Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
xxx.xxx
Project
Construction Project of Three (3) Petroleum
Depots in Chad
Client
Contractor
CONTENTS
2.0 SCOPE
xxx
xxx
3.0 REFERENCES
- xxx
- xxx
- xxx
- xxx
- xxx
- xxx
- HSE Plan
- QA/QC Plan
- Approved Drawings
- xxx
- xxx
4.0 DEFINITIONS
5.0 RESPONSIBILITIES
Site Engineer & Foreman; responsible in ensuring that the site preparation
activities are conducted according to the approved method statement and all
activities on site are carried out in accordance with the schedule and the
construction drawing and take care all worker to be work with their
responsibilities and make a decision when some nonconformance occurring
their report to construction manager.
5.6 Worker
6.0 RESOURCES
- Generators x
- Air Compressors x
- Mobile Cranes x
- Fork Lifts x
- Lifting Equipments x
- Plate Plasma Cutting Machines x
- Welding Groove Opening Machine x
- Automatic ClosedShotblasting Machine x
- Shop Primer Painting Machine x
- Plate Bending Machine x
- SAW Welding Machines x
- Electric Welding Machines xx
- Electrode / FluxBakingOvens x
- Electrode / Flux Holding Ovens x
- Grinders xx
- Radiography Test Machine x
- Vacuum Test Equipment x
- Exhaust Fan x
- Paint Guns xx
- Trailers x
- Pick-ups x
-
- Total XXX
2. Occupational Health and Safety issues and risks in the work area are
identified, assessed and reported to designated personnel.
3. Safe workplace procedures and safe work instructions are followed for
controlling risks.
8.0 HSE
9. Daily Tool Box talk shall be conducted prior to proceed for the work.
15.Tools and equipment will be provided with back-up alarms, lights, and
all other applicable safety devices.
16.Tested and certified lifting equipment should be used for lifting and
shifting purpose.
9.0 QA/QC
5. Plant, tools and equipment selected to carry out tasks are consistent
with the requirements of the job, checked for serviceability and any
faults are rectified or reported prior to commencement.
10.4 Fabrication
4. Curved edges of roof, bottom sketch plates and annular plates shall
be cut to shape by the machine operated gas torch.
7. The resulting surface shall be uniform, smooth and free from scale or
slag accumulations.
10.4.2 Marking
3. Each weld joint shall be marked with joint number and welder
number.
1. The edge of the tank plates shall be sheared, machine cut or beveled
with a machine operated gas-cutting torch.
1. All plate material shall be shot blasted and shop primed for temporary
protection during storage and construction.
2. Any corrosions / mill scale shall be removed from the steel plates.
4. Post shot blasting, the material passes to the shop primer coating.
6. Drying of the paint will be ensured, and being ready, it will be placed
on the carrying table.
10.4.5 Rolling of Shell Plate
7. Check radius using the above template stage by stage until the
required radius is obtained.
6. Shell plates will be bent at the bending machine (roller) with the help
of temporary tools prepared for bending.
7. Surfaces of shell plates will be cleared of any oil or dirt and the
treated corners will be wrapped with masking tape.
9. Drying of the paint will be ensured, and being ready, it will be placed
on the carrying table.
17.Its dimensions and DFT (dry film thickness) will be measured for
ready-made package lists for each stage of the production and
transportation to the work site.
6. Repeating the same operations for the central section and performing
the cleaning activities.
7. Application of the first paint coat to the finished and cleaned parts
according to the painting procedure.
12.It will be ensured that surface preparation is performed and first coat
of paint is applied according to the procedure.
4. All the cutting operation, as per requirement shall be carried out after
getting the clearance from inspection authority.
6. All the cutting operation shall be carried out by gas cutting method.
9. Dimensions of the parts which are cut of welded with approved WPS
will be verified.
14.All stages of the plant production for each tank inspection shall be
performed in accordance with Consultants Procedure and the
company records will be completed without error.
15.Preparation of package lists for all parts and the placed layers.
20.The produced components will be cut at full scale when they are
placed into their locations, for instance, flanges and metal parts, and
they will be prepared and joined according to the drawings.
22.Each weld shall be started (root pass) and finished while the preheat
temperature is maintained without interruption.
3. Bolts, nuts, nipples, and other small parts shall be boxed or put in
kegs or bags for shipment.
