


Pipes - (4" dia X 10') PIECE 200.00
Pipes - (3" dia X 10') PIECE 150.00
Sanitary Tee, (3" dai) PIECE 40.00
Elbow, 1/8 Bend (3" dia) PIECE 40.00
Elbow, 90o (3" dia) PIECE 40.00
Reducer Coupling, (2" dia X 3" dia) PIECE 50.00
Floor Drain Trap, (2" dia) PIECE 50.00
Clean-out w/ Plug, (3" dia) PIECE 30.00

GI Pipes and Fittings


Pipes - (1" dia X 20') PIECE 400.00
Pipes - (3/4" dia X 20') PIECE 300.00
Pipes - (1/2" dia X 20') PIECE 230.00
Elbow, 90o (3/4" dia) PIECE 25.00
Elbow, 90 (1" dia)
o
PIECE 30.00
Elbow, 90o (1/2" dia) PIECE 10.00
Street Ell, (1/2") PIECE 12.00
Tapped Tee, (1/2") PIECE 15.00
Tapped Tee, (3/4") PIECE 18.00
Reducer Tee, (1" X 3/4") PIECE 40.00
Reducer Ell, (1/2" X 3/4") PIECE 40.00
Niple, (1/2" X 6") PIECE 40.00
Coupling, (1/2") PIECE 10.00
Coupling, (3/4") PIECE 15.00
Coupling, (1") PIECE 18.00
Union, (1") PIECE 50.00
Union, (3/4") PIECE 40.00
Union, (1/2") PIECE 30.00
Teflon Tape (1/2) Roll 10.00
Water Meter PIECE
Gate Valve PIECE
Faucet (brass plain bibb 1/2) PIECE 100.00
Hose Bibbs PIECE 100.00
SOLVENTCEMENT liter
p-trap (3/4" dia) PIECE
p-trap (1" dia) PIECE
p-trap (1/2" dia) PIECE
wye reducer (4x2) PIECE
wye (4x4) PIECE

4. PLUMBING FIXTURES AND ACCESSORIES

Water Closet set


4200.00
Lavatory set
Soap Holder set 120.00
Toilet Paper Holder set 120.00
Kitchen Sink set
Towel Holder set 250.00
Shower Head (chrome) set 300.00
Floor Drain (durametal) PIECE 100.00

5. FLOOR AND OTHER INTERIOR WORKS

Kent Vinyl Floor Tiles, (12" X 12") PIECE


Rugby Glue for Vinyl Tiles 4Lcan
Unglazed Floor Tiles, (4" X 8")
Unglazed Floor Tiles, (8" X 8") PIECE
Glazed Wall Tiles, (4" X 8")
Glazed Wall Tiles, (8" X 8") PIECE
Prime White Cement BAG
Patching compound
tile adhesive kilo
6. ELECTRICAL MATERIALS

Entrance Cap, (1" dia.) PIECE


Rigid Steel Conduit, (1"dia X 3 m.) PIECE
Conduit Clamp for 1" dia. PIECE
Metal Locknut with Bushing, 1" dia.
Automatic Circuit Breaker, 100A Main Switch, with 6 Branch
set
Circuits
RSC Elbow, 90o Long Bend, 1" dia PIECE
RSC Coupling, 1" dia PIECE
uPVC pipe, 20mm dia. X 3.0 m PIECE
uPVC coupling, 20mm dia. PIECE

PIECE
uPVC adaptor w/locknut and bushing, 20mm dia.
uPVC range pipe, 25mm dia. X 3.0 m PIECE

pair
uPVC adaptor w/locknut and bushing, 25mm dia.
uPVC utility boxes, 38mmX100mmX54mm PIECE
uPVC junction boxes, 38mmX100mmX54mm PIECE
Solvent Cement LITER
Electric Wire 3.5mm 150m/box
Wire for Range 5.5mm meter
Wire for Range 8.0mm meter
Wire for service Entrance 14mm meter
Wire for service Entrance 22mm meter
plastics Lamp Receptacle PIECE
Porcelain Lamp Receptacle PIECE
Plate Assembly for Single-Gang Switch set
Plate Assembly for two-Gang Switch set
Plate Assembly for three-Gang Switch set
Wall Switch Module, 5A, 250V, AC PIECE
Three-way Switch Module, 5A, 250V, AC PIECE
Duplex Convenience Outlets PIECE
Range outlet with cover plate, 3-prongs set
Friction/plastic tape, Big size roll
ACU outlet PIECE
ELECTRICAL WIRE ROLL
BREAKER 100ampere PIECE
BREAKER 60ampere PIECE
BREAKER 40ampere PIECE
BREAKER 30ampere PIECE
BREAKER 20ampere PIECE
BREAKER 15ampere PIECE
PANEL BOARD 6HOLE PIECE
PANEL BOARD 8HOLE PIECE
PANEL BOARD 10HOLE PIECE
flourescent lamp w/ baluster (1m) set
flourescent lamp w/ baluster (0.5m) set
circular flourescent lamp set
daylight bulb PIECE
7. PAINTING MATERIALS (DUTCH BOY
OR BOYSEN)

Flatwall LATEX Paint, White 16L can


Flatwall Enamel Paint, White 16L can 2000.00
Quick Drying Enamel, White 16L can 2200.00
Exterior Wood Primer and Sealer 16L can
Interior Wood Primer and Sealer 16L can
Oil Tinting Colors
Green 1/4L can 250.00
Yellow 1/4L can 250.00
Brown 1L can 250.00
Black 1/4L can 250.00
Primer Thinner 4L can 200.00
Gloss Enamel 16L can 2050.00
Acrylic Semi-Gloss Latex Paint 16L can 2000.00
Concrete Neutralizer
Acrylic Concrete Primer Sealer 4L can 459.00
Gloss Latex 16L can 1902.00
Masonry putty 4L
Glazing Putty gal
Sandpapers #100 pcs
Steel Brush piece
Plexibon gal
Rust Converter gal
ROLLER TRAY 25.00
Roller Brush 7" piece 35.00
Roller Brush 9" piece 40.00
Paint Brush 4" piece 45.00
Paint Brush 3" piece 55.00
Paint Brush 2" ordinary piece 15.00
Paint Brush 1" ordinary piece 8.00
Paint Brush 1 1/2"ordinary piece 10.00
Paint Brush 1/2"ordinary piece 8.00

8. DOORS AND WINDOWS


Sliding door piece
Panel door solid piece
PVC door piece
DESCRIPTION: 3/16" THK. CLEAR GLASS IN STEEL CASEMENT
TYPE WINDOW WITH 12MM SQUARE BAR GRILLS

TINTED FT2
SMOKE FT2
CLEAR FT2
set
MOBILITY
Unit cost

205.00
170.00
200.00
210.00
7.00
8.00

106.00
175.00
320.00
50
50.00
50.00
50.00
50.00

60.00
37.00
14.00
320.00
290.00
750.00

520.00
580.00
185.00
280.00
450.00
350.00
320.00
80.00
80.00

95.00

95.00
320.00
380.00
150.00
40.00
90.00
190.00
50.00
75.00

650.00
550.00
40.00
40.00
40.00
55.00
50.00
30.00

420.00
350.00
290.00
25.00
30.00
10.00
15.00
15.00
15.00
40.00
40.00
40.00
15.00
15.00
15.00
40.00
40.00
40.00
8.00

