RECEIVING ROTOR
Standard rigging practices should
be followed. Confirmation of load
ratings and safety inspections
should be performed prior to any
lifts being performed.
Use of a spreader beam is highly
recommended.
The lift points should be the seal
areas of the stub shafts unless
lifting plates attached to the
couplings are available
1
COMPRESSOR ROTOR REPAIR
Power Plant Services
INCOMING INSPECTIONS
Placing the rotor in the lathe for
rotating facilitates the inspection
process.
The general condition of the rotor is
photo documented including all
serial numbers, part numbers,
blade damage, balance weight
locations etc.
Rotor run out data is collected
including three(3) body run outs to
determine journal /body/journal
centerline axis relationship. (rotor
bow)
2
COMPRESSOR ROTOR REPAIR
Power Plant Services
INCOMING BALANCE
The rotor is placed in the balance
machine to determine the incoming
balance condition. The previous
overhaul balance weight
corrections are removed during this
process.
This information should align with
the previously recorded run out
condition.
The incoming inspections are
evaluated to determine the need to
dis-assemble the unit for repairs.
3
COMPRESSOR ROTOR REPAIR
Power Plant Services
4
COMPRESSOR ROTOR REPAIR
Power Plant Services
5
COMPRESSOR ROTOR REPAIR
Power Plant Services
6
COMPRESSOR ROTOR REPAIR
Power Plant Services
7
COMPRESSOR ROTOR REPAIR
Power Plant Services
8
COMPRESSOR ROTOR REPAIR
Power Plant Services
FRAME7ROTORCOMPRESSORROTORUNSTACKANDREASSEMBLE
9
COMPRESSOR ROTOR REPAIR
Power Plant Services
10
COMPRESSOR ROTOR REPAIR
Power Plant Services
11
COMPRESSOR ROTOR REPAIR
Power Plant Services
12
COMPRESSOR ROTOR REPAIR
Power Plant Services
NUT REMOVAL
The process for nut removal after
seizing is to split the nut in half.
This is accomplished by using and
end mill and plunging down each
side of the nut, 180 degrees apart.
The nuts are removed from the
countersunk hole and the OD of the
bolt is ground smooth to allow for
the passing of the individual wheels
13
COMPRESSOR ROTOR REPAIR
Power Plant Services
ROTOR DE-STACK
Once the nuts have been removed,
dry ice is applied to the aft stub.
This freezing allows for shrinkage
of the male rabbet fit allowing it to
release form the 16th stage female
rabbet fit.
Care should be taken to not
damage the threads on the bolts
during the removal process.
14
COMPRESSOR ROTOR REPAIR
Power Plant Services
15
COMPRESSOR ROTOR REPAIR
Power Plant Services
16
COMPRESSOR ROTOR REPAIR
Power Plant Services
17
COMPRESSOR ROTOR REPAIR
Power Plant Services
18
COMPRESSOR ROTOR REPAIR
Power Plant Services
19
COMPRESSOR ROTOR REPAIR
Power Plant Services
DEFLECTOR CONE
The fit area of this cone and
retaining plate can see extreme
wear. If this becomes loose during
operation, severe imbalance forces
can be imparted into the unit.
20
COMPRESSOR ROTOR REPAIR
Power Plant Services
21
COMPRESSOR ROTOR REPAIR
Power Plant Services
22
COMPRESSOR ROTOR REPAIR
Power Plant Services
23
COMPRESSOR ROTOR REPAIR
Power Plant Services
COUPLING HELICOILS
These helicoils should be replaced
during every major rebuild of the
rotor.
24
COMPRESSOR ROTOR REPAIR
Power Plant Services
25
COMPRESSOR ROTOR REPAIR
Power Plant Services
BLADE BLENDING
Examples of compressor blade tip
blending
26
Power Plant Services
27
COMPRESSOR ROTOR REPAIR
Power Plant Services
COMPRESSOR RESTACK
Each compressor wheel is
individually protected during the
stacking process. The number 1
bolt hole location is clearly
identified to ensure correct
orientation.
28
COMPRESSOR ROTOR REPAIR
Power Plant Services
29
COMPRESSOR ROTOR REPAIR
Power Plant Services
BOLT STRETCH
The bolts are positioned to be flush
in the pie nut. A at rest drop is
measured from bolt end to the face
of the stub.
The bolt stretch procedure is
implemented and following a three
step process, an overstretch is
performed.
The final bolt stretch is established
and verified with a tensioned drop
measurement taken at the same
location as the original at rest
30
COMPRESSOR ROTOR REPAIR
Power Plant Services
BALANCE VERIFICATION
The rotor is placed into the balance
machine and the total vectored
correction is determined. The
maximum allowable is 9500 inch
grams total or 4750 inch gram per
plane.