Packing for bottom, roof and shell steel plates will be done in following
forms;
10.6 Inspection of Foundation
8. The tank should be oriented on the tank circle whose 0, 90, 180 and
270 degree points are drawn on the concrete ground.
2. Check the dimension of anchor bolt diameter, if its not enough, cut
around the slots of the bolt.
4. Start annular plate erect form clean out door. (If any)
11.The weld area (8'') upon which the shell plates to be erected shall be
ground flush.
3. The bottom plates, starting from the center plate shall be laid
progressively towards the annular plates in accordance with the
project drawings.
5. Laps shall be maintained while the fit-up of short seam and long seam as
per drawing.
6. Temporary tack weld to be carry out on the long seam to avoid
uneven movements and distortion while the fit-up and welding of
short seam.
12.Minimum laps shall be maintained while the fit-up of long seam as per
approved drawing.
15.Sketch to annular plate joint shall be welded only after shell to bottom
joint welding.
16.After completion of the welding works, the gauges are removed and
point welding places are cleaned thoroughly by wire brushing and
grinding.
20.All the bottom plate's joints vacuum box test shall be carried out as
per approved process and code specification.
21.If any defect found the defect weld shall be removed by grinding and
re-weld and conduct the vacuum box test. Repeat the sequence until
the defect cleared.
Bottom plates welding sequence
3. All required fixtures shall be installed on the inside of the shell plates.
4. All required fixtures shall be installed on the inside and outside of the
annular plates to ensure that the shell plates are aligned with the
scribed line.
5. Bracket hooks shall be fitted inside and outside each shell plate
before it is lifted into position.
6. Each shell plate shall be secured on the annular plate and aligned by
using guides and wedges.
7. The first shell plate with its edge on the start mark shall be erected
upright using a 100 mm channel support.
9. The alignment fixtures shall be removed, all tacks cleaned and all
vertical joints of the first shell course welded.
16.Aligning horizontal seam between 1st and 2nd courses, and fit up
check shall be carried out after tack welding.
1. Pad location for the stair case support shall be marked on the shell
plates.
11.All the shell manholes or nozzles final weld from both sides and
reinforcing pads welds shall be inspected by visually and by LPT, to
the satisfaction of the Consultant.
7. Assemble and welding the center ring and center plate complete with
stiffener and rib plate.
1. When half portion of the bottom plates are welded, including annular
plates segment plus the internal welding between 1st shell course
and annular plates, vacuum box test shall be conducted and cleared
for internal float roof assembly.
2. Internal floating roof lower deck plates shall be laid and welded in
same sequence of bottom plates.
3. Mark up on the lower deck plates, the location of outer rim,
Intermediate rim, compartment plates, structures, leg supports and
accessories.
5. Complete welding of vertical and all joints to the lower deck plates
7. When total assembly and welding of the floating roof without roof
plates is completed, including sleeves supporting legs, all manholes
and nozzles of 1st shell course shall be closed.
9. Closing of the 1st, 2nd and, in case, 3rd shell course will be done in
steps, in order to complete at the same time the assembly of the
floating roof (still without roof plates).
10.Water shall be pumped inside the tank trough one nozzle and slowly
float roof will be lifted up.
11.Water shall be pumped until the float reaches the height allowing the
insertion of the pins into the legs.
12.Check the orientation of the floating roof, as per floating roof layout
drawing.
19.Primary shoe and seal shall be installed after final hydrotest and
internal painting, as per supplier instruction.
4. The shell to bottom weld shall be inspected by wet MPI on the inside
and outside after the 1st pass each side and after hydro test on the
completed welds.
5. When roof truss main supporting members are made up from two
shorter length, the penetration of these welds shall be examined by
radiography.
1. All tank bottom and roof plate welds shall be tested, before hydro-test
& painting, using vacuum box soapy water shall be applied to all
joints.
3. Roof plate shall be tested applying internal air pressure not exceeding
the weight of the roof plates and applying to the weld joint a soap
solution for the detection of leaks.
1. After filling the tank up to curb angle, all openings in the roof shall be
closed and internal pressure shall be applied equivalent to the weight
of roof plates, all welded joints in roof shall be checked with soap-suds
for detection of leaks.
2. For tanks with small internal pressure, the test pressure shall be equal
to 1.25 design pressure.
10.9 Calibration
5. All paint containers shall only be opened prior to utilization and shall
be carefully closed immediately after withdrawal of material.
14.Tank number and capacity shall be painted on each tank with suitable
size letters and numbers.