100.00
95.00
235.00

65.00
65.00
110.00
120.00

4500.00
900.00
120.00
120.00
500.00
250.00
350.00
75.00

15.00
600.00
8.00

8.00

250.00

240.00

5.00
250.00
70.00

20.00
20.00

2700.00

20.00
12.00

50.00
125.00

20.00
100.00

600.00
400.00
400.00
350.00
200.00
150.00
480.00
550.00
750.00
180.00

210.00
50.00

1600.00
2000.00
2000.00

250.00
260.00
40.00
35.00

35.00
40.00
50.00
50.00
30.00
15.00
10.00
12.00
8.00

2700.00
1100.00

220.00

170.00
Project Title: Proposed 2-Storey Residential with Attic
Project Owner: Rodel T. Grande
Project Location: Brgy. Tolega Sur, Moncada, Tarlac

BILL OF MATERIALS

Description of Materials Quantity Unit

1. FOUNDATION, CONCRETE COLUMNS, AND


CONCRETE HOLLOW BLOCKS WALLS

Portland Cement 830 BAG


Sand (S-1) 223 CU.M.
Gravel or Crushed Stones (G-1) 52 CU.M.
Earth Fill (MIX) 145 CU.M.
C.H.B. 4" 2200 PIECE
5" 5521 PIECE
Steel Reinforcing Bars, Deformed
10mmX6.00 meters 893 PIECE
12mmX6.00 meters 1111 PIECE
Wire No. 16 for Tying 303 KILO
Common Wire Nails: 50mm(2") 9 KILO
75mm(3") 49 KILO
100mm(4") 13.5 KILO
125mm(5") 4.5 KILO
Finishing Nails: 31mm(1-1/4") 9 KILO
Concrete Nails, 75mm(3") 9 KILO
Form lumber: (Good) 1049 BD.FT.
Form lumber:(Coco) 11277 BD.FT.
Ordinary Plywood, 1/4"X4'X8' 90 SHEET
Marine Plywood, 1/4"X4'X8' 68 SHEET

2. ROOFING MATERIALS
3/16" X2"X2" Angle Bar (6m) 149 PIECE
2"X 3" ST. C-Purlins (1mm) 483 PIECE
2"X 6" ST. C-Purlins (1mm) 14 PIECE
Corrugated G.I sheet 156 PIECE
Ridge Roll 22 METER
Flashing 10 METER
Gutter(Spanish Type) 37 PIECE
Vulcaseal Sealant 5 LITER
G.I Rivet 19 KILO
Hack saw blade (ordinary) 20 PIECE
Welding rod 20 KILO

3. PLUMBING PIPES AND FITTINGS

Sanitary Pipes and Fittings


Pipes - (4" dia X 10') 22 PIECE
Pipes - (3" dia X 10') 10 PIECE
Sanitary Tee, (3" dai) 4 PIECE
Elbow, 1/8 Bend (3" dia) 3 PIECE
Elbow, 90o (3" dia) 18 PIECE
Reducer Coupling, (2" dia X 3" dia) 4 PIECE
Floor Drain Trap, (2" dia) 2 PIECE
Clean-out w/ Plug, (3" dia) 7 PIECE
GI Pipes and Fittings
Pipes - (1" dia X 20') 20 PIECE
Elbow, 90o (3/4" dia) 5 PIECE
Elbow, 90o (1" dia) 20 PIECE
Elbow, 90o (1/2" dia) 2 PIECE
Niple, (1/2" X 6") 4 PIECE
Coupling, (1") 10 PIECE
Teflon Tape (1/2) 10 Roll
Water Meter 1 PIECE
Gate Valve 1 PIECE
Faucet (brass plain bibb 1/2) 5 PIECE
Hose Bibbs 1 PIECE
Solvent Cement 5 liter
P-trap (1" dia) 7 PIECE
Wye reducer (4x2) 4 PIECE
Wye (4x4) 4 PIECE

4. PLUMBING FIXTURES AND ACCESSORIES

Water Closet 3 set


Lavatory 3 set
Soap Holder 3 set
Toilet Paper Holder 3 set
Kitchen Sink 1 set
Towel Holder 3 set
Shower Head (chrome) 3 set
Floor Drain (durametal) 3 PIECE

5. FLOOR AND OTHER INTERIOR WORKS

Glazed Wall Tiles, (8" X 8") 1425 PIECE


Rugby Glue for Vinyl Tiles 8 4Lcan
Unglazed Floor Tiles, (8" X 8") 141
Prime White Cement 6 BAG
Tile adhesive 6 kilo

6. ELECTRICAL MATERIALS

uPVC utility boxes, 38mmX100mmX54mm 15 PIECE


uPVC junction boxes, 38mmX100mmX54mm 15 PIECE
Wire for Range 8.0mm 5 meter
Wire for service Entrance 14mm 10 meter
Plastics Lamp Receptacle 40 PIECE
Wall Switch Module, 5A, 250V, AC 10 PIECE
Duplex Convenience Outlets 6 PIECE
Three-way Switch Module, 5A, 250V, AC 6 PIECE
ACU outlet 1 PIECE
Breaker 30ampere 3 PIECE
Breaker 20ampere 7 PIECE
Breaker 60ampere 1 PIECE
Panel Board 8hole 1 PIECE
Circular flourescent lamp 25 PIECE
Daylight bulb 11 PIECE

7. PAINTING MATERIALS
(DUTCH BOY OR BOYSEN)

Flatwall Latex Paint, White 42 16L can


Flatwall Enamel Paint, White 44 16L can
Quick Drying Enamel, White 44 16L can
Oil Tinting Colors (Brown) 5 1L can
Acrylic Tinting Colors (Brown) 3 1L can
Primer Thinner 42 4L can
Gloss Enamel 48 16L can
Concrete Neutralizer 29 liters
Gloss Latex 22 16L can
Masonry putty 29 4L
Glazing Putty 20 gal
Sandpapers #100 14 pcs
Steel Brush 5 piece
ROLLER TRAY 10
Roller Brush 7" 3 piece
Roller Brush 9" 3 piece
Paint Brush 4" 7 piece
Paint Brush 3" 7 piece
Paint Brush 2" ordinary 3 piece
Paint Brush 1" ordinary 5 piece
Paint Brush 1 1/2"ordinary 5 piece
Paint Brush 1/2"ordinary 3 piece

8. DOORS AND WINDOWS


Steel Casement Window 198 FT2
Fixed Window 71 FT
Panel Type Door (1.00 x 2.10) 2 set
Panel Type Door (0.80 x 2.10) 4 set
Flush Type Door (0.70 x 2.10) 4 set
PVC Type Door (0.70 x 2.10) 3 set

Designer:___________________________ Checked by:____________________


Rodel T. Grande Engr. Ritchie Malas
(Student)

Approved by:__________________________________
Kevin G. Martin
(Owner)
tial with Attic

cada, Tarlac

BILL OF MATERIALS

Unit cost Total cost

188.00 156040
130.00 28990
130.00 6760
155.00 22475
7.00 15400
8.00 44168

130.00 116025
188.00 208868
35 10605
35.00 315
35.00 1715
35.00 472.5
35.00 157.5
45.00 405
45.00 405
34.00 35666
12.00 135324
270.00 24300
255.00 17340
825431

390.00 58110
140.00 67620
390.00 5460
280.00 43680
80.00 1760
60.00 600
95.00 3515
360.00 1800
30.00 573
35.00 700
50.00 1000
184818

230.00 5060
170.00 1700
35.00 140
35.00 105
35.00 630
25.00 100
40.00 80
30.00 210
420.00 8400
25.00 125
20.00 400
20.00 40
35.00 140
15.00 150
7.00 70
160.00 160
210.00 210
115.00 575
95.00 95
190.00 950
50.00 350
65.00 260
65.00 260
20210