Three rotor body run out
measurements are taken and
compared to the balance weight
requirements.
If acceptable, final balance is
performed and the rotor is ready for
machining
31
COMPRESSOR ROTOR REPAIR
Power Plant Services
32
COMPRESSOR ROTOR REPAIR
Power Plant Services
33
COMPRESSOR ROTOR REPAIR
Power Plant Services
FINAL PACKING
Uncoated rotors are completely
coated with preservative. A light oil
such as WD-40 is used for short
term and a more viscous product
such as LPS-3 is used for
intermediate (less than 1 year).
Long term storage should be
performed using controlled
atmosphere. The rotor is completely
wrapped in heavy corrugated
cardboard and wrapped in plastic
stretch wrap. The journal is
wrapped seperately.
34
COMPRESSOR ROTOR REPAIR
Power Plant Services
35
MS7001 B - EA TURBINE ROTOR REPAIR MODULE
36
TURBINE ROTOR REPAIR
Power Plant Services
37
TURBINE ROTOR REPAIR
Power Plant Services
INCOMING INSPECTION
The rotor is set up in a lathe or
precision roller stand to measure
and record the run out.
The buckets are measured and
visually inspected.
The coupling rabbet fits are
measured and recorded
38
TURBINE ROTOR REPAIR
Power Plant Services
JOURNAL INSPECTION
The journals and seal areas are
inspected for size and roundness
The probe areas are located and
protected.
The coupling bolt holes are
inspected.
39
TURBINE ROTOR REPAIR
Power Plant Services
40
TURBINE ROTOR REPORT
Power Plant Services
INCOMING BALANCE
The incoming balance is measured
and recorded
The buckets can be intermittently
removed and measured if desired.
The buckets can also be removed
all rows and weights to determine
the bare rotor condition.
The bare rotor balance condition
along with the run out data are key
to determining the need to de-stack
the rotor.
41
TURBINE ROTOR REPAIR
Power Plant Services
42
TURBINE ROTOR REPAIR
Power Plant Services
BALANCE WEIGHTS
The staking and securing of the
turbine balance weights is
complicated by the interrupted
weight groove
The weight locations are recorded
and used to evaluate incoming
balance condition
43
TURBINE ROTOR REPAIR
Power Plant Services
SEAL COATING
The stage one and stage two
buckets receive coating on the fir
tree areas to provide a seal
boundary for the cooling air.
This boundary forces the cooling air
up through the airfoil cooling holes
preventing damage to the buckets
from excessive heat.
44
TURBINE ROTOR REPAIR
Power Plant Services
45
TURBINE ROTOR REPAIR
Power Plant Services
DISCOURAGER SEAL
The Model EA units are equipped
with an axially inserted discourager
seal. This seal is located on the aft
face of the 1-2 spacer.
This works along with the fir tree
coating to provide a sealing
boundary for the bucket cooling air.
Clearance/ Crush checks must be
performed on this seal with each
bucket change
46
TURBINE ROTOR REPAIR
Power Plant Services
TURBINE DE-STACK
The turbine rotor is turned vertically
and placed into a stack pit or
mounted to an dis-assembly plate.
Heat is used on the nuts and all are
removed mechanically, (no bolt
stretch)
Dry ice is used to freeze the stub
shaft allowing separation from the
turbine wheel.
47
TURBINE ROTOR REPAIR
Power Plant Services
48
TURBINE ROTOR REPAIR
Power Plant Services
DE-STACK PROCESS
The turbine wheels have female
rabbets on both sides. Heating up
to 350 degrees F is permitted for
removal and installation
The wheel spacers and stub shafts
have male rabbets and require dry
ice for removal and installation.
Stack temperature normalization is
required before proceeding to the
next piece in the process.
49
TURBINE ROTOR REPAIR
Power Plant Services
COMPONENT INSPECTIONS
All of the individual rotor
components are blast cleaned
using 220 grit AlOx. Extreme care
must be taken to not dwell on the fir
tree areas.
All components are then MPI
inspected. Areas of concern are the
fir trees and the turbine wheel
rabbet fit areas.
50
TURBINE ROTOR REPORT
Power Plant Services
51
TURBINE ROTOR REPORT
Power Plant Services
52
TURBINE ROTOR REPAIR
Power Plant Services
STUB SHAFTS
Both turbine rotor stub shafts are
set up and checked for
concentricity.
54
TURBINE ROTOR REPAIR
Power Plant Services
Re-assembly
The aft stub shaft is placed in the
stacking area. The bolts are placed
into the stub and held up in place
with temporary supports.
55
TURBINE ROTOR REPAIR
Power Plant Services
RE-ASSEMBLY
Using alternating heat and dry ice,
the turbine rotor is re-assembled.
