Specifier Notes: This product guide specification is written according to the Construction Specifications
Institute (CSI) 3-Part Format, including MasterFormat, SectionFormat, and PageFormat, as described
in The Project Resource ManualCSI Manual of Practice, Fifth Edition.
This section must be carefully reviewed and edited by the Architect or Engineer to meet the
requirements of the project and local building code. Coordinate this section with other specification
sections and the Drawings. Delete all Specifier Notes after editing this section.
Section numbers are from MasterFormat 1995 Edition, with section numbers and titles from
MasterFormat 2004 Edition in parentheses. Delete version not required.
Specifier Notes: This section covers PDU Cables prefabricated, computer-grade, branch-circuit,
power distribution unit (PDU) cable assemblies for use in access flooring for data center applications.
Consult PDU Cables for assistance in editing this section for the specific application and for more
information regarding custom capabilities.
Use PDU Cables Power Cable and Equipment Configurator Excel-based software program to create
custom cable assembly plans. Consult PDU Cables for more information regarding this software.
PART 1 GENERAL
B. Section 10275 (09 69 53.13) Cable Seals: Access flooring cable seals.
Specifier Notes: List reference standards mentioned in this section, complete with designations and
titles. Delete reference standards not included in this edited section. This article does not require
compliance with reference standards, but is merely a listing of those used.
D. UL 498 Standard for Electrical Connectors and UL 2453 Standard for Wiring Assemblies
1.4 SUBMITTALS
Specifier Notes: Edit submittal requirements as required. Delete submittals not required.
E. Test and Evaluation Reports: Submit manufacturers listing and file numbers showing that
prefabricated PDU cable assemblies have been tested and certified by independent testing
laboratory to UL requirements for data processing equipment cables.
F. Source Quality Control Submittals: Submit results of manufacturers factory tests on each
cable.
PART 2 PRODUCTS
2.1 MANUFACTURER
A. PDU Cables, 5401 Smetana Drive, Minnetonka, Minnesota 55343. Toll Free (866) 631-4238.
Fax (800) 336-2801. Website www.pducables.com. E-mail pducables@pducables.com.
a. Liquid tight.
b. Integral Copper Ground Wire: Ensures proper EMI/RFI shielding and ground
bonding integrity.
4. Receptacles and Devices:
a. UL 498.
b. Federal Specification WC-596. ?
c. Industrial grade.
Specifier Notes: Specify requirements for the power cables here or in PDU Cables Power Cable and
Equipment Configurator.
1. Part Number: .
2. Receptacle: .
3. Service:
a. Volts: .
b. AMP: .
c. Phase: .
4. Breaker:
a. Phase: .
b. AMP: .
5. Wire:
a. Quantity: . b.
Size: AWG.
6. Conduit:
a. Size: inches.
1. Part Number: .
2. Service:
a. Volts: [120] [208] [120/208].
b. AMP: [15] [20] [30] [40] [50] [60] [70] [80] [90] [100].
c. Phase: [1] [3].
d. Number of Wires: [3] [4] [5] [6] [7] [8] [ ].
D. Labeling:
1. Cable Identification Labels: Include the following information on cable identification labels
for each cable:
a. Circuit number.
b. Equipment.
c. PDU panel.
d. Receptacle.
e. Cable length.
f. UL certification.
g. Custom configuration, if applicable.
h. Cable manufacturers name and contact information.
2. Label Protection: Clear heat-shrink tubing to prevent alteration or accidental removal.
3. Label Location: Each end of cable.
4. Mark each cable with the following information:
a. Date of manufacture.
b. Technicians identity.
Specifier Notes: Specify required conduit colors. Delete colors not required.
E. Conduit Colors: [Black] [Blue] [Brown] [Dark Purple] [Gray] [Green] [Orange] [Purple] [Red]
[White] [Yellow] [Indicated on the Drawings] [Indicated on the PDU Cables Power Cable and
Equipment Configurator].
2.3 ACCESSORIES
Specifier Notes: Specify required accessories. Consult PDU Cables for more information regarding
accessories and custom capabilities.
B. Multiple-Circuit Cables:
1. Daisy-chained cables.
2. Nippled-box cables.
C. Custom-mounting hardware.
Specifier Notes: Specify requirements for the power cord assemblies. Consult PDU Cables for more
information regarding UL-listed, custom-length, power cord assemblies for applications that do not
require conduit. Also, consult PDU Cables for information regarding custom-cord assemblies.
1. Part Number: .
2. Length: feet.
3. Cable Type: .
E. Custom-label options.
G. Colored faceplates.
A. Tests:
1. Meet UL requirements for Data Processing Equipment cables or Wiring Assemblies.
2. Perform the following factory tests on each cable:
a. Ground integrity.
b. Continuity.
c. Insulation leakage.
d. Proper phase rotation.
e. Circuit Voltage Capacity: Hi-Pot tested at twice rated circuit voltage plus 1,000 volts.
PART 3 EXECUTION
3.1 EXAMINATION
B. Notify Architect of conditions that would adversely affect installation or subsequent use.
3.2 INSTALLATION
A. Install prefabricated PDU cable assemblies in accordance with manufacturers instructions and
NFPA 70.
3.3 PROTECTION
A. Protect installed prefabricated PDU cable assemblies from damage during construction.