3100.00 9300
1500.00 4500
100.00 300
80.00 240
650.00 650
150.00 450
550.00 1650
65.00 195
17285

15.00 21375
600.00 4800
122.00 17202
260.00 1560
230.00 230.00
18992.00

20.00 300
20.00 300
50.00 250
50.00 500
20.00 800
45.00 450
130.00 780
50.00
100.00 100
320.00 960
160.00 1120
350.00 350
480.00 480
210.00 5250
50.00 550
11590

1800.00 75600
1600.00 70400
1900.00 83600
88.00 440
88.00 234.432
35.00 1470
980.00 47040
35.00 1015
1300.00 28600
250.00 7250
450.00 9000
8.00 112
13.00 65
19.00 190
30.00 90
35.00 105
35.00 245
15.00 105
15.00 45
10.00 50
12.00 60
8.00 24

325740.432

750.00 148500
500.00 35500
880.00 1760
750.00 3000
450.00 1800
1400.00 4200

194760

Checked by:________________________
Engr. Ritchie Malasan
(Instructor)
Project Title: Proposed 2-Storey Residential with Attic
Project Owner: Rodel T. Grande
Project Location: Brgy. Tolega Sur, Moncada, Tarlac

SUMMARY COST ESTIMATES FOR MATERIALS, LABOR AND OTHER CONSTRUCTION


EXPENSES

A. ESTIMATES COST OF MATERIALS


FOUNDATION, CONCRETE COLUMNS, AND CONCRETE
1 825431.000
HOLLOW BLOCKS WALLS
2 ROOF FRAMING
184818.000
3 ROOFING MATERIALS
4 PLUMBING FIXTURES AND ACCESSORIES 11740.000
5 CEILING, FLOOR AND OTHER INTERIOR WORKS 18992.000
6 ELECTRICAL MATERIALS 11590.000
7 PAINTING MATERIALS 325740.432
8 DOORS AND WINDOWS 194760.000
1573071.432
B. ESTIMATE COST OF LABOR (45%) 629228.5728

C. CONTINGENCY FUND(5%) 78653.5716

C. TAX(12%) 188768.57184

ESTIMATED TOTAL DIRECT COST 2469722.148

Designer: Checked by:


Rodel T. Grande Engr. Ritchie Malasan
(student) (Instructor)

Approved by:
Kevin G. Martin
(owner)
dential with Attic

Moncada, Tarlac

ES FOR MATERIALS, LABOR AND OTHER CONSTRUCTION


EXPENSES

825431.000

184818.000

11740.000
18992.000
11590.000
325740.432
194760.000
1573071.432
629228.5728

78653.5716

188768.57184

2469722.148

Engr. Ritchie Malasan


(Instructor)
ESTIMATE OF 2-STOREY RESIDENTIAL BUILDING

MASONRY AND CONCRETE WORKS

COLUMN AND COLUMN FOOTING

CRITERIA C1F1 C2F1 WALL


Height above the GL (1st floor) 3.40 3.4 3.40
Height above the GL (2nd floor) 3.00 1 3.00
Height below the GL 0.90 0.7 0.40
Number of Pieces (1st floor) 23 8
Number of Pieces (2nd floor) 15 6
Width 0.30 0.25 0.20
64.35
Length 0.20 0.25
56.60
Height of footing 0.30 0.3 0.20
Footing width 1.00 1.00 0.40
Footing length 1.00 1.00 64.35

SLAB
LEVEL THICKNESS AREA
1st floor 0.13 127.39
67.66
2nd floor 0.10
89.66

VC1 = 0.30 * 0.20 * 7.3 * 38


= 16.644 m
VC2-1 = 0.25 * 0.25 * 4.1 * 8
= 2.05 m
VC2-2 = 0.25 * 0.25 * 1 * 6
= 0.375 m
VF1 = 1.00 * 1.00 * 0.3 * 31
= 9.3 m

VT = 28.369 m

Using 40 kg Cement, Class A Mixture


Cement = 28.369 * 9.0 = 256 bags
Sand = 28.369 * 0.5 = 14.1845 m
Gravel = 28.369 * 1.0 = 28.369 m
WALL FOOTING
For Residential Bldg. For Septic Tank & Catch Basin
PW = 64.35 m VT = 0.06
VT = 64.35 x 0.20 x 0.20 = 0.09
= 2.574 m

Using 40 kg Cement, Class A Mixture


Cement = 2.66 * 9.0 = 24 bags
Sand = 2.66 * 0.5 = 1.332 m
Gravel = 2.66 * 1.0 = 2.664 m
CONCRETE BEAM
PW = 64.35 m
VT = 64.35 x 0.30 x 0.20
= 3.861 m

Using 40 kg Cement, Class A Mixture


Cement = 3.861 * 9.0 = 35 bags
Sand = 3.861 * 0.5 = 1.9305 m
Gravel = 3.861 * 1.0 = 3.861 m

CONCRETE SLAB
For Residential Bldg. For Septic Tank & Catch Basin
VT = 127.39 x 0.13 VT = 0.34
= 16.17853 m = 0.51

Using 40 kg Cement, Class A Mixture


Cement = 16.68 * 9.0 = 151 bags
Sand = 16.68 * 0.5 = 8.34239 m
Gravel = 16.68 * 1.0 = 16.68478 m

CONRETE HOLLOW BLOCK (CHB)


For Residential Bldg. For Septic Tank & Catch Basin
AWALL-1 = 3.60 x 64.35 AWALL-1 = 10.50
= 231.66 m = 16.8
AWALL-2 = 3.00 x 56.60 AWALL-2 = 2.40
= 169.8 m = 10.08
#CHB = 401.5 x 12.50 #CHB = 26.9
= 5018 pcs = 336

15 x 20 x 40 cm CHB
# CHB = 5018.3 * 1.1 = 5521 pcs
10 x 20 x 40 cm CHB
# CHB = 336.0 * 1.1 = 370 pcs

CEMENT MORTAR FOR CHB


AWALL-T = 231.66 + 169.8 + 26.88
= 428.34 m

Along 15x20x30cm CHB, Class B


Cement = 428.34 * 0.522 = 224 bags
Sand = 428.34 * 0.435 = 186.3279 m
CEMENT MORTAR FOR PLASTERING
AT = 231.66 + 169.8 + 26.88 x 2
= 856.68 m

Using 40 kg Cement, Class B Mixture, 12mm


Cement = 856.68 * 0.144 = 124 bags
Sand = 856.68 * 0.012 = 10.28016 m
STAIRCASE
A1 = 0.288 m
A2 = 5.8157 m
AT = 6.1037 m
VT = 10.98666 m

Using 40 kg Cement, Class B Mixture, 12mm


Cement = 10.98666 * 0.144 = 2 bags
Sand = 10.98666 * 0.012 = 0.13184 m

SUMMARY
Cement = 814 bags of 40 kg cement
Sand = 223 m
Gravel = 52 m
# CHB = 5521 pieces of 15x20x30cm CHB
= 370 pieces of 10x20x30cm CHB
METAL REINFORCEMENT

REINFORCEMENT FOR CHB


AWALL-1 = 3.60 x 64.35
= 231.66 m 2693.59587
# 6m RSB =
AWALL-2 = 3.00 x 56.60 6
= 169.8 m = 449
AT = 231.66 + 169.8
= 401.46 m Tie Wires
# kg = 401.46
For Vert. Reinf. in every 3 layers = 10.5
L = 401.46 x 2.13
= 855.1098 m
For Hor. Reinf. 0.6 spacing
L = 855.1098 x 2.15
= 1838.48607 m
LT = 855.1098 + 1838.486
= 2693.59587 m