After each component is added to
the stack, the temperature is
allowed to normalize and the bolts
are checked to insure they can be
turned.
56
TURBINE ROTOR REPAIR
Power Plant Services
RE-ASSEMBLY
The photo is an assembled rotor
prior to re-stretch of the bolts. This
is actually a 7B rotor. The large gap
shown between the 1-2 spacer and
the second stage wheel is far less
wide on the EA unit. The edge of
that spacer holds the discourager
seal for the second stage buckets.
57
TURBINE ROTOR REPAIR
Power Plant Services
58
TURBINE ROTOR REPAIR
Power Plant Services
59
TURBINE ROTOR REPAIR
Power Plant Services
COUPLING MACHINING
The rotor coupling rabbet fits and
face perpendicularity are measured
and recorded.
Patch rings are utilized for rabbet fit
corrections
Tool post grinding is used to reclaim
the tolerances of the coupling
faces.
60
TURBINE ROTOR REPAIR
Power Plant Services
ROTOR BALANCE
The turbine rotor is placed into
the balance machine and the
bare rotor balance is measured
and recorded.
The total vectored allowable
unbalance is 7500 inch-grams.
Either correction plane cannot
exceed 3750 inch-grams.
The second stage buckets are
normally installed first to facilitate
twist lock staking
61
TURBINE ROTOR REPAIR
Power Plant Services
62
TURBINE ROTOR REPAIR
Power Plant Services
FINAL PACKING
Each stage of buckets is wrapped
with Styrofoam packing. The
complete rotor body is then
covered with heavy corrugated
cardboard.
This is then seal wrapped
completely with plastic stretch
wrap.
Preservation is the same process
as the compressor rotor.
63
TURBINE ROTOR REPAIR
Power Plant Services
64
MS 7001 ROTOR REPAIR MODULE
Power Plant Services
65
MS 7001 ROTOR REPAIR MODULE
Power Plant Services
66
MS 7001 REPAIR MODULE
Power Plant Services
BACKGROUND (2007)
A gas turbines risk of failure increases the longer it is in service as a
result of normal wear and tear of components in the system. It is
believed the exceeding of the service life of the rotor system can lead to
wheel failure severe enough to cause extensive damage to the gas
turbine as well as the potential for substantial damage to adjacent
equipment and serious injury to nearby personnel.
GER 3620 (Heavy Duty Gas Turbine Operating and Maintenance
Considerations) requires that a rotor inspection be performed at specific
intervals recommended by GE. These intervals are set forth in GER
3620 or through Technical Information Letters. Where specific intervals
have not been defined, rotor inspection should be performed at 5,000
factored starts or 200,000 factored hours.
67
MS 7001 REPAIR MODULE
Power Plant Services
68
MS7001 ROTOR REPAIR MODULE
Power Plant Services
RECOMMENDATIONS (2007)
GE has defined inspection programs for rotors reaching the tear down
inspection intervals. Numerous techniques are required to fully inspect a
gas turbine rotor for both surface connected and subsurface defects.
These inspections. which include magnetic particle. eddy current and
ultrasonic techniques. should be performed in a GE service center where
the GE inspection team uses proprietary algorithms to identify potential
sub-surface defects that may have grown during operation. The inspection
results can be combined with design analysis and specific turbine
operating histories to provide recommendations for rotor refurbishment,
replacement and continued service.
69
MS 7001 ROTOR REPAIR MODULE
Power Plant Services
RECOMMENDATIONS (2007)
Depending upon the condition of the rotor at the inspection. one hours based
life extension may be possible for up to 100,000 hours for frame 3 and 5 units
and up to 50,000 hours for E- class units that have not passed their starts
based interval limits as defined in GER 3620, after which the rotor must be
retired. Extensions are under evaluation for FA class units. Currently. there
are no life extensions available for units that reach their starts based interval
limit.
Contact GE
70
MS 7001 ROTOR REPAIR MODULE
Power Plant Services
RECOMMENDATION MODIFICATION
In 2011 GE issued revision 1 to the TIL. There were only three
changes from the original, two of those minor in nature and
the third quite significant.
The units affected was changed from FA class to F class
The inspection process of penetrant was added to the list of
types of NDT
The limiting language of 2007 was modified to not specifically
eliminate starts based extensions and the implied easing of
the hours based limitation
71
MS 7001 ROTOR REPAIR MODULE
Power Plant Services
RECOMMENDATION (2011)
Depending upon the condition of the rotor, specific unit configuration,
operating history, and prior maintenance history at the inspection interval, a
rotor life extension may be viable.
Contact GE
72
MS 7001 ROTOR REPAIR MODULE
Power Plant Services
OTHER ISSUES
TIL-1049-3R1. TURBINE WHEEL DOVETAIL MATERIAL LOSS
73