FOR COLUMN FOOTING


10 - 12 mm RSB 6
# CB/6m =
LCB = 0.85 + 0.216 2
= 2 m # 6m RSB = 104
# CB = 310
Tie Wires
# kg = 93
= 1.8

FOR WALL FOOTING


Continuous Bars 3 -12mm 212.355
# 6m RSB =
LT = 64.35 * 1.1 6
= 212.355 m = 36

Transverse Bars 6
# TB/6m =
12 mm RSB & 0.3 m spacing 1
LCB = 0.25 + 0.216 # 6m RSB = 36
= 1 m
# TB = 214 pcs Tie Wires
# kg = 749.25
= 14.2
FOR COLUMN
Main reinf.
Column 1 6 -12mm
LC1-1T = 4.60 x 23
= 761.76 m 1283.52
# 6m RSB =
LC1-2T = 3.00 x 15 6
= 324.00 m = 214
Column 2 4 -12mm
LC2-1T = 4.40 x 8 6
# LT1/6m =
= 168.96 m 0.88
LC2-1T = 1.00 x 6 = 6.82
= 28.80 m
Lateral Ties 0.2 spacing 6
# LT2/6m =
Column 1 10 mm RSB 0.88
L1 = 0.68 + 0.2 = 6.82
= 0.88 m
# LT1 = 1482 pcs # 6m RSB = 275
Column 2 10 mm RSB
L2 = 0.68 + 0.2 Tie Wires
= 0.88 m # kg = 9456
# LT2 = 392 pcs = 178.5

FOR BEAMS
Main reinf.
LT = 64.35 + 56.60 x 1.2 145.14
# 6m RSB =
= 145.14 m 6
= 25
Stirrups 10 mm RSB
0.2 spacing 6
# S/6m =
LT = 0.68 + 0.2 0.88
= 0.88 m = 6
# Stir. = 605 pcs # 6m RSB = 101

Tie Wires
# kg = 1089 / 53 m/kg # kg = 20.6

FOR SLAB REINFORCEMENT (ONE WAY)


Main Reinfocement = 0.15 m, 12 mm RSB
Temperature bar = 0.30 m, 12 mm RSB

Main reinf. Using 6m RSB, 0.15m spacing, 12mm


AT = 127.39 m # 6m RSB = 127.39
330
Tie Wires Along 0.15m spacing, 0.30 m Tie Wires
# kg = 127 x 0.228 kg/m # kg = 29.1

FOR SLAB REINFORCEMENT (TWO WAY)


Main Reinfocement = 0.10 m, 12 mm RSB
Temperature bar = 0.20 m, 12 mm RSB

Main reinf. Using 6m RSB, 0.10m spacing, 12mm


AT = 89.66 m # 6m RSB = 89.66
338
Tie Wires Along 0.10m spacing, 0.30 m Tie Wires
# kg = 89.66 x 0.474 kg/m # kg = 42.5
FOR STAIRCASE
Main reinf.
LT = 2.3 + 1.7 + 2 # Bars = 9
= 6 m # 6m RSB = 54

Hor. Bars
LHB = 1 m # 6m RSB = 10
# HB = 60 pcs
# B/6m = 6 pcs

Tie Wires
# kg = 162 / 53 m/kg # kg = 3.1

FOR SEPTIC TANK


For CHB
AT = 16.8 71.904
# 6m RSB =
For Vert. Reinf. in every 3 layers 6
L = 16.8 x 2.13 = 12
= 35.784 m
For Hor. Reinf. 0.6 spacing Tie Wires
L = 16.8 x 2.15 # kg = 16.8
= 36.12 m = 0.5
LT = 35.784 + 36.12
= 71.904 m

For Slab
L1 = 3 # Bars = 8
# B/6m = 2 pcs
L2 = 1.5 # Bars = 14
# B/6m = 4 pcs # 6m RSB = 8

Tie Wires
# kg = 19.8 / 53 m/kg # kg = 0.4

FOR CATCH BASIN


For CHB
L1 = 0.6 # Bars = 8
# B/6m = 10 pcs # 6m RSB = 4

For Slab
L1 = 0.6 # Bars = 8
# B/6m = 10 pcs # 6m RSB = 8

Tie Wires
# kg = 44 / 53 m/kg # kg = 1

SUMMARY
RSB = 1111 pcs. 12mm RSB
= 893 pcs. 10mm RSB
Tie wire = 303 kg # 16 GI Wire

EXCAVATION AND BACKFILL

Volume of soil recovered


= 9.3 + 2.574 + 0.09
= 11.96 m

Volume of space req'd to fill


= 127.39 + 0.4 - 0.13
= 127.66 m

Volume of earth req'd


= 127.66 - 11.96 * 1.25
= 144.62375 m

SUMMARY
Earth = 145 m of Earth Fill (mix)

TILE WORKS

NO. OF GLAZED WALL TILES


AT = 1.5 x 2.5 + 2.25 x 2
= 57.00 m
AT = 0.2 x 0.2
= 0.04 m
# Tiles = 57 / 0.04
= 1425 pcs

NO. OF UNGLAZED FLOOR TILES


AT = 2.5 x 2.25
= 5.625 m
AT = 0.2 x 0.2
= 0.04 m
# Tiles = 5.625 / 0.04
= 141 pcs

NO. OF CEMENT, SAND, ADHESIVE


AT = 57 + 5.63
= 62.63

Using 40 kg Cement, Class A Mixture


Cement = 62.63 * 0.086 = 6 bags
Sand = 62.63 * 0.172 = 11 m
Adhesive = 62.63 * 0.086 = 6 m

SUMMARY
Cement = 6 bags of 40 kg cement
Sand = 11 m
Adhesive = 6 m
# Tiles = 1425 pieces of 1/8"x8"x8" Glazed tile
= 141 pieces of 1/8"x8"x8" Glazed tile

CEILING JOIST AND CEILING BOARD

CEILING JOIST
AT = 127.39 + 67.66
= 195.05 m

Using 2"x2", 0.4x0.6m spacing


# bd ft = 195.05 * 5.373 = 1049 bd ft.
# kg = 1 * 8 = 9 kg of nail

CEILING BOARD
AT = 195.05 m

Using 1/4"X4'X8' Marine Plywood


# PW = 195.05 / 2.880 = 68 Pcs

SUMMARY
bd ft. = 1049 bd ft 2"x2" of good lumber
pcs = 68 pcs of 1/4"x4'x8' marine plywood
kg = 9 kg of 2 1/2" nail

FORM, SCAFOLDING AND STAGING

FORM FOR COLUMN


Plywood Form
P = 1.2 m
P = 1.2 m
AT = 147.84 + 39.84
= 187.68 m

Using 1/4"X4'X8' Marine Plywood


# PW = 147.84 / 2.880 = 52 Pcs

2" x 2" Frame


Using 2"X2" Frame, 1/4" thk. Plywood
# bd ft = 52 * 29.67 = 1543 bd ft
# kg = 1.54 * 8 = 13 kg of nail

FORM FOR BEAM & GIRDER


Plywood Form
PT = 120.95 m
PB = 0.9 m
AT = 108.855 m

Using 1/4"X4'X8' Plywood


# PW = 108.86 / 2.880 = 38 Pcs

2" x 2" Frame


Using 2"X2" Frame, 1/4" thk. Plywood
# bd ft = 38 * 25.06 = 953 bd ft
# kg = 0.95 * 8 = 8 kg of nail

FORM FOR FLOOR SLAB


AT = 89.66 m

Using 2"X2" Frame, 1/4" thk. Plywood


# bd ft = 89.66 * 2.88 = 259 bd ft
# kg = 0.26 * 8 = 3 kg of nail

SCAFOLDING FOR COLUMN


LT = 161.6 m

For Vert. Support


Using 2"X2" lumber
# bd ft = 162 * 4.7 = 755 bd ft

For Hor. Support


Using 2"X2" lumber
# bd ft = 162 * 21 = 3394 bd ft

For Diagonal Brace


Using 2"X2" lumber
# bd ft = 162 * 11.7 = 1891 bd ft
# kg = 1.89 * 8 = 16 kg of nail

SCAFOLDING FOR BEAM


LT = 120.95 m

For Vert. Support


Using 2"X2" lumber
# bd ft = 121 * 5 = 565 bd ft

For Hor. Support


Using 2"X2" lumber
# bd ft = 121 * 9.1 = 1101 bd ft
# kg = 1.10 * 8 = 9 kg of nail

SCAFOLDING FOR SLAB


AT = 89.66 m

Using 2"X3" lumber


# bd ft = 90 * 9 = 816 bd ft

SUMMARY
bd ft. = ### bd ft 2"x2" of Coco lumber
bd ft. = 816 bd ft 2"x3" of Coco lumber
pcs = 90 pcs of 1/4"x4'x8' plywood
kg = 49 kg of 3" nail
ROOFING MATERIALS

CORRUGATED G1 SHEET
A1 = 18.2 x 6.07
= 110.474 m
A2 = 14.015 x 2.9
= 40.6435 m
A3 = 7.14 x 2.34 x 2
= 33.4152 m
A4 = 26.0151 x 3.64
= 94.694964 m
A5 = 12.8 x 3.76
= 48.128 m

AE = 2.1
# pcs = 327.355664 / 2.1
# pcs = 156 pcs of 10 ft Corr. GI Sheet

RIVETS
# kg = 156 x 22 / 180
# kg = 19.10 kg

G.I. WASHERS
# pcs = 225.328 / 126
# pcs = 28 kg

C-PURLINS
2"x3"x6m
# 6.07 + 2.9 + 2.34 + 3.64 + 3.76
=
0.6
= 37 pcs
LP = 78.1701 m
LT = 2892.2937 m

# 6m = 483 pcs of 2"x3" C-purlins

2"x6"x6m
LT = 78.1701

# 6m = 14 pcs of 2"x6" C-purlins


RIDGE ROLL
LT = 47.095

# 2.2 = 22 pcs of 2.2 m Ridge roll

GUTTER & FLASHING GUTTER


LT1 = 85.3101 m
LT2 = 21.05 m

#G = 36.3021702 pcs of 2.35 gutter


# FG = 9.15217391 pcs of 2.35 flashing gutter
ANGLE BAR
LT = 893.225664 m

# 6m< B = 149 pcs of 2"x3/16"x6m Angle Bar

TEKSCREW
AT = 327.355664 m

# kg = 17 kg of tekscrew

SUMMARY
Sheet = 156 pcs of 10 ft Corr. GI Sheet
Rivet = 19 kg
Washer = 28 kg
C-purlins = 483 pcs of 2"x3" C-purlins
C-purlins = 14 pcs of 2"x6" C-purlins
Ridge roll = 22 pcs of 2.2 m Ridge roll
Gutter = 37 pcs of 2.35 gutter
FG = 10 pcs of 2.35 flashing gutter
< Bar = 149 pcs of 2"x3/16"x6m Angle Bar
Tekscrew = 17 kg of tekscrew

PAINTING WORKS

MASONRY
AT = 856.68 m

Concrete neutralizer
#L = 29 16L of concrete neutralizer

Primer
#L = 25 16L of Flat Wall Latex

Masonry Putty
#L = 29 4L of Masonry Putty

Primer
#L = 25 16L of Flat Wall Latex

Finishing
#L = 22 16L of Gloss Latex
#L = 4 1L of Acrylic tinting color
pcs = 5 pcs of 1 1/2" brush
pcs = 9 pcs of roller tray
pcs = 8 pcs of sand paper
pcs = 4 pcs roller brush

WOOD
AT = 571.12 m
Solignum
#L = 20 L of solignum

Primer
#L = 17 L of Flat Wall Enamel

Glazing Putty
# gal = 20 gal of Glazing putty

Primer
#L = 17 L of Flat Wall Enamel

Finishing
#L = 30 L of Gloss Enamel
#L = 5 1L of Oil tinting color (brown)
pcs = 3 pcs of 2" brush
pcs = 1 pcs of roller tray
pcs = 6 pcs of sand paper
pcs = 3 pcs roller brush

ROOF
AT = 327.355664 m

Rust Converter
#L = 11 L of rust converter

Primer
#L = 10 L of Flat Wall Enamel

Finishing
#L = 18 L of Gloss Enamel
#L = 6 1L of Oil tinting color (red & black)
pcs = 7 pcs of 4" brush
pcs = 2 pcs roller brush

SUMMARY
#L = 29 16L of concrete neutralizer
#L = 42 16L of Flat Wall Latex
#L = 29 4L of Masonry Putty
#L = 22 16L of Gloss Latex
#L = 20 L of solignum
#L = 44 L of Flat Wall Enamel
# gal = 20 gal of Glazing putty
#L = 48 L of Gloss Enamel
#L = 3 1L of Acrylic tinting color
#L = 5 1L of Oil tinting color (brown)
#L = 11 L of rust converter
#L = 6 1L of Oil tinting color (red & black)
pcs = 5 pcs of 1 1/2" brush
pcs = 3 pcs of 2" brush
pcs = 7 pcs of 4" brush
pcs = 10 pcs of roller tray
pcs = 14 pcs of sand paper
pcs = 9 pcs roller brush

PLUMBING WORKS

SANITARY PIPES
LT = 64.35 m

Pipes - (4" dia X 10') = 22 pcs


Pipes - (3" dia X 10') = 10 pcs
Sanitary Tee, (3" dai) = 4 pcs
Elbow, 1/8 Bend (3" dia) = 3 pcs
Elbow, 90o (3" dia) = 18 pcs
Reducer Coupling, (2" dia X 3" dia) = 4 pcs
Floor Drain Trap, (2" dia) = 2 pcs
Clean-out w/ Plug, (3" dia) = 7 pcs

GI PIPES & FITTINGS


LT = 115.83 m

Pipes - (1" dia X 20') = 20 pcs


Elbow, 90o (3/4" dia) = 5 pcs
Elbow, 90 (1" dia)
o = 20 pcs
Elbow, 90o (1/2" dia) = 2 pcs
Niple, (1/2" X 6") = 4 pcs
Coupling, (1") = 10 pcs
Teflon Tape (1/2) = 10 roll
Water Meter = 1 pcs
Gate Valve = 1 pcs
Faucet (brass plain bibb 1/2) = 5 pcs
Hose Bibbs = 1 pcs
Solvent Cement = 5 L
P-trap (1" dia) = 7 pcs
Wye reducer (4x2) = 4 pcs
Wye (4x4) = 4 pcs

PLUMBING FIXTURE & ACCESSORIES

Water Closet = 2 set


Lavatory = 2 set
Soap Holder = 2 set
Toilet Paper Holder = 2 set
Kitchen Sink = 1 set
Towel Holder = 2 set
Shower Head (chrome) = 2 set
Floor Drain (durametal) = 2 pcs
Bath tub = 1 pcs
ELECTRICAL WORK
WIRES
LT = 257.40 m

LWIRE = 2 m/box

FLEXIBLE HOSE
LFH = 258 m

OTHER ELECTRICAL MATERIALS

uPVC utility boxes, 38mmX100mmX54mm = 15 pcs


uPVC junction boxes, 38mmX100mmX54mm = 15 pcs
Wire for Range 8.0mm = 5 m
Wire for service Entrance 14mm = 10 m
Plastics Lamp Receptacle = 40 pcs
Wall Switch Module, 5A, 250V, AC = 10 pcs
Three-way Switch Module, 5A, 250V, AC = 6 pcs
Duplex Convenience Outlets = 6 pcs
ACU outlet = 1 pcs
Breaker 40ampere = 3 pcs
Breaker 20ampere = 7 pcs
Breaker 100ampere = 1 pcs
Panel Board 10hole = 1 pcs
Circular flourescent lamp = 25 pcs
Daylight bulb = 11 pcs

DOORS & WINDOWS

AT = 5.3026 + 21.5869 + 2.88 + 1.5814


31.3509 m
#W = 19 pcs
Sliding window = 32 ft2
Panel door solid narra = 9 pcs
PVC door = 2 pcs
2-STOREY RESIDENTIAL BUILDING

RY AND CONCRETE WORKS

BEAM
0.3
0.3

0.2

64.35

SLAB
ELEV.
0.4
0
For Septic Tank & Catch Basin
x 1.50
m
For Septic Tank & Catch Basin
x 1.50
m

For Septic Tank & Catch Basin


x 1.60
m
x 0.60
m
x 12.50
pcs
ETAL REINFORCEMENT

pcs. 10mm RSB

x 0.026
kg # 16 GI Wire

= 3

pcs. 12mm RSB

/ 53 m/kg
kg # 16 GI Wire

pcs. 12mm RSB

= 6

pcs. 10mm RSB

/ 53 m/kg
kg # 16 GI Wire
pcs. 12mm RSB
pcs. 10mm RSB

/ 53 m/kg
kg # 16 GI Wire

pcs. 12mm RSB

pcs. 10mm RSB

kg # 16 GI Wire

Using 6m RSB, 0.15m spacing, 12mm RSB


x 2.584
pcs. 12mm RSB
Along 0.15m spacing, 0.30 m Tie Wires
kg # 16 GI Wire

Using 6m RSB, 0.10m spacing, 12mm RSB


x 3.764
pcs. 12mm RSB
Along 0.10m spacing, 0.30 m Tie Wires
kg # 16 GI Wire
pcs
pcs. 12mm RSB

pcs. 12mm RSB

kg # 16 GI Wire

pcs. 10mm RSB

x 0.026
kg # 16 GI Wire

pcs

pcs
pcs. 10mm RSB

kg # 16 GI Wire

pcs
pcs. 10mm RSB

pcs
pcs. 10mm RSB

kg # 16 GI Wire

AVATION AND BACKFILL

TILE WORKS
ROOFING MATERIALS

+ 5
PAINTING WORKS
PLUMBING WORKS
ELECTRICAL WORK

DOORS & WINDOWS


COMPUTATION OF LABOR
(1 working day = 8 hours)

Activity 1: CLEARING OF SITE & JOB LAY-OUT

Manual Clearing
Manhour Capability = 0.03 hr/m2
Total Area = 340 m2
Layout & Staking =
Manhour Capability = 0.20 hr/m2
Total Floor Area = 217.05 m2

No. of Persons = 4
No. of Days = 1.68 day(s) say 2 day(s)

Activity 2: EXCAVATION (FOOTING, COLUMN & SEPTIC TANK)

Manhour Capability = 1.35 m3/md


Total Volume = 127.66 m3
No. of Persons = 12
No. of Days = 7.88 days say 8 day(s)

Activity 3: FABRICATION OF REBARS FOR COLUMN FOOTINGS & WALL FOOTING

Manhour Capability = 0.071 MH/kg


Total No. of KG = 879.4 kg

No. of Persons = 15
No. of Days = 0.5 days say 1 day(s)

Activity 4: FABRICATION OF FORMS

Manhour Capability = 1.42333333 MH/m


Total Area = 386.2 m2

No. of Persons = 8
No. of Days = 8.6 days say 9 day(s)

Activity 5: INSTALLATION OF COLUMN FOOTING & WALL FOOTING

Manhour Capability = 0.071 MH/kg


Total No. of KG = 1071.3 kg

No. of Persons = 15
No. of Days = 0.6 days say 1 day(s)

Activity 6: ROUGHING IN PLUMBING

Manhour Capability =
Pipes = 1.00 hr/pc 52 pcs
Clean Outs = 2.00 hr/pc 7 pcs

No. of Persons = 6
No. of Days = 1.38 days say 2 day(s)

Activity 7: CONCRETING OF COLUMN FOOTING AND WALL FOOTING

Equipment Capability
1 Bagger conc. mixer = 8.00 m3/day x 85% = 6.8
Pouring = 5.00 hr/m 3

Total Volume = 11.87 m3

No. of Persons = 5
No. of Days = 3.23 days say 4 day(s)
Activity 8: LAYING OF CHB WALL

Manhour Capability = 1.25 m2/hr


Total Area = 428.3 m2

No. of Persons = 18
No. of Days = 4.76 days say 5 day(s)

Activity 9: INSTALLATION OF FORMS, SCAFFOLDING & STAGING FOR COLUMNS

Manhour Capability = 0.85 m2/hr


Total Area of Columns = 187.7 m2

No. of Persons = 8
No. of Days = 6.90 days say 7 day(s)

Activity 10: CONCRETING OF COLUMN

Equipment
1 Bagger conc. mixer = 8.00 m3/day x 85% = 6.8
Pouring = 5.00 hr/m3
Total Volume = 18.69 m3

No. of Persons = 8
No. of Days = 4.21 days say 5 day(s)

Activity 11: FABRICATION OF REBARS FOR BEAM & SLAB

Manhour Capability = 10 kg/hr


Total No. of KG = 2308.5 kg
No. of Persons = 15
No. of Days = 1.92 days say 2 day(s)

Activity 12 : REMOVAL OF FORMS & SCAFFOLDING FOR COLUMN


Manhour Capability = 2.35 m2/hr
Total Area of Columns = 187.68 m2
No. of Persons = 5
No. of Days = 3.99 days say 4 day(s)

Activity 13: INSTALLATION OF FORMS, SCAFFOLDING & STAGING FOR BEAMS


Manhour Capability = 0.65 m2/hr
Total Area of Beams = 108.86 m2
No. of Persons = 10
No. of Days = 4.19 days say 5 day(s)

Activity 14: INSTALLATION OF RC BEAM REBARS

Manhour Capability = 10 kg/hr


Total No. of KG = 506.95 kg
No. of Persons = 15
No. of Days = 0.84 days say 1 day(s)
Activity 15: CONCRETING OF RC BEAM

Equipment Capability
1 Bagger conc. mixer = 8.00 m3/day x 85% = 6.8
Pouring = 5.00 hr/m 3

Total Volume = 8.71 m3


No. of Persons = 6
No. of Days = 2.19 days say 3 day(s)

Activity 16: BACKFILLING OF FOOTING AND FLOOR SLAB

Manhour Capability = 1.22 m3/hr


Total Volume of backfill = 11.96 m3
No. of Persons = 2
No. of Days = 0.61 days say 1 day(s)

Activity 17: SPREADING, TAMPING & GRADING

Manhour Capability = 2.09 m2/hr


Total Area = 127.66 m2
No. of Persons = 4
No. of Days = 1.91 days say 2 day(s)

Activity 18: CONCRETING OF FLOOR SLAB

Manhour Capability = 0.20 m2/hr


Total Area = 217.05 m2
No. of Persons = 6
No. of Days = 22.61 days say 23 day(s)

Activity 19: STRIPPING OF FORMS AT BEAM STRUCTURE

Manhour Capability = 1.95 m2/hr


Total Area of Beams = 108.86 m2
No. of Persons = 4
No. of Days = 3.49 days say 4 day(s)

Activity 20: SEPTIC TANK

Fabrication of Rebars
Manhour Capability = 10 kg/hr
Total No. of KG = 72.15 kg
No. of Persons = 2
No. of Days = 0.90 days say 1 day(s)

Installation of Rebars
Manhour Capability = 10 kg/hr
Total No. of KG = 72.15 kg
No. of Persons = 2
No. of Days = 0.90 days say 1 day(s)

Concreting
Equipment Capability
1 Bagger conc. mixer = 8.00 m3/day x 85% = 6.8
Pouring = 5.00 hr/m3
Total Volume = 7.20 m3

No. of Persons = 4
No. of Days = 2.18 days say 3 day(s)
Laying (4" CHB) = 1.25 m2/hr
Total Area = 26.88 m2
No. of Persons = 4
No. of Days = 1.34 days say 2 day(s)

Activity 21: INSTALLATION OF FABRICATED DOOR JAMB

Manhour Capability = 40.00 bf/day


Total bd.ft = 55.00 bd.ft

No. of Persons = 2
No. of Days = 0.69 days say 1 day(s)

Activity 22: STEEL TRUSS FABRICATION & INSTALLATION

Fabrication of Rebars
Manhour Capability = 3.06 hr/m2
Total No. of pcs = 149.00 m2 2" x 2" 3/16" Angle Bar
No. of Persons = 17
No. of Days = 3.35 days say 4 day(s)

Installation of Rebars
Manhour Capability = 3.06 hr/m2
Total No. of pcs = 156.50 m2 2" x 2" 3/16" Angle Bar
No. of Persons = 17
No. of Days = 3.52 days say 4 day(s)

Activity 23: INSTALLATION OF PURLINS & RAFTERS

Manhour Capability = 3.06 hr/m2


Roof Area = 327 m2

No. of Persons = 15
No. of Days = 8.35 days say 9 day(s)

Activity 24: ROUGH IN ELECTRICAL CONDUIT

Manhour Capability = 1.33 hr/m2


Total Area = 127.39 m2

No. of Persons = 6
No. of Days = 3.53 days say 4 day(s)

Activity 25: INSTALLATION OF CORRUGATED GI SHEET ROOFING

Total Area of Roof = 327.36 m2


Lifting
Manhour Capability = 1.08 hr/m2

Installing
Manhour Capability = 3.06 hr/m2

No. of Persons = 14
No. of Days = 12.10 days say 13 day(s)
Activity 26: PLASTERING OF CHB WALLS

Manhour Capability = 1.67 hr/m2


Total Wall Area = 428.34 m2

No. of Persons = 20
No. of Days = 4.47 days say 5 day(s)

Activity 27: INSTALLATION OF GUTTER & DOWN SPOUT

Gutter
Manhour Capability = 0.81 hr/m
Total Perimeter = 106.36 m

Down Spout
Manhour Capability = 0.31 hr/m
Total Length = 64.00 m

No. of Persons = 5
No. of Days = 2.65 days say 3 day(s)

Activity 28: INSTALLATION OF SCAFFOLDING FOR CEILING

Manhour Capability = 0.50 hr/m2


Total Area of Ceiling = 195.05 m2

No. of Persons = 4
No. of Days = 3.05 days say 4 day(s)

Activity 29: INSTALLATION OF CEILING FRAME

Manhour Capability = 1.33 hr/m2


Total Area of Ceiling = 127.61 m2

No. of Persons = 6
No. of Days = 2.00 days say 2 day(s)

Activity 30: INSTALLATION OF ELECTRICAL FIXTURES

Manhour Capability
Lighting Fixtures = 1.25 hr/set 36 sets
CO = 1.25 hr/set 6 sets
THHN #10/7 = 0.267 hr/m 47 m
THHN #12/7 = 0.267 nr/m 50 m
Panel Board = 1.15 hr/set 1 sets
Utility Box = 0.19 hr/set 15 sets
Switches = 1.25 hr/set 16 sets

No. of Persons = 6
No. of Days = 2.13 days say 3 day(s)
Activity 31: INSTALLATION OF CEILING BOARD

Manhour Capability = 1.00 hr/m2


Total Area of Ceiling = 127.61 m2

No. of Persons = 8
No. of Days = 1.99 days say 2 day(s)

Activity 32: INSTALLATION OF SANITARY FIXTURES

Manhour Capability
Lavatory = 8 hr/set 2 sets
Water closet = 8 hr/set 2 sets
Bath tub = 8 hr/set 1 sets
Kitchen sink = 14 hr/set 1 sets
Kitchen faucet = 2 hr/set 1 sets
Gate Valve = 8 hr/set 1 sets
Faucet = 2 hr/set 5 sets
Floor Drain = 2 hr/set 2 sets

No. of Persons = 8
No. of Days = 1.22 days say 2 day(s)

Activity 33: INSTALLATION OF FABRICATED DOORS & WINDOWS

Manhour Capability
Doors = 2 sets/day 9 sets
Windows = 1 set/hr 19 sets

No. of Persons = 4
No. of Days = 1.72 days say 2 day(s)

Activity 34: INSTALLATION OF TILE WORKS

Manhour Capability = 3 hr/m2


Total Area = 62.63 m2

No. of Persons = 10
No. of Days = 2.35 days say 3 day(s)

Activity 35: PAINTING WORKS


Manhour Capability = 0.43 hr/m2
Total Area = 1,755 m2

No. of Persons = 15
No. of Days = 6.29 days say 7 day(s)

Activity 36: CLEARING OF SITE FOR FINAL INSPECTION & TRANSFER TO THE OWNER

Manhour Capability = 0.30 hr/m2


Total Area = 340 m2

No. of Persons = 7
No. of Days = 1.82 days say 2 day(s)
ABOR
ours)

S & WALL FOOTING


m3/day
NG FOR COLUMNS

m3/day

ING FOR BEAMS


m3/day
m3/day
2" 3/16" Angle Bar

2" 3/16" Angle Bar


ANSFER TO THE OWNER

6
SCHEDULIN

Activity
Activity No.
Path
A 1 - 2
B 2 - 3
C 3 - 4
D 4 - 5
E 5 - 6
F 6 - 7
G 7 - 8
H 8 - 9
I 9 - 10
J 10 - 11
K 11 - 12
L 12 - 13
M 13 - 14
N 14 - 15
O 13 - 16
P 16 - 17
Q 17 - 18
R 18 - 19
S 19 - 20
T 17 - 21
U 21 - 22
V 22 - 23
W 20 - 24
X 24 - 25
Y 25 - 26
Z 25 - 27
A' 26 - 28
B' 28 - 29
C' 29 - 30
D' 29 - 31
E' 30 - 32
F' 32 - 33
G' 33 - 34
H' 34 - 35
I' 35 - 36
J' 36 - 37
K' 34 - 38
L' 38 - 39
M' 39 - 40
N' 39 - 41
O' 40 - 42
P' 42 - 43
Q' 43 - 44
R' 44 - 45
S' 40 - 46
T' 46 - 47
U' 45 - 48
V' 48 - 49
W' 49 - 50
X' 50 - 51
Y' 50 - 52
Z' 52 - 53
A'' 50 - 54
B'' 53 - 55
C'' 55 - 56
D'' 56 - 57
E'' 57 - 58
SCHEDULING

Estimated Time
Duration (Days)
Mobilization
Temporary Facility
Layout
Excavation
Compaction
Fabrication and installation of steel reinforcement bars in column footings
Pouring of concrete on column footing
Fabrication and installation of steel reinforcement bars in columns
Fabrication and installation of forms, scaffoldings and conduit pipes in columns.
Pouring of concrete on columns
Fabrication and installation of steel reinforcement bars for tie beams
Pouring of concrete on tie beams
Fabrication and installation of steel reinforcement bars for CHB wall
Laying of CHB at the interior and exterior walls
Backfilling and earthfilling
Compaction
Fabrication and installation of steel reinforcement bars for on-fill slab
Fabrication and installation of plumbing pipes
Pouring of concrete on on-fill slab
Fabrication and installation of steel reinforcement bars for stairs (until landing)
Fabrication and installation of forms and scaffoldings for stairs
Pouring of concrete and vibrating on stairs
Fabrication and installation of steel reinforcement bars for floor beams
Fabrication and installation of forms and scaffoldings for floor beams, 2nd floor slab and stairs
Fabrication and installation of steel reinforcement bars for 2nd floor slab and stairs
Fabrication and installation of conduit pipes and plumbing pipes on 2nd floor slab and floor beams
Pouring of concrete and vibrating on floor beams, 2nd floor slab and stairs
Fabrication and installation of steel reinforcement bars for 2nd floor columns
Fabrication and installation of forms and scaffoldings for 2nd floor columns
Fabrication and installation of conduit pipes on 2nd floor columns
Pouring of concrete on 2nd floor columns
Fabrication and installation of steel reinforcement bars for CHB wall
Laying of CHB at the interior and exterior walls
Fabrication and installation of steel reinforcement bars for stairs (until landing)
Fabrication and installation of forms and scaffoldings for stairs
Pouring of concrete and vibrating on stairs
Fabrication and installation of steel reinforcement bars for roof deck beams
Fabrication and installation of forms and scaffoldings for roof deck beams, roof deck slab and stairs
Fabrication and installation of steel reinforcement bars for roof deck slab and stairs
Fabrication and installation of conduit pipes on roof deck slab and beams
Pouring of concrete and vibrating on roof deck beams, roof deck slab and stairs
Fabrication and installation of steel reinforcement bars in roof deck columns
Fabrication and installation of forms and scaffoldings in roof deck columns.
Pouring of concretes and vibrating on roof deck columns
Laying of CHB, door jambs and window frames at the exterior walls
Laying of CHB, door jamb and window frames at the interior walls
Fabrication and installation of steel reinforcement bars for parapet wall
Laying of CHB at the parapet wall
Plastering of the CHB at the exterior and interior walls
Installation of doors and window glasses
Installation of plumbing fixtures
Fabrication and installation of tiles (glazed and unglazed)
Installation of electrical fixtures
Painting of exterior and interior walls
Provision of 30m main entrance wire
Demobilization
Clearing
DATA SHEET

Estimated START FINISH FLOAT


Activity NODES
Time ES LS EF LF Total Free
A 1 - 2 0 0 0 0 0 0 0
B 2 - 3 0 0 0 0 0 0 0
C 3 - 4 0 0 0 0 0 0 0
D 3 - 7 0 0 0 0 0 0 0
E 4 - 5 0 0 0 0 0 0 0
F 4 - 9 0 0 0 0 0 0 0
G 5 - 6 0 0 0 0 0 0 0
H 6 - 9 0 0 0 0 0 0 0
I 7 - 8 0 0 0 0 0 0 0
J 8 - 9 0 0 0 0 0 0 0
K 9 - 11 0 0 0 0 0 0 0
L 9 - 10 0 0 0 0 0 0 0
M 10 - 13 0 0 0 0 0 0 0
N 11 - 12 0 0 0 0 0 0 0
O 12 - 16 0 0 0 0 0 0 0
P 13 - 14 0 0 0 0 0 0 0
Q 14 - 15 0 0 0 0 0 0 0
R 15 - 17 0 0 0 0 0 0 0
S 16 - 17 0 0 0 0 0 0 0
T 17 - 21 0 0 0 0 0 0 0
U 17 - 19 0 0 0 0 0 0 0
V 17 - 18 0 0 0 0 0 0 0
W 18 - 20 0 0 0 0 0 0 0
X 19 - 22 0 0 0 0 0 0 0
Y 20 - 22 0 0 0 0 0 0 0
Z 21 - 23 0 0 0 0 0 0 0
A' 22 - 23 0 0 0 0 0 0 0
B' 23 - 24 0 0 0 0 0 0 0
C' 24 - 25 0 0 0 0 0 0 0
D' 24 - 26 0 0 0 0 0 0 0
E' 25 - 27 0 0 0 0 0 0 0
F' 26 - 27 0 0 0 0 0 0 0
G' 27 - 28 0 0 0 0 0 0 0
H' 26 - 28 0 0 0 0 0 0 0
I' 28 - 29 0 0 0 0 0 0 0
J' 29 - 30 0 0 0 0 0 0 0
DATA SHEET

CRITICAL
ACTIVITY
*
*

*
*

*
*

*
*
*

*
*

*
*

*
*

*
*
GANTT C
ACTIVITY 0 2 4 6 8 10 12 14 16 18 20

A Site Clearing and & Job Layout


B Excavation (Footing, Column & Septic Tank)
C Fabrication of Rebars for CF & WF
D Fabrication of Forms
E Installation of Column & Footing
F Roughing in Plumbing
G Concreting of CF and WF
H Laying of CHB Wall
I Installation of Forms, scaffolding & staging for Columns
J Concreting of Column
K Fabrication of Rears for Beam & Slab
L Stripping of Forms & Scaffolding for Columns
M Installation of Forms, scaffolding & staging for Beams
N Installation of RC Beam Rebars
O Concreting of RC Beam
P Backfilling of Footing & Floor Slab
Q Spreading, Tamping & Grading
R Concreting of Floor Slab
S Stripping of Forms at Beam Structure
T Septic Tank
U Installation of Fabricated Door Jamb
V Steel Trust Fabrication & Installation
W Installation of Purlins & Rafters
X Rough in Electrical Conduit
Y Installation of Corrugated GI Sheet Roofing
Z Plastering of CHB Walls
A` Installation of Gutter & Down Spout
B` Installation of Scaffolding for Ceiling
C` Installation of Ceiling Frame
D` Installation of Electrical Fixtures
E` Installation of Ceiling Board
F` Installation of Sanitary Fixtures
G` Installation of Fabricated Doors & Windows
H` Installation of Tile Works
I` Painting Works
J` Clearing of Site For Final Inspection & Transfers to the Owner
GANTT CHART
20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 62 64
66 68 70
NET

5 G 6
0
H K
E 0 0 0

1 3 C 4 F 9
A 0 0
B
0 2 0 0 J
D 0 L
7 I 8
0
NETWORK DIAGRAM

12

N O
0 0
11 16 21

S Z
0 T 0 0

15 R 17 U 19 X 22 A' 23 B'
0 0 0 0 0

0 Q 0 0
V 0
10 14 18 Y

M P 0 W
0 0
13
20
25 E' 27
0
C' G'
0 F' 0 0

24 D' 26 H' 28
0 0

I' 0
29

J' 0

30